Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
ABOUT THE PROJECT The Spring Lake Wind Project is proposed of up to 200 megawatts (MW) of wind generating capacity to be developed, constructed and operated in the Rural Municipalities of Coulee and Whiska Creek, Southeast of Swift Current, Saskatchewan. In addition to working with the Rural Municipalities (RM), EDF EN Canada will seek necessary approvals for the Project from SaskPower, the Ministry of Environment and the Ministry of Parks, Culture and Sport.
In the coming months, the Project team will engage with community members, local First Nations, local government officials and local businesses to make sure the final Project design is socially, environmentally and economically sustainable. Our goal is to minimize potential impacts to the environment, local stakeholders and First Nation communities.
OPEN HOUSE
We invite you to come out and learn more about the Spring Lake Wind Project at our first community open house. Refreshments will be served. We hope to see you there!
TUESDAY, JULY 11, 2017 5:00 - 8:00 PM
Neville Community Centre231 Mowbray St., Neville, SK
Wind Turbines The Project will consist of 55-100 turbines with a capacity of 2 - 4.2 MW per turbine.
Each turbine will have a hub height be- tween 80 - 112.5 metres (m) and have a rotor diameter of 110 - 141 m.
Electric System Each turbine will be linked to the Project substation by a medium voltage collector system. The low volt-age cables will be buried underground, wherever practical. The location of the collector substation has not been deter-mined at this time.
Interconnection The Project will be interconnected to the 230 kilovolt (kV) transmission system in the area being operated by SaskPower.
Access Roads and Other Facili-ties During development and opera-tions of the Project, existing municipal roads will be used to access the Project site, wherever practical. There will also be an operations and maintenance building located on or near the Project boundary. We will work with the RM’s of Whiska Creek and Coulee to develop a road use agreement. This agreement ensures EDF EN Canada respects existing road use and conditions throughout construction and operation of the Project. During construc-tion, a temporary laydown area may also be required.
Meteorological Towers A number of temporary meteorological towers have already been installed at the Project site to measure wind speed, wind direction, air temperature, and barometric pressure. Permanent meteorological towers will be installed for monitoring during the opera-tional phase.
KEY PROJECT DETAILS
SUMMER 2017
SPR NG LAKEwind project
SPR NG LAKEwind project
WHY WIND, WHY NOW? Wind is among the lowest cost options for new
electricity generation. The Saskatchewan govern-
ment and SaskPower have committed to managing
emissions by rebuilding the electricity system to
meet the province’s current needs and to power a
sustainable future. In 2015, SaskPower set a target
EDF EN Canada has completed desktop analyses and
commenced field work on various Project aspects.
As development progresses, additional studies will
focus on:
o Wildlife – birds and bats
o Wetlands – mapping and classification
o Noise – impact assessment
o Heritage Resources
ANTICIPATED PROJECT TIMELINE
SPRING 2016 Desktop review and constraints analysis.
Land signing commenced
FALL 2016 - FALL 2017 Preliminary field work
Stakeholder engagement prior to project’s submission
to SaskPower
Q4 2017 – Q4 2018 Complete permitting
and stakeholder engagement
Second Open House
LATE 2017/ EARLY 2018Anticipate SaskPower will
announce winner of renew-able energy procurement
Q4 2018Issue Notice to Proceed (NTP) with contractors
Q4 2018 – Q2 2020 Commencement of construc-
tion, foundations, access roads, cabling, interconnection, erecting
towers and commissioning
APRIL 1, 2020Target Commercial
Operation Date
APRIL 1, 2040 Target
Decommissioning
FALL 2017Submit project for
consideration in SaskPower renewable energy
procurement
of 50% of generation capacity from renewable
energy by 2030. By meeting this target the province will
reduce greenhouse gas emissions by 40% below 2005
levels. To achieve this goal, SaskPower is projected
to bring on over 2,000 MW of NEW wind power capacity in
just over 12 years.
Throughout the development of the Project, we will
work closely with the Ministry of Environment and
Ministry of Parks, Culture and Sport to ensure we have
a robust understanding of the site.
ENVIRONMENTAL STUDIES UNDERWAY
Community Benefits
EDF EN Canada values the long-term benefits of working with the local community. If the Spring Lake Wind Project is approved, the local community will benefit from the following:
■ Employment opportunities during the construction and operation phases of the Project.
■ Contract opportunities for local businesses.
■ Local investments into hospitality and construction services during the development, construction and operations phases of the Project.
■ Tax revenues throughout the life of the Project.
First Nation Engagement We are committed to sustainable
stewardship of our natural resources
and value the unique traditions and
culture of First Nation communities.
As part of this commitment, we will
engage with potentially impacted
communities to better understand
their traditions and priorities.
IN YOUR COMMUNITY
Community Involvement
EDF EN Canada believes every renewable energy project should be developed in lasting partnership with the local community. We strive to be a good neighbour and we work closely with the community to design our Project in a way that is respectful to the needs, heritage and future of the RM of Coulee and the RM of Whiska Creek.
The quantity of energy produced by a turbine largely depends on:
■ wind speed
■ the area swept by the blades
■ generator size
■ air density and temperature
■ 10.5 km/h (3 m/s) is the minimum speed needed to generate enough lift to start operation and electricity.
■ 43 km/h (12 m/s) is the speed needed to produce at full power.
■ 90 km/h (25 m/s) is the maximum speed. At speeds higher than this, the turbine shuts down to ensure safety and prevent equipment failure.
HOW WIND WORKS
5 6
Turbine blades generate lift from energy extracted from the wind with rotations between 9-16 RPM.
1 32 The electrical generator inside the turbine rotor converts mechanical energy into electrical energy. The electricity produced is then converted to the right voltage for distribution.
The transformer is located at the base of the turbine or inside the nacelle and efficiently transports electricity by the collector system.
It might appear relatively small, but the powerful nacelle, which is the box at the top of the turbine, weighs roughly 70 tonnes and contains the majority of the wind turbine compo-nents, which includes the gearbox, rotor shaft, brake assembly and the transformer.
The collector system carries electricity to the substation. Collector systems are under- ground circuits that connect wind turbines together.
4 At the substation, the voltage is transformed once more to higher voltages.
Electricity is metered and delivered to the utility.
EDF EN Canada Inc.53 Jarvis Street, Suite 300 Toronto, ON M5C 2H21-844-55-EDF-EN / 1-844-553-3336www.edf-en.ca
ABOUT EDF EN CANADA
Expertise | Innovation | Commitment EDF EN Canada’s strength is grounded in the extensive experience the company has gained across the spectrum of services required for the development and long-term operation of successful renewable projects.
Whether building a 10 MWp solar project or a 350 MW wind project, EDF EN Canada simplifies the entire process by consolidating all the services under one roof. We manage the project every step of the way, from site analyses, system design, procurement of equipment, financing, construction, to operation and maintenance.
We proudly stand behind our installations and our name. We believe every installation is the beginning of a lasting partnership.
1,680+ MW Put into Service, Under Construction, or In Development
844-55-EDF-EN / 844-553-3336
www.edf-en.ca/project/spring-lake-wind-project/
Arnprior23.4 MWp
Dec 2009
Saint-Robert- Bellarmin
80 MWOct 2012
Blackspring Ridge
300 MWMay 2014
Riviere- du-Moulin350 MWNov 2015
Pendelton~15 MWp
Dec 2018
Barlow~12 MWp
Dec 2018
1,680+ MW Put into Service, Under Construction, or In Development
La Mitis 24,6 MW
Oct 2014
Lac-Alfred 300 MW
Jan 2013
Mont-Rothery
74 MWDec 2015
Nicolas-Riou
224,25 MW
Dec 2017Massif du Sud
150 MWJan 2013
Wind
Solar
Le Granit 24,6 MW
Nov 2014
St. Isidore23.4 MWp
Dec 2010
Romney60 MWDec 2019
Elmsley24 MWpDec 2010
EDF Renewable Energy, EDF EN Canada, EDF EN Mexico are Renewable Independent Power Producers (IPP) originating, developing, building and managing projects. EDF Energies Nouvelles (EDF EN), is the global renewable energy arm of the Group. Present in more than 20 countries, the company develops, builds and operates renewable power plants. In North America, EDF EN is represented by three subsidiaries.
EDF Group, through its subsidiaries in North America delivers results to utilities, commercial & industrial, and corporate purchasers through the supply of renewable energy.
is the leading electricity company in the world.
CONTACT US
EDF EN Canada is part of the global leader in electricity
EDF EN Canada is a green energy pioneer and market leader with over 1,680 MW of wind and solar energy in varying stages of development, active construction and operation across Canada. We develop, design, build and operate renewable energy projects that harness the earth’s renewable resources.
425,000
Over 3,000
>$11,000,000
>$3.5 billion
equivalent homes powered by EDF EN Canada
cumulative workers during peak construction across our portfolio
Annual landowner revenue from land payments
invested in Canada since 2008
ECONOMIC IMPACT of EDF EN Canada’s Renewable Energy Projects