22
OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore Wind Farm 1 st Annual Report JULY 2006 – JUNE 2007 URN NUMBER: 09/P45

OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Embed Size (px)

Citation preview

Page 1: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

OFFSHORE WIND CAPITAL GRANTS SCHEME

Barrow Offshore Wind Farm 1st Annual Report

JULY 2006 – JUNE 2007

URN NUMBER: 09/P45

Page 2: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 2 of 22

EXECUTIVE SUMMARY

The proposal for establishing an offshore wind farm near Barrow originated in 2001

and was made by the then Warwick Offshore Wind Limited, who organised

preliminary permissions, environmental impact statements, draft lease agreements

etc. for an offshore wind farm at Barrow, about 10 km southeast of Barrow-in-

Furness, Cumbria.

In 2003 DONG VE Ltd. took over Warwick Offshore Wind Limited, and a co-

operation agreement was subsequently made with Centrica Plc for establishing

BOW Ltd. on a shared 50%/50% basis with DONG VE Ltd as the lead partner. All

consents and legal obligations for establishment of the wind farm were obtained,

and a £10m capital grant towards the capital costs was obtained from the

Department of Trade and Industry (DTI) Grant reference number

W102/00/00009/00/00.

Tender documents were issued in 2004 for the work under an EPIC contract

including a 5-year O&M phase.

The EPIC contract was awarded to the VKBR Joint Venture with Vestas Celtic and

KBR (Kellogg Brown & Root Ltd.) as the two partners in the joint venture. As major

sub-contractors VKBR used SIF & Smulders Hoboken for steelworks, AREVA for

electrical works and Marine Projects International Ltd. (MPI) for the marine

installation works. Construction works were initiated in May 2005. The original date

for completion of construction was 20 September 2005. However, this was delayed

by 6 months and the actual construction completion date was 30 April 2006.

The original date for commissioning of the wind farm was 20 November 2005 but

the actual commissioning date was 31 May 2006, a delay of 6 months.

It has been agreed that the period of this first annual report should cover July 2006-

June 2007 because sufficient data does not exist for June 2006.

BOW consists of 30 V90 wind turbine generators (WTGs) manufactured by Vestas,

each of 3.0 MW. Then total installed capacity is 90 MW compared with a total

capacity of maximum 108 MW (30 WTGs a 3.6 MW) provided for in the FEPA license

for the construction.

The original eligible project cost was £81.251m, while the current forecast of total

project cost is now £123m. £112.2 million had already been spent by 31 July 2007.

The total DTI Capital Grant obtained for the project was £10million.

The construction cost per MW installed is £1.37 million (forecast) with a grant

contribution of £0.11 million per MW installed. The construction cost per turbine

installed is £4.10 million.

Page 3: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 3 of 22

Site plan

A location map of Barrow Offshore Wind (BOW) is shown below. The 30 WTGs are

placed in 4 rows of alternating 7 and 8 WTGs. The wind farm itself covers an offshore

area of c. 4 x 2.5 km southwest of Barrow-in-Furness, with a distance of 8 km from

the shoreline to the first row of turbines. The general water depth in the area is

about 15 m below Chart Datum.

The alignment of the 27 km long offshore high voltage export cable from the

offshore sub-station to Heysham ashore sub-station is also shown on the location

map below.

The geographical coordinates of each WTG are presented in the table overleaf.

Page 4: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 4 of 22

WTG id Position (WGS84)

Longitude (°, ‘, ‘’) Latitude (°, ‘, ‘’)

1 D8 3 19 45.167 W 53 59 42.878 N

2 D7 3 19 25.036 W 53 59 32.226 N

3 D6 3 19 4.908 W 53 59 21.570 N

4 D5 3 18 44.780 W 53 59 10.914 N

5 D4 3 18 24.653 W 53 59 0.254 N

6 D3 3 18 4.532 W 53 58 49.598 N

7 D2 3 17 44.412 W 53 58 38.939 N

8 D1 3 17 24.299 W 53 58 28.279 N

9 C7 3 19 6.974 W 53 59 56.004 N 10 C6 3 18 46.840 W 53 59 45.348 N

11 C5 3 18 26.712 W 53 59 34.692 N

12 C4 3 18 6.588 W 53 59 24.032 N

13 C3 3 17 46.460 W 53 59 13.376 N

14 C2 3 17 26.340 W 53 59 2.713 N

15 C1 3 17 6.216 W 53 58 52.054 N

16 B8 3 18 48.899 W 54 0 19.786 N

17 B7 3 18 28.768 W 54 0 9.130 N

18 B6 3 18 8.636 W 53 59 58.470 N

19 B5 3 17 48.509 W 53 59 47.810 N

20 B4 3 17 28.381 W 53 59 37.151 N

21 B3 3 17 8.257 W 53 59 26.491 N

22 B2 3 16 48.140 W 53 59 15.828 N

23 B1 3 16 28.024 W 53 59 5.165 N

24 A7 3 18 10.696 W 54 0 32.908 N

25 A6 3 17 50.557 W 54 0 22.248 N

26 A5 3 17 30.426 W 54 0 11.588 N

27 A4 3 17 10.295 W 54 0 0.929 N

28 A3 3 16 50.171 W 53 59 50.266 N

29 A2 3 16 30.050 W 53 59 39.602 N

30 A1 3 16 9.934 W 53 59 28.939 N

Substation 3 16 12.713 W 53 59 15.104 N

Landfall cable 2 54 42.552 W 54 1 27.840 N

Page 5: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 5 of 22

CONSTRUCTION

Overview of the Construction Programme to July 2007

The following table provides an overview of the actual progress of the

procurement and construction works.

2004 2005 2006 2007

3rd qt 4th qt 1st qt nd qt 3rd qt 4th qt 1st qt 2nd qt 3rd qt 4th qt 1st qt 2nd qt 3rd qtID Description J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S

1 Procurement of plant

2 Onshore work

3 Foundation installation

4 Turbine installation

5 Offshore cabling

6 Grid connection

7 Commissioning

8 Wind farm tests9 Outstanding and

remedial EPIC works

Description of Construction Methods

Procurement of plant

The EPIC main contractor VKBR (Vestas Celtic and Kellog Brown) procured and

installed all items necessary for establishment of BOW.

VKBR used SIF & Smulders Hoboken as sub-contractors for the procurement of the

foundation steel works, i.e. for manufacturing of monopiles, transition pieces and J-

tubes and delivery to the load out site at H&W in Belfast. AREVA was engaged as the

sub-contractor for the supply and delivery of all electrical and related components,

i.e. the offshore sub-station at BOW and the onshore sub-station in Heysham.

Vestas Celtic, the one partner of VKBR Joint Venture, supplied the 30 wind turbine

generators.

Onshore preparation

BOW is connected by a high voltage export cable, which includes a 1.5 km long

onshore section, to Heysham electrical sub-station and the national grid. For the

connection of BOW to the national electricity grid a separate onshore sub-station

has been constructed at Heysham sub-station.

Electrical installations for the BOW sub-station in Heysham are all complete, and the

SCADA system is linked up and running.

Page 6: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 6 of 22

Foundation installation

The structure used to support the WTGs is a monopole foundation. This type of

foundation has also been used for other large offshore wind farms. A main steel pile

is driven into the seabed by means of a hydraulic hammer, being operated from a

jack-up vessel (“Resolution”). At 9 out of 30 monopiles it was necessary to drill out

the internal soil plug prior to driving the pile to the final level. The monopiles

installed all have a diameter of 4.750 m and a length of between 49 and 61 m – the

actual pile length was determined on the basis of an assessment of the soil

conditions at each WTG position. All monopiles were driven to a final level, so each

monopole has been installed with a top level of +5.0 m CD (corresponding to Mean

Sea Level (MSL)).

The transition pieces (TPs) with a service platform for operation and maintenance

were then grouted onto the monopole. The transition piece also has a flange for

bolting the wind turbine tower to it. The top level of each TP is +20.25 m CD.

In order to connect the WTGs to the grid, the foundations hold internal J-tubes for

installation of submarine cables. The foundation installation was started in May

2005 and completed in November 2005, using the jack-up vessel, “Resolution”, as

installation vessel. The installation of foundations was delayed for various reasons,

for example, design of grout seal connection, the required time for drilling out the

soil plug for 9 monopiles, and weather downtime.

Offshore turbine installation

After completion of the foundations, the WTGs were then installed and this was

completed on 30 April 2006. Four complete WTG sub-assemblies were transported

on “Resolution” from Belfast to BOW. Three lifts were required for each complete

wind turbine:

– The first lift is the complete tower;

– The second lift is the nacelle with 2 turbine blades (“bunny ears”.); and

– The third lift is the final turbine blade, which finalises the mechanical

installation.

The hub height of the WTGs installed is at a level of +80 m CD, and the rotor

diameter is 90 m.

Offshore cabling

The cables from the WTGs interconnect in 4 rows of 7-8 WTGs, each having one

cable connection to the offshore sub-station, from which the export cable was laid

to the shore at Heysham and onwards to the onshore sub-station, also at Heysham,

where it connects to the onshore grid. For the offshore cabling a special purpose

cable installation vessel was used.

Page 7: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 7 of 22

The initial cable burial depth achieved was not sufficient to requirements at some

locations . After a survey of exact burial depth during the summer 2006, which was

undertaken as part of the post-construction survey as agreed in the FEPA licence,

supplementary jetting of the offshore transmission cable was carried out in March -

April 2007. To date a few remaining sections are still in need of additional protection.

Evaluation of the solutions including the need for reburial are ongoing within the

project

All infield cables were completed on 30 April 2006. Additional burial works (by

jetting) of the inter-array cables were executed in April – May 2007. About half of the

cable ends are in need of additional uraduct protection, and some have free spans

substantially longer than assumed in project design. Diving work for placing this

supplementary protection will be initiated at the end of July 2007.

Grid connection

The grid connection is available and the WTGs are producing power.

First power was produced from WTG D6 on 4 March 2006 and by the end of May

2006 all WTGs were running.

Commissioning & tests

Commissioning and energization of the WTGs was completed by 31 December 2006.

Outstanding and remedial works

A number of outstanding and remedial works related to the EPIC Contract are

currently being undertaken by VKBR and were scheduled for completion in autumn

2007. However, adverse weather over summer 2007 has delayed this work and the

scheduled completion date is now 1 July 2008.

Page 8: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 8 of 22

Wind farm annual operation information

PERFORMANCE REPORTING

Availability

Three measures of availability are used to describe the performance of the wind

farm.

• Technical availability of the wind farm is the actual availability - the time that

the wind turbines are available to generate as a percentage, compared to the

theoretical maximum. There is no allowance for routine or breakdown

maintenance activities or for the effects of external influence.

• Commercial Availability is based on the technical availability but includes

alleviation for requested stops, the loss of the external grid connection and for

weather days.

• Planned availability is the technical availability forecasted for the year,

calculated by taking into account all of the planned work and available recourses,

calculated from the annual work plan. The work plan details all of the routine and

planned works and was developed to ensure that all work was fully assessed,

prioritised and completed within the required timescales.

Output and Capacity Factor

The capacity factor is calculated as a percentage, comparing the amount of

generation produced, with the theoretical maximum generation that would have

been produced if the turbines operated at maximum output during a specified time

period.

The annual budgeted capacity factor is calculated as budgeted production divided

by maximum output for 8760 hours in a normal year.

Page 9: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 9 of 22

Availability (hours %)

Table 1 shows the monthly the recorded technical availability for each WTG at BOW

over the period July 2006 – June 2007.

Table 1 Monthly availability of WTG’s (% of time) July 2006 - June 2007.

The recorded average availability is 67%, while the planned availability of the WTGs

was 90.25%. Thus, actual availability has been significantly lower than planned.

The lower availability after October 2007 is due to a number of WTG faults, mainly

generator bearings and rotor cable faults combined with low access to the WTG

because of high waves.

Furthermore, the wave climate in the winter season 2006-2007 has been dominated

by persistent westerly winds yielding significantly more adverse weather than

statistically expected for long-term conditions. This has to some extent been

unexpected for the company undertaking the operation and maintenance work.

We have not at this stage completed an analysis of down-time. This is currently

scheduled to take place in spring 2008.

Unit Jul-06 Aug Sep Oct Nov Dec Jan-07 Feb Mar Apr May Jun Avg

A1 87 72 26 88 98 100 76 34 66 94 93 80 76

A2 65 92 90 92 44 16 26 92 95 99 31 68 68

A3 47 95 69 53 52 87 29 92 83 91 87 75 72

A4 97 99 82 43 59 51 99 78 21 85 89 97 75

A5 66 99 99 78 100 92 13 88 64 89 15 47 71

A6 90 92 93 83 83 66 12 55 26 0 0 0 50

A7 96 82 39 48 12 23 1 76 92 98 94 98 63

B1 89 88 94 99 29 0 0 60 63 76 0 0 50

B2 78 75 86 99 6 15 1 66 90 96 91 97 67

B3 91 99 62 70 69 62 44 21 13 74 84 98 65

B4 94 97 70 79 49 37 16 42 96 95 99 85 72

B5 95 77 78 98 97 42 67 23 0 1 0 0 48

B6 95 94 98 93 64 40 43 87 100 95 98 98 84

B7 100 100 99 100 68 67 45 51 38 96 62 93 77

B8 79 71 91 99 96 54 0 65 89 97 97 95 78

C1 98 99 97 83 31 38 78 98 94 64 0 0 65

C2 60 78 97 91 98 100 34 85 6 62 95 93 75

C3 96 96 95 95 5 82 54 79 31 96 91 95 76

C4 58 75 99 79 24 50 0 71 96 60 75 95 65

C5 95 94 97 83 100 100 32 90 98 99 50 71 84

C6 95 62 87 89 6 83 5 60 87 98 96 90 71

C7 93 74 86 99 70 51 60 96 95 17 89 91 77

D1 86 73 53 89 67 68 96 81 41 96 85 91 77

D2 98 98 80 94 91 87 5 48 71 31 0 0 58

D3 80 85 79 71 49 56 46 81 56 62 50 41 63

D4 51 56 83 62 31 26 64 87 84 71 75 76 64

D5 60 52 89 85 50 49 97 94 51 95 16 75 68

D6 90 92 77 94 95 98 0 12 0 0 0 0 46

D7 69 95 84 85 84 64 36 90 85 84 69 26 73

D8 98 84 99 77 95 50 0 0 0 0 0 0 42

Avg 83 85 83 83 61 58 36 67 61 71 58 63 67

Page 10: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 10 of 22

Wind speed (m/s)

For the 12-month period, July 2006 – June 2007, the yearly average wind speed was

9.0 m/s at hub height for all turbines. Table 2 also sets out the monthly average wind

speed recorded at each turbine. However, for a number of turbines with limited data

coverage the recorded average wind speed has not been included, because data

communication has been incomplete over long periods due to cable communication

failure and/or WTG repairs.

Table 2 Monthly average wind speed at each turbine July 2006 – June 2007 Wind speed [m/s]

Year: 2006 2007

Parkunit Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr

May Jun Average

A1 6,6 8,3 8,1 9,7 12,1 11,3 13,8 8,2 9,9 6,9 7,8 6,5 9,1

A2 6,7 7,9 8,4 9,6 11,6 10,5 13,5 8,7 10,2 7,0 7,0 6,9 9,0

A3 6,5 8,1 8,3 9,9 11,7 10,4 6,2 8,6 10,1 7,0 7,7 6,5 8,4

A4 6,6 8,0 8,1 9,6 11,6 10,8 13,7 8,1 9,9 6,8 7,7 7,1 9,0

A5 6,5 8,2 8,0 9,0 13,0 8,8 10,0 7,5 7,5 7,4 8,6

A6 6,6 8,3 8,2 9,6 11,6 10,1 10,0 9,9 6,9 7,5 5,1 8,5

A7 7,0 8,2 8,0 10,2 12,2 10,8 13,3 8,8 10,4 7,8 8,3 7,5 9,4

B1 6,6 8,3 8,4 9,6 11,3 11,2 13,7 8,8 10,3 6,7 7,9 9,3

B2 6,7 8,0 8,3 8,7 12,0 10,8 14,4 8,8 10,5 7,0 7,9 7,2 9,2

B3 6,5 8,0 8,3 9,8 11,5 11,2 12,3 4,8 6,8 7,4 7,7 6,9 8,4

B4 6,6 8,2 8,1 9,3 11,7 10,9 8,7 10,4 7,0 7,9 7,0 8,7

B5 6,8 8,3 8,3 9,8 11,8 11,2 13,8 9,5 10,0 6,9 7,5 4,9 9,1

B6 6,6 8,3 8,0 9,4 11,6 10,7 11,4 8,2 10,0 7,1 7,8 7,0 8,8

B7 8,2 9,7 11,6 11,0 14,0 8,6 9,9 7,1 7,6 7,1 9,5

B8 6,9 8,4 8,1 9,6 10,7 10,2 8,4 7,6 8,3 7,6 8,6

C1 6,7 8,3 8,6 9,9 11,3 11,3 14,2 9,0 10,5 6,9 7,9 9,5

C2 6,6 8,1 8,4 9,5 12,2 11,1 13,9 8,8 9,7 7,2 8,1 7,2 9,2

C3 6,6 8,1 8,1 9,1 11,7 8,6 8,7 7,0 7,9 7,0 8,3

C4 6,5 8,1 8,2 9,4 11,1 9,2 10,4 6,8 8,0 7,1 8,5

C5 7,1 8,7 8,6 10,0 12,3 11,5 13,8 9,2 10,8 7,7 8,4 7,4 9,6

C6 6,8 8,2 8,2 10,3 11,5 15,0 10,9 8,7 10,6 7,4 8,2 7,3 9,4

C7 6,6 8,3 8,0 9,3 11,4 10,2 13,6 8,5 9,9 6,7 7,6 6,9 8,9

D1 6,8 8,3 8,4 10,0 12,1 14,5 8,9 9,1 7,2 8,0 7,3 9,1

D2 7,5 8,1 8,2 10,3 12,2 12,7 13,0 8,6 9,2 6,6 7,4 9,4

D3 6,6 8,3 8,4 9,9 11,7 13,9 8,8 10,4 7,1 7,5 6,8 9,0

D4 6,8 8,7 8,6 10,0 11,8 11,1 13,9 9,2 10,6 7,5 8,2 7,2 9,5

D5 7,1 8,3 8,5 9,9 12,1 11,1 13,9 9,1 10,0 7,6 8,9 7,4 9,5

D6 6,8 8,4 7,5 9,6 7,9 11,2 7,2 8,4

D7 6,7 8,6 8,5 10,0 12,4 11,3 13,8 9,0 10,5 7,3 8,0 7,5 9,5

D8 7,0 8,8 8,6 9,9 12,1 12,3 10,8 10,2 7,3 8,5 9,6

Average 6,7 8,3 8,3 9,7 11,7 11,3 13,0 8,8 10,0 7,1 7,9 7,0 9,04

The recorded average wind speed for individual turbines varies from 8.3 – 9.6 m/s

with an overall average annual wind speed of 9.0 m/s. These observed variations

from turbine to turbine can be assigned to the influence of data gaps, spikes in the

data time series and effects of instrument calibration. Natural fluctuations from

Page 11: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 11 of 22

turbine to turbine, as a result of lee effects and impact of rotors running or not

running, are also expected to have some influence.

A wind study undertaken by Tripod Wind Energy in 2006 showed that the long-term

mean wind speed at Shell Flat (at a height of 75m which is representative of Barrow)

is 9.2 m/s. Thus, the average wind speed in the reporting period has more or less

been at the long term mean level.

The wind direction on the wind turbines and at the meteorological station has been

recorded, but unfortunately not been calibrated with respect to recording wind

direction in comparison to the north direction. Therefore, wind roses from the

various turbines are not consistent. For two selected turbines, B6 and C5, the below

figure shows recorded wind roses, illustrating the distribution on wind direction.

The wind roses from the corresponding turbines illustrate that their lack of

calibration has affected the data.

Output (MWh)

Monthly power production July 2006 to June 2007

The annual power production generated at all 30 WTGs during the 12-month period

was 193,784 MWh, which was less than the expected budget of 301.910 MWh. This

represents 64.2% of the actual annual production target.

However, during May 2007 there was a problem with data availability for calculation

of production at each WTG. Table 3 shows that the total production for May 2007

was less than the exported production - 11,795MWh versus 12,793 MWh. It is likely

Page 12: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 12 of 22

that the actual total production was about 13,100 MWh (instead of 11,795 MWh),

which would mean the the total annual production was 195,089 MWh or 64.6% of

budgeted production.

Table 3: The production in MWh for each turbine per month and year WTG 2006 2007 12-month

id Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Period

A1 476 555 131 811 1480 1169 1269 137 768 591 706 413 8.506

A2 179 446 670 838 510 13 284 826 1141 611 170 344 6.032

A3 154 754 492 334 688 731 497 810 938 556 664 399 7.016

A4 511 820 663 390 710 252 1593 519 157 528 662 604 7.412

A5 354 819 776 436 0 136 150 666 534 553 69 193 4.686

A6 427 741 709 966 1073 199 230 601 369 -6 -8 0 5.302

A7 538 460 -2 305 43 79 3 544 1094 678 125 583 4.449

B1 417 647 756 983 226 -5 -8 578 649 439 0 0 4.680

B2 371 506 594 299 -1 0 -2 727 1125 591 709 604 5.523

B3 475 814 385 565 957 483 627 48 91 398 560 586 5.988

B4 497 773 454 701 538 200 301 417 1145 578 758 482 6.844

B5 512 536 547 1035 1450 231 1147 202 -1 -4 0 0 5.655

B6 507 842 787 867 901 226 795 779 1148 616 748 564 8.779

B7 432 429 786 1074 941 197 699 441 274 618 451 600 6.941

B8 481 561 698 1084 715 -1 -3 704 884 681 796 600 7.201

C1 519 833 851 868 252 226 1199 881 1159 330 0 0 7.119

C2 202 534 807 701 1458 1206 488 716 19 361 737 585 7.814

C3 522 823 776 873 -5 -1 63 564 236 600 734 574 5.759

C4 259 666 810 719 220 -2 0 748 1133 337 501 583 5.974

C5 514 826 746 797 1522 1213 461 799 1189 630 349 301 9.348

C6 519 447 608 422 -11 0 84 463 1060 648 765 574 5.580

C7 531 645 633 1082 999 49 963 847 1168 77 744 589 8.327

D1 514 521 189 852 992 231 1527 687 359 662 694 608 7.836

D2 528 573 369 976 1404 961 -11 515 799 163 -2 0 6.275

D3 391 624 468 680 603 32 618 660 501 463 262 257 5.558

D4 219 485 614 674 346 35 978 765 1058 386 601 405 6.568

D5 217 339 687 987 673 335 1640 861 440 632 0 543 7.355

D6 463 782 601 1026 238 0 0 33 -1 -3 0 0 3.139

D7 330 824 715 847 1317 503 449 764 1050 549 0 247 7.595

D8 550 714 853 742 1515 153 -1 -1 0 -3 -1 0 4.521

Sum at WTG 12.610 19.337 18.171 22.935 21.756 8.850 16.041 17.303 20.486 13.261 11.795 11.239 193.783

Exported 12.263 18.843 17.705 22.411 21.195 8.537 15.560 16.892 19.912 12.921 12.793 11.077 190.109

Imported 131 66 69 22 22 64 18 83 31 76 77 91 750

Budget 21.170 20.560 23.120 27.100 26.110 27.350 29.600 31.100 28.500 22.800 22.000 22.500 301.910

The annual exported power production of 190,109 MWh is 2.6% less than the power

that is produced 195,089 MWh. This is mainly due to cable and transformer losses.

Load factor (Capacity factor, %)

Table 4 sets out an overview of the observed capacity factors for the wind farm as a

whole, calculated on the basis of theoretical production as well as the budgeted

production. It is seen below that the actual capacity factor is 24% compared to

budget 37%, which at this stage is only to be assumed to be due to the lower

availability.

Page 13: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 13 of 22

Table 4 Overview of observed capacity factors for BOW

Year Month Period

length

Theoretical

production at

Maximum

rated output

Budget

Production

Exported

Power

Import Gross

Power

Exported

Capacity

factor

(actual)

Capacity

factor

(budget)

Days MWh MWh MWh MWh MWh % %

2006 July 31 66,960 21,170 12,263 131 12,132 18.1% 42.7%

August 31 66,960 20,560 18,843 66 18,777 28.0% 8.7%

September 30 64,800 23,120 17,705 69 17,636 27.2% 23.7%

October 31 66,960 27,100 22,411 22 22,389 33.4% 17.4%

November 30 64,800 26,110 21,195 22 21,173 32.7% 18.9%

December 31 66,960 27,350 8,537 64 8,473 12.7% 69.0%

2007 January 31 66,960 29,600 15,560 18 15,542 23.2% 47.5%

February 28 60,480 31,100 16,892 83 16,809 27.8% 46.0%

March 31 66,960 28,500 19,912 31 19,881 29.7% 30.2%

April 30 64,800 22,800 12,921 76 12,845 19.8% 43.7%

May 31 66,960 22,000 12,793 77 12,716 19.0% 42.2%

June 30 64,800 22,500 11,077 91 10,986 17.0% 51.2%

Total 365 788,400 301,910 190,109 750 189,359 24.0% 37.3%

Operation and maintenance costs

BOW has been operated since 1 January 2007 by Vestas on a 5-year operation and

maintenance contract and so any costs are mainly covered by the O&M Contract

with Vestas. Items such as management, lease payments to Crown Estate, post-

construction monitoring and insurances are paid by BOW outside the contract with

Vestas. A breakdown with approximate figures for the 6 months is presented in

Table 5.

Table 5 Breakdown of approximate O&M Costs in 6-month period (£k)

Jan 2007 – June 2007

O&M offshore facilities incl. service contract

Vestas 1,558

O&M lease and license 102

Environmental Management 297

Other 35

Total O&M Costs 1,992

The accounted costs are somewhat higher but due to an incentive mechanism with

VKBR, some of the costs have been kept out of the above in order to show relevant

O&M costs. The reported costs are only for the last 6 months as this is the only O&M

period in the reported 12 months.

For the 6-month period, January – June 2007, with a total export production of

89,155 MWh this gives an O&M cost of:

• £22,133 per MW installed (for half-year)

• £66,400 per wind turbine (for half-year)

Page 14: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 14 of 22

• £22.34 per MWh produced / exported

Operational issues

Work performed on the wind farm is categorized as planned or unplanned

maintenance.

Planned work

• 3-month Service

– The 3-monthly turbine service started on 14th June 2006 and was completed

on 28th July 2006 as planned.

• 12-month Service

– The 12-monthly turbine service started in June 2007, but has not yet been

completed due to bad weather. It will be finished within 3 months from June

2007.

• Monthly inspections of HV systems on offshore and onshore substation

– The monthly inspections are carried out according to manufacturer’s

recommendation.

• Annual turbine transformer inspection

– During the transformer inspections a fault on a transformer was detected.

The turbine was shut down and the transformer will be replaced in August

2007.

• The annual offshore safety rescue exercise “Cumbrian Breeze” in cooperation

with MCA and RNLI was postponed due to bad weather twice. The exercise will

be undertaken in September 2007.

• Annual inspections of firefighting equipment

• Environmental Surveys as agreed in the site consent Unplanned work

Unplanned work on the turbines in the reporting period has been substantial. Some

of the issues have been minor technical problems, which have been solved by a local

reset or minor work to the turbine.

Other larger issues, which have been dealt with, are:

Page 15: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 15 of 22

• Generator bearings have failed and replaced with a new type.

• Generator rotor cables have been replaced with a new type

• Pitch system has been modified.

In late August 2006 problems with the bearings and rotor cables on the generators

started. Due to bad weather, a lack of spare parts and a lack of certified technicians

to do the repair works the turbines have since had long periods of downtime.

At the same time, problems began on the pitch system and adverse weather has

contributed to some of the turbines having long periods of downtime.

Due to gearbox problems seen on other turbines of the same type, an inspection

process was begun at the start of 2007. These inspections showed that a few

gearboxes were beginning to have similar problems. The EPIC contractor, VKBR,

decided on their own to proactively replace gearboxes before failure.

The replacement schedule started in July 2007 and was completed in early-October

2007. Furthermore, the replacement of gearboxes will have an impact on the

schedule for completion of the outstanding and remedial works under the EPIC

Contract, which has also been delayed by adverse weather during the summer 2007.

Access arrangements

Access to the wind farm is via transfer vessels.

A maximum significant wave height (Hs) limit of 1.5m was enforced in the summer

and autumn 2007 but due to extreme bad weather, BOW tried to work above this

limit by using different vessels for the transfer and can under some circumstances

transfer safely up to a significant wave height of 2m. By autumn 2007 one of the

service vessels was able to operate in significant wave heights of up to 2m.

Page 16: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 16 of 22

The wind farm is situated in an exposed area as demonstrated by the accessibility

figure of 51%. This limited access to the wind farm contributed to the lower

availability of the WTGs.

The monthly number of days with weather downtime, with corresponding

percentage, in the period July 2006 – June 2007 is presented in Table 6. Total

weather days in the reporting period was 178 days giving an average accessibility of

51%. Table 6 Monthly number of days with weather downtime

2006 2007

July Aug Sep Oct Nov Dec Jan Feb Mar April May June

5 17 14 19 25 21 23 15 16 5 8 10

16.1% 54.8% 46.6% 61.3% 83.3% 67.8% 74.2% 53.6% 51.6% 16.6% 25.8% 33.3%

Remote monitoring

The production of the wind farm is monitored round the clock through the SCADA

system. The site operator monitors the wind farm in the daytime, and the operator’s

24h surveillance center in Denmark takes over the monitoring outside normal

working hours. Stopped turbines can be restarted through the SCADA system. BOW

has direct access to Vestas’ SCADA system.

Health and safety

The health and safety standards at BOW are considered to be good and the site has

experienced a low number of accidents although the incidents that have occurred

are considered to be serious.

Through the year the health and safety managers and the BOW site manager have

been working proactively to develop a rigorous approach to health and safety to

prevent accidents.

Accidents and incidents over the reporting period

13 October 2006

Whilst lifting hoses for a generator gear box oil change from the vessel

Amstelestroom up to the nacelle on WTG D5, the deck winch blocked. The chain

failed and dropped, 80% landed in the sea and 20% landed on the deck of the vessel.

There were no injuries to personnel, no damage to any assets and no environmental

releases. All items that landed in the sea have been recovered.

Page 17: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 17 of 22

24 January 2007

Whilst using the davit on the transition piece the shackle pin (50g) on the davit itself

came loose and fell approximately 10m on to the vessel below.

14 February 2007

A Vestas technician badly twisted his right ankle, whilst disembarking from the

offshore provider service vessel. He was treated at hospital and the accident was

reported to RIDDOR (Reporting of Injuries, Diseases and Dangerous Occurrences

Regulations 1995).

12 April 2007

During work on a WTG about 100 litres of oil leaked out and down the outside of the

tower from the nacelle. Some of the oil ran all the way down the tower and dripped

into the sea. Cleaning up was carried out immediately to minimise pollution.

23 May 2007.

An employee sprained his ankle, when he lost his balance stepping down from a

storage locker, resulting in a lost time injury (8 days).

Proactive safety initiatives

Due to the severity of the accidents, a system of issuing awards to personnel

reporting HSE (Health, Safety, Environment) incidents, near miss events and/or HSE

hazard observations has been established by the O&M Contractor, Vestas, in order

to improve the employees’ way of thinking about safety. Initially, the award was

issued as a team award, which had no impact. Then awards were issued to

individuals, and 18 safety observations were made in June 2007, and in July 2007

another 6 observations have been filed to BOW.

Examples of observations:

• Railing on the service boat too low

• Slippery area on the service boat

• Suggestion to install electrical hoist on davit on transition peice • Non-certified

lifting equipments

The observations give the Vestas HSE manager a good platform for identifying

initiatives aiming at improving the HSE environment at BOW.

Alcohol and drug test

Vestas has introduced random drug and alcohol tests on site to ensure that all

employees are fit for work at all times.

Other proactive safety initiatives

• HSE is a priority agenda item at each O&M meeting.

Page 18: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 18 of 22

• No work is executed without method statements and risk assessments being

reviewed and approved by BOW beforehand.

• Regular internal inspections/audits from Vestas HSE manager.

Emergency exercises

On 5 April 2007 Vestas carried out two internal emergency exercises with good

results. The objective of each exercise was to test the communication links between

site personnel and the crew vessel skippers and to highlight potential issues with

regards to lowering a casualty from the nacelle to the vessel using a stretcher. The

two photographs overleaf are from these exercises. During each exercise notes on

the actions of each participant was made together with a time log. Then, the

exercise was concluded with a debriefing session with comments for further

improvement.

Similar exercises will be carried out on a regular basis.

Page 19: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 19 of 22

Future events

An emergency response exercise called Cumbria Breeze is scheduled in September

2007, subject to weather conditions. The HSE Manager of Vestas arranged a

meeting with MCA (Maritime and Coastguard Agency) in July 2007 to plan the

exercise. The emergency response exercise is a real time, Search and Rescue

Exercise. This includes HM Coastguard, Royal National Lifeboat Institution and

Cumbria Ambulance Service.

Page 20: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 20 of 22

Documentation

For each operation to be executed in BOW it is necessary that BOW prior to the start

of the operation has commented and approved the method statement and risk

assessment. It is desirable that the contractor would be more proactive in revising

and presenting risk assessments and method statements when introducing new

operations and this issue is on the agenda at every quarterly HSE meeting.

Environmental monitoring

Seabed and Scour monitoring

Monitoring of scour around turbines and along the export cable takes place in

accordance with the FEPA Licence requirement, and is undertaken at six-monthly

intervals.

The first post-construction scour monitoring survey was undertaken in September

/October 2006 and covered all 30 turbines foundations and the export cable. This

survey indicated that scour was present around the turbines to varying extent. The

extension of the scour was not larger than expected. Furthermore, depressions

created from the jack-up vessel could be identified at some of locations. The survey

of the export cable identified that it was exposed in some sections.

The second post-construction seabed and scour monitoring survey was undertaken

in April 2007. This survey included 9 turbines and the export cable. This survey

indicated that the scour at some locations has been partially in-filled by natural

sedimentation processes and that the area of scour is dynamic in extent.

Furthermore, the data indicated that the sea bed depressions created by the jack-up

vessels used for installation of the wind turbines were backfilled by natural

sedimentation processes.

The April 2007 survey of the export cable identified some exposed sections of the

export cable. Further work has been undertaken in May 2007 at exposed sections

along the export cable in order to bury these sections. The collected data is now

evaluated and the need for further work on the cable will be considered.

Fishery monitoring

The first post-construction fishery survey was carried out in December 2006, and the

second post-construction fishery survey was carried out in March 2007. A third post-

construction fishery survey is planned for October 2007. The survey results were

analysed and reported and will be included in the annual report to the Licence

Authority in November 2007. A comparative analysis between pre-construction and

post-construction data will be included in the annual report to the Licence Authority

in autumn 2008.

Page 21: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 21 of 22

Benthic monitoring

An inter-tidal and sub-tidal benthic survey was undertaken in March 2007 as a part

of the post-construction monitoring programme required in the FEPA Licence. Grab

samples collected from the sea bed at the development site (wind farm and cable

route) and reference sites have been analysed and reported in June 2007. A

comparative analysis between pre-construction and post-construction data is to be

undertaken in August 2007 and will be reported in the first year post-construction

monitoring report.

Noise monitoring

An underwater operational noise survey was undertaken in January - February 2007.

The main conclusions of the report were that:

• The levels of underwater noise measured throughout the survey were

sufficiently low that damage to marine species will not occur. The underwater

noise from the operational wind farm is unlikely to cause a behavioural

(avoidance) response in marine animals in the region.

• The marginal increase in very low frequency noise around individual turbines is

likely to be due to tidal flow around turbine structure. An increase in noise in and

around the turbine array is likely to be due to increased wind and wave noise

interacting with the turbine structures.

• The increase in noise is within the typical variation that would be expected in

shallow water regions due to weather, sea state and tidal flow conditions.

The survey results were included in the annual report to the Licence Authority in

November 2007.

Ornithology

Boat-based and aerial bird survey data was collected at the wind farm and in a

reference area during the period July 2006 - July 2007. In January 2007 BOW and

Natural England agreed on a post-construction monitoring programme including

boat-based and aerial surveys.

Boat-based surveys have been undertaken in August 2006, October 2006, May 2007

and July 2007. Aerial surveys have been undertaken in October 2006 and March

2007. Data will be analysed and reported in the annual report to Licence Authority in

November 2007 in relation to the monitoring objectives set up in the FEPA Licence

and as agreed with Natural England.

Current measurements

According to the FEPA Licence a post-construction survey of the current profile

around a monopile shall be undertaken and used to verify the numerical modelling

used in the Environmental Statement. The current measurements were undertaken

with an ADCP (Acoustic Doppler Current Profiler) around 3 monopiles. The main

Page 22: OFFSHORE WIND CAPITAL GRANTS SCHEME Barrow Offshore

Page 22 of 22

conclusions of the survey indicated that the suggestions based on the numerical

modelling were not unreasonable. The survey results will be included in the annual

report to licence Authority in November 2007.

Annual reporting of monitoring results

The annual report covering monitoring during construction was submitted to the

Licence Authority in November 2006. The first year post-construction monitoring

was be summarised in a report and submitted to the Licence Authority in November

2007. The report will include the technical reports.

Public relations

As Barrow was completed journalists and the Secretary of State for Trade &

Industry, Alistair Darling, visited the wind farm on 14 July 2006. To coincide with this

visit, DONG Energy and Centrica issued a press release announcing the event and an

explanation of the importance of the wind farm. In the press release, Alistair Darling

said, "... The Barrow wind farm is a further signal of the energy industry continuing

to invest in green projects, which can enhance future security of supply, as well as

helping reduce carbon emissions."

On 25 September Centrica and DONG Energy declared the wind farm officially open

and celebrated this by sponsoring the local Walney School in their efforts to win

specialist engineering status. The sponsorship and the official opening of the wind

farm were also announced through a press event, where journalists from the UK and

Denmark were invited to visit the school as well as the wind farm. This event was

also marked by a press release issued by BOW.

This report was prepared by Dong Energy A/S.

For further information on the project contact: [email protected]

For further information on the Capital Grant Scheme contact:

Nick Beale at [email protected]

Tel 0870 190 6042

Printed in the UK on recycled paper containing a minimum of 75% post consumer waste.

First published May 2008. Department of Business Enterprise and Regulatory Reform. www.berr.gov.uk

©Crown Copyright. URN 09/P45