Upload
slav-kornik
View
221
Download
0
Embed Size (px)
Citation preview
7/25/2019 OHS Worker Fatalities Report
1/43
Workers Crushed y
Collapse
of Tank Roof Support Structure
Date of Incident: pril 24 2007
Type of Incident: Double Fatality
2 Serious Injuries
3
Minor
Injuries
7/25/2019 OHS Worker Fatalities Report
2/43
TABLE
OF CONTENTS PAGE NUMBER
SECTION
1.0
DATE
AND TIME
OF
INCIDENT
3
SECTION
2.0
NAME
ADDRESS
OF PRINCIPAL
3
ST
AKEHOLDER S)
-
Owner s)
-
Prime
Contractor
-
Employer s)
-
Stakeholders
SECTION
3.0
DESCRIPTION OF PRINCIPAL
4
STAKEHOLDER S)
SECTION
4.0
LOCATION
OF
INCIDENT
6
SECTION 5.0
EQUIPMENT
AND
MATERIAL INVOLVED
7
SECTIO N 6.0 NA
RRATIVE DESCRIPTION
OF
INCIDENT
8
SECTION 7.0
ANALYSIS 12
SECTION
8.0
APPLICABLE LEGISLATION
14
SECTION
9.0 FOLLOW-
UP/ACTION
TAKEN
17
SECTION
10.0
SIGNATURES
18
SECTION
11.0
ATTACHMENTS
18
2
September
7
,
20
07
7/25/2019 OHS Worker Fatalities Report
3/43
File: F-536919
Section 1.0 DATE AND TIME OF INCIDENT
1.1 April 24, 2007, approximately 2:30 p.m.
Section 2.0 NAME ADDRESS OF PRINCIPAL STAKEHOLDER S)
2 1 Owner s)
2.
1
I Canadian Natural Resources Limited
2500-855 2 Street SW, Calgary, Alberta T2P 41 8
2.2 Prime Contractor
2.2.
Ca
nadian Natural
Re
sources Limited Horizon Oil Sands Corporation (CN
RL
Horizon)
PO Bag
4025, Fort
McMurray
, Al
berta
T9H 3H5
2.3 Employer 1
2.3. 1 SSEC Canada Ltd. SSEC Canada)
1800, 250-6 A venue,
Ca
lgary, Alberta T2P
3H7
2.4 Employer 2
2.4. Tenth Construction Company of Sinopec (TCC)
PO Box 132, Zibo, Shandong, China 255438
2.5 Stakeholder 1
2.5. 1 Sinopec Shanghai Engineering Company Ltd. SSEC China)
769 Zhangyang Road, Pudong New Area, Shanghai, China
2.6 Stakeholder 2
2.6.1 China Petrol
eum
and Chemical [Petrochemical] Corporation (Sinopec)
PO Box 3013, Beijing 100011, China
2.7
Stakeholder 3
2.7.1 The Zachry Group
Suite 250, 700 Sixth Avenue SW, Calgary, Alberta, T2P OT8
3
September 27, 2007
7/25/2019 OHS Worker Fatalities Report
4/43
File: F-536919
2.8 Stakeholder 4
2.8.1 Zachry Energy International Inc
1238, 13351 Commerce Parkway, Richmond, British Columbia V6V 2X7
2.9
Stakeholder 5
2.9.1 TIW Division
of
Canadian Erectors Ltd. (TIW)
23 Smith Street, St. Catherine's, Ontario L2R 6Y6
Section 3.0 DESCRIPTION
O
PRINCIPAL STAKEHOLDER S)
3.1 Canadian Natural Resources Limited CNRL)
3 1.1
CNRL
is a senior independent oil and natural gas exploration, development and
production company based in Calgary, Alberta.
3.1.2 The CNRL Horizon Oil Sands Project is located approximately 7 m north ofFort
McMurray and 3 km north of Fort MacKay, Alberta. CNRL owns and operates
leases covering approximately 115,000 acres and will use open pi t mining
me
thods to
mine oil sands. A plant is being constructed that will separate raw bitumen from the
oil sands and upgrade the bitumen to a synthetic crnde oil using delayed coking and
hydro-treating technologies. Phase 1 started in 2005 and is scheduled fo r completion
in 2008, ramping up to produce 11 0,000 barrels of synthetic crude oil per da
y
Phases
2 and 3
wi ll
proceed until projected completion in 20 12 Phase 3 is expected to bring
production to 232,000 barrels of synthetic crude oil per day. At the time of the
incident approximately 6,000 workers were working on the construction of the
project.
3.2 SSEC Canada Ltd. SSEC Canada)
3.2.1 SSEC Canada is an Alberta corporation. The company was incorporated in April,
2006 to bid for work in the Alberta oil sands.
The
company is 90 owned
by
SSEC
China, a Chinese company, and 10 owned
by
Zachry Energy International Inc., a
companybased in British Columbia. SSEC Canada uses management, technical and
journeyman workers drawn from
SSEC China and Tenth Construction Company
of
Sinopec (TCC), working in Alberta as temporary foreign workers, to carry out
projects such as the tank farm project at the
CNRL
Horizon Oil Sands Project.
3.2.2 SSEC Canada was contracted by CNRL Ho
ri
zon to construct a total of 14 tanks, 11
on the east tank farm and 3 on the west tank farm at the CNRL Horizon Plant Site.
The effective date of he contract was April 11 , 2006. SSECCanada was expected to
have workers available July 2006 to commence the tank assembly at the west tank
farm. Wo rk on the three tanks at the west tank fan11 was scheduled for completion by
September, 2007.
September 27, 2007
7/25/2019 OHS Worker Fatalities Report
5/43
Fil
e:
F-536919
3.2.3 The three tanks on the west tank farm were being constructed in accordance with a
tank erection schedule prepared by CNRL. The schedule specified a
se
quence of
construction where the tank floors were laid, the walls were started and the internal
roof support structures were erected. SSEC Canada was required to construct the
tanks in accordance with
th
e tank erection sched
ul e
and in accordance wi
tb
component and mate
ri al sc
hedules and engineered drawings provided by
TIW
. The
TIW drawings showed how the components and materials they had supplied fitted
together. SSEC Canada was responsible for the direction of their workers, which
included giving
in
structions on how component
pa
rts of the roof suppo
rt
structure
were to be suppotied from movement or falling until the construction was complete
and the tank assemblies were self-supporting.
3
.3
Tenth Construction Co
mpan
y
of
Sinopec (TCC)
3.3. l TCC is an industrial construction company in China, specializing in the construction
and in stallat ion of petroleum refining projects. TCC has undertaken construction
projects in Africa, Asia and Saudi Arabia.
3 4 Sinopec
Shanghai Engineering Company
(SSEC
China
SSEC
China is a Chinese company based in Shanghai, Ch ina. SSEC China has the
capacity to undertake mid
to large engineering projects including projects in the
petrochemical industry. SSEC China has some contacts with engineering companies
inte
rn
ationally. SSEC China own a 90% share of SSEC Canada and exercises full
control of all activities of SSEC Canada.
The
Horizon tank project was sub
contracted to
TCC
by
SSEC China. All workers were recruited by
TCC
. Most
construction management personnel were employed by TCC. SSEC China employed
one
bus
in
ess representa
ti
ve
in Ca
lgary to deal with the finances and one secretary at
the CNRL sit
e.
3.5
Sinopec C
hina Petroleum
and Chemical Petrochemical Corporation (Sinopec)
3.5 .1 Sinopec is the largest producer and marketer of refined oil products in China and
Asia, and is the largestproducer and distributor of petrochemicals in China. Sinopec
is a state-owned Chinese corporation, is the second largest oil and gas explorer in
China, and is the parent co
mpany
of
both TCC and SSEC Chin
a.
3.6
T
he Zachry Group
3.6 .1 The Zachry Group is an Alberta registered company that designs and manufactures
equipment fo
r the oil and gas, pulp a
nd
paper, sawm
ill
s and mining industries.
5
September 27, 2007
7/25/2019 OHS Worker Fatalities Report
6/43
File: F-536919
3.
7.
Zachry Energy International Inc.
3.7.1 Zachry Energy International Inc. is a British Columbia registered company that is
60% owned by the Zachry Group. Zachry Energy International Inc. provides
overview and management input to SSEC Canada and is 10% shareholder
ofSSEC
Ca
nada. Zachry International Inc. focused on helping
SSEC
Chin a to liai
se
with
CNRL and to penetrate the oil and gas construction market in Alberta. They were
responsible to assist SSEC China to
li
aise with
CNRL
and assist with requirements
of
training
of
he trade workers.They were responsible to assist SSEC China workers to
obtain work visas, and coordinated with Alberta Apprenticeship and Indust ry
Training (AAIT) requirements for designated trades.They assisted SSEC China to set
up SSEC Canada Ltd. , and assisted SSEC Canada Ltd. with obtaining legal counsel
to help the company deal with local regulations and laws in connection with their
establishment in Alberta. In March of
2007 Zachary Energy International Inc.
relinquished its 10% share
of
SSEC Canada. SSECChina and Sinopec requested that
Zachary Energy International Inc. be the lead contact for SSEC Canada in relation to
the investigation ofWHSC with respect to the April 24, 2007 incident at the
CNRL
Horizon site.
3.8 T W Division of Canada Erectors Ltd. TIW)
3.8. l TIW is engaged in the fabrication, construction and distribution sectors
of
the stee l
industry.
TlW
is a fully integrated unit for design, manufacturing and construction of
fi eld erected steel platework structures.TIW was contracted byCNRL to provide the
components, material schedules for arriva l on site, and the engineered drawings for
th e 14 tanks on the east and west tank fanns at the CNRL Horizon plant site.
3 .8.2 The
roof
support structures were all fabricated in house by TIW at their faci i ies,
with the exception
of
the weldingofcolumns to the cap plates, which was perfo1med
by Bartonair Fabrications of Hamilton. Bartonair is a regular supplier to TIW.
Bartonair was required to use TIW supplied materials, consumables and welding
procedures. TIW inspection personnel reviewed the materials before shipment. TIW
coordinated the identification, packaging and shipment
of
he
roof
support structures
(including columns) to the CNRL Horizon site.
Section 4.0 LOCATION OF INCIDENT
4.1 Tank 72-TK- l B, located on the west tank farm of the CNRL Horizon Oil Sands
Project,
approximately
70
km north
of
Fort McMurray and 30 km north
of
Fort
MacKay, Alberta.
6
September 27, 2007
7/25/2019 OHS Worker Fatalities Report
7/43
Fi
le: F-5369 19
Section 5.0 EQUIPMENT AND MATERIAL INVOLVED
5.1
he
West Tank Farm
5 .1 I The west tank farm is located approximatel y northwest of centre on the Horizon Plant
Site. (Attachment
C ,
Site Layout
).
As
the tanks had restricted
mea
ns
of
entry and
exit and could become hazardous to workers entering them, they were designated as
confined space. Three high-cone steel tanks, Tank 72-TK-lA, 72-TK- IB and 72-TK-
1
C
are located on
the
west tank farm, in a line east to
west
with Tank 72-TK-1A at
the
west, Tank 72-TK-
lB in
the centre and Tank 72-TK- lC at the east end of he row
of tanks.
The
tanks are
all
the same size and of the sa
me
construction. At the time of
the incident the
roof
support structure in tank 72-
TK
-
l
B was in a suspended state of
completion with the centre support column, the inside ring of6 support columns and
the outer ring of 12 support columns in place, with the girders and rafters fitted,
waiting for the she ll assembly to be completed. Once the she ll assembl y was
completed,
th
e rafters from the outer ring 's girders would be connected to the she
ll
wal1. The roof support structure in
ta
nk 72-TK-1 B had been completed the day before
the co llapse. At the time of
th
e incident a team
of
bo ilermakers and scaffolders was
working in Tank 72 -TK-1 C on the assembly of th e roof support structure.
(Attachment A'', Photographs 1 1, #15)
5.2
The East
ank
Farm
5.2.1 The east tank farm is located at the east
of
the Horiz
on
Plant Site (Attachment
C'
',
Site Layout).
When
completed, the east tank farm will contain 10 tanks of various
siz
es
, and
of
generally similar construction to the tanks
on the
west tank fann. At the
time
of the
incident,
the
roof support structures in two tanks
on the
east tank farm,
Tank 73-TK-11
and
73-TK-12 were also in a suspended state
of
assembly waiting for
the shell walls to be competed. After which they would connect the rafters from the
outer rin
gs'
girders to the top of th e she
ll
wa
ll
s.
(A
ttachm ent A , Phot
ogra
ph #17)
5.3
Tank 72 TK tB
5.3. 1
Ta
nk 72-
TK-l
B (described as a Dilbit Dewatering
Ta
nk), located on the west tank
farm, was to be a circular steel high-cone roof tank, 56.5 mi n diameter and 19.8 m
hig
h.
At the time
of
the incident the tank wa
ll
she
ll
was only completed to a height of
5.6 m.The tank structure consists of wall,
fl
oor and roof constructed from steel plate.
The
roof
is constructed onto a
roof
supp
or
t
st
ructure cons isting
of
vertical circular
column
s,
supporting girders and
ra
dial rafters. (Attachment D , Sketch of Roof
Support Structure). The components of th e roof support structure are assembled
together
with
19 mm
X
inch) nuts and bolts. At the time of the incident a team of
welders was working in the tank constructing the tank wall. Two technicians were
also in the tank carrying out weld testing, and one scaffolder
wa
s in Tank 72-TK-l
B.
There was an Electrical Consultant and awelding foreman who we re checking out a
we lding machine on top
of
the wa ll .
7
September 27, 2007
7/25/2019 OHS Worker Fatalities Report
8/43
File: F-536919
5.4
ssembly Procedure for
Tanks
5.4.1 SSEC Canada developed a procedure
fo
r assembling and supporting the tank roof
support structures for the tanks on the west tank farm. Erection of the shell was
independent
of
the
roof
support structure - they were being assembled concurrently.
The procedure consisted ofraising the centre support column first, using a crane and
securing it in the ve1
ica
l position by workers operating elevating work platfo
1m
s to
in
stall 4 steel cables, secured to the top of the column and anchored to lugs welded
onto the tank floor
The
cables were tightened using
co
me-alongs . ( Come-along
is a generic tenn to de
sc
ribe mechanical tensioning devices). The inner ring of 6
support columns was erected in a similar manner, but with 3 cables on each column.
The girders connecting the inner ring of columns were then lifted and bolted into
place, using 19 mm ( :y ; inch) bolts, and the ra
di
al rafters were installed between the
centre column and the inner ring. After the inner ring was completed, one cable,
extending towards the ta
nk
centre, was removed from each
of
the 6 inner ring
columns The outer ring of 12 columns was erected, using 3 cables to support each
column. The girders connecting the outer ring ofcolumns were lifted and bolted into
place, and all of the radial rafters were installed. After
th
e outer ring of the
roof
support structure was assembled, 6 steel cables were installed, extending from girders
to alternate columns in the outer ring to anchor lugs welded into the floor of he tank,
close to the tank wall. When
th
ese 6 support cables were in place and tightened using
come-alongs'', all of the cables used to support the individual columns were
removed. The six cables remaining were intended to support and stabilize the
roof
sup port structure unt il the she ll was completed to ful l height The come-alongs
were removed after the cables had been tightened.
Section 6.0 N RR TIVE DESCRIPTION OF INC IDENT
6. 1 SSEC Canada recruited 132 Mandarin-speaking Chinese workers from TCC to work
as temporary foreign workers on the CNRL tank construction project.
The
workers
had at least 5 years expe
ri
ence as trades-people and had recei ved additional training
from a Canadian training agency before arriving in Canada.
The
workers started to
arrive
in
Canada
in
September of 2006.
6.2 On April 24, 2007, at the west tank farm, the
roof
support structures in tanks 72-TK
lA (Attachment
A ,
Photograph #11) and
72-TK-lB
were in the suspended state of
completion waiting for the shell to
be
assembled. Each
roof
sup
port structure was
supported by six cables
The
roof
support structure in tank 72-T
K-lC
was being
assembled The centre column and the inner ring had been completed and the steel
cables were still attached to the columns. No work was taking place
in Tank 72-
TK
l A on April 24, 2007. A team of boilermakers was working in Tank 72-TK-I C,
assembling the roof suppo1t structure. (Attachment A , Photograph #15)
8
September 27, 2007
7/25/2019 OHS Worker Fatalities Report
9/43
6.3
6.4
6.5
Fil
e:
F-536919
On April 24, 2007, a team of welders was working in tank 72-TK-1 B, welding
sections into the tank wall. The tank wall sec
ti
ons were being welded together by
welders and helpers wo rking inside welding machines that tracked around the inside
of the tank wa ll. (Attachment A ,Photographs #20, #21) One Electrical Consultant
and a welder foreman were inside the tank checking an elect
ri
cal failure on one
of
he
we
lding machines. One scaffolder was also on th e
fl
oor area inside the tank. Two
weld test technicians were also in Tank 72-TK-1 B, testing and marking the welds on
the tank wall.
At approximately2:30 p.m. on April 24, 2007, workers inand around tank 72-TK- lB
heard several sounds, described as loud bangs or pops. The roofsupport structure in
tank 72-TK-1 B started to fal l in an easterly direction during windy conditions. As the
structure collapsed, some of the support cables failed, many of th e bolts that were
holding the components together failed and then the components began to come
apart. (Attachment A, Photograph s #8, #9, #10, # 22) The stru cture fell onto the
east side of the tank wall. Some of he components of the roofsupport structure can1e
to rest on th e floor of the tank , some components came to rest leaning against the
tank wall, and some components came to rest on the outside of the tank on the east
side. Many of the components we re bent or damaged by the impact.
Af
ter the roof
support structure co llapsed so
me
of the workers who
were
in tank 72-TK-1 B,
managed to escape from the tank through manways or other holes in the tank wal
(Attachment A , Photographs #1, #2, #3, #4)
SSEC Canada workers from tank 72-T
K-.1
C and other workers on the west tank farm,
as
well
as workers from other contractors who were working near the west tank fa1m ,
went to tank 72-TK-lB to provide assistance. CNRL Horizon emergency services
were called and attended. Rescuers had to lift a large section
of
steel inside the tank
to remove the fatally injured Scaffolder. The Electrical Consultant was standing on
the top of a welding machine, which was located on top of he wall, and was fatally
injured
when he
was struck
by
falling steel. His body was thrown onto scaffolding
outside the tank. The Electrical Consultant was pronounced dead at the scene. The
Scaffolder, who was on the tank floor, was crushed by the falling steel and died in an
eme
rgency conveyance vehicle on the way to Fort McMurray. Two other workers
received serious injuries and three more workers received minor inj uries. The two
se
riously injured workers and two of the workers who had received minor injuries
were transported to hospital in Fort McMurray. The two seriously injured workers
were subsequently transferred to hospital in Edmonto
n.
6.6
INV STIGT ION OBSERV TIONS ND FORMT ION
6.6. 1 Workplace Health and Safety Compliance (WHSC) was notified of the incident by
CNRL Horizon at 3:08 p.m. on April 24, 2007. Workplace Health and Safety officers
from Fo1t McMurray were dispatched to the scene and while en route made contact
with RCMP Fort McMurray Detachment. WHSC officers arrived at the site at
5:
19
p.m
. The scene had been secured
by
CNRL and RCMP.
9
September 27, 2007
7/25/2019 OHS Worker Fatalities Report
10/43
File: F-536919
6.6.2
WHSC
issued a verbal Stop Work Order to CNRL at 8:36 p.m.
on
April 24, 2007.
The Stop Work Order was for construction of the three tanks on the west tank farm
and any similar tanks on the Horizon site.
6.6.3 On April 24, 2007 a WHSC Lead
In
ves
ti
gator was di spatched from Edmonton to
direct the investigation The Lead Investi
ga
tor atTived at the CNRL Horizon Oil
Sands Project at 9:00 am . on April 25, 2007.
CN
RL Ho
ri
zon set up an internal
investigation team a
nd
met with
th
e Lead Investigator a
nd
other Workplace Health
and Safety of
fi
cers on April 25, 2007. The Lead Investigator confirmed the ve
rb
al
Stop Work Order a
nd
reminded CNRL Ho
ri
zon that no workers were
to
enter the
area and to have the area secured.
6.6.4 On April 25, 2007 a seco
nd
WHSC Lead
In
vestigator, the WH SC Manager
of
Compliance, and an employee from another Govenunent of Albe1ta depa1tment, who
speaks Mandarin, were dispatched from Edmonton to assist with the investigation.
The second Lead Investigator, the Manager and the other employee arrived at the
CNRL Horizon plant site at 6:00 p.m.
6.6.5 t was found that there had been
13
workers inside tank 72-TK-lB at the time the
incident occurred.
Ten
workers were Chinese temporary foreign workers employed
by
SSEC Canada, one Chinese worker (the Electrical Consultant) was directly
employed
by
TCC and two workers were Canadian workers employed by Iris
NDT
,
carrying out weld testing. All of the fatally injured and other injured workers were
Chinese temporary foreign work ers. SSEC Canada workers and others who had
attended the scene were interviewed over a pe
ri
od of several days, in o
rd
er to
determine the circumstances of the inc
id
ent and the loca
ti
ons
of
a
ll of
t
he
workers
who were inside the tank at the time of the incident. t was found
th
at
th
e workers
had carri ed out the assembly of
th
e
ro
of suppo
rt
structures in accordance with SSEC
Canada
's
chief engineer
's in
structions a
nd
the assembly drawings prov
id
ed by T IW .
6.6.6 One
of
the
fa
tally injured workers, an Electrical Consultant, had been on the top
of
a
welding m
ac
hine working on
th
e east side of the tank wall. The Electrical Consultant
had been struck in the head and back by a section of the falling steel and thrown onto
scaffolding outside the east wall
of
the tank.
The
other fatally injured worker, a
Scaffolder, had been standing on the tank floor, east of the tank centre, and had been
caught and crushed under a falling girder. Rescuers had manually lifted the girder to
rescue him. The Scaffolder died during transport to hospital. (Attachment
A
,
Photographs #4, #5, #7)
1
September 27, 2007
7/25/2019 OHS Worker Fatalities Report
11/43
6.6.7
6.6.8
6.6 .9
6.6.10
6.6.11
File: F-536919
One
of
the seriously injured workers, Welder l , had been inside the same welding
machine that the Electrical Consultant was working on. The welding machine } ad
been struck by fall ing steel and partially dislodged from the tank
wa
ll. Welder
1
was
trapped inside the welding machine and was rescued by CNRL staff a
nd
other
contract workers.
The
other seriously injured worker, Welder 2, was inside another
welding machine on the east wall that had been struck by falling steel and completely
dislodged from the wall, falling to the tank floor. Welder 2 was rescued by his
Chinese co-workers. (Attachment A , Photographs #5, #6)
The verbal Stop Work Order was confirmed in writing on April 27, 2007. The Stop
Work Order prevented access to the east and west tank farms.
The
Stop Work Order
was re-issued on May 1, 2007 to define a specific part of the east tank farm around
tanks 73-TK-1 and 73-TK 12 where workers could be at risk from the collapse of
the
roof
support structures. The remainder of the east tank farm was released to
CNRL. The Stop Work Order for the west tank farm remained in effect. CNRL
cooperated with the Stop Work Orders and provided barriers and security
staff
to
ensure that the order was made effec
ti
ve.
On May 1
2,
2007 the roof suppo1t structure in tank 72-TK-lA on the west ta
nk
farm
collapsed during windy conditions. The Stop Work Order was st ill in effect and no
workers were near the collapse. Before the collapse it had been observed that the roof
support structure was twisting during windy conditions. (Attachment
A
,
Photographs #18, #19)
CNRL developed an engineered procedure for securing and dismantling the roof
support structures in tanks 73-TK-1 and 73-TK-12 on the east tank farm. The Stop
Work Order for the east tank farm was lifted on May 16, 2007 and the site was
released to CNRL Horizon to enable the remediation work to be done. The work on
dismantling and removal of the roof support structures was completed on June
11
,
2007 by SRS Industrial Services Ltd.
CNRL developed an engineered procedure for the removal of fallen materials in
tanks 72-TK-lA and 72-TK lB and the dismantling of the roof support structure
from tank 72-TK-l C. The Stop Work Order for the west tank farm was lifted on June
6, 2007. Work on tank 72-TK-I A commenced on June
8,
2007
an
d was completed on
June 13, 2007. Work then sta1ted on tank 72-TK-I B a
nd
was completed on June 20,
2007.
The
removal
of
he roofsupport structure in tank 72-TK-l C was completed on
June 22, 2007 by Penny Industrial Fabricators Ltd. The WHSC Lead
In
vestigator
monitored the removal
of
the fallen materials from tanks 72-TK-1A and 72-
TK-1
B
and during the removal retrieved materials from both tanks for analysis by an
independent
co
nsulting engineering firm.
September 27, 2007
7/25/2019 OHS Worker Fatalities Report
12/43
File: F-536919
Section 7.0 ANALYSIS
7 1 Direct ause
7 1.1 Two workers working on the construction ofa large steel tank 72-TK-1 B were fatally
injured two other workers were seriously injured and three workers received min
or
injuries when the
roof
support structure inside the tank collapsed suddenly and
without warning onto the workers.
7 2 ontributing
Factors
7 2. 1 SSEC Canada assembl
ed
the
roof
support structure as a stand alone structure which
was not intended to be assembled as such by the T l drawings. Neither CNRL n
or
SSEC Canada consult
ed
with
TIW
with respect to what assembly sequence should
be
fo ll
owed for the con
st
ruction of the
roof
support structure. As the erection
of
the
shell was independent of the roof support structure and they were being assembled
concun-ently the top of the shell and the outer ring were not supporting each other.
7.2.2 TIW did not specify
an
erection sequence to follow to erect the tank they designed.
TIW did not specify the assembly sequence because that was not part of he contract
with CNRL.
7 2.3 CNRL prepared a tank erection schedule specifying the sequence
of
construction
such as when the tank floors were to be laid the
wa lls to be started and the internal
roof
support structures were to be erected. SSEC Canada followed the tank erection
schedule as set out
by
CNRL.
7.
2.4 SSEC Canada did not provide written engineered erection procedures for the
assembly
of th
e roof suppo
rt
structure. C
NRL
did not require SSEC Canada to
provi
de
written engineered assembly procedures.
7 2.5 The SSEC Canada chief engineer who developed the erection procedure for the roof
supp
o1i
structures and specified the number si
ze
and locati
on
of the guy wires was
not a qualified professional engineer.
7.2.6 The roof support structure was a completely bolted structure using ASTM A- 307
Grade bolts without the use of wedges
or
washers. The bolted roof support
structure which was required to be flexible did not have the necessary restraints to
resist the lateral forces generated by the wind.
12
September 27. 2007
7/25/2019 OHS Worker Fatalities Report
13/43
7.2 .7
7.2.8
7.2.9
7.2.10
7.2
11
7.2.11.1
Fi
le: F-536919
The number and size of guy wires that were supporting the roofsupport structure in
tanks 72-TK- IA
and 72-TK-1 B, was not designed for the static and dynamic loads
imposed by the 33 to 45 km/h wind that occurred
on
the day
of
the incident, let alone
for the maximum expected wind speed of 83 km/h, as determined by the Alber
ta
Building Code or 1
90
km/h recommended by the American Petroleum Institute.
(Attachment
A
, Photographs #
12
, #
13
, #14, #16)
There were six guy wires wrapped around girders located near the outer ring columns
to stabilize the roofsupport structure. Three
of he guy
wires were aligned in a radial
direction through
the
centre column axis; however,
the other
three
guy
wires were
significantly offset from radial alignment and
were
angled in the same direction by
14 to
24
Because
of the
offset alignment, this action would result in forces
attempting to twist the roof support structure
in
a clockwise (easterly) direction,
which is the direction of
he
eventual collapse.
Because
of
the flexible bolted structure, any
movement
caused by the wind, would
pro
vide
means to loosen the nuts on the bolts as well as intensify the twisting force
on the guy wires .
Examination
of
the roofsupport structures in tanks 72-TK-1C, 73-TK-1 and 73-TK
2 showed that many
of
the bolts used to asse
mb
le the structures were loose; so
me
bolts had become bent during tightening, or necked because the thread length was to
short. o washers
or
bevelled washers were used in the a
ss
emb ly
of
the roofsupport
structure.
On April 25 , 2007 Workplace Health and Safety
Co
mpliance contracted Anderson
Associates Consulting Engineers Inc. to examine
the
circumstances leading to the
collapse
of
he
roof
support structure in tank 72-TK-
B.
The
Professional Engineer's
report summarized the following causes:
The
collapse was primarily
the
result
of
inadequate
guy
wires used as wind bracing
on the
partially assembled flexible roof structure. As wind speeds increased, the
flexible roof structure began to load the guy wires. Due to the structure 's flexibility
and
the
unbalanced load conditions (the unbalanced geometry
of he
channel rafters
and the poor alignment
of guy
wires with
the
structure), the roof oscillated
in
the
wind. This
mo
ve
ment of
the 127 metric ton roof structu
re
imparted cyclic loading
onto the guy wires. The upwind guy w
ir
e failed first as the wire rope clips
became
o
ve
rloaded and slipped toward the floor attachment lug. Once the structure
was
able
to
move
out
of
position, it collapsed in a downwind direction-essentially blown ove
r
13
September 27, 2007
7/25/2019 OHS Worker Fatalities Report
14/43
File: F-53691 9
7 .2.
11
.2 The design
of
he guy wire wind bracing was based
on
API 650 calculation methods.
These methods are inadequate for structural steel stability, although they are suitable
for their intended use tank stability). As a result, the designer, who was not a
professional engineer, determined that there was minimal need for wind bracing.
Only six 12.5 mm (half nch) guy wires were used to brace the structure against wind
loads. These were neither aligned to prevent rotation
of
he
structure
nor
sized with a
normal safety factor. When the wind speed increased, the structure began to oscillate
and the guy wires were overloaded by the inertia of the structural steel s movement.
7.2.11.3 Bracing to make the structure more rigid was not installed by the erector. This or
other temporary cross-bracing may have helped prevent
or
reduce the oscill ation that
led to the
in
ertial loa
d
More wind bracing, in tenn s
of
guy wires or structural steel
c
ro
ss-bracing, would have been required to prevent the incident.
7.
2 11
.4 The inc
id
ent was n
ot
caused by mate
ri
al failure of the wire ropes,
fi
ttings or erect ion
equipment. Testing of the wire rope and wire rope clips confin
ned
their design
capacity. Damage to the structural steel was all a result
of h
e incident The A-307
bolts used to connect the structural steel were proper strength when tested. They had
failed as the structure collapsed. t is unlikely that stronger bolts al one would have
prov id
ed the rigidity required to
pr
event the incident.
Section 8.0 APPLICABLE LEGISLATION
8 1 Occupational Health and Safety Act, Section 2 1) a) i)
Obligations o employers
8.1.1 SSEC Canada did not take reasonably practicable measures to protect the health and
safety of all the workers who were working inside the tank when the incident
occurred The tank roof support structure that co llapsed onto the workers was a
skeleton structur
e
The erection procedures
fo
r erecting the
roof
support structures
had not been prepared and certifi ed by a professional engineer
8 1 .2 Tenth Construction Company
of
Sinopec TCC) did not take reasonabl y prac
ti
cable
measures to p
ro
tect the health and safety
of th
e Electrical Consultant. The tank roof
support st
ru
cture that collapsed onto the worker was a skeleton structure. The
erecti on procedures for erecting the roofsupport structures had not been prepared and
certified by a Professional Enginee
r
Th
e El
ec
trical Consultant did not have a work
permit as a temporary
fo
reign wo
rk
er a
nd
thus should not have been working at this
work site.
14
September 27, 2007
7/25/2019 OHS Worker Fatalities Report
15/43
8.2 Occupational Health
and
Safety Act, Section 3 3)
Prime
Contractor
File: F 536919
8.2. 1 CNRL did not do what was reasonable and practicable to ens
ur
e
the Act
a
nd the
regulations
we
re complied with by failing to ensure that one of their contractors had
er
ect
i
on
drawings and proced
ur
es for a skeleton
st
ructure certified by a professi
ona
l
engrneer.
8.3 Occupational Health and Safety Regulation, Section 7 1)
Availability of specifications
8.3. 1 The Occupat ional Health and Safety Code requires skele ton structures to be erected
in accordance with engineered erection procedures. SSEC Canada did not provide
engineered erection procedures.
Th
e procedures fo r the erection of the
roof
suppo1
structure were not certified by a professional engineer and the specifications were not
readily available to the workers responsible for
the
work.
The
workers
were given
only verbal instructions on the erection procedure.
8.4 Occupational Health
and
Safety Regulation, Section 13 1) a) b)
General protection of workers
8.4. 1 SSEC Canada did not ensure that
the
engineer who developed
the
erection drawings
and procedures of he roof support structure was a professional engineer competent to
do the work, or supervised by a professional enginee
r
85 Occupational Health and Safety Code, Section 7 1)
Hazard assessment
8 5 1
SSEC
Ca
nada he ld daily too lbox meetin
gs
be fore work started. Field level risk
assessments were carried out during
the
too lbox meetings.
SSEC Ca
nada had
prepared a HSE Manual containi
ng
generic safety procedures.
8.6 Occupational Health
and
Safety Code, Section 14 1)
Certification by a professional engineer
8.6.1
The
Code requires that skeleton structures are erected in accordance with erection
procedures certified by a profession
al
engineer. SSEC Canada did not ensure that
the
erection procedure and drawings had been certified, signed and stamped
by
a
profes
sional engineer.
5
September 27, 2007
7/25/2019 OHS Worker Fatalities Report
16/43
File: F-536919
8.7
Occupational health and Safety Code, Section 46 3)
Confined space training
8.7
1 SSEC Canada
did
not
ensure that
the
worker
who was
assigned duties relating
to
confined space en
tr
y
was
trained by a competent person. The worker who had
been
de
si
gna
ted the
Co
nfined
Space Mo
nitor fo r the day
of
the
incident
was
not
aware
of
the
purpose
of the
confined space designation his
dutie
s in terms
of
mai
nta
i
ning
communi cation w ith the work
ers
in the confined space or his
dut
ies
if
an emergency
occurred. The Confined S
pace
Monitor had not been effectively trained in his
duties
and
was
n
ot compe
t
ent
to
per
fo
nn
the duties required. The Confined Space
Mon
i
tor
was not
able to
com
municate w ith the workers insi
de the
tank and was not
able to
rai
se
an alarm following the incident.
8.8
8.8. 1
8.9
8.9.1
8. 10
8.10.1
8.
11
8.1
1 1
Occupational Health and Safety Code, Section 55 1)
Confined space emergency response
SSEC Canada had an
eme
rgency respon se procedure.
Howeve
r on the day
of the
incide
nt th
e worker who had
be
en des ignated as the
Co
nfined Space Monitor was not
awa
re
of
the emergency respon
se
requirements and
was
not
capa
bl e
of
raising an
alarm or implementing an effective rescue SSEC
Canada
did
not
ensure
that the
e
mergency
res
ponse
plan included procedures
to
evacuate the confined
space
immediately.
Occupational Health and Safety Code, Section 56 1)
Confined space tending worker
The wo
rk
er
who had been
de
signated as
th
e
Co
nfined Space Monitor
was
not
comp
ete
nt. SSEC Canada did
not
designate a
com
petent worker to
be
in
co
mmuni
cation with the
worke
rs in the co nfined space.
Occupational Health and Safety Code, Section 56 2)
Confined space tending worker
On
the
day
of the
incident the worker who
was
the
Co
nfined
Space
Monitor did not
h
ave
a telephone or
rad
io to s
umm
on assistance.
SSEC Canada
did not ensure that
the designated
worke
r had a suitable system for s
ummonin
g assis
tanc
e.
Occupational Health and Safety Code, Section 190 1)
Skeleton structures
SSEC
Ca n
ada
did not ensure that er
ec
ti
on
drawing and procedures for the erecti
on of
the roof
support structure in tank 72-
TK
IB were prepared and certified
by
a
professional
eng
ineer.
16
Septembe
r 27 2007
7/25/2019 OHS Worker Fatalities Report
17/43
8. 12
Occupational Health and Safety Code, Section l90 2)
Skeleton structures
File: F-536919
8
1
2. 1
The
erection procedure
pr
epared by SSEC Canada for the erection
of
he roof
suppo1
i
stmcture in tank 72-TK-1
B
did n
ot
ensure that the structure was stable during
assembly.
8.13 Occupational Health and Safety Code, Section 300 1)
Cable clips
8.13. 1 SSEC Can
ada
did not ensure that u-bolt type clips used for fasteni ng wire rope were
installed so that the u-bolt section of the clip bears on the dead side of the rope and
the saddle
of
the clip bears on the live s ide
of
the rope.
8
1
4 Occupational Health and Safety Code, Section 306 1)
Wire rope
8.14.1 SSEC Canada did not remove from service wire rope used to support the
roof
support
structure
in
tank 72-TK- lB that had been distorted because
of
kinking where it had
been attached around girders.
Section 9.0 FOLLOW -UP ACTION TAKEN
9. 1 Alberta Employme
n
Immigration Industry
9.1. I
WHSC
issued Stop Work Orders to CNRL for the construction
of
the east and west
tank farms. WHSC issued orders for securing and dismantling the roof support
stru
ct
ures
in
the east and west tank farm. Orders were issued fo r remedial acti
on
s to
r
emove
fa
ll
en rnate1ial in tanks 1A and 1B Orders w
er
e also issued for
doc
umentation hazard assessments and for an investigation repot
i.
9. 1 2
WHSC
issued orders to SSEC Canada to provide documentation such as worker
information worker training records hazard assessment and engineeringprocedures.
Orders were also i
ss
ued to SSEC Canada to cooperate with CNRL s incident
investigation.
9. 1
3
WH
SC i
ss
ued orders to TIW to provide the tank drawing specifications assembly
instructions component testing and contact information with SSEC Canada.
9. 1.4
WHSC
i
ss
ued orders to ewfab Industries Ltd. to provide
wr
itten observations from
the disassembly of the roof support structure in tank 72-TK- 1C.
17
September 27. 2007
7/25/2019 OHS Worker Fatalities Report
18/43
File: F 536919
9.1.5 WHSC issued orders to SRS Industrial Services for written observations from the
securing and the di
smantling of the
roof
support structures in tanks 73-TK 1 1 and
73-TK
1
2.
9.2 Industry
9.2.1 At this timeCN
RL
has complied with all of he written orders with the exception of
the order p
er
taining to the completion of an incident investigation report.
9.2.2 SSEC Canada complied with all of the orders written.
9.2.3 TIW complied with all of the orders written.
9.2.4 Newfab Industries Ltd. complied with all of the orders written.
9.2.5 SRS Industrial Services complied with all of the orders written.
9.3 Additional Measures
9.3
.1
o additional measures
we
re required.
Section 10 0 SI
GN TURES
Section 11 0 TT CHMENTS
Attachment A
Attachment
B
Attachment C
Attachment D
. > ' ~ A 6J c:>o7
e
S e : P 1
e ~ e i s i k ~
Date
~ Z 2 P o 7
ate ../
Photographs
Location Map
Site Layout
Sketch ofRoof Support Structure
18
September 27 2007
7/25/2019 OHS Worker Fatalities Report
19/43
Photograph 1
File: F-536919
Attachment A
Page 1of22
Shows the debris field on the east side of tank 72-TK lB
after the collapse of the tank roof support structure.
7/25/2019 OHS Worker Fatalities Report
20/43
Photograph 2
File: F-536919
Attachment A
Page 2
of22
Shows part
of
the debris field
on
the outside
of
tank 72-TK
lB
after the collapse. Arrow A indicates the top
of
the
welding machine where the Electrical Consultant was
standing when he was struck by the collapsing steel. Arrow
B
indicates where the Electrical Consultant's body was
found.
7/25/2019 OHS Worker Fatalities Report
21/43
Photograph #3
File: F-536919
Attachment A
Page 3 of22
Shows the interior
of
tank 72-TK- l B after the collapse of
the roof support structure. This image was computer
generated from several photographs. Arrows A indicate
one of the vertical columns in the outer ring, and the base
where it was standing before
the
collapse. Arrows B
indicate one
of
the vertical columns in the inner ring and its
base.
7/25/2019 OHS Worker Fatalities Report
22/43
File: F-536919
Attachment A
Page 4 of22
Photograph #4 Shows the interior of tank 7 -TK-lB after the collapse of
the roof support structure. Arrow A indicates the centre
support column. Arrow B indicates the hard hat that was
worn
y
the Scaffolder.
7/25/2019 OHS Worker Fatalities Report
23/43
Photograph #5
File: F-536919
Attachment A
Page 5
of22
Shows the interior of tank -
TK-lB
after the collapse of
the
roof
support structure. Arrow
A
indicates the welding
machine partially dislodged from the
tank wall that the
Electrical Consultant was standing on, and Welder 1 was
working in, at the time
of
the incident. Arrow B indicates
the welding machine that fell from the tank wall, that
Welder 2 was working in.
7/25/2019 OHS Worker Fatalities Report
24/43
Photograph #6
File: F-536919
Attachment A
Page 6 of22
Shows a closeup view of the welding machine that Welder 2
was working in.
7/25/2019 OHS Worker Fatalities Report
25/43
Photograph #7
File: F
36919
Attachment A
Page 7 of
Shows a closeup view of the welding machine that the
Electrical Consultant was standing on, and that Welder 1
was working in.
7/25/2019 OHS Worker Fatalities Report
26/43
Photograph 8
File: F-536919
Attachment
A
Page 8 of22
Shows part of the collapsed structure from tank 72-TK-lB,
showing one of the % inch bolts that were used to bolt the
components of the roof support structure together.
7/25/2019 OHS Worker Fatalities Report
27/43
Fil
e
F-536919
Attachment
A
Page 9
of22
Photograph 9 Shows a sheared
4
inch bolt on the ground to the east
of
tank 72-TK
-lB.
7/25/2019 OHS Worker Fatalities Report
28/43
File: F-536919
At
tachment A
Page 10 of
Photograph #10 Shows the bolt also shown in photograph 9. The markings
on the bolt head indicating the specification of the bol
t
A-
307-B, can be seen.
7/25/2019 OHS Worker Fatalities Report
29/43
File: F-536919
Attachment A
Page of22
Photograph #11 Shows the completed roof support structure in tank 72-TK
lA before it also collapsed. The roof structure that
collapsed in tank 72-TK-lB was identical to this. Arrow
indicates one of the support cables.
7/25/2019 OHS Worker Fatalities Report
30/43
File: F-536919
Attachment
A
Page 12
of22
Photograph #12 Shows a closeup
of
one
of
the support cable top connections
on tank 72-TK
1A
Arrow
A
indicates where the support
cable has been secured back onto itselfusing a screw pin
shackle. Arrow
B
shows the top connection of one of the
cables that had been used to support the vertical column
during the erection
of
the roof support structure. This cable
had not been removed after the assembly
of
the structure
was completed.
7/25/2019 OHS Worker Fatalities Report
31/43
File: F-536919
Attachment
A
Page
3
of22
Photograph
3
Shows the top connection of another support cable on tank
72-TK- lA. Arrow indicates where the cable is kinked as it
passes over the top plate of the column.
7/25/2019 OHS Worker Fatalities Report
32/43
File: F-536919
Attachment
A
Page
14of22
Photograph 4 Shows a beam from tank 72-TK-lB after the collapse
of
the
roopf support structure. The top end of one of the support
cables is still attached to the beam. Arrow indicates where
the cable has been kinked and distorted as it passed through
the shackle.
7/25/2019 OHS Worker Fatalities Report
33/43
File: F
5
36919
Attachment
A
Page 15 of22
Photograph
15
Shows the partially completed roof structure in tank 72-TK
l
C.
The cables used to support the vertical columns can
be
seen. The centre column and the inner ring of6 columns
have been erected, the beams have been installed joining the
inner ring, and some
of
the radial purlins have been
installed.
7/25/2019 OHS Worker Fatalities Report
34/43
File: F-536919
Attachment A
Page 16
of22
Photograph #16 Shows the base
of
the centre column in tank 72-TK-lC. The
come-alongs tensioning the cable supporting the columns
can be seen. Arrow A indicates a cable that has been
clamped correctly, with the saddle clamps installed so that
the saddles are on the live side
of
the cable. Arrow B
shows one that has been made up incorrectly, with t
he
saddles on the dead side of the cable.
7/25/2019 OHS Worker Fatalities Report
35/43
File: F-536919
Attachment A
Page 17of22
Photograph 17 Shows tanks
73
-TK-l land 73-TK
1
2 on the east tank farm.
These tanks are smaller than the tanks on the west tank
farm. The roof support structures consist of a centre colwnn
and one ring of6 columns. The roof support structure
installation has been completed and the support cables can
be
seen.
7/25/2019 OHS Worker Fatalities Report
36/43
File: F-536919
Attachment A
Page 18of22
Photograph # 8 Shows the debris field on the east side of tank 72-TK-lA
after the roof support structure in this tank also collapsed.
7/25/2019 OHS Worker Fatalities Report
37/43
.....
File: F-536919
Attachment A
Page 19 of22
Photograph #19 Shows the collapsed roof support structure on the east side
of
tank 72-TK-lA. t can be seen that several tank wall
sections were broken off this tank during the collapse.
7/25/2019 OHS Worker Fatalities Report
38/43
File: F-536919
Attachment A
Page 20 of22
Photograph #20 Shows an intact orbital welding machine on the inside of a
tank wall. A welder working inside the welding machine
would be welding the horizontal seam indicated by the
arrow.
7/25/2019 OHS Worker Fatalities Report
39/43
.
File: F-536919
Attachment A
Page
21 of
22
Photograph
21
Shows an inta
ct
orbital
we
lding machine seen from outside
the tanlc The work platform on the top of the welding
machine can
e
seen. The Electrical Consultant was
standing on the top work platform of
a sim
il
ar
we
lding
machine at the time of the incident.
7/25/2019 OHS Worker Fatalities Report
40/43
File: F-536919
Attachment A
Page 22 of22
Photograph 22 Shows the lower end of one of the cables supporting the
roof
support structure in Tank 72-
TK-lB
after the collapse
of he structure.
7/25/2019 OHS Worker Fatalities Report
41/43
ort
Ma aii
File Number: F-536919
Attachment: B
Location Map
Not
t
Scale
N
s
7/25/2019 OHS Worker Fatalities Report
42/43
Sulphur
Recovery:
Coker Diluent Reco ery
Cogeneratlon Plant and Utilities
N
WestTank Farm
w s
Ad
min Warehousing
\ To Aerodrome 5km
File Number: F 369 9
Attachment:
Site Layout
Not to Scale
C
Camp3
Lodge
astTank Farm
Hydrogen Plant
Hydrotreating
Heat
Integration
\Froth Treatment
To South Mine
Mine Maintenance and
Administration Facilities
PllSlse
D
Phase: D
7/25/2019 OHS Worker Fatalities Report
43/43
.
GUY
WIRES
1
OUTER
RING
SUPPORT
COLUMN
TANK
SHELL
TANK SHELL
ELEV TION
INNER
RING
SUPPORT COLUMN
CENTRE SUPPORT
COLUMN
GUYWIRES
F536919
Attachment D
Sketch of
roof
support
structure
Not to scale
OUTER RING
GIRDERS
INNER
RING
GIRDERS