CURRENT PROJECT CAPACITY START-UP REGULATORY STATUS NORTH ATHABASCA REGION — MINING Canadian Natural Resources Limited Horizon Updated: May 2012 Canadian Natural says that during the first quarter, a third ore preparation plant and associated hydrotransport unit were successfully integrated into operations. The infrastructure is expected to increase reliability going forward by allowing the company to maintain steady feedstock to the upgrader with two of the three ore preparation plants continually on stream. Phase 1 135,000 2008 Operating Phase 2A 10,000 2014 Approved Phase 2B 45,000 TBD Approved Phase 3 80,000 TBD Approved Tranche 2 5,000 2012 Operating Imperial Oil Limited Kearl Updated: May 2012 Imperial Oil says that construction of Kearl Phase 1 is 90 per cent complete and is progressing to expected start-up in late 2012. Phase 1 110,000 2012 Construction Phase 2 110,000 2015 Construction Phase 3 Debottleneck 70,000 2020 Approved Shell Albian Sands Jackpine Updated: Jun 2012 The joint review panel reviewing the proposed Jackpine mine expansion has extended its period of public comment to August 3. Expansion 100,000 2017 Application Phase 1A 100,000 2010 Operating Phase 1B 100,000 TBD Approved Muskeg River Updated: May 2012 Twenty per cent project owner Marathon Oil Corporation says that production rates were down during Q1 due to reliability issues. Commercial 155,000 2002 Operating Expansion & Debottlenecking 115,000 TBD Approved Pierre River Updated: Jun 2012 A joint review panel of the Canadian Environmental Assessment Agency and the Energy Resources Conservation Board has been established to review the proposed Pierre River mine project. Phase 1 100,000 2018 Application Phase 2 100,000 TBD Application Suncor Energy Inc. Base Operations Updated: May 2012 Suncor is now mining volumes from the North Steepbank Extension. The company expects that its Millennium Naphtha Unit (MNU) project will be fully operational by mid-year. In April, Suncor announced its upgrader had successfully returned to normal operations following a brief shutdown due to a fractionated performance issue. Suncor has started commissioning assets associated with its tailings reduction operations infrastructure project and anticipates to start using these assets during Q2. Millennium Debottlenecking 23,000 2008 Operating Millennium Mine 294,000 1967 Operating North Steepbank Extension 180,000 2012 Operating Steepbank Debottleneck Phase 3 4,000 2007 Operating CURRENT PROJECT CAPACITY START-UP REGULATORY STATUS Fort Hills Updated: May 2012 Suncor says current work on Fort Hills includes progressing design basis memorandum engineering, site preparation and procurement for long-lead items. The company expects to present development plans to the board of directors for sanction in 2013. Debottleneck 25,000 TBD Approved Phase 1 165,000 2016 Approved Voyageur South Updated: May 2012 Suncor considers Voyageur South to be a longer-term project and has not confirmed a start-up date. Phase 1 120,000 TBD Application Syncrude Canada Ltd. Mildred Lake/Aurora North & South Updated: May 2012 Construction is underway on a number of major projects including mine train replacement and re- location, the Aurora North Tailings Management Project, the Syncrude Emissions Reduction Project and the Centrifuge Tailings Management Project. Aurora South Train 1 100,000 2016 Approved Aurora South Train 2 100,000 2018 Approved Base Mine Stage 1 & 2 Expansion 290,700 1978 Operating Stage 3 Expansion 116,300 2006 Operating Teck Recources Limited Frontier Updated: May 2012 The Canadian Environmental Assessment Agency has announced that a period of public comment is underway and participant funding is being allocated. Comments are being accepted until June 4. Teck says that no field exploration activities are planned in 2012 and the key focus will be on supporting the regulatory application review, the consultations with stakeholders and the ongoing engineering studies. Phase 1 75,000 2021 Application Phase 2 80,000 2024 Application Phase 3 80,000 2027 Application Phase 4 Equinox 40,000 2030 Application Total E&P Canada Ltd. Joslyn North Mine Updated: May 2012 Project partner Suncor Energy says that current capital expenditures are around further design work, drilling and site preparation. The partners plan to submit development plans to their respective boards of directors for sanction in 2013. Phase 1 100,000 2018 Approved NORTH ATHABASCA REGION — IN SITU Athabasca Oil Corporation Birch Updated: May 2012 AOSC says the updated contingent resources on its Birch holdings total 1.9 billion barrels. The company plans to submit its Birch regulatory application in late 2012 based on additional drilling and 3-D seismic. Phase 1 12,000 TBD Announced Dover West Carbonates (Leduc) Updated: May 2012 AOSC says production testing continues while it works on the TAGD pilot. An update from the TAGD proof of concept is expected in Q2. The company has responded to the first round of supplemental information requests from regulators and has launched work on its design basis memorandum. Phase 1 Demonstration 6,000 2015 Application Phase 2 Demonstration 6,000 TBD Application 36 OILSANDS REVIEW | AUGUST 2012 PROJECT STATUS PROJECT STATUS Peace River Region Athabasca Region Northwestern Saskatchewan Industrial Heartland Region Cold Lake Region 08. 12 Sourced from company releases, the Energy Resources Conservation Board, and the Daily Oil Bulletin, with files from Strategy West. For changes and updates, please contact Deborah Jaremko at [email protected]. Disclaimer: Oilsands Review accepts no liability for errors or inaccuracies in the information provided in this report. For even more details on all of these projects, visit www.oilsandsreview.com. NORTH ATHABASCA REGION SOUTH ATHABASCA REGION COLD LAKE REGION SASKATCHEWAN REGION INDUSTRIAL HEARTLAND REGION NEW EXPORT PIPELINES PEACE RIVER REGION NEW INFORMATION THIS MONTH

Oilsands Review Project Status August 2012

Embed Size (px)

DESCRIPTION

Sourced from company releases, the Energy Resources Conservation Board and the Daily Oil Bulletin, with files from Strategy West. For changes and updates, please contact Deborah Jaremko at [email protected].

Citation preview

Page 1: Oilsands Review Project Status August 2012

current proJect capacity start-up reGulatory status

nortH AtHAbAScA reGion — mininGcanadian natural resources limited

Horizon Updated: may 2012

canadian natural says that during the first quarter, a third ore preparation plant and associated hydrotransport unit were successfully integrated into operations. the infrastructure is expected to increase reliability going forward by allowing the company to maintain steady feedstock to the upgrader with two of the three ore preparation plants continually on stream.

phase 1 135,000 2008 operating

phase 2a 10,000 2014 approved

phase 2B 45,000 tBd approved

phase 3 80,000 tBd approved

tranche 2 5,000 2012 operating

imperial oil limited

kearl Updated: may 2012

imperial oil says that construction of Kearl phase 1 is 90 per cent complete and is progressing to expected start-up in late 2012.

phase 1 110,000 2012 construction

phase 2 110,000 2015 construction

phase 3 debottleneck 70,000 2020 approved

Shell Albian Sands

• jackpine Updated: jun 2012

the joint review panel reviewing the proposed Jackpine mine expansion has extended its period of public comment to august 3.

expansion 100,000 2017 application

phase 1a 100,000 2010 operating

phase 1B 100,000 tBd approved

muskeg river Updated: may 2012

twenty per cent project owner Marathon oil corporation says that production rates were down during Q1 due to reliability issues.

commercial 155,000 2002 operating

expansion & debottlenecking 115,000 tBd approved

• pierre river Updated: jun 2012

a joint review panel of the canadian environmental assessment agency and the energy resources conservation Board has been established to review the proposed pierre river mine project.

phase 1 100,000 2018 application

phase 2 100,000 tBd application

Suncor energy inc.

base operations Updated: may 2012

suncor is now mining volumes from the north steepbank extension. the company expects that its Millennium naphtha unit (Mnu) project will be fully operational by mid-year. in april, suncor announced its upgrader had successfully returned to normal operations following a brief shutdown due to a fractionated performance issue. suncor has started commissioning assets associated with its tailings reduction operations infrastructure project and anticipates to start using these assets during Q2.

Millennium debottlenecking 23,000 2008 operating

Millennium Mine 294,000 1967 operating

north steepbank extension 180,000 2012 operating

steepbank debottleneck phase 3 4,000 2007 operating

current proJect capacity start-up reGulatory status

fort Hills Updated: may 2012

suncor says current work on fort hills includes progressing design basis memorandum engineering, site preparation and procurement for long-lead items. the company expects to present development plans to the board of directors for sanction in 2013.

debottleneck 25,000 tBd approved

phase 1 165,000 2016 approved

voyageur South Updated: may 2012

suncor considers voyageur south to be a longer-term project and has not confirmed a start-up date.

phase 1 120,000 tBd application

Syncrude canada ltd.

mildred lake/Aurora north & South Updated: may 2012

construction is underway on a number of major projects including mine train replacement and re-location, the aurora north tailings Management project, the syncrude emissions reduction project and the centrifuge tailings Management project.

aurora south train 1 100,000 2016 approved

aurora south train 2 100,000 2018 approved

Base Mine stage 1 & 2 expansion 290,700 1978 operating

stage 3 expansion 116,300 2006 operating

teck recources limited

frontier Updated: may 2012

the canadian environmental assessment agency has announced that a period of public comment is underway and participant funding is being allocated. comments are being accepted until June 4. teck says that no field exploration activities are planned in 2012 and the key focus will be on supporting the regulatory application review, the consultations with stakeholders and the ongoing engineering studies.

phase 1 75,000 2021 application

phase 2 80,000 2024 application

phase 3 80,000 2027 application

phase 4 equinox 40,000 2030 application

total e&p canada ltd.

joslyn north mine Updated: may 2012

project partner suncor energy says that current capital expenditures are around further design work, drilling and site preparation. the partners plan to submit development plans to their respective boards of directors for sanction in 2013.

phase 1 100,000 2018 approved

nortH AtHAbAScA reGion — in SitUAthabasca oil corporation

birch Updated: may 2012

aosc says the updated contingent resources on its Birch holdings total 1.9 billion barrels. the company plans to submit its Birch regulatory application in late 2012 based on additional drilling and 3-d seismic.

phase 1 12,000 tBd announced

dover West carbonates (leduc) Updated: may 2012

aosc says production testing continues while it works on the taGd pilot. an update from the taGd proof of concept is expected in Q2. the company has responded to the first round of supplemental information requests from regulators and has launched work on its design basis memorandum.

phase 1 demonstration 6,000 2015 application

phase 2 demonstration 6,000 tBd application

36 oilsands review | AUGUST 2012

P R O J E C T S TAT U S

project STATUSPeace River Region

Athabasca Region

Northwestern Saskatchewan

Industrial Heartland Region

Cold Lake Region08.12

Sourced from company releases, the energy Resources Conservation Board, and the Daily Oil Bulletin, with files from Strategy West. For changes and updates, please contact deborah jaremko at [email protected]. Disclaimer: Oilsands Review accepts no liability for errors or inaccuracies in the information provided in this report.

For even more details on all of these projects, visit www.oilsandsreview.com.

nortH AtHAbAScA reGion

SoUtH AtHAbAScA reGion

cold lAke reGion

SASkAtcHeWAn reGion

indUStriAl HeArtlAnd reGion

neW eXport pipelineS

peAce river reGion neW informAtion tHiS montH•

Page 2: Oilsands Review Project Status August 2012

FEATURE LISTING:FOR SALE LEASE, FT. MCMURRAY, AB, CANADAKUUSAMO DEVELOPMENTS - MACKENZIE PARK

> 400 MacKenzie Blvd., Ft. McMurray> 1,500–29,000 SF> IB - Business Industrial> Grade Loading

Contact: Ken Shebib, CCIM

780 881 6297www.collierscanada.com/5981

Colliers Macaulay Nicolls Inc.3555 Manulife Place, 10180 - 101 StreetEdmonton, AB T5J 3S4

780 420 1585www.collierscanada.com

Leading businesses have come to rely on Colliers International to advance their interests in real estate. With a greater sense of drive, as well as local market expertise, we’ll help you move swiftly along the right track—to accelerate your success.

LOCAL PEOPLE WITH GLOBAL STRENGTH

current proJect capacity start-up reGulatory status

dover West Sands & clastics Updated: may 2012

aosc says construction of an all-weather access road to the dover west area is 85 per cent com-plete, with one bridge remaining to be built. completion is expected in Q3.

phase 1 12,000 2015 application

phase 2 35,000 2018 announced

phase 3 35,000 2020 announced

bp p.l.c.

terre de Grace Updated: mar 2012

pilot 10,000 tBd approved

canadian natural resources limited

• birch mountain Updated: jun 2012

canadian natural says first steam for phase 1 is expected in 2019, 2023 for phase 2.

phase 1 60,000 2019 announced

phase 2 60,000 2023 announced

cenovus energy inc.

telephone lake borealis Updated: may 2012

cenovus says it continues to search for a strategic transaction to support development of the telephone lake project.

phase a 45,000 tBd application

phase B 45,000 tBd application

dover operating corp.

dover Updated: Apr 2012

dover opco says the project is in the final stages of the regulatory review process.

phase 1 50,000 2015 application

subsequent phases 200,000 tBd application

mackay river Updated: Apr 2012

ercB project approval was granted in January 2012. dover opco says construction is underway.

phase 1 35,000 2014 construction

phase 2 40,000 2017 approved

phase 3 40,000 2019 approved

phase 4 35,000 tBd approved

e-t energy ltd.

• poplar creek Updated: jun 2012

the ercB has released its decision on the 10,000-barrel-per-day project application. it says e-t has not demonstrated the technology is capable of obtaining or sustaining commercial pro-duction rates and the application is not approved. the ercB says e-t can reapply based on more performance data, which the company says it has (the application did not include data from the current test).

phase 1 10,000 tBd announced

phase 2 40,000 tBd announced

pilot 1,000 2007 operating

current proJect capacity start-up reGulatory status

Husky energy inc.

Saleski Updated: may 2012

carbonate pilot tBd 2016 announced

Sunrise Updated: may 2012

husky says phase 1 construction remains on schedule for first production in 2014. all 49 horizontal well pairs have been completed. construction of the camp is nearing completion and occupancy is expected in Q2. detailed engineering for facilities and supporting infrastructure continues, as well as early engineering for the next phase.

phase 1 60,000 2014 construction

phase 2 50,000 2016 approved

phase 3 50,000 tBd approved

phase 4 50,000 tBd approved

ivanhoe energy inc.

tamarack Updated: may 2012

ivanhoe says it has received a second round of supplemental information requests regarding its pro-ject application from the ercB. it continues to expect approval in 2012.

phase 1 20,000 2013 application

phase 2 20,000 tBd application

marathon oil corporation

birchwood Updated: Sep 2011

demonstration 12,000 2016 application

oak point energy ltd.

lewis Updated: mar 2012

pilot 1,720 2013 application

SilverWillow energy corporation

• Audet Updated: jun 2012

silverwillow says for the remainder of 2012 it will focus on analyzing samples and data from this year’s drilling program. it will also be conducting an environmental baseline assessment and prepar-ing preliminary engineering design for a pilot saGd project to enable preparation of a regulatory application, which is expected to be filed in the second quarter of 2013.

pilot 12,000 2016 announced

Southern pacific resource corp.

• Stp-mckay Updated: july 2012

southern pacific says it has commenced steam injection at the stp-McKay project. first oil is expected within three to four months.

phase 1 12,000 2012 operating

phase 1 expansion 6,000 tBd application

phase 2a 12,000 2015 application

phase 2B 6,000 tBd application

Suncor energy inc.

firebag Updated: may 2012

suncor says that ramp-up of the firebag stage 3 expansion is proceeding in line with expectations. construction of stage 4 is also proceeding. during Q1, suncor says it focused on construction of two new well pads, central processing facilities and cogeneration units.

cogeneration and expansion 25,000 2007 operating

AUGUST 2012 | oilsandsreview.coM 37

P R O J E C T S TAT U S

Page 3: Oilsands Review Project Status August 2012

Proof 1

Long on expertise, short on bureaucracyAs SAGD specialists, PROJEX brings proven rigor to oil sands thermal engineering projects. What we don’t bring is red tape and bureaucracy. Give us a call. We’d welcome the chance to show you the PROJEX difference. Contact Scott Rempel at 403.705.4151.

experience • exceLLence • execution

current proJect capacity start-up reGulatory status

stage 1 35,000 2004 operating

stage 2 35,000 2006 operating

stage 3 62,500 2011 operating

stage 3-6 debottleneck 23,000 tBd application

stage 4 62,500 2013 construction

stage 5 62,500 2018 approved

stage 6 62,500 2019 approved

lewis Updated: dec 2010

phase 1 40,000 tBd application

phase 2 40,000 tBd application

mackay river Updated: feb 2012

suncor has commenced production from a new phase of six wells at MacKay river and initiated steam injection into additional wells. production from these developments is expected to offset natural declines in the future.

Mr2 40,000 2016 application

phase 1 33,000 2002 operating

Sunshine oilsands ltd.

Harper Updated: may 2012

sunshine says that steam cycle injection operations at harper have proved thermally induced oil mobility.

carbonate pilot 1,000 2011 operating

legend lake Updated: may 2012

phase 1 10,000 2016 application

phase 2 10,000 tBd announced

phase 2 expansion 10,000 tBd announced

phase 3 20,000 tBd announced

phase 3 expansion 10,000 tBd announced

thickwood Updated: may 2012

sunshine oilsands has submitted the regulatory application for its thickwood saGd project, antici-pating project start-up in 2015.

phase 1 10,000 2015 application

phase 2 20,000 2018 announced

phase 2 expansion 20,000 2021 announced

West ells Updated: may 2012

sunshine says that following regulatory approval, its external reservoir engineering firm, GlJ petroleum consultants, considers the project to have a high degree of certainty of implementation and that development will proceed.

a phase 1 5,000 2013 construction

a phase 2 5,000 2014 approved

a phase 3 20,000 2018 announced

B phase 1 20,000 2020 announced

B phase 2 20,000 tBd announced

c phase 1 30,000 tBd announced

current proJect capacity start-up reGulatory status

SoUtH AtHAbAScA reGion — in SitUAlberta oilsands inc.

• clearwater West Updated: jun 2012

alberta oilsands says it has responded to a third round of supplemental information requests from the ercB regarding the project application. the company expects the regulator will hold a public hearing into the project, due in part to its proximity to the fort McMurray airport.

phase 1 pilot 4,350 tBd application

phase 2 25,000 2016 announced

Athabasca oil corporation

Hangingstone Updated: may 2012

in early March, aosc responded to its second round of supplemental information requests from the ercB. the company anticipates regulatory approval in Q3, and has placed orders for more than 75 per cent of long-lead items required for construction. aosc says tenders received conform to budget and schedule.

phase 1 12,000 2014 application

phase 2 35,000 2017 announced

phase 3 35,000 2019 announced

blackpearl resources inc.

• blackrod Updated: jun 2012

Blackpearl says production from the pilot has reached commercial production rates. the company has filed the regulatory application for the full 80,000-barrel-per-day project.

phase 1 20,000 2016 application

phase 2 30,000 2018 application

phase 3 30,000 2021 application

pilot 800 2011 operating

canadian natural resources limited

• Gregoire lake Updated: jun 2012

canadian natural says first steam for phase 1 is expected in 2021, and 2025 for phase 2.

phase 1 40,000 2021 announced

phase 2 40,000 2025 announced

• Grouse Updated: jun 2012

regulatory application filed in May. canadian natural says it plans to file a regulatory expansion for an expansion at Grouse in 2012.

commercial 50,000 2018 application

• kirby north Updated: jun 2012

canadian natural says construction preparation work is underway for Kirby north phase 1, including construction of the main access road and site clearing for the plant. the company plans to complete the engineering design specifications for phase 1 in 2012.

phase 1 40,000 2016 application

phase 2 40,000 2019 application

kirby South Updated: may 2012

canadian natural says construction of phase 1 is 42 per cent complete and remains on-cost and on-schedule for first steam in 2013. the fourth of seven well pads is being drilled, with wells reportedly confirming geological expectations.

phase 1 40,000 2013 construction

phase 2 20,000 2020 application

38 oilsands review | AUGUST 2012

P R O J E C T S TAT U S

Page 4: Oilsands Review Project Status August 2012

822403Sound QI Inc

1/4h · tqcno stacking

Learn how our Quantitative Interpretation (QI) expertise in the oil sands improves reservoir understanding and enhances recovery.sound-qi.com

SOUND SOLUTIONS

SOUND SCIENCE. SOUND RESULTS. SOUND QI.

current proJect capacity start-up reGulatory status

cavalier energy inc.

Hoole Updated: may 2012

cavalier owner paramount resources says that during the first quarter, cavalier continued to build its management team with the addition of key technical personnel. the hoole project application is expected to be submitted in Q4.

phase 1 10,000 2015 announced

phase 2 30,000 tBd announced

phase 3 30,000 tBd announced

phase 4 30,000 tBd announced

cenovus energy inc.

christina lake Updated: may 2012

construction of phase d is more than three-quarters complete and production is expected in the fourth quarter of this year. construction of phase e is more than 40 per cent complete, with produc-tion expected in the fourth-quarter of 2013. site preparation continues for phase f.

phase 1a 10,000 2002 operating

phase 1B 8,800 2008 operating

phase c 40,000 2011 operating

phase d 40,000 2012 construction

phase e 40,000 2013 construction

phase f 50,000 2016 approved

phase G 50,000 2017 approved

phase h 40,000 2019 announced

foster creek Updated: may 2012

cenovus says it continues to work on fabrication and facility construction for phase f, earthworks and site preparation for phase G, and design engineering for phase h.

phase a 24,000 2001 operating

phase B debottleneck 6,000 2003 operating

phase c stage 1 10,000 2005 operating

phase c stage 2 20,000 2007 operating

phase d 30,000 2009 operating

phase e 30,000 2009 operating

phase f 45,000 2014 construction

phase G 40,000 2015 approved

phase h 40,000 2016 approved

phase i 45,000 2017 announced

• narrows lake Updated: jun 2012

narrows lake regulatory approval granted in late May. sanction by partners cenovus and conocophillips canada anticipated later this year.

phase 1 43,333 2016 approved

phase 2 43,333 tBd approved

phase 3 43,334 tBd approved

current proJect capacity start-up reGulatory status

pelican lake Grand rapids Updated: may 2012

cenovus drilled a second well pair at its Grand rapids saGd pilot in Q1.

phase a 60,000 2017 application

phase B 60,000 tBd application

phase c 60,000 tBd application

pilot 600 2011 operating

connacher oil And Gas limited

• Great divide Updated: jun 2012

connacher reports that, with its budget constrained for 2012, operational activities include increasing net-backs by reducing operating costs and increasing realized bitumen prices, maintaining production within its announced guidance, de-risking and preparing various short-term projects for bitumen production increases, and improving production with technology innovations such as saGd+ at algar and gas re-injection at Great divide. the company’s strategic review process continues.

algar pod 2 10,000 2010 operating

expansion 1a 12,000 2014 application

expansion 1B 12,000 2016 application

pod 1 10,000 2007 operating

conocophillips canada limited

Surmont Updated: mar 2012

phase 1 27,000 2007 operating

phase 2 109,000 2015 construction

pilot 1,200 1997 operating

devon canada corporation

jackfish Updated: dec 2011

devon reports that Jackfish 3 construction is now underway, and that Jackfish 2 volumes are ramp-ing up ahead of plan and on target to reach capacity of 35,000 barrels per day by late 2012.

phase 1 35,000 2007 operating

phase 2 35,000 2011 operating

phase 3 35,000 2015 construction

• pike Updated: jun 2012

devon filed the regulatory application for all three phases of the pike project in June. the company says facility construction and saGd drilling for the first phase will begin in late 2013 or early 2014, pending corporate approvals.

1a 35,000 2016 application

1B 35,000 2017 application

1c 35,000 2018 application

Grizzly oil Sands Ulc

Algar lake Updated: may 2012

part-owner Gulfport energy says Grizzly’s algar construction is on track for commissioning in Q4, with first production in mid-2013. Grizzly also believes it has delineated sufficient resource at thickwood hills to support commercial development of the property and plans to submit a project regulatory application in 2012.

phase 1 5,650 2013 construction

phase 2 5,650 2014 approved

AUGUST 2012 | oilsandsreview.coM 39

P R O J E C T S TAT U S

Page 5: Oilsands Review Project Status August 2012

current proJect capacity start-up reGulatory status

may river Updated: Apr 2012

Grizzly has closed its acquisition of May river from petrobank energy and resources. development plans are under review.

phase 1 10,000 2013 application

subsequent phases 90,000 tBd disclosed

Harvest operations corp.

blackGold Updated: may 2012

harvest says its 2012 activities for BlackGold will consist of module assembly, facility construction and drilling of 15 saGd well pairs.

phase 1 10,000 2014 construction

phase 2 20,000 2015 application

Husky energy inc.

mcmullen Updated: may 2012

husky says that during Q1, 24 slant wells drilled in 2011 were put on cold production. at the air injec-tion pilot, three horizontal well producers were drilled to further evaluate the resource.

air injection pilot-experimental 755 2012 construction

japan canada oil Sands limited

Hangingstone Updated: jan 2012

Jacos owner Japan petroleum exploration is delaying a decision on an expansion at hangingstone until mid-2012 due to a delay in regulatory approval.

expansion 35,000 2016 application

Hangingstone pilot Updated: jan 2012

pilot 11,000 1999 operating

koch exploration canada corporation

• muskwa Updated: jun 2012

Koch’s canadian subsidiaries are seeking a strategic investor to advance development and monetize certain oilsands interests including the Muskwa asset.

pilot 10,000 2015 application

laricina energy ltd.

• Germain Updated: jun 2012

laricina says detailed engineering is 80 per cent complete. procurement of long-lead items is complete, piling commenced in January and modules began being transported to the site in March. the company has applied to add a fourth once-through steam generator and associated equipment due to anticipated reservoir behaviour.

phase 1 cdp 5,000 tBd construction

phase 2 30,000 2015 application

phase 3 60,000 tBd application

phase 4 60,000 tBd application

Saleski Updated: may 2012

laricina says an additional well pair has been drilled at the pilot, awaiting tie-in for steaming in Q2. production and injection cycles are ongoing. the company has responded to the first round of supplemental information requests from the regulator regarding the commercial project application.

phase 1 10,700 2014 application

pilot 1,800 2011 operating

current proJect capacity start-up reGulatory status

meG energy corporation

christina lake Updated: may 2012

MeG says it has achieved a significant reduction in its steam to oil ratios through the introduction of infill wells and non-condensable gas injection. for phase 2B, MeG says detailed engineering is more than 96 per cent complete, and all materials and modules have been ordered, with delivery and on-site construction expected to continue through 2012 and into 2013. the company says the project remains on schedule and budget. for phase 3, MeG says engineering work is underway to determine the optimum size and schedule of project phases.

phase 1 pilot 3,000 2008 operating

phase 2a 22,000 2009 operating

phase 2B 35,000 2013 construction

phase 3a 50,000 2016 approved

phase 3B 50,000 2018 approved

phase 3c 50,000 2020 approved

Surmont Updated: may 2012

MeG plans to file its regulatory application for surmont in the second half of 2012.

phase 1 60,000 2018 announced

phase 2 60,000 tBd announced

n-Solv corporation

• dover Updated: jun 2012

reports are that first results from a $60-million n-solv field test are expected in spring 2013.

demonstration plant 500 2012 announced

nexen inc.

• long lake Updated: jun 2012

nexen says it has reached two key milestones in its strategy to fill the long lake upgrader: first pro-duction from one new well pad (ahead of schedule) and steam injection into another. the company says ramp-up is continuing at yet another pad and construction is underway on two more.

long lake south (Kinosis) phase 1 40,000 tBd approved

long lake south (Kinosis) phase 2 40,000 tBd approved

phase 1 72,000 2008 operating

phase 2 72,000 tBd approved

phase 3 72,000 tBd application

phase 4 72,000 tBd announced

Statoil

• kai kos dehseh Updated: jun 2012

statoil says its next projects will be an expansion to leismer, and the corner project. corner will be sanctioned in late 2013 or in early 2014.

corner 40,000 2017 approved

corner expansion 40,000 tBd application

hangingstone 20,000 tBd application

leismer commercial 10,000 tBd approved

leismer demonstration 10,000 2010 operating

leismer expansion 20,000 tBd approved

leismer northwest 20,000 tBd application

leismer south 20,000 tBd application

thornbury 40,000 tBd application

thornbury expansion 20,000 tBd application

40 oilsands review | AUGUST 2012

P R O J E C T S TAT U S

Page 6: Oilsands Review Project Status August 2012

current proJect capacity start-up reGulatory status

Suncor energy inc.

chard Updated: dec 2010

phase 1 40,000 tBd announced

meadow creek Updated: dec 2010

phase 1 40,000 tBd approved

phase 2 40,000 tBd approved

Surmont energy ltd.

Wildwood Updated: Apr 2012

phase 1 12,000 2015 announced

value creation inc.

Advanced triStar Updated: may 2012

value creation says it is preparing the regulatory application for the advanced tristar project.

ats-1 15,000 2016 announced

ats-2 30,000 2019 announced

ats-3 30,000 2022 announced

cold lAke reGion — in SitUbirchwood resources inc.

• Sage Updated: jun 2012

Birchwood has released its public disclosure document and has held an open house with area residents, some of whom were concerned by the development.

pilot 5,000 2015 announced

canadian natural resources limited

• primrose & Wolf lake Updated: jun 2012

canadian natural says its near-term priorities at primrose include maximizing steam-plant utilization by adding pads, a future facility debottleneck/expansion, assessment of a potential Grand rapids for-mation expansion, and optimization of steaming techniques to improve on the 15 per cent recovery factor. two pilots will be conducted in 2012.

primrose east 32,000 2008 operating

primrose north 30,000 2006 operating

primrose south 45,000 1985 operating

wolf lake 13,000 1985 operating

devon canada corporation

• Walleye Updated: jun 2012

devon filed its regulatory application for walleye in June. the company says construction will start in 2013.

phase 1 9,000 2015 application

Husky energy inc.

caribou Updated: nov 2010

demonstration 10,000 tBd approved

tucker Updated: feb 2012

production at tucker has increased significantly, exiting 2011 at over 9,000 barrels per day versus 4,000 barrels per day the previous year. husky says it has addressed subsurface challenges by remediating older wells with new completion and stimulation techniques and initiating revised start-up procedures.

phase 1 30,000 2006 operating

imperial oil limited

cold lake Updated: may 2012

imperial says drilling has been completed at cold lake on a three-well cyclic solvent process pilot that is expected to start up in late 2013.

phase 1-10 110,000 1985 operating

current proJect capacity start-up reGulatory status

phase 11-13 30,000 2002 operating

phase 14-16 40,000 2014 construction

koch exploration canada corporation

• Gemini Updated: jun 2012

Koch’s canadian subsidiaries are seeking a strategic investor to advance development and monetize certain oilsands interests including the cold lake (Gemini) asset.

stage 1 1,200 tBd approved

stage 2 10,000 tBd approved

osum oil Sands corp.

taiga Updated: Apr 2012

the ercB has scheduled a public hearing into the taiga project for May 23.

phase 1 23,000 2016 application

phase 2 22,000 2017 application

pengrowth energy corporation

lindbergh Updated: may 2012

pengrowth achieved first steam at the lindbergh pilot in february. the company says the reservoir is responding to steam injection and production performance so far indicates good oil mobility, straightforward treating and minimal solids production, all of which are encouraging at this early stage. full saGd operations are expected in Q2.

phase 1 commercial 12,500 2014 application

phase 2 commercial 17,500 2016 announced

pilot 1,200 2012 operating

royal dutch Shell plc

• orion Updated: jun 2012

shell is looking to sell the orion property, reportedly to focus on in situ operations at peace river.

phase 1 10,000 2007 operating

phase 2 10,000 tBd approved

peAce river reGion — in SitUAndora energy corporation

• Sawn lake Updated: jun 2012

andora energy majority owner panorient energy corp. anticipates that activities related to the sawn lake asset will come into focus over the remainder of 2012, with a clear course of action to be com-municated shortly after the sale of assets in thailand, which occured in mid-June.

saGd demonstration 1,400 tBd approved

northern Alberta oil ltd.

Sawn lake Updated: mar 2012

company owner deep well oil & Gas says deGolyer & Macnaughton canada has completed its reservoir modelling for a proposed horizontal cyclic steam stimulation pilot at sawn lake, concluding the project would yield commercial viable extraction. deep well is currently preparing a pilot plan and options for capitalization.

css pilot 700 tBd approved

petrobank energy And resources ltd.

dawson Updated: may 2012

petrobank says it has concluded that the dawson reservoir would benefit from being pre-conditioned for thai operations by producing conventional cold heavy oil from the current horizontal production wells. the two-well thai pilot is now expected in 2013, with commercial development to follow, subject to operational success.

phase 2 10,000 tBd announced

thai demonstration-experimental tBd 2013 construction

AUGUST 2012 | oilsandsreview.coM 41

P R O J E C T S TAT U S

Page 7: Oilsands Review Project Status August 2012

current proJect capacity start-up reGulatory status

royal dutch Shell plc

peace river Updated: dec 2011

alberta’s environmental assessment director has deemed complete shell canada’s environmental impact assessment report for the carmon creek expansion.

cadotte lake 12,500 1986 operating

carmon creek - phase 1 40,000 2015 application

carmon creek - phase 2 40,000 2018 application

Southern pacific resource corp.

red earth Updated: may 2012

southern pacific is analyzing results from its latest css test at red earth. the company says it will finalize future development plans by the end of Q2.

commercial 10,000 tBd announced

pilot 1,000 2009 operating

pilot expansion 3,000 tBd announced

SASkAtcHeWAn reGion — in SitUoilsands quest inc.

• Axe lake Updated: jun 2012

oilsands Quest says that some of the bids received to acquire, restructure or recapitalize its business could, if subject to further negotiation, be capable of being brought before the court for approval. the company and its court-appointed monitor, ernst & young inc., have agreed that the best interests of oilsands Quest and its stakeholders will be best served if ernst & young takes over operational responsibilities, including completion of a transaction.

commercial 30,000 tBd on hold

reservoir test 600 2008 on hold

saGd pilot tBd tBd on hold

nortH AtHAbAScA reGion — UpGrAderbp p.l.c.

terre de Grace Updated: mar 2012

pilot 8,400 tBd approved

canadian natural resources limited

Horizon Updated: may 2012

canadian natural says that during the first quarter, a third ore preparation plant and associated hydrotransport unit were successfully integrated into operations. the infrastructure is expected to increase reliability going forward by allowing the company to maintain steady feedstock to the upgrader with two of the three ore preparation plants continually on stream.

phase 1 114,000 2009 operating

phase 2a 10,000 2014 approved

phase 2B 45,000 tBd approved

phase 3 80,000 tBd approved

tranche 2 5,000 2012 operating

ivanhoe energy inc.

tamarack Updated: may 2012

ivanhoe says it has received a second round of supplemental information requests regarding its pro-ject application from the ercB. it continues to expect approval in 2012.

phase 1 34,784 2014 application

Suncor energy inc.

base operations Updated: may 2012

suncor is now mining volumes from tne north steepbank extension. the company expects that its Millennium naphtha unit (Mnu) project will be fully operational by mid-year. in april, suncor announced its upgrader had successfully returned to normal operations following a brief shutdown due to a fractionated performance issue. suncor has started commissioning assets associated with its tailings reduction operations infrastructure project and anticipates to start using these assets during Q2.

Millennium coker unit 97,000 2008 operating

Millennium vacuum unit 35,000 2005 operating

u1 and u2 225,000 1967 operating

fort Hills Updated: may 2012

suncor says current work on fort hills includes progressing design basis memorandum engineering, site preparation and procurement for long-lead items. the company expects to present development plans to the board of directors for sanction in 2013.

phase 1 145,000 tBd on hold

phase 2 & 3 145,000 tBd on hold

voyageur Upgrader 3 Updated: may 2012

suncor says that current work is on validating project scope, developing the project execution plan, engineering and progressing site preparation. the company and its partner plan to submit develop-ment plans to their respective boards of directors for sanction in 2013.

phase 1 127,000 2016 approved

phase 2 63,000 tBd approved

current proJect capacity start-up reGulatory status

Syncrude canada ltd.

mildred lake/Aurora north & South Updated: may 2012

construction is underway on a number of major projects including mine train replacement and re-location, the aurora north tailings Management project, the syncrude emissions reduction project and the centrifuge tailings Management project.

Base plant stage 1 & 2 debottleneck 250,000 1978 operating

stage 3 debottleneck 75,000 tBd announced

stage 3 expansion (ue-1) 100,000 2006 operating

SoUtH AtHAbAScA reGion — UpGrAdernexen inc.

• long lake Updated: jun 2012

nexen says it has reached two key milestones in its strategy to fill the long lake upgrader: first pro-duction from one new well pad (ahead of schedule) and steam injection into another. the company says ramp-up is continuing at yet another pad and construction is underway on two more.

phase 1 58,500 2008 operating

phase 2 58,500 tBd approved

phase 3 58,500 tBd application

phase 4 58,500 tBd announced

value creation inc.

Advanced triStar Updated: may 2012

value creation says it is preparing the regulatory application for the advanced tristar project.

ats-1 12,750 2016 announced

ats-2 25,500 2019 announced

ats-3 25,500 tBd announced

indUStriAl HeArtlAnd reGion — UpGrAdernorth West Upgrading inc.

redwater Upgrader Updated: feb 2012

final sanction is anticipated in 2012.

phase 1 77,000 2013 approved

phase 2 77,000 2018 approved

phase 3 77,000 tBd approved

Shell Albian Sands

Scotford Upgrader 1 Updated: may 2012

twenty per cent project partner Marathon oil corporation says volumes were down from the athabasca oil sands project during Q1 due to reliability issues. alberta’s environmental impact assessment director has deemed complete the environmental impact assessment report for shell canada’s Quest carbon capture and storage project from the scotford upgrader.

commercial 158,000 2003 operating

expansion 91,000 2011 operating

value creation inc.

Heartland Updated: nov 2010

construction was suspended in september 2008.

phase 1 46,300 tBd on hold

phase 2 46,300 tBd approved

phase 3 46,300 tBd approved

NeW exPORT PIPeLINeSenbridge

• northern Gateway Updated: jun 2012

the joint review panel conducting the Gateway review has finalized the schedule for the remaining public hearings. the questioning phase of the of the final hearings will start in september. final arguments will take place april 2013, with report and findings to follow in december 2013.

alberta to Kitimat, B.c.525,000 plus 70,000 diluent line

2017 application

Kinder Morgan Canada

• trans mountain expansion (tmX) Updated: jun 2012

regulatory application to be filed late in 2013. Kinder Morgan confirms committed shippers as Bp canada, canadian oil sands limited, cenovus energy inc., devon canada corporation, husky energy, imperial oil limited, nexen, statoil canada and tesoro canada.

edmonton to Burnaby, B.c., washington state and offshore

expansion up to 850,000 2017 announced

TransCanada Pipelines

• keystone expansion Updated: jun 2012

the u.s. department of state has confirmed its expectation to issue a decision on the Keystone Xl pipeline, with its realigned route around the nebraska sand hills, by the first quarter of 2013.

cushing, okla., to u.s. Gulf coast 500,000 tBd application

42 oilsands review | AUGUST 2012