Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
11
Oasis Midstream ServicesMidstream Business Unit Guidelines
Version 1.1
2
3
Section 1 - Introduction
Section 2 - Environmental Health & Safety
Section 3 - Program Administration
Section 4 - Construction Guidelines
Section 5 - General Equipment & Mechanical Guidelines
Table of Contents
4
6
20
28
78
4
Introduction
1.0 Introduction
Oasis Midstream Services values the
safety of all workers and the protection
of the environment. We are committed
to the quality of our work, as well as
maintaining an incident free workplace.
This goal can only be attained working as
a team with our contractors.
The following terms are used in this
handbook to describe the contractor
company and personnel mentioned in
the guidelines:
Guidebook and Handbook Terms
Contractor - A contractor is defined for
the purposes of this document as any
company or individual whom by contract,
subcontract, or purchase order performs
work or provides services or equipment
to or for Oasis Midstream Services.
Contractor Supervisor - This individual
represents the contractor company that
supervises the work of a contractor or
contractors.
Oasis Representative - An individual
authorized to oversee, manage, or direct
work on behalf of Oasis Petroleum.
Section 1
5
Version 1.1
This handbook provides guidance and a minimum set of expectations for Oasis Midstream Services (OMS) employees and contractors regarding contractor work performed for OMS. As the contractor, you are required to follow the policies and procedures established by the contractor’s company in addition to any of Oasis site-specific policies. This handbook is intended to supplement, not replace, the contractor’s company safety program, which the contractor is required to implement. In the event of a conflict between this handbook and the contractor’s company safety program, the more stringent rule shall apply. The contractor company’s contract with OMS may be canceled, or an individual may be asked to leave OMS owned property if the contents of this guideline are not followed.
1.1 Excellence through Teamwork
Environmental, health, safety, and
production goals cannot be reached
by operational groups operating
independently. This is true for OMS as
well as our contractors. While performing
work for OMS, contractors will be
exposed to hazards as well as operational
challenges and will be expected to
recognize, manage, and effectively solve
and mitigate these obstacles. This is
critical for our business to succeed.
1.2 How to Use this Guidebook
The intent of this handbook is to
provide guidance to our contractors
and employees regarding Oasis’s
expectations of its contractor workforce.
Included is mapping information,
operational specifications, DOT and
other federal regulations, manufacturer
requirements and other documents.
1.3 How to Use the Contractor Handbook
All of Oasis’s contractors should have
a copy of this handbook accessible to
them. The contents of this handbook
should be reviewed, discussed, and
understood by contract personnel
before any work is performed for
Oasis. If an HSE issue arises that is
not addressed in the handbook or by
the contractor’s own safety program,
you must ask for guidance from the
contractor representative or an Oasis
representative.
1.4 How to Use the Inspector Handbook
Inspectors and supervisors provide
services that require additional
information necessary for the quality
assurance and control of various
projects. Operational Specifications,
map information, and other historical
project scopes will be accessible to Oasis
employee or contractor inspectors.
6
Environmental Health & Safety
Introduction1. Purpose and Scope
2. Stop Work Authority
Oasis Commitment 1. Commitment to People
2. Commitment to Safety
3. Commitment to the Environment
4. Regulatory Compliance
Responsibilities1. OMS Manager Responsibility
2. OMS Employee Responsibility
3. OMS Contractor Responsibility
4. OMS Inspector Responsibility
5. Service Providers
Environmental Health and Safety (EHS) PolicyExpectations for Individuals
Expectation of Contractors
1. Contractor’s Commitment
2. General Health, Safety and Welfare2.1 Contractor Personnel Fitness/Personal Hygiene
2.2 EHS Orientation
2.3 Incident Reporting and Investigation
2.4 Reporting Hazards, Unsafe Conditions, & Near Misses
2.5 Behavior-Based Safety Observation Programs
2.6 Substance Abuse, Dangerous Materials and Firearms
2.7 Horseplay
2.8 Housekeeping
2.9 Clothing and Other Apparel
2.10 Compressed Gas Cylinders and Compressed Air
2.11 Storage, Use and Labeling of Chemicals, Solvents and Paint
2.12 Personal Protective Equipment
2.13 Overhead Work
2.14 Scaffolds or Platforms
2.15 Fall Protection Equipment
2.16 Non-Destructive Testing (NDT)
2.17 Safe Work Systems (SWS)
2.18 Hydrogen Sulfide
2.19 Fire Protection
2.20 Safety Equipment
Table of Contents
8
8
8
9
10
10
Section 2
7
Version 1.1
2.21 Safety Training
2.22 EHS Meetings
2.23 English Language Proficiency
2.24 DOT Safety
2.25 Minimum Certifications and Licenses
2.26 Electrical Safety
2.27 Emergencies
3. Environmental Management3.1 Environmental Housekeeping
3.2 Reporting
3.3 Diligence
3.4 Waste Management
3.4.1 Waste Management Plan3.5 Tanks and Vessels
3.6 Waste Water
3.7 Wildlife Management
17
8
Environmental Health & Safety
Introduction
1. Purpose and Scope
This manual was created to be a
guidance document for all OMS
employees, contractors, and consultants
regarding best practices within Oasis
Midstream Services.
Our service providers are chosen
based on professional integrity and are
expected to perform the job correctly/
safely on all Oasis projects and location
regardless of adverse circumstances,
or perceived time constraints. It should
be noted that these are MINIMUM
expectations.
Any changes to the processes
outlined in this document require MOC
(Management of Change) / Oasis
Representative approval.
2. Stop Work Authority
All contractors are authorized as well
as required to stop any work that is
perceived as a risk to any persons’ safety
or a risk to the environment.
No repercussions will result from any
worker or contractor exercising Stop
Work Authority.
If a contractor or contractor’s employee
feel they are being discouraged from or
penalized for using Stop Work Authority
they must report it immediately to an
Oasis Petroleum representative.
Oasis Commitment
Oasis is committed to the safety and
health of all employees and contractors
as well as the communities and
environment in which Oasis operates.
1. Commitment to People
Oasis is not satisfied unless everyone
goes home in the same condition they
arrived.
2. Commitment to Safety
Anyone; employee or contractor, can
call a safety time-out or use Stop Work
Authority to halt an unsafe condition or
behavior.
3. Commitment to the Environment
Oasis is committed to the preservation
of the environment. Any incident that
threatens the environment must be
reported immediately and appropriate
steps taken to mitigate and fix or clean
up the issue.
4. Regulatory Compliance
Oasis is committed to maintaining
regulatory compliance on the county,
state and federal level.
Responsibilities
1. OMS Manager Responsibility
Managers are expected to demonstrate
positive HSE behaviors at all times
Managers will engage in proactive
leadership and two-way communication
with all workers, contractors and
consultants
Be aware of requirements presented in
the handbook
Ensure that all contractors performing
work for Oasis Petroleum are meeting
expectations in accordance with the
requirements presented in the handbook
Environmental Health & Safety
Section 2
9
Version 1.1
2. OMS Employee Responsibility
Be aware of the contractor handbook
and its requirements
Ensure that contractors are aware of the
requirements and expectations of them
and have a copy of the handbook
Ensure that all contractors working
for Oasis Petroleum are meeting the
expectations put forth by the handbook
3. OMS Contractor Responsibility
Contractor companies are responsible for
the contractors employees’ safety and
health and ensuring that all contractors
perform their work safe and acceptable
manner
Contractor must become familiar with
Oasis Petroleum’s requirements and
expectations, many of which are outlined
in this handbook. These guidelines are a
supplement to, not a replacement of the
contractors own safety program. In the
case where the contractors procedures
and Oasis Petroleum procedures conflict,
the more stringent rule should be
followed
Contractors must be aware of Oasis
Petroleum’s contractor handbook and it’s
requirements
4. OMS Inspector Responsibility
Inspectors are responsible to know,
follow, and oversee contractor use and
application of the guidelines in this
handbook.
Are accountable for technical quality
assurance
Responsible to ensure all forms are filled
out and completed prior to start, during
work, and after project is completed
5. Service Providers
It is OMS expectation that service
providers will ensure work is performed
in accordance within the framework
of OMS expectations, contractor
requirements, as well as any and all
county, state and federal regulations
Environmental Health and Safety (EHS) Policy
This document is a summary of the EHS
requirements and working procedures
that are the minimum standards and
practices to which all contractor
personnel must adhere while working
for Oasis Petroleum North America LLC,
or Oasis Midstream Services (OMS)
(collectively, “Company”). These are
Company minimum requirements, and
are in addition to, and intended to
Inspectors are responsible to know, follow, and oversee contractor use and application of the guidelines in
this handbook.
10
Environmental Health & Safety
supplement, all other applicable laws,
rules and regulations. Contractor must
develop its own EHS program, policies
and procedures and through its program,
policies and procedures demonstrate
compliance with all federal, state, county
and municipal laws, rules and regulations
applicable to Contractor’s work and
Contractor’s services, items, materials,
equipment, or personnel to be used
in performing such work, including,
but not limited to, the following (as
may be supplemented and amended
from time to time): the Occupational
Safety and Health Act, the Clean Air
Act, the Comprehensive Environmental
Response, Compensation and Liability
Act, the Federal Water Pollution Control
Act, the Solid Waste Disposal Act, the
Resources Conservation and Recovery
Act, the Safe Drinking Water Act, the
Toxic Substances Control Act, the
Hazardous Materials Transportation Act,
the Federal Oil Pollution Act of 1990 and
comparable state and local statutes and
implementing rules or regulations.
Expectations for Individuals
It is the minimum responsibility of every
individual working at a Company location
to comply with the requirements set
out in this document. It is not within
the scope of this document to detail all
government regulations or Company
EHS procedures, but rather to provide
an overview of Company requirements.
If any questions or concerns arise
about safe work practices, consult your
supervisor and/or a Company supervisor
for the facility where you are working.
Expectation of Contractors
Contractor shall be responsible
for compliance with the enclosed
requirements, other Company
requirements, which may be
subsequently issued, and all government
regulations applicable to Contractor’s
employees and subcontractors.
1. Contractor’s Commitment
Contractor shall demonstrate a strong
commitment to EHS matters and must
have established EHS-related policies
and procedures. Contractor shall be
responsible for complying with its
policies and procedures related to EHS
matters. Contractor shall be responsible
for all aspects of Contractor’s EHS
performance, and for ensuring that
Contractor has a supervisory person
at the worksite at all times who is
competent and has the authority to
implement the Contractor’s EHS system
properly and meet Company’s EHS
requirements. To assist Company in
evaluating Contractor’s EHS program
contents and implementation, Contractor
shall maintain a current Standardized
Safety Questionnaire (SSQ) through
PEC Premier (www.pecpremier.com).
Although participation in other PEC
Premier programs is voluntary at this
time, contractors who participate will be
given priority for assignment of work.
2. General Health, Safety and Welfare
Contractor is responsible for maintaining
all facilities and associated services
under Contractor’s direction or
responsibility in a manner which does
not create or otherwise contribute to an
unhealthy working or living environment.
In order to accomplish this objective,
Contractor shall ensure the following:
Section 2
11
Version 1.1
2.1 Contractor Personnel Fitness/
Personal Hygiene
Contractor and any of its subcontractors
acknowledge that the work to be
performed for Company by Contractor
and subcontractor employees can
require extensive physical demands.
Contractor and all subcontractors shall
ensure that all personnel assigned to any
Company location can safely perform
the essential functions of his/her job
assignment with or without reasonable
accommodation by Company. Contractor
shall ensure that Contractor’s personnel
maintain appropriate standards of
personal hygiene in connection with the
performance of the work on Company’s
behalf.
2.2 EHS Orientation
An employee EHS orientation program
shall be implemented by Contractor, and
shall be given to all of Contractor’s and
all subcontractors’ personnel, regardless
of prior experience. This EHS orientation
shall address Contractor’s mandatory
EHS procedures, rules, and regulations.
Each employee of Contractor and any of
its subcontractors must receive the EHS
orientation before being allowed on any
of Company’s work sites.
2.3 Incident Reporting and Investigation
Contractor is required to immediately
notify OWS of all safety-related incidents
(e.g., any work-related injury, illness,
fatality or other EHS-related recordable
incidents) involving Contractor or any
subcontractor personnel. In addition, a
written report of such incident must be
prepared by Contractor and delivered to
Company within twenty-four (24) hours
of each such incident. Contractor shall
promptly investigate all such incidents,
conduct a Root Cause Analysis, and
provide final incident investigation
reports (including recommendations
and corrective action plans identified
during investigations) to Company within
thirty (30) days of the incident. The
Contractor shall agree that designated
Company personnel may participate
in any Contractor investigation of such
incidents. Contractor shall provide
Company with copies of all incident
reports that result in formal notification
to any Government agency.
Contractor will be required to provide
a monthly safety performance report
undertaken as part of, any work
performed by Contractor, or the
obligations of Contractor under any
Master Service Agreement (MSA). The
monthly cut off for each report shall be
close of business up to and including the
final day of each month. Contractor’s
safety performance report shall be based
on the following formula for determining
recordable incident frequency rate:
(Total Number of Fatalities, Lost Time
Incidents & Medical Treatments X
200,000) Total Number of Man-hours on
Company’s Work Sites
This information will be reported
monthly through Contractor’s PEC
Premier account (SSQ) and will be
completed no later than the 3rd business
day of the month following the reporting
month.
2.4 Reporting Hazards, Unsafe
Conditions, & Near Misses
Unsafe conditions shall be immediately
reported to Company. “Near Miss”
12
Environmental Health & Safety
incidents that could have resulted in
injury or damage shall be reported
immediately to Company in order to
ensure corrective action is taken. At
Company’s discretion, a Root Cause
Analysis may be requested to fully
determine causes and appropriate
corrective actions to address “Near Miss”
incidents.
2.5 Behavior-Based Safety Observation
Programs
Behavior-Based Safety Observation
Programs are recognized as an
effective tool in the development and
growth of a proactive safety culture.
Contractors are encouraged, but not
required, to implement a Behavior-
Based Safety Observation Program.
When such programs are implemented
by Contractor, quarterly reports shall
be shared with Company where those
programs are used by Contractor crews
working on behalf of Company.
2.6 Substance Abuse, Dangerous
Materials and Firearms
Without prejudice to Company’s other
remedies, any of Contractor’s personnel
who are in breach of the provisions
of Company’s rules, regulations, and
policies relating to substance abuse,
dangerous materials, and firearms,
shall be immediately removed from
the applicable worksite. Entry into
Company property is conditioned
upon the Company’s right to conduct
unannounced searches for such
contraband. Contractor shall cause
Contractor’s personnel to comply
with and be subject to all such rules,
regulations, and policies.
2.7 Horseplay
Horseplay, such as wrestling and
practical jokes, etc., can be dangerous
and is prohibited at Company locations.
2.8 Housekeeping
Contractor must use good maintenance
practices around the work site. Work
areas shall be maintained in a neat and
orderly manner. Trash, spills, unused
tools or materials, etc. must be cleaned
up or put away as soon as possible.
Aisles, emergency exits, electrical
panel accesses, fire extinguishers and
emergency controls must be kept clear
and free of materials at all times. All
wastes are to be properly and safely
disposed of. Contractor shall leave all
work sites clean, orderly and in good
condition as directed by Company. All
remaining trash, debris, surplus materials
and equipment must be removed from
Company locations or neighboring
property upon completion of work.
2.9 Clothing and Other Apparel
Clothing suitable for the job shall be
worn. Long pants and shirts or coveralls
should be worn at all times during
the performance of the work. Ragged
or loose clothing and jewelry (rings,
watches, necklaces, etc.) are not to
be worn when operating equipment.
Any clothing that becomes saturated
with petroleum products or hazardous
chemicals should be promptly removed
or changed. Fire retardant clothing
(FRC) must be worn when working in
areas where the potential for a flash fire
exists. These areas include production
facilities, salt water disposal facilities,
compression facilities and well sites
during all phases of drilling, completions
and work-over activity.
Section 2
13
Version 1.1
Individuals on location but not engaged
in work activity or not present in the
area where work is conducted are not
required to wear FRC. Examples of these
exclusions include visits to a drilling
location to make material or equipment
deliveries and visits to secure signatures
on work tickets. Individuals conducting
construction activities on locations prior
to drilling a well are not required to wear
FRC.
2.10 Compressed Gas Cylinders and
Compressed Air
All compressed gas cylinders shall be
returned immediately to a suitable
storage area after use. Protective
caps shall be placed over the cylinder
valves when not in use or when being
transported. Compressed gas cylinders
shall be kept away from heat, fire, molten
metal, or electrical lines, and shall not be
transported by mobile cranes unless a
special carrier is used. Compressed gas
cylinders shall be stored in the upright
position and secured. Acetylene or
liquid compressed gas cylinders shall
never be used in a horizontal position,
as the liquid may be forced out through
the hose causing a fire hazard or
explosion. Cylinders shall be handled,
maintained and stored as required by
29CFR1910.253.
Compressed air shall not be used for
cleaning clothing or parts of the body.
If used for other cleaning, the discharge
shall not exceed thirty (30) psi and eye
protection shall be worn.
2.11 Storage, Use and Labeling of
Chemicals, Solvents and Paint
All chemicals, solvents, and paints are
to be stored in accordance with industry
practice in a storage locker designed and
installed to meet the requirements of
NFPA 30. Chemicals, solvents and paints
should be returned to the storage locker
after use and at the end of each workday
or shift.
All chemicals, solvents and paints must
be kept in clearly labeled containers.
Material Safety Data Sheets (“MSDS”)
must be supplied for Contractor’s
materials supplied under any MSA,
or in connection with any work
performed by Contractor or any of its
subcontractors, and all of Contractor’s
and all of its subcontractors’ personnel
must be instructed in the safe use
of the chemicals in accordance
with an appropriate written Hazard
Communication Program. Protective
equipment as outlined in the MSDS or as
otherwise required by operating location
management must be provided to and
worn by potentially exposed Contractor
personnel.
Personal protective equipment (PPE) or clothing shall meet American National Standards
Institute (ANSI) or a Company-approved equivalent standard.
14
Environmental Health & Safety
Low flash point solvents shall not be
used for any washing or cleaning. The
use of gasoline for anything other than
the intended purpose is not permitted at
Company sites.
2.12 Personal Protective Equipment
Personal protective equipment (PPE)
or clothing shall meet American
National Standards Institute (ANSI) or a
Company-approved equivalent standard.
The wearing of appropriate PPE is
required at the worksite or any location
where hazards exist in the work place
and in all specifically designated areas.
The following PPE, along with training
in its use and care, is to be furnished by
Contractor:
• Head Protection
• Eye and Face Protection
• Hand and Foot Protection
• Hearing Protection
• Flame Resistant Clothing
• Clothing for Handling Hazardous
Chemicals
• Fall Protection
• Other equipment, i.e., breathing
apparatus, gloves, harnesses or
belts, rain gear or chemical resistant
clothing, etc., must be worn when
the hazards to which an individual is
exposed dictate their use.
The following items of PPE shall be used
and/or worn by Contractor’s personnel
at all times in and around the work site:
• Hard hats
• Safety Glasses with side shields
• Steel-Toed Safety Shoes or Boots
• Hearing Protection must be worn in
high-noise areas
2.13 Overhead Work
When working overhead, the area below
shall be roped off or other equivalent
measures taken to protect workers on
the worksite. Danger signs to be used
shall read “Danger – Overhead Work”
and will be conspicuously posted by
contractor. Please follow all applicable
signage requirements. When possible,
tools will be tied off or equipped with a
tether or lanyard.
Contractor’s personnel shall never pass
under a suspended load. Tag lines will
be used for positioning equipment
or materials during a lift. All lifts will
be conducted using properly rated
equipment, and all slings, chains and
other lifting devices will be certified
and tagged. All lifting equipment will be
inspected prior to use.
2.14 Scaffolds or Platforms
All scaffolds or platforms used for
installation and maintenance or removal
Contractor’s personnel shall never pass under a suspended load. Tag lines will be used for positioning
equipment or materials during a lift.
Section 2
15
Version 1.1
of machinery and equipment shall be
constructed, maintained, and used
in compliance with the applicable
occupational health and safety
construction regulations. All scaffolds
shall be inspected and tagged by a
competent individual prior to use.
2.15 Fall Protection Equipment
Full body safety harnesses and lifelines
shall be supplied by Contractor and
worn by all workers when working
above six (6’) feet. All fall protection
equipment shall be routinely inspected
and maintained following manufacturer
recommendations.
2.16 Non-Destructive Testing (NDT)
Radioactive isotopes, x-rays, etc., shall
only be used by licensed individuals.
All others onsite shall be notified of the
testing activities and instructed to stay
clear of the area. NDT may have to be
scheduled such that individuals do not
have to work in the affected area.
2.17 Safe Work Systems (SWS)
Safe Work Systems include Permit to
Work (PTW), Confined Space Entry
(CSE), Hot Work, Lock-out Tag- out
(LOTO), and Trenching & Excavation.
Contractor is required to implement SWS
programs relevant to the work being
performed, including, but not limited to,
hot work, confined space entry, control
of potentially hazardous energy and
excavation work.
2.18 Hydrogen Sulfide
Hydrogen Sulfide, or H2S, may be
encountered at Company facilities.
Contractor is responsible for ensuring
that Contractor’s personnel are properly
trained and equipped in accordance
with applicable regulations and to a
recognized industry standard when
working in areas where hydrogen sulfide
may be encountered due to the nature of
the work.
2.19 Fire Protection
Any unauthorized use of fire protection
equipment for any other purpose other
than its intended use is forbidden.
Contractor shall provide fire protection
equipment appropriate for the work
being performed.
Smoking is only permitted in designated
areas. Any work that has the potential
to produce a spark or open flame (i.e.,
welding, cutting, grinding, electrical)
in areas where flammable vapors or
combustible materials may exist is
strictly prohibited.
2.20 Safety Equipment
Contractor shall provide adequate
safety equipment of an approved
type and amount as is required for the
Contractor shall provide fire protection equipment appropriate
for the work being performed.
16
Environmental Health & Safety
performance of the work. Contractor
shall maintain this equipment in a
professional manner as dictated by legal
and industry standards. In addition,
Contractor shall keep up-to-date records
of all said equipment.
2.21 Safety Training
Contractor shall ensure that Contractor’s
personnel have been given the
necessary safety, emergency, and job-
related training required by petroleum
industry standards and practice, as
well as Contractor’s and Company’s
EHS policies and procedures. Training
records must be available to Company
for review. Contractor shall ensure that
certificates for mandatory training have
been obtained by Contractor prior to
Contractor’s personnel travelling to any
location to start the work.
2.22 EHS Meetings
Regular EHS meetings should be held
and pre-job toolbox talks should be
established. Such EHS meetings should
be documented and copies forwarded to
Company’s Authorized Representative as
requested.
2.23 English Language Proficiency
Contractor shall ensure that all
Contractor management and supervisory
personnel are proficient in reading and
writing of the English language. This is
critical for all aspects of EHS including
implementation of procedures, permits
to work, training, signs, and emergency
response actions.
2.24 DOT Safety
Contractor shall operate all Commercial
Motor Vehicles in compliance with
State and Federal Motor Carrier Safety
Regulations.
2.25 Minimum Certifications and
Licenses
Contractor will ensure that all personnel
have the necessary certifications or
licenses required for their jobs. Examples
include, but are not limited to, IADC Well
Control, radiation safety, rigger, crane
operator, welder, electrician, plumber,
forklift operator and commercial motor
vehicle driver.
2.26 Electrical Safety
Contractor shall ensure that Contractor’s personnel have
been given the necessary safety, emergency, and job- related training
required by petroleum industry standards and practice, as well as Contractor’s and Company’s EHS
policies and procedures.
Section 2
17
Version 1.1
Contractor’s personnel working
around electrical equipment shall take
precautions to ensure that the equipment
is de-energized while work is being
conducted on or around such equipment.
Work that is to be conducted near any
overhead power line shall be planned
such that a clearance of no less than
ten feet is maintained throughout the
duration of the job to prevent accidental
contact with energized equipment
or lines. If work is to be performed
within a ten-foot radius of overhead
energized equipment, the equipment
must be de-energized prior to starting
the work, unless adequately controlled
by the safe work system. Ladders
used around electrical equipment
should be constructed of wood or
other nonconductive material. Strict
precautions should be taken to ensure
that all equipment used is properly
grounded and that accidental contact
with ungrounded electrical sources is
prevented.
2.27 Emergencies
Contractor’s personnel shall become
familiar with Company’s Emergency
Response Plans and Procedures at
Company work locations and will
participate in emergency drills when
conducted on Company property. If there
are questions concerning evacuation
or emergency response arrangements,
Contractor must immediately notify
a Company supervisor for further
explanation.
3. Environmental Management
Contractor is responsible for compliance
with all applicable U.S. Environmental
Protection Agency, state and other
federal laws and regulations related to
the environment. Contractor shall pay
due regard to the environment and
shall act responsibly in order to protect
the environment from adverse effects
resulting from Contractor’s activities and
to minimize any adverse impact which
may arise from such activities. In order
to accomplish this objective, Contractor
shall ensure the following:
3.1 Environmental Housekeeping
All work and maintenance shall be
completed in such a manner as to
preclude contamination of land sites and
subterranean fresh water zones through
the use of good international oil industry
practices.
3.2 Reporting
Contractor shall immediately report any
oil, produced water or chemical spills to
Company using Oasis’ online reporting
If there are questions concerning evacuation or emergency response
arrangements, Contractor must immediately notify a Company
supervisor for further explanation.
18
Environmental Health & Safety
system at: www.oasispetroleum.com.
3.3 Diligence
Company, to ensure there are no
detrimental effects being imposed on
surrounding inhabitants, may periodically
assess noise levels from operations.
When requested by Company, Contractor
shall install sound absorption and
mitigation devices.
3.4 Waste Management
All unused chemicals NOT consumed
in operations or maintenance shall be
kept in stock, returned to the supplier
if applicable, recycled, or returned by
Contractor at its sole expense.
3.4.1 Waste Management Plan
At the discretion of Company and
dependent on the nature of work,
Contractor may be requested to develop
and implement a Waste Management
Plan (WMP) for handling and disposing
of hazardous and non- hazardous waste
material. This WMP shall be subject to
the review and approval of Company. At
a minimum, all wastes shall be identified
and catalogued as either Non-Hazardous
and/or Hazardous Wastes.
3.5 Tanks and Vessels
Tanks or vessels for fuel and lubricants
storage shall be properly closed,
installed at ground level, and be
contained inside an impermeable dike
technically designed for this purpose,
with a retention capacity equal to the
110% of the largest tank. Tanks or vessels
shall comply with all technical and
safety requirements to avoid excessive
evaporation, contamination, explosion
or fuel spill. The Contractor shall inspect
these tanks on a daily basis and any
accumulation of fuel/oil shall be removed
to preclude eventual overflows and
seepage into the ground.
3.6 Waste Water
All wash down water and other water
derived from execution of the work is
be controlled and managed in such a
manner as to prevent direct discharge to
land or inland rivers and lakes.
3.7 Wildlife Management
Contractor’s employees shall not hunt,
fish, trap, trade or keep wild animals in
captivity on Company locations.
All unused chemicals NOT consumed in operations or maintenance shall be kept in stock, returned to the
supplier if applicable, recycled, or returned by Contractor at its sole
expense.
Section 2
19
Version 1.1
Program Administration
20
3.0 Scope3.1 Engineering
3.2 Land Department
3.3 Construction Department
3.4 Operations Department
3.5 Regulatory Compliance
3.0 DOT Pipeline Construction3.1 Veriforce
4.0 Non-DOT Pipelines4.1 Recordkeeping
5.0 Internal Compliance5.1 Management of Change
Table of Contents
22
24
27
27
Section 3
Version 1.1
21
Program Administration
DOT - PHMSA - Department of
Transportation – (Pipeline and Hazardous
Materials Safety Administration).
Oversees construction, integrity
management, public awareness and
reporting on all regulated pipelines.
API - American Petroleum Institute.
Provides best practices and guidelines
for public awareness and construction of
DOT regulated pipelines.
Process Management - Methods of
administrating all OMS projects from the
planning stage to final completion. This
includes; engineering, AFE development,
landowner agreements, permitting,
construction, inspection, and final
reporting.
One Call - Process used to manage and
track all requests to perform excavation
activities.
High-Consequence Area - Distance from
any pipeline where “higher than normal”
risk is thought to exist. Determined by
the type of material, size of pipe, and
proximity to public areas.
Public Awareness - Required planning
and sharing of knowledge in order to
keep any affected public informed of
Oasis projects on a consistent basis.
Stakeholders - Individuals who reside
or own property near a DOT regulated
pipeline.
AFE - Authorization for Expenditures
SWD - Salt Water Disposal
Departments: Engineering, Land,
Construction, Production
Considerations: Quality Control,
Management of Change
Program Administration
22
3.0 Scope
This section has been structured to
provide a guiding document for OMS
personnel and service providers in
order to understand the process for
developing, completing, and maintaining
all portions of the OMS Business Unit.
3.1 Engineering
OMS Engineering performs many of the
developmental and financial functions of
Oasis Midstream Services.
Design and coordinate project technical
scopes
Comply with governmental regulations
and industry best practices
Determine pipe size and design
Determine equipment size and design
Develop and communicate OMS internal
scopes of work, and contractor scopes of
work.
Model existing and proposed pipelines
Support Construction, Operations,
project engineering, and commercial
development
Perform hydraulic computer modeling to
design gathering systems, and identify
methods to increase existing systems
efficiency and production volumes.
Develop required authorization for
expenditures AFE’s
Create and submit AFEs and economic
justification metrics
Track costs and monitor expenditures for
all AFE’s and budgets
Coordinate project activities with
multiple entities including Marketing,
Operations, Land, Legal, and
Accounting along with external entities
such as service providers, vendors,
government agencies, regulatory bodies,
landowners, and other production
companies.
Track all production volumes and audit
performance
Track OMS revenue and expenditures
3.2 Land Department
• Receives mapping information from
Houston Engineering, outlining area
to be developed.
• Contacts surface owners for survey
permission
• Coordinates with construction group
to ensure survey accuracy and
confirm route with surface owners.
• Obtains ROW agreement in
coordination with surface owners.
• Receives permitting for all roads or
other utility crossings.
• Coordinates with construction
department and engineering prior to
project construction phase.
• Land and Construction coordinate
as-builds post construction.
• Reviews as-builds information and
designs with surface owners.
• Attaches As-build to ROW
agreement.
• Records ROW agreement with the
county.
• Coordinates with construction group
and surface/asset owners when
necessary to assess damages or
other finalization concerns.
Section 3
Version 1.1
23
• Manages any and all amendments.
• Agreement amendments initiated
by landowner, construction, or other
party when necessary, will restart the
agreement process.
• If any agreements require written
documentation with: city, county,
federal, land owners, stakeholders,
other utility owners, land department
will be present and execute such
agreements.
3.3 Construction Department
Develops Initial Cost Estimate.
Coordinates Survey with Survey Crews.
Completes Construction (Review section
4).
Reports to DOT and files all DOT
paperwork, reports, etc.
Internally files all agreements.
3.4 Operations Department
1. Foreman
Coordinates with construction on new
and existing pipeline layout.
Works with engineering on facility design
and layout.
Coordinates with team lead on day to
day operations of disposals and pipelines
Approves invoices of venders
transporting sw to disposals.
2. Team Lead
Coordinates with foreman and team
members in regards to daily maintenance
and repair of SWD’s and pipelines.
Assists team members with ongoing
operations as needed.
Covers for team members on days off.
3. Team Members
Inspect and maintain SWD’s on a daily
basis.
Perform quarterly pressure tests on all
pipelines within the OMS system.
Perform inspection and maintenance on
transfer pumps on a weekly basis.
In the event of a spill, they coordinate
cleanup and disposal of contaminated
materials.
4. Measurement
The measurement division of OMS
Operations department is primarily
responsible for the oil production
custody transfer to service providers
who purchase Oasis Petroleum’s crude
oil. Their functions are as follows:
Communicates with Purchasing Service
Providers.
Receives information about receiving
LACT Units.
Organizes set-up and ensures they are
correctly wired-in.
Coordinates startup.
Communicates with OMS Engineering for
projected start-up.
Performs daily measurement to collect
production information.
Program Administration
24
Communicates maintenance needs with
purchasing vendors.
Troubleshoots problems with pumps, and
other OMS equipment.
Performs proving operations on sales
meters.
Calibrates all meters on a quarterly basis.
3.5 Regulatory Compliance
Below are various regulatory
considerations that must are managed
by the OMS group internally, by use of
service providers, or in conjunction with
other departments when necessary.
1. One Call System Management
Manages the process and system utilized
by OMS personnel to track, record,
and complete one-call requests and
notifications.
Completes all requirements prompted by
OMS designated online reporting system.
Duties include one-calls requested in
Montana.
Training and Awareness.
• Employees
• Contractors
• Line Locator Qualifications
2. Construction Documentation
Project Build Record – [ref. Section 4.4.2]
PBR – Figure 1
The Project Build Record is utilized as
a recording tool for OMS Construction
personnel to track and manage that all
required documents are created, stored,
and completed throughout the process
of construction. They apply to both DOT
and Non DOT Lines
Completing Project Build Records
Construction Administration personnel
will ensure all necessary documents are
contained with the appropriate files,
both physically and electronically.
Administrative personnel archive
construction and process information
electronically on the designated server.
Inspectors are responsible for
completing and delivering PBR’s to
OMS managers and/or administrative
personnel.
3.0 DOT Pipeline Construction
1. Reporting Procedures
A) Annual Reporting
New Construction
All new construction projects involving
DOT Lines must be documented with as
builds attached.
Types of Pipe
By classification, by type Must be
recorded and reported annually.
Length of Pipes
By classification, by type must be
recorded and reported annually.
Section 3
Version 1.1
25
Figure 1 - Project Build Record
Program Administration
26
Incidents
Any incidents involving OMS DOT lines
must be documented and incident
reports must be completed and filed
immediately onto the PHSMA portal
database.
Drug Testing Information
OMS personnel who are responsible for:
constructing, completing; maintaining; or
responding to emergencies on any DOT
regulated pipeline must be part of a DOT
standard drug testing consortium and
plan.
Accidents
Accidents involving any DOT pipeline
must also be reported immediately online
within the PHMSA portal.
Near Miss / Incident Reporting (to
PHMSA – online – within 24 hours of any
incident)
Integrity Management
Integrity management programs involve
methods of ensuring the longevity and
safety of DOT Regulated pipelines.
This can include maintenance, public
awareness programs (Including posting,
mailers, and pipeline markers) and
preventative maintenance.
• Maintenance
• Quarterly Maintenance (Documented)
• Pressure Testing
• Leak Testing
• Valve Operation / Inspection
• ROW Inspection
• Equipment Maintenance and
Inspection
• Public Awareness Programs
• Public Awareness programs include
the following necessary components:
• Mailers / Reports
• Response Metrics
• Surveys
• Public Awareness Meetings
The value and effectiveness of these
programs must be audited on an
annual basis, reports compiled, and
findings recorded for ongoing program
development.
Contractor Management
DOT standards require that contractors
performing work on behalf of any
pipeline regulated by the DOT, complete
operator qualification programs and be
enrolled in DOT regulated drug & alcohol
consortiums. OMS utilizes Veriforce as
their approved service provider and
standardization group for contractors
performing construction, maintenance,
or emergency response on DOT
regulated pipelines.
3.1 Veriforce
Drug and Alcohol Programs
100% Consortium Participation
All personnel who take part in the
construction of a DOT regulated pipeline;
inspectors, foreman, supervisors,
laborers, truck drivers, must be enrolled
in a DOT consortium. Veriforce verifies
that selected contractors are enrolled,
and make these records available to OMS
personnel.
Internal Review
OMS regards the safety and health of
their contractors highly. To ensure that
Section 3
Version 1.1
27
contractors are up-to-date with training
and verification, OMS will perform a
review semi-annually for gaps in any
contractor compliance.
Recordkeeping
Throughout the process of construction
of DOT lines, all records of construction
data must be maintained. Some of these
include:
• Pipe and special invoices and
manufacturer information
• Fuse logs
• Pressure / Leak Testing information
• Weld tests and Welder certification
information
• Annual Review
• Records will be reviewed and audited
on an annual basis. This process will
correlate with the April 15th deadline
for DOT reporting.
4.0 Non-DOT Pipelines
4.1. Recordkeeping
Although non-regulated pipelines
do not require records be kept as
thoroughly and completely as regulated
pipelines, OMS expects that the same
recordkeeping procedures be followed.
5.0 Internal Compliance
It is OMS expectation that its operations
be reviewed on a regular basis by OMS
personnel who will assess its process
from a quality assurance and quality
control perspective. Some of these
functions are as follows.
5.1.Management of Change
When a change to an internal OMS
system occurs, a Management of Change
(MOC) process must be completed. This
is to ensure that all changes with OMS
production are documented thoroughly,
included with justification for the
change, cost savings (if applicable) and
desired outcome. These processes will
be reviewed from time to time to ensure
that changes being made are effective.
Changes that require an MOC process
include, but are not limited to:
• Administration Procedures
• Existing Lines
• Clean-ups
• Processes
• Type of Equipment Used
(Technology)
• Methods of Document Control
• Responsibility changes
• Divisions created
• Final Inspection/ Close-out Protocol
28
Construction Guidelines
References
Federal Standards
OSHA
1926.651
1926.652
DOT (if applicable)
T.49.C.D.192
T.49.C.D.195
Other Standards
ASTM
F2620
D638
D1598
2634
C150
API
1104
1107
NACE
#1 - Construction
Process
Material Transfer
ROW Establishment
ROW Survey
ROW Construction
Pipelaying
Tie-ins
Crossings
Civil Construction
Facility Construction
Coating
Backfill
Pressure Testing
ROW Cleanup
Pressure Testing
Considerations
PPE
Hard Hat
FR Clothing
Goggles
Face Shield
Hard Toed boots
Chemical Resistant Gloves
Safety Glasses
Other equipment as applicable
Section 4
29
Version 1.1
Construction Guidelines
Oasis Representative - Any individual
who has authority on an Oasis project,
location, or situation regarding Oasis
assets or personnel.
Inspector - Any individual authorized
to supervise construction, quality, or
management of an Oasis construction
project.
Material Transfer - (See Material Transfer
Form-OMS-10010) The process used to
track OMS inventory
ROW - Right-of-Way Predetermined
area established by agreement or grant,
to pass along a specific route through
grounds or property belonging to
another party.
Poly (PE) - Polypropylene Pipe. Also
known as “Plastic” or HDPE Pipe.
SDS - Safety Data Sheets
Instrumentation & Electrical (I&E) -
Components involved in automated
measurement and electrical interface
with a variety of pipeline and production
equipment.
OSHA - Occupational Safety and Health
Administration
DOT - Department of Transportation
ASTM - American Society for Testing &
Materials
AISC - American Institute of Steel
Construction
API - American Petroleum Institute
SMYS - Specified Minimum Yield
Strength
NACE - National Association of Corrosion
Engineers
SSPC - Society for Protective Coatings
Holiday - A pipe anomaly such as a ding
or dent that will cause early corrosion.
30
Construction Guidelines
4.1 Material Transfer4.1.1 General
A) Pipe HandlingB) Inventory
C) LoadingD) Material Return
4.2 ROW Corridor Establishment4.2.1 General
A) Engineering – Develops Project Scope and Design
4.3 Right of Way (ROW) Survey4.3.1 General
A) Construction StakingB) As BuildC) Mapping
4.4 ROW Construction4.4.1 General
A) One CallB) Line LocatingC) HydroVaccing
D) Relocating4.4.2 Project Build Record (PBR)
4.4.3 Preparation of Right of Way (ROW)
A) ClearingB) GradingC) Topsoil
4.4.5 Housekeeping
A) Poly shavingsB) Tools
C) Equipment Storage4.4.6 Preservation of ROW
4.5 Pipelining4.5.1 General
4.5.2 Stringing
A) Quality ControlB) Unloading Methods
C) InspectionA) General Considerations
B) Butt Fusion Joining RestrictionsC) Outside Diameter (OD) Compatibility
D) Wall Thickness (DR) Compatibility
Table of Contents
34
38
39
39
41
Section 4
31
Version 1.1
E) Fusion Quality Verification – Data Logging and TestingF) Fusion Evaluation Tests – Mechanical Field and Laboratory Tests
G) Weather Guidelines4.5.4 Bending
A) Field-Bending – Steel PipeB) Field Bend Data - Steel Pipe
4.5.5 Trenching / Excavation
A) Trenching / Excavation PermittingB) Daily Inspection
C) Trench Boxes / Shoring4.5.6 Lowering Pipe
A) Trench Bed ConditionB) Trench Bed MaterialC) Inspection & Testing
4.5.7 Welding
A) GeneralB) Requirements
C) MethodD) Line Pipe Weld Procedures
4.5.8 Boring
A) Equipment RequirementsB) Boring System
C) Other EquipmentD) Boring Operations
E) Utility Locates
4.6 Tie-Ins4.6.1 General
A) Water ConsiderationsB) Backfilling
C). Cold CuttingD) Live Tie-InE) Squeezing
4.7 Crossings4.7.1 General
A) ApprovalsB) Line Crossings
C) Road crossingsD) Water CrossingsE) Boring Crossings
F) Section Lines
58
62
32
Construction Guidelines
4.8 Civil Construction4.8.1 General
A) CementB) Structural Steel
C) Roads / WalkwaysD) Location / Well Pad
4.9 Facility Construction4.9.1 General
A) PumpsB) HousesC) Risers
D) Instrumentation and Electrical (I&E)
4.10 Coating4.10.1 General
A) PaintingB) External Painting
C) Jeep Sticks
4.11 Tracer Tape & Wire4.11.1 General
A) DepthB) Wire Location
C) Wire Protection
4.12 Backfill4.12.1 Material
4.12.2 Backfill Method
A) Backfill MaterialB) General
C) PaddingD) Padding Density
4.12.3 Final Compaction
A) Moisture4.12.4 Restoration of Construction Areas
4.12.5 Overburden / Crown
4.12.6 Irrigation & Drainage
4.12.7. Reinforcing
4.12.8. Topsoil
63
65
66
69
70
Section 4
33
Version 1.1
4.13 Leak & Pressure Testing4.13.1 General
A) Location of EquipmentB) Test Duration
C) Water SourcesD) Failures
E) DepressurizingF) Dewatering
4.14 ROW Clean-Up4.14.1 Post-Construction Clean-up
A) FencesB) Gates
C) Line MarkersD) Test LeadsE) Reseeding
F) Erosion ControlG) Rock Picking
4.15 Start-upA) Removal of Isolation Devices
B) Opening of Block ValvesC) Suction Line Leak Test
D) Oil SystemE) Pump to Line Leak Test
F) System Leak Tests
4.16 Project Sign-off4.16.1 Final Inspection
72
74
74
76
34
Construction Guidelines
4.1 Material Transfer
4.1.1 General
Oasis Midstream Services (OMS) requires
that all operations be performed in a safe
and efficient manner. A major component
of operating this way involves the
process of handling and transporting
materials. This section reviews overviews
safe guidelines in order to handle and
transport materials for OMS in a safe and
professional manner.
A) Pipe Handling
1. Prior to loading or unloading any pipe,
trucks and trailers must be parked in
a way that they are level and secure.
Parking (hand) brakes should be set and
the wheels correctly chocked. The truck’s
engine should be off and left in gear and
the driver’s location known at all times.
Personnel directly involved should be
the only ones within the area of pipe
handling. Non-essential personnel must
stay clear of work area.
2. Poly pipe becomes extremely slippery
when wet. Caution should be used at all
times when handling poly pipe, especially
in rainy or snowy conditions. When
handling this pipe in these conditions
work slowly.
3. Black poly pipe becomes extremely
hot when exposed to direct sunlight,
therefore exercise caution and wear
appropriate PPE at all times when
handling black poly pipe.
B) Inventory
It is the responsibility of OMS personnel
to oversee and take record of all
equipment, pipes, and specials that
enter or leave the OMS yard. This will be
accomplished through internal inventory
management systems.
1.A) Equipment Storage - Jobsite
Storage areas should have smooth, level
surfaces that are free of stones, debris
and other materials that may damage
pipe.
If no adequate surface can be prepared,
pipe should be placed on evenly
spaced planking, racks, or other means
of supporting and protecting pipes
and equipment. Weather conditions
should also be considered when storing
materials that could be damaged by
extreme temperatures, ice, wind, or
moisture.
Pipe should be separated and stored
according to length and diameter as is
most feasible. Piles must only contain a
single size of pipe and be constructed in
a pyramid shape with the bottom layer
braced to prevent movement of any kind.
Rows of pipe should all for easy loading
and offloading of pipe by use of available
loading equipment.
1.B) Off-Site Storage
When storing pipe off-site, it should
be placed in pipe racks according to
length and diameter of pipe to prevent
from rolling or falling. Pipe larger than 2
inches should be stacked with spacing
strips.
If pipe is stored outdoors, pipe racks
should be made of material that will not
deteriorate.
1.C) Indoor/Outdoor Storage
Section 4
35
Version 1.1
Black poly pipe contains more than 2%
carbon black and will resist UV damage.
It may be stored unprotected from UV.
Other colors must be stored no longer
than two years.
C) Loading
1. Operator Experience
Only experienced operators are allowed
to use heavy equipment. This includes
a verification as per OSHA standard
1926.1427.
Staging area must be clear of workers,
equipment and other obstacles while
material is being loaded or unloaded and
must allow for clear line of sight.
2. Weight Limitations
Never exceed rated lifting capacity of
equipment.
The proper and safe use of forklifts
and other heavy equipment is the
responsibility of the contractor.
2.A) Inspection
• Check forks for jagged edges/burrs.
• Forks set to widest setting.
• Always lift from center.
2.B) Fork Application
Slide forks gently underneath pipe. Take
care to ensure that forks are not forced
underneath pipe, or positioned in a way
that could damage pipe racks.
2.C) Tilt Degree
When tilting the load of pipe or spools
tilt slightly back in order to stabilize and
prevent objects from rolling or sliding
forward without control.
2.D) Handling Loads
When transporting a load, move with the
load as close to the ground as possible,
taking care to not allow pipe to drag.
Drive as slowly as necessary as to avoid
bouncing.
3. Front End Loaders
The proper and safe use of front end
loaders falls under the responsibility of
the operator.
3.A) Compliance
If equipped with forks, loaders are used
as forklifts and treated as such. Always
maintain stability and center of gravity
precautions.
4. Pipe Handling Accessories
Accessories used to handle and support
pipe should be properly constructed and
rated above the capacity of the load that
they are intended to support.
Never exceed rated lifting capacity of equipment.
36
Construction Guidelines
Chains, steel cable, wire rope, or hooks
are not to be used to handle poly pipe.
Slings must be wide band to distribute
load.
Nylon rope is acceptable to use with poly
pipe.
Only specially designed pipe tongs can
be used to lift poly pipe.
Lifting capacities of equipment and
attachments are not to be exceeded. The
angle between each lifting leg must not
exceed 45 degrees.
4.A) Unloading Coiled Pipe
Certain precautions must be taken into
consideration prior to unloading coiled
pipe. When unstrapping a load of coiled
pipe, it is necessary to ensure that
personnel are out of line with the ends
of pipe. Trailers must be level before
unloading either palletized or non-
palletized coils.
Never push, pull or roll coils off of trailer.
Never stand behind, under or around the
load as it is being unloaded.
When the securement banding is being
cut or removed, the coiled pipe has the
potential to whip away from the coil.
Ensure no personnel are in the area while
removing these bands.
DO NOT remove straps until sling is
secured.
4.B) Straight Length Pipe
It is necessary to ensure the load has not
shifted during transport before removing
securement straps.
Bundles should be unloaded with forks,
forked loaders or cranes with spreader
bars.
Steel bands used on bundles shall not
be removed until bundle is secure and
stabilized in storage area (remove from
ground with extension device).
Never stand on a load of pipe. If
breaking the banding is not possible
from the ground, personnel must remove
bands by the use of extension breaker
bars.
4.C) Strip Loads
Chains, steel cable, wire rope, or hooks are not to be used to handle
poly pipe. Slings must be wide band to distribute load. Nylon rope is
acceptable to use with poly pipe. Only specially designed pipe tongs
can be used to lift poly pipe.
Section 4
37
Version 1.1
Cranes should use spreader bars to
ensure proper transportation of the pipe.
Do not cut bands until pipe is secure in
storage.
Ensure all wheel chocks are in place
before beginning to unload.
D) Material Return
1. Material Transfer Forms (MTF)
All materials designated to arrive to,
or leave from Oasis yard, must have a
Material Transfer Form (MTF) completed
prior to being transported. Minimum
details to be included:
• Lease Name / Location
• AFE / LOE #
• Person receiving materials name/
company/signature
• Information about who the material
is for
2. Incoming Materials
2.A) Gate Check-in
All vendors or contractors delivering
material for OMS projects must check in
at the designated gate.
2.B) Bill of Lading
The yard personnel will unload the
material and check the material against
the packing list before signing the BOL
(Bill of Lading); personnel will then stage
the material in a predetermined location.
2.C) Damaged Material
If material is damaged beyond use/
repair, it will be cited as “Condition D”
and billed to contractor or rejected.
3. Outgoing Material
3.A) Gate Checkout
All personnel with the crews picking up
material must check in at the north gate.
Yard personnel will receive and must
have the following information before
loading any material:
1. Location
2. AFE
3. Name of Oasis supervisor
4. List of material required
The yard personnel will then fill out a
yard Material Transfer Form (MTF) and
have the person picking up the material
sign it before leaving.
All materials designated to arrive to, or leave from Oasis yard, must
have a Material Transfer Form (MTF) completed prior to being
transported.
38
Construction Guidelines
Support documents [OMS-10010 –
Material Transfer Form]
4.2 ROW Corridor Establishment
4.2.1 General
The corridor is established as the
beginning stage of preparation for
installing a pipeline. Each department has
various roles to play in this development
process. They are outlined below, as well
as other establishment criteria.
A) Engineering – Develops Project Scope and Design
Responsibilities
1. The OMS engineering group will
develop all pressure scopes, elevation,
necessary equipment, operating
specifications, and other data relative
to the design and operation of the
proposed pipeline.
B) Land department – Manages Agreements and Planning
Responsibilities
1. Develop and approve proposed
pipeline route taking into consideration:
feasibility; financial viability; topography;
environmental; operational optimization;
and gaining the necessary approvals
from stakeholders. Record plat to county
and work with other reporting and
recording agencies.
2. Record plat to county and work with
other reporting and recording agencies.
3. Obtain and finalize ROW agreement
and landowner signoff.
4. After project completion, obtain final
signature from landowner to release the
project.
C) Construction Department – Completes the Project
Responsibilities
1. Manage contractors, understand
deadlines, follow regulatory guidelines,
maintain quality control and review OMS
programs in order to verify compliance.
In addition to ensuring all documentation
is maintained, remediation is
accomplished if necessary, and all
procedures are followed.
2. The construction department is also
required to notify Land Department
when a project is complete.
Yard personnel will receive and must have the following information
before loading any material:Location, AFE, Name of Oasis
supervisor, and the list of material required
Section 4
39
Version 1.1
4.3 Right of Way (ROW) Survey
4.3.1 General
The ROW is a route that is selected on a
preliminary basis to determine the scope
and cost of a project (determined by
the engineering department). The ROW
is a legal right, established by usage
or grant, to pass along a specific route
through grounds or property belonging
to another.
A) Construction Staking
Construction staking will be
performed with the direction of Oasis
Representatives. Oasis will mark route
of the centerline of the right-of-way or
ROW, as well as the ROW boundaries,
at the company’s discretion. Oasis
contractors will be responsible for
staking the ditch line within the right-
of-way ROW, which will be addressed
in the construction folder. Stakes will
be of such regularity that continuity
may be maintained, normally at 100-
to 200-foot intervals, along with the
beginning, middle and end of all points
of intersection, bores, and any/all other
landowner considerations. These stakes
will also be used to gauge construction
progress and to reference specific
locations on drawings and in reports.
Contractor is responsible for submitting
One Call to coordinate locating existing
pipelines, sewers, water or gas mains,
and electric or telephone installations.
Contractor shall take all necessary
precautions to protect and to avoid
damage or interference with these
facilities and shall repair these lines
immediately if damaged. Contractor is
responsible for maintaining all survey and
line markers. Failure to do so will result
in immediate shutdown of the job until
adequate markers are maintained.
B) As Build
-Reference Section 3-
C) Mapping
The scope of mapping is transferred
from survey to the Houston mapping
group with all required details and
info. Houston will then complete a field
map with all valves, roads, crossings,
landmarks, well names, etc.
4.4 ROW Construction
4.4.1 General
The Right of Way is the most permanent
picture of the quality of work that OMS
does. The process involved in acquiring,
maintaining, and leaving the ROW are
extremely important to our relationships
with our stakeholders, our assets, and
our reputation.
A) One Call
A One Call must be made prior to any
digging being performed. This can be
accomplished by calling 811 in both North
Dakota and Montana. In Montana, it is
also possible to fax-a-locate, however
there must be a pre-approval process
completed prior to the One Call being
processed. Montana’s One Call fax
number: (406) 752-7306 and website:
(www.mt1call.com).
*Faxing a locate to ND One Call will only
be available through the end of Dec
2014.
1. ‘Locate’ Wait Duration
40
Construction Guidelines
After a One Call is made, line-locating
personnel will arrive at the desired
location within 48 hours of the One Call
submission and locate any Oasis, or other
entity’s lines. Oasis does not authorize
excavation prior to lines being located
under ANY circumstances, even if at
times a locate does not occur within 48
hours. The locate ticket must be followed
to the exact specifications written on the
ticket.
B) Line Locating
1. Project Relocating & Re-spots
After a line has been located, there are
many things that could require a “re-
spot” including:
Flags being moved by landowner;
Flags being moved by contractor/service
provider;
Uncertainty about accuracy of utility /
facility markers;
Change in job scope / area;
One Call tickets whose territory located
does not clearly indicate where the
locate starts or ends.
2. Distance from Flags
Minimum distance to maintain is 2 feet
from any flag or utility marker, in any
direction.
C) HydroVaccing
Hydrovaccing is the process of locating
a line with non-destructive means. Water
is used in lieu of shovels, excavation
equipment, etc. This process uses water
at high pressures to locate lines, and
has the additional benefit of vacuuming,
or removing the water/mud that is
created in the process. All tie-ins must be
hydrovacced, as well as any time a line
crossing is performed.
D) Relocating
Locate tickets are good for 21 days
only. The locate ticket will indicate the
expiration of the One Call ticket.
4.4.2 Project Build Record (PBR)
A) Required forms
• [OMS 1001] Oasis Dig Permit
• [OMS 1002] Anode Installation
• [OMS 1003] Confined Space Entry
Permit
• [OMS 1004] Construction Summary
• [OMS 1005] Foreign Line Crossing
• [OMS 1006] Hot Tap Permit
• [OMS 1007] Hot Tap Info
• [OMS 1008] Hydro Test Data
• [OMS 1009] Locate Wire Installation
• [OMS 1010] LOTO Process
• [OMS 1011] One Call Log
• [OMS 1012] Pipe Tally
• [OMS 1013] Pressure Test Data
• [OMS 1014] Poly Report
• [OMS 1015] Project Build Record
• [OMS 1016] Steel Pipe Record
• [OMS 1017] Cost Estimate
• [OMS 1018] Measurement Change
Form
• [OMS 1019] Final Inspection Report
4.4.3 Preparation of Right of Way
(ROW)
A) Clearing
It is required prior to construction that
removal of brush, grass, weeds, trees,
Section 4
41
Version 1.1
crops, or anything that is on the ROW
occurs. Contractor will use Brush Hog, or
other sufficient means to accomplish this.
B) Grading
Preparing the ROW to the standard
grade, side hilling, acquiring proper highs
and lows to ensure your equipment gets
through without issue.
C) Topsoil
Cut into your soil top. Location
geography will determine depth of
topsoil. Topsoil is moved to one side of
ROW until the final step where it will be
redistributed evenly. State lands require
12 inches of topsoil to be removed.
4.4.4 ROW Access
Oasis Petroleum shall obtain easements
for ROW’s and permits for roads and
railroad crossings. Contractors may only
access the ROW from approved public
roads and points unless specifically
designated by Oasis representatives.
No two-track roads will be used unless
specifically authorized. Section lines
can only be used with prior Oasis
authorization.
Settlement of any off-ROW damages is
the sole responsibility of the contractor,
specific indemnity language is written
into Oasis Master Service Agreements.
4.4.5 Housekeeping
A) Poly shavings
Any waste materials created during the
process of stringing, fusing, bending,
or shaving pipe must be gathered and
disposed of in the correct manner. These
spare materials are not to be buried or
left behind.
B) Tools
Tools must be kept a minimum of 2
feet from the edge from any excavation
including open excavation, trench, bell
hole, etc.
C) Equipment Storage
Equipment storage locations/laydown
areas must be established prior to the
commencements of Oasis projects. All
agreements for additional space will
be initiated by the contractor but must
have Oasis approval prior to contact
with landowners. The cost of these
areas may be assessed only to the
contractor, however, Oasis may choose
to be involved or lead in the negotiation
process.
4.4.6 Preservation of ROW
Contractors shall offset all centerline and
locating stakes in a uniform manner, as
required for clearing and grading. After
clearing and grading contractors shall
reset the stakes in their original position.
Contractors will be held responsible for
the preservation of all stakes and line
markers. Contractors shall bear the cost
of replacing any stakes destroyed or lost
and re-survey work required.
4.5 Pipelining
4.5.1 General
The method used to lay, seal and bury
pipe is foundational to the success
of OMS. When contractors, internal
departments, and engineering groups
work together as a team, projects will be
42
Construction Guidelines
completed correctly and to the quality
OMS aspires to. The following guidelines
have been created with the expectation
that contractors will have reference
material to rely on in order to uphold and
understand OMS requirements.
4.5.2 Stringing
A) Quality Control
OMS requests that pipe be strung along
the ROW and be aligned in accordance
with good pipeline construction practices
using pipe furnished only by Oasis.
Stringing of pipe on the ROW should
done in such a manner as to cause
minimal impact to the surround area, and
gaps shall be left at intervals to permit
use of the land and passage of farm
livestock and equipment across the ROW.
B) Unloading Methods
Pipe is to be unloaded from the stringing
trucks and lowered onto approved
padded skids by using canvas slings
or pipe hooks. Pipe is not to be rolled
off the truck. In areas where the ROW
crosses rocky terrain, special care shall
be taken in lowering the pipe to see that
pipe is not dropped on rocks or allowed
to rest on sharp or jagged surfaces.
Non-ferrous pipe can be pulled provided
that no visible damage occurs. A tag
line will be attached to hooks to control
the suspension of the pipe at each end
during stringing operations. In instances
where spooled pipe is being laid,
contractor is responsible for maintaining
pipe integrity. Pipe shall not be strung
without Oasis approval.
C) Inspection
After pipe has been strung, OMS
personnel and contractors will inspect it
thoroughly. Contractors will reimburse
Oasis for any and all damaged pipe.
D) Bedding
Bedding material must be clean sand or
soil and must not contain stones having
a maximum dimension larger than 2
inches. Material must be placed to a
minimum depth of
6 inches under the pipe and 6 inches
over the top of the pipe. The remaining
backfill must not contain rock larger than
6 inches. Organic material and wood are
not permitted for bedding and backfill
since they will deteriorate over time,
allowing for subsidence and subsequent
shifting and possible pipe damage.
4.5.3 Fusing
A) General Considerations
Butt-fusing operations and procedures
It is OMS expectation that contractors will provide trained and qualified personnel to perform butt-
fusion operations.
Section 4
43
Version 1.1
are not for novice employees. Personnel
must at minimum, prior to work,
understand and review manufacturer
recommendations and requirements.
Oasis can provide these materials if
contractor does not have access to
these materials. It is OMS expectation
that contractors will provide trained and
qualified personnel to perform butt-
fusion operations.
The process of butt fusion joins plain
end polyethylene pipes and fittings
end-to-end without couplings, inserts
or additional materials. Equipment must
be used to hold the components in
alignment and move the components
toward and away from each other
during preparation, heating and joining
operations. The equipment includes tools
to face (plane) and heat the component
ends.
Butt fusion equipment is manually
operated for smaller pipe sizes and
hydraulically operated for larger sizes.
The equipment covers a range of
pipe sizes and is properly set up by
adjusting pipe holding clamps, setting
the heating tool temperature, and for
hydraulic equipment, setting the fusion
joining pressure. Additional setup will be
required depending on the equipment.
Butt fusion equipment is set up,
operated and maintained in accordance
with the equipment manufacturer’s
instructions. Improperly set up, operated
or maintained fusion equipment can
produce faulty joints.
Other equipment such as pipe supports
and appropriate equipment for handling
pipe and fittings is required.
B) Butt Fusion Joining Restrictions
The ends of pipes and other components
such as fittings, flange adapters, MJ
adapters, etc., that are joined together
must have the same outside diameter
and comparable wall thickness.
Additional information about thickness
and diameter compatibility is found
below.
C) Outside Diameter (OD) Compatibility
Several OD controlled sizing systems
are used for Poly piping components.
These include IPS (iron pipe size), DIPS
(ductile iron pipe size), DIOD (ductile
iron outside diameter), CTS (copper
tubing size), inch-OD, or mm-OD as
applicable. For butt fusion joining, the
component ends being joined must be
the same outside diameter dimension
and system. For example, both pipes
must be the same IPS diameter, or the
same DIPS diameter. Different OD sizing
systems are not compatible, e.g., IPS and
DIPS cannot be butt fused to each other.
ID controlled (SIDR) pipes are joined
using insert type mechanical fittings and
are not suitable for butt fusion joining.
See Reference R-WL116 for applicable PE
pipe standards.
D) Wall Thickness (DR) Compatibility
The DR of the lower component ends
must not be less than 0.79 times the
DR of the higher component end. This
is to ensure the quality of flow rate, and
that pressures do not compromise the
components connections. In order to
determine if components with different
DR’s can be joined together, multiply the
higher DR by 0.79. If the lower DR is this
number or higher, the components can
be joined together using this procedure.
44
Construction Guidelines
E) Fusion Quality Verification – Data Logging and Testing
It is recommended that hydraulic butt
fusion machines be equipped with data
logging technology to monitor and
record time, temperature and pressure
during fusion. Field fusion data logging
records that compare favorably with
tested trial fusion data logging records
can provide confidence in field fusion
quality. Data logging records must
be delivered to OMS personnel at the
completion of the project.
Fusion quality is tested by preparing a
trial fusion and performing destructive
tests such as two D638 tensile tests, a
DF2620 bent strap test, or ASTM F2634
tensile impact tests of specimens cut
from the fusion. Prior to testing, test
samples must be cooled to 73°F/23°C.
ASTM D638 tensile tests are conducted
on Type III or Type IV tensile bar
specimens machined from samples cut
longitudinally from each quadrant of a
trial fusion with the fusion in the center
of the reduced area. The sides of the
tensile bar specimen-reduced area must
be smooth and free from nicks and cuts.
If wall thickness is reduced, the tensile
specimen fused area should be from the
middle of the pipe wall. After machining,
condition test specimens by immersion
in temperature controlled circulating
air for not less than four hours or in
temperature controlled circulating water
for not less than one hour. Test at 73°F
and 2-in/min separation rate. Ductile
elongation should exceed 400% either
between the fusion and the end of the
gauge area, or for the entire gauge
area length. If desired, the tensile yield
strength of fusion test specimens and
pipe parent material test specimens may
be compared; however, the preferred
evaluation is ductile elongation rather
than tensile yield strength.
The pipes and specials shall be jointed
by automatic butt or electro fusion
welding to form a string above ground
and shall be supported by smooth
rollers. Three standard lengths of pipe on
each side of the fusion machine require
two roller supports per length of pipe.
All fusion joints shall be inspected and
assessed with joint record printouts from
the automatic butt or electro fusion
machine. Oasis personnel must approve
all joints before the contractor is allowed
to proceed with pipelining works. The
maximum pulling length of fusion jointed
PE pipes into position alongside or
directly into pipe trench after fusion
jointing shall not exceed 1,000 feet or
length limited by the hydraulic actuator
of the automatic butt fusion machine.
Dragging on ground surface is strictly
prohibited. All jointing of specials, tees
closing lengths etc., to be conducted in
the trench shall be by automatic electro
fusion couplers or other electro fusion
fittings.
Data logging records must be delivered to OMS personnel at the
completion of the project.
Section 4
45
Version 1.1
ASTM F2620 includes a bent strap test
for pipes having a wall thickness of 1 inch
(25 mm) or less. Butt fusions may be
evaluated by cutting straps from a trial
fusion and conducting an ASTM F2620
strap bend test. See Figure 2. The cut
through the fusion should be visually
examined. Voids or dis-bonded areas
are not acceptable. Strap specimens are
then bent with the pipe OD or ID to the
inside of the bend so that the ends of the
strap touch. Failure or dis-bonding at the
fusion is unacceptable.
F) Fusion Evaluation Tests – Mechanical Field and Laboratory Tests
ASTM standard tests and techniques
such as ASTM D638 tensile tests, ASTM
D1598 sustained pressure, ASTM D1599
quick burst, ASTM D1822 tensile impact
and ASTM F2634 high-speed tensile
impact are strongly recommended for
evaluating fusion joint quality. Published
ASTM testing procedures have been
confirmed to produce reliable, repeatable
results. Unproven, experimental, tests
and techniques even those that are being
developed, may be too stringent or
ineffective and are not reliable indicators
of fusion quality. Experimental tests
should not be used until published by
ASTM.
Tests such as root bend tests for metal
welds, bending a strap or coupon in
a bench vise, bending back and forth
multiple times, or hammering on bent
or unbent specimens are not reliable
indicators of butt fusion quality.
G) Weather Guidelines
Butt fusion can be successfully
performed over a broad range of field
conditions. However, some weather
and temperature conditions can affect
equipment operation or performance,
or could potentially introduce
contaminants, compromising joint
quality. Joining procedures may need
to be adjusted to compensate for wind,
weather or temperature. PE pipe and
fittings will expand and contract with
changes in temperature. If butt fusion
machine pipe clamp closure is limited,
shims of elastomeric material may be
necessary to secure very cold pipe
against slippage. In four-clamp machines,
shims should be used only in the outer
clamps.
1.A) Wind Effects
A windbreak or shelter should be used
when jobsite wind intensity exceeds
“gentle breeze” conditions.
Wind intensity above “strong breeze”
may require suspending fusing
operations.
4.5.4 Bending
A) Field-Bending – Steel Pipe
Joining procedures may need to be adjusted to compensate for wind,
weather or temperature.
46
Construction Guidelines
Contractor shall make all necessary field
bends required in the construction of
the line except those shop bends which
company shall specifically furnish.
Contractor shall also fit the pipe to the
contour of the bottom of the ditch, and
shall restrict the arc and increase the
radius of the bends to such an extent as
will prevent the buckling or flattening
of the pipe, weakening of welds, and
will permit the free passage through
said bend of an internal inspection type
of pipeline scraper. All bends shall be
made using a lined bending shoe so as to
eliminate scratching and gouging of the
pipe.
Dimensions across the minimum and
maximum axis of the field bends will
be subject to measurement and shall
not have a difference in excess of 2.53
degrees.
Each field bend shall comply with the
following:
The bend must be smooth and uniform.
On pipe 12 inches and larger an internal
mandrel shall be used.
After bending the pipe must be free from
buckling, cracks, or any other mechanical
damage and must conform to the profile
of the completed ditch.
There must be no wrinkle bends or
mitered bends (not including deflections
up to 3 degrees that are caused by
misalignment).
No girth weld may be placed inside
the bending shoe if the weld protrudes
above the outer wall of the pipe.
Pipe containing a longitudinal weld must
be bent so that the seam is located near
the neutral axis.
No bend shall be made any closer than 5
feet from the end of a joint or 3 feet from
an existing girth weld.
B) Field Bend Data - Steel Pipe
All field bends shall be made by the cold
stretch bending method, and an accurate
method of measurement shall be used to
determine the tolerances as follows:
4.5.5 Trenching / Excavation
A) Trenching / Excavation Permitting
1) Dig Permit
Prior to any excavation an Oasis dig
permit must be complete [OMS Form
1000]. Included in this permit are
required action items including: ensuring
the applicable state One Call system
has been utilized; all potential utilities
and facilities have been identified; and
areas of concern hydrovacced etc. If an
excavation is determined to be 48 inches
or greater in depth, adequate sloping,
shoring, or trench boxes must be created
or installed. Other action items include:
North Dakota One Call has been notified
and contacts conducted to determine
existence and location of underground
facilities in the work area.
Available records have been referenced
and a plot plan indicating the location
of all underground facilities has been
provided and is available for reference at
the job site.
Have Oasis operations personnel been
consulted for obtaining or discussing:
Section 4
47
Version 1.1
Plot plans
Pipeline or facility maps
Lease maps
Has the work area been checked for
facilities/pipelines, or utility markers?
And companies on markers contacted?
Are there ANY signs of ground
disturbance within the proposed work
area?
Have attempts been made to
communicate with landowner to verify
buried utilities?
All necessary approvals, notification and
agreements have been obtained.
A pre-job safety meeting including
JSA and emergency response plan
completed?
The proposed ground disturbance
area(s) are identified and all underground
facilities in the dig zone/search zone
have been identified and incorporated
into the plan.
Approved techniques for exposing
facilities with 2 feet of ground
disturbance have been (or will be)
used to verify the location of all known
underground facilities.
Other required Safe Work Permits have
been issued (Confined Space, Hot Work,
LOTO, etc.)
Precautions have been taken to prevent
contact with overhead power lines
New non-metallic underground facilities
are being installed with tracers
All personnel involved in the excavation
have received the appropriate training
Risk has been assessed and provisions
have been made to address unattended
open excavations to ensure the safety
of other contractors, the public, wildlife,
etc.
B) Daily Inspection
A competent person must inspect
trenches that individuals plan to enter, or
could potentially enter as a part of their
All trench boxes or shoring must be approved by the manufacturer to be used at the depth they are
planned to be used in, for the type of material they are supporting, and must not be modified in any manner
that could affect the integrity or safety of these units.
48
Construction Guidelines
work scope. Trenches will be tested for:
resistivity of the soil; porosity of the soil
(classification test); crumbling; distance
of spoil pile from trench; as well as any
shoring/trench box systems. All trench
boxes or shoring must be approved by
the manufacturer to be used at the depth
they are planned to be used in, for the
type of material they are supporting, and
must not be modified in any manner that
could affect the integrity or safety of
these units.
C) Trench Boxes / Shoring
Trench boxes and shoring are protective
measures designed to eliminate the
likelihood of a trench caving in while
personnel are working inside the trench.
These methods are required whenever
a trench or open excavation requires
an employee to work below 4 feet of
depth, and proper sloping cannot be
established. Trench boxes must extend a
minimum of 18 inches above the edge of
the trench, on both sides of the trench.
4.5.6 Lowering Pipe
A) Trench Bed Condition
The trench bottom shall be free from all
rocks, boulders, stones or hard particles
when particles, which may damage
the pipe walls. The trench bed should
maintain the minimum approved depth
taking into consideration the contour of
the land.
Before any pipes or specials are lowered
into the trench, they are to be inspected
again for deep cuts and scratches
described above. The fusion joints should
also have cooled sufficiently (specified
cooling time for the last joint has
elapsed) before stress is imposed on any
premade joints.
When lowering pipe into trenches, care
should be taken to avoid scoring of
the pipe by contact with the sides and
bottom of the trench. Special care is
needed when passing under/around
obstructions or other utilities.
Pipe roller supports for the first four
lengths of pipes from the pipe end to
be lowered into the trench shall be
provided. Cut section of rejected or
damaged PE pipes, planks and rope shall
be used for protecting the remaining
pipes where appropriate, but wire ropes
or chains shall not be used.
B) Trench Bed Material
Trench bottoms shall be layered with
well-graded earth that is free from
stones or hard particles larger that may
damage pipe. Under no circumstances
shall hot bending, in any form, be
allowed on site. A distance of one foot
from obstructions and other services
must be maintained for the length of
the pipeline. The pipe shall be kept as
central as possible within the trench
to enable correct side-fill compaction.
Some snaking to compensate for thermal
expansion of the pipe is acceptable.
Pipes and fittings to be embedded in
concrete shall be firmly held in position
and protected from damage during
pouring or compaction by a heavy-duty
polyethylene sheet. Should any pipe
or specials become either partially or
wholly clogged before final acceptance
of work, it shall be cleaned out or
replaced by the contractor at his own
expense.
After laying the interior of pipes or
specials shall be carefully cleaned to
Section 4
49
Version 1.1
remove any debris, dirt, stones or other
matter that may have entered during
installation.
Except when work is proceeding, all
open ends of pipes and specials in the
trench shall be kept closed by means of
a fine wire gauge, wooden stopper or
other approved means to prevent the
entry of dirt, soil, stones and the like, but
still allow the entry of water.
C) Inspection & Testing
Inspectors must look for deep cuts or
scratches that gouge deeper than 10%
of the pipe wall thickness. The depth
of these gouges should be measured
with approved depth gauges of suitable
accuracy supplied or approved by
OMS personnel. All damaged or flawed
sections of pipe will be cut out and
removed to the satisfaction of the Oasis
representative before jointing according
to OMS Section 4.13.
4.4.7 Welding
A) General
1.A) Contractors are responsible for
adhering to welding specifications and
guidelines set out by ASME B31.8.
1.B) Hot Work Permits must be
completed by contractors when any hot
work is performed on behalf of OMS.
B) Requirements
Joint design, materials, procedures
and practices shall be in accordance
with the latest edition of API standard
1104, “Standard for welding pipelines
and related facilities,” ASME code B3
1.8, “Gas Transmission and Distribution
Piping Systems” and all applicable DOT
regulations.
C) Method
Shielded metal-arc welding shall be used
for all manual welding. Gas metal-arc
and submerged metal-arc welding may
be used with prior approval from Oasis.
Back-up rings are prohibited.
D) Line Pipe Weld Procedures
1. Requirements
With manual, shielded metal-arc butt
welds, pipe with a wall thickness ¼ inch
and less shall have three weld beads.
Four or more beads shall be used on
pipe having a thickness greater than ¼
inch. Two welders will be used to run the
stringer bead on pipe 12 inches O.D. and
larger.
The second bead, or hot pass, shall be
applied immediately after the stringer
bead. Hot passes shall be completed
up to and including the last completed
stringer bead whenever the stringer
welding is stopped for any reason and
at the end of the day’s work. No two
succeeding passes shall start or stop at
the same point. All beads are to be made
by starting the pass near the top of the
pipe and proceeding downward on each
side of the pipe to the bottom. On any
land-laid section of line not more than
an interval of 25 joints shall separate the
hot pass welding and the filler and cap
welding processes. This interval may be
reduced by Oasis inspector if conditions
warrant. Before the end of the day, all
cap welding shall be complete.
2. Qualifications
Prior to the start of production a
detailed procedure shall be established
50
Construction Guidelines
and verified to demonstrate that welds
having suitable mechanical properties
and soundness can be accomplished by
this procedure. The quality of the welds
shall be determined by testing with the
destructive tests described below.
3. Records
The details of each qualified procedure
shall be recorded and maintained on
approved forms. This record shall show
complete results of the procedure
qualification tests. Similar records shall
be made for all weld methods employed
whether in field or shop construction.
Strict compliance with these procedures
shall be required during construction
except where a change is specifically
authorized by Oasis and its qualification
recorded.
4. Procedure Specifications
Contractor is responsible for maintaining
specific welding procedures and welder
qualifications as outlined in ASME B
31.8., however, Oasis may at times accept
other standards that are equal to or more
stringent than ASME B 31.8.
5. Line Pipe Welder Qualification
Welders must pass all required
verification tests in order to weld any
OMS DOT, or other line.
6. Qualification Test
Contractor shall provide only competent,
skilled and qualified welders. Each
welder shall be required to pass
satisfactorily a test in accordance with
ASME B 31.8 for each of the procedures
to which he will be assigned, before
being allowed to weld on the line.
Oasis’ welding inspectors or designated
qualified representatives, other than an
employee of the contractor, shall witness
the tests and judge the specimens.
A report form describing each of the
procedures and the results of each test
shall be completed for each welder
and submitted to the Oasis. A welder is
disqualified at any time during the test if
his performance is judged unsatisfactory
by an Oasis inspector.
7. Equipment
Contractor shall furnish all welding
equipment, prepare all spools used
in testing and shall bear all cost in
connection with the test other than the
cost of the pipe, which will be furnished
by OMS. Test welds will be accomplished
and the weld quality tested in
accordance with ASME B 31.8, unless
otherwise specified. An Oasis approved
pulling machine for tensile tests will be
furnished by contractor with certified
gauge and calibration dates and tests.
8. Preparation For Welding Line Pipe
8.A) Welding Surfaces
Welding surfaces must be thoroughly
cleaned so as to be dry and free from
paint, oil, rust, scale, and any other
material detrimental to weld quality.
Each bead shall be ground or buffed
before any following weld passes are
made.
8.B) Alignment
8.B.1) Joints
The ends of pipe to pipe or fitting to
pipe joints shall be aligned as accurately
as practicable in consideration of
Section 4
51
Version 1.1
the commercial tolerances on pipe
diameters, wall thickness and out-of-
roundness. Methods of alignment to
provide the proper size and deposition of
stringer beads shall comply API standard
1104, except as noted below:
Internal line-up clamps shall be used for
all welded joints on pipe sizes 12-inch
and larger, or where specified by Oasis,
except on tie-in and other prohibitive
joints. Internal line-up clamps shall be
left in place until the stringer bead has
been 1003 completed, unless otherwise
approved by company welding inspector.
External line-up clamps shall be left in
place until a minimum of 503 of the
stringer bead, which shall be equally
spaced, has been completed.
Spacing tools shall be used in
conjunction with the line-up clamp to
assure proper joint spacing and to permit
full weld penetration.
When external clamps are used, all
tack welds shall be ground to ensure
complete stringer bead continuity.
All slag cavities, surface porosity, cold
laps, starts and stops, and high points
shall be removed by grinding.
All slag and remaining flux shall be
buffed with a power buffer between
passes.
8.B.2) Rotation Of Seams
Electric resistance welded pipe shall be
aligned so that the longitudinal seams
will be located on either side of the
line within 30 degrees of horizontal.
Successive joints of pipe shall be rotated
to the right or left not less than 20
degrees, or have the seam located on the
opposite side to avoid aligning seams on
adjacent joints. Longitudinal seams on
pipe bends, however, shall be located 90
degrees from the radius of the bend. On
bends requiring more than one joint of
pipe, longitudinal seams shall be located
180 degrees from each other.
8.C) Weather
Welding areas must be protected from
conditions that would impair the quality
of the completed weld. At times this
may require constructing a barrier wall
or enclosure (provided with adequate
ventilation) to protect the welds from
adverse weather conditions.
8.D) Materials And Equipment For Welding
8.D.1) Electrodes - Rod or Wire
Electrodes shall be in size and kind
suitable for the material being welded
and acceptable to Oasis. They shall
conform to API standard 1104.
8.D.2) Shielding Gases
Shall conform to API standard 1104.
8.D.3) Handling & Storage
Welding electrodes must be protected
from all forms of deterioration prior
to actual use. Bectrodes and fluxes,
which show any sign of damage or
deterioration, shall not be used. Any
welding materials condemned by Oasis
welding inspector shall be promptly
removed from the job site and disposed
of according to contractors waste
management procedures.
52
Construction Guidelines
8.E) Equipment
8.E.1) Machines
Welding machines shall be operated at
the approximate voltage and current
ranges recommended for each type of
electrode used and shall not be operated
beyond their rated capacity. Generating
sets and/or automatic or semiautomatic
welding machines shall be maintained in
good working order and equipment that
does not meet OMS requirements must
be either repaired or replaced.
8.E.2) Leads
The ground leads of welding machines
shall be fastened securely to the pipe
metal by means of clamps or other
mechanical means (not by welding). No
arcing between the ground leads and the
pipe will be permitted and any leads with
insulation damaged to the extent that
wire is exposed shall be discarded.
8.F) Inspection & Testing of Line Pipe Welds
8.F.1) Non-Destructive Testing
All completed weld surfaces and
surrounding areas shall be cleaned and
excessive spatter must be removed prior
to welding inspection.
Radiographic Inspection
All field welds must have a radiographic
inspection completed for 10% of the
weld. A larger percentage up to and
including 10% of the field welds may be
inspected at OMS discretion. A minimum
of 10% of all field welds made within
railroad or public highway ROW, river
and stream crossing rights-of-way,
above ground piping, and at tie-ins will
be inspected for 10% of the weld. The
contractor may be required to provide
transportation to the job site and along
the ROW as well as to provide space at
the work location for equipment and
personnel.
Leads
Magnetic particle, ultrasonic, or other
non-destructive test methods may be
utilized at OMS discretion.
Defects
All welds or portions of welds disclosed
by radiographic inspection to be
defective will be repaired in accordance
with API 1104 at contractor’s expense.
Welds which are found to be defective
by OMS inspectors will be cut out and
tested in the method described in
section 8.H of this manual.
8.G) Visual Inspection
Completed welds must be visually
inspected and marked as acceptable
by OMS inspectors before the joint
coating is applied. It will not be deemed
satisfactory unless it meets the standards
of acceptability and testing requirements
as defined in API standard 1104 for
welding of pipelines.
8.H) Destructive Tests of Field Welds
Contractors will be responsible to cut
out any welds as required by Oasis
and deliver the sample for testing and
examination, and re-weld the pipe. OMS
will not require the contractor to cut out
more than one non defective weld per
welder without reimbursing contractor,
Section 4
53
Version 1.1
regardless of whether the weld was
cut out because of the results of non-
destructive testing methods (other
than radiographic), visual inspection or
other reasons. Coupons cut from test
welds shall be pulled for tensile strength
by an OMS approved pulling machine,
furnished by contractor. Welds may
be further tested by cutting additional
coupons for bend tests and nick-
break tests and the ductility and grain
structure of the welded metal examined.
Contractors will replace all defective
welds and one non-defective weld per
welder at their expense. A record of the
results of each test shall be jointly signed
by an Oasis representative and the
contractor.
8.I) Weld Identification
Oasis shall assign a specific number
to each contractor welder. It shall be
the duty of each welder to personally
affix such number with a permanent
waterproof felt or paint marker, adjacent
to each weld on which he works for
future identification. In the event any
welder leaves the project, his number
will be voided and not duplicated
when another welder is utilized. If
radiographic or physical tests indicate
the production of defective welds, the
welder responsible shall be disqualified
from further welding on the project.
Should two or more welders participate
in making the defective welds, the
contractor, welding foreman and OMS
inspector shall determine which welder
was responsible for the defective work.
8.J) Replacement of Test Welds or Rejected Welds
When welding the line together at places
where welds have been removed, if
possible, one weld shall be made after
moving the line back into position;
otherwise two welds shall be made by
installing a spool with the minimum
length of 1¼ times the pipe diameter.
8.K) Repair of Weld Defects
Weld defects, other than cracks, may be
repaired if the weld was not previously
repaired if authorized by an OMS
inspector. Such defects shall be removed
by grinding to clean, sound metal before
re-welding and shown by radiographic
inspection to be free of defects before
acceptance. Should laminations, split
end or longitudinal seam defects be
discovered in the pipe, the full joint
containing the defect shall be removed
from the line.
8.L) Standard of Acceptability
Minimum acceptable standards for
penetration, fusion, burned-through
areas, slag inclusion, gas pockets,
discontinuities and undercutting shall be
in accordance with API standard 1104,
and ASME 831.8 code.
8.M) Arc Burns
Contractor shall prevent arc burns. Arc
burns, where they occur, shall be cut out
at contractor’s expense.
8.N) Preheating & Stress Relieving
8.M.1) General Practices
The welding procedure shall specify the
preheating and stress relieving practices
to be followed when materials or
weather conditions make either or both
necessary.
54
Construction Guidelines
8.O) Preheating
When the weld procedures and/or
carbon content or the carbon equivalent
of the pipe requires preheating, or the
ambient temperature is 40°F or less,
the weld zone shall be preheated to an
appropriate uniform temperature. The
hot pass shall be made no longer than
five minutes after the stringer bead and
before the weld joint is cooled to below
200°F. The preheating temperature shall
be accurately tested to assure that the
required temperature is obtained prior
to and maintained during the welding
operation. OMS will pay for preheating
required during cold weather. Preheating
required by weld procedures will not be
paid by Oasis.
8.P) Stress Relief
Stress relieving may be designated
by Oasis and shall be accomplished
in accordance with the instructions
in ASME b 31.8 and the Oasis welding
inspector. Butt welds on weld-end valves
shall not be stress relieved and in no
case shall cold expanded pipe be stress
relieved. Oasis will pay for stress relief.
4.5.8 Boring
A) Equipment Requirements
Directional boring equipment must
have a rig of sufficient capacity to
perform the bore and pull back the
pipe, a boring fluid mixing and delivery
system of sufficient capacity to
successfully complete the crossing, a
guidance system to accurately guide
boring operations and trained and
competent personnel to operate the
system. All equipment shall be in good,
safe operating condition with sufficient
supplies, materials and spare parts on
Diagram 4.5A
Section 4
55
Version 1.1
hand to maintain the system in good
working order for the duration of this
project.
B) Boring System
1. Boring Machine
The directional boring machine shall
consist of a hydraulically powered
system to rotate, push and pull hollow
drill pipe into the ground at a variable
angle while delivering a pressurized
fluid mixture to a guidable drill (bore)
head. The machine shall be anchored
to the ground to withstand the pulling,
pushing and rotating pressure required
to complete the crossing. The hydraulic
power system shall be self-contained
with sufficient pressure and volume
to power boring operations. Hydraulic
system shall be free of leaks. Rigs shall
have a system to monitor and record
maximum pullback pressure during
pullback operations. Boring rigs must be
grounded during boring and pullback
operations. Sufficient spares shall be kept
on hand for any breakdowns, which can
be reasonably anticipated.
1.A) Bore Head
The bore head shall be guided by
changing it’s rotation and shall provide
the necessary cutting surfaces and
boring fluid jets.
Mud motors shall be of adequate power
to turn the required boring tools.
It is required that the boring profile is
supplied electronically, with operator’s
signature and supplied upon invoice.
1.B) Guidance System
The Guidance System shall be of
a proven type and shall be set up
and operated by personnel trained
and experienced with this system.
The operator shall be aware of any
magnetic anomalies and shall consider
such influences in the operation of the
guidance system if using a magnetic
system.
2. Boring Fluid (Mud) System
2.A) Mixing System
A self-contained, closed, boring fluid
mixing system shall be of sufficient
size to mix and deliver boring fluid
composed of Bentonite clay, potable
water and appropriate additives. Mixing
system shall be able to molecularly
shear individual Bentonite particles from
the dry powder to avoid clumping and
ensure thorough mixing. Mixing system
shall continually agitate the boring fluid
during boring operations.
2.B) Boring Fluids
Boring rigs must be grounded during boring and pullback
operations.
56
Construction Guidelines
Drilling fluid shall be composed of clean
water and an appropriate additive.
Water shall be from a clean source with
a pH of 8.5-10. Water of a lower pH or
with excessive calcium shall be treated
with the appropriate amount of sodium
carbonate or equal. Water and additives
shall be mixed thoroughly and be absent
of any clumps or clods. No hazardous
additives may be used. Boring fluid shall
be maintained at a viscosity sufficient
to suspend cuttings and maintain the
integrity of bore wall.
3. Delivery System
The mud pumping system shall have
a gallon per minute (GPM) capacity
equal to the hole size and be capable of
delivering the boring fluid at a constant
minimum pressure of the same. The
delivery system shall have filters in line to
prevent solids from being pumped into
the drill pipe. Connections between the
pump and drill pipe shall be relatively
leak-free. If fluid is anticipated to leave
the ROW, it is recommended that
contractors utilize containment methods.
Used boring fluid and boring fluid
spilled during boring operations shall
be contained and properly disposed of.
Berms constructed a minimum of 1 foot
high, shall be maintained around boring
equipment, boring fluid mixing system,
entry and exit pits, and boring fluid
recycling system (if used) to prevent
spills into the surrounding environment.
Pumps and or vacuum truck(s) of
sufficient size shall be in place to convey
excess boring fluid from containment
areas to storage facilities.
4. Pipe Rollers
Pipe rollers, if required, shall be of
sufficient size to fully support the weight
Diagram 4.5B
Section 4
57
Version 1.1
of the pipe while being hydro-tested and
during pullback operations. Sufficient
numbers of rollers shall used to prevent
excess sagging of pipe.
C) Other Equipment
1. Pipe Rammers/Pullers
Hydraulic or pneumatic pipe rammers
or pullers may only be used if necessary
and with the authorization of Engineer.
2. Other Equipment
Other devices or utility placement
systems for providing horizontal thrust
other than those previously defined in
the preceding sections may only be used
if approved by OMS personnel.
D) Boring Operations
1. General
OMS engineering group and inspectors
must be involved in pre-job meeting
prior to boring operations starting. The
directional bore shall not begin until an
OMS representative is present at the job
site and agrees that proper preparations
for the operation have been made. The
engineer’s approval for beginning the
installation shall in no way relieve the
contractor of the ultimate responsibility
for satisfactory completion of the work
as authorized under the contract.
It is the responsibility of the construction
department to provide inspectors
without causing undue hardship by
reason of delay to the contractor.
All personnel shall be fully trained in
their respective duties as part of the
directional boring crew as well as in all
safety considerations. Training shall be
provided specific to the project if any
potential hazards may be encountered
which has not already been included in
Diagram 4.5C
58
Construction Guidelines
personnel’s training.
2. Boring Procedure
2.A) Site Preparation
Prior to any alterations to the worksite,
contractor shall photograph or record a
video of the entire work area, including
entry and exit points. One copy of which
shall be given to engineer and one copy
to remain with contractor for a period of
one year following the completion of the
project.
Worksite as indicated on drawings
within the ROW shall be graded or filled
to provide a level working area. No
alterations beyond what is required for
operations are to be made. Contractors
shall confine all activities to designated
work areas.
2.B) Bore Path Survey
Drill paths will be accurately surveyed
with entry and exit stakes placed in the
appropriate locations within the areas
indicated on drawings. If contractors are
using a magnetic guidance system, the
drill path will be surveyed for any surface
geomagnetic variations or anomalies.
2.C) Environmental Protection
Contractor shall place silt fence
between all boring operations and any
drainage, wetland, waterway or other
area designated for such protection as
outlined in contract documents, state,
federal or local regulations. Additional
environmental protection necessary to
contain any hydraulic or boring fluid
spills shall be put in place, including
berms, liners, turbidity curtains and other
measures. Contractors will adhere to all
applicable environmental regulations.
Fuel or oil may not be stored in bulk
containers within 200 feet of any body
of water or wetland.
OMS personnel must be present prior to
releasing any wastewater on any OMS
ROW.
E) Utility Locates
Contractors are responsible to notify
companies with underground utilities
in the work area via the state or local
One Call to obtain utility locates
(811). Once utilities have been located
contractor shall physically identify
the exact location of the utilities by
vacuum or hand excavation, when
possible and necessary, in order to
determine the actual location and path
of any underground utilities which
might be within 20 feet of the bore
path. Contractor shall not commence
boring operations until the location of
all underground utilities within the work
area have been verified.
4.6 Tie-Ins
4.6.1 General
The intent of this section is to provide
guidance for construction operations
regarding the connecting of two or more
pipelines with the intent of optimizing
pipeline infrastructure.
A) Water Considerations
Tie-ins or tested sections containing fill
water for sections to be subsequently
tested shall not be made in cases where
excessive air, entrapped as a result of the
tie-ins, will be injected into the section to
be tested.
Section 4
59
Version 1.1
*Note that in many cases the loss of
water at tie-ins will be considerable.
In such cases this water shall not be
allowed to flow into running streams,
rivers or wells that are used for domestic
water supplies.
B) Backfilling
[ref. Section 4.13] at the tie-in sites shall
be carried out in accordance with the
General Construction Specifications.
C). Cold Cutting
Cold cutting must to be completed with
either non-sparking equipment on live
tie-ins or by means of a guillotine system.
Safe grounding measures are to be used
in order to discharge static electricity
build up must be utilized.
D) Live Tie-In
1. Hot Tap
1.A) General
Hot taps performed on a pipeline under
pressure will only be performed by a
crew qualified to perform this type of
operation. Contractors must supply
sufficient documentation to OMS
indicating qualification of individuals
performing hot tap procedures.
1.B) Requirements
Hot Tap design, materials, procedures
and practices shall be in accordance
with the latest edition of API Standard
2201, “Procedures for Welding or Hot
Tapping on Equipment Containing
Flammable Liquids”; API Standard 1104,
“Standard for Welding Pipelines and
Related Facilities”; API Standard 1107,
“Recommended Pipeline Maintenance
Welding Practices”; ASME B31.8,
“Gas Transmission and Distribution
Piping Systems”; and all applicable
DOT Regulations, except as otherwise
specified herein.
1.C) Welding Personnel
Welders must be qualified in accordance
with ASME B 31.8 and API 1104. They
shall be thoroughly familiar with welding
equipment and procedures to be used.
For additional information please
reference section 4.4.7(D) of this manual.
1.D) Welding Design
Only full encirclement type saddles are
to be used for the branch connection.
Fillet welding procedures for the full
encirclement saddle shall be specified in
within release alignment sheet.
Full penetration welding on branch
connections and longitudinal butt-
It is essential that all surfaces remain clean before, during and after the
welding process.
60
Construction Guidelines
welding on reinforcing saddles shall
follow standard welding procedures
outlined in API Standard 1104 and 1107.
2.) Fillet Welding Procedure
2.A) Process
Welding shall be done by the shielded
metal arc welding process.
2.B) Parent Metals
Metals welded according to this standard
shall be Grade A through X-70.
2.C) Diameter & Wall Thickness
This procedure shall apply to material
having any diameter or wall thickness.
2.D) Joint Design
2.D.1) Branch Connections
Branch ends must be beveled to an angle
of 45°, plus 5°, minus 0°, with a root face
of 1/16” ± 1/32”. The root opening shall be
1/16” ± 1/32”
2.D.2) Sleeves
Side seams shall be beveled to an angle
of 30°, plus 5°, minus 0°, with a root face
of 1/16”±1/32”. The end preparation shall
be 90° ± 5° with as little space between
the sleeve and the pipe as possible.
2.D.3) Filler Material
The filler material shall conform to A.W.S.
Classification A5.5, E-8018-C3, Group
F-4, weld analysis A-10.
2.E) Electrical Characteristics
The welding current shall be D.C. reverse
polarity (electrode positive).
2.F) Direction of Welding
Welding shall proceed upward from
bottom center or any point of the side of
the pipe to top center.
2.G) Speed of Travel
The speed of travel shall be within the
range of 4 to 13 inches per minute,
inclusive.
2.H) Number of Welders
One welder may be used to run the
stringer bead (root bead) when the
nominal branch diameter for branches
or the nominal run diameter for sleeves
is less than 16 inches. When the nominal
branch diameter is 16 inches or greater,
two welders will be required to run the
stringer bead. Oasis reserves the right
to require additional welders for the
stringer bead without altering the unit
price, if, in Oasis’S opinion, danger of
stringer bead cracking exists or slow
progress is experienced. One welder may
be used to run all passes subsequent to
the stringer bead on all sizes of pipe.
2.I) Time Lapse Between Passes
The second pass (“Hot Pass”) shall follow
the stringer bead (root bead) within
five minutes, except when unavoidable
circumstances prevail which make this
requirement impractical. All second
passes shall be completed before the
end of the day. The entire weld should be
finished before the end of the day.
2.J) Line-Up Clamp
Section 4
61
Version 1.1
Line-up clamp must properly align the
pieces of pipe intended to be welded.
2.J.1) Branch Connections
Spacing tools and manual holding
during tacking off is acceptable if
correct stringer bead space and proper
alignment is maintained; if not, then
mechanical holding devices are required.
2.J.2) Sleeves and Patches
Chains, clamps, hydraulic jacks or other
similar mechanical holding devices shall
be used to hold the sleeve or patch in
intimate contact with the pipe before
welding starts.
2.K) Removal of Line-Up Clamp
When repairing leaks, clamping devices
shall remain in place until all welding
is completed. On other fillet welds, the
clamping devices may be removed
whenever tacking adequate to maintain
spacing and alignment has been
completed.
2.L) Cleaning
It is essential that all surfaces remain
clean before, during and after the
welding process. All dirt and foreign
matter must be removed from the
beveled surface before welding begins;
the bevel surface includes the area on
the inside of the pipe in the immediate
proximity of the pipe end. Slag shall
be removed from the bead surface
before the next bead is applied. Power
tools may be used. The finished weld
and immediately adjacent pipe must
be cleaned of all flux, smoke and weld
splatter.
2.M) Preheat
Preheat shall be required when moisture
is present on the parent metal; it
shall be driven off by preheating to a
temperature at which it will not reform
during the welding operation.
3. Hot Tap Operation
Hot Tapping operations are to be carried
out by a qualified technician who is
thoroughly familiar with all applicable
safety procedures and industry
standards.
4. Testing
1. The metal thickness of the
existing header is to be measured
radio graphically, and absence of
imperfections is to be verified prior to
beginning any part of the welding or hot
tapping procedure.
Pits for boring shall be excavated no more than 48 hours in advance
of boring operations and backfilled within 48 hours of boring operation
completion.
62
Construction Guidelines
2. All welds are to be tested in
accordance to company 1003 spec and
up to judgment of welding inspector.
3. After welding of the full encirclement
saddle is complete, but before hot
tapping begins, the branch connection is
to be completed in the manner in which
it will be operating, and a hydrostatic test
performed.
E) Squeezing
Squeeze tools will only be used in
emergency situations, and not ordinarily
in day-to-day operations. Isolation and
drain down areas (prior to hot-tap,
etc.) will be implemented in normal
conditions.
Squeeze tool availability must be verified
prior to operations commencing when
the likelihood or the risk of a line strike is
thought to be high.
4.7 Crossings
4.7.1 General
This section provides guidance on
the processes implemented when
crossing OMS, or foreign utilities during
construction processes.
A) Approvals
OMS will obtain easement permits
for highway, line, or railway crossings
prior to any foreign facility crossings.
It is expected that contractor will not
perform excavation on the highway or
railroad ROW without direct written
approval from OMS. Contractors are
responsible to review all permits and be
knowledgeable about the provisions and
restrictions of crossing permits and shall
conduct the work in strict accordance
with such requirements and restrictions,
including notification of highway and
railway representatives. Contractors
may not cut into any highway or road
surface of concrete, asphalt, gravel, oil
or any binding material without written
permission from the authority under
whose jurisdiction the permit is issued.
B) Line Crossings
Oasis Petroleum’s land department
shall obtain approval from the owners
of foreign pipelines and stakeholders
for the installation of test leads on the
foreign line (if necessary). Contractor
shall, upon receipt of owner’s approval,
install test leads on the foreign line
and repair the coating to the owner’s
satisfaction. Test leads may only be
installed by individuals with adequate
training who possess cathodic protection
certifications.
C) Road crossings
State & County Road Crossing County
regulations must be referenced prior to
any civil construction or deconstruction
operations commence.
D) Water Crossings
Contractors shall construct pipelines
across drainage ditches, bayous, creeks,
streams, canals, rivers and adjacent
lowlands and flood plains. No extra
payment will be made to contractors by
OMS for such ditches, creeks and rivers.
Such crossings are to be considered a
part of the project and are expected to
be a part of the contractors bid.
Section 4
63
Version 1.1
1. Weights & Anchors
Sections of pipeline intended to
be laid across lakes; washes; rivers
and waterways must be weighted
or anchored as specified by Oasis.
Contractors must furnish all materials
and equipment including weights and
anchors. Contractors are responsible
for transporting stringing and installing
weights and anchors at locations and
in the manner designated by OMS
personnel.
Several thicknesses of rock shield shall
be placed between the pipe and each
weight. Where weights are installed on
long sections of pipe, care shall be taken
in handling to prevent buckling of the
pipe.
Pipeline anchors must be installed
in accordance with manufacturer’s
specifications. During installation, every
precaution shall be taken to prevent
damage to the pipe and coating.
E) Boring Crossings
When paved roads are crossed, boring
shall be done from pits located a
minimum of 30 feet from the edge of
pavement on fully access-controlled
highways and at a distance of 10 feet
plus the depth of pit without shoring
on conventional highways. If shoring
is used, the pits shall be located at a
minimum of 10 feet from the pavement
on conventional highways. Such shoring
shall be installed immediately after
excavation of the pit and it shall be
constructed and maintained so that it
will safely support all vertical and lateral
loads that may be imposed upon it
during the boring operation.
Pits for boring shall be excavated no
more than 48 hours in advance of boring
operations and backfilled within 48
hours of boring operation completion.
F) Section Lines
Facilities installed near section lines to
be a minimum of 2 feet deeper than
depth of trench. Section lines have the
potential to become roads in the future,
and this should be considered when
crossing section lines.
4.8 Civil Construction
4.8.1 General
This section overviews construction in
relationship to roadways, railways, and
other public or private use structures,
generally operated alongside the
transmission of petroleum, water, or
other assets.
A) Cement
All concrete installations shall be
constructed as shown on the drawings
and details. It is imperative that the
concrete mixture meets all requirements
in order to ensure the integrity of the
system
All cement shall conform to the latest
edition of ASTM C-150 and all concrete
shall conform to the latest edition of
ASTM C-94.
All concrete, concrete placement,
curing, deformed reinforcement bars,
testing and other applicable concrete
requirements shall be in accordance with
applicable standards regarding concrete
construction.
64
Construction Guidelines
B) Structural Steel
The fabrication of structural steel shapes,
connection plates, base plates and
bolt holes shall conform to the AISC
“Specification for the Design, Fabrication,
and Erection of Structural Steel for
Buildings” in the latest edition of the
Manual of Steel Construction.
1. Handling
All structural materials shall be handled
in a manner to prevent material damage.
The material shall be supported on skids
that are properly spaced to prevent
permanent deflection in the structural
member. Skids shall be of adequate size
to keep the material above ground, clean
and properly drained.
2. Workmanship
Workmanship shall conform to AISC
specifications. Bolt holes to secure other
materials shall be as shown on drawings.
3. Erection
Erection shall be in accordance with
AISC specifications, and shall include the
setting of all columns; beams; trusses;
grating; floor plates; handrails; the
installation of cranes; and the erection
of all other structural steel to true line,
grade and flushness.
4. Field Connections
Field connections shall be bolted and
bolts drawn up tight and set, so that nuts
will not become loose. All bolt-ups need
to adhere to torque specs with markings
to identify that the last bolt secured.
Drifting, other than light drifting
necessary to draw the holes together,
will not be permitted.
Welding shall be done in accordance
with the Code for Fusion Welding and
Gas Cutting in Building Construction
Code I Part A, Structural Steel, of the
American Welding Society.
5. Cutting & Fitting
Cutting of flanges, webs or angles will
not be permitted without prior OMS
approval.
6. Grouting
All bearing plates, loose lintels, beams
and columns shall be set to proper grade
and level before grouting.
7. Cleaning & Painting
All structural steel shall be cleaned
and painted in accordance with colors
outlined in project plan.
C) Roads / Walkways
Normal location walkways need to be
installed to prevent slip, trip and fall
hazards due to inadequate walking
surfaces. Material such as scoria/gravel
should be used.
D) Location / Well Pad
All locations and well pads should have
a engineered drawings representing all
underground lines; utilities lines; well
names; roads; crossings; foreign lines
leaving location; old reserve pits located;
and equipment (electrical & mechanical)
logged to map.
Section 4
65
Version 1.1
4.9 Facility Construction
4.9.1 General
Facility construction covers many
important aspects of OMS operations.
The quality of the equipment provided,
as well as ensuring the proper application
and planning is imperative to the safe
and efficient operation of OMS pipelines.
A) Pumps
1. Installation
Depending on the elevation and
number of wells on site, pumps are
sized accordingly by OMS engineering
personnel.
Hand sketched drawing are sent from the
field to welding shops.
CAD drawings are then produced with a
Make to Order (MTO) for project scope.
Parts are ordered and documented as
a part of the project file. Fabricated
packages are to be delivered to the
field and recorded using OMS required
Material Transfer Forms. Electronic
versions must be given to OMS personnel
as well as hard copies maintained in the
field. Fabrication shops must maintain
X-ray maps, Material Transfer Forms and
welder information.
Pumps will ordinarily be constructed
prior to being delivered to the field. All
drawings and plans are required to be
preapproved by OMS engineers.
B) Houses
In most applications, houses will be
designed and built prior to being
installed on locations.
1. Installation
Houses are to be set, leveled and sealed
at the time of pump set. Considerations
must be taken to identify prevailing wind
direction in order to protect doors from
being damaged.
2. Insulation
Freshwater connections are to be heated
and insulated to prevent freezing.
3. Heat Tape
Any pipe that is exposed to the elements
above ground require heat tape and
insulation to prevent freezing.
C) Risers
Risers are to be constructed by certified
API 1104 welders. They will have both a
purge as well as a non-purge procedure.
We will use 316 stainless steel for all
saltwater above ground pipe. The
riser should be coated with a VisoTaq
Coating.
D) Instrumentation and Electrical (I&E)
1. Automation
Transfer pumps are controlled by
two controls, one is located within
production tanks and monitors high
and low levels, the other is the pressure
transducer controlling the pump per its
engineered MAOP.
2. Measurement
Measurement meters must be calibrated
frequently to ensure accuracy.
How frequently this occurs is to be
designated by OMS Engineering. All
66
Construction Guidelines
calibrations must be accompanied with
documentation.
Leak tests should be performed
quarterly.
4.10 Coating
4.10.1 General
Protective coatings are imperative for the
integrity of all pipelines. Dings, scrapes
or nicks can cause anomalies that last the
lifetime of the line, and pose serious risk
to all stakeholders near pipelines as well
as significant risk to the environment.
A) Painting
1. Surface Preparation
Surface shall be degreased prior to
sandblasting. Organic solvents, alkaline
solutions, steam, hot water with
detergents, or other systems that will
completely remove dirt, oil, grease, etc.,
may be used.
1.A) Edge Preparation
All edges shall be ground to a minimum
of a 1/8 inch radius. This includes clips,
baffles, nozzle connections, etc.
1.B) Surface Abrasion
The immersion service surface shall
be blasted to a NACE (National
Association of Corrosion Engineers)
No. 1 or SSPC (Society for Protective
Coatings)-sp5-63 white metal blast
cleaned surface. An anchor pattern or
“tooth” in the metal shall be established
according to the coating manufacturer’s
recommendations. The anchor pattern
shall be sharp and no evidence of a
polished surface is allowed.
1.C) Sandblasting
The external surface to be painted shall
be blasted to a NACE no. 3 or SSPC sp-
6-63 commercial blast cleaned surface.
The surface profile should be 1.5 to 2.0
mils.
Blasting shall be done with washed
sharp silica sand of 16/35-grade mesh
or finer. This sand shall be clean, dry
and free of clay particles and other
extraneous matter or, the grit used shall
be sharp silica sand, steel slag grit similar
or equal to black beauty bb 16 or any
other abrasive that has a sharp hard
cutting surface, properly graded, non-
contaminating, dry and best quality.
Steel surfaces shall not be blasted when
the surface temperature is less than 5°F
above the dew point, relative humidity is
greater that 80%, or there is a possibility
that the blasted surface will be subject
to wetting before the first coat of primer
can be applied. No painting shall take
place when the ambient temperature is
below 50°F.
1.D) Surface Cleaning after Sandblasting
Traces of blasting abrasive and dust
must be removed with a vacuum
or by brushing. Care must be taken
to avoid contaminating the surface
with fingerprints or from foreign and
potentially detrimental material from the
workers clothes or shoes.
1.E) Immediate Priming
Freshly blasted surfaces are subject to
immediate corrosion, particularly in areas
of high humidity. After surfaces are blast
cleaned then they can be prime-coated
before visible or detrimental re-rusting
Section 4
67
Version 1.1
occurs. Blasted surfaces shall be prime-
coated or plastic-coated no later than at
the end of the same workday.
A 12-inch wide strip of uncoated, blasted
surface shall be left between primed
surfaces and those non-blasted surfaces
to prevent damage to the newly dried
coating when additional blasting is
done. When blast cleaning is resumed,
the 12-inch strip of previously blasted
surface shall require only a light brush
blast to remove any rust that might
remain. Cleaning shall be accomplished
by holding the cleaning nozzle in a
direction away from the coated surface
and personnel.
1.D) Compressed Air Quality
The compressed air used for blasting
shall be free of detrimental amounts of
water and oil. Adequate traps, filters
and separators shall be provided at the
compressor and must be checked daily.
1.E) Metallic Surfaces
All non-metallic surfaces shall be clean,
dry and free from scale, oil and dirt.
Contractors shall protect all gasket
surfaces, valve stems, name plates,
pressure gauges, instrument cases,
gauge glasses and all previously
installed and coated equipment
including galvanizing. If the coating on
any previously installed equipment is
damaged, the damage will be repaired
at the contractor’s expense. If any
previously installed equipment is
damaged during coating, the equipment
will be replaced or repaired by the
contractor. All tape protection shall be
removed after coating.
B) External Painting
All piping, equipment, structures
and metal portions of buildings, not
galvanized or of aluminum construction,
shall be painted to protect against
corrosion and to provide a satisfactory
appearance. Equipment and piping to
be insulated will be protected with one
primer coat only. A minimum of one
primer coat and one finish coat shall
be applied to un-insulated equipment.
Floors may be colored, coated or hard-
surfaced as specified.
Paint shall be spray applied in
accordance with the manufacturer’s
recommendations. Any or additions by
the company will take precedent over
the manufacturer’s recommendations.
Only competent personnel applying
coating by proper techniques are
authorized to perform this task. After
coatings have been applied facilities shall
not contain sags, runs, wrinkles, spots,
blisters or other application flaws which
would cause premature coating failure.
The finished external coating shall be
free of holidays when checked with a
67.5 volt Holiday Detector.
1. Coating Equipment Inspection
All spray equipment shall be inspected
and approved by OMS personnel before
any application is begun.
2. Moisture Trap
Moisture traps are to be used by placing
them in line from air supply to pressure
pot and spray gun. This trap shall be
opened slightly to provide a continuous
bleed.
68
Construction Guidelines
3. Use of Regulators/Gauges
Regulators and gauges shall be provided
for air to both pressure pot and spray
gun.
4. Application Distance-Primer
Primer shall not be applied closer than
12-inches to a non-blasted area. Any
subsequent blasting operation shall not
result in sand particles being embedded
in the paint film.
5. Spray Guns
Spray guns are to be held perpendicular
to the surface being painted, and
handled and adjusted in such a manner
that dry overspray is kept to a minimum.
6. Sequence
The sequence to be followed in painting
shall be such that a minimum of damage
to finish coatings will result.
7. Confined Space Ventilation
When paint is being applied to the
interior of tanks or confined areas,
sufficient blowers and fans shall be
installed to provide adequate ventilation.
8. Priming
The prime coat shall be a high build type
with a minimum dry film thickness of five
(5.0) mils to six (6.0) mils, depending on
the brand used.
9. Brand Use
All materials required for external
painting and finishing shall be of the
brand(s) manufactured by: Polyguard or
a similar vendor provided the quality is
not reduced.
Ground level protection should be
ViscoTaq Coat Wrap ST or equivalent.
Changes in brand/type may be
approved, but only by OMS written
authorization.
Coating materials shall be stored in a
cool dry place free from the potential
of spark or flame. Paint materials
susceptible to freezing are not to be
stored where the temperature will drop
below 32°F. All such materials shall be
used or applied in strict accordance with
manufacturer’s directions.
10. External Applications
Application of the external coatings is
allowed only when the air, surface and
product temperatures are above 50°F
and at least 5°F above the dew point.
One finish coat of not less than two (2.0)
to two point five (2.5) dry mils must be
applied.
11. Additional Coats
Surfaces are not to be recoated until the
preceding coat has properly dried or
cured. The surface may be considered
ready for recoating when the next coat
can be applied without the development
of paint film irregularities, such as lifting
or loss of adhesion of the undercoat.
However, the minimum or maximum
drying or curing time specified by
the paint manufacturer shall be the
acceptable recoat period. Paint shall not
be force dried under conditions that will
cause wrinkling, blistering, formation of
pores, or which will be detrimental to its
condition or appearance.
Section 4
69
Version 1.1
12. Paint Thinning
Only best quality products will be used
and paints shall be thinned only as
recommended by the manufacturer.
Resin systems or two component
systems will be used within the pot-life
time specified and in no case shall any
thinning be used.
13. Curing
Each coat will be thoroughly dried or
cured before the next coat is applied.
14. Paint Damage
Where paint has been damaged in
handling, all damaged and loosely
adhering paint shall be removed and the
surface thoroughly cleaned. Edges of the
breaks shall be feathered and designated
prime and finish coats applied.
C) Jeep Sticks
If a nick (or holiday) is found in a coated
steel pipe, a hot melt patch is needed
to repair it. Recommended use of 3M
Scotchkote Hot Melt Patch Compound
226P.
Holiday detection equipment must be
used to detect holidays in the coating of
the pipe.
F) Pipe Wrap / Tape
For rocky soil a protective coating wrap
such as Tuff-N-Nuff Rockshield should
be used to keep large jagged edges from
affecting the coating of the pipe. (See
Appendices)
G) Insulation
Pipe should be adequately insulated if
placed above 4 feet in depth. The quality
of the insulation such be such that the
R-Factor can protect against anticipated
temperatures.
4.11 Tracer Tape & Wire
4.11.1 General
It is imperative that all utilities installed
by Oasis Midstream Services have the
ability to be located. This includes
correct installation, and integrity
management of locating devices.
A) Depth
All tape must be installed above the
pipe and a minimum of 2 feet below the
surface of the top of the existing ground
surface and be made of magnetic
material. When soil is crowned, tracer
tape may need to be installed at an even
greater depth. Consult OMS personnel if
adequate depth is in question.
B) Wire Location
All tracer wire must be installed
according to section DOT 192.321 or 195.
Test leads should be installed ideally
every ¼ mile to ensure adequate
coverage.
Test leads shall be color coded with
a proper sticker to indicate company
name, product in pipe and emergency
contact, preferably a tri-sided
(triangular) post.
70
Construction Guidelines
C) Wire Protection
Wires must be protected from corrosion
as well as from abnormal protrusions
underground. For this reason anode
protection is required. Tracer wire
should be constructed to the following
specifications:
Composed of a dead soft annealed
copper conductor utilizing UNS C10200
grade copper;
Insulated in 45 MIL High Density,
High Molecular Weight Polyethylene
(HMWPE);
Shall be UL listed, rated for direct burial,
moisture, gasoline and oil resistant, and
suitable for operations at 600 volts.
4.12 Backfill
4.12.1 Material
The quality and type of material used
for backfilling after construction is
imperative to the life of the pipeline.
Using material of poor quality, can either
damage the pipe or require contractors
to return to the ROW to re-compact
soil. Backfill 12 inches above top of pipe
shall be free from rocks, frozen clods
or other hard objects. Contractors
are required to bear the cost of any
special treatment necessary to eliminate
such hard objects. Where required by
company or by ROW agreement, topsoil
shall be segregated from other spoil
and placed at the top of the fill to the
specified depth. In cultivated areas, no
rock shall be placed in the top of the fill
above the depth of normal tilling. Excess
rock must be disposed of by contractor
to the satisfaction of OMS personnel.
Contractors must also comply with
requirements concerning the order, in
which respective materials are backfilled,
contained in ROW restrictions.
4.12.2 Backfill Method
A) Backfill Material
Immediately after the pipe has been
lowered, it shall be shaded by filling the
ditch over the pipe with backfill material.
Backfill material shall be placed around
the pipeline in a manner to ensure
that no significant rocks, vegetation
or foreign objects strike or contact
the pipeline in a way that could cause
damage. Special considerations for the
initial 2 feet of backfill [ref. sec. 4.12.1]
B) General
Backfilling methodology should be done
in a way to maintain the integrity of the
ROW as well as a minimum disturbance
area. Backfilling shall be done in such a
manner as to ensure all area below and
around the pipe is surrounded by fill dirt.
Contractors are to use any acceptable
method approved by OMS personnel
in order to ensure compaction of the
backfill while not applying so much
pressure that the pipe may lose its
shape. Backfill packing shall not be done
through rocky land where the exterior
pipe or coating might be damaged,
or through sections where drain tile is
encountered and might be damaged.
All pipe must be buried a minimum of 6’
Deep, unless otherwise required by OMS
personnel or governing authorities
C) Padding
Where padding of the pipe is required
materials must be deposited in ditch
simultaneously on both sides of the pipe.
Section 4
71
Version 1.1
In the event the native ditch material
is considered by the company to be
unsuitable for backfill material, the
contractor shall purchase, haul, place
and choose the highest quality backfill
material possible in accordance with
these instructions. Contractors may use
a padding machine to achieve padding
requirements without hauling select back
fill to the worksite. If a shaker bucket is
used in place of a padding machine or
hauling in pad material, padding costs
are considered to be a part of the bid
price of the project.
D) Padding Density
Padding shall extend across the full
width of the ditch and be thoroughly
compacted until a minimum of 12 inches
of padding is in place. If more than one
pipeline is in the ditch, the select backfill
material shall be placed between the
lines and shall be brought to a level of
12 inches above the highest line. OMS
reserves the option to require additional
padding in extremely rocky areas.
The remaining backfill shall be placed in
the pipeline ditch and spread on both
sides of the pipeline ditch. ROW that
has been disturbed during construction
shall be graded and tilled in a manner
satisfactory to OMS and the landowner
and seeded. Backfilling across drainage
ditches, irrigation ditches, terraces, levee
districts, railroads, public highways,
private drives, trails, roads, or streams
shall be compacted to at least 953
standard proctor density throughout in
a manner satisfactory to company and
to any private or governmental authority
having jurisdiction.
4.12.3 Final Compaction
Compaction may be accomplished by
tamping or other method approved
by OMS. “Walking in” with a track or
wheeled vehicle is normally acceptable
on wide ditches, subject to prior OMS
approval. There shall be a minimum of
30 inches of cover material over the pipe
prior to compaction by vehicles. Wheels
and tracks must be narrower than the
ditch line for effective compaction.
Where non-ferrous or large diameter
thin wall pipe is involved, a limit may
be placed by OMS on the maximum
weight of the vehicle, or there may be a
requirement that the line be pressurized
during the operation. Compaction to a
density that will prevent excess settling
of the ditch backfill material is required.
A) Moisture
At road crossings where selected
backfill material is required, it shall
have the proper moisture content to
reach necessary 80% compaction and
the moisture content shall be uniform
throughout each layer.
4.12.4 Restoration of Construction Areas
Roads, slopes, creek banks, levees and
other places where earth has been
moved to facilitate the operation of
contractor equipment, the contractor
is required to restore these areas to
their original profile and condition,
to the satisfaction of OMS and/or the
landowner.
4.12.5 Overburden / Crown
Backfill over the pipe ditch shall be
crowned to a height of not less than 8
inches (8”) and no more than 12 inches
72
Construction Guidelines
(12”) above the adjacent ground surface,
except through irrigated farm land
where the backfill will be compacted
to the satisfaction of company and the
landowner. Through rocky lands where
livestock is confined, 20-foot wide gaps
shall be provided across the backfilled
line at 100-yard intervals to provide
passageway for livestock.
Gaps shall be level with surrounding
ground and surfaced with backfill
material free from large and sharp rocks,
all to the satisfaction of OMS personnel
and/or the landowner.
4.12.6 Irrigation & Drainage
When backfilling across irrigated fields
contractors must provide furrows across
pipeline ROW as required by OMS
personnel and/or landowner, in order
to direct the flow of water into normal
irrigation courses.Finished backfills must
be sufficiently level to permit normal
irrigation, even if harrowing, disking or
hand raking is required. When borrowed
dirt is necessary to crown the backfill
to the required height, Oasis and those
having jurisdiction of the property must
approve the manner and method of
securing dirt.
All terraces, levees and sides of drainage
or irrigation canals, and all roads
and highways that are cut shall be
backfilled in one foot lifts and each layer
thoroughly tamped by hand or machine
to provide a good bond between the
undisturbed sides of the ditch and the
new backfill material.
When backfilling on hillsides or sloping
ground, four-foot-high furrows or
terraces shall be provided across the
pipeline ditch to direct the flow of water
into the natural drainage courses and
away from the pipeline ditch. In no
case is surface drainage to be diverted
into channels other than the ones
they followed before the line was laid.
Particular care shall be exercised in
order that all drainage ditches shall be
maintained and left unobstructed to
prevent the backing up of water against
the spoil bank or backfill crown.
Diversion berms / Water bars should
be used wherever ROW ascends or
descends a steep grade to the following
specifications:
4.12.7. Reinforcing
When applicable, contractors are
to reinforce backfilling near or on
river banks, streams, ravines or other
watercourses, irrigation or drainage
ditches, as well as farm terraces with
earth filled sacks, rock riprap or concrete
headwalls. Contractors are responsible
to, at contractor’s expense, to repair
damage to levees, roadways, lanes,
private drives and farm terraces, as
may be caused by settling or washing
through the ditch portion of same, up to
and including the date of acceptance of
the work included herein and through
the one-year warranty period.
4.12.8. Topsoil
Topsoil is considered by OMS to be
the top layer of soil. At times, topsoil
by standard definition will not apply,
in which case the top 2’ of soil will be
considered “topsoil”.
Topsoil shall be segregated in a method
that protects it from overburden, being
trampled, or from mixing with fill dirt.
Contractor is responsible for maintaining
the separation and quality of topsoil.
Section 4
73
Version 1.1
4.13 Leak & Pressure Testing
4.13.1 General
The intent of leak testing is to find
unacceptable faults in a piping system.
If such faults exist, they may manifest
themselves by leakage or rupture; this
may result in catastrophic failure. Piping
systems that rupture may cause sudden,
forcible, uncontrolled movement of
system piping or components, or parts of
components.
A) Location of Equipment
Pipeline systems being tested should be
restrained against sudden uncontrolled
movement from catastrophic failure. All
poly pipe should be located in the trench
and backfilled.
Air compressors should be located a
minimum of 20 feet and no more than
25 feet from the end of the pipe being
tested. Discharge hoses and hard piping
should be secured to the ground in a
manner to restrain it from movement
in the event of a catastrophic failure.
Restraints such as stakes and cables,
straps or tie downs are acceptable. Any
other style of restraint must have OMS
approval.
Pressure recording devices must be a
minimum of 20 feet and no more than
25 feet from the test head, and is to
be located perpendicular to the pipe
being tested. The recorder’s placement
should be out of the whip radius of the
compressor’s discharge hose and/or
hard piping. Chart recorder hoses must
have restraint whip checks installed as
well. The recording device should be
a chart recorder, digital recorder, or
any other recording device approved
by OMS for the length of pipe being
tested. Certifications will be required
for all recorders and gauges for the test
duration.
B) Test Duration
All piping systems are required to be
tested for no less than 8 hours. There
will be no exceptions of pipe footage to
not be tested. The maximum length for
a single tested piping system is 20,000
feet (3.75 miles).
C) Water Sources
1. Quality
Water used for pressure testing must
be from a known clean source, and be
treated with an agent that eliminates the
potential for bacteria growth.
2. Quantity
The quantity of water to be used will be
determined by OMS personnel.
F) Failures
Contractors are responsible for the cost
of labor and materials to repair any
leaks found during the pressure test.
Contractors are responsible for labor and
materials required to isolate the ends of
the pipelines prior to pressure testing.
OMS personnel will be responsible for
purging and placing the pipelines in
service.
G) Depressurizing
After the line has been tested, the
contractor must relieve pressure by
74
Construction Guidelines
means of opening a valve downstream
predetermined by OMS personnel.
H) Dewatering
1. Disposal of Water
Water should be disposed of in
accordance with all local, state, and
federal laws. It is acceptable that water
removed from the pipeline trench be
disposed of on the ROW.
4.14 ROW Clean-Up
4.14.1 Post-Construction Clean-up
It is OMS expectation that construction
materials will be removed from the
ROW as well as any established laydown
areas, roadways, and approved staging
yards. Other restoration agreements may
necessary.
A) Fences
Fences must be restored to original or
better than original condition prior to
project finalization.
B) Gates
Permanent gates must be installed
across all ROWs.
C) Line Markers
Permanent line markers must be installed
prior to project completion.
D) Test Leads
Test leads must be installed at minimum
every mile, at every road crossing, and at
every bore start and end point.
1. Anode Installation
Anodes must be installed on all steel
risers.
E) Reseeding
Reseeding must be completed according
to ROW agreements, with appropriate
seed for the region in which it is
performed. Consult federal, state, and
local regulations for correct type of seed.
F) Erosion Control
Stake Bales, Straw waddles, or
water bars must be used when the
possibility of slope erosion is imminent.
Near regulated lands (U.S. Corps of
Engineers, Federal, state, Bureau of Land
Management, etc.) Silt fence must be
used to provide a filtration barrier and
protect the environment.
G) Rock Picking
Rocks must be removed from trench
bed if they are larger than 6 inches in
diameter. When rocky conditions exist,
other protective measures will need
to be taken. Never drag pipe on top of
rocky soil.
4.15 Start-up
A) Removal of Isolation Devices
All contractors prior to removing
pancakes, locks, blind flanges, etc. must
follow proper LO/TO procedures for
removing such devices.
B) Opening of Block Valves
Block valves are only to be opened by
OMS personnel. It is imperative that
these valves be operated in such a
Section 4
75
Version 1.1
manner to allow for equal pressure on
both sides of the valve.
C) Suction Line Leak Test
Tank valves must be open and a leak
observation / inspection must be
maintained for at least 30 minutes.
1. Water Systems
1.A) Pressure Limits
Pressure limits will be determined by
OMS personnel. Reference Section 5 for
additional information.
2.A) MAOP Sign-off – Water Systems
Prior to operating equipment, a
maximum allowable operating pressure
(MAOP) must be established and
confirmed by OMS personnel. Under no
circumstances should any equipment
or facility be operated without this
document, or verification of MAOP
established.
D) Oil System
1. Pressure Limits
Pressure limits will be determined by
OMS personnel. Reference Section 5 for
additional information.
MAOP Sign-off – Oil Systems
Prior to operating any equipment, the
MAOP must be confirmed by OMS
personnel. Under no circumstances
should any equipment or facility be
operated without this document, or
verification of MAOP established.
E) Pump to Line Leak Test
1. Pump Start-up
Prior to final production, pump and line
leak tests will be performed by closing
the main line discharge valve. The
pump shall be operated at the MAOP to
ensure all equipment components are
functional, and no leaks exist in the line.
2. Line Purge
When lines are to be purged, OMS
personnel must be present to ensure
the protection of personnel and the
environment. Line purges have many
unique challenges that are specific to the
point at which the release is taking place,
as well as the material and methodology
chosen to safely complete this task.
3. Disposal / Release
All material that originates from an
Oasis owned facility must be contained
properly. Spills of any amount must be
immediately reported to OMS personnel.
4. Trucking
When transporting liquids released
from OMS facilities, proper waste
management protocol must be followed.
Consult OMS personnel for direction on
where and how to properly dispose of
material.
F) System Leak Tests
System leak test will be performed
quarterly, maintaining max MAOP for two
hours while monitoring for any pressure
deviation.
76
Construction Guidelines
Valves must be operated on a quarterly
basis to ensure proper operating
functionality.
1. Vent Valves / Plugs
All plugs and pressure relief valves must
be inspected on a quarterly basis to
ensure they are secured properly and
are in proper working condition. Only
use appropriate tools to check these
functions.
2. Installation Confirmation
After construction is complete and
system is believed to be ready for
production, a final inspection must
be performed on ALL systems, valves
and equipment by contractor and
OMS personnel. This inspection can be
completed by both OMS and contractors
or separately, as long as documentation
is completed.
4.16 Project Sign-off
4.16.1 Final Inspection
When a project is completed, all
departments within OMS are required to
sign the final inspection form. The intent
behind this form is to ensure that all
documentation including pictures, test
records, forms, and billing information
are in OMS’ possession.
Reference Final Inspection Form – [OMS
1019]
Section 4
77
Version 1.1
78
General Equipment & Mechanical Guidelines
Section 5
79
Version 1.1
General Equipment & Mechanical Guidelines
OMS - Oasis Midstream Services
EHS - Environmental Health & Safety
Lifting Eyes - Device attached to frame
of equipment and/or machinery to be
used to lift equipment with weighing
more than 100lbs.
Sound Dampening - Device used to
reduce decibel rating to under 85
decibels as per OSHA CFR 1910.95
Manufacturer Instructions & Manuals
Provides guidelines for installation,
maintenance, and operations for
equipment and materials. Referencing
this material is required prior to
performing work on or with any
equipment.
References:
A. American Gear Manufacturers
Association (AGMA)
B. American Institute of Steel
Construction (AISC)
C. Hydraulic Institute (HI)
D. National Electrical Manufacturers
Association (NEMA)
E. Occupational Safety and Health
Administration (OSHA)
1910.212
1910.144
F. American Society of Mechanical
Engineers (ASME)
G. Oasis Petroleum North America EHS
Manual
Expectations: Standards for Work,
Project Bid Submittal, Design, Materials
and Standard Specifications, Installation
Considerations: Mechanical Integrity,
Quality Control
80
General Equipment & Mechanical Guidelines
5.1 GeneralA) Purpose
B) ScopeC) Safety
5.2 Standards For Work5.2.1 Complete Systems
5.2.2 Quality of Equipment
5.2.3 Manufacturer Recommendations
5.3 Project Bid Submittal5.3.1 Equipment
5.3.2 Motors
5.3.3 Verification
5.4 Design5.4.1 General
5.4.2 Controls
5.5 Materials And Standard Specifications5.5.1 Materials
5.5.2 Uniformity
5.5.3 Lubrication
5.5.4 Structural Metal Framing
5.5.5 Equipment Bases and Bedplates
A) Mounting EquipmentB) Supporting Equipment
5.5.6 Anchors
A) Bolt PatternsB) Size and Strength
C) Types5.5.7 Safety Guards
A) CoversB) Outdoor Installation
C) Guarding other Surfaces5.5.8 Lifting Eyes
5.5.9 Mechanical Seals
5.5.10 Drives
5.5.11 Nameplates / Labels
A) Manufacturer’s NameplateB) Rotation Direction Labeling
C) IdentificationD) Letters
E) Color
Table of Contents
82
82
82
83
83
Section 5
81
Version 1.1
F) Fasteners5.5.13 Special Tools
5.5.14 Finishes
A) Factory PaintingB) Shop Priming
C) Rust Prevention5.5.15 Noise and Vibration
A) Decibel LimitsB) Noise Levels due to Vibration
5.5.16 Factory Tests
A) VerificationB) Performance Records
5.5.17 Examination
5.5.18 Preparation
5.6 Installation5.6.1 Structural Fabrications
5.6.2 Anchor Bolts
A) DeliveryB) Base and Bedplate Grouting
5.6.3 Equipment Startup and Adjustment
5.6.4 Sound Level Testing
5.6.5 Tools, Loose Parts and Lubricants
A) InventoryB) Recommended Spare Parts
C) Documentation
88
82
General Equipment & Mechanical Guidelines
5.1 General
A) Purpose
The purpose of this section is to provide
a guidance document for subcontractors
and suppliers of equipment for or in
conjunction with Oasis Midstream
Service (OMS) operations.
B) Scope
This documents applies to employees,
contractors, and representatives
operating on, near, or with Oasis owned
facilities, Right-of-Ways, or equipment.
C) Safety
While performing work on behalf of OMS,
whether in the field or in a contractor
owned facility, it is expected that work
will be performed in a manner that best
represents Oasis’s commitment to safety
and health at all times. Please refer to
Section 2 (EHS Expectations) of this
manual for more information.
5.2 Standards For Work
5.2.1 Complete Systems
Provide pipe, fittings, wiring and
supports to produce complete,
operable systems with all elements
properly interconnected. If a specific
dimensioned location is not shown for
interconnections or smaller system
elements, select appropriate locations
and show them on shop drawings
submittals for review.
5.2.2 Quality of Equipment
It is OMS expectation that contractors
will provide new equipment that is free
of any known operating malfunctions.
This includes materials quality as well.
OMS also requires that contractors
Install equipment that is aligned, leveled,
cleaned and adjusted for satisfactory
operation. Installed equipment must
be in accordance with manufacturer’s
recommendations and industry best
practices so that; connecting and
disconnecting of piping and accessories
can be readily made; and all parts
are easily accessible for inspection;
operation; maintenance and repair.
Oil and lubrication fittings must be
clear of and away from guards, base
and equipment, and within reach from
the ground or operating floor. The
location of all motor connections must
be coordinated in order to properly
orient encased electrical conduits. To
meet these equipment requirements
as furnished, minor deviations from
drawings may be made, however, they
must be approved by OMS personnel.
5.2.3 Manufacturer Recommendations
The recommendations and instructions
of the manufacturers of products used
in the work are hereby made part of
these specifications except as they may
be superseded by other specification
requirements.
5.3 Project Bid Submittal
5.3.1 Equipment
• Each piece of equipment that
requires a certified witness or non-
witness performance test, must be
accompanied by a completed form
containing the following information:
• Oasis’s name and location of project
• Contractor’s name and subcontractor
if applicable
Section 5
83
Version 1.1
• Name of item being submitted
• Specification reference by section,
paragraph and page
• Item specifications (manufacturer,
general descriptive data, dimensions,
size of connections, speeds,
performance curves, serial number);
Contractor must provide test results
and a list, which shows the values
that differ from specifications.
-Reference Figure 1-
5.3.2 Motors
Motor data, type, voltage, frequency,
phase, full load amperes, starting
method, frame size, enclosure insulation
type (NEMA Code letter), dimensions,
service factor and serial number.
5.3.3 Verification
All forms must be verified by the date
and signature of the person certifying
the performance. This is required to
verify that equipment has been inspected
and is in proper working condition. OMS
contractors are required to ensure this
verification has been provided prior
to performing work on OMS locations,
equipment, or projects.
5.4 Design
5.4.1 General
Equipment should be designed for
the service they are intended for and
be of ample strength for all stresses
that may occur during fabrication,
transportation, erection, and during
operation. It is expected that equipment
will be adequately braced, anchored,
and installed in a neat and professional
manner. Consideration should be given
to appearance and safety, as well as
intended utilization and placement in
the design and details. Use cathodically
(electrically) compatible materials of
construction.
5.4.2 Controls
Electrical control designs for systems
and/or equipment packages are the
responsibility of the manufacturer and/
or the equipment package provider.
Elementary control diagrams as shown
on the electrical drawings and the
diagrams shown on the instrumentation
drawings are to be generally illustrative
for control and monitoring requirements.
Manufacturers must design their own
functional electric control devices and
circuitry, in consultation with the specific
elementary control diagrams and other
project specifications, to meet the
equipment control requirements. In many
cases these will need to be National
Electric Manufactures Association
(NEMA) approved for use in flammable
atmospheres.
It is the expectation that supervisors
ensure these system diagrams and
package controls are furnished by the
equipment manufacturer, except the
controls shown in motor control centers
and process controllers, remote control
devices and their interconnecting wiring.
5.5 Materials And Standard Specifications
5.5.1 Materials
OMS expects that designs, fabrication,
and assembling of equipment and
systems be equipped with new materials,
and in accordance with acceptable
modern engineering and sbest practices.
84
General Equipment & Mechanical Guidelines
Individual parts should be manufactured
to standard sizes and gauges so that
repair parts can be installed in the field
and if possible, purchased in a timely and
affordable manner.
5.5.2 Uniformity
Unless otherwise specified, equipment
or material should be constructed of the
same type or classification used for the
same purpose shall be the product of
the same manufacturer and shall be the
same model. This is to ensure that parts
are easy to find, replace, and install on an
as-needed basis.
5.5.3 Lubrication
Lubricant types should be rated for the
temperature variations encountered in
the field by OMS personnel. Quantities
sufficient for consumption prior to
completion, testing and final acceptance
are expected to be secured.
5.5.4 Structural Metal Framing
Weld submerged steel surfaces, which
butt or bear against each other, must
have sealed surfaces that protect against
the penetration of liquids. Gaps cannot
exist between adjacent submerged steel
surfaces less than 1/32-inch wide in order
to ensure a seal on the surfaces.
5.5.5 Equipment Bases and Bedplates
A) Mounting Equipment
Equipment mount assemblies should be
constructed of a single heavy cast iron
or welded steel bedplate or skid unless
otherwise shown or specified. Skids with
bases; bedplates; machined support
pads; tapered dowels for alignment or
mating of adjacent items; adequate
openings to facilitate grouting; and
openings for electrical conduits shall be
provided. Round or chamfer and grind
all corners until they are smooth and free
of burrs. Weld seams continuously and
contact edges between steel plates and
shapes, and grind welds smooth.
B) Supporting Equipment
Machinery and piping on bedplates
should not be supported in any way
other than that which is factory designed
and installed. Bases for equipment
should be provided with axial and
transverse jackscrews to facilitate
horizontal and longitudinal adjustment. If
necessary, stainless steel leveling blocks
and shims or jackscrews shall be used
for leveling the base prior to grouting.
Leveling nuts may be used for leveling
bases weighing less than 200 pounds.
All leveling shall be against steel surfaces
(jackscrew plates, leveling blocks or
leveling nuts). Mount all equipment bases
and baseplates on reinforced concrete
pads at least 3 inches high.
5.5.6 Anchors
A) Bolt Patterns
Equipment shall be furnished with an
anchor bolt pattern and the required
anchor bolts, nuts and washers of
adequate design for securing bases and
bedplates to concrete bases. Anchor
bolts should be of length to allow for
1¼ inches of grout under baseplates
and adequate anchorage into structural
concrete unless otherwise shown or
specified.
Section 5
85
Version 1.1
B) Size and Strength
Anchors and assembly bolts should
have nuts of ample size and strength
for the purpose intended. Bolts shall
be standard machine bolts, with cold-
pressed hexagon nuts. Provide suitable
de-galling compounds for bronze and
stainless steel threaded components. Any
space wholly or partially underground, or
having a wall or ceiling forming part of
a water channel, is classified as a moist
location. Unless specified or noted on the
drawings, provide materials as follows:
• Bolts and nuts in submerged
locations or submerged and
embedded in concrete or buried in
earth.
• Bolts and nuts for supports or
equipment in dry or moist locations:
galvanized steel (hot-dipped) with
oversize nuts.
• Use other bolting materials where
specifically called for in the
specifications or in the drawings.
C) Types
Motor-driven equipment must be
anchored with cast-in-place anchor
bolts or drilled-in anchors set with
epoxy adhesive. Expansion type anchors
for motor-driven equipment are not
approved.
Anchor all non-motor-driven equipment
with cast-in-place anchor bolts or drilled-
in anchors set with epoxy adhesive
except that, where specifically allowed
by note on the Drawing expansion type
anchors may be used.
5.5.7 Safety Guards
A) Covers
Cover belt or chain drives, fan blades,
couplings, nip points, exposed shafts
and other moving or rotating parts on
all sides with safety guards conforming
to all federal, state, and local codes and
regulations. Guards must conform to
the most restrictive requirement. Guards
should be designed easy installation
and removal, complete with necessary
supports, accessories and fasteners, all
hot-dip galvanized.
B) Outdoor Installation
Design guards in outdoor locations to
prevent entrance of rain and dripping
water. Provide tachometer test opening
in line with ends of shafts. Typically
guards shall be expanded metal on
a structural steel frame, except that
outdoor guards may be of solid material.
Provide hinged doors with latch for
service and lubrication access.
C) Guarding other Surfaces
Cover all pipes, manifolds, heaters
and other surfaces that have a surface
temperature sufficient to burn human
tissue with a thermal insulating material,
or otherwise guard against contact.
All machine guards must comply with
OSHA standards (CFR 1910.212).
5.5.8 Lifting Eyes
Equipment weighing over 100 pounds
must be supplied with lifting eyes. Parts
of equipment assemblies, which are
normally serviced separately, such as
motors, should have lifting eyes of their
own.
86
General Equipment & Mechanical Guidelines
5.5.9 Mechanical Seals
Where specified, pumps shall have single,
split-type, self-aligning, self-centering
mechanical seals with seals and stuffing
boxes designed for the presence of
moist environments. The seal shall be
of a nondestructive (non-fretting) type
requiring no wearing sleeve for the
shaft. Shafts for pumps specified with
mechanical seals shall be furnished with
no reduction in size through the seal
area. Mechanical seals shall require no
field assembly, other than assembly
around the shaft and insertion into the
pump. Non-shaft O-rings will be of ball
and socket type requiring no gluing.
Initial installation at the factory will be
with non-split faces, with all spare seals
and spare kits to have split faces. The
face combination will be hard/hard. This
device:
On initial flooding of the rotating
equipment, releases entrapped air from
the seal chamber through an integral,
self-cleaning air vent in top of the
bushing;
Creates fluid exchange and improved
circulation in the seal chamber that
reduces frictional heat accumulation
around the mechanical seal;
Positions particulate matter/
contaminants for removal by conveying
them from the bore to the shaft by
means of an integral machined spiral;
Removes particulate matter/
contaminants from the seal chamber
to the impeller for expulsion, without
seal flush water, through and integral
machined exit groove;
Pump seals shall be hydraulically
balanced and designed for 200% of the
seal area pressure under operating RPM
and temperature conditions of the RAS
stream;
Mechanical seals shall be manufactured
to the highest quality standards.
5.5.10 Drives
Provide all drive units with a rating and
service factor suitable for 24 hours per
day operation under the operating load.
5.5.11 Nameplates / Labels
A) Manufacturer’s Nameplate
Equipment and drivers shall be installed
with a corrosion-resistant metal
nameplate fastened in a readily readable
position. This nameplate shall contain the
manufacturer’s name, equipment rating,
capacity, size, model, serial number and
speed. All written or printed information
written shall be written in English.
B) Rotation Direction Labeling
Furnish each piece of rotating equipment
with a direction of rotation arrow. This
label should conform to OSHA CFR
1910.144.
C) Identification
Each piece of equipment should be
identified using a high quality (weather
resistant) label with the functional name
and number of the equipment.
Fasten labels to the equipment, its base
or other acceptable location.
Section 5
87
Version 1.1
D) Letters
Letters shall be sized at least 3-inch high
with the border trim on all sides not less
than 3-inch.
E) Color
The color of labeling should be green
background with white letters.
F) Fasteners
Brass or stainless steel screwed into
inserts, anchor shields or tapped holes in
equipment or base.
5.5.12 Protection against Electrolysis
Where dissimilar metals are used in
conjunction with each other, suitable
insulation should be installed between
adjacent surfaces to eliminate direct
contact and any potential electrolysis.
Connections of dissimilar piping
materials shall utilize dielectric unions,
flanges, couplings or bushings.
5.5.13 Special Tools
For each type of equipment, a list of
special tools needed (including grease
guns or other lubricating devices), which
may be necessary for the adjustment,
operation and maintenance of such
equipment should be provided.
5.5.14 Finishes
A) Factory Painting
Pumps; motors; drives; starters; control
panels; and other similar self-contained
or enclosed component shall have a
factory protective paint system applied
unless otherwise noted. Paint or protect
surfaces that are inaccessible after
assembly by a method to provide
protection for the life of the equipment.
B) Shop Priming
Except where field sandblasting is
required, apply one or more shop coats
of metal primer (of sufficient thickness
to protect surfaces until finished) on
surfaces to be finish painted at the site.
Primer shall be compatible with finish
coat.
C) Rust Prevention
Machined, polished, and other ferrous
and non-ferrous surfaced equipment are
not to be painted with rust preventive
compound.
5.5.15 Noise and Vibration
A) Decibel Limits
It is OMS desire that equipment not
operate at a sound level about the
maximum allowable level by OSHA,
however, if the required sound level
cannot be achieved by bare equipment
in its designated environment, a sound
dampening device should be provided.
These devices shall have necessary
ventilation to prevent equipment
overheating and shall be constructed
for easy removal to permit maintenance.
Devices necessary for day-to-day
operation shall pierce the enclosure or
otherwise be accessible without need to
remove the enclosure.
B) Noise Levels due to Vibration
Equipment that has obvious excessive
vibrations when in operation shall be
repaired or replaced as directed by
88
General Equipment & Mechanical Guidelines
OMS personnel. Baseline vibration
measurements shall be made where
specified.
5.5.16 Factory Tests
A) Verification
Proof of factory tests for each piece of
equipment should be provided with the
equipment. Note that factory tests are
inherent in many reference standards.
The requirement for a factory test in a
referenced standard is hereby made a
part of these specifications. Factory tests
should be conducted at the same speeds
and conditions at which the equipment
will operate in the field, except as noted.
B) Performance Records
Where specifically noted, performance
tests may be witnessed by the Oasis
representative or his/her representative.
Inform OMS personnel in sufficient
time to allow arrangements to be made
for witness of such tests. When non-
witnessed tests are performed, supply
certified results.
Factory testing of pumps and
compressors shall be supplied in
accordance with the requirements and
standards of the Hydraulic Institute (HI).
5.5.17 Examination
Equipment shall be inspected for
damage, defects, completeness and
correct operation before installing,
and after installation and pressure or
operations test is performed.
5.5.18 Preparation
Prior to installing equipment, ensure
that areas are clean. Maintain areas
in a broom-clean condition during
installation operations. Clean, condition,
and service equipment in accordance
with the approved Instruction Manuals
and specific recommendations of the
equipment manufacturer.
5.6 Installation
5.6.1 Structural Fabrications
Equipment must conform to AISC Codes
as well as to approved Manufacture
provided instruction manuals. Only
skilled and experienced trained on
methods of installing of the types
of equipment specified, are the only
approved personnel may fabricate
equipment on behalf of OMS. Specialized
tools and equipment shall be utilized,
such as precision machinist levels, dial
indicators, gauges and micrometers, as
applicable. Equipment shall be installed
free of over vibration or other defects.
Align and pin to common bedplate
equipment and drivers connected by
flexible couplings.
5.6.2 Anchor Bolts
A) Delivery
Deliver bolts with templates or setting
drawings and verify that bolts are
correctly located before structural
concrete is placed.
B) Base and Bedplate Grouting
Grouting equipment on concrete pads
shall take place prior to connection of
piping or electrical and instrumentation
systems. Initial fitting and alignment
of connected piping prior to grouting
is acceptable, however, final alignment
and connection of piping shall be done
Section 5
89
Version 1.1
after equipment grouting is completed.
Level and align equipment base on the
concrete foundation, then clamp the
baseplate in position by installing the
equipment anchor nuts and washers and
making snug tight.
Contractors are expected to ensure
alignment has been maintained after
clamping. The space under the base or
bedplates shall be filled completely with
grout. Exposed grout shall be beveled
at a 45-degree angle, except round
exposed grout at horizontal surfaces for
drainage. Trowel or point exposed grout
to a smooth, dense finish and damp
cure with burlap for three days. When
grout is fully hardened, leveling blocks
and shims or jacking screws shall be
removed, or leveling nuts shall be backed
off to allow the grout to fully support
the equipment base. Tighten nuts on
anchor bolts to one-quarter turn past
snug tight in an alternating pattern to
avoid stress concentration on the grout
surface. Block outs for access to leveling
nuts or leveling blocks, and shims shall
be filled with the grout material installed
under the base and pointed. Holes in
the base associated with jackscrews
shall be filled with flexible sealant.
Check the installation for alignment and
that it is level, and perform approved
corrective work as required to conform
to the tolerances given in the applicable
instruction manual.
5.6.3 Equipment Startup and
Adjustment
Equipment should be oriented in a way
most suitable for authorized factory-
trained representatives of the vendors
supplying the various items of equipment
to check the equipment after installation
and adjust and test the equipment
as necessary prior to startup. This
representative shall be experienced and
knowledgeable of the equipment being
tested. They are expected to assist and
instruct the operating staff in adjusting
and operating the equipment during the
initial operation period, providing initial
lubrication for all equipment.
Equipment should be tested and results
available to OMS personnel to ensure
proper functioning. For pumps and
compressors, include measurement
of suction and discharge pressure at
the equipment and measurement of
equipment rate by volumetric means
or through a suitably calibrated meter
for two points on the performance
curve. For adjustable-speed pumps
and compressors, conduct tests at a
minimum of two speeds. Furnish any
required test equipment or measuring
devices that are not part of the
permanent installation.
In addition, demonstrate that the entire
facility is in full operating condition prior
to the acceptance of the work. Should
any equipment or part thereof fail to
operate as intended, immediately remove
and replace it, all at the contractor’s
expense. Pay for all tests involved in this
section.
Pressure test equipment and connections
as required by these specifications.
For each electrical motor, measure
terminal voltage, line current, power
factor and watts at motor terminals while
running at full load.
5.6.4 Sound Level Testing
Measure the sound level developed by
all mechanical and electrical equipment
90
provided. Perform testing in all rooms
and spaces containing such equipment
during the final operation test program
with all equipment operating. Use OSHA
approved instrument, and record the
highest sound level developed when
measured according to OSHA standards
in each room and space. Deliver a copy
of records to Oasis management.
5.6.5 Tools, Loose Parts and Lubricants
A) Inventory
Inventory lists for tools and loose parts
are expected to be maintained for
each project. Extra inventory and parts
should be returned to OMS in a timely
manner after a project is complete. Oasis
Material Transfer Forms [ref. Sec. 4]
acknowledgment of receipt is required
for project completion. Loose parts are
defined as items such as special tools,
keys, safety equipment and portable
equipment.
B) Recommended Spare Parts
Furnish a complete list of recommended
spare parts and supplies for each piece
of equipment furnished with current
prices and a source of supply.
C) Documentation
Provide a list of all recommended
lubricants not listed in the operation and
maintenance manuals.
91
92