Upload
vudat
View
212
Download
0
Embed Size (px)
Citation preview
NOTE TO USERS
This reproduction is the best copy available.
-- - - - -
Belief Network Analysis of Direct Cost Risk in Building Construction
Kevin Eyers
A thesis submitted in conforrnity with the requirements for the degree of Masters of Applied Science Graduate Department of Civil Engineering
University of Toronto
O Copyright by Kevin Eyers 200 1
National Library 1*1 ofCanada BibIiothèque nationale du Canada
Acquisitions and Acquisitions et Bibliographie Services services bibliographiques 395 Wellington Street 395. me Wellington OnawaON KlAON4 Ottawa ON K I A ON4 Canada Canada
The author has granted a non- exclusive licence allowing the National Library of Canada to reproduce, loan, distriiute or seU copies of this thesis in microform, paper or electronic formats.
The author retains ownership of the copyright in this thesis. Neither the thesis nor substantial extracts fiom it may be printed or othewise reproduced without the author' s permission.
L'auteur a accordé une licence non exclusive permettant à la Bibliothèque nationale du Canada de reproduire, prêter, distribuer ou vendre des copies de cette thèse sous la forme de microfiche/film, de reproduction sur papier ou sur format électronique.
L'auteur conserve la propriété du droit d'auteur qui protège cette thèse. Ni la thèse ni des extraits substantiels de celle-ci ne doivent être impximés ou autrement reproduits sans son autorisation.
Abstract -- -- - --
Beiief Nehvork Analysis of Direct Cost Risk in Building Construction
Kevin Eyers
M.A.Sc. Department of Civil Engineering, University of Toronto, 200 1
Research was undertaken to develop a model to predict cost overruns on land-based,
North Amencan construction projects. A belief network model was chosen to meet this
goal. First, a catalogue of ail risks to construction cost was compiled. These risk
variables were ranked from most dependent variable to most independent variable to aid
in model development. Relationships between each of the risk variables on the list were
determined by surveying experts in the field. Thirdly, conditional probabilities for each
of the relationships in the model were calculated, again with the aid of expert surveys.
Finally, the model was calibrated using data fiom actual completed projects.
The user may set values of each of the vanables in the model, and read the likelihood of a
range of cost overnins for each of the Equipment, Labour and Material Costs on a
construction project. Two completed p-ojects were tested, and the differenccs between
actual and predicted cost overrun were found to be within 10%.
Belief Arenvork Anaiysis of Direct Cost Risk in Building Constnlcfion . . 11
Acknowledgements
For two years 1 have participated in the M.A.Sc. programme at the University of Toronto,
with the goal of contributing something o f value to the field of Construction Engineering
and Management. This research is the ~ e s u l t of that effort: and the contents of these
pages would not have been possible without the support, mentorship and guidance of
colleagues and fi-iends.
Professor Brenda McCabe has given me the opportunity to pursue this research. More
irnportantly, however, she has assisted me every step of the way. providing insight,
guidance and encouragement. 1 extend sincerest gratitude to her and thank her for her
dedication and support.
E would also like to thank Professor Tamer El-Diraby for his time and effort in reviewing
this research and sharing his ideas and comrnents.
The time and effort put foah by MGP Project Managers made the second and third
sections of this research, the sections requiring expert survey, possible. Paul Stein and
Sam Vaskov in particular were very helpful and supportive. In addition, I would like to
recognize the expert input of Ervin Arden, Peep Korgemagi, Cuthbert Radix, Cecil
Holtrop, Mark Doyle, and Cristina Segal.
Belief Nenrork -4nalysis o/Direa Cosr Risk in Birilding Consrrucrion ..- 111
Colleagues at the University of Toronto also provided guidance and assistance. I would
like to thank Daud Nasir: Roya Azad, Hrodny Njardardottir, Peter Pilateris and Joe
Ramani.
Away f?om the office, the unwavering support and love of family and friends helped to
motivate me to push on when times were tough. My parents? Brian and Cathy, along
with my brother and sister, Karen and Kyle- and my good friend Melanie Fairbrother
were aii there with words of encouragement when 1 needed them. I thank them
wholeheartedly.
Finally, 1 would like to acknowledge the financial support of the Ontario Government
Scholarship programme, the Department of Civil Engineering at the University of
Toronto, and MGP Project Managers.
Table of Contents
Abstract
Table of Contents
Table of Tables
Table of Figures
Table of Appendices
Chapter One: Scope and Objectives
1.1 Problem S tatement 1.2 Objectives of Research 1.3 Scope of Research 1 -4 Research Method
Chapter Two: Risk Basics, Mode1 Basics
2.1 Introduction 2.2 Construction Risks 2.3 Construction Cost Risks 2.4 Belief Networks
3-4.1 Introduction 2-42 Belief Network Terminology 2.4.3 Sample Evaluation 2-4.4 Belief Network Construction
2.5 Why Belief Networks?
Chapter Three: Risk Identification
3.1 Introduction 3.2 Risk List 3.3 Risk Categories
3 -3.1 Construction Risks 3 -3 -2 ContractuaVLegal Risks 3 -3.3 Management Risks 3 -3.4 Owner Risks 3.3.5 Design Risks 3 -3 -6 Project Characteristics Risks 3.3 -7 Location Risks
Belief A'envork Andysrs of Direct Cosr Risk in Building Cons~nrcrion v
3 -3 -8 Economic Risks 3 -3 -9 Political Risks 3 -3.10 Environment RÏsks
3 -4 Risk List Ranking 3.5 Risk State Definition 3 -6 Divorcing Variables 3 -7 Predictor Variables
Chapter Four: Relationship Identification
4.1 Introduction 4.2 Expert Survey 4.3 Survey Results Andysis 4-4 Literature Search 4.5 Divorcing 4-6 Data Reduction
4.6.1 Relationship Elimination:
4.6.2 Relations hip Elimination:
4 - 6 3 Relationship Elimination:
4.6.4 Relationship Elimination:
4.6.5 Relationship Elimination:
Cliapter Five: Probability Determination
5.1 Introduction 5.2 Data Reduction
5.2.1 Asymmetric Assessrnent
Tenant Reqztirement Change - Design CZaims Qrral9ed Local Labour - Labozlr Delays Local Suirab le 1Mcrrerials - Projecr Material Shortage Tenunt Reqtrirernent Change - Design Changes Design Tearn Coordination - 45 Design Changes
48
5.2.2 Parent State Combination Ranking 5 -3.3 Probability Curve Development
5.2.3.1 Probability Curve Parent State Ranking 5.2.3 -2 Probability Cumes 5.2.3.3 Divorcing Cuves
5.3 Probability Expert Survey 5.3.1 Expert Survey Development 5.3.2 Survey Data Analysis
5.4 MSBNTM Model 5.4.1 Model Construction 5.4.2 MSBNTM Text File 5.4.3 Using the Model
Belief iVenr.ork Analysis of Direct Cosr Risk in Building Consfnrcrion vi
Chapter Six: Model VerificatiodValidation
6 - 1 Introduction 6.2 Sensitivity Andysis 6-3 Model Validation
6.3.1 Project One: ABC Manufacturing Facility 6.3 -2 Project Two: 123 Company Building Envelope
Restoration 6.3 -3 Validation Discussion
Chapter Seven: Conclusions
7.1 Conclusions 7.2 Contributions 7.3 Recommendations
References
Appendices
Bei~ef Nenvork Analysis of Direct Cosr Risk in Building Consrnicrion vii
Table of Tables
Table 1.1
Table 2.1
Table 3.1
Table 3.2
Table 3.3
Table 3 -4
Table 3.5
Table 3.6
Table 3.7
Table 3.8
Table 3 -9
Table 3.10
Table 3.1 1
Table 3.12
Table 4.1
Table 4.2
Table 4.3
Table 4.4
Table 4.5
Table 5.1
Table 5.2
Research Methodology
Mathematical Notation
Appendix A Columns
Construction Risks
ContractualLegal Risks
Management Risks
Owner Risks
Design Risks
Project Characteristics Risks
Location Risks
Economic Risks
Political Risks
Environrnent Risks
Ranked List of Construction Cost Risks
Relationship S w e y Rejection Tests
Relationship Survey Acceptance Tests
Borderline Relationships eliminated as a result of expert analysis
Variable Relationships identified in Lirerature Study
Divorcing the Construcrion Claims Variab le
Regression of Parent State-interpolated variables
Difference between interpolated values and surveyed values
Beltej:Venr.ork -4nalysis o j Direct Cos! Risk in Bzttlding Constnrclion ... V l l l
Table 5.3 Strength of Parent Variables on Equiprnent Cost predictor variable
Table 5.4 Exarnple Ranking Calculation
Table 5.5 Appendix G SarnpIe
Table 5.6 Appendix H Sarnple
Table 5.7 Division of questions on the probability survey
Table 6.1 Predicted likelihood of various cost overruns for each cost Category, ABC Manufacturing Facility
Table 6.2 Predicted likelihood of various cost o v e m s for each cost category, 123 Company Building
Brlief Nenvork Anaiysis of Direcr COSI Risk in Buildrng Consrnrcrron ix
Table of Figures
Figure 2.1
Figure 2 2
Figure 4- 1
Figure 4-2
Figure 4-3
Figure 4.4
Fi,oure 5.1
Figure 5.2
Figure 5.3
Figure 5.4
Figure 5.5
Figure 5.6
Figure 5.7
Figure 5.8
Fibgure 5.9
Figure 5.10
Sarnple Belief Network
"A" is a child of "B"
Sarnple Relationship Identification Survey
Non-divorced Construction Claims Variable
Divorced Constrzrction Claims Variable
Completed Belief Network Mode1 Structure
Asymrnetric Assessment structure for Project Mcrterial Shortcrge
Ranking from most severe conditions to least severe conditions, Overrime child variable
Probability Curves for Predictor variables
Sample Probability Survey
Example of Situation where average value was not selected
Text file node definition - Srrituble Eqzlipmenr Availubility
Suitable Equipmenr Availnbilify Conditional Probabilities
Asyrnrnetric Assessrnent Structure - Suitable Equiprnent Availabilii'y Text File
Asymrnetric Assessment Structure - Szrituble Equipment Availubilify Graphical File
Sarnple MSBN Evaluation
Belie/:Venvork Analysts of Direc! Cos! Risk in Building Consrnicrion X
Table of Appendices
Appendix A Risk Variable Information 92
Appendix B Risk Relationship S w e y 100
Appendix C Risk S w e y Analysis 106
Appendis D Divorcing 116
Appendix E Asyrnmetrk Assessrnent Structures 119
Appendix F Cornparison: Probability Survey Interpolated Values to S w e y Values
Appendix G
Appendix H
Appendix 1
Appendix J
Appendix K
Appendix L
Appendix M
Probability Curves
Predictor Variable Ranking
Probability Survey Results, Prior ProbabiIities
Divorcing Variable Ranking
Data Reduction Description
MSBN Test File
Mode1 Validation Results
Belief iVenvork Anabsis of Direcr Cosr Risk in Building Consrnicrion xi
For Laura
Chapter One: Scope and Objectives
1 . PROBLEM STATEMENT
Construction projects are subject to enormous uncertainty. In general, the greater the size
and duration of the project, the greater the uncertainty that exists. Long-term projects are
particularly prone to cost and schedule overruns; there is great uncertainty in trying to
predict what may occur several years into the future. As such, it is important that al1
project participants (owners, project and construction managers, contractors,
subcontractors, bonding and insurance agencies, etc.) have a good grasp of events that
rnay befall their project, and the likelihood that these events will occur.
Recent research focused on the identification of schedule risks, determination of the
likelihood of these risks, and their effects on overall project schedule (Nasir, 2000). In
addition, work is being done on the identification of risks to budget, and their effects on
final project cost (Elhag and Boussabaine, 2000). However, no work to date has been
found that predicts cost overnins in a probabiIistic marner.
What is the likelihood that the project cost will exceed the original project budget,
and by how much, given current conditions?
Answers to questions ILke L ~ S provide project participants with the opporhmity to
undertake corrective mesures to bring project cost back to the estimated budget cost.
The ability to address budget concerns during the course of a project is greater when the
project is long-term; therefore, while more risk exists, more opporhmity exists to fix
Belief Nenvork Anaipis o j Direct Cost Risk in 611ilding Construction 1
problems before they seriously affect the final outcome of a long-term project. This
report deals with the assessment of degree of, and associated likelihood of, cost overrun
on long-term projects.
Studies have been conducted on determinhg the risks associated with cost overruns
(Elhag and Boussabaine 1999, Mulholland and Christian 1999). However, none predicts
cost risks in a manner that attaches probabilities to each degree of ove rm. Additionally,
a need was identified to gain a better understanding of the interaction between the
variables affecting project costs.
The primary objective of this research is:
to develop a model that will predict the most Iikely cost overrun for each of the
major cost centres in a long-term building project budget
While the development of such a model is the primary focus of this work, several
preliminary steps were of academic and practicd value, and served as milestones
throughout the thesis. These preliminary goals include
1. identi@ing factors affecting the cost of construction projects,
2. determination of the manner in which these factors affect cost,
3. development of a more efficient expert surveying method,
4. determination of the degree to which these variables affect cost.
Each of these preliminary steps led to the development of a Bayesian belief network
model that accomplished the primary objective of this research.
Belief Nenvork iinafysis of Dlrecr Cos! Risk in Building Conslruclion 2
1.3 SCOPE OF RESEARCH
This research deals with construction projects that have the following characteristics:
Long-Term
"Long-term" refers to the fact that the time value of money plays a role. If
the duration of the project is long enough that inflation and construction
market escaiation need to be considered, then the project is considered to
be long-term. There is much more uncertainty in the construction of large
projects simply because of the time and resources that need be committed
to their construction. The author believes that ~here is more to be gained
by studying long-term construction than short tem.
Land-Based
There are many additional factors that corne into play in the construction
of offshore projects. Facilities like the Hibernia oil fields encounter risks
that do not affect land-based construction projects. This mode1 does not
consider such factors.
Preliminary Design Only Necessarily Complete (Le. assume project is fast-tracked)
The mode1 assumes that only the preliminary design is necessarily
complete. Most long-terrn construction projects these days are constructed
on a fast-track basis. That is, they are designed as construction proceeds -
design drawings become available as construction requires them. As a
result, only some detailed drawings are complete at the commencement of
Belief lVenrork Analqsis o j Drrecr Cosr Rtsk in Building Consrnicrion 3
construction. On the other hand, gross design drawings are necessary to
begin building. This model is useful at any point afier prelirninary design
is cornpiete.
Mistake-Free Budget Estirnate
This work seeks to identifi the probability of cost overrun. As such, it is
necessary to have a budget to which the final actual cost can be compared.
It is also necessary to assume that this budget estimate is correct.
Additional risk in the forrn of the possibility of an inaccurate estimate
rnust be considered if this assumption is not met. This model makes no
such allowance.
Based in the United States or Canada
Construction takes place under different circumstances al1 over the world.
On the other hand, Canada and the United States have similar construction
environrnents in which to work. To eliminate differences that may occur
due to construction projects overseas or in third world countries and the
like, the scope of this model has been limited to the relatively stable and
sirnila. environments of Canada and the U.S..
Contractors are Pre-Qualified and Bonded
Large construction projects require owners and project managers to be
concerned about the ability and experience of the construction
Belief Xenvork Anulysis of D~recr Cos! Risk in Building Consrmcrion 4
participants. To that end, project owners go to great lengths to ensure that
al1 participants are competent and able to do the work efficiently. The
means that they use to gain this assurance are pre-quaIification and
bonding. Pre-qualification ensures that d l project bidders have shown the
ability to do similar work in the past. whiile bonding protects the owner in
the event that the work does not get completed due to insolvency.
Only Building Construction considered
Only elements of building construction are considered. Infrastructure and
residential construction projects, for exarnple, are not included in the
scope of this research.
Four main steps were taken in the development of this model. The four steps, described
in more detail throughout the report, are shown i n Table 1.1. Since sirnilar research using
Belief Networks was conducted at the University of Toronto for schedule risks in
construction (Nasir 2000), similar methodology was therefore used.
Belie f Nenvork A nalysis of Direct COSI Risk in Buddrng Consrntction 5
~ 1 or in combination, have an effect on 1 with some informal expert II
Table 1.1: Research Methodology
Quantification 1 every parent state combination for 1 II
Primary Research Techniques Literature search prirnarily, along
S tep Risk Identification
1
I
Relationship Identification
Relationship
Description Identi@ ail factors that, either alone
1 1 actual direct cost overruns
direct costs in construction Determine most significant cause- effect relationsliips for every variable identified in the Risk identification step Calculate conditiona1 probability o f
Mode1 Verificatiod Validation
The four steps identified in Table 1.1 are typical steps used in the development of Belief
interview PrimariIy expert survey (approximately 90%) along with a minor literature searzh (1 0%)
Exclusively expert survey
Networks (McCabe et al, 1998). A study of al1 available literature was conducted to
every variable in the mode1 Ensure that the mode! is predicting reasonabIe values
identify al1 risk variables to cost on construction projects that meet the limitations of the
Using completed projects, compare predicted direct cost overruns with
research scope as described previously. This literature search identified any causal
relationships between chosen risk variables. As a suppIement to the literature search,
informal expert interviews were conducted to gain additional insight into direct cost risks
in construction. The Iist of risks was then ranked to aid in rnodel development, and States
were identified for each of the variables included in the model.
Secondly an expert survey, in matrix format, was created to identiQ cause-effect
relationships between each of the risks identified in step one. For each "effect variable",
the strength of relationship with every appropriate "cause variable" was determined, and
the strongest relationships were retained for use in the rnodel. This ensured that
important model relationships were included, while weaker relationships that increase
model complexity more than they increase model completeness were excluded. To
increase the ease with which the experts could complete what was admittedly a
Belie/;Venvork rlnalysis O/ Direct Cost Risk in Buiiding Consfruction 6
complicated s w e y . the author was available at al1 times via e-mail or telephone to
answer questions.
Experts were chosen fiom a pool of project management experts at MGP Project
Managers, project managers at the Lester B. Pearson International Airport new terminal
construction in Toronto. The experts were chosen to reflect a wide range of expertise and
expenence.
At this stage. every variable had been assigned between zero and six parent variables.
For every variable, each combination of causal variable and effect variable states was
assigned a probability between 1 - 100: reflective of the likelihood that the causal variable
state combination would produce the effect variable state. An expert survey was used
exclusively to this end. A structured interview process was the method of survey chosen
for this stage of research. This made it easier for experts to complete the survey, which
in many cases needed quite a bit of clarification.
Finally, information regarding actual cornpleted projects was used in the model to arrive
at a predicted direct cost overrun. This cost overrun was compared to the actual direct
cost oven-un, and a statement about the effectiveness of the completed model made.
Beirejh'envork Analysts o/Direcr Cos1 Risk m Brddrng Cons!nrcrron 7
Chapter Two: Risk Basics, Mode1 Basics
2.1 INTRODUCTION
Risk is a concept with many definitions depending on the perspective of the individual
defining it. At its most basic. risk can be categorized as "1. The possibility of suffering
harm or loss; danger ... 2. A factor, elemenf or course involving uncertain danger; a
hazard." (Webster, 1990). This definition is, at best, rudimentary. The Construction
Industry Institute (1989) goes further, stating that risk is the probability that an
davourable outcorne will occur. Conversely, the probability that a favourable outcome
will occur is defuied as opportunity. Risk and opportunity go hand in hand. High-risk
situations are usually accompanied by the potential for great reward. On the other hand,
if the potential for reward is great, one should beware of the fact that the situation is
likely quite risky as well. This risk-reward partnership is especially evident in
construction.
2.2 CONSTRUCTION RISKS
Long-term projects costing in the billions of dollars are subject to tremendous amounts of
uncertainty, not the least of which has to do with the fact that these types of projects
occur over several years (witness the 10-year, $4.4 Billion prograrn of construction at
Lester B. Pearson International Airport in Toronto). It is impossible to completely and
accurately predict what may or may not occur over a 10-year planning horizon; $4.4
billion is a large sum of money to risk, given that degree of uncertainty. Constmctors are
especially focused on two main categories: scheduie risks and cost risks. Research on
Belief Nenrork Anaiysis of Direct Cosr Risk in B u i l h g Consrnrcrion 8
schedule risks using Belief Nehvorks has already been undertaken. This work focuses on
risks to cost,
2.3 CONSTRUCTION COST RISKS
Ultimately, construction is undertaken by contractors in order to earn profits. Project
owners have different goals, such as the construction of facilities that fit their needs. An
important goal of construction fiom the owner's point of view is to have the project
completed on time, and on or under budget. Cost is, therefore, of the uûnost importance
to al1 parties involved with a construction project.
Project managers w-ith years of accumulated experience develop instincts about what may
go wrong on their projects. It is important to capture these intuitions as well as possible
in a mode1 like this. As such, every risk factor needs to be catalogued and analyzed.
These risk variables include factors that can be affected by management (labour
productivity and overtime, for exarnple) as well as factors that are outside human control
(e-g. geology, natural disasters).
2.4 BELIEF NETWORKS
2.4.1 INTRODUCTION
First developed at Stanford in the 1970s, the Bayesian belief network is a forrn of
artificial intelligence that has only recently gained some acceptance in construction
applications. The Belief Network is a flexible modeling tool that allows the modeler to
Befie/Xenvork Analysis of Direct Cosr Risk in Building Consrnrcrion 9
not only predict the outcome of a situation, but also predict the probability of a range of
different outcomes (McCabe et al. 1998).
A belief network is a collection of nodes, representing mode1 variables, and directed arcs
(arrows) denoting dependent relationships between variables (Pearl 1 996)- Belief
Networks are "directed acyclic graphs'' (DAGs), meaning that the arrows cannot be
directed away fiom a node to other nodes, and then back to the original
is used to illustrate terminology associated with belief networks.
4cceptable Productivit b
node. Figure 2.1
Figure 2.1: Sampie belief network, (McCabe et al., 1998)
The nodes such as Too Few Loaders denote the factors being studied, while the arcs
denote the relationships between factors. Beside each node are the conditional
probabilities that apply to that particular node and its parents (Le. the nodes that affect it).
In this belief network, the number of loaders and the number of trucks have an effect on
the effrciency and productivity of a truck loading operation. Too few ioaders or too many
trucks, and a queue may forrn (Acceptable Queuina). The length of the queues affect the
productivity of the system. In addition, the number of trucks used aiso affects the
integrity of the road surface (Sozmd Roud Surface).
Belief ~Venvork ..lnuiysis of Direct Cosr Risk in Building Constntcrion 10
For clarity throughout the report, variable names will be s h o w in italic. Section 2.4.2 is
a co1Iection of terms needed to understand discussions of belief networks. Following
that, Section 2.43 provides an exarnple of the calculations perfonned in belief network
evaluation.
Throughout this thesis, the notation fiom propositional caiculus in Table 2.1 will be used.
Notation P(TFL)
Table 2.1: Mathematical Notation Definition Denotes the probability that there are Too Few Loaders Denotes the probability of variable Acceptable Productivity? given that there is acceptable queuing Denotes '&andn - P(AQ&) denotes the probability that acceptable queuing and acceptable productivity occur Denotes the negative state - P(-AQ) denotes the probability of unacceptable queuing
2.4.2 BEL~EF NETWORK TERMINOLOGY
The following is a list of terms used in discussing belief networks.
Baves' Theorem: Bayes' Theorem deals with conditional probabilities. In belief
networks, Bayes' Theorem is used to revise the belief about the state of one variable
given the States of al1 other variables in the network. Bayes' Theorem stipulates that:
(1) (singIe variable influence)
(2) (multiple variable influence)
Belief Xehvork Analps of Direct COS[ Risk rn Building Consrnrcrion 11
Child: Node "A" is a child of Node "B" if an arc orïginates at Node " B and terminates at
Node "AY'- In Figure 2.1, Acceptable @elring is a child of both Tou Few Loaders and
Figure 2.2: "A" is a child of "B"
D-separation: In the example network, Too Many Trucks affects Acceptable Quezring,
which in turn affects AcceptrrbZe Productivi&. Too Many Trzicks clearly has an affect on
Acceptubk Productivi~ through Acceptable Queuing. On the other hand, if the state of
Acceptable Qzreuing is known, then the state of Acceptable Productivity is not at d l
dependent on Too Muny Trucks. Acceptable Productivity and Too Many Trucks are said
to be d-separated by the instantiation of the intermediate node AQ. This is a very usefui
property of beiief networks, and allows vast simplification of calculations. The example
calcdations perfomed in the next section will demonstrate this effect.
Instantiation: A node is instantiated when its value is known. If, for example, it becomes
known that Sound Roud Szrfice is fdse in Figure 2.1, the variable SRS is said to be
instantiated. If SRS-rio, it means that the road surface is not sound, and that P(-SRS) =
1, and P(SRS) = 0.
Orphan: A node is an orphan if it has no parents. In the Figure 2.1, Tou Few Loaders and
Too Muny Trucks are both orphans.
BelieJiVenvork rlnalysis of Direcr Cosr Risk in Bitilding Comrnrcrion 12
Parent: Node A is a parent of Node B if an arc originates at Node A and terminates at
Node B. In the Figure 2.1' Too Many Tmch is a parent of both Acceptable eueuhg and
Sound Road Surface.
Variable State: A variable may take on different values. In a belief network, these values
are cdled "States". Each of the variables in the sarnple network has two States (Le. they
are binary). In general, variables need not necessarily be binary.
2.4.3 SAMPLE EVALUATION
The following is an exarnple evaluation of the sarnple network. The evaluation is taken
from (McCabe et al., 1998) and is based on Figure 2.1.
Problem: Determine the likelihood that there are too many trucks in the system, given
that the road has deteriorated and the productivity of the system is acceptable. In effect,
find:
~(TMTIAPA-SRS) (Problem Equation)
Step 1 : Use Bayes' Theorem to condition the previous statement on a parent
P(TMT 1 AP A -SRS) = P(AP A 4 R S 1 TMT) * P(TMT)
P(AP A --SRS) (Eq- 1)
P(TMT) can be read directly from Figure 2.1. The remaining phrases need additional
manipulation before they can be taken from the belief network.
Belief Nenvork Analysis of Direct Cost Risk in Building Construcrion 13
Step 2: Use the concept of d-separation to simplify P(APA-SRSITMT). Since the state of
TMT is given in this statement? AP and SRS are d-separated, and therefore independent.
so,
P(AP"-SRS [TMT) = P(AP/TMT)* P(-SRS (TMT) (Eq. 2)
Now, P(TMT) and P(-SRSITMT) can be extracted from Figure 2.1. Remaining
unknown values include P(AP/TMT) and P(APA-SRS).
Stev 3: Condition the probability of AP on al1 parents of AP, given the evidence that
TMT = true.
P(AP(TMT)=P(APITMTAAQ)*P(AQITMT)+P(API-AQ)*P(-AQlTMT) (Eq. 3)
Note: AP and TMT are d-separated by AQ, so the probability of AP depends only on AQ.
Therefore,
P(APITMTAAQ) = P(AP1AQ) (Eq. 4)
Step 4: Determine P(AQ1TMT). Note that P(-AQITMT) = 1 - P(AQ1TMT).
P(AQ1TMT) = P(AQITMTATFL)*P(TFL)+P(AQfTMTA-TFL)*P(TFL) (Eq. 5)
Al1 four right-hand-side values are known. Only the denominator remains to be
evaluated.
P(TMT), P(-SRSITMT), P(APIAQ), P(AQITMTATFL), P(TFL), P(AQ/TMTA-TFL),
P(-TFL), P(-AQ[TMT)=l-P(AQ(TMT) can al1 be taken from the beiief network in
Figure 2.1. P(APh-SRS) remains.
BeliejArenvork Analysis of Direct Cost Risk in Building Comtn~crion 14
Step 5: Evaiuate the denorninator:
P(AP"-SRS) = f (-SRSIAP)*P(AP) (Eq. 6 )
Note: P(-SRSIAP) = 1-P(SRS/AP) (Eq. 7)
Therefore,
1 -P(SRSIAP) = 1 -[P(SRSIAPATMT)*P(TMTIAE') + P(SRSIAPA-TMT)*P(-TMTIAP)]
Where ,
Since SRS and AP are d-separated by TMT,
P(SRSIAPATMT)=P(SRSITMT) (Eq.9)
EveIything except P(AP) has been evaluated.
Step 6: Evaluate P(AP) by conditioning on a11 parents.
P(AP) = P(APIAQ)*P(AQ)+P(API-AQ)*P(-AQ) (Eq. 10)
where,
P(AQ)=P(AQ[TFLATMT)*P(TFL)*P(TMT)
tP(AQITFLA-TMT)*P(TFL)*P(-TMT)
+P(AQI-TFLATMT)*P(-TFL)*P(TMT)
tP(AQ1-TFLA-TMT)*P(-TFL) "P(-TMT) (Eq. 1 1 )
Step 7: Work backwards through the calculations to arrive at the desired outcome
By Eq. 11, P(AQ) = 0.05*0.5*0.5+0.35*0.5*0.5+0.35*0.5*00.9*05*0 = 0.413
By Eq. 10 P(AP)=0.85*0.413+0.15*0.587=0.439
By Eq. 8 P(TMTIAP)=0.29*0.5/0.43 9 = 0.330
Belief Nenvork Anaiys;s 01 Direct Cosr Risk in Building Consrnicrion 15
By Eq. 7 P(-SRSIAP)=l -(O. lS*O.330+0.9*0.670) = 0.348
By Eq. 6 P(APA-SRS)=O-348*0.439 = 0- 1%
By Eq. 5 P(AQ[TMT)=0.05*0.5+0.3 5*O-j=O.2
By Eq. 3 P(AP~TMT)=0.85*0.2+0.15*0.8= 0.290
By Eq. 2 P(AP-SRSITMT)=O.29*0-85 = 0.247
Therefore,
(Problem Equation) P(TMTIAPA-SRS)=O.~~~*OS/O. 153 = 0.807
Step 8: Conclude:
It may be concluded with 8 1% confidence that there are too many trucks in the system, or
P(TMTIAPA-SRS) = 8 1%.
2.4.4 BELIEF NETWORK CONSTRUCTION
Four main steps need be taken in the development of a belief network (Poole et al. 1998).
They are:
1. Define relevant variables and identifi variable States
2. Define variable relationships
3. Determine conditional probabilities of relationships
4. VeriQ and validate the network
Each of these four steps is taken in the development of the mode1 for this thesis, and will
be discussed in one of four chapters devoted to the cost mode1 construction.
Belief h'envork ilnalysis of Direcr COSI Risk in Building Constntcrion 16
2.5 WHY BELIEF NETWORKS?
The main alternatives to the belief network for the type of mode1 to be used in thLs
research are Neural Networks, Linear / Dynamic Programming, Regression Analysis, and
Simulation / Risk Analysis. Some limitations of these types of models include (Elhag and
Boussabaine, 1999):
+ Unknown combined effects and interrelationships of cost risk variables
0 Imprecision and uncertainty of data and variables affecting costs of
construction projects
Belief Networks not only allow examination of these combined effects, they also seek to
quanti@ the uncertainty of data and variables, and allow probabilistic analysis. In the
sarnple evaluation, it was deterrnined, with 81% certainty, that there were too many
trucks in the system. Neural networks do not intrinsically allow for this quantification of
degree of belief. Because this research attempts to quanti@ uncertainty, the probabilistic
basis was important, In addition, neural networks require a tremendous amount of
historical data to train the network (Portas and AbourRizk 1997). These data were
simply not available to the author of this work as each project data would have to be
collected individually where it was even possible to collect it.
Another benefit of belief networks is their flexibility. Nodes may be added to or
subtracted from the network if it is deemed necessary by any user. AIso, evidence for
every variable need not be gathered. Either of these changes would require complete
reconstruction and training of a neural network.
Belief A'enrwk Analysis of Direct Cosr Risk in Building Constn~rion 17
At the time of this research Elhag and Boussabaine were using neural networks to deal
with this problem. Their model most closely resembles the research done in this rnodel.
Cost risk variables were collected and grouped according to their main effect on cost.
The researchers then ranked the risk variables according to the magnitude of their effect
on final project cost. The research m e r proposes to use neural networks and fuzzy
logic to predict final project cost and schedule overmns. The neural network portion of
this research is not yet complete. As a result of the fact that neural networks are being
used for similar research. a different approach was sought to attack the problem.
Ln the final analysis it was detennined that, for the reasons detailed above, the belief
network was the best type of model to be used in this research. The subsequent chapters
of this report detail the steps taken in the construction of a belief network to predict cost
ovenruns on construction projects.
Belief .Vencork Anaipis of Direct Cosr Risk in Building Consrnrcrron 18
Chanter Three - Risk Identification
3.1 INTRODUCTION
A search of available Iiterature was conducted to identiq factors affecting cost on
construction projects. Factors that affect cost in a direct manner, as well as those that
acted indirectly (Le. through other factors) were studied. In the end, a Iist of 75 risk
variables affecting construction costs was compiled. The risk variables chosen were
carefdly defined so that relationships could be established at a Iater stage. This list \vas
then r d e d so that any given risk on the list may only be affected by risk variables lower
on the list. Finally, risk States were detemiined for each of the variables. Each of these
stages in the risk identification process will now be discussed in M e r detail.
3.2 RISKLIST
Several sources were studied for factors affecting construction cost. After reviewing
available literature, it was determined that no research had yet produced a compilation of
al1 risks to construction cost. As a result, information fiom several sources, including
textbooks, journal articles, and persona1 expert interviews were compiled into a master
list. A paper was later discovered that included a similar compilation of factors affecting
construction cost (Elhag and Boussabaine 1999). The two lists of construction cost risk
variables were compared, and found to contain a similar collection of variables. Where
factors were missing from this research list, they were either added or included in the
definition of variables already in the collection.
Belief Xenrork Anaiysis of Direct COSI Risk in Brrrld~ng Consrnrcrion 19
There are ten different categones of nsk identified in this research. Each of the 75 risks
to cost discovered in the literature search is classified in one of the ten categories.
Appendix A contains a list of al1 risk variables used in the development of this belief
network model, ranked fiom most dependent to most independent, with al1 variable states
definitions, and ~Iassifications listed. The columns in the appendix are listed and
explained in Table 3.12.
3.3.1 CONSTRUCTION Rrs~s
Construction risks, in the context of this project, are defined as risk variables that occur
as a direct result of, or directly affect the building construction. If one studies the risk
variables in this group, it is apparent that these are risks rnost affected by. or under the
control of the main contractors on site. The construction risk variables are shown in
Table 3.1: Appendiv A columns
Table 3.2.
Column Heading Ris k Name/Source Risk Definition Risk States Risk Parents
The first three variables- equipment cost, labour cost and materid cost are the three
variable used to predict the actual project cost, which c m then be compared to the
budgeted cost. These three "predictor variables" will be discussed in more detail Iater in
this chapter.
Definition The name of the variabIe and the prirnary Iiterature source in which it was found A short explanation of the variable A list of al1 of the variable states that the variable may take on A Iist of al1 the variables that have a direct effect on the respective rïsk variable
Belief Xenrork Anaiysis of Direct Cost Ris& in Budding Constntct~on 20
Table 3.2: Construction Risks - - -
1 Risk 1 Source W Equipment Cost Labour Cost Material Cost
CI1 1989 CH 1989 CI1 1989
Il Overtime Construction Delavs
L
CII 1989, Thomas 1992 CI1 1989
Failure Delays Labour Productivity Work Quantity Deviations Matenal S hortage Material Waste Defective Work Equipment Productivity Material/Eaui~ment Loss
1 Flanagan and Norman 1993 Wideman 1992, Thomas and Napolitan 1993 CI1 1989 Nasir 2000 CI1 1989 .
- -- -
CI1 1989 Wideman 1992 CI1 1990
1 .l
Often, construction costs are impacted significantly by the project schedule. Factors that
Labour Injuries/Accidents Archaeo logical Survey Construction/Operations Interference Trafic Congestion Number of Workers on Site Construction TechnoIogy
cause the project to lag behind schedule may also indirectly put strain on the project
CI1 1989, Hinze et al 1998 Nasir 2000 E.upert Interview CI1 1989 CI1 1989 CI1 1989
budget. For example, overtime costs more than regular time, and as a result, adversely
affects project cost. Other factors related to the project schedule are construction delays,
participant failure delays, labour productivity, equipment productivity,
construction/operations interference, and traffic congestion on site. Each of these factors
alone or in combination can cause a project to fa11 behind schedule and increase cost as a
result.
Work quantity deviations, material waste, and defective work al1 affect the material
quantities that are used on the project. This has a direct impact on project material cost,
as does the use of foreign purchased goods and services.
Belief Nenvork Anaiysis of Direcf Cost Risk in Brriiding Constnrcrion 21
Finally, material/equipment loss/darnage, labour injuriedaccidents, the number of
workers on site, and technology requirements directly or indirectly affect the cost of a
building project.
Projects of a large magnitude such as those being studied in this research require very
significant contractual and legal agreements. It is quite important to t&e account of these
arrangements to gain a full understanding of the environment in which a project exists.
Table 3.3 outlines these risks.
Contract clauses create the iegal environment under which the project participants
operate. In conjunction with the contractor payment type, they also determine the party
to which the cost risk on the project is transferred, This risk can either be accepted by the
contractor, the owner, or shared by both parties.
Table 3.3: Contractual/Legal Risks
Construction claims c m cause significant project delays and cost increases. Claims c m
also serve to create animosity between interested parties, thus affecting future work on
the project,
Ris k Construction CIaims Contract Clauses Contractor Payment Type
Especially on large projects, project management iç a crucial elernent of cost control.
Source CU 1989, Diekman and Nelson 1985 CI1 1989 CI1 1989
Projects that are well organized and managed stand a better chance of finishing on time
Beitef Xenvork rlnaiysis of Direct Cosr Risk in Btrilding Consmcr~on 22
and on budget @ozzi et al. 1996). There are a number 04 factors that make up project
management, but the variable that al1 others are related IO is the composition of the
project management (PM) tearn itself. Table 3.4 outlines al1 of the factors included in
this mode1 that relate to the management of the project.
Table 3.4: Management R i s k Ris k Cost Accountino
Cooperative Environment 1 Expert Interview, Larson 1997, McMarnamy 1997 Il
- - -
Source Ex~er t Interview I
Y
Trade Coordination Long Work Stoppages Materials DeIiverv
Wideman 1992 CI1 1989, Zack 1997 CI1 1989
PM knowledge of area 1 CI1 1989 11 PM PM work familiaritv
Qualified key PM personnel 1 CI1 1989
The availability of PM personnel, their knowledpe of the area. farniliarity with the type of
Expert Interview, Dozzi et al, 1996 CI1 1989
work being done, and their comrnitment to the project goals are factors that directly affect
1
how well the project is organized, and consequently the smccess or failure of the project
in relation to the budget and schedule.
One event that occurs on many projects is a prolonged work stoppage due to a labour
dispute. Strikes c m affect project schedules and deadlimes, again indirectly affecting
project cost. They can also cause construction clairns for either extra time or money by
other project participants, directly increasing costs. One w a y to mitigate such claims is
by the use of Partnering. Partnering is a management technique pioneered by the US .
Army Corps of Engineers in 1983 in response to $1 B in outstanding clairns and appeals.
Partnering has been shown to improve relationships on building projects and these
improved relationships can lead to improved Trade Coordination, and more prompt
Beliej Arenvork Analysis of Direcr Cost Risk in Building Constnicrton 23
Materials Delivery. These are two other management factors found to affect cost on
long-term construction projects.
Finally, cost control is highly dependent on accurate and timely cost reporting and
accounting- Project managers that keep carefùl track of costs on a consistent basis stand
a better chance of spotting problems and addressing them before they get out of control
and seriously affect the final project cost.
3.3.4 OWNER RISKS
The project owner uitimately makes d l decisions with regards to project construction -
the owner is in charge. As a result, the project owner has a significant impact on whether
the project finishes on budget. The type of owner determines the h d i n g source
(government, private, or some combination). The fùnding source, and financial stability
of the owner and this significantly affects the project philosophy regarding factors such
as budget revisions. In short, the ow-ner establishes the fiscal environment under which
the project is built. Table 3.5 shows al1 risk variables related to project ownership.
Table 3.5: Owner Risks r
One of the major cornponents of any construction project is the design of the building to
Ris k Budget Revisions
I
be constmcted. Construction cannot be completed prior to the submittd of design
Source Expert Interview
documents. It should be noted that the scope of this project is Limited to fast-track
Belief Nenvork Anaq'sis of Direct Cosr Risk in Building Consrnrcrion 24
Funding Source Owner Financial Stabiliw
Wideman 1992 CI1 1989 1
projects, that is, projects that are built while many of the design documents are still being
completed. Designs are produced as the construction requires them. Table 3.6 lists the
risk variables in this category-
Table 3.6: Desim Risks Ris k
Design Submittal Design Quatity
11 Tenant ~ e a u i r e r n e n t ~ h k s e -
Complexity/ConstructabiIity of Design Design Team Coordination
- Source Design News 1997 Flanaean and Norman 1993. Hester and Ku~renas 1987 Arditi and Gunaydin 1998 CE1 1990 CI1 1989 E x ~ e r t interview
Expert Interview 1
Because there is Iittle tirne in between design submittal and the use of design documents
in construction, timely production of a quality design is crucial in keeping the project on
schedule, and consequentiy, on budget. Changes to designs resdt in late design submittal
and problems such as defective work and reduced productivity, as do scope creep,
complex designs and changes in tenant requirements.
Three effective methods for reducing the cost of construction at the design stage are good
communication, coordination of design tearns and Value Engineering. Value
Engineering is an efFective design practice because redundancies in design are
eliminated, costs are saved, and problems anticipated. The project may, as a result, be
built more efficiently.
3.3.6 PROJECT CHARACTERISTICS ~ S K S
The type of project and its characteristics largely deterrnine the ease with which a
building may be constructed. Table 3.7 lists the risk variables in this category.
Belref Nenvork Analysis of Direct Cosr Risk in Building Consrnrction 25
Access and egress to the site? physical project size and other competing activity on site
Table 3.7: Project Characteristics Risks
are three factors that are critical determinants of the amount of congestion on site. They
Ris k Site Security Site Access Physical Project Size Cornpeting Activity on Site
also affect the ability of project supervisors to secure the site, thus protecting the project
Source CI1 1989 Expert Interview Expert Interview CI1 1989
from materials or equipment thefi. These characteristics are 1argeIy determined by the
location of the project and the previous use of the project site. Projects that are built on
land previously used for other purposes, or large-scale renovation projects (such as the
new terminal project at Lester B. Pearson International Airport) require much more
carefid planning and time. Ail of these factors directly affect cost, and the Iikelihood that
the cost may escalate as a result.
As much as factors within the project site boundaries affèct construction, so too does the
surrounding area and environrnent in which the project is buik The risk variables in this
category are listed in Table 3 -8.
Table 3.8: Location Risks
Beiief ~Venvork Analysis of Direcr Cosr Risk in Building Constn~tion 26
Ris k Foreign Purchased Goods Local Suitable Materials Suitable Equipment Availability Quaiified Local Labour Construction Support Facilities Locai Construction Market Availability of Energy Utilities Area Affluence
Source Stiglitz and Boadway 1994 CI1 1989, Laufer and Cohenca 1990 CI1 1989 Thomas and Napolitan 1995 CI1 1989 E x ~ e r t Interview CI1 t 989 CI1 1989 RandoI~h 1993
The affluence of the population of the surrounding area can affect attitudes and public
support for the project being built, Relevant public inquiries and hearings can be held up
indefinitely by citizens not in support of the construction. The affluence of the
population also affects the availability of construction support facilities such as housing
for labour and emergency medical services' as well as the presence of energy sources for
equipment.
Also important is the availability of locai labour and local equipment suitable for the
construction of the project. Laws of supply and demand dictate that greater availability
of goods or services reduce the cost of those goods and services. The availability of these
resources is greatly affected by the amount of other construction being done in the area as
compared to the capacity of contractors in the area.
3.3.8 ECONOMCC Rrs~s
There are two main types of risk variables in this category: performance of project
participants, and fiscal risks. Table 3.9 lists al1 of the risk variables in this category.
Table 3.9: Economic Risks
On occasion, contractors and suppliers to the project are unable to fulfill their obligations
Ris k Contractor Failure Subcontractor Failure Supplier FaiIure International Market Prices Construction Market Escalation Inflation Tax Rates Exchange Rates
to the project. The use of contractor prequalification processes has reduced the fiequency
- --
Source Flanagan and Norman 1993 Flanagan and Norman 1993 Flanagan and Norman 1993 StigIitz and Boadway 1 994 Widernan 1992 Stiglitz and Boadway 1994 CI1 1989 CI1 1989
Belief Nenvork .4naiysis of Direct Cost Risk in Building Consrrucrion 27
with which contractors on the project go out of business; however, insolvencies do occur.
U'hen they do, they can significantly impact project schedule and cost, not to mention the
fact that they may halt construction of the project altogether.
Fiscal factors that can affect the cost of construction projects are market escdation,
inflation, tax rates and exchange rates. These factors are al1 out of the control of the
project managers and project owners. As a result, they c m have a considerable impact on
final cost when they change in ways that are unexpected.
3.3.9 PO LITICAL RISKS
Politically related risk variables are generally out of the control of the project
participants. Table 3.10 lists the political nsk variables considered in this research.
Table 3.10: Political Risks
- - - - -- - -
Govemrnent stability and spending greatly affect the ainount of construction being done
Ris k Regulatory PenaIties Permits Required Government Spending on Construction Government
and consequently, market escalation and inflation. Government also influences
regulatory environments in which construction companies operate. Regulations and
permits are required on al1 construction projects, and if they are particularly stringent in a
Source Okpala and Aniekwu 1988, Wideman 1992 CI1 1989 CI1 1989, Stiglitz and Boadway 1994 CI1 1989. Stiolitz and Boadwav 1994
given jurisdiction, construction in that jurisdiction is more difficult to complete.
Belief Nenvork Analysis of Direct Cost Risk in Blrilding Constnrction 28
The rnost unpredictable and uncontrollable of risk variables on a construction project are
related to the environmental factors that are encountered. Project geology, altitude and
geology are factors of the physical environment that result in uncertainty in ground
conditions and the environmental sensitivity of a project site. In addition, natural
disasters such as mudslides or earthquakes are influenced by the ground conditions and
the prevailing geology of the area. Table 3.1 1 shows d l risk variables in this category.
Environmental Sensitivity 1 Flanagan and Norman 1993 II
Table 3.11: Environment Risks Ris k Ground Conditions
Source Flanagan and Norman 1993
Land-related natural disaster Weather Extremes Climate
The final major environmental factors that have an influence on project cost and schedule
Expert Interview CI1 1989, Thomas and Napolitan 1995 Mulholland and Christian 1999
Altitude Geology
are the weather and climate of the region. Both the ability to do work, and the
CaterpilIar 1997 CI1 1989, Cooper and Chapman 1987
productivity of labourers c m be reduced by inclement weather. The normal clirnate and
weather extremes such as hurricanes, tornadoes, ice storms, can seriously impede the
progress of a construction project.
3.4 R r s ~ LIST RANKTNG
Following compilation of al1 risk variables, the list of construction cost risk variables that
was compiled fiom the various sources was next ranked in such a way that only risk
variables lower on the list may have a causal effect on any particular risk. The reason
that the risk variables were ranked in this fashion is to aid in the construction of the belief
Belief :Ven~ork Analysis O/ Direct Cosr Risk in Building Constnrcfion 29
network; risk variables are drawn on to the network one at a time fiom the top of the list
to the bottom of the liste Connections may be drawn only fiom a newly entered variable
to those that are already on the model as appropriate. This is done to ensure that the
belief network model is acyclic (McCabe 1998).
To rank the lists from most dependent variable to most independent variable, a number of
intermediate steps were taken. First, each of the risk variables was grouped into one of
the ten main categories detailed in section 3.3. Afier the risk variables were categorized,
they were ranked within their groups. Literature was largely used in the ranking of these
lists, although some expert opinion was also solicited in the form of informa1 telephone
and persona1 interviews. Once the risk variables were ranked within their groups, the ten
groups were joined to create a master list. Note that the ten risk categories are ordered in
much the sarne way as the individual risk variables within the groups (groups lower on
the list in general affect groups higher on the list). This was done so that when the
groups were joined together, a master list of al1 risk variables would be formed that
followed the ranking rules. Some minor movement of risk variables between groups was
required following the joining of the groups, but on the whole the nsk variables were
correctly ordered. Table 3.12 is the result of the risk variable ranking.
Table 3.12: Ranked List of Construction Cost Risks
11 2. Labour Cost 1 Construction II 1
II 6. Cost Accounting 1 Management II
Construction Cost Risk Factor 1. Eouiornent Cost
3 . Material Cost 4. Construction daims 5. Overtime
11 7. Value Engineering ( Design II
Construction ContractuaVLegal Constmction
Ris k Ca tego ry Construction
Belief iVenvork Anaiysis of Direct Cost Risk in Btiriding Constmc~lon 30
1
I 8. Construction Delays 9. Failure delavs
Constmction Construction 1
Il 10. Contractor FaiIure ) Econornic 1 1. Subcontractor Failure 1 Economic 1 12. Supplier Failure 13. Labour productivity 14. Work OuantitY Deviations
Economic Constmction Construction
I I
11 22. Materials delivery 1 Management II
15. Material Shortage 16. Materia1 Waste
pp ---
19. Trade Coordination 20. Reaulatory PenaIties 2 1 - Long Work s t o ~ ~ a c e s
(1 23. Cooperative environment 1 Management II
Construction Construction
1 7. Design changes 18- Defective work
Management Political Management
11 24. International market mices 1 Economic II
Design Construction 1
. - -
25. Foreign purchased goods Location
II 27. Equiprnent productivity 28. SuitabIe eaui~ment availabilitv
11 31. Design Subrninal 1 Design II
26. LocaI suitable materials Location -1 -
29. MateriaV equiprnent Ioss 30- Labour Injuries/accidents 3 1. Qualified local labour 32. Ground Conditions 33. Archaeolozical Survev
Construction Location Constmction Construction Location EnvironrnentaI Construction
11 37. ~ u d g e t revkons 1 V
1 Owner II
1
I
11 4 1. Contractor payment type 1 ContractuaVLegal
3 5. Design Quality 36. Scorie Creen
38. Tenant Requirement Change 39. PM 40. Contract Clauses
Design Desion
Design Management Contractual/Leoal
42. PM work familiarity 43. PM knowledge of area 44. Construction/Ouerations Interference
Management Management Construction
-
45. Site security 46. Trafic congestion 47. Site access 48, Permits Reauired
11 53. Design team coordination 1 Design Il
-
Project Construction Project Political
-- --
49, Number of workers on site 50. Environmental sensitivity 5 1. Construction technology requirements 52. Corn~IexitY/ConstTUctabilitv of desion
~onstruct& Environmentai Construction Design
54. Qualified key PM personnel 55. Construction .sumort facilities
Management Location
56. Funding Source 57. Construction market escalation 58. Local construction market
Belief ;frenvork Anaiysis of Direcr C m Risk in Building Constnmion 3 1
Owner Economic Location -
59. Owner financial stabiiity 60. Physical project size 6 1. Competing activity on site
Owner Project Project
62. AvaiIability o f energy Location
64. Area affluence 65. Inflation
Location Economic
-- (1 7 1. Weather Extrernes 1 ~nvironmental 11
1 - -
68. Exchange Rates 69. Government 70. Land - related naturd disaster
1 63. Utilities
66. Government spending on construction 67. Tax Rates - - - . . - - . . . -
Econornic PoIitical Environmental
Location
Political Economic
72. CIirnate 73. Geo,gaphy
3.5 Rrs~ STATE DEFINITION
Afier ranking the risk variables to be used in the model from the most dependent variable
to most independent variable. the final task in the Risk Identification and Definition stage
of belief network Mode1 building is to define the states for every risk variable. Risk
states are the set of values that each variable may attain. The set of Risk states must be
mutually exclusive and collectively exhaustive. It must not be possible for any variable
to achieve more than one of its states at once, and the set of states must also include every
possible outcome that need to be uIcIuded in the model
Environmenta1 Environmental
74, AItitude 75. Geology
Nthough it is important to be diligent in coverïng a11 of the possible states, the greater the
number of variable states, the greater the nurnber of probabilities that must be elicited
f?om experts in later stages of mode1 development. Therefore, a balance must be struck
between completeness and overkill. To stnke that balance, an attempt was made to
ensure that each variable in the model is binary; that is. it has only two states. This may
introduce errors in accuracy. For example, consider the variable International Marker
l Environniental Environmental 1
Belief ~Venvork Analysis of Direct Cosr Risk in Building Construction 32
Relured Price Increases. The two states for Uris particular variable were "Greater than
expected" and "Less than or as expected". Zn truth? International Marker Related Price
lncrecrses can take on any value between -infïïty and +infiniS. To introduce the
number of states that would be required to be compIete wodd serve t o introduce
computational complexity that would make expert knowledge solicitation almost
impossible. For variables in which more states were absolutely necessary, more states
were added.
It is important to note, however, that extensive research into the best possible variable
states for each variable was not undertaken. Instead, the focus was to ensure that the
states for any given variable were mutually exclusive and exhaustive. Fwther research
needs to be conducted to better amve at the number of , and definition of, states for every
variable in the model.
3.6 DIvORCING VAWLES
A number of variables were added in the relationship identification process to reduce
computational complexity in the model. They are not shown in the original list of
variables as they were not part of the literature search process. These variabies and
descriptions of each will be discussed in Chapter Four: Relationship Identification.
3.7 PREDICTOR VARIABLES
As mentioned earlier, three variables were identified that are used to predict the final cost
of the project. The three variables are material cost, labour cost and equipment cost.
Beiief Nenvork Analysis oj' Direct Cosr Risk rn Binlding Consrrticrron 33
These three variables were found to have an impact on ten different building construction
cost centres. The new terminal project at Lester B. Pearson International Airport in
Toronto was used as an example project to provide the research with Spica1 construction
cost centres for large scaIe building projects. A total of IO cost centres were identified as
being represented by the three predictor variables. The cost centres are:
Substmcture Work (Excavation and B ackfill, Piling)
Structural Steel
Structural Concrete
Other Concrete (Concrete on Metal DecWSlab on Metd Deck)
Purchased, Prefabricated Construction Matenals (Precast Concrete,
Metal Deck, Miscellaneous Steel)
Roofing
~AC/Plumbing/EIectrical/Mechanical
Building Technical Systems/Comrnunications Systems/IT, Baggage
Handling, Security
Masonry, Carpentry
Finishings (Waterproofing/Fireproofing, Skylights, Doors, Ceilings,
Wall Finishes/Floor Finishes, Painting, Floorifig, Specialties, Window
Washing Systems, Fire Protection, Signs and Signage, Curtain wall,
Hardware, Glazing, Elevators/Escalators/Travelators, etc.)
Initially, these cost centres were to form the basis of the predictor variables. In effect, an
equipment cost, material cost, and labour cost variable was to be applied to each of these
cost centres. Following fùrther discussion with experts, it was determined that three
Belie f Nehrork Anabsis oj' Direct COSI Risk in Btrrlding Construction 34
macroscopic variables (Cost of Equiprnent, Casi of Labour, Cost of Materials) would
provide al1 of the accuracy required for a mode1 of this type. As a result, there are three
predictor variables used to assess the likelihood of various cost overruns in this research-
The next stage of research focuses on the determination of relationships between rïsk
variables.
Belzef Network Anaiysis of Direcf Cost Risk in Building Comnlcrion 35
Chapter Four: Relationship Identification
4.1 INTRODUCTION
The frrst step in the development of the belief network involved the identification of
factors that may affect the cost of a construction project - the nodes of the belief network
were identified. The second stage of belief network development involved the
identification of relationships between nsk variables, that is the connectors on the beIief
network. Two main methods were used in the relationship identification. They were:
0 Expert Swvey
Literature Search
Following each of these steps, an effort was made to reduce the cornplexity of the belief
network by eliminating nodes that had littie effect on the overall model, along with
eliminating direct connections between variables that could be made in other ways.
4.2 EXPERT SURVEY
A survey was developed to elicit expert opinion with regard to the identification of
relationships between risk variables. This survey was used to identie relationships that
were not documented in any available literature. A study on Schedule Risks in
Construction (Nasir 2000) used a similar survey to gain an understanding of how
schedule risk variables affect others. The same survey format was used in this research.
The 75 ranked schedule risks identified in the Iiteratwe search were listed down the side
of a 75x75 matrix, as well as across the bottom. The risk variables down the side of the
matrix represent causal variables (or parents) and the risk variables across the bottom
Beliefh'envork Analysis of Direct Cost Risk in Buildrng Consrnicrion 36
represent effect variables (children). AIso, as stated in Chapter Three, the nsk variables
were ranked so that no risk higher cn the list could have an effect on any Rsk Iower on
the list. Ranking the variables in this rnanner allowed the opportunity to eliminate one-
half of al1 the relationship pairs in the matrix (the upper-rïght half of the matrix was
composed of cause-effect relationships that were deemed impossible by virtue of the
ranking process.) This was a critical step; a 75x75 matrix would require the evaluation
of 5625 cause-effect pairs. Eliminating half of the relationships Iefi 28 13 relationships to
be studied. This, however, was still an unacceptable Iength. To furuier reduce the
number of cause-effect pairs to be analyzed in the survey, each pair was examined and
impossible causai variables were elirninated for each of the eBect variables in the survey.
This was done using expert interview with two experts, as well as literature wherever
possible. For example, it was determined that Site Sectrriiy would have such a negligible
or impossible effect on the Cost of labozcr that this particular pairing could be omitted
fiom the survey. The result of this process is a survey, a portion of which is shown in
Figure 4.1.
Grey-shaded areas are either impossible, or negligible. Unshaded boxes are relationships
that are possible; the experts were asked to make an assessrnent of the stren,& of these
relationships. The scoring system used by the experts was as follows:
O = causal risk has no effect on effect risk
1 = causal risk has a weak effect on effect risk
m 2 = causal risk has a significant effect on effect risk
r 3 = causal risk has a very strong effect on effect risk
Beliej~Venr.or.4 Anaiysis of Direct COSI Risk in Building Consinicrion 37
Fifteen experts were asked for survey opinions. Each expert was currently working as
part of the project management team at Pearson International Airport, but had previous
experience in a wide variety of different aspects of the building construction process. The
range of expert experience included individuals who had worked previously as
estirnators, daims evaluators, operations managers, and project upper management. Most
had worked on airport projects before, as well as other types of non-residential
construction. Experts were selected to ensure that survey group expertise was varied.
Surveys were conducted by distributing the questionnaires to the experts, explaining to
the group as a whole how the survey was to be filled out? and then being available for
questions over the phone or via e-mail. The experts were given a week to complete the
work. Nine experts responded to the request. The survey rnay be found in Appendix B.
i3eiief:Venvork i inalpis of Direct Cosr R d rn Biirlding Consrnrcrron 38
4.3 SURVEY RESULTS ANALYSIS
After the experts completed the surveys and retumed hem, the next step was to use those
results to determine which relationships should be included in the beiief network. This
required a consistent set of niles to analyze the colIection of responses. This research
used a set of rules similar to that used in the analysis of schedule risk research (Nasir,
2000). A two-tiered approach was used. The f ~ s t step was to eliminate al1 relationships
that received results that strongly suggested the experts felt there was no significant
cause-effect relationship; rejection tests were used for this purpose. Second, the
rernaining relationships had to pass one of severd acceptance tests that indicate a
significant relationship. Cause-effect pairs that did not fail any of the rejection tests, and
passed at least one of the acceptance tests were deemed to be valid pairs that should be
incIuded in the model. The elimination and acceptance tests used in the construction of
the model are shown in Tables 4.1 and 4.2.
Survey Rejection tests Result
Table 4.1: Relationshil
No Relationship No Relationship
1
No Relationship
Condition
Average score < 1 .O 1 Average score < 1.5 and weak scores (Os, 1s) outnumber strong scores (2s, 3s) Average score < 1.5 and data skewness positive
(1 Average score > 1.99 1 Relationship
Table 4.2: Relationship Survey Acceptance Tests Condition
11 No zeroes in survev result set 1 Relationship
Result
Average score > 1.49 and strong scores (2s, 3s) outnumber weak scores (Os, 1s) Average score > 1.49 and skewness negative or zero
Belief Xenvork .4nalysis oJDirecr Cos1 Risk in Building Cons~ruc~ion 39
Reiationship
Relationship
Skewness characterizes the degree of asymmetry of a distribution about its mean. In
sirnpler tems, it measures whether the Ionger tail of the statistical distribution lies to the
positive or negative side of the mean. If the Ionger tail is to the Ieft (Le. negative) side of
the mean, then more of the data is grouped around higher values; the skewness is said to
be negative, and vice versa. Skewness is important to this analysis because it helps to
determine whether the survey results are "Ieaning" toward values that indicate acceptable
relationships.
Of the 452 relationships analyzed in the s w e y . 171 were accepted by the experts, 28 1
were rejected. Appendix C shows the distribution of the number of responses for each
score, for each parent-child combination sweyed. The number of Os, ls, 2s, and 3s are
shown,
These tests are, in general, more inclusive than the schedule risk tests (Nasir, 2000). As a
result, 58 additional cause-effect pairs were accepted in this research that would have
been rejected by the scheduie research criteria. Each of these 58 "borderline
relationships" were discussed with tcvo experts to determine which should be included,
and which should not be included in the model. Table 4.3 is a list of borderline
relationships that passed the criteria in this research, but were rejected as a result of
expert review.
Belief ~Venvork ..lnalysis oJDirecr Cosr Ruk in Building Cansrnlcrron 40
Following the expert survey. a Iiterature search was conducted to detemine if there were
reIationships that existed that were not identified as a resuft of the expert survey. Results
of the similar schedule risk (Nasir, 2000) research were used, as were the sources from
the risk identification literature search. Table 4.4 shows parent-child (cause-effect)
relationships that were identified as a result of this effort.
Table 4.3: Borderline Relationships eliminated as a result of expert analysis l 1
Parent Variable 1. Site AccessEgress 2. Land related naturai disaster
Chiid VariabIe Site Security Availabilitv of enerm
3 - Construction market escalation 4. Work Quan:ity Deviations 5. Work Quantity Deviations 6- MaterialfEquiprnent LossKlarnage 7. Owner Financial Stability 8. Subcontractor FaiIure
Budget revisions allowed Construction Clairns Construction Delays Construction Delays Contract Clauses Contractor FaiIure
9. PM ~ b i l i t y / W i G ~ n e s s to meet obligations 10. PM Familiarity with type of work I 1. Ground Conditions 12. Construction Market Escalation
17. Geology 1 Work Quantity Deviations
- -
rade Coordination Trade Coordination Equipment Cost Labour Cost
1 13. MaterialEquipment Loss/Damage ' 14. Design Changes 1 15. Geology
1 6. Budget Revisions Allowed
Material Cost Defective Work Design Changes Work Quantity Deviations
18- Presence/location of utilities 19. Stabilitv/so~histication of zovernment
Equiprnent productivity Exchanoe rates
20- Complexity/Constnictability of Design 2 1. Weather Extrernes 22. StabilitylSophistication of Govemment
- --
26- Design Quality 1 Design Tirneliness
Labour Productivity Land related naturaI disaster Permits required
23- Altitude 24. Qualified Key PM Personnel 25. Sumlier Failure
Weather Extrernes PM Farniliarity with type of work Subcontractor failure
27. Weather Extremes 28. Land Related NaturaI Disaster 29. Long Work Stoppages
Only 18 additional relationships were identified in the literatwe study, but these
Overtirne Environmental Sensitivity Labour Productivity
30. Ground Conditions 3 1. Environmenta1 Sensitivity
relationships added to the completeness of the overall model. Also of note are the
Labour Productiviv Labour Productivity
BefcefrVehvork Anaipis of Direct Cost Rrsk in Building Construcfion 41
variables that appear in Table 4.4 that.were not part of the original list of risk variables
developed in the Risk Identification step, or present in the expert survey. These extra
variables were added as part of the Divorcing process originally introduced in Chapter
Three. The reason that these relationships were not identified in the expert survey is that
the literature search to identiQ relationships occurred afier the survey results were
identified. To ensure model completeness, these relationships were added.
In some cases, risk variables were found to have a large number of parent variables. The
Table 4.4: Variable Relationships identified in Literature Study
nurnber of required probabilities of a single chiid variable increases exponentially with
Parent Variable 1, Climate 2. Labour Injuries/Accidents 3 J - Project Material Shortage 4. Suitable Equipment Availability 5. Number of Workers on Site 6. Trafic Congestion on Site 7. Construction Technology Requirements 8. Design Changes 9. Defective Work IO. Design Changes I I . MateriaEquipment Loss Darnage 12, Materials Delivery Prompmess 13 - Material Waste 14. Altitude 15. Materiais/Equiprnent LossiDamage IO. Archaeological Survey 17. Construction Technology Requirements 18- Project Material Shortage
the addition of a single parent variable. A child with 2 parents and each parent with 2
Child Variable Short Breaks Short Breaks Short Breaks Short Breaks Labour Congestion Labour Congestion Labour Understanding of Design Work Quantity Deviations Work Quantity Deviations Project Material Shortage Project Material Shortage Project Materia1 S hortage Project Material Shortage Equipment Productivity Suitable Equipment Availability Ground Conditions Design Quality Cost of Materials
states requires the determination of 22 = 4 probabilities; the sarne child with 5 parents
requires 23 = 32 probabilities (it is a 2" relationship). In this model, there were three
variables (construction claims, construction delays, labour productivity) with at least ten
Belief 'Venvork Analysis of Direct Cost Risk in Building Cornlaion 42
parents. These three variables done would have required the solicitation of 68608
probabilities eom experts in the relationship quantification stage of research - more Sian
the other 72 variables combined,
A technique called "Divorcing" (Jensen, 1996) was used to reduce the number of
probabilities required in the relationship quantification stage, and the number of
calculations required once the mode1 was complete. Divorcing involves the introduction
of "intermediate" variables that are placed on the network between the existing parent
and child variables. Introduction of these intermediate variables reduces the exponential
effect of having a Large number of parents.
The Constrz(cfion CIaims variable, for example, had 12 parents. Without divorcing, there
would have been 4096 cornbinations of parent states to examine. Following divorcing,
54 different cornbinations needed to be studied.
Available Qzralzfied key PM
Personnel
PM A b ility/WiZZingness to meet
o bligarions
Tenant Requirement Change
Design Changes
Scope Creep
Design Tirneliness
Constrzrctio n De Zays
Overtime
Long Work Stoppages
Defective Work
Grotrnd Conditions
Trade Co ordination
Prior to divorcing, the twelve parents of the Tonstniction Claims" variable were:
Belie/iVenvork linalysis of Direct Cosf Risk in Building Consrnrcrion 43
Divorcing the Construction Claims node involved
variables. The four intermediate variables were:
Design Related CZuims
Delay Reluted Claims
Field Reluted Claims
PMAbiMyto MitigateClairns
the addition of four intermediate
Each of the original 12 parent variables was assigned as the parent of one of these
intermediate variables. The original parent variable Sius becarne "Grandparents" to the
Constrzrction CZaims variable. Table 4.5 shows how each original parent variable was
assigned.
Table 4.5: Divorcine the Construction Claims Variable - New Construction Claims Parent Variable Design Claims
Delay Clairns
Original Parent Variable; Construction CIaims "Grandparent Variable" Design Changes Scope Creep Design Subrnittal Tenant Reauirement Change
Construction Delays Overtime Long Work Stoppages l
Field Clairns Trade Coordination Ground Conditions
l
As a result of this divorcing process, 8 probabilities were collected for each of the D e l q
Claims and Field Cluims variables, 16 for the Design Clciirns node, while 4 probabilities
/
need to be collected for the PM ability to mitigate claims variable. In addition, since the
Defective Work
PM Ability to Mitigate Clairni I
Qualified key PM personnel PM
four intermediate variables are now the only parents of the Construction Claim variable,
I
16 more probabilities were collected for a total of 52. Belief ~Venvork Analysis of Direct Cost Risk in Building Consrnrcrion 44
The Conslruction Delays and Labour Productivity variables were divorced in a sirnilar
manner. Details are found in Appendix D. The appendix shows divorced configurations
of parent variables for each of the three divorced variables in the model. Figure 4.3
shows an example of what is found in Appendix D. Figure 4.2 shows the original
Constrziction Claims configuration. Figure 4.3 shows the divorced situation.
Figure 4.2: Non-divorced Construction CInims Variable
Figure 4.3: Divorced Ctmstruction Chims Variable
Belief h'envork Anaiysis of Direcr Cost Ri& in Btrilding Consrnrcrion 45
4.6 DATA REDUCTION
Following the determination of valid relationships for the belief network model, and the
divorcing process for three of the variables, it was important to further reduce the
computational complexity of the rnodel (Sarkar and Murthy 1996). Each of the
modifications invoIved the elimination of either a risk factor, or a variable connector. A
description of each of the modifications follows. Further information may be found in
Appendix K.
4.6.1 RELATIONSHIP ELIMINATION: TENANTREQUIREMENT CHANGE-DESIGN CLAIMS
The Design CZciirns node was introduced as a divorcing variable for Constrzrction CZaims.
Originally, it had four parents. They were:
Design Changes
Scope Creep
Design Timeliness
Tenant Requirernenr Change
Tenant Requirement Change, however, is a parent of Scope Creep. It was determined
that the Tenant Requirement Change variable would influence the Design Clnirns
variable through this mitigating variable (Tenant Reqzrirernenr Change remains as a
"grandparent", so to speak). As such, the connection between Tenant Requirement
Change and Design CZaims was removed.
BelieJNenvork Anolysis of Direct Cosr Risk in Building Consfnrction 46
4.6.2 R~ZLATIONSHIP ELIMINATION: QUALIFIED LOCAL LABOUR-LABOUR DELA YS
Labour Delays is a node that was introduced as a result of the divorcing process
involving the Constrzïction DeZays variable. Original parents of the Labozïr DeZays
variable were:
Labour Productivity
QuaZzFed Local Labour
Defective Work
Long WorkStoppages
Trade Coordination
QunlzJied Local Labour is a parent of both Lubozïr Prodzïctivity and Defective Work. As
a result, it affects Labour Delays as a grandparent through these two variables, and the
QzmIz@ed Local Labour - Labozïr DeZays connection was rernoved.
Original parents of the Project Materid Shortage variable were:
Local Szïitable Materials
Design Changes
Materiuls Delivery Promptness
Materiul Waste
Local Suirable Materiuls, a parent of iMateria1.s Delivery Prompfness is therefore a
grandparent of Project Material Shortage. As a result, the Local Szritable Materials -
Project Material Shortage pair was eliminated.
Bekf Nenvork Analysis o j Direcf Cosl Ruk in Brtilding Consrrucrion 47
Tenant Requirement Change is a parent of Scope Creep, which is also a parent of Design
Changes. As a result, it was determined that Tenanr Reqtrirement Change would affect
Design Changes through &ope Creep. The Tenant Requirement Change - Design
Change comection was therefore elirninated
Design Team Coordination is a parent of Scope Creep, which is also a parent of Design
Changes. As a result, the connection between Design Team Coordinafion and Design
Changes was eliminated because it was determined that Design Team Coordinarion had
influence through Scope Creep.
4.7 MODEL STRUCTURE
A nurnber of techniques, including Divorcing, Risk EIimination and Relationship
Elimination were used to minimize the nwnber of connections on the belief network
model. These techniques were employed in such a way that the completeness of the
rnodel was not compromised. Risk variables were eliminated only when they had little
impact. Relationships were elirninated only when the original parent variable maintained
an influence over the child in a "grandparent" role. The resulting rnodel has 87 variables
(including added divorcing variables and 3 predictor variables), and 152 connections
(including 134 risk connections and 18 connections to predictor variables).
BeiieJNenvork AnaIysis of' Direcl Cost Risk in Building Consrnrction 48
Figure 4.4 shows a completed diagram of the entire beIief network model. It is difficult
to discern each of the nodes and connections by Looking at the chart itself; a table with
each child variable, dong with respective parent variables, variable definitions and
variable States rnay be found in Appendix A.
Bslief Nenvork Analysis of Direct Cost Risk in BzrilâÏng Constnlc~ion 49
Chapter Five: Probability Determination
5.1 INTRODUCTION
Following the identification of relationships between risk variables, conditionai
probabiIities for every node were determined for each parent state combination. Expert
survey was used to determine these probabilities. This was quite a long and involved
task, and steps taken to reduce the extent of this exercise were documented in the
previous chapter (relationship elimination, risk elimination). In this chapter, three
additional swey-reducing techniques are detailed. Also, the steps taken to determine
each of the conditional probabilities required are also discussed.
5.2 DATA REDUCTION
There are 87 variables, 153 variable connections on the cornpleted model. As a result,
there are 493 conditional probabilities required for connections behveen risk variables,
1568 required for connections to predictor variables. Clearly an effort was required to
reduce the nurnber of probabilities that were to be determined by expert survey. Three
main techniques were used in order to accomplish this goal. They were:
@ Asymrnetric Assessrnent
@ Parent State Ranking
8 Probability Cuve Development
Each of these three techniques wiil now be discussed in turn.
Belief Nenvork Anaiysis of DÏrect Cost Risk in Building Cons!nrcrion 5 1
5.2-1 ASYMMETRIC ASSESSMENT
Asymmetrk Assessment is a technique used to eliminate parent state combinations that
either do not make sense, or are dominated by a subset of the parent state variables,
Figure 5.1 shows an exarnple of a variable that was asyrnmetrically assessed. A shortage
of materiais on site is a critical factor that can put a project behind schedule. Parent
variables of the Muterid Shortage variable are Design Changes, Murerial/Equipmenr
Loss/Damage, Materials Dehery Prornptness. and Mulerial Waste. Most importantl y,
however is the delivery of materiais to the site. Without materiais on site, no arnount of
design changes, materials loss or darnage, or material waste matter. In effect, the
Materials DeZivery Promptness dominates the three variables when its state is "frequently
Iate".
Frequently Late Generally on time
b ~ a t e r i a l Waste
ateriaVEquipment Loss
sign Changes Maior Minor or no or no sign Changes M aior Minor or no
MateriaVEquipment Loss Major
Design Changes m ~ a i o r F=
Figure 5.1: Asymrnetric Assessment structure for Project MaterialS/'ortage
The "generally on time" state of the Mderiuls DeZivery variable is not dominant. As a
result, al1 of the other combinations of the other parent variables must be considered. On
Relief rVenvot-k Analysis of Direct Cosl Risk in Bt~ilding Constnrction 52
the other hand, when materials are kequently delivered late to the site, the other parent
variables need not be considered. The portion of the asymmetric assessment as shown
above reflects this fact,
In this model, the following variables were asyrnmetrically assessed:
Cons&rzrction Delays
* Work Qzlantity Deviations
Project Material Shortage
O Sztitable Equipment AvaiZab iZi@
TI-afic Congestion on Sire
Asymrnetric Assessrnent structures for al1 of the above variables may be found in
Appendix E. The structures of the Asymmetnc Assessrnents in Appendix F are as shown
in Figure 5.1. Probabilities are required for each of the termination points in the
structure. In Figure 5.1, for example, the "Major" and "Minor or no" States of Design
Changes are termination points, and require that probabilities be surveyed.
The benefit of asymmetrically assessing variables is clear from studying the structure of
the Mntei-id Shortage variable asymmetric assessrnent. In this case, only nine parent
state combinations need conditional probabilities attached to them. Without asymmetric
assessment, 16 probabilities would need to be determined. Not only does this accomplish
shortening the expert survey, but it seemed as though the survey was easier for the expert
to handle with fewer probabilities to assess for a single variable. That is, trying to
differentiate between parent state combinations when there are 16 such combinations is
Eleliej~Venvork Rnalysts of Direct Cosr Risk in Bzrrlding Consfnrcfion 53
much more difficult than if there are only 9 combinations. Asymmetnc Assessrnent
reduced the effort required from experts.
5.2.2 PARENT STATE COMB~NATION ~ N W N G
Another technique used to reduce the effort required from experts was tested on a limited
basis in this study. Parent state cornbinations for every variable were ranked after careful
analysis from highest likelihood to lowest Iikelihood of causing a negative impact on the
child variable. An exarnple of this is shown in Figure 5.2. This was done in an attempt,
again, to reduce the effort required from the experts.
In Figure 5.2, the first colurnn is an identification number. The second column shows the
combination of parents and parent States. The last colurnn in the table shows the child
variable, and child state.
In addition to this ranking of al1 variables, some variables that had a large number of
parent state combinations were subject to an alternative method of surveying. Instead of
asking al1 experts to attach a probability to every combination, one of the three experts
was asked to reply to only every third or fourth combination. Probabilities in between
surveyed combinations were interpolated using the regression tool in Microsofi Excel.
Regression analysis is used to minimize the sum of the differences between predicted and
actual values. Each of the five trend-line regression tools (linear, logarithmic, 2"d degree
polynomial, power and exponential) were tested for each of the variables surveyed in this
manner. The regression that produced the R-squared value closest to 1 (the best fit) was
Belief :tlenvork Anafysis o/ Direcl Cost Risk in Building Consrnrcrion 54
chosen to interpolate the data not surveyed- Important to note is the fact that the values
given by the experts were used (Le, the regression curve vaIues for parent state
combinations replied to in the survey were not used). Again, this resulted in fewer
questions being asked of the expert, and a faster survey completion tirne.
ID# Parent Variable and State ChiId Variable. state 6 1 I ~ a j o r Construction DeIays Vif i l 1 Result in
l ~ o r s e than Expected Labour Productivity
l ~ r e s e n c e of Scope Creep
I --
Construction Delays Wi l l Result in *expected Overtime o or se than Expected Labour Pmductivity
-
3 Major Construction Delays Wi l l Resul t in -expected Overtime
IAS expected o r better Labour Productivity
4 Major Construction Delays WiII Result in ,expected Overtim e
(AS expected or better Labour Productivity
5 Minor o r no Construction Delays Wi l l Result in expected Overtirne
l ~ o r s e than Expected Labour Productivity
l ~ r e s e n c e of Scope Creep
Wil l Result in zexpected Overtime I 6 Minor or no Construction Delays
l ~ o r s e than Expected Labour Productivity
No Scope Creep
Wil l Result in >.expected Ovenime e --
7 I ~ i n o r o r ni Construction Delays
[AS expected or bttter Labour Pmductivity
I ~ r e s e n c e o f Scope Creep r
Wil l Result in >expected Overtirne I 8 Minor or no Construction Delays
IAS expected or better Labour Productivity
!NO Scope Creep
Figure 5 i: Ranking from severe conditions least severe conditions, Overfime child variable
The variabIes swveyed in this manner were:
Suirable Equipment Availnbiliy
Work Quantiiy Deviafions
Labour Productivity
Belie/Nenrork Analysis of Direct Cos1 Risk in Building Constnrc~ion 55
Table 5.1 shows the child variable, regression c u v e used, regression equation, and
corresponding R-squared value.
Table 5.1: Regression of Parent State-interpoiated variables
- - --
As shown above, the R-squared values are certaidy reasonable. The curves fit the
Availability Work Quantity Deviations Labow Productivity
surveyed data relatively well. In addition, when the interpolated values were compared
R-squared 0.67
Child Variable Suitable Equipment
to the values surveyed Erom the other two experts that answered the same questions, they
Exponential
2nd Degree Po lvnomial
were found to be quite similar.
Regression Type Logarithmic
Table 5.2 is an exarnple cornparison for the Labozrr Procizrctivity variable. The difference
between the interpolated value and the two sux-veyed values is shown as well. As c m be
seen, the difference between surveyed and interpolated values is relatively small, and
acceptable given the precision of this survey (it will be explained later that surveyed
values are acceptable if they were within 20% of the average).
Regression Equation y=- 16.7Inxt80-3
Y=92.1 exp(-0.123 7x)
y=-0.2 1 x'-0.57x+9 1.1
Experts 2 and 9 were surveyed for a11 of the parent state combinations. Expert 7 was
surveyed only for rankings 1, 5, 9, 13 and 16. The other values for Expert 7 were
interpolated.
0.59
0.73
Belief A'envork rinalysrs of Direct Cosr Risk in Building Consrntcrion 56
Cornparisons simiIar to that offered in Table 5.2 for the other two variables surveyed in
this manner may be found in Appendix F. Shown in the appendk is the chart format as
in Table 5.2, as well as the regression graph that corresponds to the analysis.
Average Differenix 1 8-2 12.7 7.0 1
Table 5.2: Difference befween interpolated values and surveyed values
%le not used extensively in this research, this technique sped up the survey process.
14 15 16
and reduced the effort required fiom the expert. It merits further attention in fi~ture
studies. The experts that were surveyed in this manner were quite receptive to this
60 50 30
method, and were thankful that survey time was reduced. The method did take a bit of
explmation, but once they understood what they were doing. they proceeded through the
40 40 20
questions quite quickly.
5.2.3 PROBABILITY CURVE DEVELOP~MENT
As srated in the begiming of this chapter, 1568 probabilities are required for the
40 30 30
connections to the predictor variables (muterid cost, labotir cos[, equiprnent cost). It
would take months to survey experts for these probabilities. As a result, this method was
46.7 40.0 26.7
Belief Xehvork Analysis of Direct Cosr Risk in Building Consrrucrion 57
-20 -2 0 nia
O 10 nia
-6-7 0.0 nia
not used. Instead, normal probability curves were developed to produce the probabilities
required for these predictor variables. Two main steps were required. First, parent state
combinations needed to be ranked. Second, normal curves were produced that assigned
probabilities to each child state, based on a corresponding parent state combination-
5.2.3.1 PROBABILITY CURVE PARENT STATE M N K I N G
The firsr step in using the probability curves kvas to rank the parent state combinations
from worst-case scenario to best-case scenario. Ranking was done by refemng to the
strengths attached to each relationship by the relationship identification expert survey
conducted in Chapter Four. For example, the Equiprnenf Cost predictor variable has six
parents. They are:
Szritable Equipment AvaiZubility
Equiprnent Productivity
Construction Market Escalcit ion
Inflar io n
Construc t ion Clairns
Value Engineering
In the relationship identification survey. experts were asked to judge the strengrh of the
relationship between each of these variables and Equipmenf Cost variables on a scale of
zero to three, A score of zero meant there was no relationship; a score of three meant a
very strong relationship. The average score returned by a survey of nine experts was
used to rank the parent combinations in t h i s stage of the relationship quantification.
Belief Nenvork Anolysis of Direcl Cost Risk in Bziilciing Consrnrcfion 58
Table 5.3 shows the strength of effect of each of the Equipment Cost parent variables on
the child variable.
Note that the final two parent variables, Construction Claims and Value Engineering
were not identified as parents by the expert survey. They were identified as part of the
Iiterature search. As a result, they were given the minimum score required to quali@ as
parents, 1.5. This minimum score is denved fiom the relationship rejection and
acceptance mies discussed in section 4.3 (Tables 4.1 and 4.2 detail these rules).
Table 5.3: Strength of parent variables on "Equipment Cost" predictor variable
1) Construction Claims 1 1.5 II
Equipment Cost Parent Variable
Suitable Equipment Availability Equipment Productivity Construction Market Escalation Inflation
[I Value Engineering 1 1.5
Strength of Parent-ChiId Relationship
2.22 1.67 1.78 1.75
When the parent variable assumed a "negative" or worst-case state, a score equal to the
strength of relationship was assigned to the parent variable combination ranking. For
example, if Suituble Equipment -4vaiZabil-y assumed the "Insufficient" state, a score of
2.22 was added to the score for that particular ranking. Table 5.4 shows an exarnple
parent state combination, and the total score used to rank that combination.
Belief Nenvork Analysis of Direcl Cosr Risk in Btrilding Constnrction 59
Table 5.4: Example ranking calculation Variable Suitable Equipment Availability Equipment P roductivity Construction Market Escalation Inflation Construction Claims Value Engineering
State Insuffkient >= Expected <= Expected > Expected
Major Practiced
Score 2-23 (negative state)
O (positive state) O (positive state)
1 -75 (negative state) 1.5 (negative state)
O (positive state) Sum: 5.47 -
Afier every possible parent state combination was scored, they were ranked from highest
score (worst-case scenarïo) to lowest score (best-case scenarïo),
5.2.3.2 PROBABILITY CURVES
The probability curves were developed assuming 16 ranked combinations of parent state
variables. ln fact, there are no predictor variables with just 16 combinations (each had
either 64 combinations or 96 combinations). On the other hand, to develop curves with
96 separate rankings would irnply that there was approximately 1% difference between
consecutive combinations. There is no way that such a minute difference could be
justified or explained. As a result, the combinations were divided into groups based on
the strength of their effect on the child variable. Combinations that had similar stren,@hs
of effect were grouped together.
Each predictor variable has eight different states (+Ils%. +95%, +75%, +55%, +35%,
l5%, -5%, -25% of budget). Eight normal curves, or distributions. were therefore
needed. The curve means were spaced evenly over the 16 rankings on the x-axis of the
probability c u v e graph. The y-axis of the graph represented the probability associated
with a given curve for a given ranking. To space the curves evenly over the 16 rankings,
the mean of each normal curve was spaced at regular intervals over the rankings on the x-
axis (the probability curve means were 1 .O, 3.14, 5.28, 7.42, 9.56, 1 1.7, 13.84, 16.0 -
spaced every 2 1/7 rankings).
Belief Nencork .4nalysrs of Direct Cosr R ~ s k in Building Consrnrcmn 60
The other data required to produce a normal c w e is the standard deviation. There is no
documented systematic method to select the standard deviation. So, a nwnber of curves
were developed, and the construction experts were asked to select the c w e that they
believed represented actual occurrences most accurately. In the final analysis, curves
with a standard deviation of 2.5 were selected. Eight curves with standard deviation 2.5,
and means 1 .O, 3.14, 5.28, 7.42, 9.56, 1 1 -7, 13 -84, 16.0 were developed. These curves
are show in Figure 5.3.
8 Child States, 16 Parent State Cornbinations, Standard Deviation = 2.5
0.600 --
1 2 3 4 5 6 7 8 9 1 0 1 1 1 2 1 3 1 4 1 5 1 6
Parent Pmbability Combination Ranking
Figure 5.3: Probability curves for Predictor variables
Each curve represents one child state. As c m be seen, for the #1 ranking (worst-case
scenario), the probabiIity of a 1 15% increase in cost over the budget is 5 1%, the
likelihood of an 95% increase is 35%, 75% increase - 11% and so on. For the second
worst case scenario, the probabilities are slightly different. As the probability of one state
Belief Nenvork rinolysrs of Direcr Cosr Risk in Building Construcrion 61
occurring increases, the others rnust decrease, and this graph represents this fact - the
surn of al1 probabilities for each parent state ranking is 1.0.
Appendix G has a chart with the raw data used to produce these curves. Table 5.5 is a
sarnple of what may be found in Appendix G.
-- ----
In Table 5.5, the top row (containing percentages fiom H 1 5 % to -25%) shows the
appropriate state of the predictor variable- The second row shows the rnean of the cuve
corresponding to the predictor variable state shown in the row above. The "StdDev" row
simpIy shows that the standard deviation for each of the curves is 2.5. The values shown
in the chart (1.0, 2.0, 3.0) are the values corresponding to the parent probability
combination ranking (1 .O = worst-case parent state combination). FinaIIy, the values,
ranging fiom 0.5 10 d o m to 0.000, are probabilities used in the model.
In the case of the Eqzuprnent Cos? variables, the Iowest ranking score (as discussed earlier
in this section) was 0, and the highest score kvas 10.42. These scores were multiplied by
a value that produced a range of scores from 0-1 6 (in this case l6/lO.42 = 1 -54). Scores
between 0-0.99 were assigned the best-case probabilities fiom the probability curve
(ranking l), scores between 1-1.99 were assigned the second best-case probabilities
(ranking 2), scores between 15-16 were assigned the worst case ranking (ranking 16) and
so forth. Appendix H shows each parent state combination for each predictor variable,
BelieJh'envork rlnalysis of Direct Cosr Risk in Building Consrrucfion 62
along with its ranking and score. Table 5.6 shows a sample of the Equipment Cost
ranking .
The chart shows the appropriate parent state combination, along with the determined
score and ranking. In the parent variable row, the parent variabIe name, as well as the
weight of the parent variable are shown.
Table 5.6: Appendix H Sample Sauioment Cost Variable Parent State Rankinq
Parent Variables: Suitable Equiprnent Availabilit-j Inflation Value Engineering Construetmn Market Escalation Equipment PmductMty Construction Claims
5.2.3.3 DIVORCING CURVES
In addition to being used for the predictor variables, the same probability cuves
(standard deviation = 2.5, evenly spaced means) were used for divorced variables. It did
not make much sense to ask experts to answer questions about variables that were
manufactured. As a result, the added variables were ranked according to the strength of
their parent variable's effect on the divorced variable. This ranking is shown in
Appendix J. The strength of these relationships was based on the values returned by
expert in the relationship identification matrix survey, in a manner similar to that
performed on predictor variables (depicted in Table 5.6).
Vanable nvndabstv ~ 2 . 2 ~ ) ~ o ~ e t i v d y ( t rn ~ a r k e t &.wan(~ 78)
State: insuriment m e Quected >=Expec!ed ~Erptded d3pcded *Exgtcted 1 mm M- rn ~sdired ~rsctised Score
Belief Nenvork Anaiysis of Direct Cosr Risk in Building Constnrction 63
4 3
1
X X X X X X
X X X X
X X X
X
X
X X X X X
X X X
X X X X
X
X X X X
X x 1
* X I
X X X X X
X
8.M 8-64 8.W 8.75 8.92
X
12.59 13.27 13.31 13.44 13.70
8.92 10.42
13.70 16.00
5.3 PROBABILITY EXPERT SURVEY
5.3.1 EXPERT SURVEY DEVELOPMENT
After reducing the number of probabilities required to be solicited from experts, an expert
survey was developed to collect the remainder of the probabilities required for the belief
network model. A survey was used because there was essentially no literature on the
topic of conditional probabilities between the parents and child variables in this model.
The expert survey was the only option for detennining these probabilities.
As stated earlier, the parent state combinations for al1 variables were ranked as much as
possible to reflect a worst-case scenario to best-case scenario progression. This was done
to aid the experts and decrease the time required to survey each expert. Nine experts
were surveyed, but each expert only answered about one third of the questions on the
survey. The experts were asked questions that, as much as possible, were related to their
area of expertise. Table 5.7 is a chart that details which expert answered which question.
Table 5.7: Division of auestions on the ~robabiiitv survev Expert Expert 1 Expert 2
II Expert 9 1 1.7.8.15.19.25.28-30.35.36.42.46.51.52.54.56.58 II
-- -- - - - -- -
Questions ~nswered 6,8,28,32-34,41 ,43-46,48,507S 134 l,l5,25,26,3 5,4 1 -44,47
Expert 3 Expert 4 Expert 5 Expert 6 Expert 7
-- - -
The survey had a column with state combinations for each parent variable, a column with
the child variable and its state, and a column with the numbers 1, 10, 20, 30, 40, 50, 60,
70, 80, 90, 100 (the numbers represented the conditional probability attached to the
Beliej.?envork Analysis o j Direct Cost Risk in Building Constnrcrion 64
19,20-22,24,26,27,3 1,47,53,55,57 23,29,30,36-40,42,45,46,49,5 1 ,53-55,57,58 6,20-S2,24,X727,3 1 -34,48 6-8,19,23,26,28,37-39,41,43-45,47,49,50,56 lS,20-22,24,27,3 1 -3S748,5O,53
relationship for the given parent state combination). Each expert was asked to study the
parent variables and their States, the child variable and its state, and assign a conditional
probability based on their experience. Three experts answered each question, Figure 5.4
shows part of the relationship quantification survey. Note that, in addition to the
quantitative response asked of the experts, a qualitative guideline was added to the survey
in the form of descriptions (Strongly Agree, Agree, In Between, Disagree, Strongly
Disagree) at the top of each page. The experts were asked to consider these qualitative
descriptions in their assessment of each conditional probability.
Each expert took approximately 30-45 minutes to complete the survey. No expert
seerned burdened with a survey of this length. The author sat with each expert during the
cornpletion of the sunrey to ensure that any questions could be answered promptly, and to
ensure the expert was not confused by the definitions of variables or their relationships to
one another. The structwed interview technique worked quite effectively in this instance
as well- In addition to these conditional probabilities collected, 23 variables had no
parents, and prior probabilities were collected by either survey or literature search.
Belief Nenvork Analys O/ Direcf Cosf Risk in Birilàing Consfruaion 65
5.3.2 SURVEY DATA ANALYSIS
Following collection of expert opinion during the sunreying process, al1 of the surveys
were combined into one master survey of d l variables with parent state combinations and
IDU
23 t
2
1
4
5
6
7
8
respective probabilities. Current research being conducted at the University of Toronto
suggests that in large network models such as this one, variables are only significantly
sensitive to changes greater than 20% in other network variables. As a result, the average
of three surveyed experts was used, except when one or more of the expert opinions
Figure 5.4: Sample Probability Survey
Car*
P o a OtsignQwEty Resmct ot k a p e Cl-p Complu CoapkdtyiConztncnbiEtp cd 0.:;9n
Good O ~ O u a ü t y Piesencc of Seope û n p Complu bmpluiqlCo.structrb*ry d OcGgr,
Poor OssiqnQdity P t a u c r ot k o p c Cr«p % d n c Cornplcitqi~on+t~~iabiuty of Dtriqn
Poor OcsignQurEty No tcopt Ocrp Conples Conpl&tqtCam~tncnbiEty of Oeiqn
G a d Oeign t&aEty Rez incr of k o p r Crep R o u t k CnnplePty4Colrtru~hb*h, of O ~ i q n
Good OcignQuaüty No k o p e û n p Conplex Compl~tylConstmc1a~1t~ d Oti-
Poar Design Qualttp No Scopc Weep Routine ConvluitvlCoasu~cabairy d 0e:ign
t o o d n~+a~dw No S a p e Clcep Routine Compl~itylCactm~tabiiily of O a q n
varied by more than 20% fiom the average. In this case, the expert was revisited and
asked if they would consider revising their response given a more complete expianation
W r d h
W l r ~ z t i n
M r d t i n
of the parent variables and parent variable States. This was done until al1 responses were
in the i 20% range. In a minority of the cases, the average was not used; a value was
fffect
M a + CeigaChange:
MaPr h i 9 1 Ch-
Wpr OtziqiChanga
selected that was not the average, but was within 20% of d l three opinions. For example,
Percentaqes S;oz Agree bBecvcea Oizagrce Stromgty
Q D i t e 100 90 O0 70 6 0 5 0 40 3 0 20 10 t
100 90 60 70 6 0 50 40 10 20 10 1
100 90 0 0 m 6 0 50 40 JO 20 10 1
Figure 5.5 shows one of the parent state combinations of the Consirzxtion CZuims
100 90 1 0 10 6 0 50 40 3 0 20 10 1
100 90 00 ïU 6 0 50 40 JO 20 10 1
100 O0 8 0 7U 60 50 40 10 PO 10 1
100 90 8 0 70 6 0 5 0 &t) JO 20 10 1
100 90 00 70 60 5 0 40 3.0 2û 10 1
Mresul t in
I n I r c u i t i n
Wl rczultin
VUrczukia
Y i l l r d t i n
variable.
Belie/Nent.ork ..lnalysts o/Direcr Cos! RI& in Building Conîlrucrion 66
Wp 0-i h n q u
W p r DcignCbanqc+
Mapr 0c;iqm Chuiqa
M + c Otsigatbaaqc
Iilkpr Otsiqi Champ
The average of the expert opinions is 63.3%. As a result, the expert that returned 40% as
if1 #2 $3 Used
a response would be considered out of the acceptable range. A value of 60% was used in
6
the model to bring that response into the acceptable range. The 40% response is therefore
within the acceptable range, as are both other responses, and no expert was re-consulted
Figure 5.5: Example of situation where average value was not selected
Guod PM daims mitigation
Minor or no Field Clairns
Major . - . - Delag Claim. Maior Design Claims
about this question. A complete list of the survey, expert-based probabilities and the fmal
Maior Construction CIaims
probabilities are shown in Appendix 1. Figure 5.5 is a sarnple of what may be found in
the appendix.
5.4 MSBN MODEL
5.4.1 MODEL CONSTRUCTION
Microsofi Belief Network (MSBNTM) \vas the sofhvare used to constnict and evaluate the
completed belief network model. A systematic method for building the model on the
computer was followed. The steps were:
1. Enter the most dependent node on the model.
2. Enter the next most dependent node on the model.
3. If a relationship exists between the most recently entered node, and a
previously entered node, draw a directed arc fiom the less dependent node
to the more dependent node.
4. Retum to step 2, uniess no more nodes need to be entered.
These steps were followed to ensure that no circular paths were constructed.
Belief Nenrork .4naiysis of Direcr Cosr Risk in Building Consrrtrcrion 67
Once ail of the nodes and arcs were entered, appropriate variable states were assigned to
each variable. For variables that required asyrnrnetric assessment, the structure of the
asyrnrnetric assessment was inputted next.
Finally, the probabilities developed as a result of the efforts descrïbed in this chapter was
entered. It was, of course, important to ensure that no errors were made. For Predictor
Variables, the MSBNTM text file was used to input probabilities. The text file was used to
reduce the time involved in entering the probability data.
5.4.2 MSBN TEXT FILE
Much information can be gathered from the MSBN iext file. In addition to a graphical
interface, MSBN provides a text file format to facilitate development and review of the
model. Variable names, states, asyrnmetric asseçsment, and conditional probabilities are
al1 contained in this document. Figures 5.6, 5.7 and 5.8 are excerpts from the text file
that show node name and state definition, conditional probability data, and asymmetric
assessment structure.
The first section of the text file is shown in Figure 5.6. Included are the node title
(StblEqpmntAvlblty) , node name (Suitable Eqziipment AvoiZabili!y), type (type:
discrete[2] - variable with 2 discrete states), and states (" hadequate", " Adequate").
"Position" refers to the physical CO-ordinates of the node in the graphical interface.
Belief ~Venvork Analysrs olDir2cr Cost Ri& in Building Constnrctmn 68
node StblEqpmntAvlblty C
name: "Suitable Equipment Availability"; type: discreteE2J =
E "Inadequate", "Adequate"
1 ; position: (L4065, 14665) ;
Figure 5.6: Text file node definition - Srtifable Eqrtipmenf Avaiiabifity
The probability portion of the file shown in Figure 5.7 first lists the parent variables
(S tblEqpmntAvlblty 1 MtrlEqpmntLss, LclCnstrctnMrkt. Geography), then the
probabilities. The code used to denote wliich parent state combination applies to which
probability looks like:
p r o b a b i l i t y ( S t b l E q p m t A v f i c 1 t y I M t r l E a g m n t L s s , LclCnscrctnMrk:, Geography) {
(O, O, O) : 0-07, 0.93; (O, O, 1): 0.07, 0.93; (O, 0, 2): 0.07, 0.93; (O, 1, 0): 0.6, 0.4; (O, 1, L) : O -37, O. 6 3 ; (O, 1, 2): 0.2, 0.8; (O, 2, O): 0.4, 0.6; (O, 2, 1) : 0.55, 0.45; (O, 2, 2): 0-3, 0.7; (1, O, 0): 0.07, 0.43; (1, O, 1): 0.07, 0.93; (1, O, 2) : 0.07, 0.53; (L, 1, O): 0.7, 0.3; (1, 1, 1) : 0-55, 0.45; (1, 1, 2 ) : 0.2, 0-8; (1, 2, O): 0.75, 0.25; (1, 2, 1): 0.75, 0.25; (1, 2, 21 : 0.3, 0.7;
- -
Figure 5.7: Suifuide Equipment AvuiiubiIity ConditionaI Probabilities
With states nurnbered starting at zero, this code applies to the #1 state of #1 parent
variable, #O state of #2 parent variable, #2 state of #3 parent variable. The #O state of a
parent variable is the #1 state listed in the text file for that variable, the #1 state of a
Belie/Nenvork Analysis oJDirecr Cosr Risk rn Biniding Conswucrion 69
parent is the #2 state listed, and so on. The probability of the #O child state of the
variable StblEqtAv o c c h g is 0.07; the probability of the #1 child state is 0.93.
node StblEugmntAvlblty I
l eve l O p a r en t LclCnstrctni-4rktr Level L s t a t e O , l eve l 1 s t a t e 1, l eve l 2 pa r en t Geography, l eve l 3 s t a t e 2, l e v e l 3 s t a t e 1, l eve l 4 Garent MtrlEqpmntLss, i e v e l 5 s t a t e O, l eve l 5 state 1, l eve l 3 s ta te O , l eve l 4 paren t MtrlEqpmntLss, l eve l 5 s t a t e O , l eve l 5 s t a t e 1, l eve l 1 s t a t e 2, l e v e l 2 parent Geography, l eve l 3 s t a t e 2, l eve l 3 s t a t e 1, l eve l 4 pzren t MtrlEqpmntLss, l e v e l 5 s t a t e O , l eve l 5 s t a t e 1, l eve l 3 s t a t e 0, l e v e l 4 paren t MtrlEagmntLss, l eve l 5 s t a t e O, leveL 5 s t a t e 1
Figure 5.8: Asymmetric Assessment Structure - Srtitable Equipment Availability Text File
Figure 5.9 is the graphical representation of Fi,we 5.8. Each level of the graphical
format is represented in the text file by a line of text.
Be fief Nenvork Annlysis of Direct Cost Risk in Building Constnrct~on 70
terialIEquipment Loss
al/Equipment Loss
riaVEquipment Loss
Figure 5.9: Asymmetric Assessment Structure - Srrifnble Equi'pment AvailabiMy Graphical FiIe
5.4.3 USING THE MODEL
In order to use the model, the user need only instantiate the variables according to the
situation as it is known for a given construction project. Microsofi Belief NetworkTM
provides a separate evaluation tool for this purpose. Following instantiation of the
appropriate nodes on the network, the probabilities associated with the likelihood of each
state for each variable c m easily be read fiom a chart. Figure 5.10 shows part of an
exarnple evaluation of the rnodel.
The left side of the screen shows the variable name (first colurnn), the variable state
(second colurnn; if the variable is not instantiated, the statement "Not Observed" is found
there), and whether the variable is included in the spreadsheet on the right side of the
page-
Belie/Nenrork Analysis of Direcr Cosf Risk in Btrilding Consrnrcfion 72
lnadtquate Y u Inadetpaie Abwed Folbdden Moderate Extrant Other Na oba u Raitine Rok to contractas Risk m owner Risk shared CMtiactor Falf No artrador fait Lump- Unit ctice Guaan(eed M m
Figure 5.10: Sample MSBN Evaluatiou
The right side of the screen shows the variable name (first colurnn) and the likelihood of
each state occumng for each variable. By reading the Iikelihoods of each of the
Equipment Cost, Marerial Cost, and Labozrr Cosr variable States, one can predict the most
likely cost overrun for each direct cost category, and consequently predict the direct cost
overrun for the entire project.
BeliejiVenvork Analyses of Direct Cos[ Risk rn Building Consrnicrion 72
Chapter Six: Mode1 VerificationNalidation
6.1 INTRODUCTION
The completed belief network model is cdled CORAL-PRO (COst Risk AnaLysis using
PRObabilities). Following the development of the CORAL-PRO model, it was most
important to ensure that the rnodel was predicting results that were reasonable and
accurate. This involved two major steps. First, the sensitivity of the model to evidence at
various nodes was tested. This ensured that the mode1 was working in the expected
manner, and that it was not highiy sensitive to evidence at any given node. Following the
sensitivity analysis, the model was tested with information fkom completed projects. This
step was taken to ensure that the mode1 is producing accurate results.
6.2 SENSITMTY ANALYSKS
MSBNTM does not have an automated sensitivity analysis function. As a result, either
another software package must be used, or a program m u t be written to test the
sensitivity of the model. Neticam is another belief network software package that does
perform single variable sensitivity analysis. That is, it changes the state of each variable
in turn, and assesses the change in the probabilities at the predictor nodes. This allows
analysis of whether predictor variables are "moving" in the expected manner. It also
allows determination of the extent to which the predictor variable probabilities change
when evidence is entered.
Belief Nenvork rinalysis of Direcr Cosr Rtsk in Building Constnrcrion 73
Sensitivity analysis was performed for three reasons. First, it is important to determine if
the model is reacting in the manner expected; that is, when evidence is entered that
should increase the likelihood of a cost overrun, the likelihood of a cost overrun should
increase. Second, if the model is particulady sensitive to a given variable, the
probabiiities entered in the model can be checked for errors. If no errors exist, then the
degree of sensitivity must be reviewed to determine if it is reasonable. Finally, extreme
value testing involves setting each of the rnodel variables to, in the first case, their
negative state, and in the second case, their positive state. This ailows determination of
the range of possible values that the model may output.
Based on the sensitivity analysis, it was determined that the model was acting in the
manner expected. Each piece of evidence entered moved the predictor variables in the
direction expected. In addition, none of the predictor variables proved to be particulariy
sensitive to any of the other variables in the model.
Extreme value testing of the mode1 found that the minimum expected value of the
predictor variables is -12%. The minimum expected value is the lowest possible value
that the model may predict for cost ovenuns. The maximum expected value is 102%.
The maximum expected value is reasonable, according to expert interview. Experts also
felt that the minimum value was reasonable, although they did identify the possibility of
being lower than that value (Le. diere is a cliance of being more than 12% under the
budget). On the other hand, in the normal range of projects. expert interview determined
Beliej'h'envork Analysis of Direct Cost Risk in Biulrling Constnicrion 74
that the -12% to 102% range would encompass most of the projects completed,
especially given that this model is limited in scope to long term projects.
6.3 MODEL VALIDATION
Cost data for two projects were used in order to calibrate the model. Revay and
Associates, Ltd., a firm that works in the construction claims business, provided access to
their files to search out this information. Many files with cost data were found, but only
two contained the data required to calibrate this model. The information required is:
4 Budgeted Project Cost
+ Final Project Cost
+ Conditions of the project
By comparing the original project cost to the final project cost, one can determine the
degree of cost overrun on a given project. The only problem encountered in the
calibration of the model was that the budget data given in the files is given as a g r o s
project budget (Le. budget is not divided into materials, equiprnent and labour costs).
CORAL-PRO does differentiate between these categories, and as such, the proportion of
the project budget devoted to each category must be determined. Average values were
used instead to calibrate this modeI. Consuitation with project managers at Pearson
International Airport New Terminal Building construction revealed that, on average, the
amount that each budget category is worth is approximately as follows:
+ 10% of project budget devoted to equipment
+ 40% of project budget devoted to materiais
50% of project budget devoted to labour
Beliej3iVenvork Analysis of Direct Cosi Risk in Building Consrrtrciion 75
This data allows the model to be calibrated, on an average basis. The following is the
information regarding the two projects used to calibrate this model. Fictional narnes are
used in order to protect the confidentiality of the claim participants.
6.3.1 PROJECT ONE: ABC MANUFACTUR~NG FACILITY
XYZ Contracting hired to perforrn construction services on the ABC Manufacturing
Facility. Following construction they submitted a claim for additional compensation on
the bais that the contract was subjected to signifiant modification and rearrangement
during performance, and was ultimately performed under substantially different
conditions to those contemplated by the contract. It was found that the following
conditions existed on the project:
Excessive Overtime
Increased Man-hour Costs
Lower equipment and labour productivity
Excessive design modifications
Incomplete design, errors in design
Construction Delays
Poor site accesdegress
Suitable equipment unavailability
No budget revisions allowed
Increased volume of work compIeted
Be/ie/Senvork Rnalysis o/Direcr Cosr Risk in Birilding Construction 76
In addition to these conditions that were found to directly contribute to the cost overnui,
the following are project charactenstics that also corresponded to variables in the cost
model:
Urban Geography
0 Value Engineering not practiced
PM ineffective in clairns mitigation
Private fiuiding source
Each of these factors were entered as evidence into the cost model, and the predictor
variables were used to predict the cost ovemin with respect to the cost of labour, cost of
equipment and cost of materials. Table 6.1 shows the results.
As c m be seen, the cost of equiprnent is predicted to be 82.9 % greater than originally
budgeted, the cost of labour 67.2% greater, and the cost of materials 79.1% overnui. The
actuai total cost overrun for this project, was 78.4%. Given the average ratio of
equipment cost: Iabour cost: material cost is equal to 1:5:4, the predicted cost of this
project is 73.5%.
Table 6.1: Predicted likelihood of various cost overruns for each cost category, ABC Manufacturing Facility
Prediction of a cost o v e m to within 5% on long-term construction projects may be
considered quite good, and acceptable given that the goal of this mode1 is to provide
Belief Nenvork Anat'ysis of Direct Cost Risk in Building Constntcrion 77
Cost of Equipment Cost of Labour Cost of Materials
+I l%
32.1%
8.1%
19.7%
+55%
16.6 % 25.4 % 16.9 '%O
+3S%
6.2%
14.9 ?40 8.5%
+95%
28%
18.6 YO 26.6 %
+75%
25.9 YO 27.1 YO 24.7 ?40
+15%
1.2%
5.0%
3.0%
-25%
0%
0.1%
0.1%
-5%
0.1%
0.9%
0.6%
Expected Value +82.9%
+67.2%
+79.1%
project managers with a guideline. This mode1 is not intended to replace the intuition of
a project manager, it is meant to provide backup evidence. In this respect, a 4.9%
deviation is quite acceptable-
6.3.2 PROJECT TwO: 123 COMPANY BUILDING ENVELOPE RESTORATION
"Construct-CO" contractors were hired by 123 Company to restore the exterior envelope
of the 123 Company Building. Dwing Sie course of the work, Construct-CO submitted
that the originally planned scope of the work was radically altered by 123 Company
through the extreme variation of the quantities of work to be completed for various unit
price items, and by the introduction of substantial additionai scope to the project through
change orders. The following statements of fact about the project were made in the daim
report:
Significant scope increase
Extensive change orders
Major Construction delays
Budget revisions allowed
Inadequate site investigation
Increased volume of work cornpleted
Maj or overtime
Loss of equipment and labour productivity
Major labour congestion
Behef ~Vknvork Anaiysis of Direct Cosr Risk in Building Consrructron 78
In addition, the following conditions were characteristics of the project:
No value engineering
Urban geography
Poor PM claims mitigation
Low altitude
Public fünding source
Risk shared by contractor and owner
The model was used to predict the expected final cost overrun. Table 6.2 details the
results.
The actual cost overrun on this project was 62%. Given the proportion of overall costs
by category, the model predicts that the actual cost overrun on this project will be 70.5%.
This means that there is an 8.5% difference between actual and predicted costs. A
difference of 8.5% is slightly more than would be desirable, but reasonable given that the
model is meant only as a guide.
Belie/Nenvork Rnalysis of Direct Cost Risk in Building Cons~ntcrion 79
Table 6.2:Predicted Iikelihood of various cost overruns for each cost category, 123 Company Building
Cost of Equipment Cost of Labour
+9S%
12.5%
19.8%
+115%
5.6%
8.9%
~ z f / .8%15.22%1 23.7% 1 17.1% Materials
+75%
30.1%
27.5%
9.6%
+55%
24.3%
24.6%
4.1%
+35%
20.4%
13.9%
1.2%
+15%
11.5%
4.5%
0.3%
-5%
4.5%
0.8%
76.6%
- 25% 1.2%
0.1%
Expected Value 55.2%
68.7%
6.3.3 VALIDATION DISCUSSCON
Testing a complex model like this one by sampling two projects should not be considered
to be an exhaustive exarnination of the accuracy of this research- It does, however,
accomplish the goal of proving that, at Ieast in a couple of cases, this mode1 is reasonabry
accurate. Further testing with longer-term projects should be conducted to show more
decisively that the model works or where modifications should be made to improve it.
BelieliVenvork Anaipis of Direct Cosr Hisk in Building Consfruction 80
Cha~ter Seven: Conclusions & Recommendations
7.1 CONCL~SIONS
This research sought to develop a model that would serve to aid project managers in the
prediction of cost overrun in long-term construction. To that end, an extensive literature
search was conducted to identify any and dl risk variables to project construction cost.
To begin with, 75 nsk variables were identified. Expert input was solicited to determine
the relationships between any two risk variables on the list. This effort resulted in a
network model that showed ail risks to construction cost, and any relationships between
those risks.
Unfortunately, while almost complete, the CORAL-PRO mode1 was irnrnensely complex.
Some variables had greater than IO parents. Some variables would have required the
elicitation of thousands of probabilities. A significant amount of work subsequently
fo1Iowed to reduce the effort required fiorn voIunteer experts. This involved the
following processes:
Divorcing
Relationship Elimination
Asyrnmetric Assessrnent
Parent State Combination Ranking
Probability Curve Development
Each of these techniques reduced the number of relationships andor the nurnber of
probabilities required.
Belief Neniwrk .4naiysis of Direcf Cost Risk in Btrrlding Constniction 8 1
Following simplification of the model, conditional probabilities were gathered for each of
the cause-effect reIationships. In most cases, these probabilities were obtained using
expert survey. In some cases, however? normal probability curves were used (predictor
variables, and divorced variables). In other cases only some of the parent state
combinations were surveyed for a given child variable. The other state combination
probabilities were interpolated using standard regression techniques.
Finally, afier the mode1 construction and probability solicitation, the completed model
was subjected to a sensitivity analysis, and tested with data from actual completed
projects.
As a result of the extensive modeling research, a belief network mode1 was developed
that predicted results of actual tested projects to within ten percent.
It rnay be concluded that:
8 Long-term projects are subject to a tremendous amount of risk.
No construction project could be characterized as easy or routine since
every construction project is different and subject to different challenges.
in particular, long-term construction meets more challenges that shorter-
duration projects simply because time allows more opportunity for things
to go wrong. In all, 75 risk variables to construction cost were identified.
Subsequent risk variables were added for model manipulation, but the 75
initially-identified risk variables constitute a collection of uncertainties
that rnust be considered whenever undertaking a long-term construction
project.
Construction of belief networks requires a good deal of costhenefit analysis
As stated earlier, a tremendous effort was expended trying to reduce the
nurnber of probabilities required in subsequent stages of research. This
effort was not without a corresponding reduction in model completeness.
Testing of the model shows it is performing well, but may not accuratety
represent actual practice. This is an issue with al1 model development;
simpliQing assumptions usually result in a loss of tnie representation.
r Belief Networks provide an excellent means for understanding situations involving uncertainty
Belief Networks allow the mode1 builder to actually "see" the situation
being modeled. Directed arcs show relationships between mode1
variables. This model in particular allowed the mode1 builder to see which
factors most directly affected budget ovemns, and which were mitigated
by other factors. This allows the model user to concentrate more on those
variables that have greater impact. It aIso facilitated discussions with
experts because the graphical nature makes the model very intuitive to
understand.
BeliejiVenvork Analysis o/Direcr Cosr Risk in Building Consrmction 83
This mode1 specificaïIy predicted cost overruns on two completed projects to within 10%
The completed model came within 10% of the actual value of budget
o v e r m on the corresponding project. This is encouraging if not
conclusive. The belief network mode1 certainly needs to be tested firrther,
but initial resuits show that it is working.
7.2 CONTRIBUTIONS
There were several goals and objectives identified in the introduction. This section seeks
to identie whether these goals have been achieved. As a surnmary, the objectives and
milestones identified were:
development of a belief network to predict cost overruns,
identification of factors affecting the cost of construction projects,
determination of the marner in which these factors affect cost,
determination of the degree to which these variables affect cost.
initial testing of a more effkient expert surveying method,
The study of risk as it pertains to construction cost has been furthered significantly by
this research. The following is a hst of contributions to the field.
1. A mode1 to predict cost overmn on long-term construction projects was
developed. This model was found to work quite well on two completed
construction projects.
2. 75 risk variables to cost in total were identified, ranked and classified. No
such Iist was found by the author prior to the construction of this model.
Befief Nenvork Anabsis of Direct Cosr R~sk in Bdding Consfnrctron 84
3. A network was constnicted that model cause-effect relationships between
each of the risk variables identified in this research.
4. Quantification of each relationship in t a s of probabilities for parent state
combinations was achieved.
5. A technique to reduce expert effort was developed. This technique
involved ranking of parent state combinations, selective surveying of some
of the parent state cornbinations, and interpolation of intermediate values.
This method of surveying certainly needs more attention on future
projects.
As c m be plainly seen, contributions 2, 3, and 4 are realiy "sub-contributions" of number
1. As stated in the introduction, however, these interrnediate milestones are of academic
significance, and are important contributions to the art and science of construction
engineering and management.
7.3 RECOMMENDATIONS
The most important M e r research that needs to occur is an examination of the
effectiveness of this model on many other long-terni construction projects. The
calibration effort undertaken as part of this research was effective and encouraging, but
certainly not exhaustive. Data from more projects need to be sought out and used to test
the cost model. These projects need to be more long-term in nature than the two projects
tested. Only then can the model be conclusively proven to be effective and reliable.
BelieJiVework Anaipis of Direct Cos[ Risk in Building Cons~ntcf ion 85
Further development of this model can occur during the continuous testing process. As
more projects are added to the database of tested works, probabilities within the model
can be refined and updated. Given the changing nature of the construction industry, it
would be prudent to continue the updating of this model.
Finally, the new method for surveying experts involving interpolation of results needs to
be M e r studied and refined. If anything was learned fiom this research, it is that
individuals working in the construction industry are incredibly busy. Those contributing
to this work were very accornmodating and helpful. but that accommodation needs to be
retumed. To that end, any effort made to reduce the arnount of time required on their part
should be made. Further study of the interpolation survey method needs to occur. If
work is dom to improve the interview process, research using the methods descnbed in
this report can occur more efficiently, and the art and science o f risk management can
progress even M e r .
References
Arditi, D,, Gunaydin, H.M., 1998. "Factors that affect Process Quality in the Life Cycle
of BuiIding Projects." Journal of Construction Engineering and Management, 124(3),
194-203.
Caterpiflar, hc., 1997. Caterpillar Performance Handbook. Edition 28. CaterpiIIar, Inc.,
Peoria, Illinois U.S.A..
Construction Industry Institute, 1989. Management of Proiect Risks and Uncertainties.
Construction Indus-try Institute, Cost/Schedule Control Task Force, University of Texas
Press, Austin, Texas, 2-23
Construction Industry Institute, 2990. The Impact of Changes on Construction Cost and
Schedule. Construction lndustry Institute Cost/Schedule Controis Task Force, Austin,
Texas.
Cooper, D.F. and Chapman, C.B., 1987. Risk Analvsis for Large Proiects: Models.
Methods and Cases. John Wiley and Sons. Chichester, U.K..
Design News, 1997. "Value Engineering: The Right Material, in the Right Place, at the
Right Time." Design News, 52, 13 8.
Belie/lVenvork Analysis of Direct Cost Risk in Building Consznrcfion 87
Diekrnann, J., Nelson, M., 1985. "Construction Claims: Frequency and Severity,"
Journal of Construction Engineering and Management? 1 1 2,74-8 1.
Dozzi, P., Hartman, F., Tidsbury, N., Ashafi, R., "More Stable Owner-Contractor
Relationships." Journal of Construction Engineering and Management, 122(1), 30-35.
Elhag, T.M.S., Boussabaine, A.H., 1999. "Factors Affecting Cost and Duration of
Construction Projects." EPSRC Research Report, Leeds University, Phase 1, 1 - 13.
Flanagan, R. and Norman, G., 1993. Risk Management and Construction. Royal
Institution of Chartered Surveyors. London, U.K..
Henrion, My Breese, J.S., Horvitz, E.J., 199 1. "Decision Analysis and Expert Systerns."
AI Magazine, Winter 1 99 1, 64-9 1.
Henrion, M., 1989. "Some Practical Issues in Constructing Belief Networks."
Uncertainty in Mificial Intelligence, 3, 2 6 1 - 1 73.
Hester, W.T. and Kuprenas, J.A., 1987. "Assessing Changes and their Real Impact."
Project Controls: Needs and Solutions by William Ibbs and David B. Ashley,
Proceedings of a Specialty Conference sponsored by the Construction Division of
American Society of Civil Engineers, June 8-9, 1987, 58-67.
Belief Xenvork Anaiysis oj' Direct Cos1 Risk in Building Construction 88
Hinze, J., Pederson, C., Fredley, J., 1998. "Edenti&ing Root Causes of Construction
Injuries," Journal of Construction Engineering and Management, 124(1), 67-71.
Jensen, F., 1996. An introduction to Bavesian Networks. University College London
Press, London, U-K- 33-67.
Larson, E., 1997. "Partnering on Construction Projects: A Study of the Relationship
Between Partnering Activities and Project Success." IEEE Transactions on Engineering
iManagement, 44, 188- 195.
Laufer, A. and Cohenca, D., 1990. "Factors affecting Construction Planning Outcomes."
Journal of Construction Engineering and Management, 1 1 6(l), 135-1 56.
McCabe, B., AbouRizk, S., Goebel, R., 1998. "Belief Networks for Construction
Performance Diagnostics." Journal of Computing in Civil Engineering, 1 ?(2), 93 - 100.
McManarny, R., 1 997. "Quiet Revolution Brews for Settling Disputes." Engineering
News Record, 2 May 1997,21-23.
Mulholland, B. and Christian, J., 1999. "Risk Assessrnent in Construction Schedules."
Journal of Construction Engineering and Management' 125(1), 8-1 5.
Nasir, D., 2000. Probabilistic Analvçis of Schedule Risks for Building Construction-
University of Toronto, Toronto, Canada.
Okpala, D-C. and Aniekwu, AN., 1988. "Causes of High Costs in Construction in
Nigeria-- Journal of Construction Engineering and Management, 1 14(S), 233-244.
Poole, D.L., Mackworth, A., and Goebel, R.G. (1 998). Computational intelligence: a
logical introduction. Osford University Press, New York, N.Y.
Portas, J-, and AbouRizk, S., 1997. ';Neural Network Mode1 for Estimating Construction
Productivity." Journal of Construction Engineering and Management, l23(4), 399-4 10.
Randolph, D., 1993. Civil Engineering for the Community. Amencan Society of Civil
Engineers, New York, N.Y., U.S.A., Chapter 8.
Sarkar, S. and Murthy, I., 1996. "Constructing Efficient BeIief Network Structures with
Expert Provided Information." IEEE Transactions on Knowledge and Data Engineering,
8(1), 134-143.
Songer, A.D. and Molenaar, K.R., 1997. "Project Characteristics for Successful Public
Sector Design Build." Journal of Construction Engineering and Management, 1 23(1),
34-40.
Stiglitz, J.E., and Boadway, R.W.. 1994. Pnncioles of Macroeconomics and the
Canadian Econornv. W,W, Norton and Company.
Thomas, H.R. and Napolitan, C.L., 1995. "Quantitative Effects of Construction Changes
on Labor Productivity." Journal of Construction Engineering and Management, 12 1(3),
290-296.
Thomas, H.R., 1992. "Effect of Scheduled Overtime on Labor Productivity." Journal of
Construction Engineering and Management, 1 1 8(1), 60-76.
Webster New World College Dictionary. 1997.
Wideman, R.M., 1993. Project and Prooram Risk Management: A Guide to Managine
Proiect Risks and Opportunities. Project Management Institute.
Zack, A.M., 1997. " C m Alternative Dispute Resolution help resoive Employment
Disputes." International Labour Review, 137, 95- 108.
Belief.Venvork Anafysis o/Direcr Cosr Risk in Brrrlding Consrnicfion 91
Appendix A: Risk Variable Information
Belie/iVenvork Analysis of Direct Cost Risk in Building Constnictton 92
Risk NamelSource 1 Risk Definition Equipment Cost 1 Total cost of equipment used (To oe applied ro on the projecr. Includcs each of rhe projecr purchse or rental cos& fuel cosr centres) cost, repais. etc.
O be applied ro the consmction of the project each o f the proiecr COSI centres
Risk States -25%
1 Matenal Cost (To 6e applied ro each of ihe prcjecr cost centres)
(crr 19891
I alterations in project content or schedule.
Construction claims (CI1 19891
Risk Parents Availability of suitable cquiprnent;
TotaI cost of materials for project use.
Claims by project participants for more t h e or money due to
Construction market escalation: Equipment Productivity General Inflation Value Engjneering Construction Claims
+ I l s % -25% -5% +l5?6 i-3 5% +55% +75% +95%
Qualified local labour Labour Productivity: Overtime; General Inflation; Project G e o ~ n p h y Construction delays;
Construction market price escalation; Design changes; Material waste; Scope creep; Material Shortage Value Engineering
i l 15% Major constniction claims: Modemte construction daims; Minor or no construction
P M claims mitigation 4 For Divorcind
PM claims mitigation: Field claims: Delay cfaims: Design clairns;
Design daims (For Divorcino)
Field claims (For Divorcino)
Delay claims 1 For Divorcing)
clairns node) The PM'S experience and skiII in diffusing construction claims before they becorne a problern. (Used in divorcing for Construction clairns node)
Construction clairns that are related to design factors. (Used in divorcing for Construction claims node) Consuuction claims that are related to field factors. (Used in divorcing for Construction claims node) Construction claims that are related to delay factors. (Used in divorcing for Construction
1 tor in the original budger II Cost Acrountine 1 The prompmess and reliabilitv
clairns Major Design related claims: Minor or no Design related claims
Major Field relatcd claims: mino or or no Field related claims
Major Delay related claims; mino or or no delay relatrd cfaims
Overtime fcrr 19891
- I of the cos; reporting and -
accounring syslern. Assume
Design changes; Scope Creep: Design Subrnittal:
Trade coordination: Ground Conditions; Defective Work
Construction Delays: Overtime Long Work Stoppages
Work above the espected amount that is not accounted
1 that the accounting is accurate. Value Engineering 1 A tool used to eliminate -
(Expert) redundancy in design and construction. The goal is [O
reduce project cost
Project manager effective at reducing construction cfaims that occur. Project manager not effective at rcducing construction
Qualified key PM personnet: PM
daims that occur 1 more ovenime than expected; 1 Construction Delays; As much or las overtime 1 Labour Productivits:
Untirnely I than espected Timely;
Scopr Creep PM
Value Engineering Practiced; Value Engineering not
Budget revisions: PM;
~racticed-
Beiief ~Venvork Anaipis of Direct Cost Risk in Building Consrrucrion 93
Constmction Deiays
Construction Delays (CI1 1989)
Major construction delays; mino or or no construction delays;
Time Iost with respect to the schedule.
Labour delays; Logistics delays; Design delays; Environmental delays; Failure delays
H Risk Name/Source 1 Risk Definition FaiIure delays 1 DeIays in construction due to Flanazan. man
I 1 Subcontractor going out of
the g&ng out o f business of one of the project participants.
Contractor Failure Flanaean. Norman
Failure Flanaoan. Norman 1
Contractor going out of business
- - - -
1) =lier Failun 1 Supplier going out of business.
Il {For ~ i v o r c i n 9 I Labour issues. (Ùsed in divorcing Construction delays
(Flanaew. Norman I993) Labour delays Construction delays related to
1 node) II Design delays 1 Construction delays related to
Logistics delays {For Divorcino)
II ( ~ o r ~ i v o r c b g ) I Design issues. (Üsed in divorcing Construction delays
node) Conswction delays related to logistics issues. (Used in divorcing Construction detays
II 1 node) Environmental 1 Constmction delays related to
l Environmental issues. (Used 11 $%ivorcino) in divorcing Construction 1 delays node) 1) Land d e l a i 1 Construction delays related to
(For ~ ivor&o)
For Divorcing in a loss of labour productivity. (Used in divorcing labour productivity node)
the ground. (Used in divorcing Environmental delays node)
1
Labour productivity (Wideman 1992)
The amount of work done by labour per unit time.
Labour congestion [For Divorcino)
(For Divorcino)
Impedirnents to eficient completion of labour work. (Used in divorcing Labour
l personnel. (Used in divorcing labour productivity node)
Deviations that was expected to be done. CI1 1989
Labour design understanding
Risk States ( Risk Parents Major delays due ta failure; 1 Contractor Failure;
Understanding of design documents by labour
ino or dela& o r no delays due to failurer
Subcontractor Failure; Supplier Failure
Contractor fails: No contractor fails
Parent Only
Subcontractor fails: No subcontractor fails
Major Delays; Minor or no delaysr
Parcnt Only
Supplier fails; No supplier fails
Labour productivity: Defective work; Long Work stoppages:
Parent OnIy
1 Trade coordination blajor delays; ) Materials Delive-; Minor or no delays 1 Conswction/Ops interference
Major delays; Minor or no delays
Design changes; Design SubmittaI
Major delays: Minor or no detays
Major delays: Minor or no delays
Ground conditions; Geology; Land related natural disaster
Land deIays; Environmental scnsitivit).: Weather extremes
( Labour design understanding Occur frequently: 1 Material Shonage;
Less productive as expected; & productive or more productive than espcctrd
Occur infrequently
Short breaks; Labour congestion; Defective Work;
Suitabk equipm>nt availability: Labour injuries/ accidents: Climate
Labour advenely affected by vehicle and person congestion; Labour not adversely affrctrd by vehicle and penon congestion
requirements; Design changes Qualified Local Labour,
Number of workers on site; Trafic congestion; Constniction/Ops Interference
Poor understanding; Good Understanding
More work encountered during construction (ive. dewaterinp, etc.); As much work or les than expected
Design Quaiity; Construction rechnology
Design Qua1 ity; Tenant Requirement Change: Ground Conditions; Design Changes; Defective Work
Befie/:Venvark Annfysis of Direct Cosr Risk in Btrrlding Constnrctron 94
Matenal Waste 1- Design changes 7 Defective work (CI1 1989)
Trade Coordination JWideman 1992)
I
Penal tics
market prices Wideman 1992
Il Foreign purchareci /
materials (CI1 1989)
Equipment producthity JWideman 1992)
Suitablc equipment availability (CI1 1989)
Risk Definition Inadequate materials on site for completion of the job
Material that is purchased for project use but is not used.
Changes in the design during the course of construction.
Construction deviations from design.
Cooperation and coordination of the various consvuction trades.
Violation of laws and niles of various regulatory bodies (OHSA, EPA etc.). Strikes. protest. public inquiries b a t atfect the timely completion of work.
The uncertainty regarding timeiy delivery ofproject materials to the site. Especially when JIT drlivery is used. The use of strategies like partnering to ensure a cooperative project effort
Increases in project costs that are anributable solely to the fact that some project aspects are international in nature.
The use of materials o r equiprnent tiiat originate outside of the project's country.
Materials required to build the project that are close enough to the site that they can be obtained in a timely rnanner.
The amount of work that equipment does per unit time.
Equipment that is capable of doing the work required and is available at a reasonable cost to work on the projecr
Risk States Risk Parents Frequently inadequate Design Changes: malerials on site: Material/Equipment Loss: infrequentiy inadequate Materials D e ~ i v e r ~ materials on site Material Waste Major material waste; Defective Work Minor or no material waste:
Major design changes; Design Quality; Minor or no design changes; Scopc Creep:
Design Team coordination: Complexity/ Constructability of
1 Design: maio or mistakes: 1 QualifÏed local labour: ino or mistakes or no I rade coordination: mistakes Design Quaiity;
1 CompIexity/ ConstructabiIity of Design
Good communication and Qualitïed key PM personnel; coordination; Complexity/ Constructability of Poor communication and design; coordination Physical Project Size Major penalties applied; Environmental Sensitivity Minor or no penalties applied; Major construction Parent Onlv stoppages; Minor or no construction
Frequently late
Partnering practiced: PM; Partnering not practiced Qualified kry PM Personnel
As expected or lower Foreign Purchased Goods
Materials andlor equiprnent Exchange Rates; purchased internationally: Suitable Equipment Availability Marerials and/or equipment purchased domestically
Adequate quality materials Local construction market available; insuficient quality materials availabIe
Equipment less productive Suitable Equipment Availability; than expected: Ground Conditions; ~ ~ u i ~ m e n t as prodiictive or Altitude more productive han expected
available: Local construction market; Insufikient equipment blaterial/Equipment Loss available
Belief rVenvork Jnaiysis oJ- Direct Cost Risk in Building Constnrction 95
CI1 1990
accidents CI1 1989
labour CI1 1989
FIanaoan, Norman - 1993)
Survey
CI1 1990
Design Quality 117
Budget revisions IF Requirement Change (Esuert)
Contract Clauses I r
Contractor payment type (CI1 19891
PiCf work familiarity CI1 1989
due to the& ;andalism or in or or no losses occur. damage. Physical injriry to labourers. Major injuries occur.
Minor or no injuries occur:
Labour workers who are able Adequate qualified labour to perfom the required wvork personnel available; and are avaiiable to work on Insuficient qualified labour this projec~ ( personnel available Geologicnl conditions that are ) Ground conditions torse
when designs are made. Ground conditions as
Availability of design Design on tirne; documents when required by Design late construction. Quality of completed design High quality design; documents available to 1 Low guality design ( e m n construction workers during f present. omissions, etc.) the course of the oroiecl. 1 Changes in the project design that alter the work that need be done.
Scope cretp present: Scope creep absent
The owner's willingness to I Revisions allowed; alter the budget afier the Revisions forbidden
I change during consinicrion; No tenant requirement
pro-iect has bëgun. Changes in final design preferences by tenants afier commencement of the project
Major tenant requirement change during construction: Minor tenant requirement
of the job on time. on budget. 1 - -
No relief for force-maieure f Risk transferred to
The project manager's commitment to the complet ion
clauses, Diffcring site conditions, Not responsible for quantity variations, HoId Harmless, No damage for deIay, Contract-imposed procurernent iimitations, Warran ties and guaranties, Bonuses and shared savings. Retention. Convacr penalties (liquidated damages. etc.) Lump surn, unit price. guaranteed mauimurn. cost reimbursable.
change during construction Project manager proactive; Project manager reactive
con tract ors; Risk transferred to owner; Risk shared by contractors and owner
Lump sum; Unit price; Guaranteed maximum;
1 Cost reimbursable The project manager's 1 PM farniliar and experienced experie6ce with simi tar projects.
PM'S understanding of the site environrnent (location, geology. population, government, etc.)
with type of constnktion; PM unfamiliar and inexperienced with type of COflStNCtlOIl
Parent Onlv
Local construction market:
Geology: ArchaeoIojica[ survey
Parent Onlv
Design Team Coordination: Scope Creep
Project manager familiar with area; Project manager unfamiliar with area
Risk Narne/Source Risk Definition ( RiskStates Materiai/equipment Loss of equipment or materials 1 Maior losses occur,
m.
-
-.
-
Construction Technology Requirements; Design Team Coordination;
Risk Parents Site Security
-
-
-
- -
-
SCO& Creep Tenant Requirement Change; Design team coordination
-
-
-
-
-
Owner Financial Stability
Parent Onlv
Qualified Key PM Personnel; PM work familiarity
Contractor Payment Type
Parent Onlv
Construction ~ e c h n o l o ~ ~ Requirernents
Qualified key PM personnel
BeliejNenvork Analysis oJ Direct Cost R~sk in Bztilding Consrnrcr~on 96
construction and existing site opentions-
The need for security and the ease at which the site c m be secured.
Vehicular trafic on and around the project site that impedes movement of construction vehicles. Available points of e n q and exit to project site.
The number of G d strïctness of perrnits required to do work.
Number of labourers, project management personnel. inspecton. etc. on site.
Environmental sensitivity of the surrounding environment
Need for unproven technology in constmction and operation of this project
Degret of difficulty of construction of this project.
Communication and cooperation benveen designers of different project componenrs.
People who are experienced in management of similar projects and are available to work on this project.
Shelter, food and other nccessities for construction staff- emergency services, communications, etc. The source of funds for the project - private or public sector.
Typical security arrangements; Atypicid security arrangementsl Movrment around site very impeded by vehicles: Movement around site largely
construccion and opentions; Little or no intertèrence
unimpeded Adequate accesdegress to
Competing Activity on Site: Trafic congestion
site; oress to Insuficient access/e=
site lnsufficient - unreasonable delays encountered when rrying to get on to o r off of site Cornplex permitting requirernents: Normal permitting requirernents Person-congrsted site: Non-person congested site
Parent OnIy
Site access; Number o f workers on site; Competing Activity on site; Physical project size Parent onlv
Parent onlv
sensitive; Environment not very sensitive
Environment very sensitive; Environment modentely
Parent Onlv
1
New technology required for 1 Complesity/ Constmctability of
Risk Name/Source Construction/ Operations Interference fE..upenl Site security fC11 1989)
T r a f i c congestion (CI1 1989)
Site access lcrr I 9891
Permits Required (Wideman - 19921
Number of morkers on site lcrr 1989)
Environmen ta[ sensitivity (CI1 1989)
Construction technology requirements (Cr1 1989)
CompIexity/ Constructability of design [CI1 1990) Design team coordination (ExD~~L)
Qualified key P M personnel [CI1 1989)
Construction Support Facilities (Cil 1989)
Funding Source {Widernan - 1992)
constmction; Proven technolog>- required
Design
Risk Definition The interference benveen
Complicated project; Routine project
Risk States 1 Risk Parents Major interference benveen ) Qualified key PM personnel;
-
Parent Onlv
-
-
-
-
-
-
-
-
-
-
4 -
management personnel available; Not rnough qualified project management personnel available
Good communication and coordination; Poor communication and coordination
Qualified key PM personnel
availablc: 1 Privately-funded job ( Government spending on
Adequate suitable facilities availablr: Not enough suitable facilities
Publicly-funded job 1 consuuction: Combination (private/public) Govemment
General area affiuence/wealth; Local construction market
Beliejh'envork Anaiysis of Direcf Cosr Risk in Bziiiding Consrnrcrion 97
Risk NamdSource 1 Risk Definition 1 Risk States 1 Risk Parents Construction 1 Fluctuation in pnces of 1 Higher than expected; Genenl Inflation; market escaiation (Exuert)
1 ) few resources tied up Owner financial 1 Fiscal situation of project 1 FinanciaiIy stable owner,
Local construction market (Eu~ert)
. -
stability 1 owner. 1 ina an ci al& unstable owner
consuuction iiarea in which project is being built
i\sexpected or-1ower than expected
Other construction projects that dmv on the same labour, equipment and resources as the given project
Govemment spending on construction: Local construction market
Area construction-satunted: Some othcr construction; Area construction-poor Construction saturated - most other labour, equipment and resources tied up. Construction poor - v e q
lcrr 1989) Physical project sixe JCII 1989)
Parent Onlv
Parent Onlv
Physical size of area on which the project is being built.
Parent Only Large project area; Srnall project area Large: dificult to shnre equipment, long travel from one point on site to others,
Competing activity on site (Cr1 1989) Availability of eneqg {Wideman 1992)
E~istence of other activities on the project site or adjacent to
Utilities <Cl1 19891
--
1 . - 1 construction is located. 1
Inflation 1 A mrasure of general price 1 Higher than espected: 1 Government Spending on
project site. Presence of required enera (elecuicity, fueI, gas, etc.) to the project site.
Area ailluence (CI1 1989)
(Ex~en] ( increases. - 1 ~ s e s ~ e c t e d or-lower than ( Construction
etc. Othrr activity competings No other activity competing
Layout of existing utilities on and around project site
Parent Onlv
Adequate energy readity available: Adequate energy not readily
Prosperity of people and industries in area in which the
Project Geography
available Utilities present, location known: Utilities present location unknown:
Government spending on construction
I I Exchange Rates ( Relative value of local 1 Worse than expected:
Parent Onlv
Utilities nat present Prosperous area; Non-prosperous area
{Stioliu and Boadwav 1994) Tax Rates (Widernan 1992)
lcrr 1989) I currency as compared to I As expecred or better than foreign currency. expected
Parent Onlv
Amount of rnoney that appIicable govemments are investino in construction.
Government espected Higher than usual: As usual or lowrr than usual
-
Money that must be paid to government as a percentage of revenue made.
Government Hi$er than espected: As expected or Iower than espected
Parent Onlv
Government (CI1 1989)
Land - related natural disaster
Belief Nenvork Analysis of Direct Cost Risk in Building Constnrcfron 98
Turnover of governrnent and the degree ofunderstanding in government of construction-
Weather Extremes f a 1 1 989)
A disaster of geology (e.g. carthquakr, landslidtt. etc.).
Stable government: UnstabIe govcmrnent
Unusually serious weather that affects the project
Parent Onlv
Disasters likely: Disasters unlikeIy
Geology
Extreme weather Iikely: E~treme wearlier unlikely
Parent Onlv
11 1 project site. 1 Extreme - not easy to adapt 1
Risk NamefSource Clirnate ICI1 19891
Geograp hy fc!i 1 989)
Risk Parents Parent Onlv
Risk Definition The nonna[ weather that c m be expected to exist on the
I
Belief Nenvork Analysis of Direct Cos( Risk in Builciing Constnrction 99
Risk States Modenre - easity adaptable to:
The proximity o f the project site to other civilization.
Gcology [cl1 1989)
* Altitude CI1 19891
tO Urban; Rural: Rernotr
level.
The composition and condition o f rock forniations underlçing
Parent OnIv
The vertical elevation of the project site as compared to sea
Low altitude (c3000tt above sea level) Favourable to construction: Unfavounble to constmction
. . -. . . - . - High altitude p3000ft above sea level)
Parent Onlv
Parent Onlv
Appendix B : Risk Relationship Survey
Belief :Vencork Anaiysrs of Direct Cost Risk in B!iilding Cons~rïcrion 1 O0
I l I l I I
tor, Nb, nippbr) Fribur.nLittddtlry, I l I I I I
BeliejNenvork Anabsis of Direct Cosf Risk in Building Constnrction 102
O t h u n v p r e o m t m c t i D n ~ i n i n r OabiirfinuiàrlstabüÏiy p w p r r * c c t , &
b m p t ~ ~ a a r i t r A v z i l r b i f i t r o f ~ Prtu-drrtilitia G.damar f fhaE .k&h GrnnlDtktioa ~ 0 f ~ V u n n m J l ! ~ o p c o ~ n
T u ma frdvne & t a
StabiiiîylrophirtPclMn o f @--nt
L u d & t e d ~ t u n i d i r u t u O r a d r L i k e e . etc1
S h Topocmphy Poteutid for Wt&r Ex- unutclinrit G.oqrphy (mbrn ptca. ZTmI, mzmte) Altir& hba
b a r d Qmirrr (nrk to contractor. 1bn4 -rh- mk) Coatractor Payment Type &=p. iait. gunnlerd m. etc.)
BelÏe/Nenvork Analysis of Direct Cost Risk in Building Construcrion 1 03
BelieJiVenvork Analysis of Direcl Cosr Risk in Building Consrnrcrion 1 O4
BeIiefiVenvork Anal),sis of Direct Cosr Risk in Building Consrnrcfion 1 05
Appendix C: Risk Survey Analysis
Belief Nenvork Rnaiysis of Direct Cos! Aisk in Bdi ing Construcfion 1 06
Cast Ouerrun
Partiçipant [contractor. sub. supplier) Failure-related delays
Contractor Failure
Relationships
Subcontractor Failure
Score Councs
0 1 1 ( 2 1 3
Subcontractor Fiilure
Suppiier Faiiure
Supplier Failure
Supplier Failure
Construction claims
Construction claims
l
Cost overrun
Participant failure related delays
Part ie i~rnt failure relatcd delaus 1 1 2
Contractor Faiiure
Partiapant failure related delays
Contractor Failure
Subcontractor Failure
Cost overrun
Contractar failure
Construction claims
Construction claims
Cosc o f equipment
Cost o f Labour
Project Manager Budget Correcting Measures
Project Manager Budget Correcting Meanires
Tirneliness o f Cost ReportingtAccounting
Timeiïness of Cost ReportingtAccounting
Construction Delays [not participant-failure relate4
Construction Oelays [not participant-faiiure relate4
Construction Oelays [not participant-failure related)
Canstruction Delags (nat participant-failure relate4
1 2 5 1
1 0 3 5
3
2 2 3 2
0 4 3 2
2 4 2 1
1 3 3 2
0 1 3 5
2 4 1 2
Unbudgeted ouertime
Unbudgeted overtime
Unbudaeted overtime
Construction Oelays [noc parricipant-failure reiated)
3 -
-
Subcontractor Failure
Supplier Failure
Casc overrun
Cost ovrrrun
Construction Delays [not participant-failure relateq
- -
2 4 1 2
2 6 0 1
2 2 3 2
2 2 3 2 - -
Construction claims
Cost OF equiprnent
Cost o f labour
Labour productiuity
Lahaur ocoductiuitu
Labour productiuity
Labour productiuity
Cnsr af materials
-
0 0 4 5
6 0 2 1
1 0 1 7 I ! Cost owerrun
1 Unbudgeted oueriime
Construction clairns
Proiect manager budget correcting measures
Cost overrun
Construction daims
Cost o f equipment
COSC o f labour
-
3 4 1 1
5 2 1 1
4 4 1 0
3 1 3 2
0 1 3 5
1 0 5 3
4 0 3 2
0 1 5 3 -
Unbudgeted ouertirne
Proiecc manager budget correcting measures
Cost of equiprnent
Cost of labour
Unbudgeted overtime
Construction delays (not participant M u r e relared)
Cost owrrun -
Cost of materials
Material Waste
Defectiue work -rnistakes
0 2 2 5
1 2 4 2
3 2 3 1
0 1 2 6
a 2 2 5
0 1 6 2
1 3 2 3
Oefective work - rnistakes
Oelective work - mistakes
Oefectiue work - mistakes
Oefectiue work -rnistakes
Coordination of Trades
-
Design changes
Design changes
Desian chanaes
-
Project manager budget correcting rneasures
Cost of materials
Construction claims
Coordination of Trades
Coordination of Trades
Coordination of Trades
Oesian chanaes
Construction delays [net participant failure related]
Labour productivity
Cost o f materials
Materiai Vaste
Construction Claims -
Construction delays [not participant failure related]
Material Vaste
Defective work - mistakes
Canstruction clairns -
Cost of equipmenr
Constructian delays (not participant failure relate4
Labour oroductivitu 1 0
i?ehefrVefwork =Ina/ysis of Direct Cos[ Risk in B~ulding Consrrucrion 107
-- - -
0 2 6 1
0 3 5 1
2 3 3 1
Design changes
Design changes
.-
2 2 3 2
1 3 1 4
0 2 5 2
0 1 4 4
1 1 4 3 -
0 2 2 5
3 5 0 1
0 4 1 4
0 1 1 7 -
3
-p
-
Cost of materials
Defectfve work - rnistakes
--
3 2 1 3
0 1 2 6
2
2 1 2 4
3 1 2 3
4
Belief Xenvork Analysis of Direcr Cosr Hisk in Btirldrng Consrntcrion 1 O8
5
3
Bonding of ContractorslSubcontractors
Bonding OF ContractorslSubcontractors
Banding of ContractorslSubcontractors
eonding of Contractors~Subcontractors
Deviatian from enpected quantities of work
Oeviation from expected quantitiesof work
Oeviation from erpected quantities of work
Reguhtory Penalties
Regulatotg Penalties
Regulatoq Penalties
York Stoppages oabour strifelpublic opposition. unrest]
Vork Stoppages (labour strifefpublic opposition. unrest]
Work Stoppages [labour strifefpubfic opposition, unrest]
Materials delivery t o site uncertainty
Matenalsdelivery CO siteuncertainty
Presence o f a cooperarivelpartnering environment
Presence of a aooperativelpartnering environment
Presencc of a cooperativefpartnering environment
Presmce of a cooperatiurfpartneiing environment
Presence of a cooperativefpartnering environment
Presence o f a cooperaiivelpartnering environment
International market-related price increases
international market-related price increases
International market-related price increases
International market-related price increases
Use of Foreign purchased rnaterialsfequipment
Adequate quantity of quality materials in area
Adequare quaniiiy o f quality materials in area
Adequate quantity o f quality materials in area
Equipmcnt productivity
Equipment productivity
Equipment productiuity
Availabiiity of suitable equipment
Auailablty o f suitable equipment
Availability of suitable equipment
Material lEquipment Loss
Material IEquiprnent Loss
Material IEquÏpment Loss
Material IEquipment Loss
Labour lniurieslaccidents
Labour Iniuriestaccidents
Labour lniuriestaccidents
Labour lniurieslaccidents
Labour In~urieslaccidents
Labour Iniurieslaccidents
Availability of qualified keg labour personnel
Availability of qualifitd key labour personnel
Availabiliiy OF qualiiied key labour personnel
Availability of qualified key labour personnel
Avaifability o f qualified key labour personnel
Bonding of ContractorslSubcontractors
Cost overrun
Proiecc manager budget correcting meanires
Design changes
Construction clairns
Construction delays [not participant failure relate4
Labour productivity
Construction claims
Construction delays[not participant FaÏiure related]
Cost overrun
Construction claims
Proiect manager budget correctrng measures
Construction delays [not participant failure related]
Coordination of Trades
Materials delivery to site uncertainty
Cost overrun
Cost of equipment
Proiect manager budget correcting measwes
Cost of materials - International market-related price increases
Cost of rnaterials
Materials delivery to site uncertainty
Use o f Foreign purchased materials~equipment
Cost of equipment
Construction delays (not participant failure relateq
Labour productivitg
Cost of equipment
Use o f foreign purchased materialsfequipment
Equipmenc productivity
Cost of equipment
Construction delays (not participant failure relate4 -
Cost o f mdtetiak
Avaiiability of suitable equipment
Cost of labour
Construction delays [no& participant failure related]
Labour productiviiy
Oefective work - mistakes
Regulatory penalties
Work stoppages
Cost of labour
Construction delays [nat patticipant failure relaied] p .
Labour productivity
Oefective work -mistakes
Labour lniuriesfaccidents
Contractor Failure --
Subconrractor Failure
Construction claims
Labour productivity
Defective work - mistakes
Construc<ion claims
Consauction delays [not participant failure relate4
Cost of materials
3 5 1 0
5 2 1 1
5 1 2 1
0 1 2 6
0 2 2 5
0 4 1 4
2 2 5 0
1 3 4 1
3 4 2 0
4 2 3 0
4 3 1 0
2 3 4 0
2 3 3 1
6 2 1 0
2 4 2 1
3 5 1 0
2 5 2 0
1 5 1 2
1 2 2 4
0 5 1 3
0 4 2 3
3 2 2 2
1 3 3 2
2 2 4 1
3 2 3 1
0 2 3 4
1 1 6 1
0 0 3 6
3 3 2 1
1 3 3 2
1 3 3 2
4 1 2 2
1 6 1 1
1 4 3 1
4
4
--
O
0
3 1 1 3
6 3 0 0
8 1 0 0
5 2 2 0
1 1 5 2
1 1 6 1
2 4 3 0
-
3 3 2 1
7 2 0 0
4 1 3 1
3 4 1 1
O
0 1 8 0
0 3 4 2
2
2 2 5 0
3 1 1 3
Proiect manageras abilitylwiilingness to meet obligarions 1 Timeliness of cost reporiingtaccounting 1 2 1 0 1 3 ) 3
Oeuiation from expecred quantities o f work
Unseen Ground Conditions
Unseen Ground Conditions
Unseen Ground Conditions
Unseen Ground Conditions
Unsecn Ground Conditions
Unseen Ground Conditions
Unseen Gtound Conditions
Unseen Ground Conditions
Timehess o f design
Belief Nenvork itnaiysis of D i rec t Cos! Risk ln Building Constnrctron 1 O9
Avaïiability of qualified key labour personnel
Construction daims
Cast of equipment
Construction delays (not participant failure relate4
Labour productivitg
Cost of materials
Equipment productkity
Availabiiity of suitable equipment
Deviatian from ewpected quantities of work
Construction claims
4 2 2 0
0 0 2 7
1 2 5 1
0 1 1 7
0 4 3 1
5 2 1 0
1 2 4 2
3 4 0 1
0 0 4 4
0 1 3 5 ---- Tirnefiness of design
Quality of design
Quality of design
Quafity OF design
Quality of design
Quality o f design
Quality of design
Completeness o f design
Cornpletenes of design
Completeness OF design
Completeness o f design
Completcness o f design
Cornpleteness o f design
Cornpleteness o f design
Scope Creep
Scope Creep
6
2
0 5 3 1
---- 0 1 6 1
6 0 1 1
0 1 5 3
2 4 3 0
Scope Creep Unbudgeted overtime
Construction delays [noc participant failure relate4
Labour productivity
Oefective work - mistakes
Design changes
Deviation frorn erpected quantiries of work
Unseen ground conditions
Timeliness o f design
Construction delays [not participant failure relate4
Labour productivity
Design changes
Scope Creep
Scope Creep
Scape Creep
Scope Creep
Scope Creep
Scope Creep
Scope Creep
Scope Creep
Budget revisions allowed
Budget revisions allowed
Budget revisions allowed
Change in Tenant Requirernents
Change in Tenant Requkements
Change in Tenant Requirements
Change in Tenant Requirements
Change in Tenant Requïrements
Change in Tenant Requirements
Change in Tenant Requirernents
Change in Tenant Requircrnents
Proiect managrrSs abilityfwillingness to met t obligations
Project manager's abilitylwillingness to meet obligations
Proiect manager's abilitylwiilingness CO mecc obligations
Proiect managerw+ abilityiwîilingness to rneet obligations
0 0 4 4
0 3 2 2
0 0 2 6
0 2 5 1
1
2 1 1 4
0 0 3 5
0 3 1 5
0 0 2 6
1 2 3 3
--
O
5
1 2
O
Oeuiation from expected quantities of work
Unseen ground conditions
Timeliness of design
Quality of design
Construction claims
Cost of equipment
Cost of materials
Design changes
Adequate quantity OF quarity materialsin area
Availabiiity OF suitable equipment
Availability of qualified key labour personnel
Timeliness of design
Qualicy of design
Cornpleteness of design
Cost overrun
Project manager budget correcting rneasures
Deviation from ewpected quancities of work
Construction Claims
Cost of materials
Material Waste
Design changes
Avaiiahility of qualified key labour personnel
Deviation [rom erpected quantities of work
Completeness of design
Scope creep
Cost overrun
Construction clairns
Unbudgeted overtime
Project manager budget correcting rneasures
O 3
0 4 2 3
0 1 1 7
0 2 5 2
O 1 7 1
0 1 6 2
1 3 3 2
1 0 3 5
4 3 1 0
3 3 2 0
4 3 0 1
0 2 2 5
0 2 6 1
0 5 2 2
1 1 5 2
0 2 5 2
1 2 5 1
0 1 4 4
3 3 2 1
1 4 4 0
0 1 1 6
3 4 0 2
3
1 4 4 0
3
Proieet manager's abilityfwiningness to mcet obligations Construction delays [not participant failure relate@
Proiect manager% abilitylwillingness to meet obligations 1 Labour lniuriesfaccidents
Proiect manager's abilitylwillingness to meet obligations
Projecr manager's abiiitylwillingness to meet obligations
Proiect manager% abiiitylwillingness to rneer obligations
Proiecc manager's abïiîtyfwillingness to meet obligations
Contract Clauses Irisk to contractor. shared. owner bears riskl
Contract Clauses [risk t o contractor. shared. owner bearsrisk)
toni ract Clauses [risk to contractor. shared owner bearsrük)
Coordination of Trades
Regulatory penalties
Presence of a cooperarivefparmering environment
Contract Clauses [risk to contractor. shared. owner bears risk]
0 4 5 0
1 4 4 0
O 1 4 4
1 Scope creep
1 ~ o s t overrun
Construction claims
Contract Clauses [risk to contractor. shared. owner bears risk) ( Project manager's abilitt~iwillingness to meet obligations ( 3 ( 3 ( 2 ( O
2 3 3 1
1 5 3 0
3 3 1 2
1 Design changes
Vork stoppages
Contractor Payment Type [lump. unit. guaranteed max. etc.]
Contractor Payrnenc Type [lump. unit. guaranteed mai. etc.]
Cost overrun l 6 1 2 l o l 1
Construction daims I s I 4 l O l o
4 , 4
Construction Procurement [design build, CM. etc.)
Construction Procurernent (design build, C M etc.]
Construction Procurement (design build. CM. etc.]
Proiect manacier's famiiiafitu with tuue of wark
5 4 0 0
1
Contractor Payment Type [lump. unit. guaranteed mai. etc.]
Contractor Payment Type (lump. unit. guaranteed mai. etc.]
Contractor Payment Type [lump. unit. guaranteed max. etc.)
Contractor Payment Type [lump. unit. quarantecd max. etc.]
Construction Procurement (design build. CM. etc.]
Construction Procurement [design build, CM. etc.)
Construction Procurement [design build. C M etc.)
O
Unbudgeted overtime
Proiect manager budget correcting rneanires
Proiect manager's abiiityfwiflingnesr to rneet obligations
Contract dauses
Construction claims
Coordinaiion of Trades
Presence of a cooperativelpartnering environment
Project manager's abilityfwillingness to meet obligations
Contract clauses
Contractor Paymcnt type
Unbudaeted overtime
Proiect manager's tarniliarity with type o f work
Proiect manager% famiiiarity with typeof uork
ConstructionlOperations Interference Problems (Coordination of Trades
3
3 1 2
Project manager's knowledge of geographical area
ConstructionfOperations Interference Problems
ConstructionlO~erations Interference Problems
CanstructionlOperations lnterkrence Problems ( Work stoppages
Proiect manager% familiaritg with type of wark
- - -
Construction delays (not participant failure relate4
Coordination of Trades
3
2
1 4 2 2
1 3 1 3
2 6 1 0
Unseen ground conditions
Construction deldys (not participant failure related]
Labour ~roductivitu
- -
CanstructiontOperations lnterference Problems MaterialfEquipment Loss
1
-
ConstructionfOperations Interference Problems 1 Labour Iniuriesfaccidents
6 2 1 0
5 4 0 0
2
0 5 3 1
3 3 1 1
1 7 1 0
2 5 1 1
O
3 1 2 0
1 3 5 0
ConstructiontOperations Interference Problems 1 Materials delivery to site uncertainty
Ability to secure prowct site
Ability ta secure proiect site
O
-
ConstrucÜcnfOperations Interference Problems
Abiiity ro secure project site
Abiiity to secure project site
Ability to secure proiect site
Traffic congestion onlaround site
1 3 5 0
1 2 4 2
2
Equipment productiuity
--
Traffic corigestion onlaround site
Traffic congestion oniaround site
Traffic congestion anfaround site
Traffic congestion onfaround site
Amount o f Site accessfegress
Amount o f Site accesslearess
Arnount of Site accesslegress
Amount o f Site accessfegress
Amount o f Site accessfegress
3 3 2 1
5
0 4 5 0
l ~ o r k sto~oaaes l l l ~ l ~ l O
2
Materials delivery to site uncertainry
MateriallEquiprnent Loss
Labour Iniurieslaeeidents
Constroetion~Ooerations interference ~roblems
Labour productivity
Materials delivery to site uncertainty
Labour lniurieslaccidents
4
ConstiuctionlOperations interference prablems
Ability to secure project site
Labour ~roductivitu
Belief Nenvork Anabsis of Direct Cosr Risk in Building Consfntction 110
-
1 1 4 0 1 7
0 5 3 1
0 7 2 0
2 4 3 0
Materialsdelivery to site uncertainty
ConstructionfOperationsinterference problerns
Ability to secure project site
TraRic congestion oniaround site
5
1 6 1 1
4
1
-
2 7 0 0
1 1 4 3
O
0 7 2 0
O
1
O
--
1 5 3 0
0 5 4 0
1 2 5 1
0 1 4 4
Permitting Requiroments
Perrnitting Requirernenis
Permitting Aequiternents
Number OF workers on site
Nurnbcr o f workers on site
Nurnber of workers on site
Nurnber of workers on site
Nurnber of uorkers on site
Number o f workers on site
Nurnber o f woriers on site
Nurnber o f workers on site
Nurnber o f workers on site
Environmental Hatards
Environmental Hazards
Enuironmental Hazards
Environmental Hazards
Environmental Hazards
Environmental Hazards
Environmental: Hazards
Environmental Hazards
Environmental Hazards
New technology requirements for construction
BeliefrWwork Anaipis of Direct Cost Risk in Building Cons~nrction 11 1
Regulatonj penalties
Labour Iniurieslaccidents
Contract clauses
Labour productiviig
Oefective work - rnistakes
Coordination of Trades
New technoloqy rtquirements for constructian
New technology requirements for construction
New technology requirementsfor construction
New technologg requirements for construction
New technology requirements for construction
New technology requirements for construction
New technalogy requirements for construction
New technologg requirements for construction
New technology requirements for construction
CompleritylConstrucUbility of design
CornplewiiylConsiructabiIity of design
Compleniq!Constructabiiiq of design
ComplenitylConstructability of design
ComplewitylConstructabilirg of design
ComplexitylConstructability of design
ComplewitylConsWctability of design
CornplewitylConstructabiIity of design
ComplexitylConstructability of design
CornplexitylConstructability of design
ComplewitytConstructability of design
CornplewitylConstructability of design
CornplenitylConstructability of design
CamplewitylConstructability of design
Complewity~Const~ctabiiity of design
Coordination of design teams
Coordination of design teams
Coordination of design tearns
Coordination of design teams
Coordination of design tearns
3 1 5 0
8 1 0 0
1 5 3 0
2 6 1 0
6 3 0 0
3 4 1 1
Equipment productivity
Labour Iniuriestaccidents
ConstructiontOperations interference problerns
Abilitg to secwe project site
Traffic congestion onlaround site
Amount of site accessleqress
Unbudgeted ouertime
Construction delays (not participant M u r e relate4
Labour productivity
Regulatory penalties
Work stoppages
Equiprnent productivity
Labour lniuriestaccidents
Contract clauses
Perrnitting requirements
Unbudgetad overtime
2 6 1 0
0 6 3 0
2 5 1 1
1 4 4 0
0 2 5 2
1 5 2 1
4 3 2 0
O 4 4 1
1 6 2 0
2 2 3 2
1 2 3 3
2 5 2 0
2 3 4 0
0 5 4 0
2 3 2 2
3 5 1 0 -- --- -
Construction delags (notparticipant failure related]
Labour productivity
Defective work -mistakes
Labour lniuriesiaccidents
Contract clauses
Proiect manager's farniliariry with type of work
Perrnitting requirements
Number o f workers on site
Environmental Hazards
Unbudgeted overtime
Construction delays (not participant failure relate4
Labour productiuity
Defective work - mistakes
Coordination of Trades
Design changes
Equiprnent productivity
Labour lnjurieslaccidents
Tirneliness of design
Quality of design
Completenessof design
Contract clauses
Permitting requirernenrs
Number of workers on site
New tcchnology requirements for construction
Design changes
Tirneliness of design
Quality of design
Completenessof design
Scope creep
2 5 1 1
0 4 4 1
0 3 4 2
0 2 2 5
0 1 4 4
0 3 4 1
0 7 2 0
1 5 2 1
1 5 1 2
4 5 0 0
1 6 2 0
0 2 7 0
3 6 0 0
3 5 1 0
7 1 1 0
3 2 3 1
2 1 6 0
1 3 3 2
0 5 2 2
O 3 4 2
0 4 4 1
1 4 4 0
3 5 1 0
2 2 4 1
1 5 1 2
1 5 2 1
2 5 2 0
5 4 0 0
0 0 5 4
Available qudified key proiect management personnel Work stappagw + 3
Auailable qualitid key proiect management personnel
Auailable quafifiid key proieet management personnel
AvaiJable qualified key proiect management personnel
Available quaGfied key proiect management personnel
--
Private or Publicly funded iob
Private or Publicly funded job
Private or Pubiicly funded iob
Private or Publiclu funded iob
Construction claims
Tünelmess of cost repartinglaccounring
Construction delays (not participant failure relate4
Coordination o f Trades
Available quatified key prokct management personnel
Auailable qualified key proiect management personnel
Available qualified key proiect management personnel
Available qualified key proiect management personnel
Available qualified key project management personnel
Auailable qualified key p ro je t management personnel
Auailable qualified key proicct management personnel
Available construction support faciüties (housing. e t c ]
Available construction support facïlïties (housing. etc-]
Auailable construction support faclties (housing. etc.)
Available construction suppoit faclties (housing. etc)
Private o r Publicly funded iob
- --
Construction rnatket prier cscalation
Construction market price escalation
Construction matket mice escalation
0 1 5 3
1 2 4 0
1 5 3 0
1 2 4 2
Presence of a cooperativelpartnering environment
Proiect manager's abilitglwilhgness to meet obligations
Construction procurement
Proiect manager's famiridrity uith type of work
Project manager's knowledge of geographical area
Const~ctionlOperations interference problems
Coordination o f design tearns
Labour productivity
Work stoppages
Availability of qualified key labour personnel
Nurnber of workers on n'te
Construction claims -
1 Budget revisions allowed
Contract c lauss
Contractor Payment type
Construction procurement
Belie f Nenvork Analysis of Direcf Cost Risk in Building Constnrction 112
O
3
O
O
O
2
3
3
Construction market price escalation
Construction market price escalation
Construction market price escalation
Other maior construction aetivitg in area
Other maior construction activity in area
Other major construction activity in area
Other maior construction activity in area
Other major construction accivity in area
Other maior construction actiuity in area
Other maior conscntction activity in area
Olher maior construction activity in area
Owner financial stabiiïty
Owner financial stabiMy
Owner financial stability
Owner financial stability
Physical proiect site
Physical proiect size
Physical proiect size
Physical proiect size
Physical project site
Physical project size
Physical proiect sRe
Physical proiect sire
Competing activity o n site
Campeting actiuity on site
Competing activity on site
Cornpeüng activity o n site
1 1
2
2
I l
2
3
1
1 6
6
1 4
4
5 -
1 5 2 1
1 6 2 0
2 3 3 1
5 1 3 0
-
- - ---
Proiect manager budget correcting measures
Cost of materials
Budger revisions allowed
Cost of materials
Materials delivery to site uncertaintg
Adequate quantity OF quaiity materials in area
Avaiiability of suitable equipment
Availability of quabfied key labour personnel
Available qualified key proiecc management personnel
Available construction support
Construction market pnce escalation
Budget revisions allowed
Contract clauses
Contractor Payment type
Construction procurement
Construction delags [not participant failure relateq
Labour productivity
Coordination of Trades
Unseen ground conditions
Ability t o secure proiecl site
Traffic congestion onlaround site
Amount of site accessfegress
Permitting requirements
Construction delays [not participant failure related)
Labour productiuity
Coordination of Trades
Equipment productivicy
Cost ouerrun
Cost of equipment 1 0
Cost of labour i l
1 3 4 1
5
2
3
3
1
3 --
1 -
3 -3
3 6 0 0
0 6 3 0
0 5 4 G
1 2
0 2 5 2
1 2 4 2
1 5 3 0
1 7 1 0
0 5 3 1
0 3 5 1
O 0 0 1
O 0 5 4
0 5 3 1
1 1 6 1
0 4 4 1
1 3 3 2
3 1 3 2
3 3 2 1
3 4 2 0
3 4 2 0
0 4 3 2
4 3 2 0
0 6 2 1
1 3 4 1
2 3 4 0
3 3 3 0
1 5 3 0
Competing activity on site
Competing activity on site
Competing actiuitg on site
Compethg actiuity on site
Competing a&vity on site
Competing activity on site
Competing activity on site
Competing activity on site
Competing activity on site
Availability of energy
Availability o f enrrgy
Auailabilitg of enrrgy
Availability of energy
Avaiiability OF energy
Availability of energy
Availability of energy
Presence!location OF utilities
Presencellocation of utilities
Pfesencellocation of uiilities
Presenceflacation of utiiities
Presencellocation of utilities
Presenceflocatian of utilicies
Prcsencellocation of utilities
Presenceflocation of utiliries
Presencelloution of utilities
General area affluenceluealth
General area affluenceiweakh
General area affluencefwealth
General inflation
General inflation
General inflation
O
3
Labour lniurieslaccidents
ConstructionlOperations interference problems
Ability to secure project site
Traffic congestion onlaround site
Amount of site accessfegress
Permitting requirements
Environmental Hazards
New technology requirements for construction
ComplenitylConnructability of design
Cost of equipment
Construction delays (not participant failure rrlated]
Labour praductivity
Cost of materials
Use of foreign purchased materialslequipment
Equipment productiuity
New tecfinology requirements for construction
Construction delays [not participant failure related]
Eauiornent oroductiuitu
General inflation
General inflation
General inflaiion
General inflation
General inflation
Arnount OF government spending o n construction
Amount of government spending o n construction
Amount of governrnenc spending o n construccion
Amount of gouernment spending on construction
Tax Rates
Belief Nenvork rlnalysis of Direct Cosr Risk in Btrilding Consrnrcf~on 113
Labour hiurieslaccidents
Unseen ground conditions
Perrnitting tequirements
Enuironmental Harards
New technology rrquirements for construction
ComplerityConstructability of design
Auailability of energy
Traffic congestion onhound site
Available consiruction support
Private or publicly funded iob
Cost overrun
Cost OF equipment
Cost OF labour
Tdx Rates
Tax Rates
Tan Rates
fan Rates
Tan Rates
Tan Rates
Tax Rates
Exchange Rates
Exchange Rates
Ewchange Rates --
5 4 0
6 2 1
3 3 2
2 4 2
1 3 5
1 3 4
1 6 2
4
3 2 4
0 4 4
0 5 4
4 4 1
7 2 0
6 2 1
5 2 2
2 4 1
1 5 3
4
Project manager budget correcting measures
Cost of materials
Construction market price escalation
Other maior construction activity in area
General area affluencefwealth
Private or publicly funded iob
Construction market price escalation
Other major construction activity in area
General inflation
Cost overrun
4
2
2
-- -
Cost of equipment
Cost of labour
Project manager budget correcting measures
Cost of materials
Other maior construction activity in arra
General area affluencelwealth
General inflation
international market-related price increases
Use of Foreign purchased materialslequipment
General inflation
0 5 3 1
2 2 3 1
3 2 3 0
3 6 0 0
4 1 3 1
6 1 2 0
4 3 1 1
2 3 3 1
0 0 5 4
0 2 3 4
2 2 5 0
5
2 6 1 0
1 6 1 1
0 1 5 3
3 2 4 0
4 1 1 0
1 2 3 3
1 2 5 1
1 2 6 0
2 7 0 0
4 2 3 0
4 2 1 2
0 4 3 2
1 5 2 1
5 3 1 0
O
5 0 2 2
5 3 1 0
0 4 3 2
4 5 0 0
0 6 2 1
0 4 2 2
0 3 3 2
2
Belref Arenvork Analysis of Direcr Cosr Risk in Building Consrrirction 114
. .-
Stabilityfsophistication of government
Sabilitylsophistication o f government
Stabfitytsophistication o f govemment
Stabilitglsaphisti~tion o f government
StabilihJlsophtication of governrnent
Stabilityhophistication of government
Land refated natural d i s t e r (Iandriide. earthquake. etc)
Land related natural dirasier (landsiide. earthquake. etc]
Land related natural disascer [landslide. earchquake. etc]
Land related natural disaster [landslide. earthquake. etc] -
Land related riaturai dwster [landskde. earthquake. etc]
Land related natural disaster [landsiide. earthquake. etc]
Land related natural disaster [landslide. earthquake. etc]
Land related natural disaster [landsiide. earthquake. etc]
Land related natural disaster [landsiide. earthquake. etc]
Land related natural disaster [landslide. earthquake. etc]
Land relatcd natural disaster [landsiide. earthquake. etc)
Site Topographg
Site Topography
Site Topagraphy
Site Topagraphy
Site Topography
Site Topography
Site fopography
Site Topography
Potential for Weather Entremes
Potentialfar Weather Extremes
Potential for Veather Entremes
Potential for Weather Ewtremes
Potential for Wealher Extremes
Potential for Weather Ewtremes
Potential for Weather Enrremes
Potential for Weather Extremes
Potential for Weather Entremes
Patential for Weather Entremes
Usual clirnate
Usual climate
Usual climate
Usual climate
Usual climate
Usual climate
Usual climate
Usual clirnate
Usual climate
Usual climate
Usual climatc
Geography turban proiect. rural. remote]
Geography (urban project. rural. remote]
Geography (urban proiect. rural. remote]
Geography (urban proiect. rural. remote]
Geography (urban project. rural. remote]
2 3 4 0
2 2 3 2
0 4 2 3
0 4 I l
1 2 3 3
1 3 2 3
0 0 5 4
3 3 2 1
5 4 0 0
6 3 0 0
3 4 1 1
6 2 1 0
1 5 2 1
1 4 2 2
O 7 1 1
0 4 5 0
1 3 2 3
2 4 3 0
1 4 4 0
3 4 2 0
3 3 2 1
3 4 1 1
3 4 2 0
2 5 2 0
2 3 4 0
1 2 6 0
0 2 7 0
3 6 0 0
O 8 1 0
2 5 2 0
0 9 0 0
3 3 2 1
3 5 1 0
3 4 2 0
1 1 6 1
6 1 1 1
5 1 3 0
5 1 3 0
4 4 1 0
3 3 3 0
2 1 2
Régulatory penalties
Perrnittmg requirements
Private o r publicly funded iob
Amount a f gouernment spending on construction
Taw rates
Exchange rates
Construction delays [not participant failure relate4
Labour productivity
Cost o f materials
Material Vaste
Materials delivery to site uncertainty
Adequate quantity of quility materials in area
Availability o f suitable equipment
MateriallEquipment Loss
Labour lniuriestaccidents
Environmental Hazards
Availability of energy
Labour productivity
Equipment productiuity
Unseen ground conditions
Environmental Hazards
ComplewitytConstructability of design
Physicdl proiect size
Presenceflocation of utilities
Land reiated natural disaster
Unbudgeted ouertime
Construction delays [not participant failure related)
Material Vaste
Materials deliuery to site uncertainty
MaterialtEquipment Loss
Labour lnjuriesfaccidents
Environmentat Hatards
ComplewityiConstructabilÎty of design
Auailability of energy
Land related natural disaster
Unbudgeted overrjme
Construction delays (not participant failure related)
Labour produciivity
Materials delivery to site uncertainty
Equipment productivity
Labour Injurieslaccidents
Environmental Hazards
New technology requirements for construction
Comp:exi~yfConstructabilitq of design
Land related naturai disaster
Patential for weather entremes
Cost of equipment
Cost of labour
Labour productivity
Cost of materials
Materials delivery to site uncertaintg
----
2
5 3 1 0
5 3 0 1
3 5 1 0
5 3 1 0
3 4 2 0
3 1 4 1
2 3 3 1
0 1 7 0
5 2 2 0
3
1 5 3 0
Geogfaphy turban project. rural. remote]
Geography turban proiect r u r d remore)
Geography [urban proiect. niraï. remote]
Geography turban proiect. rurai. remote)
Geography turban proiect. mai. remote]
Geography (urban proicct. rural. remote]
Geogaphy [urban proiect. rural. remote]
Geography [urban proiect. ~ r a l . remote]
Geography (urban proiect. rurai. remate)
Geography (urban project.rural.remote]
Geography [urban proiecr. rural. remote] - -
Geography [uiban proiect. rural. remore]
Altitude
Altitude
Altitude
Altitude
Altitude
Altitude
Altitude
Altitude
Aitirude
Altitude
Altitude
Altitude
Altitude
4
Use of foreign purchased materialdequipment
Adequate quantity of quality materials in area
Auailability o f mitable equipmenr
Auailability of quaiified keg labour personnel
Proiect manager's knouledge of geographical area
Traffic congestion onlaround site
Phyr ia l praject size
Auaiiability of energy
Presenceflocation oF utilities
General area affluenceluealth
Potential for weather ertremes - - .
Usual climate
Cos; of equipment
Cost of labour
Altitude
Altitude
Altitude
Geolagy
Geolagy
Labour produciiuity
Cost of materials
Materials deliuery to site uncertainty
Equipment productivity
Unseen ground conditions
New technology requirements for constructian
ComplenitylConstructability of design
Avdilability of energy
Presenceilocation of utilities
Land related natural disaster
Site :opography
-
Geobgy
Geology
Geoloau
2
4 3 1 1
5 3 1 0
3 6 0 0
6 2 1 0
6 2 1 0
5 4 0 0
5 3 1 0
4 2 3 0
4 3 2 0
2 5 2 0
3 1 4 0
Potential for weather extremes
Usual climate
Geography
Cost of equiprnent
Unbudgeted overtime
--
Geology
Geology
Geology
1 3 4 1
3 5 1 0
4 2 3 0
2 3 3 1
3 2 4 0 - -- -- - -
Construction delaystnot participant failure relate4
Labour productiuity
Cost of materials
Geology
Geology
Geology
Geology
Geology
Geology
Geology
Geology
Geology
BeliejA'envork .Inalysis of Direct Cosr Risk in Building Consfnrcfion 115
6 1 2 0
2 3 3 1
0 5 2 2
3 4 2 0
2 3 4 0
4 3 1 1
4 3 2 0
0 5 2 2
3 3 2 1
4 4 0 1
3 2 2 2
5 3 1 0
5 2 2 0
2
- -- - -
Design changes
Adequate quantity of quality materials in area
Equipment productiuity
Geology
Geology
-
0
0 0 7 2
2 2 4 1
7 1 1 0
1 1 6 0
7 1 0 1
3 1 5 0 -
Oeviation from erpected quantities of work
Unseen ground conditions
Enuironmental Harards
New technology requirernents for construction
CompleritylConstructabiliiy of design
Auailability of eneigy
Presencellocation of utiiities
Land related natutal disaster
Site topography
-
Geography
Altitude
2 2 3 1
3 3 2 1
6 2 1 0
1 1 7 0
0 1 5 3
3 4 2 0
5 2 2 0
1 4 4 0
6 2 1 0
4 3 2 0
0 1 5 3
Appendix D: Divorcing
Belief Nenrork .4nalysis o j Direcf Cosf Risk in Blrikiing Consrruction 116
Labour Productivity Divorcing
ed key Labour Pe iuctionlOps lnterfe
Construction Delays Divorcing
Behef ~Vefivork Anuiys~s of Direct Cosf Risk in Building Consrnrctcon 117
Construction Claims Divorcing
Appendix E: Asymmetric Assessrnent Structures
Belief iVenvork Anaiysis oJDirec! Cos! Risk in Building Cons!nrcrion 119
Asymmetric Assessment: Construction Delays
Construction Delays Parents: Environmental Deiays Participant Failure Delays Design Delays Logistics Delays Labour Delays
Asymmetric Assessment Structure:
+ Environment Delays + Major X + Minor or None + Participant Failure Delays
3 Major X 3 Minor or None
3 Design Delays + Major + Logistics Delays 3 Major
3 Labour Delays + Major X 3 Minor or None X
-3 Minor or None 3 Labour Delays + Major X + Minor or None X
+ Minor or None + Logistics Delays Major + Labour Delays + Major X
4' Minor or None X + Minor or None 3 Labour Delays
3 Major X 3 Minor or None X
10 probabilities required in total (marked with an X)
Bzlief Senrork .4nalysis of Direct Cost Rirk in Building Consrnrcrron 120
Asymmetric Assessment: Work Quantity Deviations
Work Quantity Deviations Parents: Design Changes Defective Work Change in Tenant Requirements Ground Conditions Design Quality
Asymmetric Assessment Structure:
+ Design Changes 3 Major X 3 Minor or None + Defective Work + Major X
3 Minor or None 3 Change in Tenant Requirements
-3 Major + Ground Conditions + Worse than Expected + Design QuaIity + Poor X + Good X
i As expected or better + Design Quality + Poor X i Good X
+ Minor + Ground Conditions -3 Worse than Expected + Design Quality
3 Poor X -3 Good X
+ As expected or better + Design Quality + Poor X + Good X + None + Ground Conditions
3 Worse than Expected 3 Design Quality
3 Poor X + Good X i .4s expected or better + Design Quality
3 Poor X i Good X
14 probabilities required in total (marked with X)
Asymmetric Assessment: Project Material Shortage
Project Material Shortage Parents: Design Changes MatenalEquipment Loss/Damage Materials Delivery Promptness Material Waste
Asymmetrïc Assessment Smcîure:
+ Materials Delivery Promptness -3 Frequently Late X + Generalty On Time
i Material Waste + Major + MaterialdEquipment Loss/Darnage
3 Major --) Design Changes
+ Major X 3 Minor or None X + Minor or None
+ Design Changes 3 Major X 3 Minor or None X
3 Minor or None + MaterialdEquipment Loss/Damage
-3 Major + Design Changes
Major X + Minor or None X
3 Minor or None Design Changes
3 Major X Minor or None X
9 probabilities required in total (marked with X)
Belief ~Vehvork =lnafysis of Direcr Cost Risk in Bzdding Consrniction 122
Asymmetric Assessment: Suitable Equipment Availability
Suitable Equipment Avaitability Parents: Project Geography Local Construction Market Saturation Materials/Equipment Loss/Damage
Asyrnrnetric Assessment Structure:
+ Local Construction Market Saturation + Saturated X -9 Some Other Construction
9 Project Geography + Remote X + Urban
+ MateriaIsEquipment Lossrnamage 3 Major X 3 Minor or none X + Rural
+ MateriaIsEquip ment Lossrnamage + Major X Minor or none X + Area Consûuction Poor + Project Geography + Remote X + Urban
3 Materia WEquipmen t Lossrnamage 3 Major X -3 Minor or none X + RuraI
3 Materials/Equipment Loss/Darnage + Major X i Minor or none X
1 1 probabilities required in total (marked with X)
BelÏe/:Venvork ilnalysis of Direct Cost Risk rn Building Consrnrcfion 2 23
Asymmetric Assessment: Traffic Congestion odaround site
T r a c Congestion Parents: Site Access/Egress Number of Workers on Site Competing Activity on Site Physical Project Size
Asymmetric Assessment Structure:
+ Physical P r ~ j e c t Size + SrnaIL + Competing Activity on Site + Yes X + No
Nurnber of Workers on Site + Person Congested X 9 Not Person Congested
3 Site AccesdEgress i Insuficient X + Adequate X
3 Large Cornpeting Activity on Site + Yes + Number of Workers on Site
3 Person Congested + Site Access/Egress + Insufficient X
i Adequate X 3 Nor Person Congested
i Site Access/Egress 3 lnsuficient X 3 Adequate X
i No i Number of Workers on Site
Person Congested Site Access/Egress + Insufficient X
3 Adequate X 3 Not Person Congested
i Site AccesdEgress + Insufficient X 3 Adequate X
12 probabilities required in total (marked with X)
Belief Nenvork Anabs is of Direct Cost Risk in Building Cons~niction 124
Appendix F: Cornparison - Probability Survey Interpolated Values to Survey
Values
Beliej'.Venrork Anaiysis of Direcl Cos[ Risk in Building Constnrcrion 125
Labour Productivity Interpolated - Surveyed Value Comparison
Ranking 1
4 5
Polynomial: Rsquared = 0.73 90 -4
Suweyed Average 90
Comparison
Combination Suweved
85.6 83.1
Combination Surveyed
Combinat ion Suweyed
8 9 10 11 12 13 14 15
I
State Combination
16
---- ----- O Labour Productivity Trend Line P o l y . (Labour Productivity Trend Line)
90 90
73.3 69.2 64.7 59.7 54.4 48.6 42.4 35.8 28.8 1 20 1 combinat ion Surveyed
Belief Nenvork Anaipis of Direct Cost Risk in Building Construcfion 126
Combination Surveyed
70 50 60 60 50 70 40 40
Work Quantity Deviations Interpolstted - Surveyed Value Comparison
Ranking 1 2 3
Exponential [Rsquared = 0.59) 81 -4
4 5
Tl -9 63.5
6 7 8 9 1 0
Comparison
Suweyed Average 90
56.1 49.6
State Combination
Combination Surveyed 30 90
43.8 38.7 34.2 30.2 26.7 - -
PP
+ Work Quantity Deviation Trendline ,
Combination Surveyed Combination Surveyed
80 50
- -
40 20 20 10
11 12 13 14
- Expon. (Work Quantity Deviation Trendline) '
Cambination Sutveyed
40 40 30 30 30
Combination Surveyed
Combination Surveyed
23 -6 20.9 18.4 16.3
Belief Nemork Analysis of Direct Cosr Risk in Birrlding Constnrcfion 127
Combination Surveyed
SuitabIe Equipment Availability Interpolated - Surveyed Value Comparison
I I -- I
5 1 53-4 1 40 1 Combination Suiveyed
Ranking 1 2 3
I I . - 1
11 1 40-2 1 40 1 Combination Surveyed
Logarithmic (Rsquared = 0.67) 80.3 68.7 61 -9
6 7
Comparison
State Combination
Surveyed Average 90
50.3 47-7
---- - - -
Suitable Equipment Availability - Log. (Suitable Equipment Availability) -- - - - -- -- - - -- - -- - - ---- --
Combination Surveyed
50 50
Belief h'envork Analysis of Direct Cosr R I S ~ in Bttrlding Constntction 128
8 9
60 60
60 An
45.5 43-5
Combination Surveyed Combination Surveyed
Combination Sutveyed
Appendix G: Probability Curves
Belirf Nenvork rlnnlysis of Direcr Cos1 Risk rn Building Consrrucrion 2 29
Probabiiity Curves
8 Child States, 16 Parent State Carnbinations, Standard Deviation = 2.5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Parent Probabllity Combination Ranking
Source Data
Worst Cas€
Best Case
LIelieJNenvork Anaiysis O/ Direct Cost Risk in Building Consrrucrion 130
Appendix H: Predictor Variable Ranking
Belief Nenvork rlnalysis of Direct COSI Risk in Budding Cons~mc~ion 131
Labour (nst Variable Parent State Rankinq I Parent Variables: Qualified Local Labour inflation Project Geography
Labour FraductMty Overtirne Canstrucîion Delays
Parent Variables: Qualified Local Labour Inflation Projecl Geaqraphy Labaur Productmty Cvertime Constmction Delays
Belief Nenvork Analysis of Direcr Cost Rrsk in Building Cons~nrcfion 132
Labour Cost Variable Parent State Rankinq
Parent Variables: Qualied Local Lahour inRation Projert Geography Labour Productmty Overtime Construction Delays
Parent Variables: Qualified Local Labour inflation Project Geography Labour Product~ty Clvertirne Construction Delays
Belief Nenvork Analysis of Direct Cost Ri& in Btrilding Constnmion 133
Variable State:
4
2 1
Ge~graphy (1 .a) , R e m e
3 X X X X
X
X
Lsbaur ~2.561 hsufficient
X X
X X X X X X X
Rurd
X X
X
~deauate
X
1 PrOdudivPy (2.56) Urfxm
X
=Expected
X X X
X X X X X X
-Erpeded
X
X X X X X
X X
c=Emeded
X
X
=Expected
X
-Expected
X
Deiavr C2.2222)
IX 1
cbpecied
X X X X
X X X X
m m
X X X X
X X X X
Score Minar
X
X
10.50 10.84 11.10 11.10 11.10 11.44 11.78 11.78 12.72 13.66
12.30 12.70 13.00 13 .00 , 13.m 13.40 13.80 13.80 14.90 16.00
Parent Variables:
Parent Variabks:
Eauinment Cmt Variable Parent State Rankinq
Suitable Equipment Availability Inflation Value Engineering Construction Market Escalation Equipment Pmductmty Construction Claims
Suitahle Equipment Availability Inflation Value Enqineerinq ~onstructi~n Market ~scalation Equipmenl Productrvity ~ o n s t ~ c c o n ~ l a h s
Belief Nenvork Anafysis of Direcc Cos! Risk in Btrilding Constnrc!ion 134
Faui~ment Cnst Variable Parent State Rankinq
Parent Variables: Suitable Equipment Amilabiiity Inflation Value Engineering Construdion Market Escalation Equipment Prnductkty ConstrriMion Clairns
BeliefrVenïork Analysis of Direct Cosr Risk in Bdding Consrnrction 135
State: 4 3
1
h s u t r i
X X X X X X
~deguatc
X e ~ e d l -
X X X
X X X
X
*tirpected) -tipecttci J*hpeded --~rpectcd..
X
X
X X X X X
X
-
X X
X X X X
MOW ( MYX
X 1 ~d ~ a d i ~ d
X X X X X
X
X X X
X X
X
Prsdiled
X _
Score 8.20 1 1259 0.64 8.67 8.75 8.92 8.92 10.42
13.27 13.31 13.44 13.70 13.70 16.00
Material Cost Variable Parent State Rankinq Parent Variables: Construction Market Escalation Scope Creep Material Shortage
Design Changes Material Waste Value Engineering
Parent Vanables: Construction Market Escalatron Scope Creep Matenal Shortage Design Changes Mafenal Waste Value Engineenng
Pare Variabl -
Star
Score 13.00 0.00 1.50 2.79 1.67 2.44 1.89 2.76 1.89 2.76 200 2.92 200 2.4 3.17 4.63 3.39 4.95 3.39 4.95 3.50 5.1 1
ire 7.88 7.88 7.96 8.04 8.12 8.12 0.12 8.12 8.28 8.45 8.45 8.61 8.61 10.16 10.32 10.32 10.32 10.32 10.48 10.64 10.64 113.80 10.m 10.89 10.89 11.05 11.05 1 1.37 - 13.08
Belief r\renuork Ana[vsis of Direcc Cost Risk in Building Consrrtrcrion 136
Appendix 1: Probability Survey Results, Prior Probabilities
ID#
f 1
2
5
Cause
Poor P M cIaims mitigation Major Field C l a h
Major Oelay C l a h
Major Design Ctaims
Good P M cbims mitigation Maior Field Claims
Maior Delay Claims
Maior
Poor PM ckims mitigation Maior Field Clairns
Minor or no Delay Claims
Major Design Clairns
6
7
1 Effect
Maior Construc~ion &rns
Maior Construction Clairns
1
Maior Construction Clairns Good PM claims mitigatian Minor or no Field C la im
Maior Delay Claims
Maior Design Clairns
8
9
Belief ~Vefivork Rnalysis of Direct Cost Risk in Building Constnrction 139
3
4
Major Construction Clairns
Good PM clairns mitigation Major Field Claims
Major Delay CIaims
Minor or no Design Claims
10
-- ----
90
80
40
Poor P M clairns mitigation Minor or no Field Claims
Maior Oelay Claims
Minor or no Design Clairns
Good PM clairns rnitigation Maior Field Clairns
Miior or no Oelay Claims
Maior Design Claims
-5
70
40
80
70
Poor P M claims micigaiion Minor or no Field Claims
Maior Oelay Claims
Maior Design Claims
Paor PM clairns mitigation Maior Field Claims
Major Delay Claims
Mmor or no Design Claims
80
Major Construction Clairns
Poor PM clàirns micigation Minor or no Field Cloims
Minor or no Delay Clairns
Maior Design Claims
80
Major Construction Clairns
Major Construction Clairns
Expert
1 2 3
100
70
Major Construction Clairns
Maior Construction Claims
70
70
40
Major Construction Clairns
100
80
80
50
60
90
40
70
80
70
70
70
60
50
80 50
Cause 1 . Expert
11 Poor PM clairns mitigation m i o r Canstruction Claims
Maior Field Clain.
Mnor or no Delay Clairns
M ï o r or no Design Uaims
12 Gaod PM claims mitigatian Maior Canstruction Claims
Minor or no Field Cbims
Maior Oclay Clahs
Minor or no Oesign Clairns
-- 13 Good P M clairns mitigatian Maior Construction Claims
Minor or no Field Claims
Minor or no Oelay Claims
Major Design Claims
14 Good P M daims mitigation Major Construction Clairns
Major FreId C!+ms Minor or no Delay Claims
Minor or no Design Ciaims
15 Poor P M claims mitigation Maior Construction Claims
Minor or no field Claims
MÏnor or no Delay Claims
Minor or no Design Uaims
16 Good
Miior or no
Minor or no
P M cldrns mitigarion
Field Ciaims
OeIay Claims
Major - -
Conslruction Clairns
6 1 Major Construction Delays
Worse than Ewpected Labour Productivity
Overtime
Prescnce OF ~ c o p e Creep I I I I
2 Maior Construction Oelags 1 >expected Overtime
Worse than Erpected Labour Productivity
No Scopr Crrrp
I
3 Maior Construction Oefays > eupected Overtime 80 70 80
As crpected or better Labour Productivity
Presence of ~ c o p e Crrep I I I I
I I I
4 Maior Cornrucrion Delays > expected Overtime BO 70 80
As erpected or beaer Labour Productiuky I I I 1 NO scope Creep I I I I
5 Mino:or no Construction Delays
Vorse than Expected Labour Productivity I --
>erpected Overtime
Presrnce ot Scope Cretp I I I I I I
Belief Xenvork Rnalysis of Direct Cosr Risk in Brdding Conmrcrion 140
ID#
7 j ~ m r a r n o Construction Debys 1 >expected Overtimc 1 30 1 20 1 40 1 30.0 1
Cauzc Elfcct Enpeit Value I 6
1 AS expected ar bctter Labour Producrivirg t 1 1 I I I (Ptesence of Scope neep I I I I I I I
Minoror no Connruction Delays
Voise than Ewpected Labour Productiuitg
No Scope Crcrp
7 1 (Reactive Proiect Manager 1 Untirnely Cost ReportingfAccounting 1 90 1 90 1 80 1 86.7
I I I I I
>ewpected Overtime
8
8 1 ( Maior Environmental Oelays Construction Drlays
I I I I I I
1
60
Minororno Construction Oelays
As eupectcd or bettrr Labour Productiuity
2
2
60
> ewpected Overtime
3
Minoror no Environmental Delays
Maior Participant Failure Oelays
4
3
60
20
Maior Labour Delays
Major Logistics Oelays
Major Design Oelags
Minor or no Environmental Oelays
Minor or no Participant Failure Oelays
( Minor cr no Participant Faiiure Oelaqs 1 1 1 1 1
Used
60.0
Major Construction Delays
Minoror no Labour Oelays
Major Logistics Oclays
Maior Design Delays
Minor or no Environmental Oelays
Minor or no Participant Failure Oelags
I
6
Behef ~Venvork rlnaiysis oJDtrect C o s Risk in Btrtlding Construction 141
10
Maior Construction Oelays
Major Construction Delays 5
100
Maior Construction Oelays
Major Labour Delays
Minor or no Logistics Delays
Maior Oesign Delayr
Minar or no Environmental Delags
Minor or no Participant Failure Delags
Major Labour Delays
Maior Logistics Delays
Minar or no Design Delays
Minor or no Environmental Oelays
1
80
80
100
BO
Maior Construction Oelays
10.3
100
70
1
100
90
80
100.0
BO
70
86.7
80
73.3
80
83.3
70 76.7
I 7 Minororno Labour O e b p Major Cansuuction Oolays
Mmor or n o Loginics Oelays
Maior Design Dclagr
1 *or or no Environmental Oelays 1 ( ~ i n a r or no Partffiipant Faaure Delays 1 I 1
I
8 Minororno Labour Oelays Maior Construction Delays
1 Maior Logistics Oelays I 1 ino or or no Design Delays I 1 Minor or no Environmental D r l a p
1 Minor or no Participant Failure Oelaÿs 1 1 I
- -
Labour Oelays 1 ~ a @ r Consmction Oelays
togistics Delays I 1 Minor or no Design Oelags 1 1 ino or o r no Environmental Oelays 1 1 Minor or no Participant Failure Delags 1 1 I
10 Minor or no Labour Delays
Logistics Oelaps
Design Oelays
Environmental Oelays
Maior Construction Delays
15 1 )frequent Short breaks 1 terpected Labour Produc;ivity
Major Labour Congestion
Major Oehctive SZark
Poor Labour Design Understanding
2 Frequent
Major
Major
. -
Short breaks
Labour Cangestion
Defective Work
pp
Labour Producriviq
( ~ o o d Labour Design Understanding ) 1 I I 1
3 Frequent Short breaks cerpected Labour Productivity
Minor or no Labour Congestion
Maior Oefoctive Work
Poor Labour Design Understanding
4 Frequcnt
Minor or no
Maior
-
Short breaks
Labour Congestion
Oefectivc Wark
cexpected Labour Productivity
( Good Labour Design Understanding 1 I I
5 lnfrequent Short breaks terpected Labour Prmductivity
Maior Labour Congestion
Major Oefective Work
Poor Labour Design Understandhg
Belief .ficfeni*ork Anabsis of Direct COSI Risk in Btrilding Consrnrcrron 142
Short breaks
Maior Labour Congestion
Maior Oef ectiue Work
Labour Oesign Understanding
Short breaks
1 Maior Labour Congestion
Minor or no Oefective Work
Poor Labour Design Underscandimg
I 8 lnfrequent Short break
Labour Congestion
Oefectiuc Vork
1 ~ o o r Labour Oesign Understanding
I 9 Frequent
Maior
Short breaks
Labour C4ngestian
1 -or or no Defective Vork
1 Good Labour Design Understanding I
10 lnfregwnt Short breaks
1 ino or or no Labour Congestion
1 ~ a j a r Oefective Work
1 Good Labour Design Understandimg
I
I I Frequcnt Short breaks
1 Minor or no Labour Congestion
1 hninor or n o Oefective Work
1 ~ o o r Labour Ccsign Understandimg
I 1
12 Frequent Short breaks
I Minor o r n o
M i i o r o r n o
Labour Congestion
Defective Work
1 Good Labour Design Understandmg
I Short breaks
Maior Labour Congestion
Minor o r n o Oefective Wotk
Labour Design Understanding
Short breaks
Maior Labour Congestion
Minor or no Defective Work
Labour Oesign Understandimg
Short breaks
Mimor or rio Labour Congestion
Minor o r no Oefective Vork
Labour Design Understandmg
cewpected Labour ProductMq
ce~pected Labour Productiviq
cenpected Labour Productivity
- -
r expected Labour Productivitg
texpected Labour Producrivity
cexpected Labour Productivity
c expecred Labour Productivity
:erpected Labour Productivitg
:expected Labour Productivitg
-
:expected Labour Productivity
Belief ~Venvork Analpis of Direcc Cosr Risk in Building Com~rttcrion 143
Short breaks
Labour Congestion
Oefrctivs Work
19 1 Forûiiden Budget revisinns
Reactive Proiect Manager
Maior Construction Oelays
--
2 Forbidden Budget revisions
Fieactive Project Manager
Minor or no Construction Oelays
3 Forbidden Budget revisions
Proactive Proiect Manager
Maior Construction Oelays
4
4 Forbideen Budget revisions
Proactive Proiect Manager
Minor or no Construction Oelays
- - - --- -
5 Aflawed Budget revisions
Reactive Project Manager
Maior Construction Delays
6 Allowed Budget revisions
1 fle.uive Project Manager
1 ~ i o r or no Construcrion Oelays
I
Proactive Proiect Manager
8 AUowed
Proactive Proiect Manager
Design Changes l 1 I
2 Minor orno Oesign Changes
Maior Oefective Vork
Design Quality
M i o r Tenant Requirement Change 1 11:~ hn Enpected Ground Conditions
rexpected Labour Producriviq 30 20 30
Uo use of Value Engineering
Uo use o f Value Engineering 40 20 60
Uo use o f Value Engineering
30 use o f Value Engineering
k use of Value Engineering 70 HO 60
JO use of Value Engineering
Io use of Value Engineering 70 50 Sa
1
Io use of Value Engineering 70 70 60
laior Vork Quantity Oeviatians ] 1 90 1 I 100 1 I 90
laior Work Quantity Oeviacions 30 10 30
Minor or n o Oesign Changes
Minor or n o DeFeclive Vork 1 1 1
Belief :Vetwork Analyris of Direct Cosi Risk in Building Construcrion 144
BefieJNehvork Analpis of Direct Cost Risii in Brriiding Constnrction 145
ID#
4
5
6
7
8
9
10
11
Value
Used
83.3
50-0
40.0
50.0
,=
16.7
35.0
Caur
Good Design Quafitg
Maior Tenant Reguuemenr Change Voae thrn Expected Graund Con6itions
Minor or no Design Changes
Mmor or no Defective Work
Poor Design Quafity
Maior Tenant Requirement Change
Asewpecred or better Ground Conditions
Minor or no Design Changes
Mmor or no Defectiue Wotk
Gaod Design QuaGty
Major Tenant Requiremenc Change
As mpected or beltrr Ground Conditions
Minor or no Design Changes
Mmor or no Oefective Votk
Good Design QuaLy
Minor Tenant Requirement Change
Worse than Eiipected Ground Conditions
Minor or no Design Changes
Minor or no Ckfectiue Vork
Poor Design Qualiry
Minor Tenant Requtrernent Change
Vorre than Expected Ground Conditions
Minor or no Design Changes
Mmor or no Oefeuivc Work
Poor Design Quaty
Minor Tenant Requirernent Change
As eipebed or bertet Ground Conditions:
Minor or no Design Changes
Mmor or na Oefective Vork
Good Design Qoafiiy
Minor Tenant Requcremenr Change
As enpected or better Ground Conditions
Minor or no Design Changes
Minor or no Defective Work
Poor Design Quality
No Tenant Requirement Change
Vorse than Enpected Grwnd Conditions
Minor or no Oesign Changes
Minor or no Dcfectiue Votk
1
70
70
40
20
-
00
10
30
fffect
Maior VoikQuantity Deuiations
Major Votk Quantity Oeuiarions
Major Vork Quantity Deuiations
Maior Vork Quantity Drviatians
Maior York Quaniity Ceviarions
Malor Vork Quantiry Deviations
Maior York Quantitg Deviations
Maior VorkQuantity iJevia~ions
Expert
2
100
95
70
SO
70
80
10
-
3
80
55
40
40
30
40
30
40
I Cause I Ulect Enpert
12 1 t o o d Design Quafitg
Tenant Requirement Change
Worse than Erpccted Ground Conditions
Mmor or no Oesign Changes
13 Poor Oesign QuaGty Maior Work Quantity Deuiations 10 - 20
N o Tenant Requirrrnent Change
Ase~pected ar better Ground Conditions
Minor or no Design Changes
1 ~ i n o r o r no Oefective Wark 1 I 1 I
14 Good Oesign Quality Maior Work Quantity Oeviatians 10 10 10
INO Tenant Requirrrnent Uiange 1 I A r erpected or better Ground Conditions
Minor or no Design Changes
21 I 1 Frequentiy Lace Materials Derwery Praiect Material Shartage 1 55 1 95 1 90
I I I I I 2 Major Design Changer Frequent Proiect Mattrial Shortagt
Maior MateriallEquiprnent Loss
Generallg an cime Materials Delivery
Maior Materiai Vaste
3 Minor o r n o Design Changes Frequent Project Material Shartage
Maior MateriaIfEquipment Loss
Generally on tirne Materials OeGvery
Maior Material Waste
4 Major Design Changes Frequenr Pioject Material Sitarcage 50 l a 40
Minor o r n o MateriallEquipment Lass
Generailp on timr Materials Deiivery
Beiiej'iVenvork Anolysis of Direcl Cosr Risk in Building Consrntcrion 146
5
6
7
Maior Material idaste
Major DesignChanges
Maior MateriallEquiprnent Loss
Generally on tirne Materials DeGvery
Minor o r n o Material V a s e
Minororno Oesign Changes
Minor or n o MateriallEquipment Loss
Generally on timo Materials Delivery
Maior Material Waste
Minor o r n o Design Changes
Maior MateriallEquipment Loss
Gencrally o n rime Materials Oelivery
Minor or n o Mattrial Waste
Frequent Proiect Matenal çhortagc
Frequent Proiect Material Sharragr
Frequent Proiect Marerial Shortage
50
10
10
10
10
10
50
20
20
2m
13.3
13.3
I Cause fffecc - -
Expert 1 Value!
8
Defeche Work Material Vaste 1 90 1 - 1 90 1 30.0 I 1 1 I I I
Minor or no Design Changes
Minor or no MiteriaYEquipment Loss
Generally on time Materials Oeiivery
Poo r Design Quaiitg Major Design Changes 100 90 90 93.3
Presrnce of Scope Creep
Complew Design Canstmctabiliry
Majar Design Changes
M i r or n o MatenallEquiprnmt Loss
Generang on time Materiair Oekery
Mmor or no Matenal Waste
Frequent Projecc Material Shortage
Complcr Design Constructabiüty 1 1 1 1 1
Frequent Proiect Matenal Shorrage
Good Design Quafity
Preseme of Scope Creep
10
1
50
Maior Design Changes
3
10
4
5
Routine
2
10
40
Poor Design Quaiity
Presence of Scope Creep
Routine Design C4nstructabiIity
6
7
- -
Design Qualiry 1 h l l io r Design Changes
20
Poor Design Qualitg
No Scope Creep
Compler Design Constructabiiiq
Good Oesign Quality
Presence of Scope Creep
Rautinr Oesign Constructabitity
Scope Creep I
3
50
13.3
60
I
Good Design Quality
N o Scope Creep
Cornplsx Design Consuuctabiiity
Poo r Design Qualitg
No Seope Creep
Routine Design Constnictabiiity
Oesian Constructabiitu 1
Used
vm
Major Design Changes
Maior Oengn Changes
Belief Nenrork haS.sis of Direct Cos! Risk in Building Constnrcrion 147
60
50 Major Design Changes
Maior Design Changes
Major Design Changes
53.3
90
/ 70
-
10
80
80
-
30 20 35.0 55
10
70
20
40
13.3
5-
Routine Design ConNuctabiTity 1 1 1
Valu
Use!
93.:
031
732
76-7
70.a
56.7
73.3
30.0
Adequate QuaGfÏed Local Labour
Poor Trade Coordination
Poor Oesign Quaiity
IO#
24 1
2
3
4
5
6
7
8
Belief Nehrork rimlysis of Direct Cost Risk in Building Conscnlcrton 148
Major Oefective Vork
Adequata Quaiified Local Labour
Good 'Frade Coordination
Poor Design Quaiity
Complen Design ConsuuctabiIitg
Cause
Insuffiuiciènt QuaGfied Local Labour
Poor Trade Coordmation
Poor Oesign Quaiitq
Compler Desfgn ConswctabiGty
Inniflicient QuaGfied Local Labour
Poor Trade Coordiination
Poor Design QuaGtg
Routine Oesign Connnictabiütjl
Insufficitnt QuaEfied Local Labour
Good Tnde Coordination
Poor Oesign QuaGq
Complcr Design Constnictabiüty
Insuffiàent Qualilied Local Labour
Poor Trade Coordinaiion
Good Design Quaiitg
Complea Design ConstmctabiGty
Adequate Qualified Local Labour
Poor Trade Coordination
Poor Oesign Qualirp
Compler Design Consuuctabiity
Insufficient Qualificd Local Labour
Gaod Trrde Coordination
Poor Design Quaiity
Routine Design Conscnictability
Inniificient Pualified Local Labour
Poor Trade Coordiiation
Good Design Qualitjl
Routine Oesign Constructabiiity
Insufficient Qualiiicd Local Labour
Good Trrde Coordination
Good Design QuaGty
Complex Design Consuuctability
3
30
70
70
80
60
50
70
30
1
90
BO
70
00
80
70
70
40
Ufect
M m Defeuiwe Work
M J P Oefectiwe Wort
Maior Oefective Work
Major Defectiue Work
Major Oefective Work
Major Oefecrive Work
Maior Oefective Work
Major Defective Wotk
&put
2
100
100
80
70
70
50
80
20
60
Maior Oefective Woik
70
40
60 633
43.3 1
50 40
IO# I Cause
Qualified Local Labour
Trade Coordiiation
Good Design QuaGtg
Cornplex
12 Insufficient Quaiified Local Labour
1 Good r r h d r Coordination
~ o o d Design Quality
1 Routine Design Consuuctabüity I
Qualitied Local Labour
Trade Coordination
Oesign Qualicg
Routine Design Constructahility
Effect Enpert Value
1 2 3 Used
Major Oefecciue Votk 50 60 70 60.0
Major Oefectiue Wotk 60 20 40 40.0
Major Oefectiue Vork 50 20 20 30.0
I I I 14 1 Adequate QuaEfied Local Labour Major Oefective Work
Poor 1 Ciood
Trade Coordination
Design QuaIitg
1 Routine Design Constructability
I 15 Adequate Qualified Local Labour
T r d e Coordination
Design Quality
Compter Oesign Construcrabilicy
Maior Oefective Vork 1 10 10 7.0
I -
16 Adequate Qualified Local Labour
/ Good Trade Coordination
1 Good Design Quafity
1 Routine Desian Constniccabilitu
25 1 1 lnsufficient Qualified PM Personnel
Cornplex Design Const~ctabiïq
Large Phgsical Projecr Size
Routine Oesign tonstrucrability
3 Insufficient Qualified PM Personnel
Complex Design Consuuccabilicy
Srnall Phgsical Proiect Sire
+ Insufficient Qualified P M Personnel
Routine Design Con-iuctability
Srnall Phgsical Pioicct Size
5 Adequate Qualified P M Personnel
Complex Design Constructability
Large Phgsical Proiect Sire
Trade Coordination 11 Trade Coordiiation
'oor Trade Coordination
>oor Trade Coordination 50 80 70 66.7
%or Trade Coordination
Belief A'envork Anaipis of Direcf Cosr Ri& in Building Consrnrcrion 149
6
l 1
8 Adequate QualiiÏed PM Personnel Foor Trade Coordination
1 t
1 Routine Design Constructability I
Adequate QuaIified P M Personnel
Camplem Uesign Constructability
Small Physical Project Size
26 t Very Sensitive Physical Environment Maior Regulatory Penalties
1 I
Poor Trade Coordination
Poor Trade Coordination 7 Adequate Quafilied P M Personnel
Routine Design Constructability
Large Phgsical Proiect Size
2 1 Moderately Sensitive Physieal Environment 1 Milaior Regulatory Penalties 1 60 ( 30 1 50 1 46.7
I I I I
1
40
50
27 1 1 lnsulficient Local Suitable Materials 1 Frequently late Materials OeIivery 1 1 I 1 I 1
28 1 1 Reaciive Proiect Manager CooperativeEnuironment 1 80 1 80 1 80 1 80.0 1
2
IO
10
3
30
30
Insufficient Qualified P M Personnel
Used
26.7
30.0
1 1 1
2
4 I~ roac t i ue Project Manager Cooperative Environment 1 20 1 1 1 30 1 17.0 1
I
29 1 1 Worse than Enpected &change Rates 1 >erpected InternationalMarketPrices 1 90 [ 100 1 100 1 96.7 1
Reactive Proiect Manager
Adequate Qualified P M Personnel
1 I
No Cooperative Environment 3
t Proactive Proiect Manager
Insulficient Qualified P M Personnel
Proiect uses Foreign Purchased Goods
3 1 Worse than Eupected Enchange Rares International Market Prices 1 - IF-1 1.0 1
Na Cooperarive Environment
40
1 1 2
50 50
4 1 As ewpected or bctter &change Rates InternationalMarket Prices 1 IO 1 l 1 1 1 4.0 1
40
I As çupected or better Enchange Rates
Proiect uses Foreign Purchased Goods
Proiect does not use Foreign Purchased Goads 1 1
- -
Exchange Rates Foreign Purchascd Guods 1 80 1 80 1 70 76.7 1
70
I
1
Suitablc Equipment 1 1 1 1 1 1
56.7
40
>ewpected International Market Prices
1
Belief ~Venvork Anaiysis of Direct Cost Risk in Building Consrnrcrion 150
40.0
10 IO 10 10.0
cause
I
2 As expected or better Enchange Rates Ptoiect uses Foreign Purchased Goods
1 Adequate Suitable Equipment 1 I I I
3 Worse than Eiipected Exchrnge Rates Project uses Foreign Purchased Goods
1 Adeqwte Suitable Equipment 1 I I I
4 A s ewprcted or better Exchange Rates Roject uses Foreign PurchasPd Goods
31 1 [Construction Saturated Local construction rnarkec 1 tnsuffiaent Local Suitable Materials
I I 2 Normal Local construction market Insuffiuent Local Suitabte Materials
32 1 Insufficient Suitabk Equiprnent cewpected Equipment Productivity
Worse than Enpected Ground Conditions
High (>3000ft] Altitude
I I 2 Insufficient Suitable Equipment texpecled Equipment Productivity
1 Worse than Enpected Ground Conditions 1 1 Normal Altitude 1 I I
3 Insufficient Suitable Equipment c expected Equipment Productivity
As erpected or better Ground Conditions
High (>3000ft] Altitude
+ Insufficient Suitable Equipment
A s eipected or better Ground Conditions
texpected Equipment Productivity
1 Normal Altitude 1 I I
5 Adequate Suitable Equipment texpected Equipment Productivity
Worse than Enpected Ground Conditions
High (>3000ft] Altitude
6 Adequate Suitable Equipment ccxpected Equipment Productivity
Vorse than Ewpected Ground Conditions
Normal Altitude
7 [ ~ d e q u a t r Suitable Equipment 1 <erpected Equipment Productivity
1 A s etrpecced or better Ground Conditions I 1 High [>3000ft] Altitude 1 1 I I
0 Adequate Suitable Equipment texpected Equipment Productiuity
16s ewpccted or better Ground Conditions I Altitude 1
33 1 1 Construction Srturated Local canstruction market 1 1nsufficier:t Suitable Equipment
Expert Value
Belief Nenvork Analysis of Direct Cost Risk in Building Construction 151
: I ~ e m o t e Project Geagraphy
Normal Local construction market
Major MateriatlEquipment Loss
Remote Proiect Geography
Construction Poor Local canstruction market 1 Maior MaterialfEaui~ment Loss
ld f i c ien t Suitable Equipment 70
I Insufficient Suitable Equiprnwt 50
Rural Project Geography Insuflicient Suitable Equipment 50
Normal Local construction market
Maior MateriallEquipment Loss
Rural Project Geographg Insuffitient Suitable Equipment 25
Normal Local construction market
Minar or no MaterialfEquipment Loss
Urban Project Geogrophy Insufficient Suitable Equipment 40
Normal Local construction market
Major MateriaIf Equipment Loss
1
Urban Project Geography
1 Normal Local construction market
1 ~ n o r or no MateriallEquiprnent Loss
I
Insufficient Suitable Equipment 10
8 1 Rural Project Geography 1 lnsufficient Suitable Equipment
( Construction Poor Local construction market 1 1 Maior MaterialfEquipment Loss 1 1 I I 1 1 I
9 Rural Project Geographq Insufficient Suit able Equipment 1 O
Construction Poor Local construction market
Minor or no MaterialiEquipment Loss
10 Urban Project Geography lnsufficient Suttable Equipment 40
Construction Poor Local construction market
Major MateriallEquiprnent Loss
1 I
11 Urban Project Geography Insuffiment Suitable Equipment 1 O
1 Construction Poor Local construction market 1 I 1 Minor or no MateriallEauioment Loss 1 !
34 1 1 Atypical Site Sccurity
I 1 Major MateriallEquipment Loss -
35 1 1 Construction Saturated Locd construction market 1 lnsufficient Qualified Local Labour
I I 2 ( Normal Local construction market Insufficien t Qualified Local Labour 20
1
3 1 Construction Poor Local conuruction market 1 Insufficient Pualified Local Labour 1 60
BelieJ'Nenvork Anaiysis of Direct Cost Risk in Building Constnrcrion 152
Value
36 1 ünfavourable Geology
2 Favourable Geology
No Archaeohgical Swey
3 Unfavourable Geology
Perforrned Archaeological Suwey
I
4 Favourable Geology
37 1 Poar Design Tearn Coordination
Presence of Sape Creep
2 1 POO^ Design Tearn Coordination
1 NO Scope Creep
I 1
3 Good Design Tram Coordination
1 Presence of Smpe Creep
I I
4 Gcod Design Team Coordination
38 1 l ~ n ~ r o v e n Construction Tech. Required
Poor Design Tearn Coordination
Presence OF Scupe Cresp
~ - ~ --
2 Prooen Construction Tech Required
Poor Design Tearn Coordination
Prescnce of Scope Cieep
3 1 Unproven Construction Tech. Required
1 ~ o o r Design Team Coordination
1 NO Scope Creep
I Construction Tech. Required
Design Team Coordination
Prescnce OF Scope Crecp
5 Proven Connruction Tech Required
Poor Design Team Coordination
No Scope Crecp
6 Proven Construction TechRequired
Good Design Tcarn Cocrdinaticn
Presence of Scope Creep
1 2 3
Worse than ewpected Ground Conditions 90 80 60
Worse than expected Ground Conditions 20 50 50
--
Vorsr than expccted Ground Conditions
1 I
Worse than expected Graund Conditions 10 20 20
Late Design Submittal
Late Design Submittal 80 80 80
I
~ a t e Design Subrnittal 60 40 80
Late Design Subrnittal
Poor Oesign Quality
Poor Oesign Qualicy
Poor Design Quality 70 80 80
Poor - -
Design Quality
=oor Design Quality 50 70 90
JO of Design Puality
Belief AknvorX- Analysis of Direct Cosf Risk in Building Construction 153
0 Proven I -- Construction Tech. Requued Poor
D M g n Team Coordination
ID#
7
Oesign Quality
Effect
Poor Design QuaTi
Cause
Unproven Connrueiion Tech. Re-d
Good Design Tearn Coord;nation
No Scope Crop
Tmant Requnernent Change Presence of I Scope Creep
Oesian Team Coord
39 1
2
Minor Tenant Requirernent Change 1 Presence o f Scope Creep
Value
Used
26.7
Expert
Good Design Tearn Caord. 1 1 1 I
1
30
Major Tenant Requüernent Change
Poor Design Team Coord
Major Tenant Requuernent Change
Gond Design Team Caord
I I f N o Tenant Requirernent Change Scope Creep 1 25 1 40 1 65 Igf Poor Design Team Coord. 1 1 1 1 I
2
40
Presence of Scope Creep
Presence o f Scope Creep
Tenant Requirernent Change Presence o f I Scope Creep
Dcsian Team Coord
3
10
40 1 1 Fmancially Unstable Owner 1 Forbidden Budget revisions
100
Insufficient Qualified PM Personnel Reactive Project Manager 80 80 70 76.7
lnewperienced PM work familiarity 1
90
3 1 Adrquate Qualificd P M Personnel 1 fleactiue Prolecl Manager 1 60 1 60 1 20
2
1 lnenperienced PM work familiarity 1 1 1 1 l
100
100
90
1 1 f
4 Adequare Qualified P M Personnel Project Manager
96-7
60
Insufficient Qualified P M Personnel
Enperienced P M work familiaritg
42 1 l ~ u m p m m Contractor Payrnent Type 1 R i k t o contractors by Conuact Clauses
I l I - -
2 1 unit ric ce Contractor Payment Type 1 Risk tu contractors by Cantract Clauses
I I l 1
Aeactive Proiect Manager
--- -- ---
3 1 Guaranteed Maximum Contractor Payrnent Type 1 Risk to contractors by Contract Clauses 1 90 1 70 1 70 1 76.7 I I I I I
4 1 Cost reimbursable Contractor Payment Type 1 Risk to contractors by Contract Clauses I 1 0 l 1 1 1 1 4 . 0
50
Belief Nencork Analysis of Direcr Cosr Risk in Building Consrnrc~ion 154
40.0 40 30
Cause Eifect
5 Lumpsum Contractor Payment Type Risk t o owners bg Contrau CIauses
6 Unit Price Contractor Pagment Type Füsk t o owners by Contract Clauses
Aak t o owners by Contract Clauses 7 1 Guaranteed Maximum Cantractor Payment Type I
43 1 1 Unproven Construction Tech. Requïred 1 lnesperienced PM work familiarity
I I
Qualified P M Personnel 1 P o o r P M knowfedge o f area
I I
I I I
45 1 insufficient Qualified P M Personnel Maior ConstructiodOps Interference
Other Cornpeting activity o n site
Interfering Traffic Congestion
I I
2 l ~ d e q u a t e auafified PM Personnel 1 Major ConstnictionfOps Interference
Oc@ - . - - . Cornpeting - - activity -. o n site
lntcrfering Traffic Cangcstion
f 1 1
3 Insufficient Quafified P M Personnel Maiot ConstructionlOps Incerfetence
1 Other Competing activity o n site 1 1 NO Incethring Traffic Congestion 1 I
4 1 Adcquate Qualified PM Personnel Major ConstructionlOps lnterference
1 Othcr Competing accivity on site 1 1 NO Inteiferïng Traffic Congestion 1 I
5 Insutficienc Qualified PM Personnel Major C o ~ t r u c l i o n l O p r Interference
1 N o Ochrr Cornpeting activity on site 1 Interfering Traffic Congestion
I Major ConstructionlOps Interference
-
6 -
Adequate Qualified PM P e r s o ~ e l
Na Other Competing actiuity on site
lntrrfering Traific Congestion
Major ConstructioniOps Interference 7
Quafificd P M Personnel ConstructionlOps Interference
tnsufficient QuafiRed P M Personnel
N o Other Cornpeting activity o n site
N o Interlering Traffic Congestion
Behef Nenvork Analysis of Direct Cos! Risk in Building Consrrucrion 155
I value Cause I Effcct
46 t
2
3
+
Interfcring Traflic Congestion
Small Physïcal Proiecc Size Interfering Traffc Congestion
Olher Competing activiry on site
Srnall Physical Proiect Size Interferhg Traffic Cangestion
No Carnpe!ing activiq on site
Large (for projectsize] Number of Workers on site
Adequate Site accesslegress lnterfering Traffic Congestion
Large [for proiecc sire) Number of Workers on site
Other Competing Activity on site
Large Physical Pro jut Sire
Insufficient %te accesslegress Interfering Traffic Congestion
Large [for project site] Number of Workers on site
Other Competing Activity on site
Large Physical Proiecc Size
5
6 Interfering Traffic Congestion
Insufficient Site accerslegress
Small [for proicct size] Number of Workers an site
Other Competing Activity on site
Large Physical Proiect Sire
Adequate Çite accesslegress
Smalt [for proiect size] Number of Workers on site
Other Competing Activity on site
Large Physical Project Size
lnsuf ficient Site accesslegress Interfering Traffic Cangestion
Small [for project sire] Number of Workers on site
No other Compcring Activity on site
Small Physical Project Size
- - -- - --
Adequate Site accesslegress lnterfering Traffic Congestion
Small [for project sae] Number of Workers on site
No other Cornpeting Activity on site
Small Physical Proiecc Size
Insufficient Site access/egress lnterfering Traffic Congestion
Large [for proiect size] Number of Workers on site
No othcr Competing Activity on site
Large Physical Project Sire
Interfering Traffic Congestion 10
Belief Nenvork Anaiysis of Direct Cos[ Risk in Building Constnrction 156
Adequate Site accessiegress
Large [for proiect sire) Nurnber of Vorkers on site
No other Competing Activity on site
Large Physical Proiect Sire
IO# Cause Effect I . Expert Value
1 11 InnilFiaent Site accesslegess Interfering Traffic Congestion
S m l l [for proiea ske] Numher of Vorkers on site
Adequate Site accesstegress Interfering
Srnall [for proiect size] Nurnber of Vorkers on site
No other Competing Actiuity on site
Larae Phusicat Praiect Size
-
Traffic Cangestion
( Ptesrnce of. [location knawn] Utilitics 1 ~eue re Perrnits Required 1 30 1 50 1 50 1 433 I I I I t I
Cornplen Design ConstnicwbTty 1 Unproven Construction TechRequired 1 90 1 80 1 70 1 80.0
I I I I I
Presence o f (location unknown] Utiiities
Qualified PM Personnel 1 Pour Design Teun coordination 1 90 1 90 1 90 1 90.0 I 1 I I I I
50 1 1 Construction Saturated Local construction market 1 lnsulficient Qualified PM Personnel 1 80 1 90 1 80 1 ô3.3 I I I l l t
Severe Pcrmits Required
- - -- -
2 1 Normal Local consvuction market Insufficient Qualified P M Personnel 30 30 40 1 33.3
90
1 Non-Prosperous
51 1
Area affluence
80
-- -
Auailable Support Faciiities ( 50 1 46.7 1
Non-Prosperous Area affluence
Construction Saturated Local ccnstruction market
50 &%$
Insufficient Available Support Facitities
Normal Local construction market 1 1
Non-Prosperous Area affluence
Consrruction Poor Local construction market
5 1 Prosperous
70
I I I I
Prosperous Arca affluence
Construction Saturated Local consuuction market
Area affluence
Insufficient Auailable Support Faciiities
--- 1 lnsufficient Available Suppart Ficilitier 171 1 50 1 46.7 1
50
Insufficient Available Support Facilities
1 Normal Local construction market 1 1 1 1
40
60
Belref Nenvork rlnalysis of Direct Cosr Risk in BuiMing Consrniciion 157
60.0
30
53.3 ! I
6
40
50 60
Prosperous Area affluence
36.7
50
M f i c i e n t Available Support FacJitier 20 40 40 33.3
--
ff fect Value
Used - 46.7
ln* I Cause
52 1 l>usual Gov. Construction Spendng Private Funding Source
1 Unstable Government
1 2 >usual Gov. Construction Spending
Stable Governmenc
Private Funding Source
Private Funding Source 3 1 AS usual or lower Gov. Construction Spcnding
1 Unstable Government I
4 As usual or lover Gov. Construction Spcnding
Stable Governrnenc
Private Funding Source
5 (,usual Gov. Conrrruction Spending Public Funding Source
1 Unstable Gouernrnenc I
6 >usual Gov. Construction Spending
Stable Government
Public Funding Source
1
7 As usual or louer Gov. Construction Spending Public Funding Source
1 Umtabie Government 1 I
8 As usual or lover Gov. Construction Spending Public Funding Source
1 Stiblr Gouernrnent
> expected Construction Market Escalation Inflation
Gov. Construction Spending
1 Construction Saturated Local construction market
> ewpected Construction Market Escalation 1
2 As usual or lover Inflation
1 > usual Gov. Construction Spending
1 Construction Saturated Local construction market
3 >usual Inflation > erpected - - -
Construction Market Escalacion
1 AS usual or lover Gov. Construction Spending
1 Construction Saturatcd Local construction market
I > erpected Construction Market Escalation 4 As usual or lover Inflarion
As usual or louer Gov. Construction Sprnding
Construction Saturated Local construction market
> erpected Construction Market Escalation 5
6 >ewpected Construction Market Escaladon
>usual Inflation
> usual Gav. Construction Spending
Normai Local construction market
As usual or louer Inflation
> usual Gov. Construction Spending
Normal Local construction market
Belief Network Anafysis of Direct Cost Risk in Building Consrmcrion 158
Effcct
1 Z 3 Used
7 >usual Inflation > ewpected Conmucrion Market Escalation 80 ?O 40 2& r7
As usual or low-r Gov. Construction Spendmg
Normal Local conmuction market
B A s m a l or louer Inflation >erpected Construction Market Escalation 10 20 10 13.3
As usual or lover Gov. Construction Sprnding
Normal Local construction market
> usual lnfbcian > ewpected Construction Market Escalation
>wual Gov. Construction Spending
Construction Poor Local construction market
As wual or lower
r usual
1 >ewpected Const~ction Market Escalacion
Gov. Construction Spending 1 Construction Poor Local construction market 1
I , usual Inflation ,expected Constwction Market Gcatation
As usual or lover Gov. Construction Spending
Construction Poor Local construction market
As usual or lower Inflation >eupected Construction Market Escalacion
As usualor louer Gov. Construction Spending
nstruction Poor Local mmtnicuon market
54 1 Remote Proiect Geography lnsufficient Availability of Energy BO 70 70 73.3
1 1 1 I -- -- -
2 1 Rural Project Geography 1 lnsufficient Availabiiity of Energy 50 50 50 50.0 1 I 1 I I I
55 1 1 >usual Gov. Construction Spending 1 >erpected Inflation
56 1 IUnstable ûovernment Gov.Construction Spending 1 60 30 40 ( 43.3
5ï 1 Unstable Government > erpected Tan Rates 1 50 1 40 1 30 1 40.0 I 1 I I 1 1
2 1 Stable Government 1 > exnected Tan Rates 1 50 1 30 1 20 1 33.3
58 1 1 Unfavourable Geology 1 Likely Land-relatedNaturalOiaster 1 - 1 30 1 30 f 30.0
1 1 1 I I I 1 I l 1 1
2 Fauourable Geology Likely Land-relatedNaturalOisaster 1 10 1 10 / 30 16.7
20 responses that did not make sens+ wert eliminated from che data set- They were climinatcd bccause enamination of the
possible state combinations. and their relative scores did not make sensa
Each of the rcsponscs that vcrc eliminatrd. the ewpcrts wrre consulted and asked if thty obietttd to the
value that was bdng usrd in the model. No obections were made.
36 mode1 values were alterrd in such a way that they accomodated al1 of the expert rcsponses.
Belief Xehrork Anaiysis of Direct Cos! Risk in Building Consmrc~ion 159
Prior Probabilities Required
1 . . , . - Contractor Failure
2
4 a Lona Work Stoaaaaes
Subcontractor Failure
3
5 Labour Iniuries/Accidents I
Sumlier Failure - - - -
7 Tenant Reauirement Chanae
6
i3 Contractor Pavment Tvoe I
Archaealogical Survev
9'site Securitv
10 Site Access
11 Nurnber of Workers on Site I 12 Ecolaaicâl Environment i 14 Local Construction Market I
State 1 Probability (1-100) 1 Contractor Fails No Contractor Fails
0.30% 99.70%
Subcontractor Fails No Subcontractor Fails
1% 99Oh
Supplier Fails NO Supplier Fails
1% 99%
Major Construction Stoppages Minor or No Construction Stoppages
30 % 70 %
Major Injuries Occur Minor or no Injuries Occur
Major 20% Minor 60% None 20%
10% 90%
Archaeological S u ~ e y Performed No Archaeological Suwey Performed
Lump Sum Unit Price Guaranteed Maximum Cost Reimbursabie
50% 50%
Typicat 80% A t v ~ i c a l 20%
Large (for project size) Small (for project size)
Not verv sensitive 1 20% 1
50 % 50%
Very Sensitive Moderately Sensitive
Saturated I 20% I
20% 60 %
Belief Xenvork Analysis O/ Direct Cosr Risk in Building Consrnrcriott 160
Normal Poor
60% 20%
Prior Probabilities Reguired
Variable . . - - . - - . . -. , Probability (1-100) State
Owner
Phvsical Proiect Size Large 90% Srnall 10%
Comaetina Activiiv on Site - -
Utilities
Othe? activjty competing No other activity competing
Not present
50% 50%
Present , location known Present . location unknown
L
15%
Area Affluence
60% 5%
Exchanqe Rates
1
Prosperous Not prosperous
Government
85% 15%
Worse than expected A s expected or better
Weathar Extremes
AItitude High (>300Q ft) 5% Low (~3000 ft) 95%
50% 50%
Stable Unstable
Geoloay Favourable 70% Unfavoura ble 30 %
95% 5%
Likely Unlikely
90% 10%
60% 30%
Climate
Beltef ~Venvork Anaiysis of Direcf Cos[ RI& in Building Consfnic[ion 161
5% 95%
Moderate Extreme
Geoaraahy Urban Rural
Appendix J: Divorcing Variable Ranking
Belief Xenvork Anaipis of Direct Cost R~sk in Building Constmction 162
Desinn Claims: Ranking
Changes Creep Major 1 Minor Mejor 1 Minor
PM Claims Mitigation: Ranking
- - - - - - -
Delay Clairns: Ranking
1 Dela y s 1 Overtime 1
1 2
3
4 5 6
7 8
Belief Nenvork Analysis of Direcr Cosr Risk in Binlding Consrnlcrion 163
1 2
3 4
Delays Major
X
X X
X
Major
X
X
Mirtar
X
X X
X
Overtime
Major
X
X X X
Stoppages
Minor
X
X
Minor
X
X X
X
Major
X
X
X X
Minor
X X
X
X
Major
X
X
Minor
X
X
Feilure Detays: Ranking I I Contredor 1 Subcontractor f Supplier I
Labour Delays: Ranking I
Major
Praductivity Defective Stoppages Coordinatian Major Minor Major Minor Major Minor Mejor Minor
X X X X X X X X
X X X X X X X X X X X X
X X X X X X X X X X X X
X X X X X X X X
X X X X X X X X X X X X
Logistics Del-: Ranking
1 Deliverv 1 lnterference
Minor
X
Design Delays: Ranking I
Major
1
Changes Submitial
Major Minor Major Minor 1 2 3
Belief Nenvork Anaiysis of Direct Cosr Risk in Brrilding Consmrclion 164
Minor
X
Major
Mejor
Minor
X
Minor
X
Major Minor
X
Conditions
1
Geolagy Disaster
Major 1 Minor Major 1 Minar
Short Breaks: Rankina
Bclief ~Venvork Analysis of Direct Cost Rlsk in Building Consrrucrion 165
Avaitebiiiiy
Major Minor
X
X
Injuries
Major
Climete
Minor
X
X
Major
X
Minor
X
Labout Congestion: Rankirtg
Workers Congestion Interference
Mejor Minor Major Minor Mejor Minor
X X X X X X
3our DesTon Understandino: Rankino
Belie f Nehvork Anaiysis of Direct Cos1 Ris& in Blnlding Consrnrcrion 166
Technalogy
Major
X
Minor
X
X X
Chenges Lebour
Major Mejor
X
Minor
X
X X X
Minor
X
X X
Appendix K: Data Reduction Description
Belief Yencork Analysis of Direct Cosr Risk in Building Consrrucrion 167
Relationship Elimination: Design Claims
Original Design Claims Parents: Design Changes Change in Tenant Requirements Design Quality Scope Creep Design Tearn Coordination Complexity/Constructability of Design
Scope Creep Change in Tenant Requirements Design Team Coordination
Design Timeliness Design Tearn Coordination Scope Creep
Change in Tenant Requirements NO PARENTS
Relationship Elimination: Eliminate conneetion bebveen "Change in Tenant Requirements" and "Design Claims"
Justification: "Change in Tenant Requirements" already affects "Design Claims" through "Scope Creep" and "Design Changes"
Revised Design Claims Parents: Design Changes Scope Creep Design Timeliness
Belief Nenvork ..lnalysis of Direct Cost Risk in Building Constntction 168
Relationship Elimination: Labour Deiays
Onginai Labour Delays Parents: Labour Productivity Short Breaks Defective Work Labour Congestion Labour understanding of design
Qualified Local Labour Local Construction Market Saturation
Defective Work QuaIified Local Labour Trade Coordination Design Quality Complexity/Constructability of Design
Long Work Stoppages PARENTONLY
Trade Coordination Available qualified key PM personnel Complexity/Constmctability of Design Physical Project Size
ReIationship Elimination: Elirninate connection between "Qualified Local Labour7' and "Labour Delays"
Justification: "Qualified Local Labour'' affects "Labour Delays" through "Labour Productivity" and "Defective Work"
Revised Design CIaims Parents: Labour Productivity Defective Work Long Work Stoppages Trade Coordination
Belief Nenvork Anuiysis of Direcr Cosr Risk in Buctding Consrrucrion 169
Relationship Elimination: Project Material Shortage
Original Material S hortage Parents: Local Suitable Materials Local Construction Market Saturation
Design Changes Change in Tenant Requirements Design Quality Scope Creep Design Tearn Coordination Cornplexity of Design
MateriaVEquipment Loss/Darnage Site Security
Materials Delivery Promptness Local Suitable Materials
Material Waste Defective Work
Relationship Elimination: Eliminate connection between "Local Suitable Materiais" and "Project Material Shortage"
Justification: "Local Suitable Materials" affects "Project Material Shortage" through "Materials Delivery Promptness"
Revised Project Material Shortage Parents: Design Changes MaterialiEquipment Lo ss/D arnage Materials Delivery Material Waste
Belief iVenvork Rnalysis of Direct Cost Risk in Building Construction 170
ReIationship Elimination: Design Changes
Original Design Changes Parents: Change in Tenant Requirements PARENTONLY
Design Quality Construction Technology Requirements Design Tearn Coordination Scope Creep
Scope Creep Change in Tenant Requirements Design Team Coordination
Design Team Coordination AvailabIe key PM personnel
Complexity/Constructability of Design PARENTONLY
Relationship Elimination:
Justification:
Elirninate connection between "Change in Tenant Requirements" and "Design Changes" Eliminate connection between "Design Team Coordination" and "Design Changes"
"Change in Tenant Requirements" affects "Design Changes" through "Scope Creep" "Design Team Coordinationy' affects "Design Changes" through "Scope Creep" and "Design Quality"
Revised Design Changes Parents: Design Quality Scope Creep Complexity/Constructability of Design
Belief Nenvork Anaiysis of Direct Cos! Risk in Building Constrtrcrion 171
Appendix L: MSBN Text File
BeIief'~Vencork rlmlysis of Direct Cost Risk in Building Constnrctiot~ 172
diagnostic nehvork "" node Equiprnent
name: "Cost of Equipmrnt"; type: discrete[81= 1
" L 15%". "95%". "75%". "55%". "35%". " 13%". "- "-25%"
1: position: ( 12093, 18985): label: informational; cost: observe = 1.00;
I
nodeLabour
narne: "Cost of Labour"; type: discrete[8] = (
"1 15%". "95%". "75%", "55%". "35%". " 15%". "- jO/o"7
"-2 j%"
1: position: ( 16857, 19000): IabeI: informational; cost: observe = 1.00;
I
node Material {
narne: "Cost of Materials"; type: discrete[8] = {
" 1 15%". "95%", "75%". " 5 5 % , "3 5%". ', 15%". "-5%" "-2 5%"
1 - 1 r
position: (22050. 19000): label: informational: cost: observe = 1.00:
1
{ name: "Consuuction Clairns"; type: discrete[2] =
"Major". "Minor or no"
j: position: (15505, 14335);
1
Belief Nenvork Analysis ojDirecr Cosr Risk in Building Consfnrction 173
{ name: "Design Claims"; type: discretel21 =
"Major", "Minor or no"
1; position: ( 19675. 14335):
1
node FieldClaims {
name: "Field Claims": type: discrete[2] = {
"Major". "Minor or no"
1: position: (1 7200, 14333):
1
node DehyClaims I
name: "Delay Claims"; type: discrete[2] = {
"Major", "Minor or no"
1; position: (18385. 14335):
1
node PMClaimsMitigation
name: "PM daims mirigation": Qpe: discretel21 =
{ "PM effective". "PM Ineffectivs"
1: position: ( 12220, 14335):
1
node ContractClauses {
name: "Contract Clauses"; type: discrete[3] =
"Risk to conuacton", "Risk to owner", "Risk shared"
1; position: (13945, 14335);
1
node CntrcuPymntTyp
name: "Contractor Paymcnt Type"; type: discretel41 =
"Lump sum", "Unit pricc", "Guaranteed Mauirnum", "Cost reimbursable"
1; position: (IO 165, 13350);
1
node Ovenime {
Belief ~Venvork Anahsis of Direct Cost Risk in Building Cons[nrcrion 174
name: "Ovenime": type: discrete[S] = {
"More than e..pectedl', "& expected or las"
1; position: (24070. 10675);
1
name: "Construction Delays": type: discrete[2] = I
"Major", "Minor or no"
I : position: (23305. 121 00):
}
node FailureDelays
name: "Failure Delays"; type: discrete[2] = I
"Major". "Minor or no"
1: position: (22765. 10675):
1
node ContractorFailure 1
narne: "Contractor Failure": type: discrete[2] =
{ "Conuactor Fails", "No contractor fails"
1; position: (2 1220, 1 1500):
1
node SbcntrcuFIr
name: "Subcontractor FaiIure": type: discrete[2] =
"Subcontractor fails". "No subcontractor fails"
1: position: (19380, 1 1435):
1
node SupplierFaifure {
name: "Supplier Failure": type: discrete[2] = (
"Supplier Failsn, "No supplier fails"
I - 1 r
position: ( 1 7995, 1 1470); 1
node LabourDelays I
name: "Labour Delays"; type: discrete(21 = {
"Major".
Be fref A'envork rlnalyss oj' Direct COSI Risk in B~rilding Construction 175
1; position: (10 [Os, 11455);
node LogisticsDelays {
name: "Logistics Delays"; type: discrete[2] = C
"Major". "Minor"
1: position: ( 1 1875. 12130);
}
node DesignDelays
name: "Design Delays"; type: discrete[2] = I
"Major". "Minor"
1; position: (13300, 12145);
I
node EnvironrnentalDelays {
narne: "Environmental Delays": type: discrete[2] = {
"Major". "Minor"
1; position: (16225, 12145):
node LandDelays f
name: "Land Delays"; type: discretel21 =
"Major", "Minor or no"
1; position: (20290. 12130);
1
node LabourProductivity I
nanie: "Labour Productivity": type: discrete[2] =
C "Less than expected", "AS expected o r better"
1; position: (10105, 10720);
1
node ShortBreaks (
narne: "Short Breaks": type: discrete['] =
{ "Frequent". "Infrequent"
1; position: (1 1845, 10705);
1
Belief Nenvork -4naiysis of Direcf Cosf Risk in Building Consfntction 176
node LabourCongestion
name: "Labour Congestion": m e : discrete[2] = t
"Interference". "No Interference"
): position: (21 160' 10675):
node LbrDsgnUndnrndng I
name: "Labour Design Understanding": type: discrete[2] = {
"Good", "Poor"
1 position: (22750, 1 1500);
I
node WrkQnttyDvtns
name: "Work Quantity Deviations": type: discret@] = {
"Major", "Minor or no"
node MaterialShortage
name: "Marerial Shortage": type: discret@] = {
"Frequently inadequate". "Infrequently inadequate"
i ; position: (21625, 121 15):
}
node MaterialWaste {
name: "Material Waste": type: discrete[2] = I
"Major", "Minor or no"
1; position: (13 133, 10705);
1
node DefectivrWork I
name: "Defective Work": type: discrete[2] =
{ "Major", "Minor or no"
1 : position: ( 13770. 12 1 15);
1
nodc EqpmntPrdctvty i'
name: "Equipment Productivity";
BeliejiVenrorA- Anaiysis of Direct Cosr Hisk in Building Constnrction 177
type: discrete[2] = {
" L e s than expected". "As expected or better"
1; position: (10060. 12145);
1
node MtrlEqprnntLss {
name: "MateriaVEquipment Loss"; type: discrete[2] =
{ "Major". "Minor or no"
I - > r
position: (13585. 1 1425);
node LbrInjrsAccdnts {
name: "Labour Injuries/Accidentsl': type: discrete[2] = {
"Major", "Minor or no"
I : position: (18 145. 12145):
1
node ArchlgclSrvy I
narne: "Archaeological Survey"; type: discrete[2] =
t "Performed", "Not performrd"
1: position: (1 1590, 1 1425):
I
node CnstrcmOprtnsIntrfrnc
name: "Consuuction/Opentions Interference"; type: discrete[2] = {
"Major". "Minor or no"
I . 1 7
position: (22255. 12835); 1
node TraficCongestion {
name: "Traftïc Congestion"; type: discrete[2] =
"Major", "Minor or no"
1: posirion: (1 35 15, 10705);
}
node NmbrOfWrkrsOnSt
narne: "Number of Workers on Site": type: discrete[2] = {
"congested", "Non congested"
Belief Nenvork A n a t ' y of Direct Cost Rtsk in Building Constnrcrion 178
1; position: (16150. 10690):
nodr CnstrctnTchn IgRqmnts (
name: "Construction Technotogy Requirements"; type: discretc[2] = {
"Unproven". "Proven"
1: position: (1 82%. 10690):
1
nodr CostAccounting {
name: "Cost Accounting"; type: discrcre[2] =
{ "Timely", "Untirnely"
1; position: (1 1980. 169 15):
1
nodr TndeCoordination t
name: "Tnde Coordination"; type: discrctef2] =
"Good", "Poor"
1 i position: (21685, 16930);
I
narne: "Long Work Stoppages": type: discrete[7] = i
"Major". "Minor or no"
1: position: (10075, 16930):
1
node MaterialsDelivery
narne: "Materials Delivery"; type: discrete[2] = {
"Generally on tirne". "Frequently Late"
1; position: (20080, 16930);
1
node CprtvEnvrnrnnt f
name: "Coopentive Environment"; type: discretel21 = :
"Partnering practiced". "Partnering not practiced"
1; position: ( 15743, 16930);
1
Belief ~Venvork Analysis of Direct Cos! RÏsk in Building Conslnicfion 179
nodr PM l
1
name: "PM"; type: discrete[2] =
" Proactive". " Reactive"
1; position: ( 13465. 169 15):
node PMWorkFamiliarïty 1
name: "PM Work Farniliarity": type: discrete[2] = {
"Good". "Poor"
); position: (14080, 16930);
node PMKnowledgeO fArea 1
namç: "PM Knowledge of Area": type: discrete[2] =
"Good", "Poor"
1: position: (23305. 16930):
;
node Ql fdKyPMPrsnnl
namc: "Qualified key PM Personnel"; type: discrete[2] = {
"Adequaten. "Inadequare"
1: position: (17860, 16930);
1
node VafueEngineering t
namr: "Value Engineering": type: discrete[21=
"Not Practiscd". "Pnctised"
); position: (15100, 13570):
1
node DesignChanges {
name: "Design Changes": type: discrete[2] = {
"Major", "Minor or no"
1: position: (13015, 12790);
I
node DesignSubrnittal
narne: "Design Subrninal": type: discrete[2] =
Belief Kenrork Analysis of Direct Cos[ Risk in Bttilding Constnrcrton 180
I "Generally on tirne", "Frequently Late"
1; position: (101 65, 12790);
I
name: "Design Quality"; type: discrete[2] =
"High". " Low"
I; position: ( 16795, 13555):
I
name: "Scope Creep"; type: discrete[Z] =
"Presence of', "Absence of'
1: position: (1 1680, 12790):
}
name: "Tenant Requirement Change"; type: discrete[3] = I
"Majorn, "Minor", "No"
1: posirion: ( 12655, 13570):
1
node Cmplx&C~trctbIs.OfDsgn {
name: "Complexity/Constn!ciabil~ of Design": type: discrete[2] = {
"Cornples", "Routine"
1: position: (18 190, 13555);
1
node DsgnTmCrdntn !
name: ''Design Team Coordination": type: discretef21 = {
"Good", "Poor"
): position: (10 180, 13570);
1
node RegulatoryPenalties I
name: "Regulatory Penalties": type: discrete[î] = {
"Major", "Minor or no"
Belief ~Venvork Analysis of DÏrecf Cost Risk in Building Consrnrcrion 181
1 position: (14530. 12803;
1
node PemitsRequired {
name: "Permits Required"; type: discretet21 =
{ "Cornplex", "Normal"
1; position: (16375. 12805):
node GvmmnrSpndngOnCnstrctn (
name: "Govemrnent Spending on Constniction"; type: discrete[2] =
"Higher than usual". "As usual or lower"
1 i position: (17995, 12835);
1
node Govemment {
name: "Government"; type: discrete[î] =
I "Stable". "UnstabIe"
1; position: (20920. 12820):
1
node IntrntnlMrktPrcs {
name: "International Market Pnces": type: discrete[2] =
"Higher than espected". "As espected or lower"
1 : position: (20965, 13570):
node CnstrctnMrktEscltn {
name: "Construction Market Escalation"; type: discrete[î] =
( "Higher than expected", "As espected or lower"
1; position: (2 1070, 13320);
1
node inflation {
nme: "Inflation": type: discrete[2] =
I "Higher than r'cpected". "As expected or lower"
}: position: (23 155. 13570);
}
Belief Nenvork Anaiysis of Direct Cosr Risk in Birilding Construcrion 182
node TavRates {
name: "Ta-Y Rates"; type: discrete[2] =
"Higher thm in~pected", "As expected or lower"
I ; position: (24025. 13555);
t
node ExhangeRates {
narne: "Exchange Rates"; type: discretel21 =
{ "Worse than Expected". "As expected or better"
1: position: (23500. 14290):
1
node FrgnPrchsdGds {
name: "Foreign Purchased Goods"; type: discrete[2] =
{ "Used", "Not used"
1 i position: (2 1415, 16105);
}
node LclStblMuls
name: "Local Suitable Materiais": type: discrete[2] = {
"Adequate", "Inadequate"
1; position: (14650, 16 105);
1
node Stbl EqpmntAvlblty
name: "Suitable Equipment AvailabiIity": type: discrete[î] =
"Inadequate", "Adequate"
1: position: (10 165, 16 120);
node QlfdLcILbr
name: "Qualified Local Labour"; type: discrete[2] = {
"Inadrquate". " Adequate"
1; position: (126 IO, 16105);
I
name: "Consuuction Support Facilities"; type: discrerr[2] =
BeliefNenc.ork Anaiysis of Direcr Cosr Hisk in Building Cànsrnlcr~on 183
C "Adequate", "Inadequaten
1: position: (16720, 16090);
1
node LcICnstrctnMrkt
name: "Local Construction Market": type: discrete[3] =
"Saturated". "Normal". "Poor"
\. 1 .
position: (19180, 16090); 1
node AvIbltyOEnrgy
name: "AvailabiIity of Energy": type: discrete[2] = {
"Adequate", "Inadequate"
}: position: (10180, 15115);
1
node Utilities {
name: "Utilities": spe: discrete[j] = C
"Presence of (location known)", "Presence of (location unknown)". "No presence of"
1; position: (12010, 15145);
1
node AreaAmuence {
name: "Area Affluence"; type: discrete[î] =
"Prosperousn, "Non-prosperous"
1: position: (23635, 16090):
1
node Ciroundconditions {
name: "Ground Conditions"; type: discrete[2] =
"Worse than Expected", "As expected or better"
1: position: (12970. 15 160):
1
nodr EnvmmntlSns~y
name: "Ecological Environment"; type: discrete[3] =
"Very sensitive".
Belief Nenvork Anaipis of Direct Cost Risk in Bidding Construction 184
"ModerateIy Sensitive", "Not Sensitive"
1; position: (14635, 15160):
1
node LndRltdNtrlDsstr
name: "Land Related Natunl Disaster"; type: discrete[2] =
{ "Likrly". "Unlikely"
1: position: (16690. 15 160);
1
node WeatherExtremes
narne: "Weather Eutremes": typer discrete[2] =
"Likelyn. "Unlikelp"
1: position: (19165. 15 175);
I
node Clirnate C
name: "Climaten; type: discrete[2] =
"Moderate", "Eutremc"
1: position: (23260, 15205):
1
node Geography {
name: "Geography"; type: discrcte[3] =
I "Rernote", "Rural". "Urban"
!: position: (210 IO, 151 75);
I
node Altitude t
name: "Altitude": type: discrete[2] = {
"High (>3000£i)", "Low (-3OOOtt)"
1: position: (24280, 15205):
1
node Geology {
narne: "Geology": type: discrete[2] =
"FavourabIe", "Unfavounble"
1;
Belief A1envork Analvsis of Direct COSI Risk in Bdd ing Consrnicrion 185
position: (22240, 15 190); 1
node BudgetRevisions i
name: "Budget Revisions"; type: discretel21 = !
"AIIowedn. "Forbidden"
1: position: (13870, 17875);
I
node FundingSource {
name: "Funding Source"; tvpe: discrete[3]=
"Privare", "Public". "Combination"
I; position: (10075, 17815);
1
node Owvnrr t
name: "Owner"; type: discrete[2] = t
"Flnancially stable". "Financially unstable"
1 : position: ( 12300. 17875);
node SiteSccurity I
name: "Site Security"; type: discrete[?] =
{ "Typical". "Atypicai"
1; position: (23260. 17845);
1
node SiteAccess C
narne: "Site Access": type: discrete[2]= {
"Adequate", "Inadequate"
1: position: (210 10, 17845):
1
node PhysclPrjctSz t
narne: "Physical Project Size"; type: discretel21 = {
"Large", "Srnall"
1; position: (1 5865. 17875);
I
Belief Nenvork Analysts of Direct Cosr Risk in Bzrildrng Cons~rnction 186
. . . . . . o o o o o o o o p
L LI id 'O id O O O - - - O - O O P
(1. 1, O. 1, 1, 1): O, O, 0~001,0.012,0.079.0251.0.38,0.777; (1. 1. 1. O, O, O): 0.002,0.022,0.113,0.281,0.333,0.19,0.052.0.007: (1. 1, 1, O, 0. 1): O, 0.001001.0.00900903,0.0650652,0217217~ 0.346346.0.264264,0.0970973; (1, 1, 1. O, 1-0): 0.0.00100 1,0.00900903,0.0650652,0.2172 I7,0.346346.0.264264,0.0970973; (1, 1- 1. O, 1, 1): O, O, 0.001,0.012,0.079.0.251,0.38,0.277; (1. 1. 1. 1, O, 0): 3,0~001001,0.00900903.0.06506510.217217,0346346.0.264264.0~0970973: (1, 1. 1. 1. O. 1): 0. O, 0.001,0.012. O-079,0.251,0.38,0.277; (1. 1, 1, 1. 1, O): O. O, 9.00l.0.012. 0.079.0.251,0.38,0.277: (1. 1, 1. 1, 1. i): 0,0,0.0.001, 0.019.0.1 17.0.353.0.51:
1
probabiIitv(Labour 1 Geography, QlfdLclLbr, Ovenime. LabourProductivity, Inflation. ConsuuctionDeIays) C
(O, O, O, O, 0.0): 0.51.0.353,0.117,0.019,0.001,0,0, O; (O, O, O, O. O, 1): 0.277.038,025-1.0.079.0~012,0.001. O, O; (O. O. O. O. 1. O): 0.277, C.38,0251,0.079.0-012,O.OOl. O, 0: (O. O, 0. O. 1. 1): 0.0970973.0.264264.0.346346,0317217. 0.0650652.0.00900903.0.00 1001. O; (0,0,0, 1, 0,O): 0.277, 0.38.0.251,0.079, 0~012,0.001.0,0; (O, O, O, 1, O, 1): 0.047037,0.179179.0.33033,0.293292,0.124124,0.025025,0~002002, O; (O, O. O, 1, 1.0): 0.047047, O. 1791 79.0.33033.0.292292, O. 124 124,0.025025,0.002002. O; (O, 0. O, 1, 1. 1): 0.007,0.052.0.19,0.333.0.281,0.113,0.022,0.002; (O, O, 1, O, O, O): 0.277. 038.0.251,0.079.0.0I2. 0.001, O, O: (O, O. 1. O. O, 1): 0.047047.0.I79l79, 0.33033,0.292292,0.124I24. 0.025025,0.002002. 0: (O, O, 1, O, 1,O): 0.047047,0.179179, 0.33033,0.292292,0.124124. 0.025025.0.002002, O; (O, O. 1, O, 1, 1): 0.007,0.052.0.19,0.333.0.28I, 0.1 13,0.022.0.002: (O. O. 1, 1. O, O): 0.037047.0.179 I79.0.33033. 0.292292.0.124 l24.O.O2502% 0.002002. O: (0,O. 1. I,O, 1):0.002,0.022,0.113.0.2SI.0.333.0.19,0.052,0.007: (0.0. 1, 1. 1, O): 0.002, 0 . 0 2 0.1 13.0.281.0.333, 0.19.0.052.0.007: (O, O, 1, 1, 1, 1): O. O70O2O02, 0.025025,0.124I24,0292292,0.33033.0.179179,0.047047; (O, 1. O. O, 0. O): 0.277.038.0.251.0.079.0.0I2.0.001, O, O: (O. 1. O, O, O. 1): 0.047047,0.179179,0.33033,0.291292, O. 123124.0.025025.0.002002. O; (O, 1, O, O, 1. O): 0.047047,0.179179,0.33033,0.292292, O. 124 l24,O.O2502j. 0.002002, O: (O, 1,0.0, 1, 1): 0.007,0.052,0.19. 0.333,0.281,0.113.0.022.0.002; (O, 1. O, 1, O, O): 0.047047,O. 179 179,0.33033,0.292292. O. 124 124,0.025025,0.002002, O; (O, 1, O, 1, O, 1): 0.002,0.022,0.113.0.281.0.333,0.19,0.052,0.007; (O. 1, O, 1. 1,O): 0.002,0.022,0.113,0.281,0.333. 0.19,O-052.0.007: (O, 1. O, 1. 1. 1): O, 0.002002,0.025025.0.124124,0.292292,0.33033.0.179179,0.017047; (O, 1. [,O, 0,O): 0.037047,0.179179,0.33033,0.292292.0.124124,0.025025,0.002002,0; (0, 1. 1.0.0, 1):0.002,0.022,0.113,0.281.0.333,0.19.0.052,0.007; (O, 1, 1, O, 1, O): 0.002.0.022.0.1 13,0.281.0.333.0.19,0.052,0.007~ (O, 1, 1. O, 1, 1): O, 0.002002,0.025025.0.124124.0.29192, 0.33033. O. 179 179.0.047047; (O, 1. 1. 1. O? O): 0.002.0.022,0.113,0.281.0.333.0.I9.0.0SZ,0.007: (O, 1. 1. 1, O, 1): 0,0.001001,0.00900903.0.0650652.0.217217. 0.346346.0.264264,0.0970973; (O. 1. 1, 1, 1, O): O, 0.00 1001,0.00900903,0.0650652, 0.2 17217. 0.346316. 0.264264,0.0970973: (O, 1, 1, 1, 1, 1): O, O, 0.001,0.012,0.079.0.251,038~ 0.277; (1. O, O, O, O. O): 0.393393,0.383383.0.179179,0.04004,0.00400/1, O. O- 0: (1, O, O, O, O. 1): 0.175.0.338,0.3 14.0.14.0.03.0.003. O. O; (1. O, O, O, 1, O): 0.175. 0.338,0.314,0.14.0.03.0.003, O, 0: (1,0,0,0. 1, 1): 0.047047,0.179179,0.33033,0.292292,0.I24124.0.025025.0.002002.0; ( 1. O, O, 1. O, O): 0.0970973, 0.264264. 0.346346,O.Z 1721 7.0.0650652. 0.00900903, 0.00 LOO 1. O: (1, O, O. 1. O. 1): 0.018981,0.103896,0.270729.0.337662,0.201798.0.0579122.0.00799209,0.000999009; (1. O. O, 1. 1.0): 0.018981.0.103896,0.270729,0.337662.0.201798.0.0579422, 0.00799209,0.000999009; (1.0,0, 1, 1, 1): 0.002. 0.022.0.1 13,0.281,0.333,0.19,0.052,0.007; (1. O, 1, O, O, 0): 0.0970973,0.264264.0.346346,0.217217,0.0630652,0.00900903,0.00 100 1, O; (1, O. 1, O, O, 1): 0.018981.0.103896,0.270729,0.337662,0301798,0.0579122.0.00799209.0.000999009; (1. O, 1.0. 1, O): 0.018981. 0.103896.0.270729.0.337662,0.201798, 0.0579122.0.00799209,0.000999009; (1, O. 1, O, 1, 1): 0.002, 0.022,O.I 13.0.281.0.333,0.19.0.052. 0.007: (1. O. 1, 1. O. 0): 0.007.0.05Z, 0.19,0.333.0.281.0.113,0.022.0.002; (1. O, 1, 1, O, 1): 0.000999009,0.00799209,0.0579422,0.20 179S,0.3376627 0.270729,O. 103896, 0.0 1898 1; (1,O. 1, 1, 1. O): 0.000999009, 0.00799209, 0.0579422.0.201798.0.337662, 0.270729,0.103S96, 0.018981: (1. O, 1. 1. 1, 1): O. 0.00 1001,0.00900903,0.0650652.02 172 17, 0.346346.0.263263,0.0970973; (1, 1. O, O. O. 0): 0.0970973,0264264,0.346346,0.217217,0.0650652.0.00900903,0.001001. O; (1, 1, O, O, O, 1): 0.018981.0.103896,0.270729,0.337662,0.201798, 0.0579422,0.00799209,0.000999009; (1, i, O, O. 1.0): 0.0 1898 1. O. 103896,0.270729,0.337662,020 1 ï38,0.0579422,0.00799209,0.000999009; (1, 1. O, O, 1, 1): 0.002,0.022,0.113,0.281,0333,0.19,0.052,0.007; (1. 1. O, 1, 0, 0): 0.007,0.052, 0.19.0.333,0.281,O.I 13, 0.022,0.002; (1, 1, O. 1. O, 1): 0.000999009.0.00799209. 0.0579422.0.201798, 0.337662. 0.270729, 0.103896, 0.018981; ( 1. 1. O, 1. 1. O): 0.000999009.0.00799209.0.0579322.0.201 798.0.337662, 0.270729, O. 103S96.0.01898 1 ; (1. 1, O, 1, 1. 1): O, 0.00 1 O0 1,0.00900903.0.0650652,0.2 172 17.0.346336, 0.264264,0.0970973; (1 . 1. 1,0, O. O): 0.007,0.052.0.19.0.333.0.281.0.113.0.022,0.002;
Belief i\'enrork Anabsis of Direct Cos1 Risk in Building Consrrucrion 188
(I, I , 1.0.0. 1): 0.000999009,0.00799209,0.0579422,0.20 l798.0.33766X 0.270729,0.I03896,0.0 1898 1; (I, I , I , 0, 1.0): 0.000999009,0.00799209,0.0579422,0.201798,0.337662.0.270729,0.103896,0.018981; (1, L, I. 0. 1, 1): 0,O.OO 100 1, 0.00900903.0.0650652 0 2 172 17,0.346346,0264264,0.0970973; (1, 1, 1, L O , 0): 0,0.002002,0.025025,0.124124,0.292292,0.33033,0.179179,0.M7047; (1, I, I, I , 0, 1): 0.0,0.003,0.03,0.14.0.314,0.338,0.175: (I, I, 1, 1, I, 0): 0.0,0.003,0.03,0.14,0.3 14.0.338.0.175; (1. I, I, 1. 1, I): 0.0,0,0.004004,0.04004.0.179179,0.383383,0.393393; (2,0,0,0,0,0): 0.277,0.38,0.251.0.079,0.012,0.001.0.0: (2,0,0,0,0, 1): 0.0970973,0264264,0.346346,0.217217,0.0650652,0.00900903,0.001001.0; (2.0,0,0, I, 0): 0.0970973,0.264264,0.346346.0217217.0.0650652,0.00900903,0.00 I00 1.0; (2.0.0.0. I , I): 0.007,0.052,0.19,0.333,0.281,0.113,0.022,0.002; (2,0,O, 1.0.0): 0.047047.0.1791 79. 0.33033,0.292292,0 I24 124.0.025025.0.002002.0; (2,0,0, 1.0, I): 0.007,0.052,0.19,0.333,0.281,0.113,0.022,0.002: (2,0,0, 1, 1.0): 0.007,0.05& 0.19,0.333.0.281,0.113,0.022,0.002; (2.0,O. 1, 1. 1): 0,0.002002,0.025025.0.124 l24,O.292292,O.33O33,O. 179 l79.O.O47O47; (2.0, I, 0.0.0): 0.047047,0.179179. 0.33033,0293292.0.124124,0.02S025,0.002002.0; (2.0, I , O,O, 1): 0.007,0.05L 0.19,0.333,0.281,0.113,0.022,0.002; (2.0, 1.0, 1.0): 0.007,0.052,0.19,0.333.0.28 1.0.1 13.0.022,0.002; (2.0, I. 0, I, I): 0,0.002002,0.025025,0.124I24,0.292292,0.33033,0.179 179,0.047047: (2.0, I, LO, 0): 0.002,0.022,0.113,0.281,0.333,0.19,0.052,0.007; (2.0, 1. 1.0. 1): 0,0.002002,0.025025,0.124 124.0.29Xl92, 0.33033,O.I 79 179, 0.047047: (2.0, 1. 1, I, 0): 0,0.002002,0.025025,0.124124,0292292,0.33033,0.179 179.0.047047; (2.0, I, I, I, 1): O,O,O.OOL, 0.012,0.079,025L, 0.38,0.277; (2, 1, 0, 0, 0,O): 0.047047,O. 179 179, 0.33033.0.292292,O. 124 l24.0.025025, 0.002002.0; (2, I. 0.0.0. 1): 0.007, 0.052,0.19.0.333,0.281.0.113,0.022,0.002; (2. 1, 0,O. 1.0): 0.007, 0.052,0.I9,0.333,0.281.0~113.0~037~ 0.002: (2, l.O,O, I , I): 0,0.002002,0.025025.0.124124.0.292292,0.33033.0.179 179.0.047017; (2, I , 0, 1.0.0): 0.002, 0.022. 0.1 13, 0.281,0.333,0.19.0.052,0.007: (2, 1,O. I, 0, 1): 0,0.002002,0.025025,0.124124,0.292292,0.33033.0.179 179.0.047047; (2, 1,0, 1, I , 0): 0,0.002002,0.025025,0.124124,0.292292,0.33033,0.179 179,0.047037; (2. 1,0, I , I , I): O,O, 0.001.0.012, 0.079,0.251.0.38, 0.277; (2, I , I , 0.0.0): 0.002.0.022. 0.1 13,0.281.0.333,0.19,0.052.0.007: (2, I, I. 0.0, 1): 0,0.002002,0.025025,0.124 124.0.292292,0.33033.0- 179 179.0.047047; (2, 1, I, 0, I , 0): 0,0.002002,0.023025.0.124124.0.292292,0.33033,0.179179.0.047047; (2. I. I. 0, I, I): 0,0.0.001,0.012,0.079.0.251,0.38.0.277: (2, 1. 1, I, 0.0): 0, O.OOIOOI, 0.00900903,0-0650652.0.217217,0.346346.0.264264.0.0970973; (2. 1. 1, I , 0, I): 0,0,0.001.0.0~2.0.079,0.251,038,0.277: (2. 1. I. I, 1,O): 0,0,0.001.0.012.0.079,0.251,0.38,0.277; (2, 1, 1. I, I, 1): 0,0,0,0.001,0.019.0.1 17.0.3S3,0.51:
1
probability(Materia1 I Materialshortage, CnstrctnblrktEscltn, Materialwaste, Scopecreep. DesignChanges. ValueEngineering)
(O,O, O,O, 0, 0): 0.51, 0.353.0.1 17,0.019, 0.001, 0, 0.0: (0, C, O,O,O, 1): 0.277,0.38,0251,0.079.0.012,0.001,0.0; (O,O, 0.0, I, 0): 0.277,038,0.25 1,0.079,0.012.0.001,0,0; (0.0.0,O. I, I): 0.0970973, 0.264264.0.346346,0.2~7217,0.0650652, 0.00900903,0.001001,0: (0.0.0. I,O, 0): 0.277,0.38, 0.251,0.079,0.012,0.001.0.0; (0.0.0, I. 0, 1): 0.0970973,0264264,0.316346,0.217217,0.0650652, 0.00900903,0.00 100 1,O: (0.0.0, 1 , 1,O): 0.047047,0.179179,0.33033,0.292292,0.L24124,0.025025,0.002002, 0; (O,O,O, I , 1, I): 0.007,0.052,0.19,0.333,0.281,0.113,0.022,0.002; (O,O, 1,O.O. 0): 0.277,0.38.0.251,0.079,0.012,0.001.0,0; (O,O, I, 0.0, I): 0.0970973,0.264264,0.346346,0.217217,0.0650652,0.00900903,0.00 1001.0; (O,O, 1.0, I, 0): 0.047047,0.179179,0.33033,0.292292.0.124124.0.025025.0.002002,0; (0.0, 1.0, I, I): 0.007.0.052,0.19.0.333.0.281,0.113,0.022.0.002: (0,O. 1. 1,0,0): 0.047047,0.179 17% 0.33033.0.292292.0.124124,0.025025,0.002002,0: (0,O. I , 1.0. I): 0.007,0.052,0.19,0.333.0.281,0.113,0.022.0.002; (0, 0, 1, 1, 1.0): 0.007,0.052, 0.19,0.333,0.281, 0.1 13,0.022,0.002; (0.0, 1. 1, I, I): 0,0.002002,0.025025,0.124124,0.292292,0.33033,0.179 I79.O.W7047; (0, I , 0.0.0.0): 0.277,0.38.0.251,0.079,0.012, 0.001.0,O; (0, I, 0,0,0, I): 0.047047,0.179179,0.~~033,0.292292,0.12-i124,0.02S025, 0.002002,O; (0, I, 0,0, I, 0): 0.047037.0.179 179, 0.33033,@.292292,0~124124,0.025025,0.002002,0; (0, 1.0.0, I. 1):0.007,0.05~0.19,0.333,0.281,0.l13,0.022,0.002: (0, 1, 0, I, 0.0): 0.047047, 0.179 179, 0.33033,0.292292, 0.124 124, 0.025025,0.002002,0; (0, I. 0, I, 0, 1): 0.007, 0.052,0.19, 0.333,0.281, 0.1 13,0.022,0.002; (0, I, 0, I, 1.0): 0.002,0.022,0.113,0.281,0333,0.19,0.052.0.007; (0, 1.0, 1. 1, 1): 0,0.002002,0.025025,0.124124.0.292292,0.33033,0.179179,0.047047: (0, I, 1,0, I), 0): 0.047047,0.179179,0.33033,0.292292,0.124124,0.025025,0.002002,0; (0, I, I, 0.0, I): 0.007,0.052, 0.19,0.333,0.281,0.113,0.022,0.002: (0, 1. 1.0, 1,0):0.002,0.022,0.113,0.281,0.333,0.19,0.052,0.007:
Belief XencporX- Analysis of Direct Cost Risk in Bidding Consrnrcrion 189
(O, 1. 1. O, 1, 1): O, O.OO2OO3 0.025025,0.124124,0.29~92,0.33033.0.I79179,0.047047: (O, 1, 1, 1, O, O): 0.002,0.022,0.1I3,0.281,0333,0.19,0.052,0.007~ (O, I , 1. I, 0, 1): 0,0.002002,0.025025,0.124124,0292292, 0.33033.0. t 79179.0.047047; (0, 1, 1. 1, 1.0): 0,0.002002,0.025025.0.124124,0292292,0.33033. O. 179 l79,0.047047; (O, 1, 1. 1, 1. 1): O. 0,0.001,0.012,0.079.0.251,0.38.0.277; (1,0,0,0. 0,O): 0.277,038,0.251,0.079, 0.0I2,0.001,0,0; (1. O, O. O, O, 1): 0.047047, O. 179179.0.33033,0.192292, O. 124 124,0.025025.0.002002. O; (1. O, O, O. 1. O): 0.047047,0.179179,0.33033,C).292292.0.124124,0.025025,0.002002, O; (I.0,O.O. 1. 1):0007,0.052.0.19.0.333,0.281,0.113,0.022,0.002: (1. O, O, 1, O, O): 0.C47047,0.l79179,0.33033.0292292,0.124123,0.015025.0.002002, O: (1 , O. O. 1, O, 1): 0.007,0.052.0.19.0.333,0.28I,O.lI3. 0.022,0.002; (1.0, 0, 1. 1.0): 0.002,0.022,0.113.O.2S~, 0333,0.19.0.052,0.007; ( 1, O, O, 1. 1, 1): 0.0.002002,0.025025,0.1Z4123,0292292,0.33033,0.179 179.0.047047: ( 1- O, 1. O. O, 0): 0.047047.0.179 I79,033033,0.292292,0.124 124,0.025025,0.002002.0: (1, O, 1, O. O, 1): 0.007,0.052,0.I9,0.333- 0.281,O.I 13, 0-022.0.002: (1, O, 1, O. 1, O): 0.002.0.02L 0.1 13,0.281.0333,0.19, 0.052.0.007; (1. O. 1, O. 1, 1): O. 0.002002,0.025025. O. 124 124, 0292292.0.33033.0.179 179.0.047047; (1, O. 1. 1, O, O): 0.002,0.022,0.113.0.281.0333,0.19.0.052.0.007: (1, O, 1. 1. O, 1): O, 0.002002.0.025025.0~123 124. 0292292.0.33033. 0.179 179.0.047047; (1, O. 1, 1. 1. O): O. 0.002002.0.025025.0.124123,0.29192.0.33033.0.179 179.0.047047: (1,O. 1, 1. 1. 1): O. O. 0.001.0.0L2,0.079.0251,0.38,0.277: (1. 1. O, O, O, O): 0.047047,0.179179, 0.37033,0.292292.0.124121.0.025025.0.002002. O; (1. 1. O, O. O. 1): 0.002, OAO22, 0-1 13,0.281.0.333.0.19,0.052,0.007; (1. 1. O, O, 1. 0): 0.002,0.022,0.1 13,0.281.0333.0.19.0.052, 0.007; (1, 1, O. O. 1, 1): O, 0.002002,0.025025,0.I24 124,0.292292,0.33033, O. 179 179,0.0470.17: (1. 1. O, 1. O, O): 0.002,0.022,0.113, 0.281.0333. 0.19.0.052.0.007: (1. 1. O, 1. O, 1): O, 0.002002,0.025025, O. 124124,0.292292,0.33033, O. 179 179.0.047047; (1, 1, O, 1. 1, O): O, 0.001001,0.00900903.0.0630652,0.2 1721 7,0.346346,0.264264.0.0970973; (1, 1. O, 1, 1. 1): O, O, 0.001,0.012, 0.079, 0251,0.38,0277: (1. 1, 1, O, O, O): 0.002,0.022,0.113.0.281,0.333. 0.19, 0.052.0.007; (1, 1. 1, O, O, 1): O, 0.002002,0.025025. O. 124 124, 0292292.0.33033, O. 179 I79.O.W7047; (1, 1. 1. O, 1, O): O, 0.001001,0.00900903. 0.0650652,02 172 17.0.346346. 0.261264,0.0970973: (1. 1, 1. O, 1, 1): O, O, 0.001,0.012,0.079,0.251,0.38,0.277; ( 1. 1. 1. 1, O. O): 0.0.001001.0.00900903.0.0650652.021 72 17.0.346346. 0.264264.0.0970973; (1. 1, 1. 1. O, 1): O, O, 0.001.0.012,0.079,0~251,0.38,0277; (1. 1. 1. 1. 1, O): O. O, 0.001.0.012.0.079. 0.251,0.38.0.277: (1. 1, 1. 1, 1, 1): O, O,O, O.OOl.O.Ol9,O.l l7,0.353,0.51;
I
(O, O, O, O): 0.6,0.4; (O. O, O, 1): 0.9, O. 1; (3, O, 1. O): 0.6.0.4; (O, O. 1, 1): 0.83,0.17; (0. 1. O, O): 0.53.0.47; (O. 1, O. 1): 0.7,03; (O. 1, 1. O): 0.5.0.5: (O, 1, 1. 1): 0.7.0.3; (1. O, O, O): 0.6.0.4: (I,O, O, 1): 0-67.0.33; (1. O, 1, O): 0.47.0.53: (1, O, I , 1): 0.73.0.27; (1, 1. O, O): 0.4.0.6; (1, 1, O, 1): O.6,O.a; (1. 1. 1, O): 0-17.0.83; (1. 1. 1. 1): 0.47,0.53;
(O, O, O): 0.67, 0.33; (O, O, 1): 0.23,0.77; (O, 1. O): 0.44.0.56; (O. 1. 1): O. l6,O.83; ( 1. O, O): 0.54,O. 16; ( 1, O. 1): O-56,O.M; (1, 1, O): 0.77.0.23; ( 1, 1, 1 }: 0.33,0.67:
1
Belle/ Nehvork Analysis of Direct Cost Risk in Building Construcrion 190
probability(FieldClaims 1 DefectiveWork GroundConditions, Traddoordination) {
(O, O, O): 0.67.0.33: (O. O, 1): 0.83. O. 16: (O. 1. O): 0.23,0.77; (O. 1. 1): 0.56.0.41; ( 1. O, 0): 0.44.0.56; (1, O, 1): O.77,0.23; (1, 1 , O): 0.l6.O.84; (1, 1, 1): 0.33.0.67;
1
probability(DelriyC1airns I LongWorkStoppages, Ovenime. ConstmctionDeIays) l
(O. O. O): 0.84,0.16: (0, O, 1): 0.77,0.23; (O, 1. O): 0.56,O.M; (O. 1. 1): 0.33.0.67; (1, O. O): 0.67.0.33: ( 1,O. I ): 0.44,0.56; ( 1 , 1, O): 0.23,0.77; (1. 1. 1): 0.16,0.84;
1
probability(PMClaimsMitigation 1 PM. QifdKyPMPnnnl) t
(O. O): 0.44.0.56; (O, 1): 0.52.0.48; (1, O): 0.45.0.52; (1. 1): 0.56.0-44;
1
probability(Conrrac1Clauses 1 Cnuctr&mntTyp) I
(O): 0.85. O. 15. O; ( 1): 0.65.0.3.0.05; (2): 0.77.0.23, O; (3): 0.04,0.9,0.06;
1
(O. O, O): 0.93.0.07; (0. O, 1): 0.7,0.3: (O. 1. O): 0.77.0.23; (O, 1, 1): 0.3, 0.7; (1. O, O): 0.9, 0.1; ( 1, O, 1 ): 0-6.0.4; ( 1. 1. O): 0.77.0.23; (1- 1, 1): 0-1, 0-9:
1
probability(ConstructionDelays 1 FailureDelays. EnvironrnentalDelays, DesignDelays, LogisticsDelays, LabourDelays) {
(0, 0,O: O, O): 0.87, 0.13; (O, O, O. O. 1): 0.87. 0.13; (O, 0. O, 1, O): 0.87.0-13; (O, O. O, 1. 1): 0.87, 0.13; (O, O. 1. O, O): 0.87. 0.13: (O, O, 1, O, 1): 0.87. 0.13: (O, O, 1 , 1, O): 0.87, O. 13; (O, O, 1, 1, 1): 0.87.0.13; (O, 1, o. o. O): 1. O; (O, 1, O, 0, 1): 1, O;
Belief Nenvork Anaiysis of Direct Cosr Risk in Btrilding Consrnrction 191
(O, l,O, 1.0): 1,o: (O, 1. O, 1. 1): 1, O: (O, 1.1.0,O): 1.0: (O, 1, 1, o. 1): 1 . O; (O. 1. 1- 1. O): 1- O: (O* 1- 1. 1.1): 1.0; (1.0,0,0.0):0.87,0.13: (1, O, 0. O. 1): 0.87,0.I3: (1. O, O. 1. O): 0.87,0.13: (1,O.O. 1, 1): 0.87.0.13; (1.0. I,O,0):0.87,0-13; (1.0, 1. O, 1): 0.87, 0.13; (1.0, t. 1,O): 0.87.0.13: (1.0, 1, 1, 1): 0.87.0.13; (1. 1.0,0.0):0.87.0.13: (1, 1. O, O, 1): 0.83,0.17; (1, 1. O. 1. O): 0.73.027: (1. 1, O, i, 1): 0.7.0.3: (1. 1, 1. O. O): 0.77.0.23; (1. 1. 1. O, 1): 0.47.0.53; (1, 1, 1, !,O): 0.73.0.27; (1. 1, 1, 1, 1): 0.01. 0.99:
1
(0. O. O): 0.84, O. 16; (O, O. 1): 0.77.0.23; (O. 1, O): 0A67. 0.33: (O, 1, 1 ): 0.34.0.56; (1, O, O): 0.56,0.44; (1, O, 1): 0.33, 0.67; (1. 1. O): 0.23.0.77; (1. 1, 1): 0.16.0.84:
I
(O, O. O, O): 0.97.0.03: (O, O, O. 1): 0.4,0.6: (0, 0, 1. 0): 0.77,0.23; (O, O, 1. 1): 0.06.0.94: (O. 1, O, 0): O. 12.0.88; (O. 1. O, 1): 0.0 1. 0.99; (O. 1, 1, O): 0.0 1. 0.99; (O, 1, 1, 1): o. 1; (1, o. O, O): 1, O; (l,O,O. 1):0.99, 0.01; (1.0. 1. O): O.99,O.Ol; (1, O. 1. 1): 0.88.0.12: ( 1 , 1. O, O): 0.94,0.06; (1, 1. O, 1): 0.23.0.77; ( 1, 1 1. O): 0.6,0.4: (1, 1. 1, 1): 0.03,0.97;
1
Belief Xenvork Anafysis of Direct Cosr Risk in Birilding Constnrction 192
probability(LogisricsDelays 1 CnstrcuiOpruisInufmc. MateriaIsDelivery) (
(O. O): 0.52.0.48; (O, 1): 0.56,0.44; (1, O): 0-44.0.56; (1. 1): 0.48.0.52;
1
probabili&(DesignDelays 1 DesignSubmittal, DesignChanges)
(O, O): 0.52. 0.48: (O, 1 ): 0.44.0.56; ( 1. O): 0.56.0.44: (1. 1): 0.48.0.52;
1
probabiIity(EnvironrnentdDe~ays 1 WeatherExuemes. EnvrnrnntlSnstvty, LandDelays) (
(O, O, O): 0.96,0_04; (O. O. 1): 0.93.0.07: (O. 1.0): 0.7 1,029: (O. 1, 1): 0.57,0.43: (O. 2.0): O. 19.0.8 1: (O, 2. L): O. 1 1,039: (1, O. O): 0.89, O. 1 1; (1, O. 1): O.Sl,O.l9: (1. 1. O): 0.43.0.57; (L, 1, 1): 029,0.71; ( : . 2, O): 0.07,0.93; (1.2. 1): 0.04.0.96;
1
probability(LandDe1ays 1 LndRltdNtrIDsstr, G~ology, GroundConditions) (
(0. O. 0): 0.77.0.23: (O, O. 1): 0.33.0.67: (O. 1. O): 0.84, O. 16: (O. 1. 1): 0-56.0.44; (1. O. O): 0*4,0.56; (1. O. 1): 0.16.0.84; (1. 1. O): 0.67.0.33; (1, 1. 1): 0.23.0.77;
1
(O, O. O, O): 0.77.0.23: (O. O, O, 1): 0.73.027; (O. O. 1, O): 0.77,O.U; (O, O, 1. 1): 0.5.0.5; (O, 1, 0. O): 0.6.0.4; (O. 1.0. 1): 0.47,0.53: (O. 1, 1. O): 0.43.0-57: (O, 1, 1, 1): 0.27,0.73; (1, O. O. 0): 0.9, 0.1; (1, O. O, 1): 0.73.0.27; (1. O, 1, O): 0.87,0.13; (1, O, 1, 1): 0.67.0.33; (1, 1, O, O): 0.63.0.37; (1, I , O. 1): 0.57,0.43; (1. 1. 1. O): 0.5.0.5; (1, l7 1. 1): 0-4.0-6;
)
probability(Short8reaks 1 Climate, LbrInjrsAccdnrs. StblEqpmntAvIblty, MaterialShonage) I
(O. 0. O. O): 0.77.023: (O. O, 0. 1): 0.0 1.0.99; (O, O, 1. O): 0.99,O.O 1;
Belie/Nenvork Anafysis 01 Direct Cost Risk in Btrilding Construction 193
(O, O. 1. 1 ): 0.6.0.4: (O, 1. O, 0): 0-06.0.94; (O. 1.O.l):O. 1; (O, 1. 1, O): 0.88.0.12; (O, 1. 1. 1): 0.03,0.97; (1. O. 0,O): 0.97,0.03; (1.0. O. 1): O. 12.0.88; (1, o. 1. O): 1. O: (1, O. 1. 1): O.94,O.O6; (1, 1.0.0): 0.4,0.6: (1, 1, O, 1): 0.01,0.99: (1. 1. 1, O): O.99,O.Ol: (1. 1. 1. 1):023.0.77:
I
probabili&(labourCongestion 1 CnstrctnOprtnslntrfmc. TrafficCongestion. NmbrOfiVrkrsOnSt) (
(O, O, 0): 0.84, O. 16; (O, O, 1): 0.77,0.23; (O, 1, O): 0.67.0-33; (O, 1, 1): 0.4,0.56; ( 1. O, O): 0-56.0.4; (1. O, 1): 0.33.0.67; (1. 1- O): 023.0.77: (1, 1. 1): 0.16,0.83;
1
(O, O, O, 0): 0.0 1.0.99: (O, o. o. 1): o. 1: (O. O. 1.0): 0.12.0-88: (O, O, 1, 1): 0.0 1.0.99: (O. 1, O, O): 0.77.023; (O, 1. O, 1): 0.06.0.94; (O, 1, 1, O): 0-97.0.03; (O, 1, 1. 1 ): 0.4,0.6; (1, O. O. O): 0.6. 0.1; (1. O. 0. 1 ): 0.03.0.97: (1, O. 1. O): 0-94.0.06; (1, O. 1. 1): 0.23.0.77; (1. 1. 0. O ) : O.99,O.OI: (1, 1, O. 1): 0.88.0.12; (1, 1. 1, O): 1, O; (1, 1, 1. 1): 0.99,O.OI;
1
probabiiity(WrkQnttyDvtns 1 DefectiveWork DesignChan~es, Groundconditions, TnntRqrmntChns DaipQuality) {
(O,O,O,O,O): 0.93.0.07; (O, O, O, O, 1): 0.93, 0.07: (O. O, O. 1. O): 0.93,0.07; (O. O, O, 1. 1): 0.93. 0.07: (O, O. O, 2. O): 0.93. 0.07; (O, O, O, 2, 1): 0-93.0.07; (O, O, 1. 0. O): 0.93.0.07: (O. O, 1, O. 1): 0.93.0.07: (O, O, 1, 1,O): 0.93.0.07: (O, O, 1, 1, 1): 0-93.0.07; (O, O, 1.2, O): 0.93,0.07; (O, O, i . 2. 1): 0.93.0.07; (O. 1. O, O, O): 0.23.0.77; (O, 1, O, O, 1): 0.23,0.77; (O, 1.0. 1, O): 0.23.0-77; (O. 1. O, 1, 1): 023.0.77: (O, 1. O, 2, O): 0.23,0.77; (O. 1, O, 2. 1): 0.23.0.77; (O. 1, 1. O, O): 023.0.77: (O. 1. 1. O. 1): 0.23-0.77: (O, 1, 1, 1. O): 0.23,0.?7;
Belief ~Venvork Anabsis of Direcr Cosr Risk in Building Consrnrction 194
(1, 1, O, 1): 057.0.43; (1, 1. 1. O): 0.63.037: (1. 1, 1, 1): 0-83.0-1 7;
1
probability(EqprnntPrdctvty 1 Altitude. GroundConditions, StblEqpmntAvlblty)
(O. O. O): 0-7.0.3; (O. O. 1): 0.83, O. 17; (O. 1. O): 0.3.0.7; [O, 1. 1): 0.7.0.3: ( 1. O, O): 0.63.0.37: (1. O, 1): 0.83,O. 17: (1- l7 O): O.I.O.9; (1, 1. 1): 0.6.0.4;
1
(O): 0.23,0.77; ( 1): O. 15,O-85;
I
probabil i~(A.rchlgclSrvy) {
0.5.0.5; 1
(O. 0. O): 0.57,0.43; (0. O, 1): 0.3.0.7; (O, 1.0): 0.35,0.65; (O. 1, 1 ): 0.03,0.96: (1, O, O): 0.87, O. 13; (1, O. 1): 0-7.0-2; (1- 1. O): 0.6.0.4: (1, 1. 1): 0.2,0.8:
probability(TraffTcCongestion PhysclPrjctSz, Cmptn:ActvtyOnSt, NrnbrOfiVrkrsOnSt. SiteAcces2 s
(O, O. O, O): 0.55, 0.45: (O. O, O. 1): 0.93, 0.07; (O, O, 1. O): 0.53.0-47; (O, O, 1, 1): 0.8. 0.2; (O. 1. O. O): O. 17.0.83: (O, 1, O. 1): 0.27.0.73; (O. 1. 1. O): O.l3,0.87; (O. 1. 1. 1): 0.27.0.73; ( 1 . O, O, 0): 0.6, 0.4; ( [ , O, O, 1 ): 0.6,0.4; (1, O. 1. O): 0.6, 0.4; ( i , O, 1, l ): 0.6,O-4: (1. 1, O, O): 0.5,0.5; (1, 1, O. 1): 0-5. 0.5: ( 1. 1, 1. O): 0.27.0.73; (1. 1, 1, 1): 0.37.0.63;
1
Beliej Nenvork Analysis of Direct Cosr Risk in Building Consrnrction 196
(O): 0.8,02; (1): 0,13,0.87;
I
probability(CostAccounting 1 PM) f
(O): 0.83, O. 17: (1): O. 13.0.87;
1
(O, 0. O): 0.27.0-73; (O, O, 1): 0.83.0.17; (O, 1. O): 0.3,0.7; (O, 1, 1): 0.75.0.25: (1, O, O): 0.27,0.73: ( l+ O, 1): 0.8,0.2: ( 1, 1. O): 0-27.0.73: (1. 1, 1): 0.67.0.33;
1
(O): 0.83, O. 17; ( 1 ): 0.33,0.67;
1
probability(CprtvEnvmmnt 1 QlfdKyPMPrsnnl. PM)
(O, O): 0.83. O. 17: (O, 1): 0.43.0.57; ( 1,O): OV6,0.4r (1. 1): 0.2, 0.8:
1
probability(PM 1 QlfdKyPMPrsnnl, PMWorkFamiliarity)
(O, O): 0.86.0.14: (O. 1): 0.6,0.4: (1,O): 0.6,0.4; (1, 1): 0.23.0.77;
(O): O. 13.0.87; ( 1): 0.7.0.3;
i
(O): 0.7.0.3: (1 1: 0.77.0-73;
1
Belief Arenvork Analysis of Direct Cosr Risk in Building Constnrcfion 197
probability(Va1ueEngineering 1 ConstructionDelays. PM, BudgetRcvisions)
(O, O. O): 0.4,O.O; (0. O, 1): 0.7,0.3; (O, 1. O): 0.3,0.7: (O, 1. 1): O. 15,0.85: (I.0,O): 0.33.0.67; (1, O. 1): 0.73.0.27; ( L, 1.0): 0.27.0.73: (1, 1, 1): O.6,OA;
1
probability(DesignChmges 1 CmplxtyCnsuctbleOfDsg- ScopeCreep. DesignQuality) \
(O. O, O): 0.53.0.47: (O, O, 1): 0.93,0.07: (O. 1, O): O. 13.0-87; (O, 1, 1): 0.8,02; (1. O, O): 0.35.0.65: (1, O. l): O-7,0.3; (1, 1. O): 0.04.0-96; (1. 1, i): 0.6. OA;
1
probability(DesignSubmitta1I ScopeCreep. DsgnTmCrdntn) I
(O. O): 0.4.0.6; (O. 1): 0.13,0.87: (1. O): 0.7, 0.3; (1. 1): 02.0.8;
1
probability(DesignQuality 1 ScopeCrerp, DsgnTmCrdntn, CnstrctnTchnlgyRqrmnfs) {
(O, O. O): 0.37.0.63; (O, O. 1): 0.7.0.3; (O, 1.0): 0.2,o.s; (O. 1. 1): 0-3.0.7; ( 1. O. 0): 0.73.0.27: (1, O. 1): 0.93. 0.07: ( 1, 1. O): 0.23, 0.77; (1. 1- 1): 0.3.0.7:
I
probability(ScopeCreep 1 DsgnTmCrdntn. TnntRqmntChng)
(O, O): 0.8, 0.2 (O, 1): 0.3, 0.7; (O. 2): 0.14.0.86: (1. O): 0.97.0.03: (1. 1): 0.55,0.45; (1.2): 0.35,0.55;
1
I (O): 0.7,0.3; (1): 0.1,O.g;
1
Beiief A'e fivork Analysis of Direct Con Risk in Building Consrnrction 198
probability(Regulato@enalties f EnvrnrnntlSns~vtv) {
(O): 0.63. 037; (1): 0.47, 0.53; (2): O. 1,0.9;
1
probability(PerrnitsRequired 1 Utilities) {
(O): 0.43.0.57; (1): 0.7. 0.3: (2): 0.04.0.96;
1
probability(GvrnrnntSpndngOnCnstrc~n 1 Government)
(O): 0.5.0.5; (1 ): 0.43.0.57:
i
probability(1ntmtntMrktPrcs 1 FrgnPrchsdGds. ExchangeRates) {
(OI 0): 0.97,0.03; (O. 1): O. 1.0.9; (1,O): 0.01. 0.99: (1, 1): 0-04.0-96:
probability(CnstrctnMrktEscItn 1 LclCnstrctniLIrkt. GvmrnntSpndngOnCnstrctn. Inflation)
(O, O, O): 0.93, 0.07; (O, O, 1): 0.8.0.2; (O. 1, O): 0.6.0.4; (O. 1. 1): 0.63,0.37; (1.0. O): 0.7,0.3: (1. O, 1): 0.47,0.53; (1, 1, O): 0.6.0.4; (1, 1, 1): 0.13, 0.87; (2. O. O): 0.4.0.6; (2, O. 1): 0.37,O-63; (2 . 1. O): 0.6.0.4; (2- 1. 1): 0.1.0-9:
1
probability(Int1ation 1 GvmmntSpndngOnCnstrctn) (
(O): 0.53.0.47; ( 1): O. 17.0.83:
1
probabiIity(TasRates 1 Govemment)
probabil ity(ExchangeRates) (
0.5.0.5; 1
probability(FrgnPrchsdGds 1 StblEqpmntAvlbIty. ExchangeRates) {
(O, O): O. 1.0.9; (O, 1): 0.2,0.8;
Belief Nenvork Analysis of Direct Cost Risk in Btrilding Consrrucrion 199
(1, O): 0.77.023; (1. 1): 0.87.0-13;
I
{ (O): 0.3.0.7:
probabiIity(StbiEqprnntAv1blty 1 MtrlEqprnntLss. LcICnstrctnMrkt. Geography) t
(O, O, O): 0.07.0.93; (O, O, 1): 0.07.0.93: (O, O, 2): 0.07.0.93; (O, 1. O): 0.6,0.3: (0. 1. 1): 0.37.0.63: (O. 1 , 2): 0.2.0.8; (O. 2. O): 0.4.0.6; (O. 2. 1): 0.55.0.45; (O, 2.2): 0.3.0.7; ( 1.0. O): 0-07.0.93: (1, O. 1 ): 0.07.0.93; ( 1. O, 2): 0.07.0.93; (1. 1. O): 0.7.03; (1, 1, 1): 0-55.0-45: (1. t . 2): 0.2,o.s; (1.2, 0): 0.75,0.25; (I,2, 1): 0.75, 0.25; (1- 2,2): 0.3.0-7:
t
probabiIity(Q1fdLclLbr 1 LclCnstrctnMrkt) (
(O): 0.8,02; (1): 0.37.0.63; (2): 0.47.0.53;
1
probability(CnsrrctnSppnFclts 1 LclCnstrctnMrkt AreaAf-fiuence) I
(O. O): 0.47.0.53; (O. 1 ): 0.4.0.6; (1. O): 0.53.0.47; (1, 1): 053.0.47; (2. O): 0.67,0.33; (2, 1 ): 0.63.0.37:
1
probabilicy(Avlblty0fEnrgy 1 Geography) i
(O): 0.83. O. 17: (1): 0.5.0.5; (2): 0.27,0.73;
I
Belie/Nenvork Anaiysis of Direcr Cos! Risk in Btdding i'onswtic!ion 200
probability(GroundConditions 1 ArchlgclSrvy, Geology) 1 i
(0.0): 0.17,0.83; (O, 1): 0.5,O.s'; (1. O): 0.4,0.6: (1. 1): 0-77.0.23:
1
probability(LndRltdNulDsstr [ Geology) {
(O): O. 17.0.83; (1): 0.3,0.7:
1
probabili&(BudgetRevisions 1 Owner)
(O): 0.37.0.63; (1): O. 17.0.83;
1
probabiIity(FundingSource 1 Govemrnent. GvmrnnrSpndngOnCnstrctn) {
(O, O): 0.37.0.55.0.08: (O, 1): 0.33.0.5, O. 17; (1, O): 0.46.034.0.2; (1. 1): 0.47.0.33,O.Z;
I
Belief Nenvork Analysis of Direct Cosf Risk in Building Consrrucrion 20 1
pro babili~(SiteAccess)
partitions I
node ConstnictionDelays 1 I
level O parent EnvironrnentalDelays, level 1 state O. level 1 stare 1, level 2 parent FailureDelays. lever 3 state O, Ievel 3 state 1. level4 parent DesignDelays. IeveI 5 state O. level 6 parent LogisticsDelqs, level 7 state O, level 8 parent LabourDelays. level9 state O. Ievcl 9 smte 1. Ievel 7 state 1. lever 8 parent LabourDelays, level9 state O. level 9 state 1. level 5 state 1, level 6 parent LogisricsDelays. IeveI 7 state O, level 8 parent LabourDelays. leve19 state O. level9 state i, level 7 state 1, level 8 parent LabourDelap. level 9 stare O, level 9 state 1
1
node WrkQnttyDvtns {
level O parent DesignChanges. level 1 state O. Ievel 1 state 1, level 2 parent DefectiveWork, level3 state O, level 3 state 1, level4 parent TnncRqrrnntChng, level 5 state O, level 6 parent GroundConditions. level 7 state O, level 8 parent DesignQuality. level 9 stare O. level 9 state 1. level 7 stare 1, level 8 parent DesignQuality, level 9 state 0. level9 state 1, level 5 state 1. level6 parent GroundConditions. Ievel 7 state 0.
Belief Nenvork rlnalysis of Direcr Cosr Risk in Building Consrrucrion 202
IeveI 8 parent DesignQuality, level 9 state O. level9 state 1, level 7 state 1, level 8 parent DesignQuality, level9 state O. Ievel9 state L. Ievel5 state 2. level 6 parent GroundConditions, level 7 statc O, level 8 parent DesignQuality. level9 state O. leveI9 state 1. level 7 state 1, level8 parent DesignQuality, level9 state O. level 9 state 1
1
node Materials hortase
level O parent MaterialsDeIivery. Ievel 1 state i. Ievel 1 state O. Ievel 2 parent MaterialWaste, level 3 state O, levcl4 parent MtrlEqpmntLss. level 5 state O. level 6 parent DesignChanges. level 7 state O, lcvel 7 state 1, levd 5 state 1, IeveI 6 parent DesignChanges. level 7 state O? level 7 state 1, level3 state 1, level 4 parent MtrlEqprnntLss, level 5 state O, level 6 parent DesignChanges. level 7 state O. Ievel 7 state 1, level 5 state 1. level 6 parent DesignChanges. level 7 state O. level 7 state 1
1
level O parent PhysclPrjctS~ Ievel 1 state 1, level2 parent Crnpui-ficwtyOnSt. level 3 state O. level 3 state 1. level4 parent NrnbrOfWrkrsOnSt, level 5 state O, level 5 state 1, level 6 parent SiteAccess. tevel 7 state O. Ievel 7 state 1, Ievel 1 state O. level 2 parent CmptngActvtyOnSt level3 state O, IeveI4 parent NrnbrOtWrkrsOnS~ level 5 state 0, level 6 parent SiteAccess. level 7 state 0, level 7 state 1. level 5 state 1, level 6 parent SiteAccess,
Belief Nenvork Anuiysis of Direct Cost Risk in Buildrng Consrnicrion 203
Ievel7 state O, Ievel 7 state 1, Ievel3 state 1. Ievel4 parent NmbrOfWrkrsOnSt. Ievel 5 state O, level 6 parent SiteAccess, level 7 state O. level 7 state 1, level 5 state 1. level6 parent SiteAccess, level 7 strite 0. level 7 state !
1
node StblEqprnntAvlblty i
level O parent LclCnstrctnMrkt. level 1 state O, level 1 srate 1. level2 parent Geography, level3 state 2, level3 state 1. level3 parent MulEqpmntLss. level5 state O, level 5 state 1. IeveI 3 state O, leveI 4 parent MtriEqpmntLss. level 5 state O, Ievel 5 state 1. Ievel 1 state 2, level 2 parent Grography, Ievel 3 state 2, level 3 state 1, level3 parent MtrlEqprnntLss, level 5 state O, level 5 state 1, level 3 state O, level 4 parent MtrlEqprnntLss, level 5 state O, level 5 state 1
Belief h'envork Analysis oJ Direct Cosr Risk in Building Comfrtrction 204
Appendix M: Mode1 Validation Results
Belief Nehvork .Inaiysis of Direct Cost Rrsk in Bur!drng Constnrcrion 205
Validation test #1 results
Contract Arnount: $5.1 95 250 Final Contract Value: $0,417,707 Fixed Cost Amaunt: $3,736,760 Final Contract Increase: 62.00% Unit Pnce Amount: 81.458.490
Details: Originally Planned Scope of Work radically Altered Additional Scope through Extensive Change orders Schedule Delays Costs arising from extended contrad duration: Costs arising from acceleration of work Budget revisions aIIowed lnadequate site investigation Poor estimating Deliberate change o f requirements lncreased volume of work cornpleted Overtime major - extended hours and weekends Loss o f productivity Labour congestion
Belief ~Venvork Anaiysis of Direct Cosf Risk in Building Consrnrcrion 206
Validation test #2 results
Contract Pmount: $1,930,055 Final Contract Value: $3,442,484 Final Contract Increase: 78.40%
Details: Excessive overtime lncreased manhour c o s tower productivity excessive modifications inromplete design, errors in design construction delays poor site accesdegress suitable equipment unavailability no budget revisions lncreased volume of work completed
1 Exoected Values
Belief Nenvork Analysts of Direct Cosf Risk in Building Constnrcrion 207