Ongoing Initiatives &Contracting Impacts
17 September 2009
Ms. Joy WhiteDirector of Contracting
Space and Missile Systems Center
2
Outline
Opening Remarks
MIRTs & Peer Reviews
Incentives
Organizational Conflict of Interest (OCI)
Questions
This Briefing Is Unclassified
3
Opening Remarks
4
Multi-Functional IndependentReview Team (MIRT)
• Charter Provide CAA feedback on
quality of clearance action Required for competitive
awards >$50M
• Team Composition Technical Legal Contracting Others as applicable
• Review Occurrences Pre ASP/AP Pre RFP Pre ENs or Competitive Range Pre FPR Pre Award
• Focus Areas for Critical Decision Points Consistency Clarity Reasonableness
5
Peer Reviews
• Policy Objectives Ensure COs implement policy &
regulations consistent & appropriate manner
Continue to improve quality of contracting process
Facilitate cross-sharing of best practices & lessons learned
• Team Composition Senior DOD contracting leaders
& members of the Office of General Counsel
• Review Occurrences Competitive - Prior to issuance
of solicitation, final proposal revisions, & contract award
Sole source - At pre and post business clearance phases
• Applicability Contracts $1B or more
6
Incentives
Moving away from Award Fee contracts
Moving toward all objective incentives
Use of negative incentives is on the rise – holding
contractors accountable for acquisition outcomes
If an award fee contract is utilized - encouraged to use
base fee
Looking at prohibiting rollover of award fee &
provisional payments
7
OCI
We are seeing very restrictive interpretations that go
beyond existing regulatory language
Concern regarding ability to have effective competition
Awaiting regulatory language that clarifies ability to
mitigate
Currently using an OCI Panel, corporate wide-plans
and open communication to minimize potential
impacts
8
QUESTIONS???