October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule

October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule

Embed Size (px)

DESCRIPTION

October 4-5, Scope Engineer, procure and install a horizontal Stochastic Cooler and associated equipment in the RHIC Blue and Yellow rings. –The major procurements include amplifiers, electronics and vacuum vessel assemblies. Each ring contains: –2 vacuum vessels with 8 cavities per vessel –1 pickup

Citation preview

Page 1: October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule

October 4-5, 20101

Status of ARRA funded AIPs

Stochastic Cooling

Alex Zaltsman

October 4, 2010

Stochastic Cooling cost and schedule

Page 2: October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule

October 4-5, 20102

Outline• Scope• Funding and Costs• Major Milestones• Management and Reporting• Bumps in the Road• Safety• From here to completion

Page 3: October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule

October 4-5, 20103

Scope

• Engineer, procure and install a horizontal Stochastic Cooler and associated equipment in the RHIC Blue and Yellow rings.– The major procurements include amplifiers, electronics and

vacuum vessel assemblies.

• Each ring contains:– 2 vacuum vessels with 8 cavities per vessel– 1 pickup

Page 4: October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule

October 4-5, 20104

Funding and Costs

Funds Labor Material commitments Fundsreceived cost cost remaining

4,000 519 2,154 1,327 -

as of August 31, 2010

Burdened K$Horizontal Stochastic

Page 5: October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule

October 4-5, 20105

Major Milestones

Stochastic Cooling Plane Milestonesplanned

mo/yractual mo/yr

ARRA milestones

Obligate Funding to BNL Jun-09 Jun-09A xStart Design Jun-09 Jun-09A xBegin Purchasing Jul-09 Aug-09A xStart Fabrication May-10 Feb-10A xWater Chillers available for Installation May-10 Apr-10A -50% of cavities tested and sent for plating Sep-10 Jun-10A -Begin Construction Nov-10 Jul-10A xStart Assembly of Cavity and Tanks Mar-11 xCables 50% complete Jun-11 -Begin Installation Aug-11 xStart Commissioning Nov-11 xProject Complete May-12 x

Currently ahead of planned schedule

The possibility still exists for installation of one pickup before RHIC start-up.

Page 6: October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule

October 4-5, 20106

Management and Reporting

• Internally• Weekly and Monthly Budget and Expense reports• Monthly labor reports (hours charged by individuals)• Open purchase orders/purchase requisitions report

(available daily)

• Reporting to DOE• Execution Plan• Monthly ARRA milestone progress reports• Monthly teleconferences• Quarterly reports• Quarterly teleconferences

Page 7: October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule

October 4-5, 20107

Bumps in the road…

Our design requires a large rectangular vacuum seal for the kicker tanks which we were trying to develop with outside vendors but were unsuccessful. This delayed us by 3-4 months, and the final resolution was to weld the tanks.

Page 8: October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule

October 4-5, 20108

Safety

• ARRA AIPs are fully integrated into the C-AD Safety organization and subject to the same standards as RHIC– ESSH&Q Division and Safety Committees– Procedures and safe practices– Trained supervisors and employees– All work has been done safely. No safety occurrences on the

project.

Page 9: October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule

October 4-5, 20109

Safety• Completed Safety milestones (on Indico)

– NEPA review– Design Review questionnaire– Preliminary Hazard Screening Report

• Planned Safety milestones/reviews:– Accelerator Systems Safety Review Committee

(ASSRC)

– Radiation Safety Committee (RSC)

Page 10: October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule

October 4-5, 201010

from here to completion…

• Current and ongoing– Finish assembly– Testing– Installation Planning

• Installation– No major risks are foreseen for the installation

during the summer shutdown 2011.