October 4-5, Scope Engineer, procure and install a horizontal Stochastic Cooler and associated equipment in the RHIC Blue and Yellow rings. –The major procurements include amplifiers, electronics and vacuum vessel assemblies. Each ring contains: –2 vacuum vessels with 8 cavities per vessel –1 pickup
Citation preview
October 4-5, 20101
Status of ARRA funded AIPs
Stochastic Cooling
Alex Zaltsman
October 4, 2010
Stochastic Cooling cost and schedule
October 4-5, 20102
Outline• Scope• Funding and Costs• Major Milestones• Management and Reporting• Bumps in the Road• Safety• From here to completion
October 4-5, 20103
Scope
• Engineer, procure and install a horizontal Stochastic Cooler and associated equipment in the RHIC Blue and Yellow rings.– The major procurements include amplifiers, electronics and
vacuum vessel assemblies.
• Each ring contains:– 2 vacuum vessels with 8 cavities per vessel– 1 pickup
October 4-5, 20104
Funding and Costs
Funds Labor Material commitments Fundsreceived cost cost remaining
4,000 519 2,154 1,327 -
as of August 31, 2010
Burdened K$Horizontal Stochastic
October 4-5, 20105
Major Milestones
Stochastic Cooling Plane Milestonesplanned
mo/yractual mo/yr
ARRA milestones
Obligate Funding to BNL Jun-09 Jun-09A xStart Design Jun-09 Jun-09A xBegin Purchasing Jul-09 Aug-09A xStart Fabrication May-10 Feb-10A xWater Chillers available for Installation May-10 Apr-10A -50% of cavities tested and sent for plating Sep-10 Jun-10A -Begin Construction Nov-10 Jul-10A xStart Assembly of Cavity and Tanks Mar-11 xCables 50% complete Jun-11 -Begin Installation Aug-11 xStart Commissioning Nov-11 xProject Complete May-12 x
Currently ahead of planned schedule
The possibility still exists for installation of one pickup before RHIC start-up.
October 4-5, 20106
Management and Reporting
• Internally• Weekly and Monthly Budget and Expense reports• Monthly labor reports (hours charged by individuals)• Open purchase orders/purchase requisitions report
(available daily)
• Reporting to DOE• Execution Plan• Monthly ARRA milestone progress reports• Monthly teleconferences• Quarterly reports• Quarterly teleconferences
October 4-5, 20107
Bumps in the road…
Our design requires a large rectangular vacuum seal for the kicker tanks which we were trying to develop with outside vendors but were unsuccessful. This delayed us by 3-4 months, and the final resolution was to weld the tanks.
October 4-5, 20108
Safety
• ARRA AIPs are fully integrated into the C-AD Safety organization and subject to the same standards as RHIC– ESSH&Q Division and Safety Committees– Procedures and safe practices– Trained supervisors and employees– All work has been done safely. No safety occurrences on the
project.
October 4-5, 20109
Safety• Completed Safety milestones (on Indico)
– NEPA review– Design Review questionnaire– Preliminary Hazard Screening Report
• Planned Safety milestones/reviews:– Accelerator Systems Safety Review Committee
(ASSRC)
– Radiation Safety Committee (RSC)
October 4-5, 201010
from here to completion…
• Current and ongoing– Finish assembly– Testing– Installation Planning
• Installation– No major risks are foreseen for the installation
during the summer shutdown 2011.