OPERATION RESEARCH
PLANNING AND SCHEDULING OF A
MULTI-STOREY RESIDENTIAL BUILDING
Project by:-
SHAIK KHAZAMOHIDDIN -11BCL1012 Name of Guide: -Prof. Uma maheswari
Introduction:
The feasibility studies stage considers the options for satisfying the client's needs, enabling
the client to prepare a business case for the preferred option and deciding whether to proceed with
the project. It is possible to make an outline planning application during this stage if the risk to the
project of not receiving planning permission is high, or if delays in receiving planning
permission would be problematic.
MS project is designed to assist a project manager in developing a plan, assigning resources to
tasks, tracking progress, managing the budget, and analyzing workloads, Cost Estimation can be
done in feasibility report.
Objective:-
• To prepare feasibility report.
• Planning, design and financial services for Multi-Storey Commercial Building
• Sub Activities:
• Survey and soil investigation
• Preparation of Feasibility Report and financial viability of Project.
• Master Plan and Conceptual Plan
• Design Development & tender Documents
• Invitation of Tenders and evaluation of Bids
• Detailed design & Construction drawings
• Top Supervision
• TIME SCHEDULE
• CONSULTANTS FEE STRUCTURE
• REMUNERATION OF SERVICES
• Complete Final Inspections
Methodology
SEQUENCE of MS Project:-
1. Set overall project information: goals, scope, assumptions, start date, manager
2. Create a Base Calendar, assign it to the project and to the Gantt chart.
3. List tasks and milestones, estimate durations
4. Outline the project (create Summary Tasks)
5. Link the tasks
6. Assign resources
7. Evaluate and refine the project
8. Save a Baseline
9. Track and update the project—Actuals
10. Communicate progress—Reports
11. Close the project
TASK Allocation:
1. Commercial Construction 11.General Conditions
2. Long Lead Procurement 12.Mobilize on Site
3. Grading and Utilities 13. Foundations
4. Steel Erection 14.Form and Pour Concrete Floors and Roof
5. Carpentry Work 15. Masonry Work
6. Roofing 16. Window wall and
7. Store front closure 17.Building Finishes
8. Elevators 18.Plumbing
9. Electrical 19.Heating and Ventilating - AC
10. Final Clean-up and Occupancy 20.Complete Final Inspections
Task Mode Task Name Duration Start Finish Predecessors Resource Names
Auto Scheduled
Commercial Construction
344 days Mon 1/3/00
Thu 4/26/01
Auto Scheduled
General Conditions
17 days Mon 1/3/00
Tue 1/25/00
Auto Scheduled
Receive notice to proceed and sign contract
3 days Mon 1/3/00 Wed 1/5/00
G.C. General Management
Auto Scheduled
Submit bond and insurance documents
2 days Thu 1/6/00 Fri 1/7/00 2
G.C. Project Management,G.C. General Management[25%]
Auto Scheduled
Prepare and submit project schedule
2 days Mon 1/10/00
Tue 1/11/00
3 G.C. Project Management[25%],G.C. Scheduler
Auto Scheduled
Prepare and submit schedule of values
2 days Wed 1/12/00
Thu 1/13/00
4 G.C. General Management[10%],G.C. Project Management
Auto Scheduled
Obtain building permits
4 days Thu 1/6/00 Tue 1/11/00
2 G.C. Project Management[50%],G.C. Procurement[50%]
Auto Scheduled
Submit preliminary shop drawings
2 wks Wed 1/12/00
Tue 1/25/00
6 G.C. Project Management[50%],G.C. Procurement[50%]
Auto Scheduled
Submit monthly requests for payment
1 day Thu 1/6/00 Thu 1/6/00 2
Auto Scheduled
Long Lead Procurement
70 days Fri 1/7/00 Thu 4/13/00
Auto Scheduled
Submit shop drawings and order long lead items - steel
2 wks Fri 1/7/00 Thu 1/20/00
8 Steel Erection Contractor Management
Auto Scheduled
Submit shop drawings and order long lead items - roofing
2 wks Wed 1/26/00
Tue 2/8/00 7 Roofing Contractor Management
Auto Scheduled
Submit shop drawings and order long lead items - elevator
2 wks Wed 1/26/00
Tue 2/8/00 7 Elevator Contractor Management
Auto Scheduled
Submit shop drawings and order long lead items - plumbing
2 wks Wed 1/26/00
Tue 2/8/00 7 Plumbing Contractor Management
Auto Scheduled
Submit shop drawings and order long lead items - electric
2 wks Wed 1/26/00
Tue 2/8/00 7 Electric Contractor Management
Auto Scheduled
Submit shop drawings and order long lead items - HVAC
2 wks Wed 1/26/00
Tue 2/8/00 7 HVAC Contractor Management
Auto Scheduled
Detail, fabricate and deliver steel
12 wks Fri 1/21/00 Thu 4/13/00
10 Steel Erection Contractor Management[50%],Steel Erection Contractor[50%]
Auto Scheduled
Mobilize on Site 10 days Thu 1/6/00 Wed 1/19/00
Auto Scheduled
Install temporary power
2 days Thu 1/6/00 Fri 1/7/00 2 Electric Contractor
Auto Scheduled
Install temporary water service
2 days Thu 1/6/00 Fri 1/7/00 2 Plumbing Contractor
Auto Scheduled
Set up site office
3 days Mon 1/10/00
Wed 1/12/00
18,19 G.C. Superintendent,G.C. Labor Crew[10%]
Auto Scheduled
Set line and grade benchmarks
3 days Thu 1/13/00
Mon 1/17/00
20 G.C. Survey Crew
Auto Scheduled
Prepare site - lay down yard and temporary fencing
2 days Tue 1/18/00
Wed 1/19/00
21 Site Grading Contractor,G.C. Labor Crew[10%]
Auto Scheduled
Site Grading and Utilities
35 days Thu 1/20/00
Wed 3/8/00
Auto Scheduled
Clear and grub site
3 days Thu 1/20/00
Mon 1/24/00
20,22 Site Grading Contractor
Auto Scheduled
Stone site access and temporary parking area
2 days Tue 1/25/00
Wed 1/26/00
24,22 Site Grading Contractor
Auto Scheduled
Rough grade site (cut and fill)
1 wk Thu 1/27/00
Wed 2/2/00
25 Site Grading Contractor
Auto Scheduled
Install storm drainage
2 wks Thu 2/3/00 Wed 2/16/00
26 Site Grading Contractor
Auto Scheduled
Install exterior fire line and building fire riser
2 wks Thu 2/3/00 Wed 2/16/00
26 Plumbing Contractor
Auto Scheduled
Perform final site grading
2 wks Thu 2/17/00
Wed 3/1/00
27FF+1 day,28 Site Grading Contractor
Auto Scheduled
Erect building batter boards and layout building
1 wk Thu 3/2/00 Wed 3/8/00
29 G.C. Survey Crew
Auto Scheduled
Foundations 33 days Thu 3/9/00 Mon 4/24/00
Auto Scheduled
Excavate foundations
2 wks Thu 3/9/00 Wed 3/22/00
30 Site Grading Contractor[50%]
Auto Scheduled
Excavate elevator pit
2 days Thu 3/9/00 Fri 3/10/00 30 Site Grading Contractor
Auto Scheduled
Form column piers and spread foundations
4 days Thu 3/23/00
Tue 3/28/00
32 G.C. Rough Carpenter Crew
Auto Scheduled
Rough-in electric and plumbing in elevator
4 days Mon 3/13/00
Thu 3/16/00
33 Plumbing Contractor, Electric Contractor
Auto Scheduled
Form elevator pit walls
4 days Fri 3/17/00 Wed 3/22/00
35 G.C. Rough Carpenter Crew
Auto Scheduled
Set reinforcing and anchor bolts
4 days Wed 3/29/00
Mon 4/3/00
34 G.C. Rough Carpenter Crew
Auto Scheduled
Pour column piers and foundations
5 days Tue 4/4/00 Mon 4/10/00
37 G.C. Concrete Crew
Auto Scheduled
Pour concrete elevator walls
1 day Thu 3/23/00
Thu 3/23/00
36 G.C. Concrete Crew
Auto Scheduled
Cure elevator wall concrete
7 days Fri 3/24/00 Mon 4/3/00
39 G.C. Labor Crew[10%]
Auto Scheduled
Cure piers and foundations
7 days Tue 4/11/00
Wed 4/19/00
38 G.C. Labor Crew[10%]
Auto Scheduled
Strip wall forms
1 day Tue 4/4/00 Tue 4/4/00 40 G.C. Labor Crew[10%]
Auto Scheduled
Strip column piers and foundation forms
3 days Thu 4/20/00
Mon 4/24/00
41 G.C. Labor Crew
Auto Scheduled
Install pneumatic tube in elevator pit
3 days Wed 4/5/00 Fri 4/7/00 42 Elevator Contractor
Auto Scheduled
Prepare and pour concrete floor in elevator pit
1 day Mon 4/10/00
Mon 4/10/00
44 G.C. Concrete Crew
Auto Scheduled
Steel Erection 45 days Tue 4/25/00
Mon 6/26/00
Auto Scheduled
Erect steel columns, beams and joist - 1st and 2nd floors
2 wks Tue 4/25/00
Mon 5/8/00
43,16 Steel Erection Contractor
Auto Scheduled
Erect steel columns, beams and joist - 3rd floor and roof
2 wks Tue 5/9/00 Mon 5/22/00
47 Steel Erection Contractor
Auto Scheduled
Install miscellaneous iron and bracing - 1st and 2nd floors
2 wks Tue 5/9/00 Mon 5/22/00
47 Steel Erection Contractor[75%]
Auto Scheduled
Install miscellaneous iron and bracing - 3rd floor and roof
2 wks Tue 5/23/00
Mon 6/5/00
48 Steel Erection Contractor[75%]
Auto Scheduled
Install stairs and miscellaneous iron railing
2 wks Tue 6/6/00 Mon 6/19/00
50 Steel Erection Contractor[50%]
Auto Scheduled
Touch-up paint on steel
1 wk Tue 6/20/00
Mon 6/26/00
51 Steel Erection Contractor[20%]
Auto Scheduled
Form and Pour Concrete - Floors and Roof
85 days Tue 5/9/00 Mon 9/4/00
Auto Scheduled
Form 2nd floor including all floor openings
5 days Tue 6/27/00
Mon 7/3/00
52,13,14,15,47 G.C. Rough Carpenter Crew,G.C. Labor Crew[20%]
Auto Scheduled
Install rebar and in-floor utilities (including mechanical, electrical, plumbing)
5 days Tue 5/9/00 Mon 5/15/00
47
G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]
Auto Scheduled
Pour 2nd floor slab
4 days Tue 7/4/00 Fri 7/7/00 55,54 G.C. Concrete Crew
Auto Scheduled
Cure 2nd floor slab
7 days Mon 7/10/00
Tue 7/18/00
56 G.C. Labor Crew[10%]
Auto Scheduled
Strip forms from 2nd floor slab
2 days Wed 7/19/00
Thu 7/20/00
57 G.C. Labor Crew
Auto Scheduled
Form 3rd floor including all floor openings
5 days Wed 7/19/00
Tue 7/25/00
57 G.C. Rough Carpenter Crew[50%],G.C. Labor Crew[20%]
Auto Scheduled
Install rebar and in-floor utilities (including mechanical, electrical, plumbing)
5 days Wed 7/19/00
Tue 7/25/00
57
G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]
Auto Scheduled
Pour 3rd floor slab
4 days Wed 7/26/00
Mon 7/31/00
60,59 G.C. Concrete Crew
Auto Scheduled
Cure 3rd floor slab
7 days Tue 8/1/00 Wed 8/9/00
61 G.C. Labor Crew[10%]
Auto Scheduled
Strip forms from 3rd floor slab
2 days Thu 8/10/00
Fri 8/11/00 62 G.C. Labor Crew
Auto Scheduled
Form roof slab including all floor openings
5 days Thu 8/10/00
Wed 8/16/00
62 G.C. Rough Carpenter Crew,G.C. Labor Crew[20%]
Auto Scheduled
Install rebar and in-floor utilities (including mechanical, electrical, plumbing)
5 days Thu 8/10/00
Wed 8/16/00
62
G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]
Auto Scheduled
Pour roof slab 4 days Thu 8/17/00
Tue 8/22/00
65,64 G.C. Concrete Crew
Auto Scheduled
Cure roof slab 7 days Wed 8/23/00
Thu 8/31/00
66 G.C. Labor Crew[10%]
Auto Scheduled
Strip forms from roof slab
2 days Fri 9/1/00 Mon 9/4/00
67 G.C. Labor Crew
Auto Scheduled
Form 1st floor 4 days Fri 7/21/00 Wed 7/26/00
58 G.C. Rough Carpenter Crew
Auto Scheduled
Install electrical underground
1 wk Fri 7/21/00 Thu 7/27/00
58 Electric Contractor
Auto Scheduled
Install plumbing underground
1 wk Fri 7/21/00 Thu 7/27/00
58 Plumbing Contractor
Auto Scheduled
Install rebar and in-floor utilities
4 days Fri 7/21/00 Wed 7/26/00
58
G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]
Auto Scheduled
Pour 1st floor slab
4 days Fri 7/28/00 Wed 8/2/00
69,72,70,71 G.C. Concrete Crew
Auto Scheduled
Cure 1st floor slab
7 days Thu 8/3/00 Fri 8/11/00 73 G.C. Labor Crew[10%]
Auto Scheduled
Strip forms from 1st floor slab
2 days Mon 8/14/00
Tue 8/15/00
74 G.C. Labor Crew
Auto Scheduled
Carpentry Work 15 days Tue 9/5/00 Mon 9/25/00
Auto Scheduled
Install exterior sheathing and metal studs
3 wks Tue 9/5/00 Mon 9/25/00
63,68 Drywall Contractor
Auto Scheduled
Masonry Work 110 days Tue 6/6/00 Mon 11/6/00
Auto Scheduled
Rough-in plumbing at toilets and masonry walls
4 wks Wed 8/16/00
Tue 9/12/00
75,13 Plumbing Contractor
Auto Scheduled
Lay masonry at core, mechanical, and toilets
4 wks Tue 6/6/00 Mon 7/3/00
49,50 Masonry Contractor
Auto Scheduled
Install exterior masonry work
5 wks Tue 9/26/00
Mon 10/30/00
77 Masonry Contractor
Auto Scheduled
Install roof drains
2 days Tue 10/31/00
Wed 11/1/00
81 Roofing Contractor
Auto Scheduled
Install tile in toilet rooms
2 wks Wed 9/13/00
Tue 9/26/00
79 Tile Contractor
Auto Scheduled
Clean masonry 1 wk Tue 10/31/00
Mon 11/6/00
81 Masonry Contractor[50%]
Auto Scheduled
Clean toilet room tile
1 wk Wed 9/27/00
Tue 10/3/00
83 Tile Contractor[50%]
Auto Scheduled
Roofing 31 days Tue 10/31/00
Tue 12/12/00
Auto Scheduled
Install flashing at parapet walls
4 days Tue 10/31/00
Fri 11/3/00 81 Roofing Contractor
Auto Scheduled
Pour lightweight concrete roof fill
2 days Mon 11/6/00
Tue 11/7/00
11,82,87 Roofing Contractor
Auto Scheduled
Install seamless roofing material
5 days Wed 11/15/00
Tue 11/21/00
88FS+5 days Roofing Contractor
Auto Scheduled
Spread stone ballast on seamless roof
5 days Wed 11/22/00
Tue 11/28/00
89 Roofing Contractor
Auto Scheduled
Set rooftop equipment
2 wks Wed 11/29/00
Tue 12/12/00
90 HVAC Contractor
Auto Scheduled
Window wall and store front closures
60 days Tue 10/31/00
Mon 1/22/01
Auto Scheduled
Install window wall aluminum and glass
5 wks Tue 10/31/00
Mon 12/4/00
81 Window Contractor
Auto Scheduled
Install interior stud walls and drywall
5 wks Tue 12/5/00
Mon 1/8/01
93 Drywall Contractor
Auto Scheduled
Install interior doors and hardware
2 wks Tue 1/9/01 Mon 1/22/01
94 G.C. Finish Carpenter Crew
Auto Scheduled
Install store front doors and hardware
3 wks Tue 10/31/00
Mon 11/20/00
81 Window Contractor
Auto Scheduled
Building Finishes 80 days Tue 12/5/00
Mon 3/26/01
Auto Scheduled
Install millwork and wood trim
3 wks Tue 1/9/01 Mon 1/29/01
96,94 G.C. Finish Carpenter Crew
Auto Scheduled
Paint walls and woodwork
4 wks Tue 1/30/01
Mon 2/26/01
98,95 Painting Contractor
Auto Scheduled
Install conduit at ceiling plenum space
3 wks Tue 12/5/00
Mon 12/25/00
93 Electric Contractor
Auto Scheduled
Install duct in ceiling plenum space
3 wks Tue 1/9/01 Mon 1/29/01
94,100 HVAC Contractor
Auto Scheduled
Install ceiling grid
2 wks Tue 1/30/01
Mon 2/12/01
94,101 Drywall Contractor
Auto Scheduled
Install ceiling tile
2 wks Tue 2/13/01
Mon 2/26/01
102 Drywall Contractor
Auto Scheduled
Hang wallpaper
2 wks Tue 2/13/01
Mon 2/26/01
102 Painting Contractor
Auto Scheduled
Install building carpet
4 wks Tue 2/27/01
Mon 3/26/01
99 Carpet Contractor
Auto Scheduled
Install hardware and accessories
3 wks Tue 2/27/01
Mon 3/19/01
99 G.C. Finish Carpenter Crew
Auto Scheduled
Complete interior and exterior sod and plantings
2 wks Tue 2/27/01
Mon 3/12/01
99 Landscape Contractor
Auto Scheduled
Pave, curb, and stripe parking lot
2 wks Tue 3/13/01
Mon 3/26/01
107 Paving Contractor
Auto Scheduled
Elevators 40 days Tue 7/4/00 Mon 8/28/00
Auto Scheduled
Set elevator equipment in shafts
4 wks Tue 7/4/00 Mon 7/31/00
80,45,12 Elevator Contractor
Auto Scheduled
Set equipment in mechanical room
2 wks Tue 8/1/00 Mon 8/14/00
110 Elevator Contractor
Auto Scheduled
Test and align doors and equipment
2 wks Tue 8/15/00
Mon 8/28/00
111 Elevator Contractor
Auto Scheduled
Plumbing 90 days Tue 11/7/00
Mon 3/12/01
Auto Scheduled
Rough-in plumbing in drywall walls
4 wks Tue 12/5/00
Mon 1/1/01
93 Plumbing Contractor
Auto Scheduled
Tie-in fire line riser and set valves
2 wks Tue 11/7/00
Mon 11/20/00
84 Plumbing Contractor
Auto Scheduled
Set plumbing fixtures and trim
3 wks Tue 1/2/01 Mon 1/22/01
85,114,79 Plumbing Contractor
Auto Scheduled
Flush, test, and clean piping and fixtures
2 wks Tue 2/27/01
Mon 3/12/01
99,115,116 Plumbing Contractor
Auto Scheduled
Electrical 139 days Wed 8/16/00
Mon 2/26/01
Auto Scheduled
Rough-in electrical in masonry walls
4 wks Wed 8/16/00
Tue 9/12/00
75,14 Electric Contractor
Auto Scheduled
Rough-in electrical in drywall walls
4 wks Tue 12/5/00
Mon 1/1/01
93 Electric Contractor
Auto Scheduled
Pull wire in conduit and set area transformers
3 wks Tue 12/26/00
Mon 1/15/01
119,100 Electric Contractor
Auto Scheduled
Install and terminate electrical devices
3 wks Tue 1/16/01
Mon 2/5/01
121,120 Electric Contractor
Auto Scheduled
Make electrical terminations for HVAC equipment
2 days Tue 1/16/01
Wed 1/17/01
121,91 Electric Contractor
Auto Scheduled
Install light fixtures - test and clean
2 wks Tue 2/13/01
Mon 2/26/01
102,122 Electric Contractor
Auto Scheduled
Heating and Ventilating - AC
180 days Tue 7/4/00 Mon 3/12/01
Auto Scheduled
Set equipment in mechanical room
2 wks Tue 7/4/00 Mon 7/17/00
80,15 HVAC Contractor
Auto Scheduled
Rough-in mechanical in masonry walls
4 wks Wed 8/16/00
Tue 9/12/00
75 HVAC Contractor
Auto Scheduled
Rough-in mechanical in drywall walls
2 wks Tue 12/5/00
Mon 12/18/00
93 HVAC Contractor
Auto Scheduled
Install duct in building chase
3 wks Tue 12/5/00
Mon 12/25/00
126,127,93 HVAC Contractor
Auto Scheduled
Set HVAC trim and test and balance system
4 wks Tue 2/13/01
Mon 3/12/01
102,129,123 HVAC Contractor
Auto Scheduled
Final Clean-up and Occupancy
60 days Tue 1/9/01 Mon 4/2/01
Auto Scheduled
Install hard tile flooring in common areas
1 wk Tue 1/9/01 Mon 1/15/01
94 Tile Contractor
Auto Scheduled
Clean hard tile floors
4 days Tue 1/16/01
Fri 1/19/01 132 Tile Contractor[50%]
Auto Scheduled
Remove debris from building and do final clean-up
4 days Tue 3/27/01
Fri 3/30/01 ########## G.C. Labor Crew
Auto Scheduled
Substantial completion date
1 day Mon 4/2/01 Mon 4/2/01
134 G.C. Superintendent
Auto Scheduled
Complete Final Inspections
6 days Mon 4/2/01
Mon 4/9/01
Auto Scheduled
Complete elevator inspection and certification
3 days Mon 4/2/01 Wed 4/4/01
134,112 Elevator Contractor
Auto Scheduled
Perform architect's inspection
1 day Thu 4/5/01 Thu 4/5/01 134,108,137
G.C. Superintendent[50%],G.C. Project Management[50%]
Auto Scheduled
Perform local building agency inspection
1 day Fri 4/6/01 Fri 4/6/01 138 G.C. Project Management[50%],G.C. Superintendent[50%]
Auto Scheduled
Perform Fire Marshal's inspection
1 day Mon 4/9/01 Mon 4/9/01
139
G.C. Superintendent[50%],G.C. Project Management[50%]
Auto Scheduled
Complete punch list items from all inspections
2 wks Tue 4/10/01
Mon 4/23/01
140
G.C. Superintendent[11%],G.C. Labor Crew[11%],Plumbing Contractor[11%],Electric Contractor[11%],HVAC Contractor[11%],Drywall Contractor[11%],Carpet Contractor[11%],Paving Contractor[11%],Painting Contractor[11%]
Auto Scheduled
Obtain certificate of occupancy
2 days Tue 4/24/01
Wed 4/25/01
141 G.C. Project Management
Auto Scheduled
Issue final completion documents including warranties
1 day Tue 4/24/01
Tue 4/24/01
141 G.C. Project Management