92
1 Oasis Midstream Services Midstream Business Unit Guidelines Version 1.1

Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

11

Oasis Midstream ServicesMidstream Business Unit Guidelines

Version 1.1

Page 2: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

2

Page 3: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

3

Section 1 - Introduction

Section 2 - Environmental Health & Safety

Section 3 - Program Administration

Section 4 - Construction Guidelines

Section 5 - General Equipment & Mechanical Guidelines

Table of Contents

4

6

20

28

78

Page 4: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

4

Introduction

1.0 Introduction

Oasis Midstream Services values the

safety of all workers and the protection

of the environment. We are committed

to the quality of our work, as well as

maintaining an incident free workplace.

This goal can only be attained working as

a team with our contractors.

The following terms are used in this

handbook to describe the contractor

company and personnel mentioned in

the guidelines:

Guidebook and Handbook Terms

Contractor - A contractor is defined for

the purposes of this document as any

company or individual whom by contract,

subcontract, or purchase order performs

work or provides services or equipment

to or for Oasis Midstream Services.

Contractor Supervisor - This individual

represents the contractor company that

supervises the work of a contractor or

contractors.

Oasis Representative - An individual

authorized to oversee, manage, or direct

work on behalf of Oasis Petroleum.

Page 5: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 1

5

Version 1.1

This handbook provides guidance and a minimum set of expectations for Oasis Midstream Services (OMS) employees and contractors regarding contractor work performed for OMS. As the contractor, you are required to follow the policies and procedures established by the contractor’s company in addition to any of Oasis site-specific policies. This handbook is intended to supplement, not replace, the contractor’s company safety program, which the contractor is required to implement. In the event of a conflict between this handbook and the contractor’s company safety program, the more stringent rule shall apply. The contractor company’s contract with OMS may be canceled, or an individual may be asked to leave OMS owned property if the contents of this guideline are not followed.

1.1 Excellence through Teamwork

Environmental, health, safety, and

production goals cannot be reached

by operational groups operating

independently. This is true for OMS as

well as our contractors. While performing

work for OMS, contractors will be

exposed to hazards as well as operational

challenges and will be expected to

recognize, manage, and effectively solve

and mitigate these obstacles. This is

critical for our business to succeed.

1.2 How to Use this Guidebook

The intent of this handbook is to

provide guidance to our contractors

and employees regarding Oasis’s

expectations of its contractor workforce.

Included is mapping information,

operational specifications, DOT and

other federal regulations, manufacturer

requirements and other documents.

1.3 How to Use the Contractor Handbook

All of Oasis’s contractors should have

a copy of this handbook accessible to

them. The contents of this handbook

should be reviewed, discussed, and

understood by contract personnel

before any work is performed for

Oasis. If an HSE issue arises that is

not addressed in the handbook or by

the contractor’s own safety program,

you must ask for guidance from the

contractor representative or an Oasis

representative.

1.4 How to Use the Inspector Handbook

Inspectors and supervisors provide

services that require additional

information necessary for the quality

assurance and control of various

projects. Operational Specifications,

map information, and other historical

project scopes will be accessible to Oasis

employee or contractor inspectors.

Page 6: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

6

Environmental Health & Safety

Introduction1. Purpose and Scope

2. Stop Work Authority

Oasis Commitment 1. Commitment to People

2. Commitment to Safety

3. Commitment to the Environment

4. Regulatory Compliance

Responsibilities1. OMS Manager Responsibility

2. OMS Employee Responsibility

3. OMS Contractor Responsibility

4. OMS Inspector Responsibility

5. Service Providers

Environmental Health and Safety (EHS) PolicyExpectations for Individuals

Expectation of Contractors

1. Contractor’s Commitment

2. General Health, Safety and Welfare2.1 Contractor Personnel Fitness/Personal Hygiene

2.2 EHS Orientation

2.3 Incident Reporting and Investigation

2.4 Reporting Hazards, Unsafe Conditions, & Near Misses

2.5 Behavior-Based Safety Observation Programs

2.6 Substance Abuse, Dangerous Materials and Firearms

2.7 Horseplay

2.8 Housekeeping

2.9 Clothing and Other Apparel

2.10 Compressed Gas Cylinders and Compressed Air

2.11 Storage, Use and Labeling of Chemicals, Solvents and Paint

2.12 Personal Protective Equipment

2.13 Overhead Work

2.14 Scaffolds or Platforms

2.15 Fall Protection Equipment

2.16 Non-Destructive Testing (NDT)

2.17 Safe Work Systems (SWS)

2.18 Hydrogen Sulfide

2.19 Fire Protection

2.20 Safety Equipment

Table of Contents

8

8

8

9

10

10

Page 7: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 2

7

Version 1.1

2.21 Safety Training

2.22 EHS Meetings

2.23 English Language Proficiency

2.24 DOT Safety

2.25 Minimum Certifications and Licenses

2.26 Electrical Safety

2.27 Emergencies

3. Environmental Management3.1 Environmental Housekeeping

3.2 Reporting

3.3 Diligence

3.4 Waste Management

3.4.1 Waste Management Plan3.5 Tanks and Vessels

3.6 Waste Water

3.7 Wildlife Management

17

Page 8: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

8

Environmental Health & Safety

Introduction

1. Purpose and Scope

This manual was created to be a

guidance document for all OMS

employees, contractors, and consultants

regarding best practices within Oasis

Midstream Services.

Our service providers are chosen

based on professional integrity and are

expected to perform the job correctly/

safely on all Oasis projects and location

regardless of adverse circumstances,

or perceived time constraints. It should

be noted that these are MINIMUM

expectations.

Any changes to the processes

outlined in this document require MOC

(Management of Change) / Oasis

Representative approval.

2. Stop Work Authority

All contractors are authorized as well

as required to stop any work that is

perceived as a risk to any persons’ safety

or a risk to the environment.

No repercussions will result from any

worker or contractor exercising Stop

Work Authority.

If a contractor or contractor’s employee

feel they are being discouraged from or

penalized for using Stop Work Authority

they must report it immediately to an

Oasis Petroleum representative.

Oasis Commitment

Oasis is committed to the safety and

health of all employees and contractors

as well as the communities and

environment in which Oasis operates.

1. Commitment to People

Oasis is not satisfied unless everyone

goes home in the same condition they

arrived.

2. Commitment to Safety

Anyone; employee or contractor, can

call a safety time-out or use Stop Work

Authority to halt an unsafe condition or

behavior.

3. Commitment to the Environment

Oasis is committed to the preservation

of the environment. Any incident that

threatens the environment must be

reported immediately and appropriate

steps taken to mitigate and fix or clean

up the issue.

4. Regulatory Compliance

Oasis is committed to maintaining

regulatory compliance on the county,

state and federal level.

Responsibilities

1. OMS Manager Responsibility

Managers are expected to demonstrate

positive HSE behaviors at all times

Managers will engage in proactive

leadership and two-way communication

with all workers, contractors and

consultants

Be aware of requirements presented in

the handbook

Ensure that all contractors performing

work for Oasis Petroleum are meeting

expectations in accordance with the

requirements presented in the handbook

Environmental Health & Safety

Page 9: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 2

9

Version 1.1

2. OMS Employee Responsibility

Be aware of the contractor handbook

and its requirements

Ensure that contractors are aware of the

requirements and expectations of them

and have a copy of the handbook

Ensure that all contractors working

for Oasis Petroleum are meeting the

expectations put forth by the handbook

3. OMS Contractor Responsibility

Contractor companies are responsible for

the contractors employees’ safety and

health and ensuring that all contractors

perform their work safe and acceptable

manner

Contractor must become familiar with

Oasis Petroleum’s requirements and

expectations, many of which are outlined

in this handbook. These guidelines are a

supplement to, not a replacement of the

contractors own safety program. In the

case where the contractors procedures

and Oasis Petroleum procedures conflict,

the more stringent rule should be

followed

Contractors must be aware of Oasis

Petroleum’s contractor handbook and it’s

requirements

4. OMS Inspector Responsibility

Inspectors are responsible to know,

follow, and oversee contractor use and

application of the guidelines in this

handbook.

Are accountable for technical quality

assurance

Responsible to ensure all forms are filled

out and completed prior to start, during

work, and after project is completed

5. Service Providers

It is OMS expectation that service

providers will ensure work is performed

in accordance within the framework

of OMS expectations, contractor

requirements, as well as any and all

county, state and federal regulations

Environmental Health and Safety (EHS) Policy

This document is a summary of the EHS

requirements and working procedures

that are the minimum standards and

practices to which all contractor

personnel must adhere while working

for Oasis Petroleum North America LLC,

or Oasis Midstream Services (OMS)

(collectively, “Company”). These are

Company minimum requirements, and

are in addition to, and intended to

Inspectors are responsible to know, follow, and oversee contractor use and application of the guidelines in

this handbook.

Page 10: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

10

Environmental Health & Safety

supplement, all other applicable laws,

rules and regulations. Contractor must

develop its own EHS program, policies

and procedures and through its program,

policies and procedures demonstrate

compliance with all federal, state, county

and municipal laws, rules and regulations

applicable to Contractor’s work and

Contractor’s services, items, materials,

equipment, or personnel to be used

in performing such work, including,

but not limited to, the following (as

may be supplemented and amended

from time to time): the Occupational

Safety and Health Act, the Clean Air

Act, the Comprehensive Environmental

Response, Compensation and Liability

Act, the Federal Water Pollution Control

Act, the Solid Waste Disposal Act, the

Resources Conservation and Recovery

Act, the Safe Drinking Water Act, the

Toxic Substances Control Act, the

Hazardous Materials Transportation Act,

the Federal Oil Pollution Act of 1990 and

comparable state and local statutes and

implementing rules or regulations.

Expectations for Individuals

It is the minimum responsibility of every

individual working at a Company location

to comply with the requirements set

out in this document. It is not within

the scope of this document to detail all

government regulations or Company

EHS procedures, but rather to provide

an overview of Company requirements.

If any questions or concerns arise

about safe work practices, consult your

supervisor and/or a Company supervisor

for the facility where you are working.

Expectation of Contractors

Contractor shall be responsible

for compliance with the enclosed

requirements, other Company

requirements, which may be

subsequently issued, and all government

regulations applicable to Contractor’s

employees and subcontractors.

1. Contractor’s Commitment

Contractor shall demonstrate a strong

commitment to EHS matters and must

have established EHS-related policies

and procedures. Contractor shall be

responsible for complying with its

policies and procedures related to EHS

matters. Contractor shall be responsible

for all aspects of Contractor’s EHS

performance, and for ensuring that

Contractor has a supervisory person

at the worksite at all times who is

competent and has the authority to

implement the Contractor’s EHS system

properly and meet Company’s EHS

requirements. To assist Company in

evaluating Contractor’s EHS program

contents and implementation, Contractor

shall maintain a current Standardized

Safety Questionnaire (SSQ) through

PEC Premier (www.pecpremier.com).

Although participation in other PEC

Premier programs is voluntary at this

time, contractors who participate will be

given priority for assignment of work.

2. General Health, Safety and Welfare

Contractor is responsible for maintaining

all facilities and associated services

under Contractor’s direction or

responsibility in a manner which does

not create or otherwise contribute to an

unhealthy working or living environment.

In order to accomplish this objective,

Contractor shall ensure the following:

Page 11: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 2

11

Version 1.1

2.1 Contractor Personnel Fitness/

Personal Hygiene

Contractor and any of its subcontractors

acknowledge that the work to be

performed for Company by Contractor

and subcontractor employees can

require extensive physical demands.

Contractor and all subcontractors shall

ensure that all personnel assigned to any

Company location can safely perform

the essential functions of his/her job

assignment with or without reasonable

accommodation by Company. Contractor

shall ensure that Contractor’s personnel

maintain appropriate standards of

personal hygiene in connection with the

performance of the work on Company’s

behalf.

2.2 EHS Orientation

An employee EHS orientation program

shall be implemented by Contractor, and

shall be given to all of Contractor’s and

all subcontractors’ personnel, regardless

of prior experience. This EHS orientation

shall address Contractor’s mandatory

EHS procedures, rules, and regulations.

Each employee of Contractor and any of

its subcontractors must receive the EHS

orientation before being allowed on any

of Company’s work sites.

2.3 Incident Reporting and Investigation

Contractor is required to immediately

notify OWS of all safety-related incidents

(e.g., any work-related injury, illness,

fatality or other EHS-related recordable

incidents) involving Contractor or any

subcontractor personnel. In addition, a

written report of such incident must be

prepared by Contractor and delivered to

Company within twenty-four (24) hours

of each such incident. Contractor shall

promptly investigate all such incidents,

conduct a Root Cause Analysis, and

provide final incident investigation

reports (including recommendations

and corrective action plans identified

during investigations) to Company within

thirty (30) days of the incident. The

Contractor shall agree that designated

Company personnel may participate

in any Contractor investigation of such

incidents. Contractor shall provide

Company with copies of all incident

reports that result in formal notification

to any Government agency.

Contractor will be required to provide

a monthly safety performance report

undertaken as part of, any work

performed by Contractor, or the

obligations of Contractor under any

Master Service Agreement (MSA). The

monthly cut off for each report shall be

close of business up to and including the

final day of each month. Contractor’s

safety performance report shall be based

on the following formula for determining

recordable incident frequency rate:

(Total Number of Fatalities, Lost Time

Incidents & Medical Treatments X

200,000) Total Number of Man-hours on

Company’s Work Sites

This information will be reported

monthly through Contractor’s PEC

Premier account (SSQ) and will be

completed no later than the 3rd business

day of the month following the reporting

month.

2.4 Reporting Hazards, Unsafe

Conditions, & Near Misses

Unsafe conditions shall be immediately

reported to Company. “Near Miss”

Page 12: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

12

Environmental Health & Safety

incidents that could have resulted in

injury or damage shall be reported

immediately to Company in order to

ensure corrective action is taken. At

Company’s discretion, a Root Cause

Analysis may be requested to fully

determine causes and appropriate

corrective actions to address “Near Miss”

incidents.

2.5 Behavior-Based Safety Observation

Programs

Behavior-Based Safety Observation

Programs are recognized as an

effective tool in the development and

growth of a proactive safety culture.

Contractors are encouraged, but not

required, to implement a Behavior-

Based Safety Observation Program.

When such programs are implemented

by Contractor, quarterly reports shall

be shared with Company where those

programs are used by Contractor crews

working on behalf of Company.

2.6 Substance Abuse, Dangerous

Materials and Firearms

Without prejudice to Company’s other

remedies, any of Contractor’s personnel

who are in breach of the provisions

of Company’s rules, regulations, and

policies relating to substance abuse,

dangerous materials, and firearms,

shall be immediately removed from

the applicable worksite. Entry into

Company property is conditioned

upon the Company’s right to conduct

unannounced searches for such

contraband. Contractor shall cause

Contractor’s personnel to comply

with and be subject to all such rules,

regulations, and policies.

2.7 Horseplay

Horseplay, such as wrestling and

practical jokes, etc., can be dangerous

and is prohibited at Company locations.

2.8 Housekeeping

Contractor must use good maintenance

practices around the work site. Work

areas shall be maintained in a neat and

orderly manner. Trash, spills, unused

tools or materials, etc. must be cleaned

up or put away as soon as possible.

Aisles, emergency exits, electrical

panel accesses, fire extinguishers and

emergency controls must be kept clear

and free of materials at all times. All

wastes are to be properly and safely

disposed of. Contractor shall leave all

work sites clean, orderly and in good

condition as directed by Company. All

remaining trash, debris, surplus materials

and equipment must be removed from

Company locations or neighboring

property upon completion of work.

2.9 Clothing and Other Apparel

Clothing suitable for the job shall be

worn. Long pants and shirts or coveralls

should be worn at all times during

the performance of the work. Ragged

or loose clothing and jewelry (rings,

watches, necklaces, etc.) are not to

be worn when operating equipment.

Any clothing that becomes saturated

with petroleum products or hazardous

chemicals should be promptly removed

or changed. Fire retardant clothing

(FRC) must be worn when working in

areas where the potential for a flash fire

exists. These areas include production

facilities, salt water disposal facilities,

compression facilities and well sites

during all phases of drilling, completions

and work-over activity.

Page 13: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 2

13

Version 1.1

Individuals on location but not engaged

in work activity or not present in the

area where work is conducted are not

required to wear FRC. Examples of these

exclusions include visits to a drilling

location to make material or equipment

deliveries and visits to secure signatures

on work tickets. Individuals conducting

construction activities on locations prior

to drilling a well are not required to wear

FRC.

2.10 Compressed Gas Cylinders and

Compressed Air

All compressed gas cylinders shall be

returned immediately to a suitable

storage area after use. Protective

caps shall be placed over the cylinder

valves when not in use or when being

transported. Compressed gas cylinders

shall be kept away from heat, fire, molten

metal, or electrical lines, and shall not be

transported by mobile cranes unless a

special carrier is used. Compressed gas

cylinders shall be stored in the upright

position and secured. Acetylene or

liquid compressed gas cylinders shall

never be used in a horizontal position,

as the liquid may be forced out through

the hose causing a fire hazard or

explosion. Cylinders shall be handled,

maintained and stored as required by

29CFR1910.253.

Compressed air shall not be used for

cleaning clothing or parts of the body.

If used for other cleaning, the discharge

shall not exceed thirty (30) psi and eye

protection shall be worn.

2.11 Storage, Use and Labeling of

Chemicals, Solvents and Paint

All chemicals, solvents, and paints are

to be stored in accordance with industry

practice in a storage locker designed and

installed to meet the requirements of

NFPA 30. Chemicals, solvents and paints

should be returned to the storage locker

after use and at the end of each workday

or shift.

All chemicals, solvents and paints must

be kept in clearly labeled containers.

Material Safety Data Sheets (“MSDS”)

must be supplied for Contractor’s

materials supplied under any MSA,

or in connection with any work

performed by Contractor or any of its

subcontractors, and all of Contractor’s

and all of its subcontractors’ personnel

must be instructed in the safe use

of the chemicals in accordance

with an appropriate written Hazard

Communication Program. Protective

equipment as outlined in the MSDS or as

otherwise required by operating location

management must be provided to and

worn by potentially exposed Contractor

personnel.

Personal protective equipment (PPE) or clothing shall meet American National Standards

Institute (ANSI) or a Company-approved equivalent standard.

Page 14: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

14

Environmental Health & Safety

Low flash point solvents shall not be

used for any washing or cleaning. The

use of gasoline for anything other than

the intended purpose is not permitted at

Company sites.

2.12 Personal Protective Equipment

Personal protective equipment (PPE)

or clothing shall meet American

National Standards Institute (ANSI) or a

Company-approved equivalent standard.

The wearing of appropriate PPE is

required at the worksite or any location

where hazards exist in the work place

and in all specifically designated areas.

The following PPE, along with training

in its use and care, is to be furnished by

Contractor:

• Head Protection

• Eye and Face Protection

• Hand and Foot Protection

• Hearing Protection

• Flame Resistant Clothing

• Clothing for Handling Hazardous

Chemicals

• Fall Protection

• Other equipment, i.e., breathing

apparatus, gloves, harnesses or

belts, rain gear or chemical resistant

clothing, etc., must be worn when

the hazards to which an individual is

exposed dictate their use.

The following items of PPE shall be used

and/or worn by Contractor’s personnel

at all times in and around the work site:

• Hard hats

• Safety Glasses with side shields

• Steel-Toed Safety Shoes or Boots

• Hearing Protection must be worn in

high-noise areas

2.13 Overhead Work

When working overhead, the area below

shall be roped off or other equivalent

measures taken to protect workers on

the worksite. Danger signs to be used

shall read “Danger – Overhead Work”

and will be conspicuously posted by

contractor. Please follow all applicable

signage requirements. When possible,

tools will be tied off or equipped with a

tether or lanyard.

Contractor’s personnel shall never pass

under a suspended load. Tag lines will

be used for positioning equipment

or materials during a lift. All lifts will

be conducted using properly rated

equipment, and all slings, chains and

other lifting devices will be certified

and tagged. All lifting equipment will be

inspected prior to use.

2.14 Scaffolds or Platforms

All scaffolds or platforms used for

installation and maintenance or removal

Contractor’s personnel shall never pass under a suspended load. Tag lines will be used for positioning

equipment or materials during a lift.

Page 15: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 2

15

Version 1.1

of machinery and equipment shall be

constructed, maintained, and used

in compliance with the applicable

occupational health and safety

construction regulations. All scaffolds

shall be inspected and tagged by a

competent individual prior to use.

2.15 Fall Protection Equipment

Full body safety harnesses and lifelines

shall be supplied by Contractor and

worn by all workers when working

above six (6’) feet. All fall protection

equipment shall be routinely inspected

and maintained following manufacturer

recommendations.

2.16 Non-Destructive Testing (NDT)

Radioactive isotopes, x-rays, etc., shall

only be used by licensed individuals.

All others onsite shall be notified of the

testing activities and instructed to stay

clear of the area. NDT may have to be

scheduled such that individuals do not

have to work in the affected area.

2.17 Safe Work Systems (SWS)

Safe Work Systems include Permit to

Work (PTW), Confined Space Entry

(CSE), Hot Work, Lock-out Tag- out

(LOTO), and Trenching & Excavation.

Contractor is required to implement SWS

programs relevant to the work being

performed, including, but not limited to,

hot work, confined space entry, control

of potentially hazardous energy and

excavation work.

2.18 Hydrogen Sulfide

Hydrogen Sulfide, or H2S, may be

encountered at Company facilities.

Contractor is responsible for ensuring

that Contractor’s personnel are properly

trained and equipped in accordance

with applicable regulations and to a

recognized industry standard when

working in areas where hydrogen sulfide

may be encountered due to the nature of

the work.

2.19 Fire Protection

Any unauthorized use of fire protection

equipment for any other purpose other

than its intended use is forbidden.

Contractor shall provide fire protection

equipment appropriate for the work

being performed.

Smoking is only permitted in designated

areas. Any work that has the potential

to produce a spark or open flame (i.e.,

welding, cutting, grinding, electrical)

in areas where flammable vapors or

combustible materials may exist is

strictly prohibited.

2.20 Safety Equipment

Contractor shall provide adequate

safety equipment of an approved

type and amount as is required for the

Contractor shall provide fire protection equipment appropriate

for the work being performed.

Page 16: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

16

Environmental Health & Safety

performance of the work. Contractor

shall maintain this equipment in a

professional manner as dictated by legal

and industry standards. In addition,

Contractor shall keep up-to-date records

of all said equipment.

2.21 Safety Training

Contractor shall ensure that Contractor’s

personnel have been given the

necessary safety, emergency, and job-

related training required by petroleum

industry standards and practice, as

well as Contractor’s and Company’s

EHS policies and procedures. Training

records must be available to Company

for review. Contractor shall ensure that

certificates for mandatory training have

been obtained by Contractor prior to

Contractor’s personnel travelling to any

location to start the work.

2.22 EHS Meetings

Regular EHS meetings should be held

and pre-job toolbox talks should be

established. Such EHS meetings should

be documented and copies forwarded to

Company’s Authorized Representative as

requested.

2.23 English Language Proficiency

Contractor shall ensure that all

Contractor management and supervisory

personnel are proficient in reading and

writing of the English language. This is

critical for all aspects of EHS including

implementation of procedures, permits

to work, training, signs, and emergency

response actions.

2.24 DOT Safety

Contractor shall operate all Commercial

Motor Vehicles in compliance with

State and Federal Motor Carrier Safety

Regulations.

2.25 Minimum Certifications and

Licenses

Contractor will ensure that all personnel

have the necessary certifications or

licenses required for their jobs. Examples

include, but are not limited to, IADC Well

Control, radiation safety, rigger, crane

operator, welder, electrician, plumber,

forklift operator and commercial motor

vehicle driver.

2.26 Electrical Safety

Contractor shall ensure that Contractor’s personnel have

been given the necessary safety, emergency, and job- related training

required by petroleum industry standards and practice, as well as Contractor’s and Company’s EHS

policies and procedures.

Page 17: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 2

17

Version 1.1

Contractor’s personnel working

around electrical equipment shall take

precautions to ensure that the equipment

is de-energized while work is being

conducted on or around such equipment.

Work that is to be conducted near any

overhead power line shall be planned

such that a clearance of no less than

ten feet is maintained throughout the

duration of the job to prevent accidental

contact with energized equipment

or lines. If work is to be performed

within a ten-foot radius of overhead

energized equipment, the equipment

must be de-energized prior to starting

the work, unless adequately controlled

by the safe work system. Ladders

used around electrical equipment

should be constructed of wood or

other nonconductive material. Strict

precautions should be taken to ensure

that all equipment used is properly

grounded and that accidental contact

with ungrounded electrical sources is

prevented.

2.27 Emergencies

Contractor’s personnel shall become

familiar with Company’s Emergency

Response Plans and Procedures at

Company work locations and will

participate in emergency drills when

conducted on Company property. If there

are questions concerning evacuation

or emergency response arrangements,

Contractor must immediately notify

a Company supervisor for further

explanation.

3. Environmental Management

Contractor is responsible for compliance

with all applicable U.S. Environmental

Protection Agency, state and other

federal laws and regulations related to

the environment. Contractor shall pay

due regard to the environment and

shall act responsibly in order to protect

the environment from adverse effects

resulting from Contractor’s activities and

to minimize any adverse impact which

may arise from such activities. In order

to accomplish this objective, Contractor

shall ensure the following:

3.1 Environmental Housekeeping

All work and maintenance shall be

completed in such a manner as to

preclude contamination of land sites and

subterranean fresh water zones through

the use of good international oil industry

practices.

3.2 Reporting

Contractor shall immediately report any

oil, produced water or chemical spills to

Company using Oasis’ online reporting

If there are questions concerning evacuation or emergency response

arrangements, Contractor must immediately notify a Company

supervisor for further explanation.

Page 18: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

18

Environmental Health & Safety

system at: www.oasispetroleum.com.

3.3 Diligence

Company, to ensure there are no

detrimental effects being imposed on

surrounding inhabitants, may periodically

assess noise levels from operations.

When requested by Company, Contractor

shall install sound absorption and

mitigation devices.

3.4 Waste Management

All unused chemicals NOT consumed

in operations or maintenance shall be

kept in stock, returned to the supplier

if applicable, recycled, or returned by

Contractor at its sole expense.

3.4.1 Waste Management Plan

At the discretion of Company and

dependent on the nature of work,

Contractor may be requested to develop

and implement a Waste Management

Plan (WMP) for handling and disposing

of hazardous and non- hazardous waste

material. This WMP shall be subject to

the review and approval of Company. At

a minimum, all wastes shall be identified

and catalogued as either Non-Hazardous

and/or Hazardous Wastes.

3.5 Tanks and Vessels

Tanks or vessels for fuel and lubricants

storage shall be properly closed,

installed at ground level, and be

contained inside an impermeable dike

technically designed for this purpose,

with a retention capacity equal to the

110% of the largest tank. Tanks or vessels

shall comply with all technical and

safety requirements to avoid excessive

evaporation, contamination, explosion

or fuel spill. The Contractor shall inspect

these tanks on a daily basis and any

accumulation of fuel/oil shall be removed

to preclude eventual overflows and

seepage into the ground.

3.6 Waste Water

All wash down water and other water

derived from execution of the work is

be controlled and managed in such a

manner as to prevent direct discharge to

land or inland rivers and lakes.

3.7 Wildlife Management

Contractor’s employees shall not hunt,

fish, trap, trade or keep wild animals in

captivity on Company locations.

All unused chemicals NOT consumed in operations or maintenance shall be kept in stock, returned to the

supplier if applicable, recycled, or returned by Contractor at its sole

expense.

Page 19: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 2

19

Version 1.1

Page 20: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Program Administration

20

3.0 Scope3.1 Engineering

3.2 Land Department

3.3 Construction Department

3.4 Operations Department

3.5 Regulatory Compliance

3.0 DOT Pipeline Construction3.1 Veriforce

4.0 Non-DOT Pipelines4.1 Recordkeeping

5.0 Internal Compliance5.1 Management of Change

Table of Contents

22

24

27

27

Page 21: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 3

Version 1.1

21

Program Administration

DOT - PHMSA - Department of

Transportation – (Pipeline and Hazardous

Materials Safety Administration).

Oversees construction, integrity

management, public awareness and

reporting on all regulated pipelines.

API - American Petroleum Institute.

Provides best practices and guidelines

for public awareness and construction of

DOT regulated pipelines.

Process Management - Methods of

administrating all OMS projects from the

planning stage to final completion. This

includes; engineering, AFE development,

landowner agreements, permitting,

construction, inspection, and final

reporting.

One Call - Process used to manage and

track all requests to perform excavation

activities.

High-Consequence Area - Distance from

any pipeline where “higher than normal”

risk is thought to exist. Determined by

the type of material, size of pipe, and

proximity to public areas.

Public Awareness - Required planning

and sharing of knowledge in order to

keep any affected public informed of

Oasis projects on a consistent basis.

Stakeholders - Individuals who reside

or own property near a DOT regulated

pipeline.

AFE - Authorization for Expenditures

SWD - Salt Water Disposal

Departments: Engineering, Land,

Construction, Production

Considerations: Quality Control,

Management of Change

Page 22: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Program Administration

22

3.0 Scope

This section has been structured to

provide a guiding document for OMS

personnel and service providers in

order to understand the process for

developing, completing, and maintaining

all portions of the OMS Business Unit.

3.1 Engineering

OMS Engineering performs many of the

developmental and financial functions of

Oasis Midstream Services.

Design and coordinate project technical

scopes

Comply with governmental regulations

and industry best practices

Determine pipe size and design

Determine equipment size and design

Develop and communicate OMS internal

scopes of work, and contractor scopes of

work.

Model existing and proposed pipelines

Support Construction, Operations,

project engineering, and commercial

development

Perform hydraulic computer modeling to

design gathering systems, and identify

methods to increase existing systems

efficiency and production volumes.

Develop required authorization for

expenditures AFE’s

Create and submit AFEs and economic

justification metrics

Track costs and monitor expenditures for

all AFE’s and budgets

Coordinate project activities with

multiple entities including Marketing,

Operations, Land, Legal, and

Accounting along with external entities

such as service providers, vendors,

government agencies, regulatory bodies,

landowners, and other production

companies.

Track all production volumes and audit

performance

Track OMS revenue and expenditures

3.2 Land Department

• Receives mapping information from

Houston Engineering, outlining area

to be developed.

• Contacts surface owners for survey

permission

• Coordinates with construction group

to ensure survey accuracy and

confirm route with surface owners.

• Obtains ROW agreement in

coordination with surface owners.

• Receives permitting for all roads or

other utility crossings.

• Coordinates with construction

department and engineering prior to

project construction phase.

• Land and Construction coordinate

as-builds post construction.

• Reviews as-builds information and

designs with surface owners.

• Attaches As-build to ROW

agreement.

• Records ROW agreement with the

county.

• Coordinates with construction group

and surface/asset owners when

necessary to assess damages or

other finalization concerns.

Page 23: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 3

Version 1.1

23

• Manages any and all amendments.

• Agreement amendments initiated

by landowner, construction, or other

party when necessary, will restart the

agreement process.

• If any agreements require written

documentation with: city, county,

federal, land owners, stakeholders,

other utility owners, land department

will be present and execute such

agreements.

3.3 Construction Department

Develops Initial Cost Estimate.

Coordinates Survey with Survey Crews.

Completes Construction (Review section

4).

Reports to DOT and files all DOT

paperwork, reports, etc.

Internally files all agreements.

3.4 Operations Department

1. Foreman

Coordinates with construction on new

and existing pipeline layout.

Works with engineering on facility design

and layout.

Coordinates with team lead on day to

day operations of disposals and pipelines

Approves invoices of venders

transporting sw to disposals.

2. Team Lead

Coordinates with foreman and team

members in regards to daily maintenance

and repair of SWD’s and pipelines.

Assists team members with ongoing

operations as needed.

Covers for team members on days off.

3. Team Members

Inspect and maintain SWD’s on a daily

basis.

Perform quarterly pressure tests on all

pipelines within the OMS system.

Perform inspection and maintenance on

transfer pumps on a weekly basis.

In the event of a spill, they coordinate

cleanup and disposal of contaminated

materials.

4. Measurement

The measurement division of OMS

Operations department is primarily

responsible for the oil production

custody transfer to service providers

who purchase Oasis Petroleum’s crude

oil. Their functions are as follows:

Communicates with Purchasing Service

Providers.

Receives information about receiving

LACT Units.

Organizes set-up and ensures they are

correctly wired-in.

Coordinates startup.

Communicates with OMS Engineering for

projected start-up.

Performs daily measurement to collect

production information.

Page 24: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Program Administration

24

Communicates maintenance needs with

purchasing vendors.

Troubleshoots problems with pumps, and

other OMS equipment.

Performs proving operations on sales

meters.

Calibrates all meters on a quarterly basis.

3.5 Regulatory Compliance

Below are various regulatory

considerations that must are managed

by the OMS group internally, by use of

service providers, or in conjunction with

other departments when necessary.

1. One Call System Management

Manages the process and system utilized

by OMS personnel to track, record,

and complete one-call requests and

notifications.

Completes all requirements prompted by

OMS designated online reporting system.

Duties include one-calls requested in

Montana.

Training and Awareness.

• Employees

• Contractors

• Line Locator Qualifications

2. Construction Documentation

Project Build Record – [ref. Section 4.4.2]

PBR – Figure 1

The Project Build Record is utilized as

a recording tool for OMS Construction

personnel to track and manage that all

required documents are created, stored,

and completed throughout the process

of construction. They apply to both DOT

and Non DOT Lines

Completing Project Build Records

Construction Administration personnel

will ensure all necessary documents are

contained with the appropriate files,

both physically and electronically.

Administrative personnel archive

construction and process information

electronically on the designated server.

Inspectors are responsible for

completing and delivering PBR’s to

OMS managers and/or administrative

personnel.

3.0 DOT Pipeline Construction

1. Reporting Procedures

A) Annual Reporting

New Construction

All new construction projects involving

DOT Lines must be documented with as

builds attached.

Types of Pipe

By classification, by type Must be

recorded and reported annually.

Length of Pipes

By classification, by type must be

recorded and reported annually.

Page 25: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 3

Version 1.1

25

Figure 1 - Project Build Record

Page 26: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Program Administration

26

Incidents

Any incidents involving OMS DOT lines

must be documented and incident

reports must be completed and filed

immediately onto the PHSMA portal

database.

Drug Testing Information

OMS personnel who are responsible for:

constructing, completing; maintaining; or

responding to emergencies on any DOT

regulated pipeline must be part of a DOT

standard drug testing consortium and

plan.

Accidents

Accidents involving any DOT pipeline

must also be reported immediately online

within the PHMSA portal.

Near Miss / Incident Reporting (to

PHMSA – online – within 24 hours of any

incident)

Integrity Management

Integrity management programs involve

methods of ensuring the longevity and

safety of DOT Regulated pipelines.

This can include maintenance, public

awareness programs (Including posting,

mailers, and pipeline markers) and

preventative maintenance.

• Maintenance

• Quarterly Maintenance (Documented)

• Pressure Testing

• Leak Testing

• Valve Operation / Inspection

• ROW Inspection

• Equipment Maintenance and

Inspection

• Public Awareness Programs

• Public Awareness programs include

the following necessary components:

• Mailers / Reports

• Response Metrics

• Surveys

• Public Awareness Meetings

The value and effectiveness of these

programs must be audited on an

annual basis, reports compiled, and

findings recorded for ongoing program

development.

Contractor Management

DOT standards require that contractors

performing work on behalf of any

pipeline regulated by the DOT, complete

operator qualification programs and be

enrolled in DOT regulated drug & alcohol

consortiums. OMS utilizes Veriforce as

their approved service provider and

standardization group for contractors

performing construction, maintenance,

or emergency response on DOT

regulated pipelines.

3.1 Veriforce

Drug and Alcohol Programs

100% Consortium Participation

All personnel who take part in the

construction of a DOT regulated pipeline;

inspectors, foreman, supervisors,

laborers, truck drivers, must be enrolled

in a DOT consortium. Veriforce verifies

that selected contractors are enrolled,

and make these records available to OMS

personnel.

Internal Review

OMS regards the safety and health of

their contractors highly. To ensure that

Page 27: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 3

Version 1.1

27

contractors are up-to-date with training

and verification, OMS will perform a

review semi-annually for gaps in any

contractor compliance.

Recordkeeping

Throughout the process of construction

of DOT lines, all records of construction

data must be maintained. Some of these

include:

• Pipe and special invoices and

manufacturer information

• Fuse logs

• Pressure / Leak Testing information

• Weld tests and Welder certification

information

• Annual Review

• Records will be reviewed and audited

on an annual basis. This process will

correlate with the April 15th deadline

for DOT reporting.

4.0 Non-DOT Pipelines

4.1. Recordkeeping

Although non-regulated pipelines

do not require records be kept as

thoroughly and completely as regulated

pipelines, OMS expects that the same

recordkeeping procedures be followed.

5.0 Internal Compliance

It is OMS expectation that its operations

be reviewed on a regular basis by OMS

personnel who will assess its process

from a quality assurance and quality

control perspective. Some of these

functions are as follows.

5.1.Management of Change

When a change to an internal OMS

system occurs, a Management of Change

(MOC) process must be completed. This

is to ensure that all changes with OMS

production are documented thoroughly,

included with justification for the

change, cost savings (if applicable) and

desired outcome. These processes will

be reviewed from time to time to ensure

that changes being made are effective.

Changes that require an MOC process

include, but are not limited to:

• Administration Procedures

• Existing Lines

• Clean-ups

• Processes

• Type of Equipment Used

(Technology)

• Methods of Document Control

• Responsibility changes

• Divisions created

• Final Inspection/ Close-out Protocol

Page 28: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

28

Construction Guidelines

References

Federal Standards

OSHA

1926.651

1926.652

DOT (if applicable)

T.49.C.D.192

T.49.C.D.195

Other Standards

ASTM

F2620

D638

D1598

2634

C150

API

1104

1107

NACE

#1 - Construction

Process

Material Transfer

ROW Establishment

ROW Survey

ROW Construction

Pipelaying

Tie-ins

Crossings

Civil Construction

Facility Construction

Coating

Backfill

Pressure Testing

ROW Cleanup

Pressure Testing

Considerations

PPE

Hard Hat

FR Clothing

Goggles

Face Shield

Hard Toed boots

Chemical Resistant Gloves

Safety Glasses

Other equipment as applicable

Page 29: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

29

Version 1.1

Construction Guidelines

Oasis Representative - Any individual

who has authority on an Oasis project,

location, or situation regarding Oasis

assets or personnel.

Inspector - Any individual authorized

to supervise construction, quality, or

management of an Oasis construction

project.

Material Transfer - (See Material Transfer

Form-OMS-10010) The process used to

track OMS inventory

ROW - Right-of-Way Predetermined

area established by agreement or grant,

to pass along a specific route through

grounds or property belonging to

another party.

Poly (PE) - Polypropylene Pipe. Also

known as “Plastic” or HDPE Pipe.

SDS - Safety Data Sheets

Instrumentation & Electrical (I&E) -

Components involved in automated

measurement and electrical interface

with a variety of pipeline and production

equipment.

OSHA - Occupational Safety and Health

Administration

DOT - Department of Transportation

ASTM - American Society for Testing &

Materials

AISC - American Institute of Steel

Construction

API - American Petroleum Institute

SMYS - Specified Minimum Yield

Strength

NACE - National Association of Corrosion

Engineers

SSPC - Society for Protective Coatings

Holiday - A pipe anomaly such as a ding

or dent that will cause early corrosion.

Page 30: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

30

Construction Guidelines

4.1 Material Transfer4.1.1 General

A) Pipe HandlingB) Inventory

C) LoadingD) Material Return

4.2 ROW Corridor Establishment4.2.1 General

A) Engineering – Develops Project Scope and Design

4.3 Right of Way (ROW) Survey4.3.1 General

A) Construction StakingB) As BuildC) Mapping

4.4 ROW Construction4.4.1 General

A) One CallB) Line LocatingC) HydroVaccing

D) Relocating4.4.2 Project Build Record (PBR)

4.4.3 Preparation of Right of Way (ROW)

A) ClearingB) GradingC) Topsoil

4.4.5 Housekeeping

A) Poly shavingsB) Tools

C) Equipment Storage4.4.6 Preservation of ROW

4.5 Pipelining4.5.1 General

4.5.2 Stringing

A) Quality ControlB) Unloading Methods

C) InspectionA) General Considerations

B) Butt Fusion Joining RestrictionsC) Outside Diameter (OD) Compatibility

D) Wall Thickness (DR) Compatibility

Table of Contents

34

38

39

39

41

Page 31: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

31

Version 1.1

E) Fusion Quality Verification – Data Logging and TestingF) Fusion Evaluation Tests – Mechanical Field and Laboratory Tests

G) Weather Guidelines4.5.4 Bending

A) Field-Bending – Steel PipeB) Field Bend Data - Steel Pipe

4.5.5 Trenching / Excavation

A) Trenching / Excavation PermittingB) Daily Inspection

C) Trench Boxes / Shoring4.5.6 Lowering Pipe

A) Trench Bed ConditionB) Trench Bed MaterialC) Inspection & Testing

4.5.7 Welding

A) GeneralB) Requirements

C) MethodD) Line Pipe Weld Procedures

4.5.8 Boring

A) Equipment RequirementsB) Boring System

C) Other EquipmentD) Boring Operations

E) Utility Locates

4.6 Tie-Ins4.6.1 General

A) Water ConsiderationsB) Backfilling

C). Cold CuttingD) Live Tie-InE) Squeezing

4.7 Crossings4.7.1 General

A) ApprovalsB) Line Crossings

C) Road crossingsD) Water CrossingsE) Boring Crossings

F) Section Lines

58

62

Page 32: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

32

Construction Guidelines

4.8 Civil Construction4.8.1 General

A) CementB) Structural Steel

C) Roads / WalkwaysD) Location / Well Pad

4.9 Facility Construction4.9.1 General

A) PumpsB) HousesC) Risers

D) Instrumentation and Electrical (I&E)

4.10 Coating4.10.1 General

A) PaintingB) External Painting

C) Jeep Sticks

4.11 Tracer Tape & Wire4.11.1 General

A) DepthB) Wire Location

C) Wire Protection

4.12 Backfill4.12.1 Material

4.12.2 Backfill Method

A) Backfill MaterialB) General

C) PaddingD) Padding Density

4.12.3 Final Compaction

A) Moisture4.12.4 Restoration of Construction Areas

4.12.5 Overburden / Crown

4.12.6 Irrigation & Drainage

4.12.7. Reinforcing

4.12.8. Topsoil

63

65

66

69

70

Page 33: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

33

Version 1.1

4.13 Leak & Pressure Testing4.13.1 General

A) Location of EquipmentB) Test Duration

C) Water SourcesD) Failures

E) DepressurizingF) Dewatering

4.14 ROW Clean-Up4.14.1 Post-Construction Clean-up

A) FencesB) Gates

C) Line MarkersD) Test LeadsE) Reseeding

F) Erosion ControlG) Rock Picking

4.15 Start-upA) Removal of Isolation Devices

B) Opening of Block ValvesC) Suction Line Leak Test

D) Oil SystemE) Pump to Line Leak Test

F) System Leak Tests

4.16 Project Sign-off4.16.1 Final Inspection

72

74

74

76

Page 34: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

34

Construction Guidelines

4.1 Material Transfer

4.1.1 General

Oasis Midstream Services (OMS) requires

that all operations be performed in a safe

and efficient manner. A major component

of operating this way involves the

process of handling and transporting

materials. This section reviews overviews

safe guidelines in order to handle and

transport materials for OMS in a safe and

professional manner.

A) Pipe Handling

1. Prior to loading or unloading any pipe,

trucks and trailers must be parked in

a way that they are level and secure.

Parking (hand) brakes should be set and

the wheels correctly chocked. The truck’s

engine should be off and left in gear and

the driver’s location known at all times.

Personnel directly involved should be

the only ones within the area of pipe

handling. Non-essential personnel must

stay clear of work area.

2. Poly pipe becomes extremely slippery

when wet. Caution should be used at all

times when handling poly pipe, especially

in rainy or snowy conditions. When

handling this pipe in these conditions

work slowly.

3. Black poly pipe becomes extremely

hot when exposed to direct sunlight,

therefore exercise caution and wear

appropriate PPE at all times when

handling black poly pipe.

B) Inventory

It is the responsibility of OMS personnel

to oversee and take record of all

equipment, pipes, and specials that

enter or leave the OMS yard. This will be

accomplished through internal inventory

management systems.

1.A) Equipment Storage - Jobsite

Storage areas should have smooth, level

surfaces that are free of stones, debris

and other materials that may damage

pipe.

If no adequate surface can be prepared,

pipe should be placed on evenly

spaced planking, racks, or other means

of supporting and protecting pipes

and equipment. Weather conditions

should also be considered when storing

materials that could be damaged by

extreme temperatures, ice, wind, or

moisture.

Pipe should be separated and stored

according to length and diameter as is

most feasible. Piles must only contain a

single size of pipe and be constructed in

a pyramid shape with the bottom layer

braced to prevent movement of any kind.

Rows of pipe should all for easy loading

and offloading of pipe by use of available

loading equipment.

1.B) Off-Site Storage

When storing pipe off-site, it should

be placed in pipe racks according to

length and diameter of pipe to prevent

from rolling or falling. Pipe larger than 2

inches should be stacked with spacing

strips.

If pipe is stored outdoors, pipe racks

should be made of material that will not

deteriorate.

1.C) Indoor/Outdoor Storage

Page 35: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

35

Version 1.1

Black poly pipe contains more than 2%

carbon black and will resist UV damage.

It may be stored unprotected from UV.

Other colors must be stored no longer

than two years.

C) Loading

1. Operator Experience

Only experienced operators are allowed

to use heavy equipment. This includes

a verification as per OSHA standard

1926.1427.

Staging area must be clear of workers,

equipment and other obstacles while

material is being loaded or unloaded and

must allow for clear line of sight.

2. Weight Limitations

Never exceed rated lifting capacity of

equipment.

The proper and safe use of forklifts

and other heavy equipment is the

responsibility of the contractor.

2.A) Inspection

• Check forks for jagged edges/burrs.

• Forks set to widest setting.

• Always lift from center.

2.B) Fork Application

Slide forks gently underneath pipe. Take

care to ensure that forks are not forced

underneath pipe, or positioned in a way

that could damage pipe racks.

2.C) Tilt Degree

When tilting the load of pipe or spools

tilt slightly back in order to stabilize and

prevent objects from rolling or sliding

forward without control.

2.D) Handling Loads

When transporting a load, move with the

load as close to the ground as possible,

taking care to not allow pipe to drag.

Drive as slowly as necessary as to avoid

bouncing.

3. Front End Loaders

The proper and safe use of front end

loaders falls under the responsibility of

the operator.

3.A) Compliance

If equipped with forks, loaders are used

as forklifts and treated as such. Always

maintain stability and center of gravity

precautions.

4. Pipe Handling Accessories

Accessories used to handle and support

pipe should be properly constructed and

rated above the capacity of the load that

they are intended to support.

Never exceed rated lifting capacity of equipment.

Page 36: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

36

Construction Guidelines

Chains, steel cable, wire rope, or hooks

are not to be used to handle poly pipe.

Slings must be wide band to distribute

load.

Nylon rope is acceptable to use with poly

pipe.

Only specially designed pipe tongs can

be used to lift poly pipe.

Lifting capacities of equipment and

attachments are not to be exceeded. The

angle between each lifting leg must not

exceed 45 degrees.

4.A) Unloading Coiled Pipe

Certain precautions must be taken into

consideration prior to unloading coiled

pipe. When unstrapping a load of coiled

pipe, it is necessary to ensure that

personnel are out of line with the ends

of pipe. Trailers must be level before

unloading either palletized or non-

palletized coils.

Never push, pull or roll coils off of trailer.

Never stand behind, under or around the

load as it is being unloaded.

When the securement banding is being

cut or removed, the coiled pipe has the

potential to whip away from the coil.

Ensure no personnel are in the area while

removing these bands.

DO NOT remove straps until sling is

secured.

4.B) Straight Length Pipe

It is necessary to ensure the load has not

shifted during transport before removing

securement straps.

Bundles should be unloaded with forks,

forked loaders or cranes with spreader

bars.

Steel bands used on bundles shall not

be removed until bundle is secure and

stabilized in storage area (remove from

ground with extension device).

Never stand on a load of pipe. If

breaking the banding is not possible

from the ground, personnel must remove

bands by the use of extension breaker

bars.

4.C) Strip Loads

Chains, steel cable, wire rope, or hooks are not to be used to handle

poly pipe. Slings must be wide band to distribute load. Nylon rope is

acceptable to use with poly pipe. Only specially designed pipe tongs

can be used to lift poly pipe.

Page 37: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

37

Version 1.1

Cranes should use spreader bars to

ensure proper transportation of the pipe.

Do not cut bands until pipe is secure in

storage.

Ensure all wheel chocks are in place

before beginning to unload.

D) Material Return

1. Material Transfer Forms (MTF)

All materials designated to arrive to,

or leave from Oasis yard, must have a

Material Transfer Form (MTF) completed

prior to being transported. Minimum

details to be included:

• Lease Name / Location

• AFE / LOE #

• Person receiving materials name/

company/signature

• Information about who the material

is for

2. Incoming Materials

2.A) Gate Check-in

All vendors or contractors delivering

material for OMS projects must check in

at the designated gate.

2.B) Bill of Lading

The yard personnel will unload the

material and check the material against

the packing list before signing the BOL

(Bill of Lading); personnel will then stage

the material in a predetermined location.

2.C) Damaged Material

If material is damaged beyond use/

repair, it will be cited as “Condition D”

and billed to contractor or rejected.

3. Outgoing Material

3.A) Gate Checkout

All personnel with the crews picking up

material must check in at the north gate.

Yard personnel will receive and must

have the following information before

loading any material:

1. Location

2. AFE

3. Name of Oasis supervisor

4. List of material required

The yard personnel will then fill out a

yard Material Transfer Form (MTF) and

have the person picking up the material

sign it before leaving.

All materials designated to arrive to, or leave from Oasis yard, must

have a Material Transfer Form (MTF) completed prior to being

transported.

Page 38: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

38

Construction Guidelines

Support documents [OMS-10010 –

Material Transfer Form]

4.2 ROW Corridor Establishment

4.2.1 General

The corridor is established as the

beginning stage of preparation for

installing a pipeline. Each department has

various roles to play in this development

process. They are outlined below, as well

as other establishment criteria.

A) Engineering – Develops Project Scope and Design

Responsibilities

1. The OMS engineering group will

develop all pressure scopes, elevation,

necessary equipment, operating

specifications, and other data relative

to the design and operation of the

proposed pipeline.

B) Land department – Manages Agreements and Planning

Responsibilities

1. Develop and approve proposed

pipeline route taking into consideration:

feasibility; financial viability; topography;

environmental; operational optimization;

and gaining the necessary approvals

from stakeholders. Record plat to county

and work with other reporting and

recording agencies.

2. Record plat to county and work with

other reporting and recording agencies.

3. Obtain and finalize ROW agreement

and landowner signoff.

4. After project completion, obtain final

signature from landowner to release the

project.

C) Construction Department – Completes the Project

Responsibilities

1. Manage contractors, understand

deadlines, follow regulatory guidelines,

maintain quality control and review OMS

programs in order to verify compliance.

In addition to ensuring all documentation

is maintained, remediation is

accomplished if necessary, and all

procedures are followed.

2. The construction department is also

required to notify Land Department

when a project is complete.

Yard personnel will receive and must have the following information

before loading any material:Location, AFE, Name of Oasis

supervisor, and the list of material required

Page 39: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

39

Version 1.1

4.3 Right of Way (ROW) Survey

4.3.1 General

The ROW is a route that is selected on a

preliminary basis to determine the scope

and cost of a project (determined by

the engineering department). The ROW

is a legal right, established by usage

or grant, to pass along a specific route

through grounds or property belonging

to another.

A) Construction Staking

Construction staking will be

performed with the direction of Oasis

Representatives. Oasis will mark route

of the centerline of the right-of-way or

ROW, as well as the ROW boundaries,

at the company’s discretion. Oasis

contractors will be responsible for

staking the ditch line within the right-

of-way ROW, which will be addressed

in the construction folder. Stakes will

be of such regularity that continuity

may be maintained, normally at 100-

to 200-foot intervals, along with the

beginning, middle and end of all points

of intersection, bores, and any/all other

landowner considerations. These stakes

will also be used to gauge construction

progress and to reference specific

locations on drawings and in reports.

Contractor is responsible for submitting

One Call to coordinate locating existing

pipelines, sewers, water or gas mains,

and electric or telephone installations.

Contractor shall take all necessary

precautions to protect and to avoid

damage or interference with these

facilities and shall repair these lines

immediately if damaged. Contractor is

responsible for maintaining all survey and

line markers. Failure to do so will result

in immediate shutdown of the job until

adequate markers are maintained.

B) As Build

-Reference Section 3-

C) Mapping

The scope of mapping is transferred

from survey to the Houston mapping

group with all required details and

info. Houston will then complete a field

map with all valves, roads, crossings,

landmarks, well names, etc.

4.4 ROW Construction

4.4.1 General

The Right of Way is the most permanent

picture of the quality of work that OMS

does. The process involved in acquiring,

maintaining, and leaving the ROW are

extremely important to our relationships

with our stakeholders, our assets, and

our reputation.

A) One Call

A One Call must be made prior to any

digging being performed. This can be

accomplished by calling 811 in both North

Dakota and Montana. In Montana, it is

also possible to fax-a-locate, however

there must be a pre-approval process

completed prior to the One Call being

processed. Montana’s One Call fax

number: (406) 752-7306 and website:

(www.mt1call.com).

*Faxing a locate to ND One Call will only

be available through the end of Dec

2014.

1. ‘Locate’ Wait Duration

Page 40: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

40

Construction Guidelines

After a One Call is made, line-locating

personnel will arrive at the desired

location within 48 hours of the One Call

submission and locate any Oasis, or other

entity’s lines. Oasis does not authorize

excavation prior to lines being located

under ANY circumstances, even if at

times a locate does not occur within 48

hours. The locate ticket must be followed

to the exact specifications written on the

ticket.

B) Line Locating

1. Project Relocating & Re-spots

After a line has been located, there are

many things that could require a “re-

spot” including:

Flags being moved by landowner;

Flags being moved by contractor/service

provider;

Uncertainty about accuracy of utility /

facility markers;

Change in job scope / area;

One Call tickets whose territory located

does not clearly indicate where the

locate starts or ends.

2. Distance from Flags

Minimum distance to maintain is 2 feet

from any flag or utility marker, in any

direction.

C) HydroVaccing

Hydrovaccing is the process of locating

a line with non-destructive means. Water

is used in lieu of shovels, excavation

equipment, etc. This process uses water

at high pressures to locate lines, and

has the additional benefit of vacuuming,

or removing the water/mud that is

created in the process. All tie-ins must be

hydrovacced, as well as any time a line

crossing is performed.

D) Relocating

Locate tickets are good for 21 days

only. The locate ticket will indicate the

expiration of the One Call ticket.

4.4.2 Project Build Record (PBR)

A) Required forms

• [OMS 1001] Oasis Dig Permit

• [OMS 1002] Anode Installation

• [OMS 1003] Confined Space Entry

Permit

• [OMS 1004] Construction Summary

• [OMS 1005] Foreign Line Crossing

• [OMS 1006] Hot Tap Permit

• [OMS 1007] Hot Tap Info

• [OMS 1008] Hydro Test Data

• [OMS 1009] Locate Wire Installation

• [OMS 1010] LOTO Process

• [OMS 1011] One Call Log

• [OMS 1012] Pipe Tally

• [OMS 1013] Pressure Test Data

• [OMS 1014] Poly Report

• [OMS 1015] Project Build Record

• [OMS 1016] Steel Pipe Record

• [OMS 1017] Cost Estimate

• [OMS 1018] Measurement Change

Form

• [OMS 1019] Final Inspection Report

4.4.3 Preparation of Right of Way

(ROW)

A) Clearing

It is required prior to construction that

removal of brush, grass, weeds, trees,

Page 41: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

41

Version 1.1

crops, or anything that is on the ROW

occurs. Contractor will use Brush Hog, or

other sufficient means to accomplish this.

B) Grading

Preparing the ROW to the standard

grade, side hilling, acquiring proper highs

and lows to ensure your equipment gets

through without issue.

C) Topsoil

Cut into your soil top. Location

geography will determine depth of

topsoil. Topsoil is moved to one side of

ROW until the final step where it will be

redistributed evenly. State lands require

12 inches of topsoil to be removed.

4.4.4 ROW Access

Oasis Petroleum shall obtain easements

for ROW’s and permits for roads and

railroad crossings. Contractors may only

access the ROW from approved public

roads and points unless specifically

designated by Oasis representatives.

No two-track roads will be used unless

specifically authorized. Section lines

can only be used with prior Oasis

authorization.

Settlement of any off-ROW damages is

the sole responsibility of the contractor,

specific indemnity language is written

into Oasis Master Service Agreements.

4.4.5 Housekeeping

A) Poly shavings

Any waste materials created during the

process of stringing, fusing, bending,

or shaving pipe must be gathered and

disposed of in the correct manner. These

spare materials are not to be buried or

left behind.

B) Tools

Tools must be kept a minimum of 2

feet from the edge from any excavation

including open excavation, trench, bell

hole, etc.

C) Equipment Storage

Equipment storage locations/laydown

areas must be established prior to the

commencements of Oasis projects. All

agreements for additional space will

be initiated by the contractor but must

have Oasis approval prior to contact

with landowners. The cost of these

areas may be assessed only to the

contractor, however, Oasis may choose

to be involved or lead in the negotiation

process.

4.4.6 Preservation of ROW

Contractors shall offset all centerline and

locating stakes in a uniform manner, as

required for clearing and grading. After

clearing and grading contractors shall

reset the stakes in their original position.

Contractors will be held responsible for

the preservation of all stakes and line

markers. Contractors shall bear the cost

of replacing any stakes destroyed or lost

and re-survey work required.

4.5 Pipelining

4.5.1 General

The method used to lay, seal and bury

pipe is foundational to the success

of OMS. When contractors, internal

departments, and engineering groups

work together as a team, projects will be

Page 42: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

42

Construction Guidelines

completed correctly and to the quality

OMS aspires to. The following guidelines

have been created with the expectation

that contractors will have reference

material to rely on in order to uphold and

understand OMS requirements.

4.5.2 Stringing

A) Quality Control

OMS requests that pipe be strung along

the ROW and be aligned in accordance

with good pipeline construction practices

using pipe furnished only by Oasis.

Stringing of pipe on the ROW should

done in such a manner as to cause

minimal impact to the surround area, and

gaps shall be left at intervals to permit

use of the land and passage of farm

livestock and equipment across the ROW.

B) Unloading Methods

Pipe is to be unloaded from the stringing

trucks and lowered onto approved

padded skids by using canvas slings

or pipe hooks. Pipe is not to be rolled

off the truck. In areas where the ROW

crosses rocky terrain, special care shall

be taken in lowering the pipe to see that

pipe is not dropped on rocks or allowed

to rest on sharp or jagged surfaces.

Non-ferrous pipe can be pulled provided

that no visible damage occurs. A tag

line will be attached to hooks to control

the suspension of the pipe at each end

during stringing operations. In instances

where spooled pipe is being laid,

contractor is responsible for maintaining

pipe integrity. Pipe shall not be strung

without Oasis approval.

C) Inspection

After pipe has been strung, OMS

personnel and contractors will inspect it

thoroughly. Contractors will reimburse

Oasis for any and all damaged pipe.

D) Bedding

Bedding material must be clean sand or

soil and must not contain stones having

a maximum dimension larger than 2

inches. Material must be placed to a

minimum depth of

6 inches under the pipe and 6 inches

over the top of the pipe. The remaining

backfill must not contain rock larger than

6 inches. Organic material and wood are

not permitted for bedding and backfill

since they will deteriorate over time,

allowing for subsidence and subsequent

shifting and possible pipe damage.

4.5.3 Fusing

A) General Considerations

Butt-fusing operations and procedures

It is OMS expectation that contractors will provide trained and qualified personnel to perform butt-

fusion operations.

Page 43: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

43

Version 1.1

are not for novice employees. Personnel

must at minimum, prior to work,

understand and review manufacturer

recommendations and requirements.

Oasis can provide these materials if

contractor does not have access to

these materials. It is OMS expectation

that contractors will provide trained and

qualified personnel to perform butt-

fusion operations.

The process of butt fusion joins plain

end polyethylene pipes and fittings

end-to-end without couplings, inserts

or additional materials. Equipment must

be used to hold the components in

alignment and move the components

toward and away from each other

during preparation, heating and joining

operations. The equipment includes tools

to face (plane) and heat the component

ends.

Butt fusion equipment is manually

operated for smaller pipe sizes and

hydraulically operated for larger sizes.

The equipment covers a range of

pipe sizes and is properly set up by

adjusting pipe holding clamps, setting

the heating tool temperature, and for

hydraulic equipment, setting the fusion

joining pressure. Additional setup will be

required depending on the equipment.

Butt fusion equipment is set up,

operated and maintained in accordance

with the equipment manufacturer’s

instructions. Improperly set up, operated

or maintained fusion equipment can

produce faulty joints.

Other equipment such as pipe supports

and appropriate equipment for handling

pipe and fittings is required.

B) Butt Fusion Joining Restrictions

The ends of pipes and other components

such as fittings, flange adapters, MJ

adapters, etc., that are joined together

must have the same outside diameter

and comparable wall thickness.

Additional information about thickness

and diameter compatibility is found

below.

C) Outside Diameter (OD) Compatibility

Several OD controlled sizing systems

are used for Poly piping components.

These include IPS (iron pipe size), DIPS

(ductile iron pipe size), DIOD (ductile

iron outside diameter), CTS (copper

tubing size), inch-OD, or mm-OD as

applicable. For butt fusion joining, the

component ends being joined must be

the same outside diameter dimension

and system. For example, both pipes

must be the same IPS diameter, or the

same DIPS diameter. Different OD sizing

systems are not compatible, e.g., IPS and

DIPS cannot be butt fused to each other.

ID controlled (SIDR) pipes are joined

using insert type mechanical fittings and

are not suitable for butt fusion joining.

See Reference R-WL116 for applicable PE

pipe standards.

D) Wall Thickness (DR) Compatibility

The DR of the lower component ends

must not be less than 0.79 times the

DR of the higher component end. This

is to ensure the quality of flow rate, and

that pressures do not compromise the

components connections. In order to

determine if components with different

DR’s can be joined together, multiply the

higher DR by 0.79. If the lower DR is this

number or higher, the components can

be joined together using this procedure.

Page 44: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

44

Construction Guidelines

E) Fusion Quality Verification – Data Logging and Testing

It is recommended that hydraulic butt

fusion machines be equipped with data

logging technology to monitor and

record time, temperature and pressure

during fusion. Field fusion data logging

records that compare favorably with

tested trial fusion data logging records

can provide confidence in field fusion

quality. Data logging records must

be delivered to OMS personnel at the

completion of the project.

Fusion quality is tested by preparing a

trial fusion and performing destructive

tests such as two D638 tensile tests, a

DF2620 bent strap test, or ASTM F2634

tensile impact tests of specimens cut

from the fusion. Prior to testing, test

samples must be cooled to 73°F/23°C.

ASTM D638 tensile tests are conducted

on Type III or Type IV tensile bar

specimens machined from samples cut

longitudinally from each quadrant of a

trial fusion with the fusion in the center

of the reduced area. The sides of the

tensile bar specimen-reduced area must

be smooth and free from nicks and cuts.

If wall thickness is reduced, the tensile

specimen fused area should be from the

middle of the pipe wall. After machining,

condition test specimens by immersion

in temperature controlled circulating

air for not less than four hours or in

temperature controlled circulating water

for not less than one hour. Test at 73°F

and 2-in/min separation rate. Ductile

elongation should exceed 400% either

between the fusion and the end of the

gauge area, or for the entire gauge

area length. If desired, the tensile yield

strength of fusion test specimens and

pipe parent material test specimens may

be compared; however, the preferred

evaluation is ductile elongation rather

than tensile yield strength.

The pipes and specials shall be jointed

by automatic butt or electro fusion

welding to form a string above ground

and shall be supported by smooth

rollers. Three standard lengths of pipe on

each side of the fusion machine require

two roller supports per length of pipe.

All fusion joints shall be inspected and

assessed with joint record printouts from

the automatic butt or electro fusion

machine. Oasis personnel must approve

all joints before the contractor is allowed

to proceed with pipelining works. The

maximum pulling length of fusion jointed

PE pipes into position alongside or

directly into pipe trench after fusion

jointing shall not exceed 1,000 feet or

length limited by the hydraulic actuator

of the automatic butt fusion machine.

Dragging on ground surface is strictly

prohibited. All jointing of specials, tees

closing lengths etc., to be conducted in

the trench shall be by automatic electro

fusion couplers or other electro fusion

fittings.

Data logging records must be delivered to OMS personnel at the

completion of the project.

Page 45: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

45

Version 1.1

ASTM F2620 includes a bent strap test

for pipes having a wall thickness of 1 inch

(25 mm) or less. Butt fusions may be

evaluated by cutting straps from a trial

fusion and conducting an ASTM F2620

strap bend test. See Figure 2. The cut

through the fusion should be visually

examined. Voids or dis-bonded areas

are not acceptable. Strap specimens are

then bent with the pipe OD or ID to the

inside of the bend so that the ends of the

strap touch. Failure or dis-bonding at the

fusion is unacceptable.

F) Fusion Evaluation Tests – Mechanical Field and Laboratory Tests

ASTM standard tests and techniques

such as ASTM D638 tensile tests, ASTM

D1598 sustained pressure, ASTM D1599

quick burst, ASTM D1822 tensile impact

and ASTM F2634 high-speed tensile

impact are strongly recommended for

evaluating fusion joint quality. Published

ASTM testing procedures have been

confirmed to produce reliable, repeatable

results. Unproven, experimental, tests

and techniques even those that are being

developed, may be too stringent or

ineffective and are not reliable indicators

of fusion quality. Experimental tests

should not be used until published by

ASTM.

Tests such as root bend tests for metal

welds, bending a strap or coupon in

a bench vise, bending back and forth

multiple times, or hammering on bent

or unbent specimens are not reliable

indicators of butt fusion quality.

G) Weather Guidelines

Butt fusion can be successfully

performed over a broad range of field

conditions. However, some weather

and temperature conditions can affect

equipment operation or performance,

or could potentially introduce

contaminants, compromising joint

quality. Joining procedures may need

to be adjusted to compensate for wind,

weather or temperature. PE pipe and

fittings will expand and contract with

changes in temperature. If butt fusion

machine pipe clamp closure is limited,

shims of elastomeric material may be

necessary to secure very cold pipe

against slippage. In four-clamp machines,

shims should be used only in the outer

clamps.

1.A) Wind Effects

A windbreak or shelter should be used

when jobsite wind intensity exceeds

“gentle breeze” conditions.

Wind intensity above “strong breeze”

may require suspending fusing

operations.

4.5.4 Bending

A) Field-Bending – Steel Pipe

Joining procedures may need to be adjusted to compensate for wind,

weather or temperature.

Page 46: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

46

Construction Guidelines

Contractor shall make all necessary field

bends required in the construction of

the line except those shop bends which

company shall specifically furnish.

Contractor shall also fit the pipe to the

contour of the bottom of the ditch, and

shall restrict the arc and increase the

radius of the bends to such an extent as

will prevent the buckling or flattening

of the pipe, weakening of welds, and

will permit the free passage through

said bend of an internal inspection type

of pipeline scraper. All bends shall be

made using a lined bending shoe so as to

eliminate scratching and gouging of the

pipe.

Dimensions across the minimum and

maximum axis of the field bends will

be subject to measurement and shall

not have a difference in excess of 2.53

degrees.

Each field bend shall comply with the

following:

The bend must be smooth and uniform.

On pipe 12 inches and larger an internal

mandrel shall be used.

After bending the pipe must be free from

buckling, cracks, or any other mechanical

damage and must conform to the profile

of the completed ditch.

There must be no wrinkle bends or

mitered bends (not including deflections

up to 3 degrees that are caused by

misalignment).

No girth weld may be placed inside

the bending shoe if the weld protrudes

above the outer wall of the pipe.

Pipe containing a longitudinal weld must

be bent so that the seam is located near

the neutral axis.

No bend shall be made any closer than 5

feet from the end of a joint or 3 feet from

an existing girth weld.

B) Field Bend Data - Steel Pipe

All field bends shall be made by the cold

stretch bending method, and an accurate

method of measurement shall be used to

determine the tolerances as follows:

4.5.5 Trenching / Excavation

A) Trenching / Excavation Permitting

1) Dig Permit

Prior to any excavation an Oasis dig

permit must be complete [OMS Form

1000]. Included in this permit are

required action items including: ensuring

the applicable state One Call system

has been utilized; all potential utilities

and facilities have been identified; and

areas of concern hydrovacced etc. If an

excavation is determined to be 48 inches

or greater in depth, adequate sloping,

shoring, or trench boxes must be created

or installed. Other action items include:

North Dakota One Call has been notified

and contacts conducted to determine

existence and location of underground

facilities in the work area.

Available records have been referenced

and a plot plan indicating the location

of all underground facilities has been

provided and is available for reference at

the job site.

Have Oasis operations personnel been

consulted for obtaining or discussing:

Page 47: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

47

Version 1.1

Plot plans

Pipeline or facility maps

Lease maps

Has the work area been checked for

facilities/pipelines, or utility markers?

And companies on markers contacted?

Are there ANY signs of ground

disturbance within the proposed work

area?

Have attempts been made to

communicate with landowner to verify

buried utilities?

All necessary approvals, notification and

agreements have been obtained.

A pre-job safety meeting including

JSA and emergency response plan

completed?

The proposed ground disturbance

area(s) are identified and all underground

facilities in the dig zone/search zone

have been identified and incorporated

into the plan.

Approved techniques for exposing

facilities with 2 feet of ground

disturbance have been (or will be)

used to verify the location of all known

underground facilities.

Other required Safe Work Permits have

been issued (Confined Space, Hot Work,

LOTO, etc.)

Precautions have been taken to prevent

contact with overhead power lines

New non-metallic underground facilities

are being installed with tracers

All personnel involved in the excavation

have received the appropriate training

Risk has been assessed and provisions

have been made to address unattended

open excavations to ensure the safety

of other contractors, the public, wildlife,

etc.

B) Daily Inspection

A competent person must inspect

trenches that individuals plan to enter, or

could potentially enter as a part of their

All trench boxes or shoring must be approved by the manufacturer to be used at the depth they are

planned to be used in, for the type of material they are supporting, and must not be modified in any manner

that could affect the integrity or safety of these units.

Page 48: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

48

Construction Guidelines

work scope. Trenches will be tested for:

resistivity of the soil; porosity of the soil

(classification test); crumbling; distance

of spoil pile from trench; as well as any

shoring/trench box systems. All trench

boxes or shoring must be approved by

the manufacturer to be used at the depth

they are planned to be used in, for the

type of material they are supporting, and

must not be modified in any manner that

could affect the integrity or safety of

these units.

C) Trench Boxes / Shoring

Trench boxes and shoring are protective

measures designed to eliminate the

likelihood of a trench caving in while

personnel are working inside the trench.

These methods are required whenever

a trench or open excavation requires

an employee to work below 4 feet of

depth, and proper sloping cannot be

established. Trench boxes must extend a

minimum of 18 inches above the edge of

the trench, on both sides of the trench.

4.5.6 Lowering Pipe

A) Trench Bed Condition

The trench bottom shall be free from all

rocks, boulders, stones or hard particles

when particles, which may damage

the pipe walls. The trench bed should

maintain the minimum approved depth

taking into consideration the contour of

the land.

Before any pipes or specials are lowered

into the trench, they are to be inspected

again for deep cuts and scratches

described above. The fusion joints should

also have cooled sufficiently (specified

cooling time for the last joint has

elapsed) before stress is imposed on any

premade joints.

When lowering pipe into trenches, care

should be taken to avoid scoring of

the pipe by contact with the sides and

bottom of the trench. Special care is

needed when passing under/around

obstructions or other utilities.

Pipe roller supports for the first four

lengths of pipes from the pipe end to

be lowered into the trench shall be

provided. Cut section of rejected or

damaged PE pipes, planks and rope shall

be used for protecting the remaining

pipes where appropriate, but wire ropes

or chains shall not be used.

B) Trench Bed Material

Trench bottoms shall be layered with

well-graded earth that is free from

stones or hard particles larger that may

damage pipe. Under no circumstances

shall hot bending, in any form, be

allowed on site. A distance of one foot

from obstructions and other services

must be maintained for the length of

the pipeline. The pipe shall be kept as

central as possible within the trench

to enable correct side-fill compaction.

Some snaking to compensate for thermal

expansion of the pipe is acceptable.

Pipes and fittings to be embedded in

concrete shall be firmly held in position

and protected from damage during

pouring or compaction by a heavy-duty

polyethylene sheet. Should any pipe

or specials become either partially or

wholly clogged before final acceptance

of work, it shall be cleaned out or

replaced by the contractor at his own

expense.

After laying the interior of pipes or

specials shall be carefully cleaned to

Page 49: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

49

Version 1.1

remove any debris, dirt, stones or other

matter that may have entered during

installation.

Except when work is proceeding, all

open ends of pipes and specials in the

trench shall be kept closed by means of

a fine wire gauge, wooden stopper or

other approved means to prevent the

entry of dirt, soil, stones and the like, but

still allow the entry of water.

C) Inspection & Testing

Inspectors must look for deep cuts or

scratches that gouge deeper than 10%

of the pipe wall thickness. The depth

of these gouges should be measured

with approved depth gauges of suitable

accuracy supplied or approved by

OMS personnel. All damaged or flawed

sections of pipe will be cut out and

removed to the satisfaction of the Oasis

representative before jointing according

to OMS Section 4.13.

4.4.7 Welding

A) General

1.A) Contractors are responsible for

adhering to welding specifications and

guidelines set out by ASME B31.8.

1.B) Hot Work Permits must be

completed by contractors when any hot

work is performed on behalf of OMS.

B) Requirements

Joint design, materials, procedures

and practices shall be in accordance

with the latest edition of API standard

1104, “Standard for welding pipelines

and related facilities,” ASME code B3

1.8, “Gas Transmission and Distribution

Piping Systems” and all applicable DOT

regulations.

C) Method

Shielded metal-arc welding shall be used

for all manual welding. Gas metal-arc

and submerged metal-arc welding may

be used with prior approval from Oasis.

Back-up rings are prohibited.

D) Line Pipe Weld Procedures

1. Requirements

With manual, shielded metal-arc butt

welds, pipe with a wall thickness ¼ inch

and less shall have three weld beads.

Four or more beads shall be used on

pipe having a thickness greater than ¼

inch. Two welders will be used to run the

stringer bead on pipe 12 inches O.D. and

larger.

The second bead, or hot pass, shall be

applied immediately after the stringer

bead. Hot passes shall be completed

up to and including the last completed

stringer bead whenever the stringer

welding is stopped for any reason and

at the end of the day’s work. No two

succeeding passes shall start or stop at

the same point. All beads are to be made

by starting the pass near the top of the

pipe and proceeding downward on each

side of the pipe to the bottom. On any

land-laid section of line not more than

an interval of 25 joints shall separate the

hot pass welding and the filler and cap

welding processes. This interval may be

reduced by Oasis inspector if conditions

warrant. Before the end of the day, all

cap welding shall be complete.

2. Qualifications

Prior to the start of production a

detailed procedure shall be established

Page 50: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

50

Construction Guidelines

and verified to demonstrate that welds

having suitable mechanical properties

and soundness can be accomplished by

this procedure. The quality of the welds

shall be determined by testing with the

destructive tests described below.

3. Records

The details of each qualified procedure

shall be recorded and maintained on

approved forms. This record shall show

complete results of the procedure

qualification tests. Similar records shall

be made for all weld methods employed

whether in field or shop construction.

Strict compliance with these procedures

shall be required during construction

except where a change is specifically

authorized by Oasis and its qualification

recorded.

4. Procedure Specifications

Contractor is responsible for maintaining

specific welding procedures and welder

qualifications as outlined in ASME B

31.8., however, Oasis may at times accept

other standards that are equal to or more

stringent than ASME B 31.8.

5. Line Pipe Welder Qualification

Welders must pass all required

verification tests in order to weld any

OMS DOT, or other line.

6. Qualification Test

Contractor shall provide only competent,

skilled and qualified welders. Each

welder shall be required to pass

satisfactorily a test in accordance with

ASME B 31.8 for each of the procedures

to which he will be assigned, before

being allowed to weld on the line.

Oasis’ welding inspectors or designated

qualified representatives, other than an

employee of the contractor, shall witness

the tests and judge the specimens.

A report form describing each of the

procedures and the results of each test

shall be completed for each welder

and submitted to the Oasis. A welder is

disqualified at any time during the test if

his performance is judged unsatisfactory

by an Oasis inspector.

7. Equipment

Contractor shall furnish all welding

equipment, prepare all spools used

in testing and shall bear all cost in

connection with the test other than the

cost of the pipe, which will be furnished

by OMS. Test welds will be accomplished

and the weld quality tested in

accordance with ASME B 31.8, unless

otherwise specified. An Oasis approved

pulling machine for tensile tests will be

furnished by contractor with certified

gauge and calibration dates and tests.

8. Preparation For Welding Line Pipe

8.A) Welding Surfaces

Welding surfaces must be thoroughly

cleaned so as to be dry and free from

paint, oil, rust, scale, and any other

material detrimental to weld quality.

Each bead shall be ground or buffed

before any following weld passes are

made.

8.B) Alignment

8.B.1) Joints

The ends of pipe to pipe or fitting to

pipe joints shall be aligned as accurately

as practicable in consideration of

Page 51: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

51

Version 1.1

the commercial tolerances on pipe

diameters, wall thickness and out-of-

roundness. Methods of alignment to

provide the proper size and deposition of

stringer beads shall comply API standard

1104, except as noted below:

Internal line-up clamps shall be used for

all welded joints on pipe sizes 12-inch

and larger, or where specified by Oasis,

except on tie-in and other prohibitive

joints. Internal line-up clamps shall be

left in place until the stringer bead has

been 1003 completed, unless otherwise

approved by company welding inspector.

External line-up clamps shall be left in

place until a minimum of 503 of the

stringer bead, which shall be equally

spaced, has been completed.

Spacing tools shall be used in

conjunction with the line-up clamp to

assure proper joint spacing and to permit

full weld penetration.

When external clamps are used, all

tack welds shall be ground to ensure

complete stringer bead continuity.

All slag cavities, surface porosity, cold

laps, starts and stops, and high points

shall be removed by grinding.

All slag and remaining flux shall be

buffed with a power buffer between

passes.

8.B.2) Rotation Of Seams

Electric resistance welded pipe shall be

aligned so that the longitudinal seams

will be located on either side of the

line within 30 degrees of horizontal.

Successive joints of pipe shall be rotated

to the right or left not less than 20

degrees, or have the seam located on the

opposite side to avoid aligning seams on

adjacent joints. Longitudinal seams on

pipe bends, however, shall be located 90

degrees from the radius of the bend. On

bends requiring more than one joint of

pipe, longitudinal seams shall be located

180 degrees from each other.

8.C) Weather

Welding areas must be protected from

conditions that would impair the quality

of the completed weld. At times this

may require constructing a barrier wall

or enclosure (provided with adequate

ventilation) to protect the welds from

adverse weather conditions.

8.D) Materials And Equipment For Welding

8.D.1) Electrodes - Rod or Wire

Electrodes shall be in size and kind

suitable for the material being welded

and acceptable to Oasis. They shall

conform to API standard 1104.

8.D.2) Shielding Gases

Shall conform to API standard 1104.

8.D.3) Handling & Storage

Welding electrodes must be protected

from all forms of deterioration prior

to actual use. Bectrodes and fluxes,

which show any sign of damage or

deterioration, shall not be used. Any

welding materials condemned by Oasis

welding inspector shall be promptly

removed from the job site and disposed

of according to contractors waste

management procedures.

Page 52: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

52

Construction Guidelines

8.E) Equipment

8.E.1) Machines

Welding machines shall be operated at

the approximate voltage and current

ranges recommended for each type of

electrode used and shall not be operated

beyond their rated capacity. Generating

sets and/or automatic or semiautomatic

welding machines shall be maintained in

good working order and equipment that

does not meet OMS requirements must

be either repaired or replaced.

8.E.2) Leads

The ground leads of welding machines

shall be fastened securely to the pipe

metal by means of clamps or other

mechanical means (not by welding). No

arcing between the ground leads and the

pipe will be permitted and any leads with

insulation damaged to the extent that

wire is exposed shall be discarded.

8.F) Inspection & Testing of Line Pipe Welds

8.F.1) Non-Destructive Testing

All completed weld surfaces and

surrounding areas shall be cleaned and

excessive spatter must be removed prior

to welding inspection.

Radiographic Inspection

All field welds must have a radiographic

inspection completed for 10% of the

weld. A larger percentage up to and

including 10% of the field welds may be

inspected at OMS discretion. A minimum

of 10% of all field welds made within

railroad or public highway ROW, river

and stream crossing rights-of-way,

above ground piping, and at tie-ins will

be inspected for 10% of the weld. The

contractor may be required to provide

transportation to the job site and along

the ROW as well as to provide space at

the work location for equipment and

personnel.

Leads

Magnetic particle, ultrasonic, or other

non-destructive test methods may be

utilized at OMS discretion.

Defects

All welds or portions of welds disclosed

by radiographic inspection to be

defective will be repaired in accordance

with API 1104 at contractor’s expense.

Welds which are found to be defective

by OMS inspectors will be cut out and

tested in the method described in

section 8.H of this manual.

8.G) Visual Inspection

Completed welds must be visually

inspected and marked as acceptable

by OMS inspectors before the joint

coating is applied. It will not be deemed

satisfactory unless it meets the standards

of acceptability and testing requirements

as defined in API standard 1104 for

welding of pipelines.

8.H) Destructive Tests of Field Welds

Contractors will be responsible to cut

out any welds as required by Oasis

and deliver the sample for testing and

examination, and re-weld the pipe. OMS

will not require the contractor to cut out

more than one non defective weld per

welder without reimbursing contractor,

Page 53: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

53

Version 1.1

regardless of whether the weld was

cut out because of the results of non-

destructive testing methods (other

than radiographic), visual inspection or

other reasons. Coupons cut from test

welds shall be pulled for tensile strength

by an OMS approved pulling machine,

furnished by contractor. Welds may

be further tested by cutting additional

coupons for bend tests and nick-

break tests and the ductility and grain

structure of the welded metal examined.

Contractors will replace all defective

welds and one non-defective weld per

welder at their expense. A record of the

results of each test shall be jointly signed

by an Oasis representative and the

contractor.

8.I) Weld Identification

Oasis shall assign a specific number

to each contractor welder. It shall be

the duty of each welder to personally

affix such number with a permanent

waterproof felt or paint marker, adjacent

to each weld on which he works for

future identification. In the event any

welder leaves the project, his number

will be voided and not duplicated

when another welder is utilized. If

radiographic or physical tests indicate

the production of defective welds, the

welder responsible shall be disqualified

from further welding on the project.

Should two or more welders participate

in making the defective welds, the

contractor, welding foreman and OMS

inspector shall determine which welder

was responsible for the defective work.

8.J) Replacement of Test Welds or Rejected Welds

When welding the line together at places

where welds have been removed, if

possible, one weld shall be made after

moving the line back into position;

otherwise two welds shall be made by

installing a spool with the minimum

length of 1¼ times the pipe diameter.

8.K) Repair of Weld Defects

Weld defects, other than cracks, may be

repaired if the weld was not previously

repaired if authorized by an OMS

inspector. Such defects shall be removed

by grinding to clean, sound metal before

re-welding and shown by radiographic

inspection to be free of defects before

acceptance. Should laminations, split

end or longitudinal seam defects be

discovered in the pipe, the full joint

containing the defect shall be removed

from the line.

8.L) Standard of Acceptability

Minimum acceptable standards for

penetration, fusion, burned-through

areas, slag inclusion, gas pockets,

discontinuities and undercutting shall be

in accordance with API standard 1104,

and ASME 831.8 code.

8.M) Arc Burns

Contractor shall prevent arc burns. Arc

burns, where they occur, shall be cut out

at contractor’s expense.

8.N) Preheating & Stress Relieving

8.M.1) General Practices

The welding procedure shall specify the

preheating and stress relieving practices

to be followed when materials or

weather conditions make either or both

necessary.

Page 54: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

54

Construction Guidelines

8.O) Preheating

When the weld procedures and/or

carbon content or the carbon equivalent

of the pipe requires preheating, or the

ambient temperature is 40°F or less,

the weld zone shall be preheated to an

appropriate uniform temperature. The

hot pass shall be made no longer than

five minutes after the stringer bead and

before the weld joint is cooled to below

200°F. The preheating temperature shall

be accurately tested to assure that the

required temperature is obtained prior

to and maintained during the welding

operation. OMS will pay for preheating

required during cold weather. Preheating

required by weld procedures will not be

paid by Oasis.

8.P) Stress Relief

Stress relieving may be designated

by Oasis and shall be accomplished

in accordance with the instructions

in ASME b 31.8 and the Oasis welding

inspector. Butt welds on weld-end valves

shall not be stress relieved and in no

case shall cold expanded pipe be stress

relieved. Oasis will pay for stress relief.

4.5.8 Boring

A) Equipment Requirements

Directional boring equipment must

have a rig of sufficient capacity to

perform the bore and pull back the

pipe, a boring fluid mixing and delivery

system of sufficient capacity to

successfully complete the crossing, a

guidance system to accurately guide

boring operations and trained and

competent personnel to operate the

system. All equipment shall be in good,

safe operating condition with sufficient

supplies, materials and spare parts on

Diagram 4.5A

Page 55: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

55

Version 1.1

hand to maintain the system in good

working order for the duration of this

project.

B) Boring System

1. Boring Machine

The directional boring machine shall

consist of a hydraulically powered

system to rotate, push and pull hollow

drill pipe into the ground at a variable

angle while delivering a pressurized

fluid mixture to a guidable drill (bore)

head. The machine shall be anchored

to the ground to withstand the pulling,

pushing and rotating pressure required

to complete the crossing. The hydraulic

power system shall be self-contained

with sufficient pressure and volume

to power boring operations. Hydraulic

system shall be free of leaks. Rigs shall

have a system to monitor and record

maximum pullback pressure during

pullback operations. Boring rigs must be

grounded during boring and pullback

operations. Sufficient spares shall be kept

on hand for any breakdowns, which can

be reasonably anticipated.

1.A) Bore Head

The bore head shall be guided by

changing it’s rotation and shall provide

the necessary cutting surfaces and

boring fluid jets.

Mud motors shall be of adequate power

to turn the required boring tools.

It is required that the boring profile is

supplied electronically, with operator’s

signature and supplied upon invoice.

1.B) Guidance System

The Guidance System shall be of

a proven type and shall be set up

and operated by personnel trained

and experienced with this system.

The operator shall be aware of any

magnetic anomalies and shall consider

such influences in the operation of the

guidance system if using a magnetic

system.

2. Boring Fluid (Mud) System

2.A) Mixing System

A self-contained, closed, boring fluid

mixing system shall be of sufficient

size to mix and deliver boring fluid

composed of Bentonite clay, potable

water and appropriate additives. Mixing

system shall be able to molecularly

shear individual Bentonite particles from

the dry powder to avoid clumping and

ensure thorough mixing. Mixing system

shall continually agitate the boring fluid

during boring operations.

2.B) Boring Fluids

Boring rigs must be grounded during boring and pullback

operations.

Page 56: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

56

Construction Guidelines

Drilling fluid shall be composed of clean

water and an appropriate additive.

Water shall be from a clean source with

a pH of 8.5-10. Water of a lower pH or

with excessive calcium shall be treated

with the appropriate amount of sodium

carbonate or equal. Water and additives

shall be mixed thoroughly and be absent

of any clumps or clods. No hazardous

additives may be used. Boring fluid shall

be maintained at a viscosity sufficient

to suspend cuttings and maintain the

integrity of bore wall.

3. Delivery System

The mud pumping system shall have

a gallon per minute (GPM) capacity

equal to the hole size and be capable of

delivering the boring fluid at a constant

minimum pressure of the same. The

delivery system shall have filters in line to

prevent solids from being pumped into

the drill pipe. Connections between the

pump and drill pipe shall be relatively

leak-free. If fluid is anticipated to leave

the ROW, it is recommended that

contractors utilize containment methods.

Used boring fluid and boring fluid

spilled during boring operations shall

be contained and properly disposed of.

Berms constructed a minimum of 1 foot

high, shall be maintained around boring

equipment, boring fluid mixing system,

entry and exit pits, and boring fluid

recycling system (if used) to prevent

spills into the surrounding environment.

Pumps and or vacuum truck(s) of

sufficient size shall be in place to convey

excess boring fluid from containment

areas to storage facilities.

4. Pipe Rollers

Pipe rollers, if required, shall be of

sufficient size to fully support the weight

Diagram 4.5B

Page 57: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

57

Version 1.1

of the pipe while being hydro-tested and

during pullback operations. Sufficient

numbers of rollers shall used to prevent

excess sagging of pipe.

C) Other Equipment

1. Pipe Rammers/Pullers

Hydraulic or pneumatic pipe rammers

or pullers may only be used if necessary

and with the authorization of Engineer.

2. Other Equipment

Other devices or utility placement

systems for providing horizontal thrust

other than those previously defined in

the preceding sections may only be used

if approved by OMS personnel.

D) Boring Operations

1. General

OMS engineering group and inspectors

must be involved in pre-job meeting

prior to boring operations starting. The

directional bore shall not begin until an

OMS representative is present at the job

site and agrees that proper preparations

for the operation have been made. The

engineer’s approval for beginning the

installation shall in no way relieve the

contractor of the ultimate responsibility

for satisfactory completion of the work

as authorized under the contract.

It is the responsibility of the construction

department to provide inspectors

without causing undue hardship by

reason of delay to the contractor.

All personnel shall be fully trained in

their respective duties as part of the

directional boring crew as well as in all

safety considerations. Training shall be

provided specific to the project if any

potential hazards may be encountered

which has not already been included in

Diagram 4.5C

Page 58: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

58

Construction Guidelines

personnel’s training.

2. Boring Procedure

2.A) Site Preparation

Prior to any alterations to the worksite,

contractor shall photograph or record a

video of the entire work area, including

entry and exit points. One copy of which

shall be given to engineer and one copy

to remain with contractor for a period of

one year following the completion of the

project.

Worksite as indicated on drawings

within the ROW shall be graded or filled

to provide a level working area. No

alterations beyond what is required for

operations are to be made. Contractors

shall confine all activities to designated

work areas.

2.B) Bore Path Survey

Drill paths will be accurately surveyed

with entry and exit stakes placed in the

appropriate locations within the areas

indicated on drawings. If contractors are

using a magnetic guidance system, the

drill path will be surveyed for any surface

geomagnetic variations or anomalies.

2.C) Environmental Protection

Contractor shall place silt fence

between all boring operations and any

drainage, wetland, waterway or other

area designated for such protection as

outlined in contract documents, state,

federal or local regulations. Additional

environmental protection necessary to

contain any hydraulic or boring fluid

spills shall be put in place, including

berms, liners, turbidity curtains and other

measures. Contractors will adhere to all

applicable environmental regulations.

Fuel or oil may not be stored in bulk

containers within 200 feet of any body

of water or wetland.

OMS personnel must be present prior to

releasing any wastewater on any OMS

ROW.

E) Utility Locates

Contractors are responsible to notify

companies with underground utilities

in the work area via the state or local

One Call to obtain utility locates

(811). Once utilities have been located

contractor shall physically identify

the exact location of the utilities by

vacuum or hand excavation, when

possible and necessary, in order to

determine the actual location and path

of any underground utilities which

might be within 20 feet of the bore

path. Contractor shall not commence

boring operations until the location of

all underground utilities within the work

area have been verified.

4.6 Tie-Ins

4.6.1 General

The intent of this section is to provide

guidance for construction operations

regarding the connecting of two or more

pipelines with the intent of optimizing

pipeline infrastructure.

A) Water Considerations

Tie-ins or tested sections containing fill

water for sections to be subsequently

tested shall not be made in cases where

excessive air, entrapped as a result of the

tie-ins, will be injected into the section to

be tested.

Page 59: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

59

Version 1.1

*Note that in many cases the loss of

water at tie-ins will be considerable.

In such cases this water shall not be

allowed to flow into running streams,

rivers or wells that are used for domestic

water supplies.

B) Backfilling

[ref. Section 4.13] at the tie-in sites shall

be carried out in accordance with the

General Construction Specifications.

C). Cold Cutting

Cold cutting must to be completed with

either non-sparking equipment on live

tie-ins or by means of a guillotine system.

Safe grounding measures are to be used

in order to discharge static electricity

build up must be utilized.

D) Live Tie-In

1. Hot Tap

1.A) General

Hot taps performed on a pipeline under

pressure will only be performed by a

crew qualified to perform this type of

operation. Contractors must supply

sufficient documentation to OMS

indicating qualification of individuals

performing hot tap procedures.

1.B) Requirements

Hot Tap design, materials, procedures

and practices shall be in accordance

with the latest edition of API Standard

2201, “Procedures for Welding or Hot

Tapping on Equipment Containing

Flammable Liquids”; API Standard 1104,

“Standard for Welding Pipelines and

Related Facilities”; API Standard 1107,

“Recommended Pipeline Maintenance

Welding Practices”; ASME B31.8,

“Gas Transmission and Distribution

Piping Systems”; and all applicable

DOT Regulations, except as otherwise

specified herein.

1.C) Welding Personnel

Welders must be qualified in accordance

with ASME B 31.8 and API 1104. They

shall be thoroughly familiar with welding

equipment and procedures to be used.

For additional information please

reference section 4.4.7(D) of this manual.

1.D) Welding Design

Only full encirclement type saddles are

to be used for the branch connection.

Fillet welding procedures for the full

encirclement saddle shall be specified in

within release alignment sheet.

Full penetration welding on branch

connections and longitudinal butt-

It is essential that all surfaces remain clean before, during and after the

welding process.

Page 60: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

60

Construction Guidelines

welding on reinforcing saddles shall

follow standard welding procedures

outlined in API Standard 1104 and 1107.

2.) Fillet Welding Procedure

2.A) Process

Welding shall be done by the shielded

metal arc welding process.

2.B) Parent Metals

Metals welded according to this standard

shall be Grade A through X-70.

2.C) Diameter & Wall Thickness

This procedure shall apply to material

having any diameter or wall thickness.

2.D) Joint Design

2.D.1) Branch Connections

Branch ends must be beveled to an angle

of 45°, plus 5°, minus 0°, with a root face

of 1/16” ± 1/32”. The root opening shall be

1/16” ± 1/32”

2.D.2) Sleeves

Side seams shall be beveled to an angle

of 30°, plus 5°, minus 0°, with a root face

of 1/16”±1/32”. The end preparation shall

be 90° ± 5° with as little space between

the sleeve and the pipe as possible.

2.D.3) Filler Material

The filler material shall conform to A.W.S.

Classification A5.5, E-8018-C3, Group

F-4, weld analysis A-10.

2.E) Electrical Characteristics

The welding current shall be D.C. reverse

polarity (electrode positive).

2.F) Direction of Welding

Welding shall proceed upward from

bottom center or any point of the side of

the pipe to top center.

2.G) Speed of Travel

The speed of travel shall be within the

range of 4 to 13 inches per minute,

inclusive.

2.H) Number of Welders

One welder may be used to run the

stringer bead (root bead) when the

nominal branch diameter for branches

or the nominal run diameter for sleeves

is less than 16 inches. When the nominal

branch diameter is 16 inches or greater,

two welders will be required to run the

stringer bead. Oasis reserves the right

to require additional welders for the

stringer bead without altering the unit

price, if, in Oasis’S opinion, danger of

stringer bead cracking exists or slow

progress is experienced. One welder may

be used to run all passes subsequent to

the stringer bead on all sizes of pipe.

2.I) Time Lapse Between Passes

The second pass (“Hot Pass”) shall follow

the stringer bead (root bead) within

five minutes, except when unavoidable

circumstances prevail which make this

requirement impractical. All second

passes shall be completed before the

end of the day. The entire weld should be

finished before the end of the day.

2.J) Line-Up Clamp

Page 61: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

61

Version 1.1

Line-up clamp must properly align the

pieces of pipe intended to be welded.

2.J.1) Branch Connections

Spacing tools and manual holding

during tacking off is acceptable if

correct stringer bead space and proper

alignment is maintained; if not, then

mechanical holding devices are required.

2.J.2) Sleeves and Patches

Chains, clamps, hydraulic jacks or other

similar mechanical holding devices shall

be used to hold the sleeve or patch in

intimate contact with the pipe before

welding starts.

2.K) Removal of Line-Up Clamp

When repairing leaks, clamping devices

shall remain in place until all welding

is completed. On other fillet welds, the

clamping devices may be removed

whenever tacking adequate to maintain

spacing and alignment has been

completed.

2.L) Cleaning

It is essential that all surfaces remain

clean before, during and after the

welding process. All dirt and foreign

matter must be removed from the

beveled surface before welding begins;

the bevel surface includes the area on

the inside of the pipe in the immediate

proximity of the pipe end. Slag shall

be removed from the bead surface

before the next bead is applied. Power

tools may be used. The finished weld

and immediately adjacent pipe must

be cleaned of all flux, smoke and weld

splatter.

2.M) Preheat

Preheat shall be required when moisture

is present on the parent metal; it

shall be driven off by preheating to a

temperature at which it will not reform

during the welding operation.

3. Hot Tap Operation

Hot Tapping operations are to be carried

out by a qualified technician who is

thoroughly familiar with all applicable

safety procedures and industry

standards.

4. Testing

1. The metal thickness of the

existing header is to be measured

radio graphically, and absence of

imperfections is to be verified prior to

beginning any part of the welding or hot

tapping procedure.

Pits for boring shall be excavated no more than 48 hours in advance

of boring operations and backfilled within 48 hours of boring operation

completion.

Page 62: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

62

Construction Guidelines

2. All welds are to be tested in

accordance to company 1003 spec and

up to judgment of welding inspector.

3. After welding of the full encirclement

saddle is complete, but before hot

tapping begins, the branch connection is

to be completed in the manner in which

it will be operating, and a hydrostatic test

performed.

E) Squeezing

Squeeze tools will only be used in

emergency situations, and not ordinarily

in day-to-day operations. Isolation and

drain down areas (prior to hot-tap,

etc.) will be implemented in normal

conditions.

Squeeze tool availability must be verified

prior to operations commencing when

the likelihood or the risk of a line strike is

thought to be high.

4.7 Crossings

4.7.1 General

This section provides guidance on

the processes implemented when

crossing OMS, or foreign utilities during

construction processes.

A) Approvals

OMS will obtain easement permits

for highway, line, or railway crossings

prior to any foreign facility crossings.

It is expected that contractor will not

perform excavation on the highway or

railroad ROW without direct written

approval from OMS. Contractors are

responsible to review all permits and be

knowledgeable about the provisions and

restrictions of crossing permits and shall

conduct the work in strict accordance

with such requirements and restrictions,

including notification of highway and

railway representatives. Contractors

may not cut into any highway or road

surface of concrete, asphalt, gravel, oil

or any binding material without written

permission from the authority under

whose jurisdiction the permit is issued.

B) Line Crossings

Oasis Petroleum’s land department

shall obtain approval from the owners

of foreign pipelines and stakeholders

for the installation of test leads on the

foreign line (if necessary). Contractor

shall, upon receipt of owner’s approval,

install test leads on the foreign line

and repair the coating to the owner’s

satisfaction. Test leads may only be

installed by individuals with adequate

training who possess cathodic protection

certifications.

C) Road crossings

State & County Road Crossing County

regulations must be referenced prior to

any civil construction or deconstruction

operations commence.

D) Water Crossings

Contractors shall construct pipelines

across drainage ditches, bayous, creeks,

streams, canals, rivers and adjacent

lowlands and flood plains. No extra

payment will be made to contractors by

OMS for such ditches, creeks and rivers.

Such crossings are to be considered a

part of the project and are expected to

be a part of the contractors bid.

Page 63: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

63

Version 1.1

1. Weights & Anchors

Sections of pipeline intended to

be laid across lakes; washes; rivers

and waterways must be weighted

or anchored as specified by Oasis.

Contractors must furnish all materials

and equipment including weights and

anchors. Contractors are responsible

for transporting stringing and installing

weights and anchors at locations and

in the manner designated by OMS

personnel.

Several thicknesses of rock shield shall

be placed between the pipe and each

weight. Where weights are installed on

long sections of pipe, care shall be taken

in handling to prevent buckling of the

pipe.

Pipeline anchors must be installed

in accordance with manufacturer’s

specifications. During installation, every

precaution shall be taken to prevent

damage to the pipe and coating.

E) Boring Crossings

When paved roads are crossed, boring

shall be done from pits located a

minimum of 30 feet from the edge of

pavement on fully access-controlled

highways and at a distance of 10 feet

plus the depth of pit without shoring

on conventional highways. If shoring

is used, the pits shall be located at a

minimum of 10 feet from the pavement

on conventional highways. Such shoring

shall be installed immediately after

excavation of the pit and it shall be

constructed and maintained so that it

will safely support all vertical and lateral

loads that may be imposed upon it

during the boring operation.

Pits for boring shall be excavated no

more than 48 hours in advance of boring

operations and backfilled within 48

hours of boring operation completion.

F) Section Lines

Facilities installed near section lines to

be a minimum of 2 feet deeper than

depth of trench. Section lines have the

potential to become roads in the future,

and this should be considered when

crossing section lines.

4.8 Civil Construction

4.8.1 General

This section overviews construction in

relationship to roadways, railways, and

other public or private use structures,

generally operated alongside the

transmission of petroleum, water, or

other assets.

A) Cement

All concrete installations shall be

constructed as shown on the drawings

and details. It is imperative that the

concrete mixture meets all requirements

in order to ensure the integrity of the

system

All cement shall conform to the latest

edition of ASTM C-150 and all concrete

shall conform to the latest edition of

ASTM C-94.

All concrete, concrete placement,

curing, deformed reinforcement bars,

testing and other applicable concrete

requirements shall be in accordance with

applicable standards regarding concrete

construction.

Page 64: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

64

Construction Guidelines

B) Structural Steel

The fabrication of structural steel shapes,

connection plates, base plates and

bolt holes shall conform to the AISC

“Specification for the Design, Fabrication,

and Erection of Structural Steel for

Buildings” in the latest edition of the

Manual of Steel Construction.

1. Handling

All structural materials shall be handled

in a manner to prevent material damage.

The material shall be supported on skids

that are properly spaced to prevent

permanent deflection in the structural

member. Skids shall be of adequate size

to keep the material above ground, clean

and properly drained.

2. Workmanship

Workmanship shall conform to AISC

specifications. Bolt holes to secure other

materials shall be as shown on drawings.

3. Erection

Erection shall be in accordance with

AISC specifications, and shall include the

setting of all columns; beams; trusses;

grating; floor plates; handrails; the

installation of cranes; and the erection

of all other structural steel to true line,

grade and flushness.

4. Field Connections

Field connections shall be bolted and

bolts drawn up tight and set, so that nuts

will not become loose. All bolt-ups need

to adhere to torque specs with markings

to identify that the last bolt secured.

Drifting, other than light drifting

necessary to draw the holes together,

will not be permitted.

Welding shall be done in accordance

with the Code for Fusion Welding and

Gas Cutting in Building Construction

Code I Part A, Structural Steel, of the

American Welding Society.

5. Cutting & Fitting

Cutting of flanges, webs or angles will

not be permitted without prior OMS

approval.

6. Grouting

All bearing plates, loose lintels, beams

and columns shall be set to proper grade

and level before grouting.

7. Cleaning & Painting

All structural steel shall be cleaned

and painted in accordance with colors

outlined in project plan.

C) Roads / Walkways

Normal location walkways need to be

installed to prevent slip, trip and fall

hazards due to inadequate walking

surfaces. Material such as scoria/gravel

should be used.

D) Location / Well Pad

All locations and well pads should have

a engineered drawings representing all

underground lines; utilities lines; well

names; roads; crossings; foreign lines

leaving location; old reserve pits located;

and equipment (electrical & mechanical)

logged to map.

Page 65: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

65

Version 1.1

4.9 Facility Construction

4.9.1 General

Facility construction covers many

important aspects of OMS operations.

The quality of the equipment provided,

as well as ensuring the proper application

and planning is imperative to the safe

and efficient operation of OMS pipelines.

A) Pumps

1. Installation

Depending on the elevation and

number of wells on site, pumps are

sized accordingly by OMS engineering

personnel.

Hand sketched drawing are sent from the

field to welding shops.

CAD drawings are then produced with a

Make to Order (MTO) for project scope.

Parts are ordered and documented as

a part of the project file. Fabricated

packages are to be delivered to the

field and recorded using OMS required

Material Transfer Forms. Electronic

versions must be given to OMS personnel

as well as hard copies maintained in the

field. Fabrication shops must maintain

X-ray maps, Material Transfer Forms and

welder information.

Pumps will ordinarily be constructed

prior to being delivered to the field. All

drawings and plans are required to be

preapproved by OMS engineers.

B) Houses

In most applications, houses will be

designed and built prior to being

installed on locations.

1. Installation

Houses are to be set, leveled and sealed

at the time of pump set. Considerations

must be taken to identify prevailing wind

direction in order to protect doors from

being damaged.

2. Insulation

Freshwater connections are to be heated

and insulated to prevent freezing.

3. Heat Tape

Any pipe that is exposed to the elements

above ground require heat tape and

insulation to prevent freezing.

C) Risers

Risers are to be constructed by certified

API 1104 welders. They will have both a

purge as well as a non-purge procedure.

We will use 316 stainless steel for all

saltwater above ground pipe. The

riser should be coated with a VisoTaq

Coating.

D) Instrumentation and Electrical (I&E)

1. Automation

Transfer pumps are controlled by

two controls, one is located within

production tanks and monitors high

and low levels, the other is the pressure

transducer controlling the pump per its

engineered MAOP.

2. Measurement

Measurement meters must be calibrated

frequently to ensure accuracy.

How frequently this occurs is to be

designated by OMS Engineering. All

Page 66: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

66

Construction Guidelines

calibrations must be accompanied with

documentation.

Leak tests should be performed

quarterly.

4.10 Coating

4.10.1 General

Protective coatings are imperative for the

integrity of all pipelines. Dings, scrapes

or nicks can cause anomalies that last the

lifetime of the line, and pose serious risk

to all stakeholders near pipelines as well

as significant risk to the environment.

A) Painting

1. Surface Preparation

Surface shall be degreased prior to

sandblasting. Organic solvents, alkaline

solutions, steam, hot water with

detergents, or other systems that will

completely remove dirt, oil, grease, etc.,

may be used.

1.A) Edge Preparation

All edges shall be ground to a minimum

of a 1/8 inch radius. This includes clips,

baffles, nozzle connections, etc.

1.B) Surface Abrasion

The immersion service surface shall

be blasted to a NACE (National

Association of Corrosion Engineers)

No. 1 or SSPC (Society for Protective

Coatings)-sp5-63 white metal blast

cleaned surface. An anchor pattern or

“tooth” in the metal shall be established

according to the coating manufacturer’s

recommendations. The anchor pattern

shall be sharp and no evidence of a

polished surface is allowed.

1.C) Sandblasting

The external surface to be painted shall

be blasted to a NACE no. 3 or SSPC sp-

6-63 commercial blast cleaned surface.

The surface profile should be 1.5 to 2.0

mils.

Blasting shall be done with washed

sharp silica sand of 16/35-grade mesh

or finer. This sand shall be clean, dry

and free of clay particles and other

extraneous matter or, the grit used shall

be sharp silica sand, steel slag grit similar

or equal to black beauty bb 16 or any

other abrasive that has a sharp hard

cutting surface, properly graded, non-

contaminating, dry and best quality.

Steel surfaces shall not be blasted when

the surface temperature is less than 5°F

above the dew point, relative humidity is

greater that 80%, or there is a possibility

that the blasted surface will be subject

to wetting before the first coat of primer

can be applied. No painting shall take

place when the ambient temperature is

below 50°F.

1.D) Surface Cleaning after Sandblasting

Traces of blasting abrasive and dust

must be removed with a vacuum

or by brushing. Care must be taken

to avoid contaminating the surface

with fingerprints or from foreign and

potentially detrimental material from the

workers clothes or shoes.

1.E) Immediate Priming

Freshly blasted surfaces are subject to

immediate corrosion, particularly in areas

of high humidity. After surfaces are blast

cleaned then they can be prime-coated

before visible or detrimental re-rusting

Page 67: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

67

Version 1.1

occurs. Blasted surfaces shall be prime-

coated or plastic-coated no later than at

the end of the same workday.

A 12-inch wide strip of uncoated, blasted

surface shall be left between primed

surfaces and those non-blasted surfaces

to prevent damage to the newly dried

coating when additional blasting is

done. When blast cleaning is resumed,

the 12-inch strip of previously blasted

surface shall require only a light brush

blast to remove any rust that might

remain. Cleaning shall be accomplished

by holding the cleaning nozzle in a

direction away from the coated surface

and personnel.

1.D) Compressed Air Quality

The compressed air used for blasting

shall be free of detrimental amounts of

water and oil. Adequate traps, filters

and separators shall be provided at the

compressor and must be checked daily.

1.E) Metallic Surfaces

All non-metallic surfaces shall be clean,

dry and free from scale, oil and dirt.

Contractors shall protect all gasket

surfaces, valve stems, name plates,

pressure gauges, instrument cases,

gauge glasses and all previously

installed and coated equipment

including galvanizing. If the coating on

any previously installed equipment is

damaged, the damage will be repaired

at the contractor’s expense. If any

previously installed equipment is

damaged during coating, the equipment

will be replaced or repaired by the

contractor. All tape protection shall be

removed after coating.

B) External Painting

All piping, equipment, structures

and metal portions of buildings, not

galvanized or of aluminum construction,

shall be painted to protect against

corrosion and to provide a satisfactory

appearance. Equipment and piping to

be insulated will be protected with one

primer coat only. A minimum of one

primer coat and one finish coat shall

be applied to un-insulated equipment.

Floors may be colored, coated or hard-

surfaced as specified.

Paint shall be spray applied in

accordance with the manufacturer’s

recommendations. Any or additions by

the company will take precedent over

the manufacturer’s recommendations.

Only competent personnel applying

coating by proper techniques are

authorized to perform this task. After

coatings have been applied facilities shall

not contain sags, runs, wrinkles, spots,

blisters or other application flaws which

would cause premature coating failure.

The finished external coating shall be

free of holidays when checked with a

67.5 volt Holiday Detector.

1. Coating Equipment Inspection

All spray equipment shall be inspected

and approved by OMS personnel before

any application is begun.

2. Moisture Trap

Moisture traps are to be used by placing

them in line from air supply to pressure

pot and spray gun. This trap shall be

opened slightly to provide a continuous

bleed.

Page 68: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

68

Construction Guidelines

3. Use of Regulators/Gauges

Regulators and gauges shall be provided

for air to both pressure pot and spray

gun.

4. Application Distance-Primer

Primer shall not be applied closer than

12-inches to a non-blasted area. Any

subsequent blasting operation shall not

result in sand particles being embedded

in the paint film.

5. Spray Guns

Spray guns are to be held perpendicular

to the surface being painted, and

handled and adjusted in such a manner

that dry overspray is kept to a minimum.

6. Sequence

The sequence to be followed in painting

shall be such that a minimum of damage

to finish coatings will result.

7. Confined Space Ventilation

When paint is being applied to the

interior of tanks or confined areas,

sufficient blowers and fans shall be

installed to provide adequate ventilation.

8. Priming

The prime coat shall be a high build type

with a minimum dry film thickness of five

(5.0) mils to six (6.0) mils, depending on

the brand used.

9. Brand Use

All materials required for external

painting and finishing shall be of the

brand(s) manufactured by: Polyguard or

a similar vendor provided the quality is

not reduced.

Ground level protection should be

ViscoTaq Coat Wrap ST or equivalent.

Changes in brand/type may be

approved, but only by OMS written

authorization.

Coating materials shall be stored in a

cool dry place free from the potential

of spark or flame. Paint materials

susceptible to freezing are not to be

stored where the temperature will drop

below 32°F. All such materials shall be

used or applied in strict accordance with

manufacturer’s directions.

10. External Applications

Application of the external coatings is

allowed only when the air, surface and

product temperatures are above 50°F

and at least 5°F above the dew point.

One finish coat of not less than two (2.0)

to two point five (2.5) dry mils must be

applied.

11. Additional Coats

Surfaces are not to be recoated until the

preceding coat has properly dried or

cured. The surface may be considered

ready for recoating when the next coat

can be applied without the development

of paint film irregularities, such as lifting

or loss of adhesion of the undercoat.

However, the minimum or maximum

drying or curing time specified by

the paint manufacturer shall be the

acceptable recoat period. Paint shall not

be force dried under conditions that will

cause wrinkling, blistering, formation of

pores, or which will be detrimental to its

condition or appearance.

Page 69: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

69

Version 1.1

12. Paint Thinning

Only best quality products will be used

and paints shall be thinned only as

recommended by the manufacturer.

Resin systems or two component

systems will be used within the pot-life

time specified and in no case shall any

thinning be used.

13. Curing

Each coat will be thoroughly dried or

cured before the next coat is applied.

14. Paint Damage

Where paint has been damaged in

handling, all damaged and loosely

adhering paint shall be removed and the

surface thoroughly cleaned. Edges of the

breaks shall be feathered and designated

prime and finish coats applied.

C) Jeep Sticks

If a nick (or holiday) is found in a coated

steel pipe, a hot melt patch is needed

to repair it. Recommended use of 3M

Scotchkote Hot Melt Patch Compound

226P.

Holiday detection equipment must be

used to detect holidays in the coating of

the pipe.

F) Pipe Wrap / Tape

For rocky soil a protective coating wrap

such as Tuff-N-Nuff Rockshield should

be used to keep large jagged edges from

affecting the coating of the pipe. (See

Appendices)

G) Insulation

Pipe should be adequately insulated if

placed above 4 feet in depth. The quality

of the insulation such be such that the

R-Factor can protect against anticipated

temperatures.

4.11 Tracer Tape & Wire

4.11.1 General

It is imperative that all utilities installed

by Oasis Midstream Services have the

ability to be located. This includes

correct installation, and integrity

management of locating devices.

A) Depth

All tape must be installed above the

pipe and a minimum of 2 feet below the

surface of the top of the existing ground

surface and be made of magnetic

material. When soil is crowned, tracer

tape may need to be installed at an even

greater depth. Consult OMS personnel if

adequate depth is in question.

B) Wire Location

All tracer wire must be installed

according to section DOT 192.321 or 195.

Test leads should be installed ideally

every ¼ mile to ensure adequate

coverage.

Test leads shall be color coded with

a proper sticker to indicate company

name, product in pipe and emergency

contact, preferably a tri-sided

(triangular) post.

Page 70: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

70

Construction Guidelines

C) Wire Protection

Wires must be protected from corrosion

as well as from abnormal protrusions

underground. For this reason anode

protection is required. Tracer wire

should be constructed to the following

specifications:

Composed of a dead soft annealed

copper conductor utilizing UNS C10200

grade copper;

Insulated in 45 MIL High Density,

High Molecular Weight Polyethylene

(HMWPE);

Shall be UL listed, rated for direct burial,

moisture, gasoline and oil resistant, and

suitable for operations at 600 volts.

4.12 Backfill

4.12.1 Material

The quality and type of material used

for backfilling after construction is

imperative to the life of the pipeline.

Using material of poor quality, can either

damage the pipe or require contractors

to return to the ROW to re-compact

soil. Backfill 12 inches above top of pipe

shall be free from rocks, frozen clods

or other hard objects. Contractors

are required to bear the cost of any

special treatment necessary to eliminate

such hard objects. Where required by

company or by ROW agreement, topsoil

shall be segregated from other spoil

and placed at the top of the fill to the

specified depth. In cultivated areas, no

rock shall be placed in the top of the fill

above the depth of normal tilling. Excess

rock must be disposed of by contractor

to the satisfaction of OMS personnel.

Contractors must also comply with

requirements concerning the order, in

which respective materials are backfilled,

contained in ROW restrictions.

4.12.2 Backfill Method

A) Backfill Material

Immediately after the pipe has been

lowered, it shall be shaded by filling the

ditch over the pipe with backfill material.

Backfill material shall be placed around

the pipeline in a manner to ensure

that no significant rocks, vegetation

or foreign objects strike or contact

the pipeline in a way that could cause

damage. Special considerations for the

initial 2 feet of backfill [ref. sec. 4.12.1]

B) General

Backfilling methodology should be done

in a way to maintain the integrity of the

ROW as well as a minimum disturbance

area. Backfilling shall be done in such a

manner as to ensure all area below and

around the pipe is surrounded by fill dirt.

Contractors are to use any acceptable

method approved by OMS personnel

in order to ensure compaction of the

backfill while not applying so much

pressure that the pipe may lose its

shape. Backfill packing shall not be done

through rocky land where the exterior

pipe or coating might be damaged,

or through sections where drain tile is

encountered and might be damaged.

All pipe must be buried a minimum of 6’

Deep, unless otherwise required by OMS

personnel or governing authorities

C) Padding

Where padding of the pipe is required

materials must be deposited in ditch

simultaneously on both sides of the pipe.

Page 71: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

71

Version 1.1

In the event the native ditch material

is considered by the company to be

unsuitable for backfill material, the

contractor shall purchase, haul, place

and choose the highest quality backfill

material possible in accordance with

these instructions. Contractors may use

a padding machine to achieve padding

requirements without hauling select back

fill to the worksite. If a shaker bucket is

used in place of a padding machine or

hauling in pad material, padding costs

are considered to be a part of the bid

price of the project.

D) Padding Density

Padding shall extend across the full

width of the ditch and be thoroughly

compacted until a minimum of 12 inches

of padding is in place. If more than one

pipeline is in the ditch, the select backfill

material shall be placed between the

lines and shall be brought to a level of

12 inches above the highest line. OMS

reserves the option to require additional

padding in extremely rocky areas.

The remaining backfill shall be placed in

the pipeline ditch and spread on both

sides of the pipeline ditch. ROW that

has been disturbed during construction

shall be graded and tilled in a manner

satisfactory to OMS and the landowner

and seeded. Backfilling across drainage

ditches, irrigation ditches, terraces, levee

districts, railroads, public highways,

private drives, trails, roads, or streams

shall be compacted to at least 953

standard proctor density throughout in

a manner satisfactory to company and

to any private or governmental authority

having jurisdiction.

4.12.3 Final Compaction

Compaction may be accomplished by

tamping or other method approved

by OMS. “Walking in” with a track or

wheeled vehicle is normally acceptable

on wide ditches, subject to prior OMS

approval. There shall be a minimum of

30 inches of cover material over the pipe

prior to compaction by vehicles. Wheels

and tracks must be narrower than the

ditch line for effective compaction.

Where non-ferrous or large diameter

thin wall pipe is involved, a limit may

be placed by OMS on the maximum

weight of the vehicle, or there may be a

requirement that the line be pressurized

during the operation. Compaction to a

density that will prevent excess settling

of the ditch backfill material is required.

A) Moisture

At road crossings where selected

backfill material is required, it shall

have the proper moisture content to

reach necessary 80% compaction and

the moisture content shall be uniform

throughout each layer.

4.12.4 Restoration of Construction Areas

Roads, slopes, creek banks, levees and

other places where earth has been

moved to facilitate the operation of

contractor equipment, the contractor

is required to restore these areas to

their original profile and condition,

to the satisfaction of OMS and/or the

landowner.

4.12.5 Overburden / Crown

Backfill over the pipe ditch shall be

crowned to a height of not less than 8

inches (8”) and no more than 12 inches

Page 72: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

72

Construction Guidelines

(12”) above the adjacent ground surface,

except through irrigated farm land

where the backfill will be compacted

to the satisfaction of company and the

landowner. Through rocky lands where

livestock is confined, 20-foot wide gaps

shall be provided across the backfilled

line at 100-yard intervals to provide

passageway for livestock.

Gaps shall be level with surrounding

ground and surfaced with backfill

material free from large and sharp rocks,

all to the satisfaction of OMS personnel

and/or the landowner.

4.12.6 Irrigation & Drainage

When backfilling across irrigated fields

contractors must provide furrows across

pipeline ROW as required by OMS

personnel and/or landowner, in order

to direct the flow of water into normal

irrigation courses.Finished backfills must

be sufficiently level to permit normal

irrigation, even if harrowing, disking or

hand raking is required. When borrowed

dirt is necessary to crown the backfill

to the required height, Oasis and those

having jurisdiction of the property must

approve the manner and method of

securing dirt.

All terraces, levees and sides of drainage

or irrigation canals, and all roads

and highways that are cut shall be

backfilled in one foot lifts and each layer

thoroughly tamped by hand or machine

to provide a good bond between the

undisturbed sides of the ditch and the

new backfill material.

When backfilling on hillsides or sloping

ground, four-foot-high furrows or

terraces shall be provided across the

pipeline ditch to direct the flow of water

into the natural drainage courses and

away from the pipeline ditch. In no

case is surface drainage to be diverted

into channels other than the ones

they followed before the line was laid.

Particular care shall be exercised in

order that all drainage ditches shall be

maintained and left unobstructed to

prevent the backing up of water against

the spoil bank or backfill crown.

Diversion berms / Water bars should

be used wherever ROW ascends or

descends a steep grade to the following

specifications:

4.12.7. Reinforcing

When applicable, contractors are

to reinforce backfilling near or on

river banks, streams, ravines or other

watercourses, irrigation or drainage

ditches, as well as farm terraces with

earth filled sacks, rock riprap or concrete

headwalls. Contractors are responsible

to, at contractor’s expense, to repair

damage to levees, roadways, lanes,

private drives and farm terraces, as

may be caused by settling or washing

through the ditch portion of same, up to

and including the date of acceptance of

the work included herein and through

the one-year warranty period.

4.12.8. Topsoil

Topsoil is considered by OMS to be

the top layer of soil. At times, topsoil

by standard definition will not apply,

in which case the top 2’ of soil will be

considered “topsoil”.

Topsoil shall be segregated in a method

that protects it from overburden, being

trampled, or from mixing with fill dirt.

Contractor is responsible for maintaining

the separation and quality of topsoil.

Page 73: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

73

Version 1.1

4.13 Leak & Pressure Testing

4.13.1 General

The intent of leak testing is to find

unacceptable faults in a piping system.

If such faults exist, they may manifest

themselves by leakage or rupture; this

may result in catastrophic failure. Piping

systems that rupture may cause sudden,

forcible, uncontrolled movement of

system piping or components, or parts of

components.

A) Location of Equipment

Pipeline systems being tested should be

restrained against sudden uncontrolled

movement from catastrophic failure. All

poly pipe should be located in the trench

and backfilled.

Air compressors should be located a

minimum of 20 feet and no more than

25 feet from the end of the pipe being

tested. Discharge hoses and hard piping

should be secured to the ground in a

manner to restrain it from movement

in the event of a catastrophic failure.

Restraints such as stakes and cables,

straps or tie downs are acceptable. Any

other style of restraint must have OMS

approval.

Pressure recording devices must be a

minimum of 20 feet and no more than

25 feet from the test head, and is to

be located perpendicular to the pipe

being tested. The recorder’s placement

should be out of the whip radius of the

compressor’s discharge hose and/or

hard piping. Chart recorder hoses must

have restraint whip checks installed as

well. The recording device should be

a chart recorder, digital recorder, or

any other recording device approved

by OMS for the length of pipe being

tested. Certifications will be required

for all recorders and gauges for the test

duration.

B) Test Duration

All piping systems are required to be

tested for no less than 8 hours. There

will be no exceptions of pipe footage to

not be tested. The maximum length for

a single tested piping system is 20,000

feet (3.75 miles).

C) Water Sources

1. Quality

Water used for pressure testing must

be from a known clean source, and be

treated with an agent that eliminates the

potential for bacteria growth.

2. Quantity

The quantity of water to be used will be

determined by OMS personnel.

F) Failures

Contractors are responsible for the cost

of labor and materials to repair any

leaks found during the pressure test.

Contractors are responsible for labor and

materials required to isolate the ends of

the pipelines prior to pressure testing.

OMS personnel will be responsible for

purging and placing the pipelines in

service.

G) Depressurizing

After the line has been tested, the

contractor must relieve pressure by

Page 74: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

74

Construction Guidelines

means of opening a valve downstream

predetermined by OMS personnel.

H) Dewatering

1. Disposal of Water

Water should be disposed of in

accordance with all local, state, and

federal laws. It is acceptable that water

removed from the pipeline trench be

disposed of on the ROW.

4.14 ROW Clean-Up

4.14.1 Post-Construction Clean-up

It is OMS expectation that construction

materials will be removed from the

ROW as well as any established laydown

areas, roadways, and approved staging

yards. Other restoration agreements may

necessary.

A) Fences

Fences must be restored to original or

better than original condition prior to

project finalization.

B) Gates

Permanent gates must be installed

across all ROWs.

C) Line Markers

Permanent line markers must be installed

prior to project completion.

D) Test Leads

Test leads must be installed at minimum

every mile, at every road crossing, and at

every bore start and end point.

1. Anode Installation

Anodes must be installed on all steel

risers.

E) Reseeding

Reseeding must be completed according

to ROW agreements, with appropriate

seed for the region in which it is

performed. Consult federal, state, and

local regulations for correct type of seed.

F) Erosion Control

Stake Bales, Straw waddles, or

water bars must be used when the

possibility of slope erosion is imminent.

Near regulated lands (U.S. Corps of

Engineers, Federal, state, Bureau of Land

Management, etc.) Silt fence must be

used to provide a filtration barrier and

protect the environment.

G) Rock Picking

Rocks must be removed from trench

bed if they are larger than 6 inches in

diameter. When rocky conditions exist,

other protective measures will need

to be taken. Never drag pipe on top of

rocky soil.

4.15 Start-up

A) Removal of Isolation Devices

All contractors prior to removing

pancakes, locks, blind flanges, etc. must

follow proper LO/TO procedures for

removing such devices.

B) Opening of Block Valves

Block valves are only to be opened by

OMS personnel. It is imperative that

these valves be operated in such a

Page 75: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

75

Version 1.1

manner to allow for equal pressure on

both sides of the valve.

C) Suction Line Leak Test

Tank valves must be open and a leak

observation / inspection must be

maintained for at least 30 minutes.

1. Water Systems

1.A) Pressure Limits

Pressure limits will be determined by

OMS personnel. Reference Section 5 for

additional information.

2.A) MAOP Sign-off – Water Systems

Prior to operating equipment, a

maximum allowable operating pressure

(MAOP) must be established and

confirmed by OMS personnel. Under no

circumstances should any equipment

or facility be operated without this

document, or verification of MAOP

established.

D) Oil System

1. Pressure Limits

Pressure limits will be determined by

OMS personnel. Reference Section 5 for

additional information.

MAOP Sign-off – Oil Systems

Prior to operating any equipment, the

MAOP must be confirmed by OMS

personnel. Under no circumstances

should any equipment or facility be

operated without this document, or

verification of MAOP established.

E) Pump to Line Leak Test

1. Pump Start-up

Prior to final production, pump and line

leak tests will be performed by closing

the main line discharge valve. The

pump shall be operated at the MAOP to

ensure all equipment components are

functional, and no leaks exist in the line.

2. Line Purge

When lines are to be purged, OMS

personnel must be present to ensure

the protection of personnel and the

environment. Line purges have many

unique challenges that are specific to the

point at which the release is taking place,

as well as the material and methodology

chosen to safely complete this task.

3. Disposal / Release

All material that originates from an

Oasis owned facility must be contained

properly. Spills of any amount must be

immediately reported to OMS personnel.

4. Trucking

When transporting liquids released

from OMS facilities, proper waste

management protocol must be followed.

Consult OMS personnel for direction on

where and how to properly dispose of

material.

F) System Leak Tests

System leak test will be performed

quarterly, maintaining max MAOP for two

hours while monitoring for any pressure

deviation.

Page 76: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

76

Construction Guidelines

Valves must be operated on a quarterly

basis to ensure proper operating

functionality.

1. Vent Valves / Plugs

All plugs and pressure relief valves must

be inspected on a quarterly basis to

ensure they are secured properly and

are in proper working condition. Only

use appropriate tools to check these

functions.

2. Installation Confirmation

After construction is complete and

system is believed to be ready for

production, a final inspection must

be performed on ALL systems, valves

and equipment by contractor and

OMS personnel. This inspection can be

completed by both OMS and contractors

or separately, as long as documentation

is completed.

4.16 Project Sign-off

4.16.1 Final Inspection

When a project is completed, all

departments within OMS are required to

sign the final inspection form. The intent

behind this form is to ensure that all

documentation including pictures, test

records, forms, and billing information

are in OMS’ possession.

Reference Final Inspection Form – [OMS

1019]

Page 77: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 4

77

Version 1.1

Page 78: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

78

General Equipment & Mechanical Guidelines

Page 79: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 5

79

Version 1.1

General Equipment & Mechanical Guidelines

OMS - Oasis Midstream Services

EHS - Environmental Health & Safety

Lifting Eyes - Device attached to frame

of equipment and/or machinery to be

used to lift equipment with weighing

more than 100lbs.

Sound Dampening - Device used to

reduce decibel rating to under 85

decibels as per OSHA CFR 1910.95

Manufacturer Instructions & Manuals

Provides guidelines for installation,

maintenance, and operations for

equipment and materials. Referencing

this material is required prior to

performing work on or with any

equipment.

References:

A. American Gear Manufacturers

Association (AGMA)

B. American Institute of Steel

Construction (AISC)

C. Hydraulic Institute (HI)

D. National Electrical Manufacturers

Association (NEMA)

E. Occupational Safety and Health

Administration (OSHA)

1910.212

1910.144

F. American Society of Mechanical

Engineers (ASME)

G. Oasis Petroleum North America EHS

Manual

Expectations: Standards for Work,

Project Bid Submittal, Design, Materials

and Standard Specifications, Installation

Considerations: Mechanical Integrity,

Quality Control

Page 80: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

80

General Equipment & Mechanical Guidelines

5.1 GeneralA) Purpose

B) ScopeC) Safety

5.2 Standards For Work5.2.1 Complete Systems

5.2.2 Quality of Equipment

5.2.3 Manufacturer Recommendations

5.3 Project Bid Submittal5.3.1 Equipment

5.3.2 Motors

5.3.3 Verification

5.4 Design5.4.1 General

5.4.2 Controls

5.5 Materials And Standard Specifications5.5.1 Materials

5.5.2 Uniformity

5.5.3 Lubrication

5.5.4 Structural Metal Framing

5.5.5 Equipment Bases and Bedplates

A) Mounting EquipmentB) Supporting Equipment

5.5.6 Anchors

A) Bolt PatternsB) Size and Strength

C) Types5.5.7 Safety Guards

A) CoversB) Outdoor Installation

C) Guarding other Surfaces5.5.8 Lifting Eyes

5.5.9 Mechanical Seals

5.5.10 Drives

5.5.11 Nameplates / Labels

A) Manufacturer’s NameplateB) Rotation Direction Labeling

C) IdentificationD) Letters

E) Color

Table of Contents

82

82

82

83

83

Page 81: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 5

81

Version 1.1

F) Fasteners5.5.13 Special Tools

5.5.14 Finishes

A) Factory PaintingB) Shop Priming

C) Rust Prevention5.5.15 Noise and Vibration

A) Decibel LimitsB) Noise Levels due to Vibration

5.5.16 Factory Tests

A) VerificationB) Performance Records

5.5.17 Examination

5.5.18 Preparation

5.6 Installation5.6.1 Structural Fabrications

5.6.2 Anchor Bolts

A) DeliveryB) Base and Bedplate Grouting

5.6.3 Equipment Startup and Adjustment

5.6.4 Sound Level Testing

5.6.5 Tools, Loose Parts and Lubricants

A) InventoryB) Recommended Spare Parts

C) Documentation

88

Page 82: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

82

General Equipment & Mechanical Guidelines

5.1 General

A) Purpose

The purpose of this section is to provide

a guidance document for subcontractors

and suppliers of equipment for or in

conjunction with Oasis Midstream

Service (OMS) operations.

B) Scope

This documents applies to employees,

contractors, and representatives

operating on, near, or with Oasis owned

facilities, Right-of-Ways, or equipment.

C) Safety

While performing work on behalf of OMS,

whether in the field or in a contractor

owned facility, it is expected that work

will be performed in a manner that best

represents Oasis’s commitment to safety

and health at all times. Please refer to

Section 2 (EHS Expectations) of this

manual for more information.

5.2 Standards For Work

5.2.1 Complete Systems

Provide pipe, fittings, wiring and

supports to produce complete,

operable systems with all elements

properly interconnected. If a specific

dimensioned location is not shown for

interconnections or smaller system

elements, select appropriate locations

and show them on shop drawings

submittals for review.

5.2.2 Quality of Equipment

It is OMS expectation that contractors

will provide new equipment that is free

of any known operating malfunctions.

This includes materials quality as well.

OMS also requires that contractors

Install equipment that is aligned, leveled,

cleaned and adjusted for satisfactory

operation. Installed equipment must

be in accordance with manufacturer’s

recommendations and industry best

practices so that; connecting and

disconnecting of piping and accessories

can be readily made; and all parts

are easily accessible for inspection;

operation; maintenance and repair.

Oil and lubrication fittings must be

clear of and away from guards, base

and equipment, and within reach from

the ground or operating floor. The

location of all motor connections must

be coordinated in order to properly

orient encased electrical conduits. To

meet these equipment requirements

as furnished, minor deviations from

drawings may be made, however, they

must be approved by OMS personnel.

5.2.3 Manufacturer Recommendations

The recommendations and instructions

of the manufacturers of products used

in the work are hereby made part of

these specifications except as they may

be superseded by other specification

requirements.

5.3 Project Bid Submittal

5.3.1 Equipment

• Each piece of equipment that

requires a certified witness or non-

witness performance test, must be

accompanied by a completed form

containing the following information:

• Oasis’s name and location of project

• Contractor’s name and subcontractor

if applicable

Page 83: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 5

83

Version 1.1

• Name of item being submitted

• Specification reference by section,

paragraph and page

• Item specifications (manufacturer,

general descriptive data, dimensions,

size of connections, speeds,

performance curves, serial number);

Contractor must provide test results

and a list, which shows the values

that differ from specifications.

-Reference Figure 1-

5.3.2 Motors

Motor data, type, voltage, frequency,

phase, full load amperes, starting

method, frame size, enclosure insulation

type (NEMA Code letter), dimensions,

service factor and serial number.

5.3.3 Verification

All forms must be verified by the date

and signature of the person certifying

the performance. This is required to

verify that equipment has been inspected

and is in proper working condition. OMS

contractors are required to ensure this

verification has been provided prior

to performing work on OMS locations,

equipment, or projects.

5.4 Design

5.4.1 General

Equipment should be designed for

the service they are intended for and

be of ample strength for all stresses

that may occur during fabrication,

transportation, erection, and during

operation. It is expected that equipment

will be adequately braced, anchored,

and installed in a neat and professional

manner. Consideration should be given

to appearance and safety, as well as

intended utilization and placement in

the design and details. Use cathodically

(electrically) compatible materials of

construction.

5.4.2 Controls

Electrical control designs for systems

and/or equipment packages are the

responsibility of the manufacturer and/

or the equipment package provider.

Elementary control diagrams as shown

on the electrical drawings and the

diagrams shown on the instrumentation

drawings are to be generally illustrative

for control and monitoring requirements.

Manufacturers must design their own

functional electric control devices and

circuitry, in consultation with the specific

elementary control diagrams and other

project specifications, to meet the

equipment control requirements. In many

cases these will need to be National

Electric Manufactures Association

(NEMA) approved for use in flammable

atmospheres.

It is the expectation that supervisors

ensure these system diagrams and

package controls are furnished by the

equipment manufacturer, except the

controls shown in motor control centers

and process controllers, remote control

devices and their interconnecting wiring.

5.5 Materials And Standard Specifications

5.5.1 Materials

OMS expects that designs, fabrication,

and assembling of equipment and

systems be equipped with new materials,

and in accordance with acceptable

modern engineering and sbest practices.

Page 84: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

84

General Equipment & Mechanical Guidelines

Individual parts should be manufactured

to standard sizes and gauges so that

repair parts can be installed in the field

and if possible, purchased in a timely and

affordable manner.

5.5.2 Uniformity

Unless otherwise specified, equipment

or material should be constructed of the

same type or classification used for the

same purpose shall be the product of

the same manufacturer and shall be the

same model. This is to ensure that parts

are easy to find, replace, and install on an

as-needed basis.

5.5.3 Lubrication

Lubricant types should be rated for the

temperature variations encountered in

the field by OMS personnel. Quantities

sufficient for consumption prior to

completion, testing and final acceptance

are expected to be secured.

5.5.4 Structural Metal Framing

Weld submerged steel surfaces, which

butt or bear against each other, must

have sealed surfaces that protect against

the penetration of liquids. Gaps cannot

exist between adjacent submerged steel

surfaces less than 1/32-inch wide in order

to ensure a seal on the surfaces.

5.5.5 Equipment Bases and Bedplates

A) Mounting Equipment

Equipment mount assemblies should be

constructed of a single heavy cast iron

or welded steel bedplate or skid unless

otherwise shown or specified. Skids with

bases; bedplates; machined support

pads; tapered dowels for alignment or

mating of adjacent items; adequate

openings to facilitate grouting; and

openings for electrical conduits shall be

provided. Round or chamfer and grind

all corners until they are smooth and free

of burrs. Weld seams continuously and

contact edges between steel plates and

shapes, and grind welds smooth.

B) Supporting Equipment

Machinery and piping on bedplates

should not be supported in any way

other than that which is factory designed

and installed. Bases for equipment

should be provided with axial and

transverse jackscrews to facilitate

horizontal and longitudinal adjustment. If

necessary, stainless steel leveling blocks

and shims or jackscrews shall be used

for leveling the base prior to grouting.

Leveling nuts may be used for leveling

bases weighing less than 200 pounds.

All leveling shall be against steel surfaces

(jackscrew plates, leveling blocks or

leveling nuts). Mount all equipment bases

and baseplates on reinforced concrete

pads at least 3 inches high.

5.5.6 Anchors

A) Bolt Patterns

Equipment shall be furnished with an

anchor bolt pattern and the required

anchor bolts, nuts and washers of

adequate design for securing bases and

bedplates to concrete bases. Anchor

bolts should be of length to allow for

1¼ inches of grout under baseplates

and adequate anchorage into structural

concrete unless otherwise shown or

specified.

Page 85: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 5

85

Version 1.1

B) Size and Strength

Anchors and assembly bolts should

have nuts of ample size and strength

for the purpose intended. Bolts shall

be standard machine bolts, with cold-

pressed hexagon nuts. Provide suitable

de-galling compounds for bronze and

stainless steel threaded components. Any

space wholly or partially underground, or

having a wall or ceiling forming part of

a water channel, is classified as a moist

location. Unless specified or noted on the

drawings, provide materials as follows:

• Bolts and nuts in submerged

locations or submerged and

embedded in concrete or buried in

earth.

• Bolts and nuts for supports or

equipment in dry or moist locations:

galvanized steel (hot-dipped) with

oversize nuts.

• Use other bolting materials where

specifically called for in the

specifications or in the drawings.

C) Types

Motor-driven equipment must be

anchored with cast-in-place anchor

bolts or drilled-in anchors set with

epoxy adhesive. Expansion type anchors

for motor-driven equipment are not

approved.

Anchor all non-motor-driven equipment

with cast-in-place anchor bolts or drilled-

in anchors set with epoxy adhesive

except that, where specifically allowed

by note on the Drawing expansion type

anchors may be used.

5.5.7 Safety Guards

A) Covers

Cover belt or chain drives, fan blades,

couplings, nip points, exposed shafts

and other moving or rotating parts on

all sides with safety guards conforming

to all federal, state, and local codes and

regulations. Guards must conform to

the most restrictive requirement. Guards

should be designed easy installation

and removal, complete with necessary

supports, accessories and fasteners, all

hot-dip galvanized.

B) Outdoor Installation

Design guards in outdoor locations to

prevent entrance of rain and dripping

water. Provide tachometer test opening

in line with ends of shafts. Typically

guards shall be expanded metal on

a structural steel frame, except that

outdoor guards may be of solid material.

Provide hinged doors with latch for

service and lubrication access.

C) Guarding other Surfaces

Cover all pipes, manifolds, heaters

and other surfaces that have a surface

temperature sufficient to burn human

tissue with a thermal insulating material,

or otherwise guard against contact.

All machine guards must comply with

OSHA standards (CFR 1910.212).

5.5.8 Lifting Eyes

Equipment weighing over 100 pounds

must be supplied with lifting eyes. Parts

of equipment assemblies, which are

normally serviced separately, such as

motors, should have lifting eyes of their

own.

Page 86: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

86

General Equipment & Mechanical Guidelines

5.5.9 Mechanical Seals

Where specified, pumps shall have single,

split-type, self-aligning, self-centering

mechanical seals with seals and stuffing

boxes designed for the presence of

moist environments. The seal shall be

of a nondestructive (non-fretting) type

requiring no wearing sleeve for the

shaft. Shafts for pumps specified with

mechanical seals shall be furnished with

no reduction in size through the seal

area. Mechanical seals shall require no

field assembly, other than assembly

around the shaft and insertion into the

pump. Non-shaft O-rings will be of ball

and socket type requiring no gluing.

Initial installation at the factory will be

with non-split faces, with all spare seals

and spare kits to have split faces. The

face combination will be hard/hard. This

device:

On initial flooding of the rotating

equipment, releases entrapped air from

the seal chamber through an integral,

self-cleaning air vent in top of the

bushing;

Creates fluid exchange and improved

circulation in the seal chamber that

reduces frictional heat accumulation

around the mechanical seal;

Positions particulate matter/

contaminants for removal by conveying

them from the bore to the shaft by

means of an integral machined spiral;

Removes particulate matter/

contaminants from the seal chamber

to the impeller for expulsion, without

seal flush water, through and integral

machined exit groove;

Pump seals shall be hydraulically

balanced and designed for 200% of the

seal area pressure under operating RPM

and temperature conditions of the RAS

stream;

Mechanical seals shall be manufactured

to the highest quality standards.

5.5.10 Drives

Provide all drive units with a rating and

service factor suitable for 24 hours per

day operation under the operating load.

5.5.11 Nameplates / Labels

A) Manufacturer’s Nameplate

Equipment and drivers shall be installed

with a corrosion-resistant metal

nameplate fastened in a readily readable

position. This nameplate shall contain the

manufacturer’s name, equipment rating,

capacity, size, model, serial number and

speed. All written or printed information

written shall be written in English.

B) Rotation Direction Labeling

Furnish each piece of rotating equipment

with a direction of rotation arrow. This

label should conform to OSHA CFR

1910.144.

C) Identification

Each piece of equipment should be

identified using a high quality (weather

resistant) label with the functional name

and number of the equipment.

Fasten labels to the equipment, its base

or other acceptable location.

Page 87: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 5

87

Version 1.1

D) Letters

Letters shall be sized at least 3-inch high

with the border trim on all sides not less

than 3-inch.

E) Color

The color of labeling should be green

background with white letters.

F) Fasteners

Brass or stainless steel screwed into

inserts, anchor shields or tapped holes in

equipment or base.

5.5.12 Protection against Electrolysis

Where dissimilar metals are used in

conjunction with each other, suitable

insulation should be installed between

adjacent surfaces to eliminate direct

contact and any potential electrolysis.

Connections of dissimilar piping

materials shall utilize dielectric unions,

flanges, couplings or bushings.

5.5.13 Special Tools

For each type of equipment, a list of

special tools needed (including grease

guns or other lubricating devices), which

may be necessary for the adjustment,

operation and maintenance of such

equipment should be provided.

5.5.14 Finishes

A) Factory Painting

Pumps; motors; drives; starters; control

panels; and other similar self-contained

or enclosed component shall have a

factory protective paint system applied

unless otherwise noted. Paint or protect

surfaces that are inaccessible after

assembly by a method to provide

protection for the life of the equipment.

B) Shop Priming

Except where field sandblasting is

required, apply one or more shop coats

of metal primer (of sufficient thickness

to protect surfaces until finished) on

surfaces to be finish painted at the site.

Primer shall be compatible with finish

coat.

C) Rust Prevention

Machined, polished, and other ferrous

and non-ferrous surfaced equipment are

not to be painted with rust preventive

compound.

5.5.15 Noise and Vibration

A) Decibel Limits

It is OMS desire that equipment not

operate at a sound level about the

maximum allowable level by OSHA,

however, if the required sound level

cannot be achieved by bare equipment

in its designated environment, a sound

dampening device should be provided.

These devices shall have necessary

ventilation to prevent equipment

overheating and shall be constructed

for easy removal to permit maintenance.

Devices necessary for day-to-day

operation shall pierce the enclosure or

otherwise be accessible without need to

remove the enclosure.

B) Noise Levels due to Vibration

Equipment that has obvious excessive

vibrations when in operation shall be

repaired or replaced as directed by

Page 88: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

88

General Equipment & Mechanical Guidelines

OMS personnel. Baseline vibration

measurements shall be made where

specified.

5.5.16 Factory Tests

A) Verification

Proof of factory tests for each piece of

equipment should be provided with the

equipment. Note that factory tests are

inherent in many reference standards.

The requirement for a factory test in a

referenced standard is hereby made a

part of these specifications. Factory tests

should be conducted at the same speeds

and conditions at which the equipment

will operate in the field, except as noted.

B) Performance Records

Where specifically noted, performance

tests may be witnessed by the Oasis

representative or his/her representative.

Inform OMS personnel in sufficient

time to allow arrangements to be made

for witness of such tests. When non-

witnessed tests are performed, supply

certified results.

Factory testing of pumps and

compressors shall be supplied in

accordance with the requirements and

standards of the Hydraulic Institute (HI).

5.5.17 Examination

Equipment shall be inspected for

damage, defects, completeness and

correct operation before installing,

and after installation and pressure or

operations test is performed.

5.5.18 Preparation

Prior to installing equipment, ensure

that areas are clean. Maintain areas

in a broom-clean condition during

installation operations. Clean, condition,

and service equipment in accordance

with the approved Instruction Manuals

and specific recommendations of the

equipment manufacturer.

5.6 Installation

5.6.1 Structural Fabrications

Equipment must conform to AISC Codes

as well as to approved Manufacture

provided instruction manuals. Only

skilled and experienced trained on

methods of installing of the types

of equipment specified, are the only

approved personnel may fabricate

equipment on behalf of OMS. Specialized

tools and equipment shall be utilized,

such as precision machinist levels, dial

indicators, gauges and micrometers, as

applicable. Equipment shall be installed

free of over vibration or other defects.

Align and pin to common bedplate

equipment and drivers connected by

flexible couplings.

5.6.2 Anchor Bolts

A) Delivery

Deliver bolts with templates or setting

drawings and verify that bolts are

correctly located before structural

concrete is placed.

B) Base and Bedplate Grouting

Grouting equipment on concrete pads

shall take place prior to connection of

piping or electrical and instrumentation

systems. Initial fitting and alignment

of connected piping prior to grouting

is acceptable, however, final alignment

and connection of piping shall be done

Page 89: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

Section 5

89

Version 1.1

after equipment grouting is completed.

Level and align equipment base on the

concrete foundation, then clamp the

baseplate in position by installing the

equipment anchor nuts and washers and

making snug tight.

Contractors are expected to ensure

alignment has been maintained after

clamping. The space under the base or

bedplates shall be filled completely with

grout. Exposed grout shall be beveled

at a 45-degree angle, except round

exposed grout at horizontal surfaces for

drainage. Trowel or point exposed grout

to a smooth, dense finish and damp

cure with burlap for three days. When

grout is fully hardened, leveling blocks

and shims or jacking screws shall be

removed, or leveling nuts shall be backed

off to allow the grout to fully support

the equipment base. Tighten nuts on

anchor bolts to one-quarter turn past

snug tight in an alternating pattern to

avoid stress concentration on the grout

surface. Block outs for access to leveling

nuts or leveling blocks, and shims shall

be filled with the grout material installed

under the base and pointed. Holes in

the base associated with jackscrews

shall be filled with flexible sealant.

Check the installation for alignment and

that it is level, and perform approved

corrective work as required to conform

to the tolerances given in the applicable

instruction manual.

5.6.3 Equipment Startup and

Adjustment

Equipment should be oriented in a way

most suitable for authorized factory-

trained representatives of the vendors

supplying the various items of equipment

to check the equipment after installation

and adjust and test the equipment

as necessary prior to startup. This

representative shall be experienced and

knowledgeable of the equipment being

tested. They are expected to assist and

instruct the operating staff in adjusting

and operating the equipment during the

initial operation period, providing initial

lubrication for all equipment.

Equipment should be tested and results

available to OMS personnel to ensure

proper functioning. For pumps and

compressors, include measurement

of suction and discharge pressure at

the equipment and measurement of

equipment rate by volumetric means

or through a suitably calibrated meter

for two points on the performance

curve. For adjustable-speed pumps

and compressors, conduct tests at a

minimum of two speeds. Furnish any

required test equipment or measuring

devices that are not part of the

permanent installation.

In addition, demonstrate that the entire

facility is in full operating condition prior

to the acceptance of the work. Should

any equipment or part thereof fail to

operate as intended, immediately remove

and replace it, all at the contractor’s

expense. Pay for all tests involved in this

section.

Pressure test equipment and connections

as required by these specifications.

For each electrical motor, measure

terminal voltage, line current, power

factor and watts at motor terminals while

running at full load.

5.6.4 Sound Level Testing

Measure the sound level developed by

all mechanical and electrical equipment

Page 90: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

90

provided. Perform testing in all rooms

and spaces containing such equipment

during the final operation test program

with all equipment operating. Use OSHA

approved instrument, and record the

highest sound level developed when

measured according to OSHA standards

in each room and space. Deliver a copy

of records to Oasis management.

5.6.5 Tools, Loose Parts and Lubricants

A) Inventory

Inventory lists for tools and loose parts

are expected to be maintained for

each project. Extra inventory and parts

should be returned to OMS in a timely

manner after a project is complete. Oasis

Material Transfer Forms [ref. Sec. 4]

acknowledgment of receipt is required

for project completion. Loose parts are

defined as items such as special tools,

keys, safety equipment and portable

equipment.

B) Recommended Spare Parts

Furnish a complete list of recommended

spare parts and supplies for each piece

of equipment furnished with current

prices and a source of supply.

C) Documentation

Provide a list of all recommended

lubricants not listed in the operation and

maintenance manuals.

Page 91: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

91

Page 92: Oasis Midstream Servicesbasinsafetyus.com/wp-content/uploads/2014/08/General-OMS...2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and

92