North Second Street Multimodal Project Design
OCTOBER 2017
Agenda Project Description Master Agreement Task Orders
Comprehensive Multimodal Network Evaluation
Grant Writing & Support Services
NACTO Early Action
Division Street Bridge Study
4th & Maclay Intersection Improvements
7th Street – Herr Street to Reily Street
Future Design Tasks
Project Description
Goal 1: Convert N. Second Street to two-way operation Comprehensive traffic study required by PennDOT
Off Second Street Improvements
Second Street Improvements
Goal 2: Advance Division Street Bridge concept Develop feasible concepts & cost estimates
HATS Tip
Goal 3: Multimodal improvements – Uptown & Midtown Goal 4: Incorporate Green Stormwater Infrastructure (GSI)
Project Timeline
Short-Range Tactical Interim Improvements
Workshops & Outreach, Identify Priorities &Develop Concepts
Implement Phase 1Low-Cost Solutions,Tactical Urbanism
Continue with Low-Cost Solutions
StudyLong-Range Improvements, Build Vision
Begin Regional Traffic & Division Street Bridge Studies
Complete Study,ID Infrastructure Needs,ID Funding Needs,Obtain Grants,Begin Design
Complete Design, Begin Phase 1 Construction
Begin Phase 2Design,Complete Phase 1 Construction
2017 2018 2019 2020
Phased Implementation PlanAdvance short-term improvements to build momentum while completing
studies and design for longer term improvements
Short-Range
Tactical Interim Improvements
Workshops & Outreach,
Identify Priorities &
Develop Concepts
Implement Phase 1
Low-Cost Solutions,
Tactical Urbanism
Continue with
Low-Cost
Solutions
Study
Long-Range Improvements, Build Vision
Begin Regional Traffic & Division Street Bridge Studies
Complete Study,
ID Infrastructure Needs,
ID Funding Needs,
Obtain Grants,
Begin Design
Complete Design, Begin Phase 1 Construction
Begin Phase 2
Design,
Complete Phase 1 Construction
2017201820192020
Phased Implementation Plan
Advance short-term improvements to build momentum while completing studies and design for longer term improvements
1
Master Agreement Master agreement with Task Order assignments
5-year term $1.5M upset limit
Task Order (TO) Assignments TO’s issued to coincide with approved FY budgets FY17-18 TO’s
Comprehensive Multimodal Network Study (~$250k) Grant Writing & Support (~$50k) NACTO Early Action (~$75k) Division Street Bridge Study (~$125k) 7th Street: Herr to Reily (~$300k)
Agreement Team
TO1: Multimodal Network Study
TO2: Grant Writing & Support Identify funding opportunities
Transportation Alternatives Set-Aside, TAP Transportation Enhancements Regional Connections Grants PennDOT Technical Assistance State Multimodal Fund Grant (PennDOT & DCED) Green-Light Go, ARLE, SPR Funding NACTO Other State/Federal/Private sources
Assist with research & grant writing Develop supporting materials (e.g. cost estimates, schedules, etc.)
TO3: NACTO Early Action Public Workshops for NACTO/GSI Determine spot locations for low cost multi-modal improvements North 6th Street Improvements Potential Division Street Bike lanes prior to full multimodal
improvements
TO4: Division Street Bridge Study Feasibility Study for a
new bridge Extends Division Street
from 7th to Industrial Road
TO4: Division Street Bridge Study
TO5: 4th Street at Maclay Street Intersection improvements
ADA compliant pedestrian ramps
Traffic signal improvements
Signing & marking improvements
TO6: 7th Street – Herr St to Reily St Roadway Improvements between Reily Street and Herr Street
Improved Multimodal Accommodations at the PHEAA Building
Potential Roundabout at 7th & Reily
Opportunity for large areas of Green Stormwater Infrastructure
Future Task: Forster St. Signal Retiming
Funded by Green-Light Go grant (~$495k) City waiting on executed grant agreement Update Coordination Plan dating from 1963 8 Signals
6 on Forster Street
1 on 6th Street
1 on 7th Street
Future Task : Division St. Multimodal Road diet to reduce traffic speeds and provide multimodal
infrastructure Potential for GSI within median or on outside shoulders Potential to reconfigure 3rd and 4th Street Intersections Reconfigure Division St and Front St Intersection
Future Task: 7th Street Multimodal Multimodal improvements between Maclay & Division Streets Green Stormwater Infrastructure improvements
Future Task: 2nd Street Two-Way Convert North 2nd Street to two-way operation Remove up to 5 traffic signals Potential for two roundabouts Green stormwater infrastructure Multimodal enhancements
Bumpouts
Curb ramps & crosswalks
Transit improvements
Signal improvements
North Second Street Multimodal Project DesignAgendaProject DescriptionProject TimelineMaster AgreementAgreement TeamTO1: Multimodal Network StudyTO2: Grant Writing & SupportTO3: NACTO Early ActionTO4: Division Street Bridge StudyTO4: Division Street Bridge StudyTO5: 4th Street at Maclay StreetTO6: 7th Street – Herr St to Reily StFuture Task: Forster St. Signal RetimingFuture Task : Division St. MultimodalFuture Task: 7th Street MultimodalFuture Task: 2nd Street Two-Way