Antti Piirto 11.06.22 The first EPR under Construction in Finland International Nuclear Forum 2008 ”Bulgarian Nuclear Energy – National, Regional and World Energy Safety”

Olkiluoto 3 project status

  • Upload
    beau

  • View
    113

  • Download
    0

Embed Size (px)

DESCRIPTION

The first EPR under Construction in Finland International Nuclear Forum 2008 ”Bulgarian Nuclear Energy – National, Regional and World Energy Safety”. Olkiluoto 3 project status. Progress of work at OL3. Focal operating areas in 2008 : - PowerPoint PPT Presentation

Citation preview

Page 1: Olkiluoto 3 project status

Antti Piirto20.04.23

The first EPR under Construction in Finland

International Nuclear Forum 2008 ”Bulgarian Nuclear Energy – National, Regional

and World Energy Safety”

Page 2: Olkiluoto 3 project status

Antti Piirto20.04.23

2

Olkiluoto 3 project status

Page 3: Olkiluoto 3 project status

Antti Piirto20.04.23

3

Page 4: Olkiluoto 3 project status

Antti Piirto20.04.23

4

Focal operating areas in 2008:

Preparation and review of design documentation and approval procedure: continues in full extent over to 2009, turbine island documentation to be completed in the autumn

Fabrication: major part of main components to be completed and the key components to be shipped to Olkiluoto during 2008. Fabrication of auxiliary equipment continues actively throughout the year

Progress of work at OL3

Page 5: Olkiluoto 3 project status

Antti Piirto20.04.23

5

Focal operating areas in 2008:

Construction: work to continue at reactor plant over to 2009. Turbine building about to be completed, other turbine island buildings will be completed in the autumn

Installation work: installation work in turbine island to be completed to a large extent by the end of the year, installation work has started in the reactor island, work intensity will increase during the year

Progress of work at OL3

Page 6: Olkiluoto 3 project status

Antti Piirto20.04.23

6

No safety, quality or (major) technical non-conformities

Refabrication of reactor coolant piping continues, five new pipes have been completed with approvable results. Two more pipes will be completed during the summer, and the last one in the autumn

Conformity / Quality assurance

Page 7: Olkiluoto 3 project status

Antti Piirto20.04.23

7

Refabrication of four so-called cross-over pipe sections (bent reactor coolant piping) continues according to plans

Rework on generator water cooling system has been completed with approvable results. Factory acceptance tests about to start

Conformity / Quality assurance

Page 8: Olkiluoto 3 project status

Antti Piirto20.04.23

8

General site occupational safety index has remained at a good level

One fatal injury on the site in September 2007

Occupational safety

Page 9: Olkiluoto 3 project status

Antti Piirto20.04.23

9

Occupational Safety Index

Page 10: Olkiluoto 3 project status

Antti Piirto20.04.23

10

More than 1900 direct subcontractors from 28 countries (about 40% from Finland)

Manpower on site about 3100

Polish workers constitute the largest group with 40%, followed by Finnish with 26%, German with 13%, French with 5%, Slovakian with 4%, Estonian with 3%

Manpower

Page 11: Olkiluoto 3 project status

Antti Piirto20.04.23

11

Manpower in construction work has reached its maximum, the share of installation work is on the increase, the number of electrical installation crew will also grow after summer 2008

All major work on the site carried out in shifts

Recruiting of operation and maintenance personnel under way, for example shift supervisors and licensed operators

Manpower

Page 12: Olkiluoto 3 project status

Antti Piirto20.04.23

12

The present delay is approximately two years Cold tests at turbine plant to start at the beginning of

2009 Turbine plant ready to a great extent in summer 2009

OL3 Schedule

Page 13: Olkiluoto 3 project status

Antti Piirto20.04.23

13

More than 50000 technical documents submitted to TVO for review, examination and approval

Submittal of further documentation to continue over to 2009

Contracts concluded for all key deliveries

All large components of reactor island in manufacture, final tests about to start (e.g. reactor pressure vessel will be shipped to Finland in late autumn)

Equipment and Component Fabrication

Page 14: Olkiluoto 3 project status

Antti Piirto20.04.23

14

Turbines have been completed, last inspections under way. Generator factory acceptance tests start this month

All but one steel liner ring sections have been produced. The fabrication of the dome section nearing completion. Liner sections 4+5 were erected in the reactor building at the beginning of May

Large moisture separators / reheaters have been shipped to the site

Equipment and Component Fabrication

Page 15: Olkiluoto 3 project status

Antti Piirto20.04.23

15

Reactor plant level +7.44 has been poured. The first internal form of the reactor pool has been erected in place

Second pouring section in the external wall of the containment has been completed. External wall stands now at level + 27 m and internal wall at level + 10 m

Work continues in auxiliary and other buildings

Approximately 127,000 m3 of concrete poured so far

Construction

Page 16: Olkiluoto 3 project status

Antti Piirto20.04.23

16

February 2008 April 2008

Construction of the Reactor Building

Page 17: Olkiluoto 3 project status

Antti Piirto20.04.23

17

Page 18: Olkiluoto 3 project status

Antti Piirto20.04.23

18

The First Internal Form of the Reactor

pool

Page 19: Olkiluoto 3 project status

Antti Piirto20.04.23

19

First containers installed in reactor building

Installation of condenser completed

Preheaters, main condensate pumps, some containers, other pumps and low-pressure piping installed in turbine building

Installation of cable trays as well as lighting and ventilation systems continues in switchgear building

Installation

Page 20: Olkiluoto 3 project status

Antti Piirto20.04.23

20

Large moisture separators / reheaters delivered to site, installation in the turbine building takes place in May

Overhead bridge crane now in operation in the turbine building

Installation

Page 21: Olkiluoto 3 project status

Antti Piirto20.04.23

2121

6.5.2008

Main Steam Valves

Page 22: Olkiluoto 3 project status

Antti Piirto20.04.23

22

Page 23: Olkiluoto 3 project status

Antti Piirto20.04.23

2323

29.4.2008

Page 24: Olkiluoto 3 project status

Antti Piirto20.04.23

24

OL3 status May 2008

Focus on construction in the reactor plant Focus shifted to installation in the turbine

plant Deliveries of large components to site have

continued Training of operating personnel continues Commercial operation of plant unit to start in

2011

Page 25: Olkiluoto 3 project status

Antti Piirto20.04.23

25

What is different from OL1 / OL2 projects?

Finnish Nuclear Safety requirements and European utility requirements vs. US Reg. guides

New regulatory reguirements related to severe reactor accidents and airplain crash

Strict Regulatory control Number of subcontractors very high ->

project management and quality control more demanding

No strikes