Upload
truongtuong
View
218
Download
5
Embed Size (px)
Citation preview
Offshore construction opportunities and challenges
28th of May 2015
Bruno Ferreol
2 Page 3-Jun-15
Challenges are at the heart of our industry
3 Page 3-Jun-15
US shales are threatening the economics of Ultra Deepwater projects
Offshore shallow water
Onshore Middle East
Extra Heavy Oil
Deepwater
Onshore Russia
Onshore Rest of World
Ultra Deepwater
American Shale
Oil Sands
20
40
60
0
80
100
120
0 20 40 60 80 100
The price of oil in US$ per barrel
Barrels of oil produced per day
Source: IHS Energy
Mid term market price?
Industry effort -30%
US shales are the new swing producers
4 Page 3-Jun-15
Over the past decade, project costs have more than doubled
SURF 2020 FOCUS
Cost drivers
Deepwater Project - 2000
Supply chain / market
Complexity and spec. choice Regulations
Deepwater Project - 2012
30-40%
45-55%
10-15%
GOM project development cost comparison, 2000 vs. 2012*
• Main drivers of the inflation in project costs are complexity and technological choices
* Source: Shell OTC 2015, McKinsey & Co.
Rig rate Material cost Technical/Construction Labour Supply Chain supply / demand
Facility and subsea Well equipment and technical design Water and well depth
Post-Macondo regulations
5 Page 3-Jun-15
“Never let a good crisis go to waste”
Winston Churchill
6 Page 3-Jun-15
Reducing our cost base
7 Page 3-Jun-15
Typical Deep Offshore EPCI cost breakdown structure
TYPICAL LARGE EPCI
PMT 5%
ENGINEERING 10%
PROCUREMENT 40%
FABRICATION 10%
OFFSHORE OPS 35%
Internal 30%
External 70%
The cost challenge goes well beyond the 1st ring of offshore contractors
8 Page 3-Jun-15
Curbing the inflation of PMT & Engineering manhours
• LEAN Engineering – Developed by the automotive and
aerospace industries in the late 70’s
– Two main concepts: avoid waste (redo, iterations, …) and focus on « value for client »
• Maintain high risk control while cutting in “non value” adding tasks
• Maintain high end expertise
• In progress with some clients on a project by project basis
– Need a more systematic approach
Louisiana Offshore Oil Port Porject Abandonment procedure
ETPM 1601, 1979
9 Page 3-Jun-15
Accelerating the path of innovation: Electrical Traced Heated PIP example
• Electrical Traced Heated PIP combines ITP high performance thermal insulation with a resistive electrical heating system laid between the insulation and inner pipe.
• Technology enabling recovery of “complex” fluids, long reach tie-backs, simplified field architecture, enhanced fluid preservation, reduced footprint on topside
CAPEX and OPEX reduction
10 Page 3-Jun-15
Bringing North Sea technology to other regions: BUNDLES
• Towed pipeline bundles are multi flowline, control and injection lines encased within a larger carrier pipe between two manifold (towhead) structures. The manifold structures range from simple valve structures to complex subsea processing structures.
• Concept develop in 80’s and continuously upgraded over the 70 Projects carried out, predominantly in the North Sea
• Technology providing cost efficient alternative for Field Development and Architecture, ability to include monitoring and subsea Processing, High thermal performance, limited offshore installation spread
Deeper waters, other areas
11 Page 3-Jun-15
Subsea 7 live projects – Leveraging on experience to bring value at concept stage
12 Page 3-Jun-15
Restructuring Client/Supplier relationship
13 Page 3-Jun-15
Current contracting model is unable to converge towards the cheapest solutions
• Supply chain process aims at minimising costs through:
– Maximise commonality to maximise competition
– Package “standard” interfaces
– Competitive bidding per package
• Process does not work anymore:
– Unrealistic project costs and schedules
– Under-optimised concepts
– Long & costly post tender clarifications (>12months)
– Major modifications to concepts required during tender process
– Unable to capture full range of opportunities because of rigid packages
Concept selection
FEED by 3rd party Eng
Competitive Tender
FID
Concept selection
FEED by 3rd party Eng
Competitive Tender FID
14 Page 3-Jun-15
Current trend: involve SURF contractor at the earliest and open door to most innovative concepts
• Major shift over the past 12 months: Clients engaging with SURF contractor at concept stage
– Fully optimised solutions (advanced technology, expertise, best combination of design/asset capabilities, …)
– Shorter time to 1st oil
– Cheaper projects
Concept selection
Design competition
FID
SURF Contractor input
Concept selection
FEED by 3rd party Eng
Competitive Tender
FID
15 Page 3-Jun-15
HSE: how will it look like in 20 years?
16 Page 3-Jun-15
Safety perception and Safety standards
17 Page 3-Jun-15
The Famous
100+ people killed during construction, but it hasn’t
caved in – Brunel is famous.
Isambard Kingdom
Brunel – the most
famous of all British
Engineers
The famous tunnel
at Box, on the GWR
18 Page 3-Jun-15
Pipeline Installation – Safety
19 Page 3-Jun-15
Pipeline Installation – Safety
20 Page 3-Jun-15
Safety standards 30 years after
• What will be our safety standards in 10, 20, 30 years?
• What are the implications in terms of risk identification, quantification and acceptability?
• What technology will we develop?
21 Page 3-Jun-15