Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Northern Line Extension
Nine Elms and Oval
Community Liaison Group 15.01.15
Update
2
• Following Ferrovial Agroman Laing O'Rourke (FLO)
appointment in Sept 2014 and TWAO approval in
Nov., enabling works have now started in KG and KP
areas.
• Main works to start during 2015 following CoCP B
approval.
• Four Community Drop in Sessions held during first
week of December for comments on CoCP B.
• FLO is now in the process of gaining approval for the
CoCP B by the Local Authorities.
NLE Project Draft timetable
3
Year Key milestones
2014 Transport and Works Act Order decision,
Design & Build contract signed
2015 Agreement on Code of Construction Practice Part B,
Start of main works at all sites
2016 Start of Tunnel Boring Machines
2017 Completion of tunnelling
2018
Fit out of new stations, Kennington shafts complete inc
reinstatement, work at Kennington station complete
2019
Testing, commissioning, trial operations
2020
NLE complete and in service
Nine Elms progress
4
What it’s been done until now
Sept - Dec
14 • FLO (Ferrovial Agroman Laing O’Rourke) awarded NLE
• TWAO approval 12th November 2014
• Start date on site due in early 2015
• Design / Procurement on going
• Liaison with Councils and Communities on going, i.e. Drop in
session (CoCP Part B) held on 3rd December 2014
• Introduction meetings with stakeholders (CGMA, Banhams
and Barratt / Sainsbury’s) already held
Nine Elms look ahead
5
Enabling Works
Jan –
March 15 • Heras fencing and Hoarding installation / Site Accommodation
• Asbestos surveys
• Demolition works to Boiler House and the Chimney
• New Access for Vehicles and Pedestrians onto Pascal Street
• Establishment of temporary haul road
• Parking Restrictions and Footpath / Crossing points Closures
Pascal Street
• Relocation of Sub-station at Sainsbury’s Car Park
• Buried services surveys incl. services protection and Trial holes
• Set up monitoring equipment (noise, dust vibration)
Nine Elms. Road Scheme
6
Ground Investigation
7
• No further ground investigation/ boreholes are
currently planned.
• FLO is now in concept design process with TfL
developing more effective solutions to carry out the
works.
• Ground conditions for tunnelling predominantly
London Clay. An ideal tunnelling medium.
• Groundwater/ step plate junction within a full face of
impermeable London Clay.
• Local de-pressurisation was from within the tunnel
maybe utilised.
Nine Elms
8
Preliminary Settlement Contours
9
Preliminary Settlement Contours
Nine Elms
Measuring & Monitoring
• Monitoring outline design completed end January 2015
• Consultants currently carrying out damage assessments which
will inform the detailed monitoring scope.
• Monitoring tender package to market at the end of January, and
award to follow around March.
• Monitoring installation to start May-June 2015
• A minimum of 4 weeks notice will be given to building owners
prior to the installation of monitoring equipment.
• Envisaged that the monitoring equipment will comprise BRE
studs (structure levelling studs) and 3D geodetic prisms.
10
Monitoring techniques
Buildings – Real time data: 3D geodetic prisms
Automatic Total Station (ATS) Prisms
ATS: an electrical/optical instrument used in modern building construction
to measure slope distances from the instrument to a particular point.
Monitoring techniques
Buildings – Manual data: BRE studs (structure levelling studs)
Defect Surveys
13
• Defect Surveys to be undertaken by a qualified chartered building
surveyor or engineer on properties predicted to experience 1mm or more
settlement.
• Defect Surveys around the station box commence in May/June to ensure
that the surveys are undertaken within 6 months of piling works
programmed for August 2015.
• Defect Surveys in areas of the running tunnels to be undertaken at a later
date in advance of construction (second half of 2016 and first half of
2017).
• TfL to contact affected properties via letter.
• A minimum of 4 weeks notice will be given to building owners prior to the
defect survey being carried out.
• Where necessary a second survey will be undertaken to establish the
difference between the two assessments.
• There will be a written and photographic record and a copy will be
available to the property owner.
Code of Construction Practice Part B
• Four drop in sessions w/c 01.12.14 hosted by FLO senior
leadership
• Information boards on programme of works, environmental
mitigation, site layout and finished schemes
• 47 registered attendees
• 145 comments raised through the paper and online questionnaire
• Feedback from Kennington Green Supporter Group (KGSG), and
further meetings held with Kennington and Wandsworth
Neighbourhood Action Group (KNWAG) and residents to discuss
specific issues
14
• Discussion process closed on 19.12.14
• CoCP B being updated to incorporate comments prior to formal
submission to the local authorities end of January.
• Summary of feedback and responses will be produced.
15
Code of Construction Practice Part B
16
Code of Construction Practice Part B
17
Traffic Management Plans
• Meetings with Local Authorities on-going.
• First draft of Traffic Management Plans (drawings) to be ready
w/c 12 Jan
• Traffic Management Plan (document) include a schedule
forecast for temporary traffic management plans (drawings)
for next six months.
• Temporary traffic management plans (drawings) will follow
when FLO have engaged statutory undertakers.
• These are submitted to Local Authorities.
Traffic Management Plans
Nine Elms
18
Traffic Management Plans
Nine Elms
19
Hoardings
• FLO is now procuring hoardings for all sites.
• Conversations with TfL for standards and design
options on-going
• FLO is looking for input on hoarding graphics.
• Corporate TfL standards
• Dialogue with local CLGs on proposals for each
location
• Feedback and proposals welcome from the CLG.
20
Hoarding at Nine Elms
21
NLE Complaints / Enquiries
Summary
• 2 valid complaints received from October to December 14
22
Date Organisation Address Details of complaint Response Status
07/11/2014 Resident Kennington
Lane
Reported damaged caused by a fox
accesing patios through Compass
temporary hoarding
Response to resident within 24 hours - telephone call and meeting.
Worksite was repaired by Compass and subsequently by FLO. Closed
17/12/2014 Resident Kennington
Road
Reported disruption due to site
lighting reflection to the inside of the
beedroom.
Response to resident within 24 hours - telephone call and email.
The issue was resolved in the same day by applied shielding to the
walkway illumination lights.
Closed
NLE Complaints / Enquiries
Summary
• Immediate solution given to complaint received at Kennington Rd.
23
Updates and newsletters
24
• Quarterly Newsletter sent at the end of November with
updates on NLE.
• Electronically sent to over 1,600 people. Advertised
on website and letter drop of 2,500 copies.
• Next quarterly newsletter due at the end of February.
• Local activity notification have been sent.
• Monthly Activity update due for end of January.
Updates and newsletters
25
Consents
26
Current applications under determination
Kennington Park and Kennington Green – partial
discharge of planning conditions 5 & 7 – works
to trees
L B Lambeth
Submitted December
2014
Approvals granted
Montford Place discharge of planning conditions
6 and 7 (boundary treatments, lighting and
CCTV)
L B Lambeth Granted December
2014
Montford Place Section 61 Consent (Control of
Pollution Act – noise and vibration)
L B Lambeth Granted December
2014
Consents
27
Key forthcoming applications for approval
All sites – application to discharge planning condition 10 -
archaeology
LB Lambeth and
LB Wandsworth
Planned be submitted
February 2015
All sites – application to discharge planning condition 7 –
CoCP pt B
LB Lambeth and
LB Wandsworth
Planned be submitted
late January 2015
All sites – applications for a Section 61 consent under the
Control of Pollution Act - the minimisation of construction
noise and vibration
LB Lambeth and
LB Wandsworth
Planned be submitted
late January 2015
Kennington Park - application to discharge planning
condition 18 – yellow hatched box junction – Kennington
Park Place/Road
LB Southwark Planned be submitted
late January 2015
Kennington Park and Kennington Green – application to
(initially) discharge Conservation Area Consent condition C
(reinstatement)
L B Lambeth
Planned be submitted
mid January 2015
Battersea – applications for approvals under Schedule 8
(Protective Provisions) of the TWAO – works within the
river.
EA, PLA, MMO Planned be submitted
February 2015
Kennington Station - application to discharge planning
condition 19 – Kennington Station passenger flow
monitoring protocols
LB Southwark
Planned be submitted
late January 2015 (direct
by TfL)
Jobs and apprenticeships
TfL’s existing programmes
• Skills & Employment Strategy, Delivery Plan for Schools and Young
People
Employment/Skills/Diversity on the NLE programme
• FlO to work in partnership with TfL and the local authorities – including the
Nine Elms Vauxhall Strategy Board Employment, Training & Business
Charter
• Make sure employment/training opportunities are advertised within the job
opportunity/brokerage schemes operated by Southwark, Lambeth &
Wandsworth councils
• Encourage jobstarts for workless people in London, placement & taster
positions, apprenticeships, skills development for staff, engagement with
schools
28
Skills and Youth Engagement Careers Expo for students (2/12 Wandsworth, 3/12 Lambeth)
• Co-ordinated by Wandsworth BEST. NLE and FLO in attendance at the
event.
• More than 100 students attended NLE (LU-FLO) workshop.
• Encourage young people to consider construction as professional option.
29
Skills and Youth Engagement • http://www.wandsworth.gov.uk/news/articl
e/12653/wandsworth_students_explore_n
ine_elms_careers
30
Careers Expo for students
organised by Southwark
• March 2015
• LU and FLO to participate
Community engagement strategy
• Draft Strategy discussed at the June – July cycle of CLG’s
• Core CLG received all comments made
• Updated Strategy and site specific engagement plans table
• Working document CLG comments and suggestions welcome..
• Southwark Career Expo March 2015.
31