Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
North River Wastewater Treatment Plant Cogeneration and Electrification Project
Contract NR‐38 Prequalification Pre‐submission Meeting
December 8, 2015
2
Agenda
Topic Presenter Allocated TimeIntroductions and Sign-in Frank Giardina 1:00 pm – 1:05 pmOverall Project Schedule Frank Giardina 1:05 pm – 1:15 pmProject Scope Mike Johnson 1:15 pm – 1:30 pmRequirements for Prequalification Joe Vaicels 1:30 pm – 1:45 pmEnvironmental Health and Safety Bruce Ehrich 1:45 pm – 2:00 pmSubmission of Statement of Qualification Package
Frank Giardina 2:00 pm – 2:15 pm
Questions 2:15 pm – 2:20 pm
3
Schedule
Activity DateIssuance of RFQ November 30, 2015 Pre-SOQ Meeting December 8, 2015
Last Day of Questions December 14, 2015 SOQ Submission January 4, 2016
Notice of Approval/Denial of Prequalification
February 24, 2016
Issuance of Bid Package March 1, 2016 Bid Submission April 12, 2016
Construction Commencement October 10, 2016 Construction Substantial Completion February 7, 2020
4
North River WWTP
Existing primary and secondary treatment facility serving 550,000 customers on Manhattan’s west side.
The facility was completed in several phases which went operational between 1986 and 1991.
Riverbank State Park is located on top of the wastewater treatment plant; the entire structure covers 28 acres.
The plant is constructed on 2,300 drilled piers over the Hudson River, supporting 95% of the platform
6
Liquid Stream Processes
Full Secondary Treatment Plant with a Design Dry Weather Capacity of 170 mgd:
Preliminary Treatment: Screenings, Influent Pumping and Flow Measurement
Primary Treatment: Primary Tanks, Primary Scum Removal, Primary Sludge Removal
Secondary Treatment: Activated Sludge and Secondary Tanks
Disinfection: Sodium Hypochlorite
7
Solids Stream Processes
Screenings Dewatering and Disposal to Landfill
Primary Sludge Pumping, Degritting and Disposal of Solids
Primary, Secondary and Return Sludge Pumping
Anaerobic Digestion of Primary Sludge and Waste Activated Sludge
Digested Sludge Hauled off Site via Barge
Digester Gas used for alternative fuel source
8
Project Scope
Installation of five 3.0 MW Spark-Ignited, Lean Burn Reciprocating Engine Generators Pre-Selected Unit: GE-Jenbacher Provide Power & Heat to the Facility Reduce Air Emissions Operate on either Natural Gas, Digester Gas or Blend of the two Rated for 3.0 MW at 4,160 volts and designed to operate in parallel with
the operation of Con Ed power feed via sync bus N+1 Configuration at average cogeneration demand while operating at
75% load factor
Engine Generators to be installed at current Blower Engine locations NR-46 is providing new high-speed turbo-blowers for Process Air as an
Advanced Contract Blower No 6 will remain in operation Removal of 5 existing Process Air Blowers and Engines
9
Project Scope
Engine Generator Auxiliary Equipment & Operation Engine exhaust piping outfitted with Oxidation Catalysts & Silencers and
utilize the existing exhaust stacks for the MSP Engines. Engine Heat Recovery system being modified extensively.
Sixth Main Sewage Pump (MSP) added to the lineup of five Existing MSPs on Level -43. N+1 Redundancy during construction N+1+1 Redundancy upon construction completion Located north of MSP 1601 New Suction & Discharge Piping with tie-ins at the Wet Well and
Forcemain Discharge Piping matches that of existing five. Suction piping will include
Straightening Vanes
10
Project Scope
MSP Drive System Existing five MSP Engines, Speed Reducer and Intermediate Lineshafting
will be removed and replaced 1,850 HP, 900 RPM Motors and Speed Reducers located on existing
supports for MSP 1601 through MSP 1605. New Foundation for MSP 1606 – enclose a portion of the existing large equipment hatch
Provided with WRIM & Resistor Bank Controllers to achieve 5 distinct speeds to cover full range of flow
Max flow of 355 mgd (340 mgd influent & 15 mgd recycle)
Digester Gas Compressors Sizing of N+2 units will be based on requirements of engines without gas
conditioning equipment.
11
Project Scope
Upgrade HVAC for Main Building to comply with NFPA 820 Electrical Improvements/Design
Coordination with Con Edison for the Service Feeders Upgrade Construction of two new Electric Rooms, Nos. 19 and 20 to house 4.16kV
switchgear lineup New batteries complete with auxiliary equipment & accessories for new
switchgear lineup Upgrade Life Safety Systems to comply with current codes:
Fire Alarm System Fire Sprinkler System Gas Detection System
Flood Protection measures to protect the facility against climate change impacts Raised Wall Openings Floor Expansion Joint Repairs
New Secondary Emergency Waste Gas Burner adjacent to the Sludge Storage Tank
14
Requirements for Pre-Qualification Section V- Organizations of Firms
Section VI - Accuracy of RFQ and Related Documents
Section VII – Vendex Submission
Updated Vendex Submission in file with Mayor’s Office of Contracts
Section VII - Costs of SOQ Preparation and Selection Process
Section IX- Evaluation Criteria
Technical Qualifications and Experience
Three Projects (similar in nature , size and scope)
‒ Completed within the past 7 years or On-going Projects more than 50% complete
Firms’ Team Qualifications
Organizational Chart of Key Personnel and Demonstrate Experience
Form A and Form B - Project Experience Forms
Identified Project Manager must be assigned full-time to the contract and will not be assigned directly or indirectly to other projects or other corporate office functions.
General Description of Subcontractors (identify trade and % subcontracted)
15
Requirements for Pre-Qualification
Quality Assurance and Quality Control
Quality of Project Delivery and Commitment to Quality
Quality Control Manual from one of the three referenced Projects
Financial and Contract Capability
Annual financial Statements (most recent 3 years)
Certification of bonding agency to issues bonding as security for the Firms’ performance for $200,000,000 of construction
List of liabilities undertaken by the firm
Filed or pending litigation
Compliance with EEO, Anti-discrimination Laws and WMBE Participation
Compliance with Local Law 34
Doing Business Data Form (Attachment C)
16
Requirements for Pre-Qualification
Section IX.E - Environmental Health and Safety
Environmental Health and Safety is the number one priority of the DEP. DEP’s goal is to manage and operate the safest and most environmentally compliant Agency in the United States. As a result, the Firm’s EHS track record is of upmost importance in the pre-qualification process.
A Firm may be disapproved for prequalification as a Firm if:
The contractor’s most recent available intrastate EMR is greater than 1.0, or
The contractor has received a Willful OSHA citation following the work-related death of an employee within the past 3 years, or
The contractor has received 3 or more Repeat or Willful OSHA citations in any one year period within the past 5 years.
The Firm shall submit the following information (See Form C):
a. Worker’s Compensation Experience Modification Rate
b. Accident and Illness Statistics
c. Regulatory Violations
d. Resources
e. Program Elements
17
DEP EHS Strategic Goals
Measure EHS performance and demand success
Integrate EHS compliance into every aspect of DEP operations and construction
Ensure effective EHS training and education for all employees
Encourage open, frequent and candid communication about EHS issues
“Our goal is to run the safest operations and capital program in the country with the best environmental compliance record of any
large water and wastewater utility.”
18
BEDC Core Values
Safety
Client Services
QualityBudget
Schedule Everyday, everyone goes home safe on
BEDC Projects
19
BEDC’s Guiding Principles
To support the DEP’s EHS goals, BEDC has embraced the following guiding principles:
o All incidents can be prevented
o Our EHS performance can be continually improved
o Management is accountable for EHS performance
o Preventing incidents and managing our environmental impacts make for good project delivery
20
BEDC EHS Requirements
Highlights of top BEDC EHS requirements:
Contractor and subcontractors have a pro-active Corporate EHS program
Must be knowledgeable and comply with all BEDC SOPs, EHS Standards, and applicable DEP EHS Policies and Procedures (found on e-Builder Knowledge Reservoir) in addition to all city, state and federal laws, rules and regulations
Must attend Orientation and EHS Standards training
Submit Safety Professional, Environmental Professional & one or more (if >100 workers) full time EHS Representative
Submit Environmental, Health and Safety Plan (EHASP)
Effectively manage subcontractors EHS performance
21
BEDC EHS Requirements
Obtain and comply with environmental permits including air, water, wastewater, wetland, petroleum/chemical bulk storage
Appropriate handling of waste streams
Required hazardous waste documentation and annual reporting
Spill prevention and preparedness program
Chemical inventory tracking and EPCRA reporting
Develop and Implement Emergency Action Plans/Fire Protection Plans
NYC – Comply with NYCDOB Building Code
SMOKING IS NOT PERMITTED ON ALL CONSTRUCTION SITES
22
Submission of Statement of Qualifications
Interested Firms shall submit a Statement of Qualifications (“SOQ”) to the DEP by 4:00 pm (EST) on January 4, 2016 to the following address:
Joseph Vaicels
Department of Environmental Protection
59-17 Junction Boulevard, 17th Floor Bid Room
Flushing, New York 11373
Firms are encouraged to submit applications earlier than the final due date.
One (1) disc (CD or DVD) and four (4) hardcopies of the full SOQ shall be submitted
The envelopes or packages shall be labeled: Contractor SOQ – Contract NR-38: North River WWTP Cogeneration & Electrification.
Late submissions will not be considered.
The SOQ shall be typed on 8½" x 11" paper using no less than 11 point font with 1” margins.
The SOQ may be stapled or bound in 3-ring binder; 19-hole, comb-type binding, or other binding format that can be easily disassembled.
23
Questions
23
All questions regarding the pre-qualification process shall be sent to in
writing to [email protected] no later than 4:00 PM (EST) on
December 14, 2015.