23
North River Wastewater Treatment Plant Cogeneration and Electrification Project Contract NR38 Prequalification Presubmission Meeting December 8, 2015

North River Wastewater Treatment Plant and Electrification

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

North River Wastewater Treatment Plant Cogeneration and Electrification Project 

Contract NR‐38 Prequalification Pre‐submission Meeting

December 8, 2015

2

Agenda

Topic Presenter Allocated TimeIntroductions and Sign-in Frank Giardina 1:00 pm – 1:05 pmOverall Project Schedule Frank Giardina 1:05 pm – 1:15 pmProject Scope Mike Johnson 1:15 pm – 1:30 pmRequirements for Prequalification Joe Vaicels 1:30 pm – 1:45 pmEnvironmental Health and Safety Bruce Ehrich 1:45 pm – 2:00 pmSubmission of Statement of Qualification Package

Frank Giardina 2:00 pm – 2:15 pm

Questions 2:15 pm – 2:20 pm

3

Schedule

Activity DateIssuance of RFQ November 30, 2015 Pre-SOQ Meeting December 8, 2015

Last Day of Questions December 14, 2015 SOQ Submission January 4, 2016

Notice of Approval/Denial of Prequalification

February 24, 2016

Issuance of Bid Package March 1, 2016 Bid Submission April 12, 2016

Construction Commencement October 10, 2016 Construction Substantial Completion February 7, 2020

4

North River WWTP

Existing primary and secondary treatment facility serving 550,000 customers on Manhattan’s west side.

The facility was completed in several phases which went operational between 1986 and 1991.

Riverbank State Park is located on top of the wastewater treatment plant; the entire structure covers 28 acres.

The plant is constructed on 2,300 drilled piers over the Hudson River, supporting 95% of the platform

5

Aerial Photo

5

6

Liquid Stream Processes

Full Secondary Treatment Plant with a Design Dry Weather Capacity of 170 mgd:

Preliminary Treatment: Screenings, Influent Pumping and Flow Measurement

Primary Treatment: Primary Tanks, Primary Scum Removal, Primary Sludge Removal

Secondary Treatment: Activated Sludge and Secondary Tanks

Disinfection: Sodium Hypochlorite

7

Solids Stream Processes

Screenings Dewatering and Disposal to Landfill

Primary Sludge Pumping, Degritting and Disposal of Solids

Primary, Secondary and Return Sludge Pumping

Anaerobic Digestion of Primary Sludge and Waste Activated Sludge

Digested Sludge Hauled off Site via Barge

Digester Gas used for alternative fuel source

8

Project Scope

Installation of five 3.0 MW Spark-Ignited, Lean Burn Reciprocating Engine Generators Pre-Selected Unit: GE-Jenbacher Provide Power & Heat to the Facility Reduce Air Emissions Operate on either Natural Gas, Digester Gas or Blend of the two Rated for 3.0 MW at 4,160 volts and designed to operate in parallel with

the operation of Con Ed power feed via sync bus N+1 Configuration at average cogeneration demand while operating at

75% load factor

Engine Generators to be installed at current Blower Engine locations NR-46 is providing new high-speed turbo-blowers for Process Air as an

Advanced Contract Blower No 6 will remain in operation Removal of 5 existing Process Air Blowers and Engines

9

Project Scope

Engine Generator Auxiliary Equipment & Operation Engine exhaust piping outfitted with Oxidation Catalysts & Silencers and

utilize the existing exhaust stacks for the MSP Engines. Engine Heat Recovery system being modified extensively.

Sixth Main Sewage Pump (MSP) added to the lineup of five Existing MSPs on Level -43. N+1 Redundancy during construction N+1+1 Redundancy upon construction completion Located north of MSP 1601 New Suction & Discharge Piping with tie-ins at the Wet Well and

Forcemain Discharge Piping matches that of existing five. Suction piping will include

Straightening Vanes

10

Project Scope

MSP Drive System Existing five MSP Engines, Speed Reducer and Intermediate Lineshafting

will be removed and replaced 1,850 HP, 900 RPM Motors and Speed Reducers located on existing

supports for MSP 1601 through MSP 1605. New Foundation for MSP 1606 – enclose a portion of the existing large equipment hatch

Provided with WRIM & Resistor Bank Controllers to achieve 5 distinct speeds to cover full range of flow

Max flow of 355 mgd (340 mgd influent & 15 mgd recycle)

Digester Gas Compressors Sizing of N+2 units will be based on requirements of engines without gas

conditioning equipment.

11

Project Scope

Upgrade HVAC for Main Building to comply with NFPA 820 Electrical Improvements/Design

Coordination with Con Edison for the Service Feeders Upgrade Construction of two new Electric Rooms, Nos. 19 and 20 to house 4.16kV

switchgear lineup New batteries complete with auxiliary equipment & accessories for new

switchgear lineup Upgrade Life Safety Systems to comply with current codes:

Fire Alarm System Fire Sprinkler System Gas Detection System

Flood Protection measures to protect the facility against climate change impacts Raised Wall Openings Floor Expansion Joint Repairs

New Secondary Emergency Waste Gas Burner adjacent to the Sludge Storage Tank

12

Overview of the Work – Level +28LEVEL +28: Engine Generators & MSP Drives

13

Overview of the Work – MSP 1606 Design

LEVEL -43: MSP 1606, Suction & Discharge Piping

14

Requirements for Pre-Qualification Section V- Organizations of Firms

Section VI - Accuracy of RFQ and Related Documents

Section VII – Vendex Submission

Updated Vendex Submission in file with Mayor’s Office of Contracts

Section VII - Costs of SOQ Preparation and Selection Process

Section IX- Evaluation Criteria

Technical Qualifications and Experience

Three Projects (similar in nature , size and scope)

‒ Completed within the past 7 years or On-going Projects more than 50% complete

Firms’ Team Qualifications

Organizational Chart of Key Personnel and Demonstrate Experience

Form A and Form B - Project Experience Forms

Identified Project Manager must be assigned full-time to the contract and will not be assigned directly or indirectly to other projects or other corporate office functions.

General Description of Subcontractors (identify trade and % subcontracted)

15

Requirements for Pre-Qualification

Quality Assurance and Quality Control

Quality of Project Delivery and Commitment to Quality

Quality Control Manual from one of the three referenced Projects

Financial and Contract Capability

Annual financial Statements (most recent 3 years)

Certification of bonding agency to issues bonding as security for the Firms’ performance for $200,000,000 of construction

List of liabilities undertaken by the firm

Filed or pending litigation

Compliance with EEO, Anti-discrimination Laws and WMBE Participation

Compliance with Local Law 34

Doing Business Data Form (Attachment C)

16

Requirements for Pre-Qualification

Section IX.E - Environmental Health and Safety

Environmental Health and Safety is the number one priority of the DEP. DEP’s goal is to manage and operate the safest and most environmentally compliant Agency in the United States. As a result, the Firm’s EHS track record is of upmost importance in the pre-qualification process.

A Firm may be disapproved for prequalification as a Firm if:

The contractor’s most recent available intrastate EMR is greater than 1.0, or

The contractor has received a Willful OSHA citation following the work-related death of an employee within the past 3 years, or

The contractor has received 3 or more Repeat or Willful OSHA citations in any one year period within the past 5 years.

The Firm shall submit the following information (See Form C):

a. Worker’s Compensation Experience Modification Rate

b. Accident and Illness Statistics

c. Regulatory Violations

d. Resources

e. Program Elements

17

DEP EHS Strategic Goals

Measure EHS performance and demand success

Integrate EHS compliance into every aspect of DEP operations and construction

Ensure effective EHS training and education for all employees

Encourage open, frequent and candid communication about EHS issues

“Our goal is to run the safest operations and capital program in the country with the best environmental compliance record of any

large water and wastewater utility.”

18

BEDC Core Values

Safety

Client Services

QualityBudget

Schedule Everyday, everyone goes home safe on

BEDC Projects

19

BEDC’s Guiding Principles

To support the DEP’s EHS goals, BEDC has embraced the following guiding principles:

o All incidents can be prevented

o Our EHS performance can be continually improved

o Management is accountable for EHS performance

o Preventing incidents and managing our environmental impacts make for good project delivery

20

BEDC EHS Requirements

Highlights of top BEDC EHS requirements:

Contractor and subcontractors have a pro-active Corporate EHS program

Must be knowledgeable and comply with all BEDC SOPs, EHS Standards, and applicable DEP EHS Policies and Procedures (found on e-Builder Knowledge Reservoir) in addition to all city, state and federal laws, rules and regulations

Must attend Orientation and EHS Standards training

Submit Safety Professional, Environmental Professional & one or more (if >100 workers) full time EHS Representative

Submit Environmental, Health and Safety Plan (EHASP)

Effectively manage subcontractors EHS performance

21

BEDC EHS Requirements

Obtain and comply with environmental permits including air, water, wastewater, wetland, petroleum/chemical bulk storage

Appropriate handling of waste streams

Required hazardous waste documentation and annual reporting

Spill prevention and preparedness program

Chemical inventory tracking and EPCRA reporting

Develop and Implement Emergency Action Plans/Fire Protection Plans

NYC – Comply with NYCDOB Building Code

SMOKING IS NOT PERMITTED ON ALL CONSTRUCTION SITES

22

Submission of Statement of Qualifications

Interested Firms shall submit a Statement of Qualifications (“SOQ”) to the DEP by 4:00 pm (EST) on January 4, 2016 to the following address:

Joseph Vaicels

Department of Environmental Protection

59-17 Junction Boulevard, 17th Floor Bid Room

Flushing, New York 11373

Firms are encouraged to submit applications earlier than the final due date.

One (1) disc (CD or DVD) and four (4) hardcopies of the full SOQ shall be submitted

The envelopes or packages shall be labeled: Contractor SOQ – Contract NR-38: North River WWTP Cogeneration & Electrification.

Late submissions will not be considered.

The SOQ shall be typed on 8½" x 11" paper using no less than 11 point font with 1” margins.

The SOQ may be stapled or bound in 3-ring binder; 19-hole, comb-type binding, or other binding format that can be easily disassembled.

23

Questions

23

All questions regarding the pre-qualification process shall be sent to in

writing to [email protected] no later than 4:00 PM (EST) on

December 14, 2015.