Upload
suzanna-lucas
View
226
Download
1
Tags:
Embed Size (px)
Citation preview
Objectives
• Finish residential electrical systems• Solve some example
• Compare electrical systems for residential and commercial building
Residential system sizing
Typically 3 wire 1 phase system 120/240 V
• Procedure defined by NEC article 220:
• Identify characteristic electrical loads• Add lighting (3W/ft2)• Add two 20 Amps circuits for kitchen• Add one 20 Amps circuit for laundry• Electricity for HVAC equipment based on requirement for
heating or cooling
Homework 5 - problem 2
• Sizing the residential electrical system
• Defined by NEC article 220-30• Similar to the example we worked out • You need to collect the data for several
characteristic consumers• Includes conductor sizing
Summary of Power Sizing
• Include enough capacity for heating and cooling
• Work through kitchen and then other rooms
• Include any items that are unusual
• Take first 10 kVA and then 40% of remaining load
Panel Sizing
• Find panel power usage and neutral usage
• Size panel conductors and associated conduit and switches
Commercial buildings-Differences
Defined by NEC and local electric code!
For example:
No NMC (non metallic sheeted cables) wiring allowed
Other differences?
• Three phase
• Multiple panels
• More attention to expansion possibilities
• More voltage levels available• For example: 277/480 and 120/208
Typical Building Electrical ServicesVoltage/Phase[V]
Current
[A]
Building Type
120/240 1 (3w)
120/208 3<200 Residential
120/240 1 (3w)
120/208 3200-800 Small
Commercial
220/380 3277/480 3347/600 3
400-2000 Large Commercial
5-15 kV low Very Large Commercial
Building Needs: Lighting and Duplexes
• Lighting• Typically use lighting power densities for building type
• Sometimes actual lighting load
• Requires neutral
• Duplexes• NEC/local electrical code specifies number that are
required for different applications
• Requires a transformer
• Requires neutral wire
Building Needs: HVAC/Other/Auxiliary
• HVAC from system sizing• Don’t forget fans, reheat coils, etc.
• Building equipment• Transportation (elevators etc.)• Food service• Specialty uses• No neutral conductor on power panel typically
• Auxiliary• Energy management, security and safety, data transfer,
telecommunications
Transformer capacity
• 200∙208∙√3 = 72 kVA ~ 75 kVA
• 200∙208 / 480 = 86 A• 100 A switch
• Neutral 117*208/480 = 50 A
• Three #1 and one #6 aluminum (could use #4)
• 100A fuse - could use 90, but likely same price
Building Needs: Lighting and Duplexes
• Lighting• Typically use lighting power densities for building type
• Sometimes actual lighting load
• Requires neutral
• Duplexes• NEC/local electrical code specifies number that are
required for different applications
• Requires a transformer
• Requires neutral wire
• Duplexes (receptacles)• Main lugs only (remote protection)• 3 Phase total 60 kVA, 14kVA (neutral)• 30 poles• 60 kVA / (208V √3 ) = 167A• Select: 200 A panel• Neutral 14 kVA /120V = 117A (or if not specified 167A)• Table 11-2 for (200A, aluminum 75C, 117 neutral, but we
expand to 130A like phase)• Hot wires should be 250 MCM, Neutral #2/0 aluminum
• 2½ inch conduit
Panel D
Transformer capacity
• P = I V ∙√3 =200∙208∙√3 = 72 kVA ~ 75 kVA
SD switch selection: • For transformer: I1E1=I2E2 • I2 = I1E1/E2 = 200∙208 / 480 = 86 A
• Select switch rated for 100 A
• For 100 A rated switch select: Three #1 (aluminum)
and one #1 for neutral (aluminum)• 90A fuse for phases
Lighting Panel
• 100A - 20 pole spaces
• Hot: 65kVA/(480V∙√3) = 78 A - #2 Aluminum
• Neutral: 22 kVA /277V = 79 A - #2 Aluminum
• 100 A three pole fused switch
• 1½ inch conduit
Power Panel
• No neutral? – all three pole circuits• 33 poles required – chose 42 standard size and allows
for expansion
• 165kVA/(480 √3) = 198 A
• Choose 225A switch (could use 200 A, but you count on expansion)
• 3 300 MCM aluminum wires – 2 inch conduit(in the book table you don’t have MCM 300, however it exist)
Wireway
• 198A + 86 A + 78 A = 362A
• 400A would allow for some expansion, some would probably go to 600A
• 400A three-pole switch
• Six 250 MCM (unlikely to find conductors big enough to just have 3) and one #2/0 aluminum
• Neutral current: maximum = 117 A, you can expand neutral too (130 A)