OHS Worker Fatalities Report

Embed Size (px)

Citation preview

  • 7/25/2019 OHS Worker Fatalities Report

    1/43

    Workers Crushed y

    Collapse

    of Tank Roof Support Structure

    Date of Incident: pril 24 2007

    Type of Incident: Double Fatality

    2 Serious Injuries

    3

    Minor

    Injuries

  • 7/25/2019 OHS Worker Fatalities Report

    2/43

    TABLE

    OF CONTENTS PAGE NUMBER

    SECTION

    1.0

    DATE

    AND TIME

    OF

    INCIDENT

    3

    SECTION

    2.0

    NAME

    ADDRESS

    OF PRINCIPAL

    3

    ST

    AKEHOLDER S)

    -

    Owner s)

    -

    Prime

    Contractor

    -

    Employer s)

    -

    Stakeholders

    SECTION

    3.0

    DESCRIPTION OF PRINCIPAL

    4

    STAKEHOLDER S)

    SECTION

    4.0

    LOCATION

    OF

    INCIDENT

    6

    SECTION 5.0

    EQUIPMENT

    AND

    MATERIAL INVOLVED

    7

    SECTIO N 6.0 NA

    RRATIVE DESCRIPTION

    OF

    INCIDENT

    8

    SECTION 7.0

    ANALYSIS 12

    SECTION

    8.0

    APPLICABLE LEGISLATION

    14

    SECTION

    9.0 FOLLOW-

    UP/ACTION

    TAKEN

    17

    SECTION

    10.0

    SIGNATURES

    18

    SECTION

    11.0

    ATTACHMENTS

    18

    2

    September

    7

    ,

    20

    07

  • 7/25/2019 OHS Worker Fatalities Report

    3/43

    File: F-536919

    Section 1.0 DATE AND TIME OF INCIDENT

    1.1 April 24, 2007, approximately 2:30 p.m.

    Section 2.0 NAME ADDRESS OF PRINCIPAL STAKEHOLDER S)

    2 1 Owner s)

    2.

    1

    I Canadian Natural Resources Limited

    2500-855 2 Street SW, Calgary, Alberta T2P 41 8

    2.2 Prime Contractor

    2.2.

    Ca

    nadian Natural

    Re

    sources Limited Horizon Oil Sands Corporation (CN

    RL

    Horizon)

    PO Bag

    4025, Fort

    McMurray

    , Al

    berta

    T9H 3H5

    2.3 Employer 1

    2.3. 1 SSEC Canada Ltd. SSEC Canada)

    1800, 250-6 A venue,

    Ca

    lgary, Alberta T2P

    3H7

    2.4 Employer 2

    2.4. Tenth Construction Company of Sinopec (TCC)

    PO Box 132, Zibo, Shandong, China 255438

    2.5 Stakeholder 1

    2.5. 1 Sinopec Shanghai Engineering Company Ltd. SSEC China)

    769 Zhangyang Road, Pudong New Area, Shanghai, China

    2.6 Stakeholder 2

    2.6.1 China Petrol

    eum

    and Chemical [Petrochemical] Corporation (Sinopec)

    PO Box 3013, Beijing 100011, China

    2.7

    Stakeholder 3

    2.7.1 The Zachry Group

    Suite 250, 700 Sixth Avenue SW, Calgary, Alberta, T2P OT8

    3

    September 27, 2007

  • 7/25/2019 OHS Worker Fatalities Report

    4/43

    File: F-536919

    2.8 Stakeholder 4

    2.8.1 Zachry Energy International Inc

    1238, 13351 Commerce Parkway, Richmond, British Columbia V6V 2X7

    2.9

    Stakeholder 5

    2.9.1 TIW Division

    of

    Canadian Erectors Ltd. (TIW)

    23 Smith Street, St. Catherine's, Ontario L2R 6Y6

    Section 3.0 DESCRIPTION

    O

    PRINCIPAL STAKEHOLDER S)

    3.1 Canadian Natural Resources Limited CNRL)

    3 1.1

    CNRL

    is a senior independent oil and natural gas exploration, development and

    production company based in Calgary, Alberta.

    3.1.2 The CNRL Horizon Oil Sands Project is located approximately 7 m north ofFort

    McMurray and 3 km north of Fort MacKay, Alberta. CNRL owns and operates

    leases covering approximately 115,000 acres and will use open pi t mining

    me

    thods to

    mine oil sands. A plant is being constructed that will separate raw bitumen from the

    oil sands and upgrade the bitumen to a synthetic crnde oil using delayed coking and

    hydro-treating technologies. Phase 1 started in 2005 and is scheduled fo r completion

    in 2008, ramping up to produce 11 0,000 barrels of synthetic crude oil per da

    y

    Phases

    2 and 3

    wi ll

    proceed until projected completion in 20 12 Phase 3 is expected to bring

    production to 232,000 barrels of synthetic crude oil per day. At the time of the

    incident approximately 6,000 workers were working on the construction of the

    project.

    3.2 SSEC Canada Ltd. SSEC Canada)

    3.2.1 SSEC Canada is an Alberta corporation. The company was incorporated in April,

    2006 to bid for work in the Alberta oil sands.

    The

    company is 90 owned

    by

    SSEC

    China, a Chinese company, and 10 owned

    by

    Zachry Energy International Inc., a

    companybased in British Columbia. SSEC Canada uses management, technical and

    journeyman workers drawn from

    SSEC China and Tenth Construction Company

    of

    Sinopec (TCC), working in Alberta as temporary foreign workers, to carry out

    projects such as the tank farm project at the

    CNRL

    Horizon Oil Sands Project.

    3.2.2 SSEC Canada was contracted by CNRL Ho

    ri

    zon to construct a total of 14 tanks, 11

    on the east tank farm and 3 on the west tank farm at the CNRL Horizon Plant Site.

    The effective date of he contract was April 11 , 2006. SSECCanada was expected to

    have workers available July 2006 to commence the tank assembly at the west tank

    farm. Wo rk on the three tanks at the west tank fan11 was scheduled for completion by

    September, 2007.

    September 27, 2007

  • 7/25/2019 OHS Worker Fatalities Report

    5/43

    Fil

    e:

    F-536919

    3.2.3 The three tanks on the west tank farm were being constructed in accordance with a

    tank erection schedule prepared by CNRL. The schedule specified a

    se

    quence of

    construction where the tank floors were laid, the walls were started and the internal

    roof support structures were erected. SSEC Canada was required to construct the

    tanks in accordance with

    th

    e tank erection sched

    ul e

    and in accordance wi

    tb

    component and mate

    ri al sc

    hedules and engineered drawings provided by

    TIW

    . The

    TIW drawings showed how the components and materials they had supplied fitted

    together. SSEC Canada was responsible for the direction of their workers, which

    included giving

    in

    structions on how component

    pa

    rts of the roof suppo

    rt

    structure

    were to be suppotied from movement or falling until the construction was complete

    and the tank assemblies were self-supporting.

    3

    .3

    Tenth Construction Co

    mpan

    y

    of

    Sinopec (TCC)

    3.3. l TCC is an industrial construction company in China, specializing in the construction

    and in stallat ion of petroleum refining projects. TCC has undertaken construction

    projects in Africa, Asia and Saudi Arabia.

    3 4 Sinopec

    Shanghai Engineering Company

    (SSEC

    China

    SSEC

    China is a Chinese company based in Shanghai, Ch ina. SSEC China has the

    capacity to undertake mid

    to large engineering projects including projects in the

    petrochemical industry. SSEC China has some contacts with engineering companies

    inte

    rn

    ationally. SSEC China own a 90% share of SSEC Canada and exercises full

    control of all activities of SSEC Canada.

    The

    Horizon tank project was sub

    contracted to

    TCC

    by

    SSEC China. All workers were recruited by

    TCC

    . Most

    construction management personnel were employed by TCC. SSEC China employed

    one

    bus

    in

    ess representa

    ti

    ve

    in Ca

    lgary to deal with the finances and one secretary at

    the CNRL sit

    e.

    3.5

    Sinopec C

    hina Petroleum

    and Chemical Petrochemical Corporation (Sinopec)

    3.5 .1 Sinopec is the largest producer and marketer of refined oil products in China and

    Asia, and is the largestproducer and distributor of petrochemicals in China. Sinopec

    is a state-owned Chinese corporation, is the second largest oil and gas explorer in

    China, and is the parent co

    mpany

    of

    both TCC and SSEC Chin

    a.

    3.6

    T

    he Zachry Group

    3.6 .1 The Zachry Group is an Alberta registered company that designs and manufactures

    equipment fo

    r the oil and gas, pulp a

    nd

    paper, sawm

    ill

    s and mining industries.

    5

    September 27, 2007

  • 7/25/2019 OHS Worker Fatalities Report

    6/43

    File: F-536919

    3.

    7.

    Zachry Energy International Inc.

    3.7.1 Zachry Energy International Inc. is a British Columbia registered company that is

    60% owned by the Zachry Group. Zachry Energy International Inc. provides

    overview and management input to SSEC Canada and is 10% shareholder

    ofSSEC

    Ca

    nada. Zachry International Inc. focused on helping

    SSEC

    Chin a to liai

    se

    with

    CNRL and to penetrate the oil and gas construction market in Alberta. They were

    responsible to assist SSEC China to

    li

    aise with

    CNRL

    and assist with requirements

    of

    training

    of

    he trade workers.They were responsible to assist SSEC China workers to

    obtain work visas, and coordinated with Alberta Apprenticeship and Indust ry

    Training (AAIT) requirements for designated trades.They assisted SSEC China to set

    up SSEC Canada Ltd. , and assisted SSEC Canada Ltd. with obtaining legal counsel

    to help the company deal with local regulations and laws in connection with their

    establishment in Alberta. In March of

    2007 Zachary Energy International Inc.

    relinquished its 10% share

    of

    SSEC Canada. SSECChina and Sinopec requested that

    Zachary Energy International Inc. be the lead contact for SSEC Canada in relation to

    the investigation ofWHSC with respect to the April 24, 2007 incident at the

    CNRL

    Horizon site.

    3.8 T W Division of Canada Erectors Ltd. TIW)

    3.8. l TIW is engaged in the fabrication, construction and distribution sectors

    of

    the stee l

    industry.

    TlW

    is a fully integrated unit for design, manufacturing and construction of

    fi eld erected steel platework structures.TIW was contracted byCNRL to provide the

    components, material schedules for arriva l on site, and the engineered drawings for

    th e 14 tanks on the east and west tank fanns at the CNRL Horizon plant site.

    3 .8.2 The

    roof

    support structures were all fabricated in house by TIW at their faci i ies,

    with the exception

    of

    the weldingofcolumns to the cap plates, which was perfo1med

    by Bartonair Fabrications of Hamilton. Bartonair is a regular supplier to TIW.

    Bartonair was required to use TIW supplied materials, consumables and welding

    procedures. TIW inspection personnel reviewed the materials before shipment. TIW

    coordinated the identification, packaging and shipment

    of

    he

    roof

    support structures

    (including columns) to the CNRL Horizon site.

    Section 4.0 LOCATION OF INCIDENT

    4.1 Tank 72-TK- l B, located on the west tank farm of the CNRL Horizon Oil Sands

    Project,

    approximately

    70

    km north

    of

    Fort McMurray and 30 km north

    of

    Fort

    MacKay, Alberta.

    6

    September 27, 2007

  • 7/25/2019 OHS Worker Fatalities Report

    7/43

    Fi

    le: F-5369 19

    Section 5.0 EQUIPMENT AND MATERIAL INVOLVED

    5.1

    he

    West Tank Farm

    5 .1 I The west tank farm is located approximatel y northwest of centre on the Horizon Plant

    Site. (Attachment

    C ,

    Site Layout

    ).

    As

    the tanks had restricted

    mea

    ns

    of

    entry and

    exit and could become hazardous to workers entering them, they were designated as

    confined space. Three high-cone steel tanks, Tank 72-TK-lA, 72-TK- IB and 72-TK-

    1

    C

    are located on

    the

    west tank farm, in a line east to

    west

    with Tank 72-TK-1A at

    the

    west, Tank 72-TK-

    lB in

    the centre and Tank 72-TK- lC at the east end of he row

    of tanks.

    The

    tanks are

    all

    the same size and of the sa

    me

    construction. At the time of

    the incident the

    roof

    support structure in tank 72-

    TK

    -

    l

    B was in a suspended state of

    completion with the centre support column, the inside ring of6 support columns and

    the outer ring of 12 support columns in place, with the girders and rafters fitted,

    waiting for the she ll assembly to be completed. Once the she ll assembl y was

    completed,

    th

    e rafters from the outer ring 's girders would be connected to the she

    ll

    wal1. The roof support structure in

    ta

    nk 72-TK-1 B had been completed the day before

    the co llapse. At the time of

    th

    e incident a team

    of

    bo ilermakers and scaffolders was

    working in Tank 72 -TK-1 C on the assembly of th e roof support structure.

    (Attachment A'', Photographs 1 1, #15)

    5.2

    The East

    ank

    Farm

    5.2.1 The east tank farm is located at the east

    of

    the Horiz

    on

    Plant Site (Attachment

    C'

    ',

    Site Layout).

    When

    completed, the east tank farm will contain 10 tanks of various

    siz

    es

    , and

    of

    generally similar construction to the tanks

    on the

    west tank fann. At the

    time

    of the

    incident,

    the

    roof support structures in two tanks

    on the

    east tank farm,

    Tank 73-TK-11

    and

    73-TK-12 were also in a suspended state

    of

    assembly waiting for

    the shell walls to be competed. After which they would connect the rafters from the

    outer rin

    gs'

    girders to the top of th e she

    ll

    wa

    ll

    s.

    (A

    ttachm ent A , Phot

    ogra

    ph #17)

    5.3

    Tank 72 TK tB

    5.3. 1

    Ta

    nk 72-

    TK-l

    B (described as a Dilbit Dewatering

    Ta

    nk), located on the west tank

    farm, was to be a circular steel high-cone roof tank, 56.5 mi n diameter and 19.8 m

    hig

    h.

    At the time

    of

    the incident the tank wa

    ll

    she

    ll

    was only completed to a height of

    5.6 m.The tank structure consists of wall,

    fl

    oor and roof constructed from steel plate.

    The

    roof

    is constructed onto a

    roof

    supp

    or

    t

    st

    ructure cons isting

    of

    vertical circular

    column

    s,

    supporting girders and

    ra

    dial rafters. (Attachment D , Sketch of Roof

    Support Structure). The components of th e roof support structure are assembled

    together

    with

    19 mm

    X

    inch) nuts and bolts. At the time of the incident a team of

    welders was working in the tank constructing the tank wall. Two technicians were

    also in the tank carrying out weld testing, and one scaffolder

    wa

    s in Tank 72-TK-l

    B.

    There was an Electrical Consultant and awelding foreman who we re checking out a

    we lding machine on top

    of

    the wa ll .

    7

    September 27, 2007

  • 7/25/2019 OHS Worker Fatalities Report

    8/43

    File: F-536919

    5.4

    ssembly Procedure for

    Tanks

    5.4.1 SSEC Canada developed a procedure

    fo

    r assembling and supporting the tank roof

    support structures for the tanks on the west tank farm. Erection of the shell was

    independent

    of

    the

    roof

    support structure - they were being assembled concurrently.

    The procedure consisted ofraising the centre support column first, using a crane and

    securing it in the ve1

    ica

    l position by workers operating elevating work platfo

    1m

    s to

    in

    stall 4 steel cables, secured to the top of the column and anchored to lugs welded

    onto the tank floor

    The

    cables were tightened using

    co

    me-alongs . ( Come-along

    is a generic tenn to de

    sc

    ribe mechanical tensioning devices). The inner ring of 6

    support columns was erected in a similar manner, but with 3 cables on each column.

    The girders connecting the inner ring of columns were then lifted and bolted into

    place, using 19 mm ( :y ; inch) bolts, and the ra

    di

    al rafters were installed between the

    centre column and the inner ring. After the inner ring was completed, one cable,

    extending towards the ta

    nk

    centre, was removed from each

    of

    the 6 inner ring

    columns The outer ring of 12 columns was erected, using 3 cables to support each

    column. The girders connecting the outer ring ofcolumns were lifted and bolted into

    place, and all of the radial rafters were installed. After

    th

    e outer ring of the

    roof

    support structure was assembled, 6 steel cables were installed, extending from girders

    to alternate columns in the outer ring to anchor lugs welded into the floor of he tank,

    close to the tank wall. When

    th

    ese 6 support cables were in place and tightened using

    come-alongs'', all of the cables used to support the individual columns were

    removed. The six cables remaining were intended to support and stabilize the

    roof

    sup port structure unt il the she ll was completed to ful l height The come-alongs

    were removed after the cables had been tightened.

    Section 6.0 N RR TIVE DESCRIPTION OF INC IDENT

    6. 1 SSEC Canada recruited 132 Mandarin-speaking Chinese workers from TCC to work

    as temporary foreign workers on the CNRL tank construction project.

    The

    workers

    had at least 5 years expe

    ri

    ence as trades-people and had recei ved additional training

    from a Canadian training agency before arriving in Canada.

    The

    workers started to

    arrive

    in

    Canada

    in

    September of 2006.

    6.2 On April 24, 2007, at the west tank farm, the

    roof

    support structures in tanks 72-TK

    lA (Attachment

    A ,

    Photograph #11) and

    72-TK-lB

    were in the suspended state of

    completion waiting for the shell to

    be

    assembled. Each

    roof

    sup

    port structure was

    supported by six cables

    The

    roof

    support structure in tank 72-T

    K-lC

    was being

    assembled The centre column and the inner ring had been completed and the steel

    cables were still attached to the columns. No work was taking place

    in Tank 72-

    TK

    l A on April 24, 2007. A team of boilermakers was working in Tank 72-TK-I C,

    assembling the roof suppo1t structure. (Attachment A , Photograph #15)

    8

    September 27, 2007

  • 7/25/2019 OHS Worker Fatalities Report

    9/43

    6.3

    6.4

    6.5

    Fil

    e:

    F-536919

    On April 24, 2007, a team of welders was working in tank 72-TK-1 B, welding

    sections into the tank wall. The tank wall sec

    ti

    ons were being welded together by

    welders and helpers wo rking inside welding machines that tracked around the inside

    of the tank wa ll. (Attachment A ,Photographs #20, #21) One Electrical Consultant

    and a welder foreman were inside the tank checking an elect

    ri

    cal failure on one

    of

    he

    we

    lding machines. One scaffolder was also on th e

    fl

    oor area inside the tank. Two

    weld test technicians were also in Tank 72-TK-1 B, testing and marking the welds on

    the tank wall.

    At approximately2:30 p.m. on April 24, 2007, workers inand around tank 72-TK- lB

    heard several sounds, described as loud bangs or pops. The roofsupport structure in

    tank 72-TK-1 B started to fal l in an easterly direction during windy conditions. As the

    structure collapsed, some of the support cables failed, many of th e bolts that were

    holding the components together failed and then the components began to come

    apart. (Attachment A, Photograph s #8, #9, #10, # 22) The stru cture fell onto the

    east side of the tank wall. Some of he components of the roofsupport structure can1e

    to rest on th e floor of the tank , some components came to rest leaning against the

    tank wall, and some components came to rest on the outside of the tank on the east

    side. Many of the components we re bent or damaged by the impact.

    Af

    ter the roof

    support structure co llapsed so

    me

    of the workers who

    were

    in tank 72-TK-1 B,

    managed to escape from the tank through manways or other holes in the tank wal

    (Attachment A , Photographs #1, #2, #3, #4)

    SSEC Canada workers from tank 72-T

    K-.1

    C and other workers on the west tank farm,

    as

    well

    as workers from other contractors who were working near the west tank fa1m ,

    went to tank 72-TK-lB to provide assistance. CNRL Horizon emergency services

    were called and attended. Rescuers had to lift a large section

    of

    steel inside the tank

    to remove the fatally injured Scaffolder. The Electrical Consultant was standing on

    the top of a welding machine, which was located on top of he wall, and was fatally

    injured

    when he

    was struck

    by

    falling steel. His body was thrown onto scaffolding

    outside the tank. The Electrical Consultant was pronounced dead at the scene. The

    Scaffolder, who was on the tank floor, was crushed by the falling steel and died in an

    eme

    rgency conveyance vehicle on the way to Fort McMurray. Two other workers

    received serious injuries and three more workers received minor inj uries. The two

    se

    riously injured workers and two of the workers who had received minor injuries

    were transported to hospital in Fort McMurray. The two seriously injured workers

    were subsequently transferred to hospital in Edmonto

    n.

    6.6

    INV STIGT ION OBSERV TIONS ND FORMT ION

    6.6. 1 Workplace Health and Safety Compliance (WHSC) was notified of the incident by

    CNRL Horizon at 3:08 p.m. on April 24, 2007. Workplace Health and Safety officers

    from Fo1t McMurray were dispatched to the scene and while en route made contact

    with RCMP Fort McMurray Detachment. WHSC officers arrived at the site at

    5:

    19

    p.m

    . The scene had been secured

    by

    CNRL and RCMP.

    9

    September 27, 2007

  • 7/25/2019 OHS Worker Fatalities Report

    10/43

    File: F-536919

    6.6.2

    WHSC

    issued a verbal Stop Work Order to CNRL at 8:36 p.m.

    on

    April 24, 2007.

    The Stop Work Order was for construction of the three tanks on the west tank farm

    and any similar tanks on the Horizon site.

    6.6.3 On April 24, 2007 a WHSC Lead

    In

    ves

    ti

    gator was di spatched from Edmonton to

    direct the investigation The Lead Investi

    ga

    tor atTived at the CNRL Horizon Oil

    Sands Project at 9:00 am . on April 25, 2007.

    CN

    RL Ho

    ri

    zon set up an internal

    investigation team a

    nd

    met with

    th

    e Lead Investigator a

    nd

    other Workplace Health

    and Safety of

    fi

    cers on April 25, 2007. The Lead Investigator confirmed the ve

    rb

    al

    Stop Work Order a

    nd

    reminded CNRL Ho

    ri

    zon that no workers were

    to

    enter the

    area and to have the area secured.

    6.6.4 On April 25, 2007 a seco

    nd

    WHSC Lead

    In

    vestigator, the WH SC Manager

    of

    Compliance, and an employee from another Govenunent of Albe1ta depa1tment, who

    speaks Mandarin, were dispatched from Edmonton to assist with the investigation.

    The second Lead Investigator, the Manager and the other employee arrived at the

    CNRL Horizon plant site at 6:00 p.m.

    6.6.5 t was found that there had been

    13

    workers inside tank 72-TK-lB at the time the

    incident occurred.

    Ten

    workers were Chinese temporary foreign workers employed

    by

    SSEC Canada, one Chinese worker (the Electrical Consultant) was directly

    employed

    by

    TCC and two workers were Canadian workers employed by Iris

    NDT

    ,

    carrying out weld testing. All of the fatally injured and other injured workers were

    Chinese temporary foreign work ers. SSEC Canada workers and others who had

    attended the scene were interviewed over a pe

    ri

    od of several days, in o

    rd

    er to

    determine the circumstances of the inc

    id

    ent and the loca

    ti

    ons

    of

    a

    ll of

    t

    he

    workers

    who were inside the tank at the time of the incident. t was found

    th

    at

    th

    e workers

    had carri ed out the assembly of

    th

    e

    ro

    of suppo

    rt

    structures in accordance with SSEC

    Canada

    's

    chief engineer

    's in

    structions a

    nd

    the assembly drawings prov

    id

    ed by T IW .

    6.6.6 One

    of

    the

    fa

    tally injured workers, an Electrical Consultant, had been on the top

    of

    a

    welding m

    ac

    hine working on

    th

    e east side of the tank wall. The Electrical Consultant

    had been struck in the head and back by a section of the falling steel and thrown onto

    scaffolding outside the east wall

    of

    the tank.

    The

    other fatally injured worker, a

    Scaffolder, had been standing on the tank floor, east of the tank centre, and had been

    caught and crushed under a falling girder. Rescuers had manually lifted the girder to

    rescue him. The Scaffolder died during transport to hospital. (Attachment

    A

    ,

    Photographs #4, #5, #7)

    1

    September 27, 2007

  • 7/25/2019 OHS Worker Fatalities Report

    11/43

    6.6.7

    6.6.8

    6.6 .9

    6.6.10

    6.6.11

    File: F-536919

    One

    of

    the seriously injured workers, Welder l , had been inside the same welding

    machine that the Electrical Consultant was working on. The welding machine } ad

    been struck by fall ing steel and partially dislodged from the tank

    wa

    ll. Welder

    1

    was

    trapped inside the welding machine and was rescued by CNRL staff a

    nd

    other

    contract workers.

    The

    other seriously injured worker, Welder 2, was inside another

    welding machine on the east wall that had been struck by falling steel and completely

    dislodged from the wall, falling to the tank floor. Welder 2 was rescued by his

    Chinese co-workers. (Attachment A , Photographs #5, #6)

    The verbal Stop Work Order was confirmed in writing on April 27, 2007. The Stop

    Work Order prevented access to the east and west tank farms.

    The

    Stop Work Order

    was re-issued on May 1, 2007 to define a specific part of the east tank farm around

    tanks 73-TK-1 and 73-TK 12 where workers could be at risk from the collapse of

    the

    roof

    support structures. The remainder of the east tank farm was released to

    CNRL. The Stop Work Order for the west tank farm remained in effect. CNRL

    cooperated with the Stop Work Orders and provided barriers and security

    staff

    to

    ensure that the order was made effec

    ti

    ve.

    On May 1

    2,

    2007 the roof suppo1t structure in tank 72-TK-lA on the west ta

    nk

    farm

    collapsed during windy conditions. The Stop Work Order was st ill in effect and no

    workers were near the collapse. Before the collapse it had been observed that the roof

    support structure was twisting during windy conditions. (Attachment

    A

    ,

    Photographs #18, #19)

    CNRL developed an engineered procedure for securing and dismantling the roof

    support structures in tanks 73-TK-1 and 73-TK-12 on the east tank farm. The Stop

    Work Order for the east tank farm was lifted on May 16, 2007 and the site was

    released to CNRL Horizon to enable the remediation work to be done. The work on

    dismantling and removal of the roof support structures was completed on June

    11

    ,

    2007 by SRS Industrial Services Ltd.

    CNRL developed an engineered procedure for the removal of fallen materials in

    tanks 72-TK-lA and 72-TK lB and the dismantling of the roof support structure

    from tank 72-TK-l C. The Stop Work Order for the west tank farm was lifted on June

    6, 2007. Work on tank 72-TK-I A commenced on June

    8,

    2007

    an

    d was completed on

    June 13, 2007. Work then sta1ted on tank 72-TK-I B a

    nd

    was completed on June 20,

    2007.

    The

    removal

    of

    he roofsupport structure in tank 72-TK-l C was completed on

    June 22, 2007 by Penny Industrial Fabricators Ltd. The WHSC Lead

    In

    vestigator

    monitored the removal

    of

    the fallen materials from tanks 72-TK-1A and 72-

    TK-1

    B

    and during the removal retrieved materials from both tanks for analysis by an

    independent

    co

    nsulting engineering firm.

    September 27, 2007

  • 7/25/2019 OHS Worker Fatalities Report

    12/43

    File: F-536919

    Section 7.0 ANALYSIS

    7 1 Direct ause

    7 1.1 Two workers working on the construction ofa large steel tank 72-TK-1 B were fatally

    injured two other workers were seriously injured and three workers received min

    or

    injuries when the

    roof

    support structure inside the tank collapsed suddenly and

    without warning onto the workers.

    7 2 ontributing

    Factors

    7 2. 1 SSEC Canada assembl

    ed

    the

    roof

    support structure as a stand alone structure which

    was not intended to be assembled as such by the T l drawings. Neither CNRL n

    or

    SSEC Canada consult

    ed

    with

    TIW

    with respect to what assembly sequence should

    be

    fo ll

    owed for the con

    st

    ruction of the

    roof

    support structure. As the erection

    of

    the

    shell was independent of the roof support structure and they were being assembled

    concun-ently the top of the shell and the outer ring were not supporting each other.

    7.2.2 TIW did not specify

    an

    erection sequence to follow to erect the tank they designed.

    TIW did not specify the assembly sequence because that was not part of he contract

    with CNRL.

    7 2.3 CNRL prepared a tank erection schedule specifying the sequence

    of

    construction

    such as when the tank floors were to be laid the

    wa lls to be started and the internal

    roof

    support structures were to be erected. SSEC Canada followed the tank erection

    schedule as set out

    by

    CNRL.

    7.

    2.4 SSEC Canada did not provide written engineered erection procedures for the

    assembly

    of th

    e roof suppo

    rt

    structure. C

    NRL

    did not require SSEC Canada to

    provi

    de

    written engineered assembly procedures.

    7 2.5 The SSEC Canada chief engineer who developed the erection procedure for the roof

    supp

    o1i

    structures and specified the number si

    ze

    and locati

    on

    of the guy wires was

    not a qualified professional engineer.

    7.2.6 The roof support structure was a completely bolted structure using ASTM A- 307

    Grade bolts without the use of wedges

    or

    washers. The bolted roof support

    structure which was required to be flexible did not have the necessary restraints to

    resist the lateral forces generated by the wind.

    12

    September 27. 2007

  • 7/25/2019 OHS Worker Fatalities Report

    13/43

    7.2 .7

    7.2.8

    7.2.9

    7.2.10

    7.2

    11

    7.2.11.1

    Fi

    le: F-536919

    The number and size of guy wires that were supporting the roofsupport structure in

    tanks 72-TK- IA

    and 72-TK-1 B, was not designed for the static and dynamic loads

    imposed by the 33 to 45 km/h wind that occurred

    on

    the day

    of

    the incident, let alone

    for the maximum expected wind speed of 83 km/h, as determined by the Alber

    ta

    Building Code or 1

    90

    km/h recommended by the American Petroleum Institute.

    (Attachment

    A

    , Photographs #

    12

    , #

    13

    , #14, #16)

    There were six guy wires wrapped around girders located near the outer ring columns

    to stabilize the roofsupport structure. Three

    of he guy

    wires were aligned in a radial

    direction through

    the

    centre column axis; however,

    the other

    three

    guy

    wires were

    significantly offset from radial alignment and

    were

    angled in the same direction by

    14 to

    24

    Because

    of the

    offset alignment, this action would result in forces

    attempting to twist the roof support structure

    in

    a clockwise (easterly) direction,

    which is the direction of

    he

    eventual collapse.

    Because

    of

    the flexible bolted structure, any

    movement

    caused by the wind, would

    pro

    vide

    means to loosen the nuts on the bolts as well as intensify the twisting force

    on the guy wires .

    Examination

    of

    the roofsupport structures in tanks 72-TK-1C, 73-TK-1 and 73-TK

    2 showed that many

    of

    the bolts used to asse

    mb

    le the structures were loose; so

    me

    bolts had become bent during tightening, or necked because the thread length was to

    short. o washers

    or

    bevelled washers were used in the a

    ss

    emb ly

    of

    the roofsupport

    structure.

    On April 25 , 2007 Workplace Health and Safety

    Co

    mpliance contracted Anderson

    Associates Consulting Engineers Inc. to examine

    the

    circumstances leading to the

    collapse

    of

    he

    roof

    support structure in tank 72-TK-

    B.

    The

    Professional Engineer's

    report summarized the following causes:

    The

    collapse was primarily

    the

    result

    of

    inadequate

    guy

    wires used as wind bracing

    on the

    partially assembled flexible roof structure. As wind speeds increased, the

    flexible roof structure began to load the guy wires. Due to the structure 's flexibility

    and

    the

    unbalanced load conditions (the unbalanced geometry

    of he

    channel rafters

    and the poor alignment

    of guy

    wires with

    the

    structure), the roof oscillated

    in

    the

    wind. This

    mo

    ve

    ment of

    the 127 metric ton roof structu

    re

    imparted cyclic loading

    onto the guy wires. The upwind guy w

    ir

    e failed first as the wire rope clips

    became

    o

    ve

    rloaded and slipped toward the floor attachment lug. Once the structure

    was

    able

    to

    move

    out

    of

    position, it collapsed in a downwind direction-essentially blown ove

    r

    13

    September 27, 2007

  • 7/25/2019 OHS Worker Fatalities Report

    14/43

    File: F-53691 9

    7 .2.

    11

    .2 The design

    of

    he guy wire wind bracing was based

    on

    API 650 calculation methods.

    These methods are inadequate for structural steel stability, although they are suitable

    for their intended use tank stability). As a result, the designer, who was not a

    professional engineer, determined that there was minimal need for wind bracing.

    Only six 12.5 mm (half nch) guy wires were used to brace the structure against wind

    loads. These were neither aligned to prevent rotation

    of

    he

    structure

    nor

    sized with a

    normal safety factor. When the wind speed increased, the structure began to oscillate

    and the guy wires were overloaded by the inertia of the structural steel s movement.

    7.2.11.3 Bracing to make the structure more rigid was not installed by the erector. This or

    other temporary cross-bracing may have helped prevent

    or

    reduce the oscill ation that

    led to the

    in

    ertial loa

    d

    More wind bracing, in tenn s

    of

    guy wires or structural steel

    c

    ro

    ss-bracing, would have been required to prevent the incident.

    7.

    2 11

    .4 The inc

    id

    ent was n

    ot

    caused by mate

    ri

    al failure of the wire ropes,

    fi

    ttings or erect ion

    equipment. Testing of the wire rope and wire rope clips confin

    ned

    their design

    capacity. Damage to the structural steel was all a result

    of h

    e incident The A-307

    bolts used to connect the structural steel were proper strength when tested. They had

    failed as the structure collapsed. t is unlikely that stronger bolts al one would have

    prov id

    ed the rigidity required to

    pr

    event the incident.

    Section 8.0 APPLICABLE LEGISLATION

    8 1 Occupational Health and Safety Act, Section 2 1) a) i)

    Obligations o employers

    8.1.1 SSEC Canada did not take reasonably practicable measures to protect the health and

    safety of all the workers who were working inside the tank when the incident

    occurred The tank roof support structure that co llapsed onto the workers was a

    skeleton structur

    e

    The erection procedures

    fo

    r erecting the

    roof

    support structures

    had not been prepared and certifi ed by a professional engineer

    8 1 .2 Tenth Construction Company

    of

    Sinopec TCC) did not take reasonabl y prac

    ti

    cable

    measures to p

    ro

    tect the health and safety

    of th

    e Electrical Consultant. The tank roof

    support st

    ru

    cture that collapsed onto the worker was a skeleton structure. The

    erecti on procedures for erecting the roofsupport structures had not been prepared and

    certified by a Professional Enginee

    r

    Th

    e El

    ec

    trical Consultant did not have a work

    permit as a temporary

    fo

    reign wo

    rk

    er a

    nd

    thus should not have been working at this

    work site.

    14

    September 27, 2007

  • 7/25/2019 OHS Worker Fatalities Report

    15/43

    8.2 Occupational Health

    and

    Safety Act, Section 3 3)

    Prime

    Contractor

    File: F 536919

    8.2. 1 CNRL did not do what was reasonable and practicable to ens

    ur

    e

    the Act

    a

    nd the

    regulations

    we

    re complied with by failing to ensure that one of their contractors had

    er

    ect

    i

    on

    drawings and proced

    ur

    es for a skeleton

    st

    ructure certified by a professi

    ona

    l

    engrneer.

    8.3 Occupational Health and Safety Regulation, Section 7 1)

    Availability of specifications

    8.3. 1 The Occupat ional Health and Safety Code requires skele ton structures to be erected

    in accordance with engineered erection procedures. SSEC Canada did not provide

    engineered erection procedures.

    Th

    e procedures fo r the erection of the

    roof

    suppo1

    structure were not certified by a professional engineer and the specifications were not

    readily available to the workers responsible for

    the

    work.

    The

    workers

    were given

    only verbal instructions on the erection procedure.

    8.4 Occupational Health

    and

    Safety Regulation, Section 13 1) a) b)

    General protection of workers

    8.4. 1 SSEC Canada did not ensure that

    the

    engineer who developed

    the

    erection drawings

    and procedures of he roof support structure was a professional engineer competent to

    do the work, or supervised by a professional enginee

    r

    85 Occupational Health and Safety Code, Section 7 1)

    Hazard assessment

    8 5 1

    SSEC

    Ca

    nada he ld daily too lbox meetin

    gs

    be fore work started. Field level risk

    assessments were carried out during

    the

    too lbox meetings.

    SSEC Ca

    nada had

    prepared a HSE Manual containi

    ng

    generic safety procedures.

    8.6 Occupational Health

    and

    Safety Code, Section 14 1)

    Certification by a professional engineer

    8.6.1

    The

    Code requires that skeleton structures are erected in accordance with erection

    procedures certified by a profession

    al

    engineer. SSEC Canada did not ensure that

    the

    erection procedure and drawings had been certified, signed and stamped

    by

    a

    profes

    sional engineer.

    5

    September 27, 2007

  • 7/25/2019 OHS Worker Fatalities Report

    16/43

    File: F-536919

    8.7

    Occupational health and Safety Code, Section 46 3)

    Confined space training

    8.7

    1 SSEC Canada

    did

    not

    ensure that

    the

    worker

    who was

    assigned duties relating

    to

    confined space en

    tr

    y

    was

    trained by a competent person. The worker who had

    been

    de

    si

    gna

    ted the

    Co

    nfined

    Space Mo

    nitor fo r the day

    of

    the

    incident

    was

    not

    aware

    of

    the

    purpose

    of the

    confined space designation his

    dutie

    s in terms

    of

    mai

    nta

    i

    ning

    communi cation w ith the work

    ers

    in the confined space or his

    dut

    ies

    if

    an emergency

    occurred. The Confined S

    pace

    Monitor had not been effectively trained in his

    duties

    and

    was

    n

    ot compe

    t

    ent

    to

    per

    fo

    nn

    the duties required. The Confined Space

    Mon

    i

    tor

    was not

    able to

    com

    municate w ith the workers insi

    de the

    tank and was not

    able to

    rai

    se

    an alarm following the incident.

    8.8

    8.8. 1

    8.9

    8.9.1

    8. 10

    8.10.1

    8.

    11

    8.1

    1 1

    Occupational Health and Safety Code, Section 55 1)

    Confined space emergency response

    SSEC Canada had an

    eme

    rgency respon se procedure.

    Howeve

    r on the day

    of the

    incide

    nt th

    e worker who had

    be

    en des ignated as the

    Co

    nfined Space Monitor was not

    awa

    re

    of

    the emergency respon

    se

    requirements and

    was

    not

    capa

    bl e

    of

    raising an

    alarm or implementing an effective rescue SSEC

    Canada

    did

    not

    ensure

    that the

    e

    mergency

    res

    ponse

    plan included procedures

    to

    evacuate the confined

    space

    immediately.

    Occupational Health and Safety Code, Section 56 1)

    Confined space tending worker

    The wo

    rk

    er

    who had been

    de

    signated as

    th

    e

    Co

    nfined Space Monitor

    was

    not

    comp

    ete

    nt. SSEC Canada did

    not

    designate a

    com

    petent worker to

    be

    in

    co

    mmuni

    cation with the

    worke

    rs in the co nfined space.

    Occupational Health and Safety Code, Section 56 2)

    Confined space tending worker

    On

    the

    day

    of the

    incident the worker who

    was

    the

    Co

    nfined

    Space

    Monitor did not

    h

    ave

    a telephone or

    rad

    io to s

    umm

    on assistance.

    SSEC Canada

    did not ensure that

    the designated

    worke

    r had a suitable system for s

    ummonin

    g assis

    tanc

    e.

    Occupational Health and Safety Code, Section 190 1)

    Skeleton structures

    SSEC

    Ca n

    ada

    did not ensure that er

    ec

    ti

    on

    drawing and procedures for the erecti

    on of

    the roof

    support structure in tank 72-

    TK

    IB were prepared and certified

    by

    a

    professional

    eng

    ineer.

    16

    Septembe

    r 27 2007

  • 7/25/2019 OHS Worker Fatalities Report

    17/43

    8. 12

    Occupational Health and Safety Code, Section l90 2)

    Skeleton structures

    File: F-536919

    8

    1

    2. 1

    The

    erection procedure

    pr

    epared by SSEC Canada for the erection

    of

    he roof

    suppo1

    i

    stmcture in tank 72-TK-1

    B

    did n

    ot

    ensure that the structure was stable during

    assembly.

    8.13 Occupational Health and Safety Code, Section 300 1)

    Cable clips

    8.13. 1 SSEC Can

    ada

    did not ensure that u-bolt type clips used for fasteni ng wire rope were

    installed so that the u-bolt section of the clip bears on the dead side of the rope and

    the saddle

    of

    the clip bears on the live s ide

    of

    the rope.

    8

    1

    4 Occupational Health and Safety Code, Section 306 1)

    Wire rope

    8.14.1 SSEC Canada did not remove from service wire rope used to support the

    roof

    support

    structure

    in

    tank 72-TK- lB that had been distorted because

    of

    kinking where it had

    been attached around girders.

    Section 9.0 FOLLOW -UP ACTION TAKEN

    9. 1 Alberta Employme

    n

    Immigration Industry

    9.1. I

    WHSC

    issued Stop Work Orders to CNRL for the construction

    of

    the east and west

    tank farms. WHSC issued orders for securing and dismantling the roof support

    stru

    ct

    ures

    in

    the east and west tank farm. Orders were issued fo r remedial acti

    on

    s to

    r

    emove

    fa

    ll

    en rnate1ial in tanks 1A and 1B Orders w

    er

    e also issued for

    doc

    umentation hazard assessments and for an investigation repot

    i.

    9. 1 2

    WHSC

    issued orders to SSEC Canada to provide documentation such as worker

    information worker training records hazard assessment and engineeringprocedures.

    Orders were also i

    ss

    ued to SSEC Canada to cooperate with CNRL s incident

    investigation.

    9. 1

    3

    WH

    SC i

    ss

    ued orders to TIW to provide the tank drawing specifications assembly

    instructions component testing and contact information with SSEC Canada.

    9. 1.4

    WHSC

    i

    ss

    ued orders to ewfab Industries Ltd. to provide

    wr

    itten observations from

    the disassembly of the roof support structure in tank 72-TK- 1C.

    17

    September 27. 2007

  • 7/25/2019 OHS Worker Fatalities Report

    18/43

    File: F 536919

    9.1.5 WHSC issued orders to SRS Industrial Services for written observations from the

    securing and the di

    smantling of the

    roof

    support structures in tanks 73-TK 1 1 and

    73-TK

    1

    2.

    9.2 Industry

    9.2.1 At this timeCN

    RL

    has complied with all of he written orders with the exception of

    the order p

    er

    taining to the completion of an incident investigation report.

    9.2.2 SSEC Canada complied with all of the orders written.

    9.2.3 TIW complied with all of the orders written.

    9.2.4 Newfab Industries Ltd. complied with all of the orders written.

    9.2.5 SRS Industrial Services complied with all of the orders written.

    9.3 Additional Measures

    9.3

    .1

    o additional measures

    we

    re required.

    Section 10 0 SI

    GN TURES

    Section 11 0 TT CHMENTS

    Attachment A

    Attachment

    B

    Attachment C

    Attachment D

    . > ' ~ A 6J c:>o7

    e

    S e : P 1

    e ~ e i s i k ~

    Date

    ~ Z 2 P o 7

    ate ../

    Photographs

    Location Map

    Site Layout

    Sketch ofRoof Support Structure

    18

    September 27 2007

  • 7/25/2019 OHS Worker Fatalities Report

    19/43

    Photograph 1

    File: F-536919

    Attachment A

    Page 1of22

    Shows the debris field on the east side of tank 72-TK lB

    after the collapse of the tank roof support structure.

  • 7/25/2019 OHS Worker Fatalities Report

    20/43

    Photograph 2

    File: F-536919

    Attachment A

    Page 2

    of22

    Shows part

    of

    the debris field

    on

    the outside

    of

    tank 72-TK

    lB

    after the collapse. Arrow A indicates the top

    of

    the

    welding machine where the Electrical Consultant was

    standing when he was struck by the collapsing steel. Arrow

    B

    indicates where the Electrical Consultant's body was

    found.

  • 7/25/2019 OHS Worker Fatalities Report

    21/43

    Photograph #3

    File: F-536919

    Attachment A

    Page 3 of22

    Shows the interior

    of

    tank 72-TK- l B after the collapse of

    the roof support structure. This image was computer

    generated from several photographs. Arrows A indicate

    one of the vertical columns in the outer ring, and the base

    where it was standing before

    the

    collapse. Arrows B

    indicate one

    of

    the vertical columns in the inner ring and its

    base.

  • 7/25/2019 OHS Worker Fatalities Report

    22/43

    File: F-536919

    Attachment A

    Page 4 of22

    Photograph #4 Shows the interior of tank 7 -TK-lB after the collapse of

    the roof support structure. Arrow A indicates the centre

    support column. Arrow B indicates the hard hat that was

    worn

    y

    the Scaffolder.

  • 7/25/2019 OHS Worker Fatalities Report

    23/43

    Photograph #5

    File: F-536919

    Attachment A

    Page 5

    of22

    Shows the interior of tank -

    TK-lB

    after the collapse of

    the

    roof

    support structure. Arrow

    A

    indicates the welding

    machine partially dislodged from the

    tank wall that the

    Electrical Consultant was standing on, and Welder 1 was

    working in, at the time

    of

    the incident. Arrow B indicates

    the welding machine that fell from the tank wall, that

    Welder 2 was working in.

  • 7/25/2019 OHS Worker Fatalities Report

    24/43

    Photograph #6

    File: F-536919

    Attachment A

    Page 6 of22

    Shows a closeup view of the welding machine that Welder 2

    was working in.

  • 7/25/2019 OHS Worker Fatalities Report

    25/43

    Photograph #7

    File: F

    36919

    Attachment A

    Page 7 of

    Shows a closeup view of the welding machine that the

    Electrical Consultant was standing on, and that Welder 1

    was working in.

  • 7/25/2019 OHS Worker Fatalities Report

    26/43

    Photograph 8

    File: F-536919

    Attachment

    A

    Page 8 of22

    Shows part of the collapsed structure from tank 72-TK-lB,

    showing one of the % inch bolts that were used to bolt the

    components of the roof support structure together.

  • 7/25/2019 OHS Worker Fatalities Report

    27/43

    Fil

    e

    F-536919

    Attachment

    A

    Page 9

    of22

    Photograph 9 Shows a sheared

    4

    inch bolt on the ground to the east

    of

    tank 72-TK

    -lB.

  • 7/25/2019 OHS Worker Fatalities Report

    28/43

    File: F-536919

    At

    tachment A

    Page 10 of

    Photograph #10 Shows the bolt also shown in photograph 9. The markings

    on the bolt head indicating the specification of the bol

    t

    A-

    307-B, can be seen.

  • 7/25/2019 OHS Worker Fatalities Report

    29/43

    File: F-536919

    Attachment A

    Page of22

    Photograph #11 Shows the completed roof support structure in tank 72-TK

    lA before it also collapsed. The roof structure that

    collapsed in tank 72-TK-lB was identical to this. Arrow

    indicates one of the support cables.

  • 7/25/2019 OHS Worker Fatalities Report

    30/43

    File: F-536919

    Attachment

    A

    Page 12

    of22

    Photograph #12 Shows a closeup

    of

    one

    of

    the support cable top connections

    on tank 72-TK

    1A

    Arrow

    A

    indicates where the support

    cable has been secured back onto itselfusing a screw pin

    shackle. Arrow

    B

    shows the top connection of one of the

    cables that had been used to support the vertical column

    during the erection

    of

    the roof support structure. This cable

    had not been removed after the assembly

    of

    the structure

    was completed.

  • 7/25/2019 OHS Worker Fatalities Report

    31/43

    File: F-536919

    Attachment

    A

    Page

    3

    of22

    Photograph

    3

    Shows the top connection of another support cable on tank

    72-TK- lA. Arrow indicates where the cable is kinked as it

    passes over the top plate of the column.

  • 7/25/2019 OHS Worker Fatalities Report

    32/43

    File: F-536919

    Attachment

    A

    Page

    14of22

    Photograph 4 Shows a beam from tank 72-TK-lB after the collapse

    of

    the

    roopf support structure. The top end of one of the support

    cables is still attached to the beam. Arrow indicates where

    the cable has been kinked and distorted as it passed through

    the shackle.

  • 7/25/2019 OHS Worker Fatalities Report

    33/43

    File: F

    5

    36919

    Attachment

    A

    Page 15 of22

    Photograph

    15

    Shows the partially completed roof structure in tank 72-TK

    l

    C.

    The cables used to support the vertical columns can

    be

    seen. The centre column and the inner ring of6 columns

    have been erected, the beams have been installed joining the

    inner ring, and some

    of

    the radial purlins have been

    installed.

  • 7/25/2019 OHS Worker Fatalities Report

    34/43

    File: F-536919

    Attachment A

    Page 16

    of22

    Photograph #16 Shows the base

    of

    the centre column in tank 72-TK-lC. The

    come-alongs tensioning the cable supporting the columns

    can be seen. Arrow A indicates a cable that has been

    clamped correctly, with the saddle clamps installed so that

    the saddles are on the live side

    of

    the cable. Arrow B

    shows one that has been made up incorrectly, with t

    he

    saddles on the dead side of the cable.

  • 7/25/2019 OHS Worker Fatalities Report

    35/43

    File: F-536919

    Attachment A

    Page 17of22

    Photograph 17 Shows tanks

    73

    -TK-l land 73-TK

    1

    2 on the east tank farm.

    These tanks are smaller than the tanks on the west tank

    farm. The roof support structures consist of a centre colwnn

    and one ring of6 columns. The roof support structure

    installation has been completed and the support cables can

    be

    seen.

  • 7/25/2019 OHS Worker Fatalities Report

    36/43

    File: F-536919

    Attachment A

    Page 18of22

    Photograph # 8 Shows the debris field on the east side of tank 72-TK-lA

    after the roof support structure in this tank also collapsed.

  • 7/25/2019 OHS Worker Fatalities Report

    37/43

    .....

    File: F-536919

    Attachment A

    Page 19 of22

    Photograph #19 Shows the collapsed roof support structure on the east side

    of

    tank 72-TK-lA. t can be seen that several tank wall

    sections were broken off this tank during the collapse.

  • 7/25/2019 OHS Worker Fatalities Report

    38/43

    File: F-536919

    Attachment A

    Page 20 of22

    Photograph #20 Shows an intact orbital welding machine on the inside of a

    tank wall. A welder working inside the welding machine

    would be welding the horizontal seam indicated by the

    arrow.

  • 7/25/2019 OHS Worker Fatalities Report

    39/43

    .

    File: F-536919

    Attachment A

    Page

    21 of

    22

    Photograph

    21

    Shows an inta

    ct

    orbital

    we

    lding machine seen from outside

    the tanlc The work platform on the top of the welding

    machine can

    e

    seen. The Electrical Consultant was

    standing on the top work platform of

    a sim

    il

    ar

    we

    lding

    machine at the time of the incident.

  • 7/25/2019 OHS Worker Fatalities Report

    40/43

    File: F-536919

    Attachment A

    Page 22 of22

    Photograph 22 Shows the lower end of one of the cables supporting the

    roof

    support structure in Tank 72-

    TK-lB

    after the collapse

    of he structure.

  • 7/25/2019 OHS Worker Fatalities Report

    41/43

    ort

    Ma aii

    File Number: F-536919

    Attachment: B

    Location Map

    Not

    t

    Scale

    N

    s

  • 7/25/2019 OHS Worker Fatalities Report

    42/43

    Sulphur

    Recovery:

    Coker Diluent Reco ery

    Cogeneratlon Plant and Utilities

    N

    WestTank Farm

    w s

    Ad

    min Warehousing

    \ To Aerodrome 5km

    File Number: F 369 9

    Attachment:

    Site Layout

    Not to Scale

    C

    Camp3

    Lodge

    astTank Farm

    Hydrogen Plant

    Hydrotreating

    Heat

    Integration

    \Froth Treatment

    To South Mine

    Mine Maintenance and

    Administration Facilities

    PllSlse

    D

    Phase: D

  • 7/25/2019 OHS Worker Fatalities Report

    43/43

    .

    GUY

    WIRES

    1

    OUTER

    RING

    SUPPORT

    COLUMN

    TANK

    SHELL

    TANK SHELL

    ELEV TION

    INNER

    RING

    SUPPORT COLUMN

    CENTRE SUPPORT

    COLUMN

    GUYWIRES

    F536919

    Attachment D

    Sketch of

    roof

    support

    structure

    Not to scale

    OUTER RING

    GIRDERS

    INNER

    RING

    GIRDERS