Northwest Corridor
Express Lanes
Update
Joe Carpenter, P.E. Division Director of P3
Committee of the Whole
February 14, 2018
2
Presentation Overview
• Northwest Corridor Express Lanes Overview
• Project Progress
• Access Points
• Incident Management and Emergency Response
• Next Steps
3
Northwest Corridor Express Lanes Overview
4
Northwest Corridor Construction Status
Current Bridge
ConstructionSouth of Windy Hill Road
Express Lanes
Nearly CompleteI-575
Roadway
Construction
on Schedule
Schedule:
Opening to traffic
90% Complete
5
Northwest Corridor Express Lanes
NWC GroundbreakingOctober 2014
A Peach Pass is needed
to use the Express Lanes
Reversible lanes
29.7Miles of newly
constructed roadway
6
NWC Express Lanes Benefits
Improves interactions
between roadway usersEliminates bottlenecks
Improves infrastructure
Sustains or advances
national or regional
economic growth
Reduces barriers
separating workers from
employment centers
Provides more choices
and reliable trip times
7
Regional Transit Wins with Georgia Express Lanes
No additional cost totransit providers and riders
Increased trip reliability
3,200+ current daily passengers
173 current daily bus trips
24% of Xpress bus trips currently utilize Express Lanes
8
Current and future Park-and-Ride locations connect to Georgia Express Lanes and boost transit opportunities.
Regional Transit Wins with Georgia Express Lanes
9
Xpress Horizon Service Plan
10
I-75 South Metro Express Lanes Success
NWC GroundbreakingOctober 2014
11
I-75 South Metro Express Lanes Success
NWC GroundbreakingOctober 2014
12
Project Progress
13
Groundbreaking October 2014
NWC GroundbreakingOctober 2014
14
Northwest Corridor Construction –On Schedule
• 36 complete
• 3 under construction
• 96% (210 of 219) bridge deck spans complete
• 62 complete
• 6 under construction
39 Bridges: 68 Retaining Walls:
15
I-285/I-75 Interchange
16
I-75/I-575 Interchange
17
I-75 at Windy Hill Road
18
I-75 Bridge over Delk Road
July 2016 January 2018
19
Express Lanes over I-75 Southbound
January 2017 January 2018
20
Bridge Deck at I-75/I-285 Interchange
21
Paving Work at I-75 near Allgood Road
22
I-75 N towards Akers Mill Road
23
Access Points
24
Northwest Corridor Access Points
25
Express Lanes Access – I-75 South Metro
26
Dedicated Access – Big Shanty Road
27
Dedicated Access – Big Shanty Road
28
Dedicated Access – Hickory Grove Road
29
Slip Ramp Access – I-575
30
Express Lanes Gates – I-75 South Metro
31
Incident Management and Emergency Response
32
Emergency Access Gates
33
Incident Response: Training Underway
34
Transportation Management Center
35
Preparations for Operationsand Pricing
36
Coordination with Stakeholders
Fire/
Emergency
Services/
HERO
COBB COUNTY
Cobb County
37
“Go Live” Committee
38
ITS Systems Installation
39
Next Steps
40
Upcoming Activities
Minor roadwork
Finalizing pricing
and ITS systems
Roadwork, pricing and ITS
activities
Bridge 11
Bridge 1, left and right Bridge 5
41
Questions
42
Program Contact and Information
Joe Carpenter, P.E.
Division Director of P3
Project Information