32
October 2009 Construction Progress

October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

Embed Size (px)

Citation preview

Page 1: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

October 2009

Construction Progress

Page 2: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

University City School District

Bond Wolfe Architects – architect

McCarthy Construction – construction manager• Barbara Jordan Elementary

Ameresco Engineering – performance contractor• Flynn Park Elementary School• Jackson Park Elementary School• Brittany Woods Middle School• High School

Page 3: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara
Page 4: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

Barbara C. Jordan Elementary

Barbara C. Jordan Elementary

Page 5: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

• BP-A ENVIRONMENTAL OPERATIONS, INC.– WC-1 HAZARDOUS WASTE ABATEMENT - 100%

• BP-B SPIRTAS WRECKING COMPANY– WC-2 BUILDING DEMOLITION - 90%

• BP-C KUESEL– WC-3 EARTHWORK (TREE PROTECTION) - 1%

– WC-4 SITE UTILITIES - 1%

CONSTRUCTION ACTIVITY TO DATE

• BP-A ENVIRONMENTAL OPERATIONS, INC.

– WC-1 HAZARDOUS WASTE ABATEMENT - 100%

• BP-B SPIRTAS WRECKING COMPANY

– WC-2 BUILDING DEMOLITION - 100%

• BP-C KUESEL

– WC-3 EARTHWORK (TREE PROTECTION) - 1%

– WC-4 SITE UTILITIES - 1%

Page 6: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

FUTURE ACTIVITIES• BP-D

– WC-5 CONCRETE - 7 BIDS• Awarded to Wilson Concrete• MBE Commitment – 15%• WBE Commitment – 8%• Minority Workforce Commitment – 10%

– WC-6 STEEL - 3 BIDS• Awarded to Ben Hur Steel • MBE Commitment – 15%• WBE Commitment – 5%• Minority Workforce Commitment – 10%

• BP-E and F– WC-7 thru WC-23

• Bidding December and January• Completes all work

Page 7: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

MBE/WBE PARTICIPATION

• BP-A ENVIRONMENTAL OPERATIONS, INC.

– MBE Participation - 29%

– WBE Participation - 0%

– Minority Workforce - 32%

• BP-B SPIRTAS WRECKING COMPANY

– MBE Participation -15%

– WBE Participation - 10%

– Minority Workforce - 22%

Page 8: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

• Master Budget Set at $13M• Current Post DD Estimate $13.3M• $200K savings on Concrete and Steel Recent Bidding• Favorable Market Conditions• Includes:

– Sustainable design– LEED Certification– Desired Program Space

BUDGET UPDATE

Page 9: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara
Page 10: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara
Page 11: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara
Page 12: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara
Page 13: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara
Page 14: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara
Page 15: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

University City High School• Switchback Ramp• Gym Restrooms• Cafeteria Restrooms• Entry/Auditorium• Exterior• ADA Parking• Third Floor Science Wing Renovation

Flynn Park

Brittany Woods

Jackson Park

Page 16: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

Maplewood-Richmond Heights School District

Ameresco Engineering – performance contractor• Flynn Park Elementary School• Jackson Park Elementary School• Brittany Woods Middle School• High School

Page 17: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

University City High School - Switchback RampWork to Date:• Complete

Page 18: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

University City High School - Gym RestroomsWork to date:• Demo is complete• New mechanical duct and exhaust fans are installed• All plumbing rough in is complete• Wall are blocked and tiled• Walls are tiled, ceiling is complete• Desco floor is installed• Door frames are set• Paint is complete• Plumbing trim started 10-15-09• Toilet partitions are complete

University City High School - Gym RestroomsFuture work over the next three weeks:• Doors, hardware, toilet accessories• Bradley sink• Electrical trim out• Punch list for a few complete items

Page 19: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara
Page 20: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

University City High School – Cafeteria RestroomsWork to date:• Abatement and demo is complete• All major mechanical, electrical and plumbing relocations are complete, including electrical feeder relocation• New mechanical duct and exhaust fans are installed• Plumbing underground rough-in is complete• Hydronic/chilled water piping has been rerouted• Trenches have been backfilled and concrete floor has been poured back• Plumbing rough in is complete• Wall are blocked and tiled• Desco floor is installed• Ceiling is installed• Door frames are set• Painting is complete•Plumbing trim began 10-21-09

University City High School – Cafeteria RestroomsFuture work over the next three weeks: • Excavate and construct elevator pit, including sump pump installation• Electrical rough in will wrap up• Doors, frames, hardware, toilet accessories• Electrical trim out• Plumbing and electrical trim out

Page 21: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara
Page 22: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

University City High School – Entry/AuditoriumWork to date:• Wood is cleaned up and sealed, new paint, terrazzo repair, stone cleaning and temporary interior lights

University City High School – Entry/AuditoriumFuture work over the next several weeks:•Lobby lights will continue to be restored and look to be installed by the end of the month•Aisle lighting and carpet

Page 23: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara
Page 24: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

University City High School – ExteriorWork to date:• Front entry elevation is washed, tuck pointed, various stones repaired and caulked• Front steps are reset and broken treads have been replaced• Lintel replacement has begun along Balson and Jackson streets• Planter walls at front entry are caulked• Caulked half the joints at entry steps, have the other half to go once first half cures• Water main in the limits of our excavation was replaced• Waterproofing and backfilling is complete• Retaining wall will be wrapped up late this week or early next week.

University City High School – ExteriorFuture work over the next several weeks:• Exterior cleaning, tuck pointing, caulking and misc. repair a long with lintel replacement will continue around the structure

Page 25: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

University City High School – ADA Parking Along BalsonWork to date:• Complete except signage

Page 26: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara
Page 27: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

University City High School – Third Floor Science Wing RenovationWork to date:• Phase 1, 2 and 3 abatement is complete.• All demo will be wrapped by end of day 10-23-09• Wall framing has commenced and roughly 30% complete• Plumbing rough in has commenced and roughly 30% complete• HVAC Daikin cassette are in our warehouse and starting arrive on side for installation• Hanging of drywall has begun along with taping

University City High School – Third Floor Science Wing RenovationFuture work over the next several weeks:• MEP chase rough in from lower level up• Installation of Daikin cassettes

Page 28: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara
Page 29: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

Flynn ParkWork to date:• Foundation has been excavated, power washed, and a footing drain installed• Windows have been removed and reinstalled to their new configuration and masonry infill has begun• New neutral air unit is in place, wired and started• Asphalt drive re-opened• Perimeter drain is installed• Openings are in-filled with masonry• Back-fill is complete• Interior windows are trimmed out

Flynn ParkFuture work over the next several weeks:• Fluid cooler repairs• Tie in all downspouts

Page 30: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

Brittany WoodsWork to date:• New neutral air units in place, wired and started

Brittany WoodsFuture work over the next several weeks:• Fluid cooler repairs

Page 31: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

Jackson ParkWork to date:• Waterproofing and backfilling is complete

Page 32: October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara

Current MBE/WBE Participation and Workforce:

MBE participation is 16%WBE participation is 5%

MBE workforce is 28%WBE workforce is 1%