October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab FNAL Oversight Panel October 24, 2000

October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

Embed Size (px)

Citation preview

Page 1: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 1

US CMS Software and Computing

Milestones and Funding Profiles

Matthias KasemannFermilab

FNAL Oversight Panel October 24, 2000

Page 2: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 2

CMS planning at LHCC review October 2000

Page 3: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 3

US CMS S&C schedule adapted to LHCUS CMS S&C schedule adapted to LHCConstraints for updated S&C schedule:

Working CMS detector by mid-2005LHC pilot run in Fall 2005, few weeks of luminosity runningComplete detector and start LHC running in Spring 2006

Lessons learned from other experiments:Pilot running: for detector as well as for

computing and analysisFall 2005

Finish facilities before physics dataearly FY06

CMS Software schedule not changed

Adapt schedule: delay start of implementation of facilitiesby 12 months (03->04)

9 month delay in startup of LHC luminosity running 3 month: US FY05 ends in 9/2005

Page 4: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 4

Received draft funding profile from DOE: 5/30/2000 Assume NSF funding profile after discussion

This is a BIG step for S&C projects: guidance to allow detailed and solid planning

We want to continue to work with funding agencies to make S&C for CMS a success

profit for science from investment into LHC program

US CMS S&C funding profileUS CMS S&C funding profile

Page 5: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 5

FY99 FY00 FY01 FY02 FY03 FY04 FY05 Total FY06CAS FTE request 7 9 10 11 12 13 13 13CAS FTE Contingency 0 0 1 1 3 3 3 3Management reserve 1 1 1.1 1.1 1.25 1.25 1.25 1.25DOE Escalation Index 1.02 1.02 1.03 1.03 1.03 1.03 1.03 1.03CAS [$M] 1.00 1.38 1.57 1.77 1.99 2.22 2.28 12.22 2.35CAS Mgmt res.[$M] 0.00 0.00 0.16 0.16 0.50 0.52 0.53 1.87 0.55CAS Total [$M] 1.00 1.38 1.73 1.94 2.49 2.74 2.82 14.09 2.90

US CMS Softw are and Com puting Project

CAS: People

0.00

0.50

1.00

1.50

2.00

2.50

3.00

3.50

FY99 FY00 FY01 FY02 FY03 FY04 FY05

FY99 FY00 FY01 FY02 FY03 FY04 FY05 Total FY06CAS FTE request 7 9 10 11 12 13 13 13CAS FTE Contingency 0 0 1 1 3 3 3 3Management reserve 1 1 1.1 1.1 1.25 1.25 1.25 1.25DOE Escalation Index 1.02 1.02 1.03 1.03 1.03 1.03 1.03 1.03CAS [$M] 1.00 1.38 1.57 1.77 1.99 2.22 2.28 12.22 2.35CAS Mgmt res.[$M] 0.00 0.00 0.16 0.16 0.50 0.52 0.53 1.87 0.55CAS Total [$M] 1.00 1.38 1.73 1.94 2.49 2.74 2.82 14.09 2.90

US CMS Softw are and Com puting Project

CAS: People

0.00

0.50

1.00

1.50

2.00

2.50

3.00

3.50

FY99 FY00 FY01 FY02 FY03 FY04 FY05

CAS Project: Scope + FundingCAS Project: Scope + FundingUS CMS CAS personnel contributions to CMS Core software:

determined by canonical scaling from CMS top-level resource-loaded WBS for Software

Add ~25% for additional US-specific software supportProposal for CAS personnel contingency:

add a fixed percentage to base cost as management reserve e.g. 10% for FY 2001 and 2002 25% for FY 2003 and beyond

All this is unchanged due to the updated schedule.

Page 6: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 6

US CMS S&C profile: January 00 versionUS CMS S&C profile: January 00 version

now

US CMS Software and Computing Project

UF: Hardware

UF: People

CAS: People

Tier2: People

Tier2: Hardware

1.152.075

2 2.5

12.5

9.5

5.5

3.53

4

5.5

8.5

13.5

17.5

0.00

2.00

4.00

6.00

8.00

10.00

12.00

14.00

16.00

18.00

20.00

FY2000 FY2001 FY2002 FY2003 FY2004 FY2005Fiscal Year

$[M]

Operations / Year

DRAFT: DOE

DOE + NSF profile

DRAFT: DOE+NSF

04: 19 month

03: 18 month

05: 19 month

USCMS S&C expected: 40%-25% of UF people contribution from FNAL, not shown here

Page 7: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 7

Schedule for US-CMS S&C ProjectSchedule for US-CMS S&C Project

In order to match the proposed funding profile from DOE/NSF more closely as well as the LHC schedule, we have stretched out the CMS Software and Computing Project Schedule.

User facilities: Now – end FY2003: R&D phase FY2004-FY2006: Implementation Phase FY2007 and onwards: Operations Phase

This required a new hardware cost estimate and resource loaded WBS.

Page 8: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 8

UF: Updated scheduleUF: Updated scheduleModified:

Stretch hardware installation on UF and Tier2 Reevaluate UF facility manpower needs

Very similar results

Tier 1 and Tier 2 center scope are: proposed by MONARC, defined by CMS Computing Model Reviewed by CERN Hoffmann Review

Hardware requirements need to remain flexible to respond to advances in technology

in storage: capacity, cost, => disk vs. tape, store vs. recalculate

in networking: bandwidth, latency, => local vs. remote data storage and access, replication

in computing: speed, cost, => servers vs. commodity type computing

results of review and planning process at CERN results of Grid R&D, availability of integrated ‘middleware’ software

=> Serious planning requires contingency here!

Page 9: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 9

Hardware Costing For UF w/o T2Hardware Costing For UF w/o T2

Cost of User Facility Hardware by SubCategory

0

200400

600

8001000

1200

14001600

1800

2001 2002 2003 2004 2005 2006 2007

Year

Co

st

in T

ho

us

and

of

$

FNAL based computing

Const. Phase Computing

S&C R&D

Networking for Tier 1

Ops and Infrastructure

System and User Support

Tier 1 Regional Center

Hardware costing for User Facilities, excluding Tier 2

Page 10: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 10

Hardware Costing For UFHardware Costing For UF

Cost of User Facility Hardware by SubCategory

0

1000

2000

3000

4000

5000

2001 2002 2003 2004 2005 2006 2007

Year

Co

st

in T

ho

us

an

d o

f $

Networking for Tier 2

Tier 2 Regional Centers

FNAL based computing

Const. Phase Computing

S&C R&D

Networking for Tier 1

Ops and Infrastructure

System and User Support

Tier 1 Regional Center

Hardware costing for User Facilities, INCLUDING Tier 2 from GriPhyN

Page 11: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 11

User Facility Personnel CostsUser Facility Personnel Costs

User Facility Personnel Costs

0100020003000400050006000700080009000

10000

2001 2002 2003 2004 2005 2006 2007

Management Reserve

UF Personnel Costs

Page 12: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 12

Total User Facility CostsTotal User Facility Costs

Total User Facility Costs

0

2000

4000

6000

8000

10000

12000

14000

16000

2001 2002 2003 2004 2005 2006 2007

Year

Co

st i

n T

ho

usa

nd

s o

f $

Personnel Costs

Hardware Costs

Page 13: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 13

Total S&C Costs

2 2.53.5

5.5

9.5

34

5.5

12.512.5

8.5

13.5

17.517.5

0

5

10

15

20

2001 2002 2003 2004 2005 2006 2007Year

Co

st i

n $

M

UF Hardware

UF personnel

Management reserve CAS Personnel

DOE funding

DOE + NSF

Total S&C Project costTotal S&C Project cost

Management reserve: 10% on manpower

Page 14: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 14

DOE funding vs. UF(Tier 1) + 2/3 CASDOE funding vs. UF(Tier 1) + 2/3 CASUF (Tier 1) cost + 2/3 CAS

2 2.53.5

5.5

12.5 12.5

9.5

0

2

4

6

8

10

12

14

2001 2002 2003 2004 2005 2006 2007Year

Co

st

in $

M

Tier1 Hardware

Tier1 personnel

Management reserve2/3 CAS Personnel

DOE funding

Management reserve: 10% on manpower

Page 15: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 15

2001 2002 2003 2004 2005 2006 2007

1.1 Tier 1 Regional Center 13 17 20 18 1.2 System and User Support 1.3 2.25 3 3 5 4.5 4.5 1.3 Operations and Infrastructure 1 1.25 1.25 3 5 4.5 4.5 1.4 Tier 2 RCs 2.5 3.5 4 5 6.5 7.5 7.5 1.5 Networking 0.5 1 2 2.5 3 3 3 1.6 Computing and

Software R&D 3 4 4.5 1.4 0.6 0.6 0.6 1.7 Construction Phase 2 2 2 0.25

Computing 1.8 Support of FNAL 0.4 1.4 1 2.6 2.25 2 2

based Computing

User Facilities (total) 10 15 18 30 37 43 41 (Without T2 Personnel) 7.5 11.5 14 25 30 36 34

Full time staff working on User Facilities tasks: (technicians, support staff, computing professionals)

From “Bottoms Up” ApproachFrom “Bottoms Up” Approach

Page 16: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 16

NSF funding vs. UF(Tier 2) + 1/3 CASNSF funding vs. UF(Tier 2) + 1/3 CASUF (Tier 2) + 1/3 CAS cost

2

3

11.5

4

55

0

1

2

3

4

5

6

7

2001 2002 2003 2004 2005 2006 2007Year

Co

st i

n $

M

Tier2 Hardware

Tier2 Personnel1/3 CAS Personnel

NSF funding

Tier2 Networking

•Tier 2 center cost:• start of Prototype centers spread over FY01-04• final implementation stretched over 2-3 years (FY04-06)• dominated by potential networking cost

Page 17: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 17

Funding - RequestFunding - Request

-5000

-4000

-3000

-2000

-1000

0

1000

2000

2001 2002 2003 2004 2005 2006 2007

Th

ou

san

ds

Total DOE part NSF part

Page 18: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 18

Evaluation of ProfilesEvaluation of Profiles The US CMS S&C project is managed and coordinated by the L1 PM,

who carries budget authority Funding shared differently for the two subprojects:

Tier1 center funded by DOE Tier2 centers expected to be funded by NSF CAS traditionally funded 2/3 DOE + 1/3 NSF

NSF part: under-funded by ~$1M/year Tier 2 center cost dominated by networking cost Uncertainty in networking cost for Tier 2 sites

Site Networking connectivity must be argument in selection process Leveraging from University sites must contribute to cost of Tier2

centers DOE part:

Dominated by Tier 1 personnel cost Leveraging from FNAL infrastructure?

Part of WBS 1.3: Operations & Infrastructure Part of WBS 1.5: Networking: LAN, WAN, monitoring, security Part of WBS 1.8: Desktop systems, Support, Remote Control Room

Page 19: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 19

Conclusion (1)Conclusion (1)The project needs to have a project office with:

Two project engineers supporting the L1 PM coordinating the activities at all levels Overseeing purchases Establishing MoU’s, SOW’s Preparing for Reviews Tracking budget Tracking the project progress

Not yet added to the previous numbers

Need to have management reserve / contingency for manpower (10% proposed, shown in the graphs)

The back loaded funding profile creates big problems now, additional help needed.

It is essential that we keep flexibility to use funds where needed most; only in this way are we able to take advantage of matching funds.

Page 20: October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab

October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann 20

Profile recognizes needs for operating S&C Profiles heavily back-loaded towards 2005 Result:

Funding does not allow to finish R&D and implementation for 2006 Very hard to reach milestones:

Deliverables for Core Application Software Contributions of US share to

Mock Data Challenges, production exercises for trigger and physics studies Test beam analyses for detector optimization

Preliminary analysis: implementation ready by 2007

Severe impact for US based CMS data analysis: Will not be able to fully contribute to CMS analysis Will compromise readiness of CMS and US CMS for Physics Disadvantage can only slowly be corrected because of operational

needs

SummarySummary