Upload
rodd29
View
227
Download
0
Embed Size (px)
Citation preview
Nuclear M f t iManufacturing
Outreach
Welcome
OPPORTUNITYOPPORTUNITY KNOCKING
Ashok BhatnagarSenior Vice President,
TVA Nuclear GenerationTVA Nuclear Generation Development and Construction
February 18, 2009
Energy Needs
Increasing demand
Meet demand by:Meet demand by:-Building nuclear and CTg-Conserving
ReliableEnergySupplyWhy Nuclear?
Clean Air Value
pp y
EconomicD l t
y
Forward Price
Stability Less
Development
CompetitiveElectricity Zero Air
Emissions
Dependence on Oil
and Gas
Low$1 07 Local BenefitsProtection
against CO2risk
LowFuel
TransportationRisk65%
of
$1.07 Local Benefitsfor
Every $1 Spent
Up to 2400
Lowers Average Cost of Power
High Capacity Factors7 x 24 Power
of Total Cost
Fixed
Jobs During Constructionand 400-500
During OperationPer Unit
Foundation of Safety
TVA Nuclear
SequoyahWatts Bar
Browns Ferry Bellefonte Sitey Bellefonte Site
Watts Bar Unit 2Watts Bar Unit 2
• On schedule, on budget
• Current staffing – 1600
• Orders placed for major equipmentOrders placed for major equipment
Domestic Nuclear Supplier BaseKnown Areas Of NeedKnown Areas Of Need
• Ultra-heavy (>350 ton) forgings
N l G d ASME (N t ) P• Nuclear Grade, ASME (N-stamp) Pumps
• Nuclear Grade, ASME Valves,
• Nuclear Grade, ASME Heat Exchangers
• Metallic Reflective “Mirror” Insulation
Challenges OpportunitiesImprovements
Shortage of skilled craftsg
Fabrication of equipment
Where To Next?
Bellefonte Option
Identified Power Planning Need2015 – 2020
Bellefonte Site(Alabama)
Key MessagesKey Messages
• Enjoy!
• Network!
• Opportunity is knocking. Answer it!knocking. Answer it!
Nuclear Energy CoalitiongyNEI Vendor ForumFebruary 18, 2009February 18, 2009
What is the Tennessee Valley Corridor?y
• National award-winning regional economic and technology development group
• Featuring key leaders across eight congressional districts in four states
• With active support of region’s top public and private technology partnersp p gy p
• Working together to grow and attract the high-tech jobs of the future
• Working in close consultation with the region’s Congressional delegation
Two-Fold MissionTwo-Fold Mission• To promote the TennesseeTo promote the Tennessee
Valley Corridor as one of the nation’s top science and technolog cente sand technology centers
• To promote and leverage the Corridor’s research andthe Corridor s research and technology assets for new jobs and new investment
TVNEC ObjectivesTVNEC Objectives• Develop and Expand the Nuclear p p
Industry Cluster in the Tennessee Valley Corridory
• Evaluate and Promote Ultra Heavy F i C bilit i th V llForging Capability in the Valley
• Promote the Development and TestingPromote the Development and Testing of Small Power Reactors
Tennessee Valley RegionTennessee Valley Region1. East Bridge Business Park
2. Commerce Park
3. The Horizon Center
4. Roane Regional B&T Park
5. Jackson Co. Industrial Park
6 Scottsboro Industrial Park6. Scottsboro Industrial Park
7. Cummings Research Park
8. JetPlex Industrial Park
9. Mallard/Fox-Creek Ind. Park
10. Enterprise South Ind. Park
11. Chattanooga Riverfront
12. Hiwassee River Park
13. Nickajack Ind. Park & Port13. Nickajack Ind. Park & Port
Technology and Business Parks
Regional Offerings• Location: Logistics and Projectsg j
Existing and planned high value nuclear projects
• Regional SynergyMajor Engineering Procurement Construction contractors in areaMajor Engineering Procurement Construction contractors in area
Qualified 2nd and 3rd tier vendors in area
• Workforce ExpertiseNuclear and manufacturing workforce availabilityNuclear and manufacturing workforce availability
Training pipelines, vocational and educational institutions
• Access to Research and Technologyk id i l bOak Ridge National Laboratory
SimCenter: National Center for Computational Engineering
Y-12 National Security Complex
NASA M h llNASA Marshall
U.S. Army on Redstone Arsenal Supplier
U.S. Interstates and Waterways
TVCTVC
•Crossroads of major interstate system
•Rail access
•Waterway access via Tennessee River
U.S. Energy Usage
TVC
TVC i C t l t USTVC is Central to US energy use, production and availability
Department of Energy and NASA
32 46
TVC
1 Mixed Oxide Fuel project (MOX)
1
35 8
7
1 Mixed Oxide Fuel project (MOX)2 Uranium Processing Facility3 Integrated Facility Disposition Project4 High Flux Isotope Reactor5 NASA Marshall6 Y-12 National Security Complex7 Oak Ridge National Lab8 Savannah River Site8 S S
Current U.S. Reactor Sites66
51
2
1
67 49
50 50 54
53 53
48 48
52 52
43 43
45
44 443941 40
1516 16
13
12
13 11 11
14 146 6
78 8
22
55
4
182
43
64 64
55
6856
48 4347 47
43
424246
34
37
35 35
37
19 19
36
1010
1 Maine Yankee2 Seabrook3 Pilgrim4 Millstone5 I di P i t
19 Surry20 Brunswick21 Catawba22 Robinson
38 Big Rock Point39 Fermi40 Perry41 Davis-Besse
55 Cooper56 Callaway57 Grand Gulf58 River Bend
6363
626262
61 61
69 69 30 30
29 29
33 3331 31
202022
21 21
2424
3123
25 255 Indian Point6 Limerick7 Oyster Creek8 Hope Creek9 Salem
10 Calvert Cliffs11 Peach Bottom12 TMI13 Beaver Valley14 Susquehanna15 RE Ginna16 Nine Mile Point
23 VC Summer24 AW Vogtle25 EI Hatch26 St Lucie27 Turkey Point28 Crystal River29 JM Farley30 Browns Ferry31 Oconee32 Bellefonte33 Sequoyah
41 Davis Besse42 Braidwood43 Dresden44 DC Cook45 Palisades46 Clinton47 LaSalle County48 Quad Cities49 Duane Arnold50 Prairie Island51 Monticello52 Byron
58 River Bend59 Waterford60 South Texas Project61 Comanche Peak62 Palo Verde63 San Onofre64 Diablo Canyon65 Vallecitos66 WNP67 Fort Calhoun68 Wolf Creek69 Arkansas Nuclear One
60 60
5758
59
29 29 25 25
2826
26
2717 JA Fitzpatrick18 Vermont Yankee
33 Sequoyah34 Watts Bar35 McGuire36 Shearon Harris37 North Anna
52 Byron53 Point Beach54 Kewaunee
69 Arkansas Nuclear One 2727
Proposed U.S. Reactor Sites
70
8371
89
72
82
73
84
74
75
78
80
81
86
85
PROPOSED70 Nine Mile Point71 Susquehanna72 Calvert Cliffs73 Harris
1 Maine Yankee2 Seabrook3 Pilgrim4 Millstone5 I di P i t
19 Surry20 Brunswick21 Catawba22 Robinson
38 Big Rock Point39 Fermi40 Perry41 Davis-Besse
55 Cooper56 Callaway57 Grand Gulf58 River Bend
76
77
79
88 87
73 Harris74 W. Lee75 VC Summer76 Levy County77 Turkey Point78 Vogtle79 River Bend80 Grand Gulf81 Bellefonte82 North Anna 83 Fermi84 Callaway
5 Indian Point6 Limerick7 Oyster Creek8 Hope Creek9 Salem10 Calvert Cliffs11 Peach Bottom12 TMI13 Beaver Valley14 Susquehanna15 RE Ginna16 Nine Mile Point
23 VC Summer24 AW Vogtle25 EI Hatch26 St Lucie27 Turkey Point28 Crystal River29 JM Farley30 Browns Ferry31 Oconee32 Bellefonte33 Sequoyah
41 Davis Besse42 Braidwood43 Dresden44 DC Cook45 Palisades46 Clinton47 LaSalle County48 Quad Cities49 Duane Arnold50 Prairie Island51 Monticello52 Byron
58 River Bend59 Waterford60 South Texas Project61 Comanche Peak62 Palo Verde63 San Onofre64 Diablo Canyon65 Vallecitos66 WNP67 Fort Calhoun68 Wolf Creek69 Arkansas Nuclear 1 7784 Callaway
85 Amarillo86 Comanche Peak87 South Texas88 Victoria County89 Bruneau
17 JA Fitzpatrick18 Vermont Yankee
33 Sequoyah34 Watts Bar35 McGuire36 Shearon Harris37 North Anna
52 Byron53 Point Beach54 Kewaunee
69 Arkansas Nuclear 1
Combined Sites66
51
2
1
70
67 49
50 50 54
53 53
48 48
52 52
43 43
45
44 443941 40
1516 16
13
12
13 11 11
14 146 6
78 8
22
55
4
182
43
8371
89
64 64
55
6856
48 4347 47
43
424246
34
37
35 35
37
19 19
36
101072
82
73
84
32
46
PROPOSED70 Nine Mile Point71 Susquehanna72 Calvert Cliffs73 Harris
1 Maine Yankee2 Seabrook3 Pilgrim4 Millstone5 I di P i t
19 Surry20 Brunswick21 Catawba22 Robinson
38 Big Rock Point39 Fermi40 Perry41 Davis-Besse
55 Cooper56 Callaway57 Grand Gulf58 River Bend
6363
626262
61 61
69 69 30 30
29 29
33 3331 31
202022
21 21
2424
3123
25 25
74
75
78
80
81
86
85
1
3 45 8
73 Harris74 W. Lee75 VC Summer76 Levy County77 Turkey Point78 Vogtle79 River Bend80 Grand Gulf81 Bellefonte82 North Anna 83 Fermi84 Callaway
5 Indian Point6 Limerick7 Oyster Creek8 Hope Creek9 Salem10 Calvert Cliffs11 Peach Bottom12 TMI13 Beaver Valley14 Susquehanna15 RE Ginna16 Nine Mile Point
23 VC Summer24 AW Vogtle25 EI Hatch26 St Lucie27 Turkey Point28 Crystal River29 JM Farley30 Browns Ferry31 Oconee32 Bellefonte33 Sequoyah
41 Davis Besse42 Braidwood43 Dresden44 DC Cook45 Palisades46 Clinton47 LaSalle County48 Quad Cities49 Duane Arnold50 Prairie Island51 Monticello52 Byron
58 River Bend59 Waterford60 South Texas Project61 Comanche Peak62 Palo Verde63 San Onofre64 Diablo Canyon65 Vallecitos66 WNP67 Fort Calhoun68 Wolf Creek69 Arkansas Nuclear 1
60 60
5758
59
29 29 25 25
2826
26
27
76
77
79
88 87 Radius 500 Mi 805 Km
84 Callaway85 Amarillo86 Comanche Peak87 South Texas88 Victoria County89 Bruneau
17 JA Fitzpatrick18 Vermont Yankee
33 Sequoyah34 Watts Bar35 McGuire36 Shearon Harris37 North Anna
52 Byron53 Point Beach54 Kewaunee
69 Arkansas Nuclear 1 272777
TVNEC for the Supplierpp
TVNEC
Supplier
Vision: Bridging the Gapg g pSuppliers, EPC’s
TVNECTVNEC
Utility
SupplierSupplier
DOE
pp
Supplier
Supplier
Regional SynergyMajor Engineering, Procurement, or Construction contractors working in area
Regional Synergyg y gy
• 2nd Tier Suppliers and Servicespp
Nuclear Inspection and testing >10 companies
B i t M f t i 50 iBasic component Manufacturing >50 companies
Large Scale Construction Services >20 companies
Nuclear Services >15 companies
Workforce DevelopmentWorkforce Development
Skilled Worker TrainingSkilled Worker TrainingApproximately 23 four-year institutionsApproximately 23 four year institutions with enrollment of almost 100,000 students
Approximately 25 Community Colleges/Tech Institutions with enrollment of approximately 55,000 students
QuestionsQVisit our website:
www.tennvalleycorridor.orgy g
OR Contact:
Gary Gilmartin
TVNEC Lead
Ph (865)-241-1790
Cell (865)-466-0748( )
New Nuclear PlantsGl b l SGlobal Status
• 43 plants under construction 3 p a ts u de co st uct o– ~ 37 GW
• 108 plants on order or planned in 24 countries– ~ 121 GW
• 266 projects under consideration in 27 countriesSt t t f i t t/ l– Statement of intent/proposal
Source WNA Jan 2008
Proposed New Nuclear PlantsProposed New Nuclear Plants
• 17 Applications17 Applications• 26 Units• 5 Designs• 5 Designs
Short-TermOrder long-lead items
COL review
Site preparation
COL Approval
Construction
Arrange financing Load fuel
COL submittedCOL submitted
Start-up testing (4-6 months)
Commercial operation
Pre-COL construction
General procurement
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
pGeneral procurement
Licensing & Construction Then and NowThen and Now
THEN NOWDesign as you build Plant designed before construction begins
Changing regulatorystandards and requirements
More stable process: NRC approves site, design, construction & operation before construction begins and p gsignificant capital is placed “at risk”
No design standardization Standard NRC-certified designs – 70+% Standard
Inefficient construction Lessons learned from overseas projectspractices Modular construction practices
Main opportunity public intervention when plant is essentially complete
More opportunities to intervene at well-defined points in process. Intervention at the end of the process must be based on objective evidence that acceptance criteriaessentially complete based on objective evidence that acceptance criteria, defined in the license, have not been, and will not be met
US Commercial Outlook to 2020US Commercial Outlook to 2020
• First 4 – 8 plants expected to start• First 4 8 plants expected to start commercial operations in 2016– Others under construction– Others under construction– Building rate and projects adjusted based on
the success of the first few projectsthe success of the first few projects
• Potential for new plants 15 20 i 2020 35+ i 2030– 15 - 20 in 2020; 35+ in 2030
– If first projects are successful
Equipment & Commodities for Fi t Ei ht Pl t (E l )First Eight Plants (Examples)
• Cable – over 1800 milesCable over 1800 miles• Nuclear grade valves – 4000 to 24000 • Pumps -- 1000 to 2000• Pumps 1000 to 2000 • Nuclear grade piping – 30 – 150 miles• Concrete over 3 million cubic yds• Concrete – over 3 million cubic yds• Electrical components -- Over 700,000
Structural & reinforcing steel 500 000 tons• Structural & reinforcing steel -- 500,000 tons• Large and small heat exchangers -- 500 to 1300
Support for New Nuclear & Expanded US Manufacturing BaseExpanded US Manufacturing Base• Bipartisan political support• Strong public support• Solid support from laborSolid support from labor• Strong support from other industries• Growing support from environmental• Growing support from environmental
community
The FutureThe Future
• New nuclear power plants will be builtp p– Need for power, environmental limitations and
need for long-term stability in electricity prices
• Opportunity is there -- will US-based manufacturers be able to take advantage?g
SSOUTHOUTH TTEXASEXAS PPROJECTROJECT
What Does a Nuclear Project Look Like?
Will JumpPlant General Manager – STP Units 3&4
February, 2009
IntroductionIntroductionIntroductionIntroduction
• The South Texas Project• The South Texas Project
• A compelling case for nuclear
• Projects of the past
• This time around• This time around
• Total project approach
• Challenges and risks
THE SOUTH TEXAS PROJECTTHE SOUTH TEXAS PROJECT\ _ g X X Z\ÅÑÜÉä|Çz _|äxá g{ÜÉâz{ XåvxÄÄxÇvx |Ç XÇxÜzç ZxÇxÜtà|ÉÇ
• STP Nuclear Operating Company
• Ownership structureOwnership structure
• Impressive site
• Existing units
• Expansion plans
A Compelling Case for NuclearA Compelling Case for NuclearA Compelling Case for NuclearA Compelling Case for Nuclear
• Performance of existing fleet
• Energy Policy Act of 2005
• Safe
• Predictable and economic
• Clean
Projects of the PastProjects of the PastProjects of the PastProjects of the Past• Standard construction techniques
• Type writers and carbon paper
• Information technology
• Integrated schedulesIntegrated schedules
• Communication and collaboration skills
• Fear and intimidation
• Overall brute force
This Time AroundThis Time AroundThis Time AroundThis Time Around
• Project management finesse
• STP culture – coupled with best construction approach
• High standards of excellence• High standards of excellence
• Planning mentality
• Strong communications
• Collaboration & decision makingg
• Teamwork
• Project management tools
Total Project ApproachTotal Project ApproachTotal Project ApproachTotal Project Approach
• LicensingLicensing
• Engineering procurementEngineering, procurement and construction
• Staffing and training
Key RisksKey RisksKey RisksKey RisksKey RisksKey RisksKey RisksKey Risks
• Existing plant performance
• Supply chain
• Skilled work forceSkilled work force
E i ti Pl t P fE i ti Pl t P fExisting Plant PerformanceExisting Plant Performance
Operating units the main focus• Operating units the main focus
• Project office offsite
• Strategic communications plan used
• Employee transfer plan well controlled
• Integrated work force management plang g p
• Increased pipelines support both
Supply ChainSupply ChainSupply ChainSupply Chain
• Early in the process• Early in the process
• Significant quantities of material and equipment
• Safety related
• Non-safety relatedNon safety related
• U.S. supply chain has eroded
• Early planning is key
• Long lead equipment
Skilled Work ForceSkilled Work ForceSkilled Work ForceSkilled Work Force
• Work force management plan
• Training programs
Recruiting• Recruiting
• Educational programs
• College relationships
• Working with partners• Working with partners
Skilled Work ForceSkilled Work ForceSkilled Work ForceSkilled Work Force
Closing ThoughtsClosing ThoughtsClosing ThoughtsClosing Thoughts
Exciting times• Exciting times
• Nuclear power renaissance is realNuclear power renaissance is real
• Significant challenges ahead
• Planning reduces risk
• Need to act now
Q ti /AQuestion/Answer
AREVAAREVA New Plants Update
“We’re not just building a plant, we’re building an
Rick Bonsall, PEManager, LWR Programs
AREVA NP, Inc.Ch l tt NC industry.”Charlotte, NC
An integrated nuclear supplier serving the entire nuclear power cyclep y
Fuel fabricationEnrichment
Renewable energies
Reactors
Chemistry
OTHER SOURCESUsed fuel treatment
RecyclingMOX fuelfabrication
Services OF ELECTRIC POWER
TransmissionMining
treatment Services
Distribution
Front End Division
Reactors and ServicesDivision
Back End Division
Transmission & DistributionDivison
AREVA Locations in the U.S.
Richland WA (785)AREVA NP (670); CEC (91);
Bellevue WA (337) T&D
Benicia CA (135)
Naperville IL (50)AREVA NP
Marlborough MA (150) AREVA NPMills WY (29)
CI (3); Pathfinder Mines (7); COGEMA Mining (19)
Meriden CT (395)Canberra
/ ( )
AREVA NP (670); CEC (91); Numatec (11); PacTec (3)
T&D
Medford OR (125)T&D
Bethlehem PA (85) T&D
Lynchburg VA (1,700)AREVA NP (NA Headquarters)
Benicia CA (135)AREVA NP
Woodbury/Dover NJ (71)AREVA NP (10); Canberra (61)
Washington DC (48)AREVA (15); CI (33)
Eddystone PA (71) T&D
Cranberry PA (86)
San Jose CA (70)AREVA NP
Alpharetta GA (64)AREVA NP (60); Canberra (4)
Charlotte NC(545) AREVA NP (520); CI (25)
( )
Albuquerque NM (104)Aquila (87); AREVA NP (15);
Canberra (2)Aiken/Seneca SC (113)
AREVA NP (105); CI (5); Canberra (3)
AREVA (15); CI (33)
> 5,200 AREVA Employees in U.S.
Fort Worth TX (50)AREVA NP
Nuclear Operation Sites
Transmission & Di t ib ti Sit
p yNuclear Operations
at 22 LocationsDistribution Sites
AREVA’s 2030 scenario for nuclear power construction or life extension of 500 GWeconstruction or life extension of 500 GWe
833 : WEO - 2007 Stabilization 450ppm
731 : WNA - 2007 Upper
691 : IAEA - 2007 High
GWe net installed
Life extension
New Construction
635344AREVA529 : WNA - 2007 Reference
525 : WEO - 2007 Alternative
447 : IAEA - 2007 Low
Theoretical end of life
447 : IAEA 2007 Low
415 : WEO - 2007 Reference
438 : DOE EIA - 2006 267
186
372
2007 2030
EPRTM Nuclear Plant
• 1600 MWe, 4590 MWth• Four independent safety
systems in separate safeguard buildings
• Designed for airplane hazards
• Being Deployed Worldwideg p y• NRC Design Certification
underway• Selected by UniStar NuclearSelected by UniStar Nuclear
FIRST Generation III+ Under Construction
4 units under construction
Olkiluoto 3, Finland Flamanville 3, France Taishan 1&2, China
Additional units proposed across the globe
2nd EPR i F
India - 2 Units
UAE - 2 units
South Africa Canada
2nd EPR in France
United Kingdom
P j t d t di t bilit b iltProject and cost predictability built on real experience
Steady Progress at OlkiluotoSteady Progress at OlkiluotoGeneral Site View
Cable Tray Installation
Reactor Vessel Arrives
Turbine Building
Olkiluoto Unit 3 - first Gen-III plant under construction, setting the stage for a world-wide renaissance of nuclear power generation
A large diversified supplier network supports this complex project
U.S. EPR™ Projects
UniStar Calvert Cliffs UnitUniStar Calvert Cliffs Unit--3, Maryland3, Maryland Ameren Callaway UnitAmeren Callaway Unit--2, Missouri2, MissouriCOLA submitted March 2008COLA submitted March 2008 COLA submitted July 2008COLA submitted July 2008
UniStar Nine Mile Point UnitUniStar Nine Mile Point Unit--3, New York3, New YorkCOLA submitted October 2008COLA submitted October 2008
PPL Bell Bend, PennsylvaniaPPL Bell Bend, PennsylvaniaCOLA submitted for October 2008COLA submitted for October 2008
U.S. EPR™ standardized fleet already underway
Anticipated growth: The “Bridge the Gap” ProgramTo Successfully meet future needs
Ability to respond to rising demand for nuclear energy and to help our Customers answer to market requirements
Driven at the highest level of and across the organization Processes to build on experience and improve efficiency Organization able to implement and benefit from itOrganization able to implement and benefit from itPersonnel competences and experiences
S d iti th l h iSecures resources and capacities across the value chain Mining and Uranium supplyFuel capacitiesIndustrial capacities
Answer to global market trends reduce project risks
Industrial capacities Engineering resources
AREVA NP Inc.
Answer to global market trends, reduce project risks and efficiently implement with a strong regional focus
Bridging the Gap: Secure Fuel Supply For the existing and new build fleets
> Mining: Large investments:6 production sites in North America, Africa, pand Asia6 additional sites planned to enter portfolio by 201220%-25% of global market share20%-25% of global market share
> EnrichmentFrance: Georges Besse II (~ €3.0B)
• Capacity of 7.5M SWU potentially up to 11.0M p y p y pSWU
• Modularity enabling production to start in 2009 United States: Eagle Rock in Idaho (~$3.0B)
• Capacity of 3 0M SWU• Capacity of 3.0M SWU• Authorization via diplomatic channels in
progress• Customers have signed letters reserving
capacity
AREVA NP Inc.
capacity
AREVA is Investing in EPR™ Supply Chain
AREVA is investing in supply chain certainty
AREVA NP Inc.
AREVA is investing in supply chain certainty.
AREVA, Northrop Grumman Announce JVAREVA Newport News, LLC
> 300 000 sq are foot facilit> 300,000 square-foot facility comprising a $360 million investment in commercial nuclear manufacturingg
> Ground-breaking in May of 2009 fully operational in2009, fully operational in December 2011
> JV brings access to approximately 1,000 engineers and 10,000 craft. Of the 10,000 craft, AREVA gains access to approximately 4,000 welders, 1,000 of which are SS welders.
AREVA NP Inc.
Bridging the Gap: TalentResources for existing and new build projectsg p j
8,600
Hiring
5 900
11,500 > 12,000
5,900
2005 2006 2007 2008
Hiring Integration Training
Investing in human capital: more than one new hire every hour
AREVA NP Inc.
y
Bechtel's Global Professional Nuclear Resources
20,000employees withe p oyees t
nuclear experience
5 0005,000engineers with nuclear
power experiencepower experience
AREVA NP Inc.
AREVA NP / Bechtel Proprietary Information
AREVA Vision: Share with more supplierspp
• A new generation of suppliers for a new generationA new generation of suppliers for a new generation of reactors– Increase the capacity of the current supply base / add new
supplierssuppliers
• Long-term partnerships will be developed with suppliers in order to:– Offer competitive solutions worldwide to our customers
• INTERNATIONAL PROJECTS
– Respond to national localization programs– Respond to national localization programs• DOMESTIC PROJECTS
AREVA P h i A T fAREVA Purchasing: A Team of more than 1000 professionals worldwide…
Involve Suppliers in a Continuous Improvement ApproachApproach
• Stimulate supplier creativity through contracts• Stimulate supplier creativity through contracts focused on quality, cost and delivery objectives
• Encourage active supplier participation in co-cou age act e supp e pa t c pat o codevelopment initiatives
• Develop and formalize long-term partnerships
• Work toward multi-project agreements
40 to 60 billion dollars at stakefor EPR suppliers through 2020for EPR suppliers through 2020
We need you…
Optimizing The Supply ChainOptimizing The Supply Chain
Brenda PetrilenaWestinghouse Electric Company
Director, Supply Chain Management
Nuclear Power PlantsProject Supply & Supplier Engineering
Presentation OverviewPresentation Overview
• Westinghouse Overview• The Global Demand for Nuclear Power• AP1000 Overview - Simplificationp• Westinghouse Supply Chain Challenge• Westinghouse Forecasted Purchasesg• Westinghouse Expectations from the Supply Base• SummarySummary
Westinghouse OverviewWestinghouse Overview
• Vision – Westinghouse will be the customers’ choice to supply leading-Vision Westinghouse will be the customers choice to supply leadingedge nuclear technology, to satisfy the world’s growing demand for energy
• 3 Core Competencies –– Nuclear Power Plants – Specializes in designing and delivering new nuclear
power plants, and manufactures precision stainless steel componentsp p , p p
– Nuclear Services – State of the art field services, engineering services, repair and replacement services, and training to our global utility customers
– Nuclear Fuel – The world’s leading integrated supplier of nuclear fuel– Nuclear Fuel – The world s leading integrated supplier of nuclear fuel products and services
The Demand for Nuclear PowerAP1000 W ld idAP1000 Worldwide
• China– Contracts for 4 units at Sanmen and Haiyang sites– Contracts for 4 units at Sanmen and Haiyang sites– Site prep work underway at both sites
• USAP1000 D i C tifi ti d b th NRC 12/30/2005– AP1000 Design Certification approved by the NRC on 12/30/2005
– 6 AP1000 Combined Operating Licenses accepted and docketed to date (12 units)1 additional COL expected in 2009 (2 units)– 1 additional COL expected in 2009 (2 units)
– 3 signed EPC contracts (6 units)• Additional interest/potential opportunities in United
Ki d C d I di UAE S th Af i S thKingdom, Canada, India, UAE, South Africa, South America, Southeast Asia, Central/Eastern Europe
The Nuclear Renaissance has arrived!
The Demand for Nuclear Power
Bellefonte
North AnnaDominion1 ESBWR
Constellation1 EPRBellefonte
North AnnaDominion1 ESBWR
North AnnaDominion1 ESBWR
Constellation1 EPR
AP1000 in the USOutside map area:
Fermi – Detroit Edison – 1 ESBWRCallaway – Ameren – 1 EPR
North AnnaDominion1 ESBWR
Calvert CliffsDominion
1 EPRBellefonte
TVA/Southern Co.2 AP1000s
1 ESBWR1 EPRBellefonteTVA/Southern Co.
2 AP1000s
1 ESBWR1 ESBWR1 EPRNine Mile Pt – Unistar – 1 EPRBell Bend – PPL – 1 EPR
1 ESBWR
Amarillo
Comanche PeakLuminant
2 USAPWR
Lee NuclearDuke/Southern Co.
HarrisProgress Energy
2 AP1000s Lee Nuclear
Duke/Southern Co.
HarrisProgress Energy
2 AP1000s
AmarilloAmarillo Pwr
2 EPRs
2 USAPWRs
2 AP1000s
Riverbend
Grand GulfEntergy
1 ESBWR
VC SummerSCE&G/Santee Cooper
2 AP1000
Vogtle
2 AP1000s
RiverbendRiverbend
Grand GulfEntergy
1 ESBWR
Grand GulfEntergy
1 ESBWR
VC SummerSCE&G/Santee Cooper
2 AP1000
Vogtle
Victoria CountyExelon
2 ABWRs RiverbendEntergy
1 ESBWR
1 ESBWR VogtleSouthern Co./Co-owners
2 AP1000sLevy County
Progress Energy
South TexasNRG Energy, Inc.
.2 ABWRs
2 AP1000s
RiverbendEntergy
1 ESBWR
RiverbendEntergy
1 ESBWR
1 ESBWR1 ESBWR VogtleSouthern Co./Co-owners
2 AP1000sLevy County
Progress EnergyLevy County
Progress Energy
South TexasNRG Energy, Inc.
.2 ABWRs
2 AP1000s
2 ABWRs
Levy CountyProgress Energy
2 AP1000sTurkey Point
FPL
EPC
2 AP1000sEnergy demand growth is
concentrated in the Southeast
Best Solution for New Plants–Si lifi tiSimplification
Simplicity in:Simplicity in:• Design
• Safety• Safety
• Construction
• Procurement
• Operations
• Maintenance
Design SimplificationFewer ComponentsFewer Components(compared to current operating fleet)
F tFewer components.Less costly to build, operate and maintain
Construction SimplificationM d l i tiModularization
Typical Breakdown of AP1000 ModulesStructural Modules
Piping Modules
Mechanical Modules Total
Containment 41 20 12 73
Typical Breakdown of AP1000 Modules
Containment 41 20 12 73Auxiliary Building 42 34 29 105Turbine Building 29 45 14 88A B ildi 10 10Annex Building 10 10
Total 122 99 55 276
Modularization allows construction tasks that were traditionallyperformed in sequence to be completed in parallel.
Westinghouse Supply Chain ChallengeWestinghouse Supply Chain Challenge…
Transition from “Design” to “Delivery”
Pl S D liPlan Source Make Deliver
Optimizing the Supply Chain.Work with suppliers who provide exceptional products & services.
Westinghouse Forecasted PurchasesWestinghouse Forecasted Purchases
Major Components Electrical Mechanical*Steam Generator *Class 1E/Non-1E Batteries *Heat Exchangers*Reactor Vessel *Class 1E/Non-1E Battery Chargers *Condensers*Control Rod Drive Mechanism *FH System Underwater Camera Equipment *Cooling Fans*Containment Vessel *FH System Underwater Camera Lights *Gas Cooler*Reactor Coolant Pumps (RCP) *Fiber-Optic cable *Piping Penetrations*Refueling Machine *Transformers *Metal Reflective Insulation*Fuel Handling (FH) Machine *RCP Switchgear *Pumps*Polar Crane *Po er Cable *Filters/Filter S stems*Polar Crane *Power Cable *Filters/Filter Systems*RCP Variable Frequency Drives *Main Generation Circuit Breaker *Tanks*Cask Crane *Pressurizer Heater Assemblies *Demineralizers*Integrated Head Package *Distribution Panels *Ion Exchangers*Simulator *Inverters *Moisture Separators*Pressurizer *Battery Monitors *Screens*Passive Safety Heat Exchanger *Electrical Penetration Assemblies *Degasifier Column/SeparatorPassive Safety Heat Exchanger Electrical Penetration Assemblies Degasifier Column/Separator*Installation & Operation Tools *Special Tools*Shipping & Handling Fixtures
Fuel Instrumentation & Control Valves & Piping*New Fuel Jib Crane *Panels *Valves - 38 Valve Classifications*New Fuel Elevator & Hoist *Cabinets ASME Section III*New Fuel Elevator & Hoist *Cabinets -ASME Section III*Fuel Transfer Conveyor *Cabinet Enclosures -ASME B16.34*New Fuel Storage Racks *Instrumentation -Safety Related*Spent Fuel Storage Racks *Switches -Non-Safety Related*Fuel Transfer Tube *Pressure Gauges *Skimmers*Spent Fuel Shipping Casks *Elements *Strainers
*Controllers *Mechanical ConnectionsControllers Mechanical Connections*Transmitters *Mechanical Disconnects*Detectors *Safety Class Piping*Probes *Rupture Discs*Monitors *Pipe Support
Westinghouse Expectations from the Supply BaseWestinghouse Expectations from the Supply Base
• An unwavering commitment to quality and safety
C• Cost competitiveness
• Value the prevention of errors
• Own and proactively solve problems
• Aggressive and predictable in terms of delivery
• Able and willing to share in the risk for future business as demand grows
• Utilize lessons learned for continuous improvement
• Teamwork
SummarySummary• Westinghouse – 3 Core Competencies, Nuclear Power Plants, Nuclear
Services, Nuclear FuelServices, Nuclear Fuel
• AP1000, Best Solution for New Plants – Passive safety, simplification, fewer components, less costly to build, operate and maintain
• Modularization allows construction tasks that were traditionally performed in sequence to be completed in parallel
• Westinghouse is aggressively purchasing equipment components• Westinghouse is aggressively purchasing equipment, components, commodities and services
• Supplier expectations: quality, safety, cost, value the prevention of errors, own & proactively solve problems, delivery, share the risk, continuous improvement, teamwork
Bechtel:The First Name in Nuclear Power
2009
Snapshot of Bechtel TodaySnapshot of Bechtel TodayBechtel Group … One of the World’s Most Experienced Builders
110 years of experience
p p
y p
Over 40 offices worldwide—40,000 employees40,000 employees
Active on 390 projects in 46 countriescountries
Bechtel … Number 1 contractor E i i N R dper Engineering News-Record
(ENR )• Bechtel ranked # 1 since 1998Bechtel ranked # 1 since 1998
Commitment to Safety: Bechtel named
Nuclear InnovationsNuclear Innovations
Peach BottomFirst HTGR reactor
EBR-1
Fi t l First HTGR reactorFirst nuclear reactor
VallecitosGeneral Electric’s
A Historyof Firsts General Electric s
first BWRof Firsts
Turkey Point
NPDCanada’s first
CANDU
Humboldt Bay
First pressure suppression Turkey Point
First pre-stressed, post-tensioned concrete
containment
suppression containment
Nuclear InnovationsNuclear Innovations
Indian Point 3One piece
replacementreplacement
V. C. SummerLaser templating A History
of FirstsGen III—ALWRs
Licensing (COLs,R. E.
of FirstsLicensing (COLs,
ESPs)StandardizationModularization
Ginna
Through-dome
l
PalisadesTemporary containment
opening
replacement
Nuclear Industry’s Most Experienced Contractor
The leading U.S. EPC/CM contractor
Worldwide nuclear plant activities• 88% of the 104 U.S. plants• 150 worldwide
Extended power upratesSteam generator replacementsReactor vessel head replacementsReactor vessel head replacementsM&O contractor for U.S. national laboratoriesC bi d t ti d tiCombined construction and operating licensesEPC on new generation
Number 1 rankingOverall U.S. contractor by ENRBest in safety by Occupational Safety
Professional ResourcesProfessional Resources
20,000,employees with
nuclear experience
5,000engineers with nuclearengineers with nuclear
power experience
Nuclear—Market SegmentsNuclear—Market Segments
Operating Plant Major Modifications New Plant
ServicesMajor Modifications Generation
New GenerationNew Generation
TVA—BellefonteABWR cost study y
TVA—Watts Bar Unit 2DSEPCompletion
Bellefonte
Completion
Dominion—North AnnaSiting and constructability studiesESPCOL
Southern—VogtlegESPCOL supportSite-specific engineering
North Anna
Exelon—Texas site (Victoria County)COL
Vogtle
New GenerationNew Generation
AREVAEPR U.S. adaptationConstructability reviews
Constellation—Calvert CliffsESP COL Engineering
Calvert CliffsESP COL Engineering
UniStarBOP ConstructionConventional IslandConventional Island
South Carolina Electric & GasCOL Site-specific engineeringV.C. Summer
Florida Power & LightCOL Extended power uprates
GE/Hitachi ABWR DeploymentGE/Hitachi ABWR DeploymentSTP Nuclear Operating Company
• Siting • COLSouth Texas
Supply ChainSupply Chain
Global procurement andGlobal procurement andvendor relationships
$25 billion annual spending$ p g
All major global suppliers
Global Supply Network—Global Supply Networkvendor surveillance, expediting, logistics,
d Q lit C t land Quality Control
Supply ChainSupply Chain
What do we look for in our suppliers?suppliers?
• Similar Culture and Values
• Certainty of outcome…deliver as sold
– Quality
Val e– Value
– On Time
• Make our end product to theMake our end product to the ultimate customer better
Managing the Ri k f th NRisks of the New Nuclear Market
Frank LopezSenior Vice President of
International and Commercial Nuclear
CH2M HILL at a GlanceCH2M HILL at a Glance
• Headquartered in Denver, Colorado ENR Ranksq ,• More than 300 offices on six continents
in 41 countries worldwide
ENR Ranks
CH2M HILL#1
in Program Management for 5 consecutive years
• More than 25,000 employees• 100 percent employee owned and US SEC registered
B dl di ifi d 12 b i t• Broadly diversified across 12 business sectors• US$6 billion in revenue (2008)
CH2M HILL Nuclear Business Group Serves Four Market SegmentsServes Four Market Segments
• Nuclear New Build and Program Management– Program Management for new build– Siting, licensing, permitting of new nuclear power plants– Balance of plant, capital upgrades, program management/owner’s engineer for
existing power plantsexisting power plants
• Defense Nuclear Liabilities Management – Federal and non-federal traditional environmental management (D&D, waste
management, environmental restoration, etc)management, environmental restoration, etc)
• Nuclear Infrastructure Management – DOE NNSA/Science/Nuclear processing operations and maintenance, infrastructure
upgrades, process and facility engineering/design and facility EPC
• Nuclear Fuel Cycle Management and Civil Liabilities– Enrichment, fuel reprocessing – Spent nuclear fuel handling, storage and disposition
CH2M HILL’s Role in New Nuclearand Program Managementand Program Management
• Areva – Combined Operating p gLicense Application Support– Calvert Cliffs
Nine Mile Point– Nine Mile Point– Bell Bend
• Amarillo Nuclear Energy –Project Management Services Agreement
• Exelon Early Site Permit• Exelon Early Site Permit
CH2M HILL’s Role in New Nuclear and Program Management contProgram Management cont.
• ENEC (UAE) – Program Management to build a fleet of nuclear reactors in Abu Dhabi
• Shearon Harris (NC) – Combined Operating License Application for Progress Energy
• Levy County (FL) – Combined Operating License Application for Progress Energy
• ITER (France) – International fusion research plant( ) p• AECL (Canada) – Waste storage facility design• Toshiba (Japan) – Modular reactor design• British Government Embedded support for nuclear new build policy• British Government – Embedded support for nuclear new build policy
and procedure development
CH2M HILL Mega-Program Management ExperienceManagement Experience
Rocky Flats Closure Project, Colorado, USA
Thames Tideway Tunnel Project, United Kingdom
London 2012 Olympic & Paralympic Games, United
Kingdom
Panama Canal Widening,Republic of Panama
Masdar, UAE Deep Tunnel Sewage System and Changi Water Reclamation
Emirates Nuclear Energy Corporation, UAE
Water Reclamation Plant, Singapore
Challenges facing Nuclear New Buildg g
• Supply chain for large components• Supply chain for large components• Financing• Skilled laborSkilled labor• Public acceptance• Cost optimization Effective Program p• Schedule Management is
crucial to meet th h llthese challenges
Program Management Provides the F ame o k to AccomplishFramework to Accomplish:
• Integration / linkage of all projects within program• Integration / linkage of all projects within program• Alignment across the program to achieve efficient,
predictable and cost-effective, program delivery and operations
• Augmentation, integration and leverage of scarce talentOptimizing and integrating business technical• Optimizing and integrating business, technical, management, project delivery, and operations solutions
• Addressing internal and external factors, challenges, and g , g ,managing multiple activities
Fl N l PFluor Nuclear Power
Welcome to the Renaissance
P t d bPresented by Tom Dawson Procurement Manager gFluor Nuclear Power
FEBRUARY 18 2009FEBRUARY 18,2009
WHAT IS THE NUCLEAR RENAISSANCE ?
KING ELECTRICAL UTILITIES
QUEEN NSSS PROVIDERS
KNIGHTS IN SHINNING ARMOR EPC CONTRACTORS
THE CALVARY YOU THE SUPPLIERS
Who is FluorWho is Fluor Five business units who provide global EPC services for clients
Employees: 46,000+ (2,750 with nuclear experience)
Corporate HQ: Dallas, TX
N l P HQ G ill SCNuclear Power HQ: Greenville, SC
International Nuclear Power Office: Camberley, UKy,
Recent Annual Spend: $14 billion
Fluor Nuclear ServicesFluor Nuclear ServicesFluor has provided Nuclear Services for clients since 1946
During the 70’s and 80’s, Fluor constructed 10 nuclear power plants and supported completion of another 10 units. Our experiences include:include:
Reactor Design & Modification
Recent Non-Reactor Nuclear Design / Build
Self Perform Reactor Procurement & Construction
Reactor Operating Plant Support Services
Nuclear Facility Decommissioningy g
Fluor Nuclear Renaissance C it tCommitment
January 2007 re-established Fluor Nuclear Power to focus on the following markets:following markets:
Nuclear new build in U.S., UK and other (selective) global markets
Capital projects at operating nuclear plants
During 2007 we underwent ASME audits for regaining Nuclear Code Stamps and Nuclear Certificates
In February 2008 we received our Nuclear Code Stamps and Nuclear Certificates
Fluor Current Nuclear ProjectsFluor Current Nuclear Projects
Oconee Nuclear FacilityOconee Nuclear FacilityDuke Oconee – Plant Upgrades
Engineering, Procurement and Constructiong g,Procurement has started and will continue through 2010
South Texas Projectj
STPNOC Units 3 & 4Engineering Procurement and Construction of 2 x 1300 MWEngineering, Procurement and Construction of 2 x 1300 MW ABWR
Procurement has started and will continue through 2015
Fluor Supplier NeedsFluor Supplier Needs
Safety Related and Non-Safety Related suppliers are needed to support current projects
Needs include:eeds c udecivil /structural, mechanical and electrical constructionpermanent plant equipment and materials
Examples of 10CFR50 Appendix B safety related suppliers in short supply:
Structural /Civil materials - concrete fabricated rebarStructural /Civil materials - concrete, fabricated rebar, fabricated structural steel, grout, fire/explosion proof doors, etc.Electrical equipment and materialsq p
Fluor Strategic Supplier RelationshipsFluor Strategic Supplier RelationshipsSupplier Integration – The PEpC Process
Construction Industry
Institute (CII) indicates:
ENGINEERINGFLUOR
StrategicSuppliers
4%–8% cost savings
10% 15%pROCUREMENT
CONSTRUCTION
PROCUREMENT10%–15% savings in
time
The ability to influence the cost of a project is greatest at the beginning of a project – bringing strategic suppliers in early is essential to success
OverviewOverviewEXAMPLE
Schedule Specifications/Drawings
Return w/ Comments
CLIENTReview & Comment
Accepted
Develop Bidder List
CLIENTFor review and
comment within 10 daysSole Contractor
ContractorIssues RFQ
ContractorySole Source Tech./Comm.
Justification
ContractorReceives
ContractorPrepares Bid
Contractor prepares Equipment Purchase
ContractorIssues RFQ
Clarification/NegotiationBids
pEvaluation
q pApproval (EPA)
Contractor Executes Subcontractwith supplier
CLIENTExecutes EPA within 5 days
Clarification/Negotiation
with supplierExecutes EPA within 5 days
Bid EvaluationBid Evaluation•Commercial Evaluation
–Go/No Go Compliance with Terms and Conditions
–Cost–Schedule–Schedule–Experience–Financial Resources–Shop Loading (How Busy Are They?)p g ( y y )
Bid EvaluationBid Evaluation
•Technical Evaluation–Head-to-Head Comparison of BidsIdentify Evaluation Items–Identify Evaluation Items
–Rate Each Bidder on Evaluation Items–Evaluate Cost Adders/Subtractors–Supplier Questions and Clarificationspp Q–Determine Technically AcceptableBiddersBidders
Bid EvaluationBid Evaluation
•Final Evaluation–Compare Commercial and Technical EvaluationsEvaluations
–Combine Cost Adders/Subtractors With Commercial Cost Evaluation to DetermineCommercial Cost Evaluation to Determine Evaluated CostSelect Lowest Evaluated Cost–Select Lowest Evaluated Cost, Technically Acceptable Bidder
Bid EvaluationBid Evaluation•Award Subcontract/Purchase Order
–Clarification Meetings & Negotiations With Recommended Bidder
–Submit Recommendation With Backup to Client for Approval
–Submit Recommendation With Backup to Owner for Approval
l f f–Upon Approval, Conform Specification to Successful Bidder’s ProposalI S b t t/P h O d–Issue Subcontract/Purchase Order
Vendor Data ReviewVendor Data Review•Required Vendor Data Specified in Contract
b l d f•Submittal Requirements Form Identifies:What is Required
•Drawings Calculations•Drawings Calculations•Schedules Test Reports•Procedures Weld maps
When it is RequiredWhen it is Required•With bid 30 days after award•Design completion Prior to test Aft t t With hi t•After test With shipment
Its Purpose•For Review •For Approval •For Information
Vendor Data ReviewVendor Data Review
Vendor Timeline
rem
ent
ete
rd C
ontr
act
ove
Des
ign
ase
for P
rocu
r
catio
n C
ompl
e
n Fa
bric
atio
n
Com
plet
e
e at
Job
site
all
Design Idle Procure Mat’ls Fabricate Test Idle
Aw
ar
App
ro
Rel
ea
Fabr
i
Beg
i n
Test
C
Arr
ive
Inst
a
Vendor Data ReviewVendor Data Review• Fluor will establish secure area online for each
d ’ di t b itt l f d tvendor’s direct submittal of data• Data received electronically by Document Control
• Notifications sent to the following for review–Responsible Engineer (RE)–Quality (if safety-related) –Construction (as applicable)Startup (as applicable)–Startup (as applicable)
–Client (as requested)–Owner (as requested)Owner (as requested)–Others (as determined by RE)
Vendor Data ReviewVendor Data Review
•Submittal dispositioned by RE•Submittal dispositioned by RE–A AcceptedB Accepted with comments–B Accepted with comments
–C Not acceptable/ResubmitD Information Only–D Information Only
•Comments, if any, consolidated by RE and t d t d f l tireturned to vendor for resolution
Strategic RelationshipsStrategic Relationships
Fluor Supply Chain Agreements
Supplier Relationship Agreements (SRA)
Contractor Strategic Relationship Agreements (CSRA)(CSRA)
Becoming a Fluor Supplier/ContractorBecoming a Fluor Supplier/Contractor
Visit our booth
Pick up and complete the Nuclear Supplier Form
After completion return form via e-mail, fax or exhibit booth
Orest HrynewychOrest Hrynewych
Manufacturing Outreach Workshops
Chattanooga, TNFebruary 18, 2009y
Sargent & Lundy...
• More than 118 years of power industry leadership and experienceexperience
• 100% exclusive dedication to power industry
R t ti f i t tl idi hi h lit• Reputation for consistently providing high quality engineering services
• Extensive state-of-the-art technical resources (people• Extensive state of the art technical resources (people, tools, and processes)
• More than 2,650 staff resources
• Consistently ranked by Engineering News-Record as a top global power industry consultant
What we know for sure…..What we know for sure…..• We are and will be performing engineering and
d i i f l it f t l tdesign services for new nuclear units for at least the next 20 years.
• We are and will be preparing, evaluating, andWe are and will be preparing, evaluating, and recommending procurement of nuclear equipment, materials, and services for new nuclear units over this time periodnuclear units over this time period.
• Our information on manufacturing suppliers of equipment, materials, and services is limited.
• The South Eastern States are well positioned to supply the market.
South East is Well Positioned to S l th M k tSupply the Market
• Piping• Steel• Concrete• Cable• Instruments• Instruments• Pumps• Valves• Valves• Heat Exchangers
What Manufacturers Need to KKnow
• Three types or levels of equipment will beThree types or levels of equipment will be used in new nuclear plants– Safety relatedSafety related– Important to safety– Non-safety relatedNon safety related
• Manufacturing capabilities and qualifications must be robustqualifications must be robust…
Manufacturing RequirementsManufacturing Requirements
• Sargent & Lundy will issue procurementSargent & Lundy will issue procurement specifications requesting detail, accuracy, specific schedules, and hard commitments.
• Codes and standards requirements must be known and followed.
• AISC • ASTM• ANSI B31 1 • HEI• ANSI B31.1 • HEI• ASHRAE • IEEE• ASME Section III • ISA
• NFPA
ExamplesExamples
T• Piping (30-150 Miles)
Types• Nuclear Safety-Related
– ~60%
p g ( )
• Steel (500,000 Tons)
• Concrete (>3 M Cu Yards)60%
• Important to Safety– 10%
Yards)
• Cable (>1800 Miles)
• Instruments (>8,000)• Non-Safety Related
– 30%• Pumps (>1,000)
• Valves (15,000-24,000)• Heat Exchangers (<500)Heat Exchangers (<500)
• Hangers (10,000-15,000)• Containment Penetrations
(>250)(>250)
Requirements to Sell to the N l M k tNuclear Market
• Safety-Relatedy– N-Stamp– NQA-1 Program
NUPIC OK– NUPIC OK• Important to Safety
– NUPIC OK
Capacity to meet demandNUPIC OK
– Scaled down QA Program• Non-Safety Related
– Commercial Grade
Sargent & Lundy’s Expectations of M f tManufacturers
• Requested Design Information is• Requested Design Information is– Technically Correct
Complete– Complete– On Schedule
M f t ' St ff A il bl t S t• Manufacturer's Staff Available to Support– Engineering & Design– Installation – Testing & Startup
What Sargent & Lundy Will Do to A i t M f tAssist Manufacturers
• We will provide opportunities for lunch• We will provide opportunities for lunch and learn meetings to highlight your products and capabilities to our staffproducts and capabilities to our staff
• Sargent & Lundy will work with you for mutual successmutual success.
ConclusionConclusion
Get involvedGet involvedPrepare a PlanE t th Pl ith th d i i dExecute the Plan with the end in mind…Contact Sargent & Lundy when you are ready.
Sargent & Lundy55 East Monroe StreetChicago, IL 60603312-269-6630www.sargentlundy.com
The Shaw Group IncThe Shaw Group, Inc.Shaw Nuclear Services
Ed TerresDirector, AP1000 Nuclear Procurement (Domestic)
Corporate ProfileCorporate ProfileCorporate ProfileCorporate ProfileFounded in 1987, The Shaw Group Inc. provides premier engineering, design, construction maintenance fabrication and manufacturing services to private-construction, maintenance, fabrication and manufacturing services to private-sector and government clients in the energy, chemicals, power, nuclear, environmental, infrastructure and emergency response markets.
• Name: The Shaw Group Inc.• Headquarters: Baton Rouge, Louisiana• Public corporation: NYSE Symbol: SGR• 2007 Revenue: $5.7 Billion• Backlog: $14.0 Billion*• Number of employees: 27,000 • Web site www.shawgrp.com
* As of the three month period ending 11/30/07
Worldwide LocationsWorldwide Locations
138 U.S. Locations
33 International Locations33 International Locations
Shaw Power- NuclearShaw Power Nuclear• Full service engineering,
design, procurement and construction
• China State Nuclear Power Technology Company
Services Significant Customers
construction
• Configuration management
• Licensing support and safety analysis
• Duke• Southern• Entergy• SCANA• Exelon
• Major component replacement
• Operating plant services
• Exelon• Progress • LES - National Enrichment
Facility• Tennessee Valley Authority • Dominion
• Maintenance & modifications services
• Decontamination & decommissioning services
• Dominion• Entergy• TXU• KOPEC• Florida Power and Light
FENOC• Environmental services
• Spent fuel dry storage
• FENOC
AP1000 Consortium awarded 4- Nuclear reactors in China;
Nuclear new-build backlog over $$700 million
AP1000 Domestic O t iti
AP1000 Domestic O t iti
Westinghouse/ Shaw
OpportunitiesOpportunitiesWestinghouse/ Shaw Consortium furnishes AP1000 to domestic utilities• Conceptual design• Detailed engineering• Project management• Construction
management• Engineering and
design servicesdesign services• Site-specific
engineering
AP1000 Project Procurement T L dTeam Leaders
• VogtlegReggie Black – Project Procurement [email protected]
• VC SummerFred Stallings – Project Procurement [email protected]
• LevyMik V h P j t P t MMike Vaughn – Project Procurement [email protected]
Project StatusProject Status
• Standard Plant and Site Specific Engineering in ProgressStandard Plant and Site Specific Engineering in Progress• Vogtle and VC Summer Sites are Preparing to Mobilize to
Begin Site Development P t i S tti St t f P t f• Procurement is Setting Strategy for Procurement of Equipment and Commodity Items
• Request for Quotations for Multi-Project Agreements for j gIdentified Equipment is Underway
• Module Team In Place• Module Facility Under Construction• Module Facility Under Construction
Doing Business with Shaw lNuclear
• Need suppliers that can provide Balance of Plant and pp pConstruction Support Materials and Equipment
– Pumps (CCW, Condensate, Misc. Vertical, Misc. Horizontal)p ( , , , )– Mechanical Equipment (Heat Exchangers, Water Treatment)– Electrical Equipment (Switchgear, Bus Duct, MCCs, Panel
boards, etc.)– Site Subsurface (Piping, Storm Drains, Ductbank)– Civil Support ( Rebar, Structural Steel, Grating, Decking)– Bulk Commodities (Electrical & Mechanical)( )– Construction Support (Welding, Safety Supplies, Hand Tools)
Doing Business with Shaw lNuclear
• Perspective new suppliers need to complete Shaw Registration Form• Suppliers will be Qualified to meet needs based on schedule
• Key Attributes for Qualification Considerations
• Meeting quality & schedule requirements • Technical expertise and problem solving• Demonstrated financial strength • Strong Quality Program in accordance with industry norms• Strong Quality Program in accordance with industry norms• Adequate capacity to meet long term supply commitments • History of competitiveness in product group or market
• Contact Shaw Procurement representatives for more information regarding the projects in your area
Company Overview and Nuclear Credentialsand Nuclear Credentials
60 continuous years of nuclear engineering60 continuous years of nuclear engineering and construction services
URS Corporationp• Global leader in the engineering,
construction, management and servicesconstruction, management and services industries
• URS Corp. and Washington Group merged in November 2007merged in November 2007
• Fully integrated services to support the full project life cycle
• Projects in over 30 countries and all 50 states
• 56,000 employees56,000 employees• Corporate Headquarters—San Francisco,
California www.urscorp.com
Rankingsg• #449 -- Fortune 500
• #1 -- ENR’s List of the Top 500 Design Firms (8th consecutive year)• #1 -- ENR s List of the Top 500 Design Firms (8th consecutive year)
• #2 – ENR List of Power Design Firms
– #2 Nuclear
• #8 – ENR List of Power Contractors
– #5 Nuclear
– #2 Fossil
– #6 Transmission & Distribution
– #9 Fossil
– #4 Transmission & Distribution
– #3 Operations & Maintenance
• #3 -- Building Design & Construction’s Design/Construct List
N d O f A i ’ S f t C i b O ti l H d M i
– #6 Operations & Maintenance
• Named One of America’s Safest Companies by Occupational Hazards Magazine (Washington Division*)
• #12 -- ENR’s List of Top 100 Design-Build Firms
Revenue and Business MixExpected 2008 Revenues*:
$9.8 billionURS Corp FY2007 2Q08 Outlook $9.8 billion
Power Sector
URS Corp FY2007 2Q08 Outlook 2008
Revenue $5.4 B $4.79 B $9.8 B
O ti $311 2 $250 3 M Sector21%Industrial &
Commercial26%
Oil & Gas
Operating Income
$311.2 M
$250.3 M
Net Income $132.2 M
$108.8 M $197 –207 M
Federal Sector35%Infrastructure
18%
Oil & Gas9%
M 207 M
Shareholder Equity
$3.5 B $3.5 B
Book of $30 B $30 7 B 18%Book of Business
$30 B $30.7 B
* Based on midpoint of guidance range for sector revenues.
A Rich Nuclear Heritage CompanyE
N
GINEERS
B
UILDER
S
Strategic Acquisitions for Growth
$ 10.0
Washington Group International Construction, Power, DOE
$9 8(1)
$ 7.0
$ 8.0
$ 9.0
Bn)
Commercial / Industrial
PM/CM, Transit, Private Sector, International
F d l O&M
$9.8(1)
$ 4.0
$ 5.0
$ 6.0
Rev
enue
s, $
B
Infrastructure/
Transportation
Federal O&M
$3 2 $3.4$3.5 $4.2
$5.4
$0.1 $0.3$ 1.0
$ 2.0
$ 3.0
( Public Sector
$0.4 $0.8$1.4
$2.2 $2.3 $2.4$3.2
1. Expected revenue (approximate) for FY 2008.
$ 0.01990 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
Major MarketsPower Federal
FacilityStart-up
Construction &
Decommissioning &
Operations &Technical
C ltiPlanning, Design &
ProjectD l t
ProgramM t Start-upConstruction
Management&
Closure
Industrial & Commercial Infrastructure
MaintenanceConsulting Design & Engineering
Development Management
Industrial & Commercial Infrastructure
Nuclear Capabilitiesp• Integrated full service capability• 7000+ nuclear professionals• 7000+ nuclear professionals• World’s largest nuclear safety / licensing consulting firm − WSMS
– 500 criticality, risk assessment, security, fire protection, emergency planning analystsanalysts
• Support to OEMs for certification of new advanced reactor designsM i t i d l t ti bilit• Maintained nuclear construction capability– Major Modifications / maintenance – Construction of DOE nuclear facilities; recent large projects − Hanford WTP,
INL IWTUINL IWTU– First new commercial nuclear construction under new licensing guidelines– Best Practices review of Japanese projects; relationships with Hitachi and MHI
Nuclear Capabilities Cont.Nuclear Capabilities Cont.
• Big project planning and execution over the past 20 years– Performed 45 nuclear plant outages– Performed over 300M workhours on mods and maint– Completed 15 refueling outages of less than 30 days
• Continuing to build major program portfolio − 2008 awards– Hanford waste tank remediation– M&O of the UK’s low level waste repository in West Cumbriap y– Selected for management of nuclear cleanup at the UK’s
Sellafield complex– M&O of Yucca Mountain– Savannah River Site Liquid Waste Management
Power Business Unit Designed and / or constructed
250 000 MW worldwide
Europe
250,000 MW worldwide
North America184,100 MW
Middle East /
Asia / Pacific37,000 MW
8,000 MW
Middle East / Africa
2,400 MWLatin America20,600 MW
Every region of the world
Every segment of the life cycle
Every major nuclear or
fossil technology cyclefossil technology
Commercial Nuclear Experiencep
• Engineer of Record 38 unitsConstructor of Record 23 units• Constructor of Record 23 units
• Engineering Modifications 100 units• Maintenance 56 units
Pl t S t S i 79 it• Plant Support Services 79 units• QA 109 units• Licensing Support 58 units
SGR 20 it l t d• SGRs 20 units completed, 3 units backlog
• RPV Head Replacements 8 units completed, 1 unit backlogFi t l f iliti i It l J M i S it l d B il S i• First nuclear facilities in Italy, Japan, Mexico, Switzerland, Brazil, Spain, and Taiwan
Proven Safety Performance
2004 2005 2006 2007Days Away from Work Rate 0 1 0 1 0 1 0 1
y
Washington Division training program has certified 1,500
Washington Division
Days Away from Work Rate 0.1 0.1 0.1 0.1Medical Recordable Rate 0.7 0.6 0.7 0.5Total Recordable Cases Rate 1.1 1.0 1.1 0.9EMR 0.68 0.68 0.65 0.68Direct Hire Exposure Hours57,596,41952,693,61452,832,61454,274,471
program has certified 1,500 managers/supervisors
Exceeded the U.S. Nuclear Industry Lost Time Rate of 0.4 in 2006 by achievinga company-wide rate of 0.1 for over 52 million work hours
First ever alliance between an engineering and construction
company and OSHAPower Business Unit
2004 2005 2006 20072004 2005 2006 2007Days Away from Work Rate 0.14 0.03 0.18 0.02Medical Recordable Rate 0.87 0.7 1.2 0.61Total Recordable Cases Rate 1.17 0.76 1.46 0.64EMR 0.68 0.68 0.65 0.65
Voted one of America’s 17 safest
Port Washington Generating Station earned OSHA VPP Star status in August 2007OSHA Corporate Pilot Program VPP Star status awarded to Washington Division in August 2006
Direct Hire Exposure Hours10,113,0237,610,051 7,828,373 8,497,463
Voted one of America’s 17 safest companies –
“Occupational Hazards” magazine
awarded to Washington Division in August 20065th Company inducted into program / First E&C Company
—Georgia Pacific, International Paper, U.S. Postal Service, Dow Chemical
PowerMajor MarketsMajor Markets
New Generation• Coal-fired power plants
Conventional• Clean air retrofits
— Sulfur oxides nitrous• Fossil and Nuclear• Transmission & Distribution
Modification Services Technical Services
– Conventional– Circulating fluidized bed– Gasification (IGCC)
• Combustion turbine plantsC bi d l
— Sulfur oxides, nitrous oxides, particulates, mercury
• Modifications• Maintenance
• Transmission & Distribution• Studies• Licensing• Consulting• Engineering– Combined cycle
– Simple cycle• Nuclear
– Boiling Water
• Component replacement— Steam generators— Pressurizers— Reactor vessel heads
g ee g• Construction Management• Utility Management• Outsourcing / Seconding
– Pressurized Water
URS Nuclear Center – Commitment to the Nuclear IndustryNuclear Industry
• Dedicated full scope nuclear project execution
• Fort Mill, SC—21 miles from Charlotte, NC• Proximate to URS resources:
– Energy & Environment base in Aiken, SCgy ,– Washington Safety Management
Solutions, Washington Energy Center in Aiken, SC
– SGT base in Charlotte, NC– 7000 in-house nuclear trained
professionalsA l i h i
URS Nuclear Center Established March 2008
• A nuclear-rich region– Universities, OEMs, utilities, E&C firms
Manufacturing & Services OpportunitiesOpportunities
Need capable qualified suppliers of both safety• Need capable, qualified suppliers of both safety and non-safety related nuclear power plant equipment material and servicesequipment, material and services
• Meet applicable codes and standards or working toward becoming qualifiedtoward becoming qualified– Regulatory Guides and/or ASME, IEEE, ANSI,
ASNI ACI etcASNI, ACI, etc.
Sample of Equipment & Service O t itiOpportunities
St t l St l S it h• Structural Steel Manufacturers
• Pipe Fabricators
• Switchgear• Motor Control Centers• Panel ManufacturersPipe Fabricators
• Valve & Operator Manufacturers
• Panel Manufacturers• Diesel Generator
Manufacturers• Fire Protection/Detection
Services• Testing Laboratories
• Radwaste Systems ManufacturersS li S t• Testing Laboratories
• Containment Liner – Design, Fabricate, Install
• Sampling Systems Manufacturers
• Instrument & ControlDesign, Fabricate, Install• Cable Manufacturers
– Power, Control, Fiber
Instrument & Control Manufacturers
• Heat Exchanger M f
How do I become a supplier?How do I become a supplier?
• Visit www.urscorp.com and click on Washington s t u sco p co a d c c o as gtoDivision
• Fill out the information as completely as possible• Important qualifications:
– Previous experience– Quality assurance compliance requirementsQuality assurance compliance requirements– Safety Record– Financial Stability– Ability to meet Corporate/Project Insurance Requirements– Ability to meet Corporate/Project Insurance Requirements– Availability and Reliance of Supply– Small Business Concern Program, if applicable
Nuclear ComponentsComponents
Supplier Pe specti ePerspective
Babcock & WilcoxNuclear Operations GroupNuclear Operations Group
M.T. Childerson
Presentation TopicsPresentation Topics
• B&W Experience• B&W Experience• Quality Assurance Organization
I t f L d hi• Importance of Leadership• Culture of Quality• Keys to Success
What Does It Take to be Successful in the Nuclear Industry?What Does It Take to be Successful in the Nuclear Industry?
B&W ExperienceB&W Experience
• 1940’s – 1950’s: Research• 1940 s 1950 s: Research Projects
• 1960’s 2000’s major supplier of• 1960 s-2000 s major supplier of reactor equipment and steam generatorsgenerators
• Supplied industry with over 1300 l h ll d1300 large, heavy-walled vessels
B&W Has A Solid Perspective of What It Takes to be Successful.
Quality Assurance OrganizationQuality Assurance Organization
• Independent from, and p ,have equal authority to design and gmanufacturing
• Quality Manual DrivenQuality Manual Driven• Independent authorized
nuclear inspectionnuclear inspection agency approval of QM
Quality Manual converts requirements into your quality system.
Importance of LeadershipImportance of Leadership
• Effective leadership is essential to assure• Effective leadership is essential to assure the mission is always known, understood, embraced and accomplishedembraced, and accomplished
• Leadership BehaviorsD h t i i ht– Do what is right
– Relentless pursuit of excellenceh f ll bl– Recognize humans are fallible
– Value diversity of thought
Importance of LeadershipImportance of Leadership
• Leadership Behaviors (cont’d)• Leadership Behaviors (cont d)– Encourage identification of weaknesses
Nurture a culture open to oversight and– Nurture a culture open to oversight and critique
– Place high value on training and development– Place high value on training and development– Intolerant of behavioral choices that do not
comply with requirementscomply with requirements
Importance of LeadershipImportance of Leadership
• Leadership Behaviors (cont’d)• Leadership Behaviors (cont d)– Do not tolerate normalization of deviation
Exhibit and demand highest level of integrity– Exhibit and demand highest level of integrity in word and action
Proper Execution and Management of Activities Depend onProper Execution and Management of Activities Depend on Leadership
Culture of QualityCulture of Quality
• Quality must be at the forefront of all• Quality must be at the forefront of all activities and decisions
• Encourage and accept a questioning• Encourage and accept a questioning attitude and open communicationN f f i l• No fear of reprisal
Quality focus integrated into all activities, every minute, every day.
PeoplePeople
• Skilled craftsman and engineering g gprofessionals harder to find
• Strong and extensive trainingStrong and extensive training program required
• Personal ownership• Personal ownership• Quality concerns promptly
investigated quickly and formallyinvestigated, quickly and formally addressed
Staffing to support nuclear QA system is a significant challenge.
Keys to SuccessKeys to Success
• Solid understanding of the requirements• Solid understanding of the requirements• Investment in human capital
O f i ti• Openness of communications• Human Performance Improvement
Techniques (Institute of Nuclear Power Operations)
Consider using Human Performance Improvement TechniquesConsider using Human Performance Improvement Techniques
ClosingClosing
• Take advantage of the• Take advantage of the opportunities in the nuclear industry renaissanceindustry renaissance
• Commit to developing the systems and staffsystems and staff
• Your leadership team and l t b itt demployees must be committed
for the long term
You can control your success as a quality nuclear supplier!
Quality Assurance R i t dRequirements and Breakout Sessions
James Fisicaro, NEIFebruary 18, 2009
Purpose of PresentationPurpose of Presentation
• Customer Requirements and ComponentCustomer Requirements and Component Categories
• Typical ExamplesTypical Examples • Describe Breakout Sessions
Customer Requirements and C C iComponent Categories
• Customer provides requirements in• Customer provides requirements in purchase order
• Two types of Components• Two types of Components– Safety Related– Non-Safety Related y
• Supplemented Quality Requirements• Commercial
• Refer to Fact Sheet for Definitions• Refer to Fact Sheet for Definitions
Typical ExamplesTypical Examples
• Safety RelatedSafety Related – Reactor Vessel, Pressurizer, Primary Piping,
– Class 1E emergency ac power (Emergency Diesel Generator)
– Seismic Design Class I
• Non Safety Related – Turbine
– Condenser Cooling Water
– LightingLighting
Typical ExamplesTypical Examples
• Non-Safety-Related, Significant Contributor to Plant y , gSafety – Associated with passive plant design:
Ch i l d l t l t• Chemical and volume control system• Normal residual heat removal system• Backup feedwater system.p y
• Non-Safety-Related, Radioactive Waste – Liquid Radioactive Waste System– Gaseous Radioactive Waste System– Solid Radioactive Waste System
Typical Examples and iRequirements
• Non-Safety-Related, Credited for Regulated Events (Augmented Quality)– Fire Protection
• Fire water pumps, fire main piping system, fire detection p p , p p g y ,
– ATWS (Anticipated transients w/o SCRAM) • PWR: Sensor output to final actuation device• BWR: Alternate Rod Injection (ARI), Standby liquid control system (SLCS)j ( ), y q y ( )• Diverse SCRAM system
– SBO (Station Blackout) • Alternate Battery Systems, Alternative off-site AC power sourcesy y , p
DOE/DOD/NRC DifferencesDOE/DOD/NRC Differences
• DOE/DOD requirements are different than• DOE/DOD requirements are different than NRC requirements.
• ISO QA Programs don’t address all NRC• ISO QA Programs don t address all NRC requirements
Breakout SessionsBreakout Sessions
• Two breakouts• Two breakouts– Safety Related and Non Safety Related
(Supplemented Quality Requirements)(Supplemented Quality Requirements)– Non Safety Related (Commercial)
• Breakouts will repeat twice• Breakouts will repeat twice• Logistics
NEI Vendor Outreach Breakout
Commercial Materials, ,Parts, and Services
Marc H Tannenbaum Electric Power Research InstituteMarc H. Tannenbaum – Electric Power Research Institute
Chattanooga, TennesseeFebruary 18 2009February 18, 2009
Commercial Materials, Parts, and ServicesServices
• Opening Comments– Marc Tannenbaum, Electric Power Research ,
Institute
• Overview of Industry ExpectationsLarry Davenport Tennessee Valley Authority– Larry Davenport, Tennessee Valley Authority
• A Local Vendor’s Perspectives– Dan Anderson, Diversified Supply Company
• Engineer, Procure & Construct (EPC) P iPerspectives– Danny Leigh, Fluor
Closing Remarks• Closing Remarks
Commercial Supplier Expectations in the
Nuclear Power IndustryNuclear Power Industry
NEI Vendor Outreach – Chattanooga, TNFebruary 18, 2009
Marc Tannenbaum, EPRI,Project Manager
Licensee Procurement Basics –Safety Class
Safety Related
Safety Class
Two basic
Nonsafety
Two basic safety classifications
. . . Those structures, systems and components that are relied upon to
remain functional during and following design basis events to assure:
(1) The integrity of the reactor coolantRelated classifications exist for Licensees:
(1) The integrity of the reactor coolant pressure boundary
(2) The capability to shut down the reactor and maintain it in a safe shutdown
condition; or
(3) The capability to prevent or mitigate the consequences of accidents which couldconsequences of accidents which could
result in potential offsite exposures
(Ref. 10CFR50.2)Plant equipment that is not Safety Related
May include equipment that is subject to specific regulatory requirements or p g y qcommitments (Augmented Quality)
Who are our suppliers?
Our suppliers fall into 2 main groups• Safety Related or “Nuclear” suppliers
– Engineer, Procure, Construct Firms (EPCs)– Nuclear Steam Supply System Firms (NSSSs)Nuclear Steam Supply System Firms (NSSSs)– Original Equipment Manufacturers (OEMs)– Original Equipment Suppliers (OESs)– Distributors– Third Party Qualifiers
• Nonsafety Related or “Commercial” suppliers• Nonsafety Related or Commercial suppliers– Original Equipment Manufacturers (OEMs)– Original Equipment Suppliers (OESs)– Distributors
Commercial Nuclear Generation SuppliersGeneration SuppliersAEs
NSSS’sOEMsOESs
OEMsOESs
AEs OEMs
NSSS s Distributors Distributors
EPCsAEs
NSSS’s OESsDistributors
Commercial Nuclear FacilitiesCommercial Nuclear Facilities
Design Construction Operations
Expectations for Safety-Related (Nuclear) Suppliers(Nuclear) Suppliers
• Maintain an approved nuclear quality assurance program• Standard commercial considerations• Charge a fair price for goods and services
Read the p chase o de ca ef ll e e time• Read the purchase order carefully every time– Focus on the technical requirements– Communicate any discrepancies before shipping– Provide accurate delivery estimates– Communicate when things change
• Always provide high quality products• Always provide high-quality products• Be aware of substandard, counterfeit and fraudulent
items
Expectations for Non Safety-Related (Commercial) SuppliersRelated (Commercial) Suppliers• Ensure the quality of items provided
St d d i l id ti• Standard commercial considerations• Charge a fair price for goods and services
Re d the p h e o de ef ll e e time• Read the purchase order carefully every time– Focus on the technical requirements– Communicate any discrepancies before shippingCommunicate any discrepancies before shipping– Provide accurate delivery estimates– Communicate when things change
• Provide a high-quality product• Be aware of substandard, counterfeit and
fraudulent itemsfraudulent items
Historical Substandard, Counterfeit and Fraudulent Item Concerns in the US Nuclear
Power Industry
Fasteners Piping
Circuit Breakers MCCBsWorm GearsPumps
Tubing FlangesValves
Worm Gears
Pipe Fittings
1E Components Anti Rotation Keys
Pipe Fittings
Structural SteelFire Protection Equipment
SealantsRelays
Fire Protection Equipment
Preventing Substandard, Counterfeit and Fraudulent Items
• Stay current• Stay current– Monitor counterfeiting news– Participate in related industry committees / p y
organizations – Maintain a list of your suppliers– Maintain a list of sub-tier suppliers for importantMaintain a list of sub tier suppliers for important
parts– Report and pursue known or suspected
counterfeitingcounterfeiting
Preventing Substandard, Counterfeit and Fraudulent Items
Implement Robust Procurement Controls
Fraudulent Items
• Implement Robust Procurement Controls – Trust but verify– Perform vigilant receipt inspectionsPerform vigilant receipt inspections– Guard Intellectual Property– Communicate and maintain a relationship with
your OEMsyour OEMs• Be aware of approved distribution chains
– Question your supplier’s design control and et n poli iereturn policies
Non-Quality Materials & ServicesMaterials & Services
Utility ExpectationsUtility Expectations
Larry Davenport - TVAFebruary 18, 2008
What does the utility expect?What does the utility expect?
• High Quality Productsg Q y• Experienced and Qualified Service Personnel • Competitive Pricing for Comparable Goods
O S h d l D li• On Schedule Delivery• Complete Compliance with Contract/PO Terms • Clear Accurate and Timely Communication• Clear, Accurate and Timely Communication• Zero Defects• EPC contractor emulates the client’sEPC contractor emulates the client s
expectations for Quality and Cost of procured items
High Quality ProductsHigh Quality Products
• The PO Specification and Technical Notes• The PO Specification and Technical Notes will describe the item or service.
• Read the Request for Proposal/Quote• Read the Request for Proposal/Quote (RFP/RFQ) carefullyQ t li ti d li h d l th t• Quote realistic delivery schedule that allows appropriate time for a quality
d tproduct
Experienced and Qualified P lPersonnel
• Ensure your engineers and technicians are• Ensure your engineers and technicians are trained and qualified to perform the activities requested by the purchaseractivities requested by the purchaser– All requirements will be delineated in the RFP
Proof of training/certification will be required– Proof of training/certification will be required– Safety for your employees and ours is
ParamountParamount
Competitive Pricing for C bl G d S iComparable Goods or Services
• Most utilities compete by bid process• Most utilities compete by bid process• Suppliers must read and understand all
commercial and technical requirements ofcommercial and technical requirements of the RFP/RFQWh i d bt f i t• When in doubt of any requirement, immediately contact the buyer, agent or
t t t t l ifi ticontract manager to get clarification.
On Schedule DeliveryOn Schedule Delivery
• RFP/RFQ will typically state a required• RFP/RFQ will typically state a required delivery date, but may request bidder to quote best deliveryquote best delivery
C t ti f N N l Pl t• Construction of New Nuclear Plants are based on complex schedules, dependant
t t i l d li f tupon accurate materials delivery forecasts
Contract ComplianceContract Compliance• Understanding of and strict compliance with all
terms and conditions of the PO or contract is expected
• Your personnel and any subcontractors you employ must also understand and comply with th t d ditithe terms and conditions
• “Overcommunicate” with the customer and your li t b th ti lsuppliers to ensure both parties always
understand contract/PO status
Clear Accurate & Timely C i tiCommunication
Communication is the critical link in the supply chain that will make or break a projectthat will make or break a project
• From Receipt of RFP/RFQ until last invoice is paid, both the customer and the supplier must maintain open and honest channels of communicationsupplier must maintain open and honest channels of communication
• Only Procurement can revise a contract or PO
• Changes to contracts and POs must be made by formal revision
• Any change must be approved in writing by the authorized Procurement Agent y g pp g y g(Buyer or Contract Manager)
Zero DefectsZero Defects
• Your Goal is to deliver a defect-free product in a timely manner
• “Measure Twice, Cut Once”
• Your expectations of your suppliers are the h h fsame as the purchaser expects of you
NEI Vendor Outreach Breakout
Supplying Commercial Materials, Parts, and Services
Dan Anderson Diversified Supply IncorporatedDan Anderson – Diversified Supply, Incorporated
Chattanooga, TennesseeFebruary 18 2009February 18, 2009
TYPICAL TYPES OF ORDERS AND S C Q STHEIR BASIC REQUIREMENTS
• Commercial standards apply• Commercial standards apply.
• Safety-related. Nuclear certification. Customer deals directly with manufacturer.Customer deals directly with manufacturer.Traceability from the point of manufacture.
• Safety-related. Nuclear certification.yTraceability from shipping point.
• Quality-related. Minor documentation may be required such as shelf life/date code information.
STANDARDS OF NUCLEAR SUPPLY
• Understand and communicate requirementsq
• Develop a diverse base of products and manufacturersmanufacturers
• Maintain document control/product traceability
• Verify material conformity to QA level requirements
• Provide 24/7 service to accommodate emergency needs
SAFETY AND SECURITYO i O Si S l W hOperating an On-Site Supply Warehouse
• Controlled access to materialsControlled access to materials
• Cooperation with site security and• Cooperation with site security and surveillance
• Adherence to site safety guidelines
CHALLENGES• Servicing multiple customers per site• Meeting expedited delivery• Meeting expedited delivery
requirements on special needs productsproducts
• Strict standards for product uniformity and documentationand documentation
• Tracking down hard-to-find products• Supporting Plant Outages• Supporting Plant Outages
REWARDSREWARDS
• Expanding customer base• Expanding customer base
O t iti f li f di t ib ti• Opportunities for new lines of distribution
• $$$
Non Safety Material, Items, &Material, Items, & Services Procured
b EPCby EPC
Shift from Safety Related to Reliability RelatedyDanny Leigh - Fluor
EPC and their RoleEPC and their Role
• Each License invokes specific requirements for ac ce se o es spec c equ e e ts onon-safety critical activities on the EPC
• Procurement documents for items and services d b h EPC ill i l d fprocured by the EPC will include or reference
documents describing applicable design bases, design requirements, and other requirementsdesign requirements, and other requirements necessary to ensure component performance
• Specific commercial, technical, and quality requirements are applied to non-safety related items.
General Vendor Considerations
• Components – Form Fit Function – Will• Components Form, Fit, Function Will be invoked by EPC
• Reliability focus• Reliability focus• Design – Will be required to support
d i b i f f t it tili ddesign basis for non-safety items utilized in non-safety systems.
General Vendor ConsiderationsC ti dContinued
• A new or separate QA program is not required, p Q p g q ,the supplier’s procedures describing the quality controls applied to the subject equipment, and will be subject to verification by the EPC Qualitywill be subject to verification by the EPC Quality or Engineering organizations
• Supplier history and performance will be key focus areas EPC will utilize industry operatingfocus areas. EPC will utilize industry operating experience (OE) from license during the selection of qualified supplier
h C Q l h• May have EPC Quality or Engineering oversight during fabrication and testing of Non-safety items
General Vendor ConsiderationsC l d dConcluded
• Material – Substandard Fraudulent• Material Substandard Fraudulent Controls – Will be invoked by EPC
• EPC may invoke selected QA process t l t b i l t d b thcontrols to be implemented by the
Supplier. Specific Quality processes h ld b id tifi d i th EPC hshould be identified in the EPC purchase
documents.
Commercial Materials, Parts, and Services – Closing RemarksServices – Closing Remarks
• QuestionsQuestions
• Where to go for help?• Where to go for help?– EPC Firms– NEINEI– EPRI
• Closing Remarks– Marc Tannenbaum
1
NEI Vendor Outreach Breakout (Materials Parts and Services(Materials, Parts, and Services
required by a QA Program) James Fisicaro - NEI
Chattanooga, Tenn.
February 18, 2009y ,
Breakout Number 1Breakout Number 1
Opening Comments – Jim Fisicaro (NEI)Opening Comments – Jim Fisicaro (NEI)
Overview of NRC Regulation and
Requirements – Tom Niessen (TVA)
EPC and their Role – TV Sarma (Bechtel)
– EPC and their role
– How to attain an ASME stampHow to attain an ASME stamp
– How to operate under a Vendor’s QA
Breakout Number 1 (cont)Breakout Number 1 (cont)
How to Operate under a Vendor’s QA Program How to Operate under a Vendor s QA Program
– Curtiss-Wright Flow Control Company –EES
G W l ki – Gary Wolski
– What to look for when a vendor provides a
h d purchase order to you.
Where to go for help? Jim Fisicaro
Closing Remarks – Jim Fisicaro
3
Quality Assurance PProgram
Requirementsq
Thomas Niessen, TVAFebruary 18, 2008
Purpose of PresentationPurpose of Presentation
• Regulatory environmentRegulatory environment • Quality assurance role • Basic QA requirements• Basic QA requirements • Component classifications and vendor types• Quality assurance requirements for vendors• Quality assurance requirements for vendors • Next steps and where do you go for help
Regulatory EnvironmentRegulatory Environment
• The NRC Commissioners set policy, direction, e C Co ss o e s set po cy, d ect o ,and approve new regulations.
• Code of Federal Regulations contain i h b (10CFR 50requirements that must be met (10CFR 50
Appendix B). • The nuclear industry operates in a regulated• The nuclear industry operates in a regulated
environment.• The Nuclear Regulatory Commission (NRC)The Nuclear Regulatory Commission (NRC)
provides regulatory oversight of the nuclear industry.
Regulatory Environment (cont)Regulatory Environment (cont)
• NRC• NRC– Washington office approves license
amendments applications etcamendments, applications, etc.– Regional inspectors perform site inspections.– Resident inspectors on current operating sites– Resident inspectors on current operating sites
to provide continuous inspection oversight. – Plans to have at least five full time residentPlans to have at least five full time resident
inspectors at each new nuclear site.
Regulatory Environment ( )(cont.)
• Licenseece see– NRC rules and requirements for almost all activities– NRC provides continuous oversight – NRC may impose fines or penalties for rule violations
• Engineering, Procurement, and Construction (EPC) vendors(EPC) vendors – required to follow rules per procurement contracts
with Licensees.• Reactor designers
– required to follow rules per procurement contracts with Licenseeswith Licensees.
Customer Requirements and d C iVendor Categories
• Customer provides requirements in• Customer provides requirements in purchase order
• Vendors are classified related to the• Vendors are classified related to the Systems, Structures and Components (SSC) provided(SSC) provided.– Safety Related
N S f t R l t d– Non-Safety Related.
Component CategoriesComponent Categories
• Safety Relatedy– ASME NQA-1 and ASME Section III– Dedicated Commercial Grade Items (CGI)
• Non-Safety Related – Supplemented Quality Requirements
• Non-Safety-Related Significant Contributor to Plant Safety• Non-Safety-Related, Significant Contributor to Plant Safety• Non-Safety-Related, Radioactive Waste• Non-Safety-Related, Credited for Regulated Events
(A t d Q lit )(Augmented Quality)
– Commercial Items (no dedication)
Safety Related DefinitionSafety Related Definition
Safety-related (10 CFR Part 50.2) y ( )• This term applies to structures, systems, components,
procedures, and controls of a facility or process that are li d i f i l d i d f ll irelied upon to remain functional during and following
design basis events to assure:– (1) The integrity of the reactor coolant pressure boundary(1) The integrity of the reactor coolant pressure boundary– (2) The capability to shut down the reactor and maintain it in
a safe shutdown condition; or(3) h b l h f– (3) The capability to prevent or mitigate the consequences of accidents which could result in potential significant offsite exposures.
Typical Examples and iRequirements
• Safety Related (NRC Reg. Guide 1.26)Safety Related (NRC Reg. Guide 1.26)– Reactor Vessel, Pressurizer, Primary Piping,
– Class 1E emergency ac power (Emergency Diesel Generator)
– Seismic Design Class I
• Non Safety Related – Turbine
– Condenser Cooling Water
– LightingLighting
Typical Examples and iRequirements
• Non-Safety-Related, Significant Contributor to Plant y , gSafety ( NRC SECY 95-132)– Associated with passive plant design:
Ch i l d l t l t• Chemical and volume control system• Normal residual heat removal system• Backup feedwater system.p y
• Non-Safety-Related, Radioactive Waste (NRC Reg. Guide 1.143)– Liquid Radioactive Waste System– Gaseous Radioactive Waste System– Solid Radioactive Waste SystemSolid Radioactive Waste System
Typical Examples and iRequirements
• Non-Safety-Related, Credited for Regulated Events (Augmented Quality) ( NUREG 0800-SRP-17.5)– Fire Protection ( 10 CFR 50.48) (NRC Reg. Guide 1.189)
• Fire water pumps, fire main piping system, fire detection p p , p p g y ,
– ATWS (Anticipated transients w/o SCRAM) (10 CFR 50.62) (NRC Generic Ltr. 85-06)
• BWR: Alternate Rod Injection (ARI), Standby liquid control system (SLCS)a od j o ( ), a dby qu d o o y ( )• PWR: Sensor output to final actuation device,• Diverse SCRAM system
– SBO (Station Blackout) (10 CFR 50.63) (NRC Reg. Guide 1.155)( ) ( ) ( g )• Alternate Battery Systems, Alternative off-site AC power sources
Typical Examples and iRequirements
• ASME Section III endorsed by 10 CFR 50.55aASME Section III endorsed by 10 CFR 50.55a– S/R Vessels and Piping (NCA-4000)– Material Supplier (NCA-3800 or 3900)pp ( )
• Dedicated CGI – Commercial Grade Item (10CFR Part 21)o a ad ( 0 a )
• Not design or manufactured as a basic component– Basic Component-designed and manufactured under a
nuclear QA programnuclear QA program
• Acceptance process for item’s critical characteristics
Quality Assurance Program iRequirements
• Requirements flow down from COL• Requirements flow down from COL applicant through vendors and sub vendorsvendors– 10 CFR Part 21
10 CFR Part 50 55e– 10 CFR Part 50.55e– QA Requirements as specified in Purchase
documentdocument
QA ProgramQA Program
• Written QA program that covers 10 CFR Part 50, Appendix B and p g ppNQA-1-1994.
• Criterion IV to Part 50 and Requirement 4 NQA-1
P t 50 i t– Part 50 requirement
• To the extent necessary procurement documents shall require suppliers to have a quality assurance program gconsistent with the applicable requirements of this appendix
– NQA-1
i il di• similar wording
• Vendors exist that can help with development of QA Programs
DOE/DOD/NRC DifferencesDOE/DOD/NRC Differences
• DOE/DOD requirements are different than NRCDOE/DOD requirements are different than NRC requirements.
• DOE and nuclear industry uses NQA-1DOE and nuclear industry uses NQA 1• No Part 21 reporting, unless NRC regulates• NRC Requires a Program that implementsNRC Requires a Program that implements
10CFR50 Appendix B• ISO Programs don’t meet NRC RequirementsISO Programs don t meet NRC Requirements
AuditingAuditing
• Owner– Surveys or qualification audits for new suppliers– Supplier-Triennial Audits, perform audits themselves or use NUPIC– Internal-Annual or once during the activity being performed
h f– Right of Access– Surveillance
• NUPIC (Nuclear Procurement Issues Committee)A dit f d b d NUPIC t th t ll lti l– Audit performed by owner under NUPIC agreement that allows multiple owners to utilize audit results.
– NUPIC performs audit based on vendors being placed on the approved supplier list.
• NIAC (Nuclear Industry Assessment Committee)– Similar to NUPIC but allows suppliers to audit sub suppliers and utilize for
multiple suppliers.
What do you do next?What do you do next?
• Talk to EPC Vendors/Utilities to indicate interest • Vendors/utilities will describe their wants and needs. • Vendors/utilities will discuss their requirements. • Work to develop a QA Program (several actions are necessary)• Work to develop a QA Program (several actions are necessary)
– (Identify a QA Manager– Obtain and review the regulations and codes and standards– Develop QA Program for the Organizationp Q g g– Develop Procedures for the implementation of the program elements applicable
products or activities – Qualify and certify appropriate personnel
Implement program or have all elements available for implementation if order is– Implement program or have all elements available for implementation if order is received
– Etc.
What do you do next? (cont )What do you do next? (cont.)
• Don’t contact NUPIC/NIAC and ask for an audit. – Utility/Vendor will do this once added to approved supplier list
EPC CONTRACTOR
QUALITY ASSURANCE PROGRAM
IMPLEMENTATION
U S NUCLEAR REGULATORY COMMISSION (NRC )COMMISSION (NRC )
ESTABLISHED QA PROGRAM REQUIREMENTS FOR Q QCONSTRUCTION OF NUCLEAR POWER PLANTS IN 10 CFR 50, APPENDIX BREQUIRES CERTAIN PIPING SYSTEMS AND REQUIRES CERTAIN PIPING SYSTEMS AND COMPONENTS COMPLY WITH ASME CODE SECTION III REQUIREMENTSENDORSED ASME NQA-1 QA STANDARD AS AN ACCEPTABLE BASIS FOR COMPLYING WITH THE REQUIREMENTSREQUIREMENTS
EPC CONTRACTOR QA PROGRAMEPC CONTRACTOR QA PROGRAM
COMPLIES WITH 10 CFR 50 APPENDIX B AND ASME NQA 1 ASME NQA-1 APPLICABLE TO SAFETY RELATED ITEMS AND ACTIVITIES DURING DESIGN, PROCUREMENT AND CONSTRUCTION PHASES OF NUCLEAR POWER PLANT CONSTRUCTIONLICENSEE/OWNER CONTRACTS SPECIFY LICENSEE/OWNER CONTRACTS SPECIFY APPLICABLE QA PROGRAM REQUIREMENTSTHE EPC CONTRACTOR SHALL PASS ON THE QA PROGRAM REQUIREMENTS TO SUPPLIERS QA PROGRAM REQUIREMENTS TO SUPPLIERS AND SUBCONTRACTORS
EPC CONTRACTOR QA PROGRAM IMPLEMENTATIONIMPLEMENTATION
SUPPLIERS OF SAFETY RELATED HARDAWRE SHALL HAVE A QA PROGRAM CONSISTENT SHALL HAVE A QA PROGRAM CONSISTENT WITH 10 CFR 50 APPENDIX B AND NQA-1EPC CONTRACTOR SHALL APPROVE THE SUPPLIER QA PROGRAM AND ITS SUPPLIER QA PROGRAM AND ITS IMPLEMENTATION SUPPLIER SHALL HAVE SUPPLEMENTAL IMPLEMENTING PROCEDURES SUPPLIERS OF SAFETY RELATED ITEMS SHALL COMPLY WITH 10 CFR PART 21 COMPLY WITH 10 CFR PART 21 SUPPLIERS ARE ALSO SUBJECT TO THE OWNER AND NRC ADDITIONAL OVERSIGHT FOR ACCEPTANCE OF THE HARDWAREACCEPTANCE OF THE HARDWARE
EPC CONTRACTOR QA PROGRAM IMPLEMENTATIONIMPLEMENTATION
SUBCONTRACTORS PROVIDING ON-SITE SERVICES MAY PERFORM UNDER THEIR OWN CONTRACTOR APPROVED QA PROGRAM & PROCEDURES OR UNDER THE CONTRACTOR QA PROCEDURES OR UNDER THE CONTRACTOR QA PROGRAM PER CONTRACT REQUIREMENTSWHEN PERFORMED UNDER THE CONTRACTOR QA PROGRAM, SUBCONTRACTOR IS PROVIDED WITH AND SHALL COMPLY WITH THE CONTRACTOR PROCEDURES IN THIS CASE THE CONTRACTOR PROCEDURES. IN THIS CASE THE CONTRACTOR WILL PERFORM QA/QC FUNCTIONS
ASME CODE SECTION IIIOBTAINING CODE STAMPOBTAINING CODE STAMP
OBTAIN CODEBOOKS
SUBMITAPPLICATION
CONTRACT WITH
DEVELOPQA
IDENTIFY REQUIRED BOOKS TO ASMEAIAPROGRAMSTAMPS
ASME ISSUESCERTIFICATES
ASMESUCCESS
N: VESSEL, PUMP, VALVE, PIPING SYSTEM, ETC.
NPT: PART, PIPING SUBASSEM-BLY & APPURTENANCE
SECTION IISECTION III
APPLICANT COMPLETES
CERTIFICATES& STAMPS
PERFORMSSURVEY
UNSUCCESSFUL
BLY, & APPURTENANCENV: PRESSURE RELIEF VALVENA: INSTALLATIONQSC: MATERIAL ORGANIZATION
(NO STAMP ISSUED)NS: SUPPORTS (NO STAMP)
SECTION IIISECTION VSECTION IX
CORRECTIVE ACTION