Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
80t
ABN: 46 114 162 597
Prepared by
Wilkinson Murray Pty Limited
April 2013
Specialist Consultant Studies Compendium Volume 1, Part 1
Noise, Vibration and Blasting
Assessment
ABN: 46 114 162 597
Noise, Vibration and Blasting
Assessment
Prepared for: R.W. Corkery & Co. Pty Limited 1st Floor, 12 Dangar Road PO Box 239 BROOKLYN NSW 2083
Tel: (02) 9985 8511 Fax: (02) 9985 8208 Email: [email protected]
On behalf of: Gloucester Resources Limited Level 37, Riverside Centre
123 Eagle Street BRISBANE QLD 4000
Tel: (07) 3006 1830 Fax: (07) 3006 1840 Email: [email protected]
Prepared by: Wilkinson Murray Pty Limited Level 4, 272 Pacific Highway
CROWS NEST NSW, 2065
Tel: (02) 9437 4611 Fax: (02) 9437 4393 Email: [email protected]
April 2013
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 2
DOCUMENT CONTROL
Version Status Date Prepared By Reviewed By
A Draft 17 September 2012 Adam Bioletti Rob Bullen
B Draft 5 October 2012 Adam Bioletti
C Draft 27 October 2012 Adam Bioletti Rob Bullen
D Final for Client Review 30 November 2012 Adam Bioletti Rob Bullen
E Final for Adequacy 11 December 2012 Adam Bioletti Rob Bullen
F Final for Client Review 21 February 2013 Adam Bioletti Rob Bullen
G Final 5 March 2013 Adam Bioletti/
Rob Bullen Barry Murray
Note All materials specified by Wilkinson Murray Pty Limited have been selected solely on the basis of acoustic performance. Any other properties of these materials, such as fire rating, chemical properties etc. should be checked with the suppliers or other specialised bodies for fitness for a given purpose. The information contained in this document produced by Wilkinson Murray is solely for the use of the client identified on the front page of this report. Our client becomes the owner of this document upon full payment of our Tax Invoice for its provision. This document must not be used for any purposes other than those of the document’s owner. Wilkinson Murray undertakes no duty to or accepts any responsibility to any third party who may rely upon this document.
Quality Assurance We are committed to and have implemented AS/NZS ISO 9001:2008 “Quality Management Systems – Requirements”. This management system has been externally certified and Licence No. QEC 13457 has been issued.
AAAC This firm is a member firm of the Association of Australian Acoustical Consultants and the work here reported has been carried out in accordance with the terms of that membership.
Celebrating 50 Years in 2012 Wilkinson Murray is an independent firm established 50 years ago originally as Carr & Wilkinson. In 1976 Barry Murray joined founding partner Roger Wilkinson and the firm adopted the name which remains today. From a successful operation in Australia, Wilkinson Murray expanded its reach into Asia by opening a Hong Kong office early in 2006. 2010 saw the introduction of our Queensland office and 2011 the introduction of our Orange office to service a growing client base in these regions. From these offices, Wilkinson Murray services the entire Asia-Pacific region.
This Copyright is included for the protection of this document
COPYRIGHT
© Wilkinson Murray Pty Limited, 2013 and
© Gloucester Resources Limited, 2013
All intellectual property and copyright reserved.
Apart from any fair dealing for the purpose of private study, research, criticism or review, as permitted under the Copyright Act, 1968, no part of this report may be reproduced, transmitted, stored in a retrieval system or adapted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without written permission. Enquiries should be addressed to Wilkinson Murray Pty Limited.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED
Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
CONTENTS Page
1 - 3
EXECUTIVE SUMMARY......................................................................................................................... 1-9
ES.1 INTRODUCTION .............................................................................................................. 1-9
ES.2 NOISE ENVIRONMENT ................................................................................................... 1-9
ES.3 OPERATIONAL NOISE ASSESSMENT CRITERIA ...................................................... 1-11
ES.4 ASSESSMENT METHODOLOGY ................................................................................. 1-11
ES.5 NOISE MODELLING ...................................................................................................... 1-12
ES.5.1 Noise Assessment Scenarios ............................................................................ 1-12
ES.5.2 Meteorological Data used for Noise Predictions ............................................... 1-13
ES.5.3 Noise Affectation Zone and Noise Management Zone ..................................... 1-13
ES.5.4 Operational Noise Modelling Key Outcomes ..................................................... 1-16
ES.6 CUMULATIVE NOISE ASSESSMENT .......................................................................... 1-16
ES.7 SLEEP DISTURBANCE ................................................................................................. 1-17
ES.8 PROJECT CONSTRUCTION NOISE ............................................................................ 1-17
ES.9 BLASTING ...................................................................................................................... 1-17
ES.10 ROAD TRAFFIC NOISE ................................................................................................. 1-17
ES.11 RAIL NOISE ................................................................................................................... 1-18
ES.12 NOISE MANAGEMENT MEASURES ............................................................................ 1-18
ES.13 CONCLUSION................................................................................................................ 1-19
GLOSSARY OF ACOUSTIC AND BLASTING TERMS ...................................................................... 1-20
ACRONYMS .......................................................................................................................................... 1-22
1. INTRODUCTION ......................................................................................................................... 1-23
1.1 SCOPE ........................................................................................................................... 1-23
1.2 OBJECTIVES OF THIS ASSESSMENT ........................................................................ 1-23
2. PROJECT DESCRIPTION .......................................................................................................... 1-29
2.1 PROJECT OVERVIEW .................................................................................................. 1-29
2.2 PROJECT TIMETABLE .................................................................................................. 1-31
2.3 ROAD TRAFFIC ............................................................................................................. 1-32
2.3.1 Site Establishment and Construction Phase ..................................................... 1-32
2.3.2 Operations ......................................................................................................... 1-33
2.4 BLASTING ...................................................................................................................... 1-33
2.5 PRODUCT DISPATCH .................................................................................................. 1-33
2.6 HOURS OF OPERATION .............................................................................................. 1-34
2.6.1 Site Establishment and Construction Hours ...................................................... 1-35
3. NOISE RECEPTORS AND SURROUNDING LAND USES ...................................................... 1-36
4. EXISTING NOISE ENVIRONMENT............................................................................................ 1-44
4.1 NOISE SOURCES ......................................................................................................... 1-44
4.2 BACKGROUND NOISE MONITORING ......................................................................... 1-44
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
CONTENTS Page
1 - 4
4.3 NOISE MEASUREMENT PROCEDURES ..................................................................... 1-45
4.3.1 Unattended Continuous Noise Logging ............................................................. 1-45
4.3.2 Operator-attended Noise Measurements .......................................................... 1-47
4.4 INSTRUMENTATION AND MEASUREMENT PARAMETERS ..................................... 1-47
4.5 UNATTENDED NOISE MEASUREMENTS ................................................................... 1-48
4.6 ATTENDED NOISE MEASUREMENTS ........................................................................ 1-49
5. OPERATIONAL NOISE ASSESSMENT CRITERIA .................................................................. 1-50
5.1 INTRUSIVENESS AND AMENITY CRITERIA ............................................................... 1-50
5.2 ASSESSMENT METHODOLOGY ................................................................................. 1-54
5.3 CRITERION FOR THE PREVENTION OF SLEEP DISTURBANCE WITHIN RESIDENCES ................................................................................................................ 1-54
5.4 WORLD HEALTH ORGANISATION CRITERIA TO PROTECT THE HEALTH OF THE SURROUNDING COMMUNITY ............................................................................. 1-55
5.5 CRITERIA FOR THE ASSESSMENT OF LOW FREQUENCY NOISE (INCLUDING INFRASOUND) ............................................................................................................... 1-56
5.5.1 Introduction ........................................................................................................ 1-56
5.5.2 DEFRA Approach .............................................................................................. 1-57
5.5.3 A Simple Outdoor Criterion ................................................................................ 1-57
5.5.4 Adopted Low Frequency Noise Approach ......................................................... 1-58
6. OPERATIONAL NOISE ASSESSMENT .................................................................................... 1-59
6.1 NOISE MODELLING METHODOLOGY ......................................................................... 1-59
6.1.1 Noise Assessment Scenarios ............................................................................ 1-59
6.1.2 Meteorological Data used for Noise Predictions ............................................... 1-62
6.2 INVESTIGATION OF FEASIBLE AND REASONABLE NOISE MITIGATION MEASURES .................................................................................................................... 1-65
6.3 FLEET LIST AND SOUND POWER LEVELS ................................................................ 1-66
6.4 PREDICTED OPERATIONAL NOISE LEVELS ............................................................. 1-67
6.4.1 Introduction ........................................................................................................ 1-67
6.4.2 Mining Operations .............................................................................................. 1-68
6.4.3 Overland Conveyor .......................................................................................... 1-106
6.4.4 Rail Load-out Facility ....................................................................................... 1-109
6.4.5 Combined Mining, Conveying and Rail Load-out Operations ......................... 1-112
6.4.6 Noise Levels in Gloucester Township ............................................................. 1-113
6.4.7 Noise Affectation Zone and Noise Management Zone .................................... 1-113
6.5 LOW FREQUENCY NOISE ASSESSMENT ................................................................ 1-115
6.6 CUMULATIVE NOISE ASSESSMENT ........................................................................ 1-116
6.7 PRIVATELY-OWNED LAND NOISE ASSESSMENT .................................................. 1-117
6.8 NEW MINE NOISE ....................................................................................................... 1-118
6.9 POTENTIAL FOR SLEEP DISTURBANCE WITHIN RESIDENCES ........................... 1-119
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED
Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
CONTENTS Page
1 - 5
6.10 NOISE MANAGEMENT MEASURES .......................................................................... 1-119
6.10.1 Noise Management Zone ................................................................................ 1-119
6.10.2 Noise Affectation Zone ................................................................................. 1-120
6.10.3 General Management Measures ..................................................................... 1-120
6.10.4 Noise Monitoring Requirements ...................................................................... 1-121
6.10.5 Noise Management Plan ................................................................................. 1-121
7. TRANSPORTATION NOISE AND VIBRATION ....................................................................... 1-123
7.1 ROAD TRAFFIC NOISE ............................................................................................... 1-123
7.1.1 Traffic During Site Establishment and Construction Phase ............................ 1-123
7.1.2 Traffic Throughout Operations ........................................................................ 1-123
7.1.3 Road Traffic Noise Criteria .............................................................................. 1-124
7.1.4 Road Traffic Impacts ....................................................................................... 1-124
7.1.5 Road Traffic Impacts ....................................................................................... 1-125
7.2 ROAD TRAFFIC VIBRATION ...................................................................................... 1-127
7.3 RAIL NOISE ................................................................................................................. 1-127
7.3.1 Rail Noise Criteria ............................................................................................ 1-127
7.3.2 Criteria for Cumulative Rail Noise ................................................................... 1-128
7.3.3 Rail Noise Impacts ........................................................................................... 1-129
8. CONSTRUCTION NOISE ......................................................................................................... 1-132
8.1 CONSTRUCTION NOISE CRITERIA .......................................................................... 1-132
8.2 PREDICTED CONSTRUCTION NOISE LEVELS ........................................................ 1-133
8.3 CONSTRUCTION MITIGATION MEASURES ............................................................. 1-134
9. BLASTING ASSESSMENT ...................................................................................................... 1-136
9.1 AIRBLAST OVERPRESSURE NOISE AND VIBRATION CRITERIA .......................... 1-136
9.1.1 Criteria for the Minimisation of Human Annoyance from Blasting ................... 1-136
9.1.2 Criteria for the Prevention of Structural Damage to Buildings ......................... 1-137
9.2 MANAGEMENT, MITIGATION AND CONTINGENCY MEASURES ........................... 1-137
9.2.1 Blasting Impacts on Residents ........................................................................ 1-137
9.2.2 Building Damage ............................................................................................. 1-138
9.2.3 Blasting Impacts on Livestock ......................................................................... 1-138
9.2.4 Rail Load-Out Facility ...................................................................................... 1-138
9.2.5 Fly Rock ........................................................................................................... 1-138
9.2.6 Cumulative Impacts ......................................................................................... 1-138
9.3 PREDICTION OF AIRBLAST OVERPRESSURE AND VIBRATION LEVELS ............ 1-139
9.4 PREDICTED OVERPRESSURE AND VIBRATION LEVELS AT RECEPTORS ........ 1-139
9.4.1 Residential Receptors ..................................................................................... 1-139
9.4.2 Building Damage ............................................................................................. 1-145
9.4.3 Livestock .......................................................................................................... 1-145
9.4.4 Vibration from Road Traffic .............................................................................. 1-146
9.4.5 Rail Load-out Facility ....................................................................................... 1-146
9.4.6 Fly Rock ........................................................................................................... 1-146
9.4.7 Cumulative Impacts ......................................................................................... 1-147
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
CONTENTS Page
1 - 6
9.5 AIRBLAST OVERPRESSURE AND VIBRATION MITIGATION .................................. 1-147
9.6 BLAST MONITORING .................................................................................................. 1-147
10. CONCLUSION .......................................................................................................................... 1-148
10.1 GENERAL ..................................................................................................................... 1-148
10.2 PROJECT OPERATIONAL NOISE .............................................................................. 1-148
10.3 CUMULATIVE NOISE .................................................................................................. 1-150
10.4 SLEEP DISTURBANCE ............................................................................................... 1-150
10.5 PROJECT CONSTRUCTION NOISE .......................................................................... 1-150
10.6 BLASTING .................................................................................................................... 1-150
10.7 ROAD TRAFFIC NOISE ............................................................................................... 1-151
10.8 RAIL NOISE .................................................................................................................. 1-151
11. REFERENCES .......................................................................................................................... 1-152 APPENDICES
Appendix 1 Statistical Ambient Noise Levels .................................................................................. 1-155
Appendix 2 Predicted Noise Level Tables ....................................................................................... 1-289
Appendix 3 Predicted Cumulative Noise Contours ......................................................................... 1-357
FIGURES
Figure ES-1 Surrounding Noise-Sensitive Receptors ........................................................................ 1-10
Figure 1.1 Proposal Location ........................................................................................................... 1-24
Figure 2.1 Proposed Site Layout ..................................................................................................... 1-30
Figure 3.1 Surrounding Noise-Sensitive Receptors ........................................................................ 1-37
Figure 3.2 Noise-Sensitive Receptors in Gloucester Township ...................................................... 1-39
Figure 4.1 Noise Monitoring Locations ............................................................................................ 1-46
Figure 5.1 Noise Catchment Areas .................................................................................................. 1-51
Figure 6.1 Percentage Occurrence of Varying Strength Temperature Inversions .......................... 1-63
Figure 6.2 Percentage Occurrence of Temperature Inversions 3°C/100m or Greater During Winter .................................................................................................................. 1-64
Figure 6.3 Year 0.5 Day Plant Layout .............................................................................................. 1-70
Figure 6.4 Year 0.5 Day – Predicted 10% Exceedance .................................................................. 1-71
Figure 6.5 Year 0.5 Evening Plant Layout ....................................................................................... 1-72
Figure 6.6 Year 0.5 Evening – Predicted 10% Exceedance............................................................ 1-73
Figure 6.7 Year 2.5 Day Plant Layout .............................................................................................. 1-76
Figure 6.8 Year 2.5 Day – Predicted 10% Exceedance .................................................................. 1-77
Figure 6.9 Year 2.5 Evening Plant Layout ....................................................................................... 1-78
Figure 6.10 Year 2.5 Evening – Predicted 10% Exceedance............................................................ 1-79
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED
Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
CONTENTS Page
1 - 7
Figure 6.11 Year 2.5 Night Plant Layout ........................................................................................... 1-80
Figure 6.12 Year 2.5 Night – Predicted 10% Exceedance ................................................................ 1-81
Figure 6.13 Year 4.25 Day Plant Layout ........................................................................................... 1-84
Figure 6.14 Year 4.25 Day – Predicted 10% Exceedance ................................................................ 1-85
Figure 6.15 Year 4.25 Evening Plant Layout ..................................................................................... 1-86
Figure 6.16 Year 4.25 Evening – Predicted 10% Exceedance ......................................................... 1-87
Figure 6.17 Year 4.25 Night Plant Layout ......................................................................................... 1-88
Figure 6.18 Year 4.25 Night – Predicted 10% Exceedance .............................................................. 1-89
Figure 6.19 Year 7.75 Day Plant Layout ........................................................................................... 1-92
Figure 6.20 Year 7.75 Day – Predicted 10% Exceedance ................................................................ 1-93
Figure 6.21 Year 7.75 Evening Plant Layout ..................................................................................... 1-94
Figure 6.22 Year 7.75 Evening – Predicted 10% Exceedance ......................................................... 1-95
Figure 6.23 Year 7.75 Night Plant Layout ......................................................................................... 1-96
Figure 6.24 Year 7.75 Night – Predicted 10% Exceedance .............................................................. 1-97
Figure 6.25 Year 13 Day Plant Layout ............................................................................................ 1-100
Figure 6.26 Year 13 Day – Predicted 10% Exceedance ................................................................. 1-101
Figure 6.27 Year 13 Evening Plant Layout ...................................................................................... 1-102
Figure 6.28 Year 13 Evening – Predicted 10% Exceedance .......................................................... 1-103
Figure 6.29 Year 13 Night Plant Layout .......................................................................................... 1-104
Figure 6.30 Year 13 Night – Predicted 10% Exceedance ............................................................... 1-105
Figure 6.31 Year 4.25 Night Concurrent Mining and Conveyor Operations – Predicted 10% Exceedance .................................................................................................................. 1-108
Figure 6.32 Year 4.25 Night with Concurrent Mining and RLF Operations – Predicted 10% Exceedance .................................................................................................................. 1-111
Figure 7.1 Residences Affected by Cumulative Rail Noise ........................................................... 1-131 TABLES
Table ES-1 Proposal Specific Criteria Summary .............................................................................. 1-11
Table ES-2 Project Noise Impact Assessment Methodology ............................................................ 1-12
Table ES-3 Summary of Potential Exceedances within Noise Management and Affectation Zones .................................................................................................... 1-14
Table ES-4 Summary of Highest Potential Exceedances throughout the Nominated Operational Scenarios .................................................................................................... 1-15
Table 1.1 Coverage of Noise-related Matters ................................................................................ 1-25
Table 2.1 Estimated Annual Overburden and ROM Coal Production ............................................ 1-32
Table 2.2 Traffic Movements During Site Establishment and Construction Phase........................ 1-32
Table 2.3 Operational Hours .......................................................................................................... 1-34
Table 2.4 Site Establishment and Construction Hours ................................................................... 1-35
Table 3.1 Receptors Considered in this Assessment (co-ordinates are MGA, zone 56) ............... 1-40
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
CONTENTS Page
1 - 8
Table 4.1 Noise Monitoring Locations ............................................................................................ 1-45
Table 4.2 Summary of Unattended Noise Monitoring Results ....................................................... 1-48
Table 5.1 Intrusiveness Criteria For Privately-owned Receptors ................................................... 1-50
Table 5.2 Proposal Specific Noise Criteria for Privately-owned Receptors ................................... 1-53
Table 5.3 Project Noise Impact ...................................................................................................... 1-54
Table 5.4 Proposed Reference Curve for Assessment of Low-Frequency Noise .......................... 1-57
Table 5.5 Outdoor Criteria for the Assessment of Low Frequency Noise ...................................... 1-58
Table 6.1 Indicative Mobile Equipment List .................................................................................... 1-66
Table 6.2 Active Noise Management Strategy Year 0.5 ................................................................ 1-69
Table 6.3 Year 0.5 Noise Levels for Receptors where Exceedances are Predicted ..................... 1-74
Table 6.4 Active Noise Management Strategy Year 2.5 ................................................................ 1-75
Table 6.5 Year 2.5 Noise Levels for Receptors where Exceedances are Predicted ..................... 1-82
Table 6.6 Active Noise Management Strategy Year 4.25 .............................................................. 1-83
Table 6.7 Year 4.25 Noise Levels for Receptors where Exceedances are Predicted ................... 1-90
Table 6.8 Active Noise Management Strategy Year 7.75 .............................................................. 1-91
Table 6.9 Year 7.75 Noise Levels for Receptors where Exceedances are Predicted ................... 1-98
Table 6.10 Active Noise Management Strategy Year 13 ................................................................. 1-99
Table 6.11 Year 13 Noise Levels for Receptors where Exceedances are Predicted .................... 1-106
Table 6.12 Noise Predictions with Conveyor Operating ................................................................. 1-107
Table 6.13 Noise Predictions with Concurrent Mining and Rail Load-out Facility Operations ....... 1-110
Table 6.14 Summary of Potential Exceedances under Adverse Meteorological Conditions ......... 1-113
Table 6.15 LAeq,Period Cumulative Noise Predictions – Year 4.25 .................................................... 1-117
Table 7.1 Traffic Movements* During Site Establishment and Construction Phase .................... 1-123
Table 7.2 Traffic Movements* During Site Mine Operations ........................................................ 1-123
Table 7.3 Criteria for Traffic Noise – Residences ......................................................................... 1-124
Table 7.4 Existing Average Weekday Traffic Volumes ................................................................ 1-124
Table 7.5 Criteria for Traffic Noise – Residences ......................................................................... 1-125
Table 7.6 Predicted Road Traffic Noise Levels at the Nearest Receiver Setback ....................... 1-126
Table 7.7 EPA Rail Noise Assessment Trigger Levels ................................................................ 1-128
Table 7.8 Train Numbers and Rail Noise Levels at 15m .............................................................. 1-130
Table 8.1 Noise at Residences using Quantitative Assessment .................................................. 1-133
Table 9.1 Predicted Blasting Overpressure and Vibration 5% Exceedance Levels ..................... 1-140
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 9
EXECUTIVE SUMMARY
ES.1 INTRODUCTION
The Site of Rocky Hill Coal Project (“the Proposal”) is located approximately 3.5 to 7km south-
east of the Gloucester urban area. It is bordered by Waukivory Road to the north, the Avon
River and Waukivory Creek to the west and south, and the Mograni Range to the east.
The Proposal comprises four principal components, namely:
1. four separate and/or contiguous open cut pits and a coal handling and
preparation plant (CHPP) within the Mine Area;
2. an overland conveyor for transporting product coal to the Rail Load-out Facility.
The overland conveyor is located within a 50m wide Overland Conveyor Corridor;
3. a Rail Load-out Facility (RLF) incorporating a rail loop and two coal storage bins;
and
4. two Power Line Corridors incorporating a re-located 132kV power line and a new
11kV power line external to the Mine Area.
This assessment addresses potential noise and blasting impacts associated with the Proposal.
ES.2 NOISE ENVIRONMENT
Noise which is currently audible at the residences surrounding the Site is attributed to a range
of sources including:
traffic on local roads and The Bucketts Way;
occasional trains on the North Coast Railway;
domestic noises such as lawn mowers;
rural noises such as tractors, insects and birds;
wind in the trees;
livestock/vehicles on properties and at the Gloucester Livestock Exchange
Centre;
a saw mill near the intersection of Jacks Road and The Bucketts Way; and
occasional light aircraft using the Gloucester airfield.
Operator-attended and unattended noise monitoring was undertaken over four periods
between July 2010 and July 2012 in order to establish the Rating Background noise level
(RBL).
The results of the monitoring established that the Site is located in a typical rural area with few
noise sources and generally low noise levels, particularly background noise levels. Ambient
noise levels in the vicinity of The Bucketts Way (Locations 11, 12 and 14 in Figure ES-1) were
elevated due to traffic noise. Within Gloucester township, daytime noise levels were
marginally above those outside the township, but generally below those at locations with
exposure to higher speed traffic on The Buckets Way. Evening and night-time noise levels
were generally consistent across all locations.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 10
Figure ES-1 Surrounding Noise-Sensitive Receptors
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 11
ES.3 OPERATIONAL NOISE ASSESSMENT CRITERIA
Operational noise criteria were determined in accordance with the NSW Industrial Noise Policy
(INP). The most stringent criteria (INP Intrusiveness criteria) are expressed in terms of the unit
LAeq,15min, and are presented in Table ES-1.
Table ES-1 Proposal Specific Criteria Summary
Receptor Numbers (see Figure ES-1)
Receptor Area Description Criterion, dBA
Day Evening Night-time
21A, 21B, 24, 63, 65, 67J, 67P, 68, 70, 73, 74, 75, 76, 77, 78, 80, 81, 82, 83, 84, 85, 86, 87, 88, 90, 91, 92, 94
* 64, 66, 67A, 67B, 67C, 67D, 67E, 67F, 67G, 67H, 67I, 67K, 67L, 67M, 67N, 67O, 67Q, 69, 71, 72, 79, 89, S93, 95, 96
Exposed to Jacks Road, The Bucketts Way and some industrial noise from the nearby estate.
Similar to Monitoring Location 10.
36 35 35
98, 99, 100, 102, 103, 104, 105, 106A, 106B, 107, 108, 109, 110
* 97
Exposed to The Bucketts Way near the intersection with Jacks Road. Some existing industrial noise impacts the RBL.
Similar to Monitoring Location 11.
43 35 35
112, 113, 114, 115, 117, 118, 119, 120, 122, 123, 125, 126, 127, 128, 129, 130, 132, 133, 138, 139, 140, 159, 181B, 181C, 182B, 183, 184B
* 19B, 19C, 111, 116, 121, 124, 131, 162
Exposed to The Bucketts Way south of intersection with Jacks Road.
Similar to Monitoring Location 12.
40 35 35
All others Rural with minimal transportation noise impacting the RBL.
35 35 35
Notes: Day: the period from 7:00 am to 6:00 pm Monday to Saturday; or 8:00 am to 6:00 pm on Sundays and public holidays
Evening: the period from 6:00 pm to 10:00 pm. Night: the remaining periods.
* Denotes land which was vacant at the time of preparing this assessment but would attract the stated criteria should sensitive receptors are established on the subject land in the future.
ES.4 ASSESSMENT METHODOLOGY
The NSW Department of Planning and Infrastructure (DP&I) has historically recognised a
Noise Management Zone and a Noise Affectation Zone as defined in Table ES-2. These have
been adopted for the assessment of impacts.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 12
Table ES-2 Project Noise Impact Assessment Methodology
Assessment Criteria Noise Management Zone Noise Affectation
Zone Marginal Impact Moderate Impact
Intrusiveness
LAeq,15 minute 1 to 2 dBA above
project-specific criterion
3 to 5 dBA above project-
specific criterion
> 5 dBA above Project-
specific criterion Amenity
LAeq,Period
ES.5 NOISE MODELLING
Operational noise levels at nearby receptors have been calculated using the Environmental
Noise Model (ENM) prediction model which predicts the total noise at each receptor due to the
operation of the Proposal under a range of scenarios. The 10th percentile methodology was
used, whereby noise levels are predicted for all meteorological conditions experienced at the
Site and the 10th percentile exceedance level is reported.
A total of 161 noise-sensitive receptors were considered, being generally residences in the
area surrounding the Site. These are shown in Figure ES-1. Figure 3.2 (in the body of this
report) displays the locations of a range of noise-sensitive receptors in Gloucester township.
ES.5.1 Noise Assessment Scenarios
Noise modelling was undertaken for:
day and evening operating scenarios for Year 0.5 which effectively equates to
the site establishment and construction phase; and
day, evening and night operating scenarios for mining Years 2.5, 4.25, 7.75
and 13.
These years were chosen as they represent each of the distinct phases of the Proposal.
Each scenario was developed in consultation with the mine planner to reflect the nominated
production schedules and require restrictions upon equipment operations. It will remain up to
the Applicant through the real-time monitoring program to establish the exact number and type
of equipment in use at any one time and their location. In brief, there would be flexibility for
more equipment to be operated in areas with substantial topographic shielding than in areas
with lesser topographic or no shielding.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 13
ES.5.2 Meteorological Data used for Noise Predictions
The noise modelling presented in this assessment is based on meteorological data from the
GRL meteorological station for the period November 2010 through October 2011.
The modelling considered 133 meteorological conditions during the day and evening periods,
and 173 meteorological conditions during the night-time period. These conditions consisted of
the eight wind directions (45° segments); six wind speeds (0.5 m/s bins between 0m/s and
3m/s); and five temperature inversion strengths (none and 3.0°C/100m to 6.0°C/100m in
1.0°C/100m increments).
ES.5.3 Noise Affectation Zone and Noise Management Zone
Table ES-3 lists receptors predicted to be located in the respective noise affectation and
management zones.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 14
Table ES-3 Summary of Potential Exceedances within Noise Management and Affectation Zones
Scenario Time Period
Noise Management Zone Noise Affectation
Zone
1 to 2 dBA exceedance 3 to 5 dBA
exceedance > 5 dBA
exceedance
Year 0.5 (Mine Area)
Day 154, 193 6, 18, 19A
Evening 6, 56A, 154, 193 18, 19A
Year 2.5 (Mine Area)
Day 23 6
Evening 7 6, 23
Night 7 23 6
Year 2.5 (Mine Area + Conveyor)
Day 18, 23 6
Evening 7 6, 18, 23
Night 7, 56A 18, 23 6
Year 2.5 (Mine Area + RLF)
Day 56A 23 6
Evening 7, 18 6, 23, 56A
Night 7, 163A, 163B, 183, 184B 23 6, 56A
Year 4.25 (Mine Area)
Day 7 6, 23
Evening 6, 18, 56A, 163A
Night 6, 18
Year 4.25 (Mine Area + Conveyor)
Day 7 18 6, 23
Evening 6, 56A, 163A 18
Night 6, 163A 18, 56A
Year 4.25 (Mine Area + RLF)
Day 7, 18 6, 23
Evening 6, 18, 56A, 163A, 183, 184B
Night 6, 18, 154, 163A, 163B, 193 56A, 183, 184B
Year 7.75 (Mine Area)
Day 19A, 23 6, 18
Evening 18
Night 18
Year 7.75 (Mine Area + Conveyor)
Day 19A, 23, 56A 6, 18
Evening 56A 18
Night 56A 18
Year 7.75 (Mine Area + RLF)
Day 19A, 23 6, 18
Evening 184B 18
Night 183 56A, 184B 18
Year 13 (Mine Area)
Day
Evening 18
Night 18
Year 13 (Mine Area + Conveyor)
Day 6, 18
Evening 18
Night 18, 56A
Year 13 (Mine Area + RLF)
Day 6
Evening 18, 183, 184B
Night 18, 163B, 183, 193 56A, 184B
Overall Day 6, 7,18, 19A, 23, 56A, 154, 193 6, 18, 19A, 23 6, 23
Evening 6, 7, 18, 56A, 154, 163A, 183, 184B, 193 6, 18, 19A, 23, 56A
Night 6, 7, 18, 56A, 154, 163A, 163B, 183, 184B, 193
18, 23, 56A, 183, 184B
6, 18, 56A
Table ES-4 presents the highest predicted noise levels for each of the residences nominated
in Table ES-3.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 15
Table ES-4 Summary of Highest Potential Exceedances throughout the Nominated Operational Scenarios
Year 0.5 Year 2.5 Year 4.25 Year 7.75 Year 13
D E D E N D E N D E N D E N
Criterion1 35 35 35 35 35 35 35 35 35 35 35 35 35 35
Receptor No/Landowner
6 R. & L. Campbell
Mine 39 37 41 40 42 47 36 37 39 - - - - -
Mine and Conveyor - - 41 40 42 47 36 37 39 - - 36 - -
Mine & Rail Load-out Facility - - 41 40 42 47 36 37 39 - - 36 - -
7 L. Ansell/R. Murray
Mine - - - 36 37 36 - - - - - - - -
Mine and Conveyor - - - 36 37 36 - - - - - - - -
Mine & Rail Load-out Facility - - - 36 37 36 - - - - - - - -
18 J. Collins/M. Barrett
Mine 39 39 - - - - 37 36 39 39 41 - 37 36
Mine and Conveyor - - 38 39 38 38 39 40 40 40 42 37 39 40
Mine & Rail Load-out Facility - - - 36 - 36 37 36 39 39 41 - 37 37
19A A. & B. Boorer
Mine 38 39 - - - - - - 36 - - - - -
Mine and Conveyor - - - - - - - - 36 - - - - -
Mine & Rail Load-out Facility - - - - - - - - 36 - - - - -
23 S. & J. Yarnold
Mine - - 39 38 40 45 - - 37 - - - - -
Mine and Conveyor - - 39 38 40 45 - - 37 - - - - -
Mine & Rail Load-out Facility - - 39 38 40 45 - - 37 - - - - -
56A W. Fraser
Mine - 37 - - - - 36 - - - 39 - - -
Mine and Conveyor - - - - 37 - 37 38 36 36 37 - - 38
Mine & Rail Load-out Facility - - 37 38 43 - 37 39 - - 39 - - 39
154 I. & S. Jackson
Mine 37 36 - - - - - - - - - - - -
Mine and Conveyor - - - - - - - - - - - - - -
Mine & Rail Load-out Facility - - - - - - - 36 - - - - - -
163A N. Bignell
Mine - - - - - - 36 - - - - - - -
Mine and Conveyor - - - - - - 36 36 - - - - - -
Mine & Rail Load-out Facility - - - - 37 - 36 36 - - - - - -
163B N. Bignell
Mine - - - - - - - - - - - - - -
Mine and Conveyor - - - - - - - - - - - - - -
Mine & Rail Load-out Facility - - - - 37 - - 36 - - - - - 36
183 G. Channon & T. Edwards
Mine - - - - - - - - - - - - - -
Mine and Conveyor - - - - - - - - - - - - - -
Mine & Rail Load-out Facility - - - - 36 - 36 38 - - 37 - 36 37
184B D. Andrews
Mine - - - - - - - - - - - - - -
Mine and Conveyor - - - - - - - - - - - - - -
Mine & Rail Load-out Facility - - - - 36 - 36 38 - 36 38 - 36 38
193 Transport for NSW
Mine 37 37 - - - - - - - - - - - -
Mine and Conveyor - - - - - - - - - - - - - -
Mine & Rail Load-out Facility - - - - - - - 36 - - - - - 36
< Criterion Criterion to Criterion + 2dB Criterion + 3dB to Criterion + 5dB > Criterion + 5dB
Note 1. Receptors 183 and 184B have a daytime criterion of 40dB(A). All other criteria are 35dB(A) as indicated
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 16
ES.5.4 Operational Noise Modelling Key Outcomes
A total of twelve receptors are predicted to receive noise levels exceeding criteria
under any circumstances, during any phase of operations.
Four receptors (6, 18, 23 and 56A) are predicted to be within the Proposal’s
Noise Affectation Zone.
Three receptors (19A, 183 and 184B) are predicted to experience noise levels
between 3-5 dB above criteria.
Five further receptors (7, 154, 163A, 163B and 193) are predicted to experience
noise levels between 1-2 dB above criteria.
Of the above receptors, three (163B, 183 and 184B) are predicted to exceed
criteria only whilst either the Rail Load-out Facility or conveyor are operating
concurrently with the operations within the Mine Area. These sources are not
continuous and as such the presented 10% exceedance levels may overstate
their impacts. In the case of the overland conveyor, given the operational
flexibility afforded by the product coal storage at the Rail Load-out Facility, it is
unlikely that it would be regularly operated at night or during unfavourable
meteorological conditions.
Construction of the Rail Load-out Facility and overland conveyor is expected to
generate noise levels above the Noise Affected Level at seven residences.
Strategies are recommended to mitigate this potential impact.
ES.6 CUMULATIVE NOISE ASSESSMENT
The Proposal would operate to the north of the existing Stratford Coal Mine and the proposed
Stratford Extension Project and in the area of approved Gloucester Gas Project (GGP).
Hence, in a worst-case situation, receptors may potentially be exposed to noise from all three
industrial sources simultaneously. A small gravel quarry is proposed approximately 2km east
of the Mine Area within the Mograni Range. However, the scale of the proposed quarry and its
location would not contribute to any cumulative noise impact from its operation.
The Stratford Extension Project EIS Appendix C Noise and Blasting Assessment details a
cumulative noise assessment. This assessment considers Stratford Extension Project, Duralie
Coal Mine and AGL’s Gloucester Gas Project (both the central processing facility and gas
field). Levels reported for each of these sources have been used (interpolated where
necessary) to assess cumulative noise impacts in the area potentially impacted by these
projects and RHCP.
For the purpose of assessing cumulative noise impacts, the above sources were modelled with
worst-case scenarios for the Proposal. Assessment was limited to the evening and night time
period, as information could be obtained from the Stratford EIS for these time periods (a similar
level of information was not included for the day period in the Stratford EIS). This is
appropriate because the evening and night time periods attract more stringent amenity criteria
(against which cumulative impacts are assessed) and as such the day time period is far less
likely to exceed criteria.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 17
RHCP Year 4.25 (see Section 6.4.2.3) was selected for assessment of both the evening and
night-time periods as these represent worst-case scenarios for the Proposal, and they are the
most likely to align with busy scenarios for the other projects which were included in the
cumulative assessment.
In each of the above cumulative noise scenarios, the overland conveyor and the Rail Load-out
Facility have been assumed to operate up to approximately 30 hours and 17 hours per week of
the time respectively, which corresponds to the maximum typical usage for each item.
ES.7 SLEEP DISTURBANCE
Modelling of LAmax noise levels at nearby receptors was undertaken for typical instantaneous
mine-site noise sources, such as the train load-out bin and loading of trucks by excavators.
This analysis indicates that predicted noise levels would not exceed the relevant screening
criterion of 45 dBA LA1,1 minute at privately-owned receptors.
ES.8 PROJECT CONSTRUCTION NOISE
Assessment of the potential for noise impacts from construction associated with the Rail Load-
out Facility and overland conveyor indicates that eight privately-owned receptors would be
‘noise affected’ as defined in the Interim Construction Noise Guideline (DECC, 2009). No
privately-owned receptors are predicted to be ‘highly noise affected’.
ES.9 BLASTING
All blasts would be designed to ensure that both airblast overpressure and ground vibration
levels are satisfied at all privately-owned receptors. During the early stages of the Proposal,
blasts would be initiated at considerable distances from the surrounding receptors and, over
time, the design of blasts would be reviewed in conjunction with monitoring results and the site
specific site law to ensure blast criteria are satisfied as blasting approaches the closest
surrounding receptors.
If the indicative maximum anticipated maximum instantaneous charge (MIC) were used for all
blasts, including those at the closest point to each receptor, standard prediction methods
indicate a potential theoretical exceedance of airblast overpressure criteria at four privately-
owned receptors. However, airblast overpressure can be managed to achieve compliance
through blast design (e.g. decking) to reduce the MIC, as well as other techniques.
No exceedances of vibration criteria are predicted to occur at any privately-owned receptors.
Measures would be put in place to avoid flyrock impacts on livestock on surrounding
properties.
ES.10 ROAD TRAFFIC NOISE
Road traffic noise along public roads has been assessed in accordance with the NSW Road
Noise Policy.
The assessment indicates that noise generated by vehicles travelling to and from the Mine
Area on Jacks Road and Waukivory Road (north of Jacks Road) would comply with relevant
criteria detailed in the Policy.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 18
ES.11 RAIL NOISE
Rail noise has been assessed in accordance with ARTC’s Environment Protection Licence and
EPA’s requirements for rail traffic-generating development.
The rail noise assessment focuses on two sections of the North Coast Railway Line, i.e. the
section between the Rocky Hill Rail Load-out Facility and the existing Stratford Coal Mine and
the Stratford Coal Mine to the Duralie Coal Mine.
Increases in rail noise due to the Proposal would be minor and always less than 2 dBA.
However, a site-specific cumulative impact assessment procedure, determined in consultation
with the EPA, indicates that there are five additional residences at which predicted rail noise
levels would exceed the EPA’s base criterion with the proposed rail movements travelling to
and from the Rocky Hill Rail Load-out Facility, but would be slightly below the criterion
otherwise.
ES.12 NOISE MANAGEMENT MEASURES
Noise management and mitigation has been considered from the outset of the Proposal. Of
the measures considered, the following key measures are recommended to achieve the
predicted noise levels in this report.
Selection of noise-attenuated mobile equipment and/or the implementation of
additional hard controls.
Establishment of a 25m-40m high (above ROM coal pad level) western and
northern visibility barrier extending the length of the western boundary and much
of the northern boundary of the Mine Area. This measure should be
implemented as soon as practicable, with the majority of work being completed
during the site establishment and construction phase.
Progressive development of central and eastern visibility barriers ahead of
proposed overburden placement.
Progressively filling behind (to the east of) the central and eastern visibility
barriers so that shielding is maximised.
Positioning haul routes as much as possible on the northern and western sides of
open cut pits in order to maximize shielding provided by each pit.
Positioning the northern haul road in cut during Years 2.5 to 4.5 and/or behind a
barrier of subsoil to maintain an 8m vertical separation between the road surface
and the top of the barrier to minimise acoustic exposure to the north.
Positioning the southern haul road as close as possible to the western and
northern visibility barrier and, in the segment rounding south of the Main Pit,
positioning the haul road in cut and/or behind a barrier so as to create a nominal
8m vertical separation.
Establishment of 5m high (above road level) barriers on the northern and western
sides of elevated haul routes such as those along the eastern visibility barrier.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 19
Maintaining topsoil and subsoil stockpiles close to operational areas to maximise
shielding.
Implementing active noise management systems whereby reduced and/or
revised operations are undertaken during adverse meteorological conditions.
Reduced or restricted operations during evening and night-time periods.
Mitigating conveyor noise at the source through selection of quiet systems and
partially enclosing the overland conveyor in exposed locations.
Locating the train load-out bin within the Rail Load-out Facility in deep cut,
thereby maximising shielding.
Operational noise impacts would be managed on an ongoing basis according to the DP&I’s
Noise Management Zone and Noise Affectation Zone protocols which provide strategies
involving community engagement, real-time noise monitoring, investigations into acoustical
mitigation measures, and if required, acquisition of property(ies).
ES.13 CONCLUSION
The proposed Rocky Hill Coal Project incorporates a number of measures to mitigate noise
impact at nearby noise-sensitive receptors, including equipment selection, significant use of
shielding by on-site bunds and barriers, restrictions on operations during evening and night
periods, and management of activities under certain meteorological conditions.
With these controls, operational noise from the Proposal is predicted to result in exceedance of
standard noise criteria at up to twelve residences, under adverse meteorological conditions, at
some period(s) during the life of the Proposal. Measures to mitigate this potential impact
would include real-time noise monitoring linked to active strategies to manage on-site
operations; investigation of any possible additional acoustical mitigation measures; and if
required, acquisition of property(ies).
Nevertheless, there would be some times when noise also from the Proposal was audible over
a wider area, including the township of Gloucester. This is likely to be the case for existing
mining operations.
Road traffic noise generated by the development is predicted to comply with criteria
promulgated by the NSW Road Noise Policy.
Noise from rail traffic associated with the project is predicted to marginally exceed relevant
criteria at some residences. Potential mitigation measures are discussed in the body of this
report.
Noise and vibration from blasting can be controlled to within relevant criteria at all potentially-
affected receivers through the use of appropriate blast designs.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 20
GLOSSARY OF ACOUSTIC AND BLASTING TERMS
Most environments are affected by environmental noise which continuously varies, often as a result of
sources such as road traffic, industrial noise, wildlife and insects. To describe the overall noise
environment, a number of noise descriptors have been developed and these involve statistical and other
analysis of the varying noise over sampling periods, typically taken as 15 minutes. These descriptors,
which are demonstrated in the graph on the following page, are defined below.
Maximum Noise Level (LAmax) – The maximum noise level over a sample period is the maximum level,
measured on fast response, during the sample period.
dB(A) – A-weighted decibels. The ear is not as effective in hearing low frequency sounds as it is hearing
high frequency sounds. That is, low frequency sounds of the same dB level are not heard as loud as
high frequency sounds. The sound level meter replicates the human response of the ear by using an
electronic filter which is called the “A” filter. A sound level measured with this filter switched on is
denoted as dB(A). Practically all noise is measured using the A filter.
Frequency – Frequency is synonymous to pitch. Sounds have a pitch which is peculiar to the nature of
the sound generator. For example, the sound of a tiny bell has a high pitch and the sound of a bass
drum has a low pitch. Frequency or pitch can be measured on a scale in units of Hertz or Hz.
Impulsive Noise – Having a high peak of short duration or a sequence of such peaks. A sequence of
impulses in rapid succession is termed repetitive impulsive noise.
Intermittent Noise – The level suddenly drops to that of the background noise several times during the
period of observation. The time during which the noise remains at levels different from that of the
ambient is one second or more.
LA1 – The LA1 level is the noise level which is exceeded for 1% of the sample period. During the sample
period, the noise level is below the LA1 level for 99% of the time.
LA10 – The LA10 level is the noise level which is exceeded for 10% of the sample period. During the
sample period, the noise level is below the LA10 level for 90% of the time. The LA10 is a common noise
descriptor for environmental noise and road traffic noise.
LA90 – The LA90 level is the noise level which is exceeded for 90% of the sample period. During the
sample period, the noise level is below the LA90 level for 10% of the time. This measure is commonly
referred to as the background noise level.
LAeq – The equivalent continuous sound level (LAeq) is the energy average of the varying noise over the
sample period and is equivalent to the level of a constant noise which contains the same energy as the
varying noise environment. This measure is also a common measure of environmental noise and road
traffic noise.
ABL – The Assessment Background Level is the single figure background level representing each
assessment period (daytime, evening and night time) for each day. It is determined by calculating the
10th percentile (lowest 10
th percent) background level (LA90) for each period.
RBL – The Rating Background Level for each period is the median value of the ABL values for the
period over all of the days measured. There is therefore an RBL value for each period – daytime,
evening and night time.
Sound Absorption – The ability of a material to absorb sound energy through its conversion into
thermal energy.
Sound Level Meter – An instrument consisting of a microphone, amplifier and indicating device, having
a declared performance and designed to measure sound pressure level.
Sound Pressure Level – The level of noise, usually expressed in decibels, as measured by a standard
sound level meter with a microphone.
Tonal Noise – Containing a prominent frequency and characterised by a definite pitch.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 21
Typical Criterion – Refers to the criterion which applies to the majority of surrounding receivers. In the
case of operational intrusiveness noise criteria, this level has been determined to be 35dBA for the
Proposal, which also corresponds with the minimum criterion derived under the INP for this purpose.
Overpressure – Instantaneous increase in air pressure caused by blasting
Peak Particle Velocity – the measure of ground vibration caused by blasting
Typical Graph of Sound Pressure Level vs Time
20
25
30
35
40
45
50
55
60
0:00 3:00 6:00 9:00 12:00 15:00
Monitoring or Survey Period (5 sec samples)
So
und
Pre
ssu
re L
eve
l (d
BA
)
L Amax
L A1
L A10
L Aeq L
A50
L A90
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 22
ACRONYMS
The following acronyms appear throughout the report.
Terminology Description
AHD Australian Height Datum
ANFO Ammonium Nitrate Fuel Oil
CHPP Coal Handling and Preparation Plant
DP&I NSW Department of Planning and Infrastructure
EA Environmental Assessment
EIS Environmental Impact Statement
ENM Environmental Noise Model
EPA NSW Environment Protection Authority
EP&A Act NSW Environmental Planning and Assessment Act, 1979
INP NSW Industrial Noise Policy
OEH NSW Office of Environment and Heritage
Mbcm Million bank cubic metres
MIC Maximum Instantaneous Charge
Mtpa Million tonnes per annum
PPV Peak Particle Velocity
RBL Rating Background Level
ROM Run-of-mine
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 23
1 . I N T R O D U C T I O N
1.1 SCOPE
This assessment has been prepared for Gloucester Resources Limited (GRL). The Rocky Hill
Coal Project (the Proposal) is a proposed open cut mining operation located approximately 3.5
to 7km south-east of Gloucester urban area in New South Wales (NSW) as shown in
Figure 1.1.
This assessment addresses potential noise and blasting impacts associated with the Proposal.
1.2 OBJECTIVES OF THIS ASSESSMENT
The primary objective of this assessment is to investigate the potential noise and blasting
impacts associated with the Proposal by addressing the Director-General’s Requirements
(DGRs) issued by the NSW Department of Planning and Infrastructure (DP&I) on 24 April
2012. These are outlined as follows.
Noise, Vibration & Blasting – including a quantitative assessment of potential:
construction, operational and off-site transport noise impacts;
blasting impacts on people, livestock and property;
reasonable and feasible mitigation measures (including assessments of
restricted night time operations, not operating at night and not operating
during evening and night-time hours), including evidence that there are no
such measures available other than those proposed; and
monitoring and management measures, in particular real-time, attended noise
monitoring and predictive meteorological forecasting;
The NSW Environment Protection Authority (EPA), Gloucester Shire Council, NSW Health and
the Barrington-Gloucester-Stroud Preservation Alliance Inc. (BGSPA) also provided additional
matters for the noise and vibration assessment to address. These matters, together with those
identified by DP&I, and the section(s) where they are addressed in this assessment, are
outlined in Table 1.1.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 24
Figure 1.1 Proposal Location
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 25
Table 1.1
Coverage of Noise-related Matters Page 1 of 4
Government Agency
Paraphrased Requirement Relevant Section(s)
NOISE
DP&I (24/04/12)
The EIS must include a quantitative assessment of potential:
construction, operational and off-site transport noise impacts;
8, 6, 7
blasting impacts on people, livestock and property; 9
reasonable and feasible mitigation measures (including assessments of restricted night time operations, not operating at night and not operating during evening and night-time hours), including evidence that there are no such measures available other than those proposed; and
6.2
monitoring and management measures, in particular real-time, attended noise monitoring and predictive meteorological forecasting.
6.10
EPA (02/04/12)
The proposed development should be assessed using the guidelines contained in the NSW Industrial Noise Policy (EPA, 2000) and Industrial Noise Policy Application Notes, as detailed on page 2 of the Interim Construction Noise Guideline (DECC, 2009).
5
Vibration from all activities (including construction and operation) to be undertaken on the premises should be assessed using the guidelines contained in the Assessing Vibration: A Technical Guideline (DEC, 2006).
9
Blasting during the construction or operational stages of the proposed development should be demonstrated to be capable of complying with the guidelines contained in Australian and New Zealand Environment Council- Technical basis for guidelines to minimise annoyance due to blasting over pressure and ground vibration (ANZEC, 1990).
9.1
Operational noise from the proposed mine (including private haul roads and private railway lines) should be assessed using the guidelines contained in the NSW Industrial Noise Policy (EPA, 2000) and Industrial Noise Policy Application Notes.
5
The EIS must determine the rating background noise level and ambient (LAeq,Period) noise levels in accordance with the NSW Industrial Noise Policy. The evaluation should take into account the construction and operational phases of the development over the "operating" hours proposed and take into account adverse weather conditions including temperature inversions. The assessment must identify any noise sensitive locations likely to be affected by activities at the site, such as residential properties, schools, churches, and hospitals.
4.5
The EIS needs to clearly document what activities will occur at what time and assess worst case impacts of that activity occurring.
6.1.1
The project specific noise levels for the site must be determined. For each identified potentially affected receptor, this should include:
a) determination of the intrusive criterion for each identified potentially affected receptor,
5.1
b) selection and justification of the appropriate amenity category for each identified potentially affected receptor,
5.1
c) determination of the amenity criterion for each receptor, 5.1
d) determination of the appropriate sleep disturbance limit. 5.3
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 26
Table 1.1 (Cont’d)
Coverage of Noise-related Matters Page 2 of 4
Government Agency
Paraphrased Requirement Relevant Section(s)
NOISE
EPA (02/04/12)
The EIS needs to:
Include a detailed assessment of background noise levels throughout Gloucester township as well as in surrounding rural-residential estates and selected rural locations; and
4.5
Detail the number and location of residents who will likely experience a changed noise environment as a result of the proposal, that is, be able to hear mine noise for the first time.
6.8
The specific meteorologic conditions of the Gloucester Valley needs to be assessed and taken into account in the noise assessments.
6.1.2
The EIS will need to assess and demonstrate compliance with relevant noise limits in both normal and “adverse” weather conditions. The above assessment relating to the number and location of residents who will likely experience a changed noise environment also needs to consider the impacts during inversion conditions.
6.4, 6.8
The noise and vibration levels likely to be received at the most sensitive locations from construction and operational activities including road construction, blasting, pit construction, overburden handling, coal extraction, coal transportation and coal loading should be determined. Potential impacts should be determined for any identified significant adverse meteorological conditions.
6, 7, 8, 9.4
Sound power levels measured or estimated for all plant and equipment should be clearly stated and justified. The expected noise level and noise character (e.g.: tonality, impulsiveness, vibration, etc.) likely to be generated from noise sources during the following phases should be determined:
- site establishment
- construction
- operational phases, including vehicle traffic, conveyors and any rail noise generated by the proposal.
6.3
The assessment should specifically address the noise generated from coal preparation plants with particular reference to nearby areas such as Forbesdale Estate.
6.1.1.2
Cumulative noise impacts from this proposal, combined with existing and proposed mining activities nearby needs to be assessed.
6.6
Rail noise from the proposed rail loop and in particular impacts on residents and private land (without houses yet) needs to be given specific attention in the EIS. In particular noise specific to this area, such as rail wheel squeal due to the radii of the rail loop, bunching and shunting noise, needs to be considered. EPA would like to see discussion in the EIS of the use of electronically controlled pneumatic (ECP) braking to reduce the potential for noise impacts from wagons bunching and stretching.
6.1.1.3
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 27
Table 1.1 (Cont’d)
Coverage of Noise-related Matters Page 3 of 4
Government Agency
Paraphrased Requirement Relevant Section(s)
NOISE
EPA (02/04/12)
As it is possible that noise from activities like: heavy vehicle movements; dozers on coal stockpiles; washery processing, conveyor operation and rail use could cause audible noise to a large number of residents, the ElS must include contour plots of cumulative noise in years 1, 3, 5, 7, 9, 11, 13, 15, 17 and 20 of mine operations and compare this to the existing situation. These noise contour plots must be overlain over a figure showing the mine premises north to include all of the town of Gloucester and south to Craven. Contour plot figures must be included for normal and worst case weather conditions, including noise enhancing winds and temperature inversions.
Appendix 3
Noise on public roads from increased road traffic generated by the mine should be assessed using the guidelines contained in the Environmental Criteria for Road Traffic Noise (EPA, 1999). http://www.environment.nsw.gov.au/noise/traffic.htm.
7.1 – assessed in accordance with RNP
Noise from new or upgraded public roads needs to be assessed using the Environmental Criteria for Road Traffic Noise (EPA, 1999). http://www.environment.nsw.gov.au/noise/traffic.htm
N/A
Noise from increased rail traffic on the NSW Rail Network should be assessed using the environmental assessment requirements for rail traffic-generating developments available at http://www.environment.nsw.gov.au/noise/railnoise.htm. The assessment should address LAeq(24hr) as well as daytime LAeq(15hr)
and night-time LAeq(9hr) descriptors. The assessment should compare levels to EPA and Australian Rail Track Corporation (ARTC) guidance, including the ARTC Environment Protection Licence noise limits covering their North Coast Railway operations. Particular attention should be given to any increased train movements at night-time as it is known that at least two residences along the North Coast Railway between Stratford and Wards River currently exceed the LAeq(9hr) ARTC night-time noise goal of 60dBA and approximately six receptors in this same area currently exceed the maximum train pass-by criterion of LAmax 85dBA. It will therefore be important to understand any additional residences that will not comply with guidance levels or if these residences would be subject to increased trains at the most sensitive time.
7.3.1
The EIS needs to detail all noise amelioration measures proposed to address any noise issues identified.
6.2, 6.10
The EIS needs to detail any noise monitoring proposed to assess compliance with relevant limits.
6.10
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 28
Table 1.1 (Cont’d)
Coverage of Noise-related Matters Page 4 of 4
Government Agency
Paraphrased Requirement Relevant Section(s)
NOISE
Gloucester Shire Council (02/04/12)
The EIS should examine all activities associated with the proposed mine in terms of potential noise disturbance. It also should be recognised that the Valley has a significant number of temperature inversions at various times of the year which have the potential to exacerbate noise impacts.
8, 6, 7, 6.1.2
The analysis needs to examine in detail and potential noise impacts from road traffic generated by the mine activity, and blasting, processing, transfer of coal, loading of trains and noise disturbance from rail transport over the proposed 24 hours of operation. The analysis should also include a detailed assessment of individual component machinery contribution to overall noise generated from the proposed activity, and opportunities for overall minimisation of noise generation from the mining activity.
Applies to many sections
The analysis should also identify how noise levels might be monitored and suggest appropriate compliance requirements.
6.10
The EIS should examine potential impacts on nearby buildings from mine related activities such as blasting and the increased road transport that will be generated from the site. The analysis should include recommendations for pre-mining assessment of nearby structures and measures for monitoring and compliance.
9.1.2, 9.4, 9.5, 7.1.3
NSW Health – Hunter New England Local Health District (29/03/12)
The EIS needs to clarify the definition of limited blasting. 9
The proponent should clarify in the EIS how issues with vibration will be mitigated and should vibration issues arise, how this will be managed.
9.5
The proponent needs to demonstrate in the EIS that there has been community consultation in relation to noise and acceptance of the community of noise they are likely to experience.
See Volume 4 Part 14 of SCSC
The EIS should also include measures to mitigate or reduce noise and indicate how noise will be managed should complaints in relation to noise be made during either mine construction or mine operational phases of the project.
6.2, 6.10
There is a need for the cumulative impacts of noise with respect to other activities conducted in the Gloucester Valley to be assessed and presented in the EIS for the proposed Rocky Hill Coal Project. Community consultation with respect to the cumulative noise impacts needs to be demonstrated in the EIS.
6.6, and see Volume 4 Part 14 of SCSC
Barrington-Gloucester-Stroud Preservation Alliance Inc. (26/03/12)
Insulation should be offered for houses in the risk area. Problem noise needs to be recorded inside the dwelling as well as outside but outdoors only is the current requirements demand.
6.10
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 29
2 . P R OJ E C T D E S C R I P T I O N
2.1 PROJECT OVERVIEW
The Site of Rocky Hill Coal Project (“the Proposal”) is located approximately 3.5km to 7km
south-east of the Gloucester urban area. It is bordered by Waukivory Road to the north, and
lies to the east of the Avon River and east and north of Waukivory Creek. Rocky Hill lies to the
east of the Site within the Mograni Range.
The proposed Rocky Hill Coal Project comprises four principal components namely:
1. four separate and/or contiguous open cut pits and a coal handling and
preparation plant (CHPP) within the Mine Area;
2. an overland conveyor for transporting product coal to the Rail Load-out Facility.
The overland conveyor is located within a 50m wide Overland Conveyor Corridor;
3. a Rail Load-out Facility (incorporating a rail loop and two coal storage bins); and
4. two Power Line Corridors incorporating a re-located 132kV power line and a new
11kV power line external to the Mine Area.
Figure 2.1 displays the conceptual layout of the proposed Mine Area comprising the following
major components.
The mine entrance off McKinleys Lane, approximately 50m beyond the
intersection of Waukivory Road.
A private Mine Area access road to the site offices and amenities area, a road
aligned generally parallel to and immediately east of McKinleys Lane.
A site offices and amenities area off McKinleys Lane.
Four open cut pits varying in depth from approximately 70m to approximately
190m, with mining within the limits of the Main Pit initially involving the
development of two smaller, shallower sub-pits to enable some production of the
highest quality coals during the initial years of mining. Though based on current
mine planning, the depths nominated are approximate given the steeply dipping
nature of the seams and the extent of geological knowledge and, in such
situations, the potential effects of changes in controlling economic factors. The
ultimate depths of development in each open cut pit would reflect the optimisation
of coal quality, the outcomes of detailed mine planning as the mine progresses,
and market factors.
Three generally north-south trending short term or long term visibility barriers.
The barriers would either be stand-alone structures or comprise the western
margins of the out-of-pit emplacement as it is progressively developed.
A consolidated in-pit overburden emplacement and out-of-pit overburden
emplacement extending beyond the open cut pits. The out-of-pit emplacement
comprises a permanent section, and an interim section which would be removed
at the cessation of coal extraction to backfill the final void in the Main Pit.
A coal handling and preparation plant (CHPP) with associated run-of-mine (ROM)
and product stockpile areas, a switchyard, workshop and ancillary buildings.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 30
Figure 2.1 Proposed Site Layout
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 31
The Proposal would involve the following principal operational components and activities.
Approximately 130 million bank cubic metres (bcm) of overburden and
interburden would be removed to gain access to the targeted coal seams within
the individual open cut pits. The overburden would be removed by a combination
of scrapers, and excavators and trucks following blasting, and be used to create
visibility barriers initially, with the remainder emplaced in, out of, or over the
exhausted pits either permanently or temporarily and used to form the final
landform.
The coal exposed in each open cut pit would be removed by excavator and
transported by haul truck to the ROM coal stockpile adjacent to the CHPP.
Annual ROM coal production is scheduled to be 2.0 million tonnes per annum
(Mtpa) although the maximum ROM coal production rate for which approval is
sought would be 2.5 Mtpa.
Processing of all ROM coal would take place at the CHPP. At the maximum ROM
coal production rate and an estimated peak yield (i.e. product coal as a
percentage of ROM coal processed through the CHPP) of 70%, 1.75Mtpa of
product coal would be produced.
Transportation of product coal would be via the overland conveyor to the Rail
Load-out Facility for despatch to the Port of Newcastle.
Other ancillary activities include clearing, stripping of topsoil and suitable subsoil
from the areas to be disturbed, equipment maintenance and rehabilitation.
A 267ha Biodiversity Offset Area on Company-owned land east of the proposed
area of disturbance within the Mine Area
2.2 PROJECT TIMETABLE
The Applicant currently plans to commence development of the mine following the receipt of
development consent and all necessary approvals, licences and leases and commence to
dispatch the first coal approximately 12 months later.
Table 2.1 presents the projected annual overburden and coal production throughout the life of
the Proposal. Beyond the cessation of mining activities, identified as Year 14 in Table 2.1, the
operational activities would primarily be restricted to backfilling of the remaining void within the
exhausted Main Pit and the completion of the remaining final landform creation and
rehabilitation activities.
In the event production levels in Table 2.1 are achieved, the life of the mine would extend for
approximately 16 years from the commencement of site establishment activities, through open
cut mining and final landform creation and completion of all rehabilitation activities. However,
to allow for any variations in production levels, approval is being sought for a maximum mine
life of 21 years.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 32
Table 2.1
Estimated Annual Overburden and ROM Coal Production
Year
Totals
Overburden (kbcm) ROM
Coal (kt)
1* 6 321 600
2 7 384 1 033
3 9 751 1 320
4 9 166 1 775
5 13 508 1 758
6 13 197 2 000
7 11 577 2 000
8 11 577 2 000
9 8 841 2 000
10 8 841 2 000
11 8 841 2 000
12 8 841 2 000
13 8 841 2 000
14 3 042 509
Totals 129 723 22 995
* Site Establishment and Construction Phase
2.3 ROAD TRAFFIC
2.3.1 Site Establishment and Construction Phase
The traffic movements during the site establishment and construction phase would initially
occur principally on Waukivory Road, via the northern intersection with The Bucketts Way and
on The Bucketts Way near the Rail Load-out Facility. A small proportion of the vehicle
movements would occur on Fairbairns Road primarily during the construction period for the
overland conveyor. It is noted that traffic movements along Jacks Road between The Bucketts
Way and Waukivory Road would commence following the completion of the construction of the
new bridge on Jacks Road crossing the Avon River, currently programmed for completion
approximately mid way during the site establishment and construction phase.
Table 2.2 lists the number of light vehicle and heavy vehicle movements likely to occur during
the site establishment and construction phase.
Table 2.2
Traffic Movements* During Site Establishment and Construction Phase
Light Vehicles (No. per day) Heavy Vehicles (No. per day)
Mine Area (off Waukivory Road) 20 - 210 0 - 10
Rail Load-out Facility (off The Bucketts Way)
10 - 50 0 - 20
Fairbairns Road 0 - 10 0 - 8
* 1 return trip generates 2 movements.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 33
2.3.2 Operations
The traffic movements during operations would occur principally to and from the Mine Area (off
Waukivory Road) and the Rail Load-out Facility (off The Bucketts Way). Limited vehicle
movements would occur on Fairbairns Road primarily during the daily checks and/or
maintenance of the overland conveyor.
Light vehicle traffic would be concentrated around shift start and finish times. Essentially, light
vehicles would enter the Mine Area during four 1-hour periods and leave the Mine Area during
four 1-hour periods and one ½ hour period. The indicative number of light vehicles entering or
leaving the Mine Area during each period would be as follows.
Entering Leaving
6:00am – 7:00am : 49 – 76 3:00pm – 4:00pm : 17 – 35
7:00am – 8:00am : 2 – 4 4:00pm – 5:00pm : 4 – 11
2:00pm – 3:00pm : 6 – 24 5:30pm – 6:30pm : 14 – 51
4:30pm – 5:30pm : 17 – 36 10:00pm – 10:30pm : 6 – 23
4:00am – 4:30am* : 17 – 20
* Excluding the Site Establishment and Construction Phase.
2.4 BLASTING
All overburden below the limit of weathering is likely to be blasted to enable it to be removed to
provide access to the coal seams. This would involve the drilling of 229mm diameter holes (or
similar) with nominally 80 to 160 holes per blast and hole depths of either 15m or 30m. It is
proposed that the maximum instantaneous charge (MIC) would generally vary from 688kg to
828kg (or larger in more distant areas where application of larger MICs could readily satisfy the
blasting amenity criteria). Where predictions indicate the possibility that airblast or ground
vibration criteria may be exceeded, MICs would be reduced by, for example, decking the
individual blast holes, to ensure compliance. Blasts would be initiated with either an electric or
a non-electric system. Each 30m blast would result in up to approximately 260 000bcm being
fragmented, whilst each 15m blast would fragment up to approximately 130 000bcm of
overburden.
The number of blasts will vary from approximately 20 to 100 in any one year with up to a likely
maximum of four blasts per week.
2.5 PRODUCT DISPATCH
All coal would be transported by rail to the Port of Newcastle. It is likely that one to three trains
per day would be despatched. For the purposes of this assessment, it is assumed three trains
per day would depart Rocky Hill Coal Project (i.e. six movements in total). It is understood
these could occur at any time of the day with the time of departure nominated by ARTC.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 34
2.6 HOURS OF OPERATION
Table 2.3 lists the proposed operational hours for the range of activities proposed within the
Site.
Table 2.3
Operational Hours
Activity Days* Hours Comments
Pre-start activities Monday – Saturday 6:00am – 7:00am
Mining Monday – Saturday 7:00am – 10:00pm
Monday – Saturday 10:00pm –4:00am Subject to confirmation by modelling and real-time monitoring that night-time and sleep disturbance criteria are satisfied at privately-owned receptors, mining would continue from 10:00pm on each of Monday to Saturday and extend to 4:00am on the following day. There would be no mining activity between 4:00am and 7:00am on any day.
CHPP Monday – Saturday 7:00am – 10:00pm Hours and days worked to match production
Coal Product Despatch (overland conveyor / train loading
Monday – Sunday Any time As required to satisfy ARTC product despatch schedule.
Maintenance Monday – Saturday 7:00am – 10:00pm
Sunday 8:00am – 10:00pm
Monday – Sunday All other hours If activities are not audible at privately-owned receptors.
* Public Holidays excluded
Operations within the Mine Area
Operations within the Mine Area and related activities would initially be undertaken between
7:00am and 10:00pm Monday to Saturday, public holidays excluded, with preparatory activities
including pre-start checks (limited personnel) to be undertaken between 6:00am to 7:00am.
Limited drilling and other activities would be undertaken between 10:00pm and 4:00am,
Monday to Saturday once the open cut pits have reached a depth below the natural ground
surface and/or behind constructed barriers where the noise modelling and real-time monitoring
confirm night-time and sleep disturbance criteria would be satisfied.
Operations within the Mine Area would be undertaken adopting a range of shifts throughout
the week. Most shifts would be either 8 hours or 10.5 hours depending on the year of
operation and the likely opportunity(ies) to operate equipment during the evening and night-
time periods. The 8 hour shifts would typically occur between 7:00am and 3:00pm and
between 2:00pm to 10:00pm. The 10.5 hour shifts would typically occur between 7:00am and
5:30pm and between 5:30pm to 4:00am.
During the early years of operation, the CHPP would likely operate on day shift only, with the
number of days and duration of operations increasing with the increase in ROM coal
production. In order to process the ROM coal at maximum production, the CHPP would
ultimately operate on two shifts from 7:00am to 10:00pm, Monday to Saturday.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 35
It is proposed that equipment maintenance be undertaken, when required, 24 hours per day,
7 days per week provided maintenance activities between 10:00pm and 7:00am are not
audible at any privately-owned receptor.
Operation of the Overland Conveyor
The overland conveyor would operate for a period of approximately 2.5 hours at a time to
deliver the coal from the product stockpile adjacent to the CHPP to the surge bin and TLO bin
within the Rail Load-out Facility. The use of the overland conveyor would be scheduled
whenever possible to occur between 7:00am and 6:00pm, or if required between 6:00pm and
10:00pm. Only in the event that train loading is undertaken between 10:00pm and 7:00am and
another train is scheduled for arrival prior to 10:00am on the following day would operation of
the overland conveyor and loading of the bins occur during the night-time period.
In the event that the overland conveyor is operated between 4:00am and 7:00am, the only
mobile equipment operating during the night-time period within the Mine Area would be a
rubber-tyred bulldozer or front-end loader within the product coal stockpile area.
Operation of the Rail Load-out Facility
The hours of operation for product despatch from the Rail Load-out Facility would be dictated
by the timetable nominated by the coal carrier on advice from ARTC (in conjunction with the
HVCCC) regarding the available train paths to the Port of Newcastle to satisfy shipping
schedules.
2.6.1 Site Establishment and Construction Hours
The proposed site establishment and construction hours are presented in Table 2.4.
Although activities would generally be undertaken within the “normal” hours nominated in
Table 2.4, limited activities may be required within the nominated contingency hours in the
event of periods of unfavourable weather which delay critical path construction activities, to
allow for the receipt of components from interstate and/or to enable the completion of particular
phases of installation or commissioning activity that cannot be readily terminated mid-stream.
Table 2.4
Site Establishment and Construction Hours
Construction Activity Normal Hours1, 3
Days
Preparatory activities (pre-start checks and administration)
6:00am – 7:00am Monday – Friday
Mine Area Earthworks and Infrastructure 7:00am – 10:00pm2 Monday – Saturday
CHPP and Workshop 7:00am -10:00pm
7:00am -1:00pm Monday – Friday
Saturday
Overland Conveyor 7:00am – 6:00pm 7:00am -1:00pm
Monday – Friday Saturday
Rail Load-out Facility 7:00am – 8:00pm Monday – Friday 7:00am – 1:00pm Saturday
Off-site Construction Activities 7:00am – 6:00pm (daylight hours)
Monday – Friday
1 Contingency hours for all on-site activities would be to 10:00pm.
2 Operational hours for earthworks in acoustically exposed areas would be limited to
7:00am – 6:00pm Monday – Friday and 8:00am to 1:00pm of a Saturday. 3
Only activities which comply with operational noise criteria (RBL +5dB(A)) would be undertaken outside the standard hours for construction activities.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 36
3 . N O I S E R E C E P TO R S A N D S U R R O U N D I N G L A N D
U S E S
Land use in the local area includes a mixture of agricultural operations, existing open cut coal
mining and rural and rural-residential areas.
The Site is located 3.5km to 7km southeast of the Gloucester urban area. To the south of the
Site are Stratford Coal Mine and the proposed Stratford Extension Project. The Gloucester
Gas Project involves the development of gas wells to the south, west, north and within the Site
together with a central processing facility and associated infrastructure. Immediately east of
the Site is the Mograni Range which extends up to in excess of 300m above the Gloucester
valley. “Rocky Hill” is a peak in this range immediately east of the Site which has an elevation
of approximately 440m AHD. To the north, west, and south of the Site there are a range of
resource company-owned and private rural/rural-residential receptors, all of which have been
considered in this assessment. These receptors are listed in Table 3.1 and shown on
Figure 3.1.
In addition to these receptors, the assessment has considered noise impacting the Gloucester
Township. This has been achieved through predictions to a selection of discrete sensitive-
receptor locations (schools, churches and health-care facilities) across the township. These
locations are shown in Figure 3.2. Noise levels at these locations are also representative of
noise levels in residential and commercial areas within the township.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 37
Figure 3.1 Surrounding Noise-Sensitive Receptors
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 39
Figure 3.2 Noise-Sensitive Receptors in Gloucester Township
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 40
Table 3.1
Receptors Considered in this Assessment (co-ordinates are MGA, zone 56) Page 1 of 4
Receptor ID. Easting (MGA) Northing (MGA) Landowner
Privately-owned Receptors
2 402346 6456613 I. Reeves
6 405555 6453564 R.B. & L.R. Campbell
7 403954 6455192 L.J. Ansell & R.K. Murray
11A 406712 6450141 A.S. Berecry
11B 406946 6449720 A.S. Berecry
18 402257 6451296 J.D. Collins & M.I. Barrett
19A 402107 6452036 A.K. & B.R. Boorer
21A 402339 6454911 E.J.A. & K.J. Robinson
21B 402357 6454840 E.J.A. & K.J. Robinson
22A 401135 6451967 G.H. Harris
23 405722 6453457 S.J. & J.G. Yarnold
24 401987 6454995 D.J & D.L. Bardwell
25A.1 403932 6456228 M.L. Green
25A.2 403807 6456176 M.L. Green
25B 404102 6455887 M.L. Green
25C 404106 6455725 M.L. Green
26 404024 6455845 W.A. Green
27 402765 6455321 B. & D. Hanson
28 402850 6455296 P. & L. Flanagan
30 403055 6455278 J. & D. House
31O 403008 6455129 Worrigee Developments Pty Limited
31P 403050 6455123 Worrigee Developments Pty Limited
33 403266 6455145 R. & M. Seale
36 402978 6454856 D. Warby
38 402891 6454887 G. & M. Hornsby
39B 402850 6454910 W. & V. Ejea
40 402799 6454927 G. & N. Fallon
43 402749 6454927 A.& C Field
44 402706 6454955 T. & L. Mason
45 402715 6455010 L. & L. Kearney
46 402758 6455064 A.& S. Wilson
47 402771 6455110 P. Warby
50 402927 6455048 R. & S. Vale
52 402945 6454968 G. Coates
53 403013 6454956 A. & C. Tate
56A 401066 6450614 W. Fraser
63 401730 6455487 S.J. Dark & V.M. Dark
65 402036 6455437 C.E. & D.M. Rodger
67P 401700 6455388 Jar Properties Pty Limited
67J 402510 6455074 Jar Properties Pty Limited
68 402280 6455381 D.M. Trinder & S.L. Ratley
70 402438 6455371 S.J. & M.C. Howlett
71 402700 6455332 L.A. & J.T. Tenbosch
73 402632 6455102 G.J. & S.G. Coles
74 402620 6455029 W.J. & P.L. Perry
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 41
Table 3.1 (Cont’d) Receptors Considered in this Assessment (co-ordinates are MGA, zone 56)
Page 2 of 4
Receptor ID. Easting (MGA) Northing (MGA) Landowner
Privately-owned Receptors
75 402633 6454960 K.F. & S. Lowe
76 402554 6455000 A.J. & R.L. Young
77 402614 6454909 E.D. Krestensen
78 402516 6454911 T.B. & A.M. Higgins
80 402421 6454996 D.W. & M.J. Schneider
81 402376 6455007 D. Bradbury & J. Richardson
82 402308 6455004 M.L. & K.M. Bonisch
83 402255 6455139 A.J. Gibbs
84 402196 6455047 H.V. & J Ellis
85 402043 6455088 D.W. & L.M. Elliott
86 401971 6455116 L.S. & M.E. West
87 401965 6455185 R.J. Yates & M.D. Moore
88 401807 6455156 D & K Reid
91 402151 6455278 A.J. Writer & F.M. Aitken
92 402305 6455245 T.J. & B.J Hamilton
94 402404 6455230 K.D. & S.A. Sage
98 401423 6455319 Laurie Earthmoving Pty Limited
99 401215 6455168 G. Maurer
100 401210 6455121 L.R. & J.R. Mitchell
102 401291 6455079 G. Salisbury
103 401242 6455054 M.R. Madden
104 401243 6455022 A.F.& K.L. Brown
105 401247 6455018 C.G. Johnston
106A 401228 6455100 A.P. & D.M. Bruce
106B 401255 6454998 A.P. & D.M. Bruce
107 401358 6455182 D.L. Genoli
108 401457 6455175 P.K. & J.M. Ballard
109 401304 6454923 A.G. & S.M. Young
110 401265 6454853 T.J.A. & M.F. Laurie
112 401246 6454544 R.E. & I.A. Waters
113 401188 6454588 R.J. Whalen
114 401184 6454563 K.A. Gardner
115 401186 6454533 N.K. Richards
117 401274 6454480 C.F. & C.J. Reynolds
118 401187 6454489 J. Burley
119 401195 6454468 E.M. Crawley
120 401189 6454447 T.M. Harris
121 401190 6454425 N.L. Fisher
122 401191 6454412 S.B. Freeman
123 401186 6454360 K.E. & S.J. Nash
125 401299 6454388 E.D.W. & L.M. Quinton, J.S. & K.J. Quinton
126 401260 6454273 W.J. Beggs & R.V. Edwards
127 401244 6454120 J.P. Dynes
128 401299 6454025 D.J. Wisemantel & J.M. Grady
129 401297 6453953 A.W. & R.A. Galvin
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 42
Table 3.1 (Cont’d) Receptors Considered in this Assessment (co-ordinates are MGA, zone 56)
Page 3 of 4
Receptor ID. Easting (MGA) Northing (MGA) Landowner
Privately-owned Receptors
130 401241 6453887 F.J. Crawley
132 401275 6453557 B.C. Chong-Sun
133 401167 6453364 J.M. Sutherland
135 401477 6453436 G.C. & P.J. Morris
137 401266 6453285 C.W. & B.N.E. Franklin
138 401127 6453277 R. & R.L. Besier
139 401154 6453218 M., C.I. & H.A.W. Bowman
140 401018 6453042 M.J. & K.I. O'Brien
141 401171 6453045 B.A. & M.L. Steadman
142 401239 6452980 D.B. Hamilton
143 401253 6453123 K.J. Wardrop
144 401470 6453134 J.C.E. Heylink
145 401378 6453039 H.J.& P.F. Cox
146 401544 6453068 S.L. Ruse
147 401532 6453193 B.J. & D. Gilbert
148 401497 6453282 H.M. Evans
149 401654 6453068 C.E. & P.M. Reynolds
150 401715 6452958 B.J. & F.P. McKechnie
151 401576 6452968 M.J. & R.A. Edwards
152 401615 6452868 J.R. & L.M. Findlay
153 401653 6452809 R.J. & R.A. West
154 401768 6452723 I.A. & S. Jackson
155 401303 6452809 P.E. & S.J. Hedditch
156 401150 6452796 B. Harris
157 401054 6452833 A.I. Ross
158 401020 6452796 G.R. & D.C. Shore
159 400782 6452710 N.A. & E.M. Rumbel
160 401190 6452639 S. & U.L. Toth
161 401108 6452300 R.K. & B.J. Saunders
163A 400895 6449908 N.E. Bignell
163B 400426 6449695 N.E. Bignell
164A.1 400591 6448645 N.J. Williams
164A.2 400468 6448476 N.J. Williams
165A 399922 6447996 B.K., L.J., T.B., & L.M. Walker
172 407120 6452732 A.C. & K.T. Vintner
173 406402 6453321 N.R. & A.B. Sage
174A 406560 6453408 V.P. Predebon
174B.1 406866 6453177 V.P. Predebon
174B.2 407012 6453020 V.P. Predebon
179 400834 6453987 M. Barnes
180 400375 6454208 G. & J. Spokes
181A 399455 6454390 G. Harris
181B 400848 6453115 G. Harris
181C 399856 6452888 G. Harris
182A 400238 6452647 A. & G. Sopher
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 43
Table 3.1 (Cont’d) Receptors Considered in this Assessment (co-ordinates are MGA, zone 56)
Page 4 of 4
Receptor ID. Easting (MGA) Northing (MGA) Landowner
Privately-owned Receptors
182B 400011 6452230 A. & G. Sopher
183 399291 6451848 G. Channon & T. Edwards
184A 400042 6452164 D. Andrews
184B 398455 6451659 D. Andrews
186 398656 6452803 Charnich Pty Limited
187 398693 6452350 V. & K. Pham
188 398588 6452152 T. Mott
189 399607 6451944 A. & S Kingston
191A 399049 6451431 Baker Place Investments Pty Limited
192A 401800 6450065 Pace Farm Pty Limited
193 399856 6452620 Transport for NSW #
Resource Company-owned Residences
1B 403924 6454975 Gloucester Resources Limited*
1C 403109 6454740 Gloucester Resources Limited*
1D 402966 6454672 Gloucester Resources Limited*
1E 403676 6454576 Gloucester Resources Limited*
1F 403780 6454484 Gloucester Resources Limited*
1K 402480 6451565 Gloucester Resources Limited*
1L 404629 6450352 Gloucester Resources Limited*
1M 404942 6450255 Gloucester Resources Limited*
1N 404315 6450214 Gloucester Resources Limited*
1O 403612 6449925 Gloucester Resources Limited*
1P 404652 6449933 Gloucester Resources Limited*
1Q 405083 6449724 Gloucester Resources Limited*
1R 405060 6449442 Gloucester Resources Limited*
3A 403784 6454363 Gloucester Resources Limited*
3B 402664 6453552 Gloucester Resources Limited*
4A.1 402799 6453735 Gloucester Resources Limited*
4A.2 402783 6453637 Gloucester Resources Limited*
5 404440 6452587 J.A. & L.N. Clarke (under option)
8 405744 6453274 Gloucester Resources Limited*
12A 404532 6450161 Stratford Coal Pty Limited
12B 404537 6449570 Stratford Coal Pty Limited
13 403881 6449498 AGL Upstream Investments Pty Ltd
14A 402990 6450203 Gloucester Resources Limited*
15 402997 6450531 P.S. & B.C. Jackson (under option)
17 402848 6450945 Gloucester Resources Limited*
20 402048 6453069 Gloucester Resources Limited*
39A 403100 6455100 Gloucester Resources Limited*
55 401212 6451194 Gloucester Resources Limited*
166A 401616 6447905 AGL Energy Limited
167A 402528 6448869 AGL Upstream Infrastructure Investments Pty Ltd
168A 402470 6447869 CIM Stratford Pty Ltd, Gloucester Coal Ltd
177 400325 6451181 Gloucester Resources Limited*
Please note: * Denotes Gloucester Resources Limited or subsidiary company
# Residence on this property is owned by G.P. Heard
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 44
4 . E X I S T I N G N O I S E E N VI R O N M EN T
4.1 NOISE SOURCES
Noise which is currently audible at the residences surrounding the Site is attributed to a range
of sources including:
traffic on local roads and The Bucketts Way;
occasional trains on the North Coast Railway;
domestic noises such as lawn mowers;
rural noises such as tractors, insects and birds;
wind in the trees;
livestock/vehicles on properties and at the Gloucester Livestock Exchange
Centre;
a saw mill near the intersection of Jacks Road and The Bucketts Way; and
occasional light aircraft using the Gloucester airfield.
4.2 BACKGROUND NOISE MONITORING
A schedule of operator-attended and unattended noise monitoring was undertaken over four
periods between July 2010 and July 2012, namely in:
July 2010;
March 2011;
July 2011; and
July 2012.
The objective of the noise monitoring was to determine the background noise levels in the
absence of any mining or other activities related to the Proposal, in order to characterise and
quantify the acoustical environment in the area surrounding the Site.
The noise monitoring locations are listed in Table 4.1 together with the attended monitoring
programme.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 45
Table 4.1
Noise Monitoring Locations
Location Easting Northing Address
No. of Operator Attended Surveys
Daytime Evening Night-time
1 405527 6453610 633 Waukivory Road 3 3 3
2 403737 6454395 412 Waukivory Road 1 1 1
3 402911 6454666 188 Jacks Road 3 3 3
4 402056 6453058 20 Grantham Road 1 1 1
5 402102 6452066 176 Fairbairns Road 1 1 1
6 402465 6451574 237 Fairbairns Road 1 1 1
7 403951 6449504 508 Fairbairns Road 1 1 1
8 401164 6452031 124 Fairbairns Road 1 1 1
9 401168 6452628 30 Fairbairns Road 3 3 3
10 401940 6455206 1 Moonlight Crescent 4 4 4
11 401247 6455142 4566 The Bucketts Way 4 4 4
12 401351 6453945 4440 The Bucketts Way 4 4 4
13 402046 6458452 35 Tyrrell Street 2 2 2
14 401779 6457746 80 Barrington Street 2 2 2
15 401630 6456557 Clement Street 2 2 2
16 402144 6450914 3 Beech Close 2 2 2
The 16 noise monitoring locations listed in Table 4.1 are presented in Figure 4.1.
4.3 NOISE MEASUREMENT PROCEDURES
Noise measurement procedures were generally guided by the requirements of AS 1055-1997
“Acoustics - Descriptions and Measurement of Environmental Noise” and the EPA’s Industrial
Noise Policy (INP).
4.3.1 Unattended Continuous Noise Logging
Eight unattended noise loggers were positioned at a selection of the closest potentially
affected receptors to the Site, namely Location 1 and Location 3 to Location 9 (Refer to
Figure 4.1) for up to 16 days commencing on Thursday 1 July 2010. A ninth unattended noise
logger was positioned at a potentially affected receptor located to the north of the Site namely
Location 2 (Figure 4.1) for 11 days commencing on Tuesday 6 July 2010.
Three additional loggers were positioned in the vicinity of The Bucketts Way and the
Thunderbolt Estate at Locations 10 to 12 for 19 days commencing on Thursday 17 March 2011
in order to meet community expectations and re-assure relevant government agencies of the
rigour of the impact assessment process.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 46
Figure 4.1 Noise Monitoring Locations
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 47
In July 2011, unattended monitoring was repeated at Locations 1, 9, 10, 11 and 12 in order to
understand some atypical results recorded during the March 2011 program, and to ascertain
the noise climate in the absence of insect influence. Measurements were repeated at
Location 3 during this survey in order confirm that the general noise environment was similar to
that of the previous monitoring.
Noise monitoring within the Gloucester township (Locations 13-16) was undertaken in July
2012 in response to regulatory government agency requirements nominated when the DGRs
were issued. Measurements were repeated at Location 10 during this survey in order confirm
that the general noise environment was similar to that of the previous monitoring.
4.3.2 Operator-attended Noise Measurements
A number of rounds of operator-attended measurements were undertaken at all monitoring
locations in order to qualify and quantify the noise environment in the vicinity of the Site. In
general, these measurements were undertaken during installation and/or collection of the
unattended noise monitors detailed above. The number of operator-attended surveys
undertaken at each location is shown in Table 4.1.
4.4 INSTRUMENTATION AND MEASUREMENT PARAMETERS
The noise monitoring equipment used for the unattended monitoring consisted of
environmental noise loggers set to A-weighted, fast response, continuously monitoring over
15-minute sampling periods. This equipment is capable of remotely monitoring and storing
noise level descriptors for later detailed analysis. The equipment calibration was checked
before and after each survey, and no significant drift occurred.
The loggers determined LA1, LA10, LA90 and LAeq levels of the ambient noise. The LA1, LA10 and
LA90 levels are the levels exceeded for 1%, 10% and 90% of the sample time respectively. The
LA1 is indicative of maximum noise levels due to individual noise events such as the occasional
pass by of a heavy vehicle. The LA90 level is used to derive the Rating Background Level
(RBL) which is used to determine the various noise criteria. The LAeq level is the Equivalent
Continuous Sound Level and has the same sound energy over the sampling period as the
actual noise environment with its fluctuating sound levels. The LAeq is used for the assessment
of operational noise and traffic noise.
Attended monitoring was conducted using Class/Type 1 Sound Level Meters (SLM).
All acoustic instrumentation used throughout the monitoring programme complied with the
requirements of AS IEC 61672.1 2004 "Electroacoustics – Sound Level Meters –
Specifications", which replaces AS 1259.2 - 1990 “Sound Level Meters”, and carried current
NATA calibration certificates.
Instrument calibration was checked before and after each measurement, with the variation in
calibrated levels not exceeding the acceptable variation of ±0.5 dB (AS 1055).
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 48
4.5 UNATTENDED NOISE MEASUREMENTS
The unattended ambient noise logger data from each monitoring location are presented
graphically on a daily basis in Appendix 1.
The ambient noise data have been processed in accordance with the requirements of the INP
in order to derive the ambient noise levels, as presented in Table 4.2. The most relevant
dataset for each monitoring location is presented. Relevance was determined by the degree of
affectation from extraneous noise sources such as insects and the nearby Gloucester
Livestock Exchange Centre etc.
Table 4.2
Summary of Unattended Noise Monitoring Results*3
Location RBL – dBA*1
LAeq(Period) – dBA*1
Day Evening Night Day Evening Night
1 30 28 27 46 36 36
2 27 28 26 46 43 38
3 26 25 22 46 42 45
4 30 28 27 47 42 39
5 26 24 23 50 44 43
6 27 27 27 46 39 39
7 26 26 26 47 49 44
8 30 27 26 60 45 51
9 29 25 24 48 42 42
10*2 31 27 25 48 42 43
11 38 29 27 58 53 52
12 35 27 27 52 50 48
13 32 28 26 50 42 36
14 35 28 27 51 42 41
15 32 28 26 50 42 36
16 30 30 27 57 41 42
Notes *1: (dB(A) re 20μPa)
*2: 5 days recorded
*3: Results are presented for the most relevant monitoring undertaken at each location (i.e. considering extraneous noise influence from sources such as insects and the nearby Gloucester Livestock Exchange Centre etc.)
Continuous weather data was obtained from the GRL weather station located within the Mine
Area (installed and operational as of Thursday 1 July 2010), in order to identify periods of
adverse weather during the unattended noise logging. Data corresponding to periods of high
winds (i.e. greater than 5m/s) and/or rain were excluded from the background noise analysis.
The removal of the weather affected noise data did not significantly affect the resulting
background noise levels.
The results of the monitoring established that the proposed activities are located in a typical
rural area with few noise sources and generally low noise levels, particularly background noise
levels.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 49
Ambient noise levels in the vicinity of The Bucketts Way (Locations 11, 12 and 14) were
elevated due to traffic noise. This was particularly evident during the daytime period when
traffic levels are greatest. The consistency of traffic noise during the day is reflected by
elevated RBLs during this time period, as compared to other locations. During the evening
and night time periods, when traffic is less consistent, little difference was observed between
RBLs determined across all locations.
Noise monitoring undertaken during March 2011 showed higher noise levels than July 2010
and July 2011 during the evening and night-time periods, ranging between 9-18 dB higher.
The elevated noise levels reflected the presence of insects and thus were not considered in
the derivation of criteria as per the INP. Whilst reliance has not been placed upon the
March 2011 noise levels when establishing noise criteria, the results identify the levels of
background noise that are already present in the surrounding community during those periods
of the year when insects are present.
At Locations 13-16, within Gloucester township, daytime RBLs were marginally above those
outside the township, but generally below those at locations such as Locations 11 and 12 with
exposure to higher-speed traffic on The Buckets Way. Evening and night-time levels were
once again consistent with those at other locations.
4.6 ATTENDED NOISE MEASUREMENTS
These measurements were used largely to confirm the sources of noise measured in the
unattended monitoring. At Locations 11, 12 and 14, noise from other industrial sources was a
significant contributor to the measured ambient noise levels but only in the daytime. However,
in those cases, the estimated contribution from other industrial noise was well below levels
requiring inclusion in an analysis of cumulative noise impacts, under the INP.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 50
5 . O P E R ATI O N A L N O I S E A S S E S S M E N T C R I T E R I A
This Section of the report details criteria for operational noise generated on the Site (including
Mine Area, Overland Conveyor Corridor and the Rail Load-out Facility). For all other
emissions, including rail and road traffic on public infrastructure, relevant criteria are detailed in
the sections addressing those components.
5.1 INTRUSIVENESS AND AMENITY CRITERIA
The INP specifies two noise criteria:
an intrusiveness criterion which requires that the equivalent continuous noise
level (LAeq,15 minute) from a specific industrial source should not exceed the
background noise level by more than 5 decibels; and
an amenity criterion which aims to maintain noise amenity over the whole
daytime, evening or night-time period where it is subjected to cumulative noise
from a number of industrial sources.
Based on the existing Rating Background Noise Levels (RBLs) for day, evening and night
periods presented in Table 4.2, the derived intrusiveness criteria are presented in Table 5.1.
RBLs for monitoring locations having significant exposure to traffic noise (e.g. The Bucketts
Way) were observed to be elevated during the daytime period, when traffic is consistent.
RBLs measured at these locations have therefore been adopted for receptors having similar
exposure to these sources.
RBLs at all other locations were equal to or below 30 dBA, which constitutes the minimum RBL
adopted under the INP. Therefore, all locations other than those identified as having
significant exposure to traffic noise have been assumed to have an RBL of 30 dBA for day,
evening and night periods.
Table 5.1
Intrusiveness Criteria For Privately-owned Receptors, dBA
Receptor Number Receptor Area Description Day Evening Night
21A, 21B, 24, 63, 65, 67J, 67P, 68, 70, 73, 74, 75, 76, 77, 78, 80, 81, 82, 83, 84, 85, 86, 87, 88, 91, 92, 94
Exposed to Jacks Road, The Bucketts Way and some industrial noise from the nearby estate. Similar to Monitoring Location 10.
36 35 35
98, 99, 100, 102, 103, 104, 105, 106A, 106B, 107, 108, 109, 110
Exposed to The Bucketts Way near the intersection with Jacks Road. Some existing industrial noise also impacts the RBL. Similar to Monitoring Location 11.
43 35 35
112, 113, 114, 115, 117, 118, 119, 120, 122, 123, 125, 126, 127, 128, 129, 130, 132, 133, 138, 139, 140, 159, 181B, 181C, 182B, 183, 184B
Exposed to The Bucketts Way south of intersection with Jacks Road. Similar to Monitoring Location 12.
40 35 35
All others Rural with minimal transportation noise impacting the RBL.
35 35 35
Notes: Day: the period from 7:00 am to 6:00 pm Monday to Saturday; or 8:00 am to 6:00 pm on Sundays and public holidays. Evening: the period from 6:00 pm to 10:00 pm. Night: the remaining periods.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 51
Figure 5.1 Noise Catchment Areas
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 52
The amenity criteria are relevant in the context of controlling cumulative noise impacts
resulting from the concurrent operation of the Proposal and the other sources of industrial
noise (for example, the Stratford Mine and/or Expansion Project, the Gloucester Gas Project
and the proposed Waukivory Road Gravel Quarry). Given the results of the attended noise
monitoring, which indicate that existing industrial noise in the area is at a very low level, these
existing and future projects are the only potential sources of cumulative noise that require
consideration.
The amenity criteria set upper limits to control the total LAeq,Period noise levels at a given
receptor from all industrial sources over the daytime, evening and night-time periods. In this
case, the surrounding receptors are situated in an area which would be classified as “Rural”
under the INP, and the relevant recommended “acceptable” amenity criteria for LAeq,Period are
50, 45 and 40 dBA for daytime, evening and night-time periods, respectively.
In addition, the INP also stipulates a recommended “maximum” amenity level of 5 dBA above
the “acceptable” levels.
The INP describes the ‘Project-specific noise criterion’ as being the lower (i.e. more stringent)
of the intrusiveness and amenity criteria. Consistent with this approach, this assessment uses
intrusiveness criteria to assess noise from the Proposal, and amenity criteria to assess
cumulative noise.
The INP does not promulgate criteria for the assessment of noise emissions impacting vacant
land. However, DP&I and EPA have historically adopted an acceptability criterion as being
that the LAeq,15min noise level should not exceed 40 dBA on more than 25% of the property.
In view of the above, Table 5.2 summarises the criteria used in this assessment for all
privately-owned land.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 53
Table 5.2
Proposal Specific Noise Criteria for Privately-owned Receptors
Receptor Numbers
Criteria Type Day Evening Night-time
21A, 21B, 24, 63, 65, 67J, 67P, 68, 70, 73, 74, 75, 76, 77, 78, 80, 81, 82, 83, 84, 85, 86, 87, 88, 90, 91, 92, 94
* 64, 66, 67A, 67B, 67C, 67D, 67E, 67F, 67G, 67H, 67I, 67K, 67L, 67M, 67N, 67O, 67Q, 69, 71, 72, 79, 89, S93, 95, 96
INP Intrusive 36 LAeq,15 minute (dBA) 35 LAeq,15 minute (dBA) 35 LAeq,15 minute (dBA)
INP Amenity 50 LAeq,Period (dBA) recommended acceptable
55 LAeq,Period (dBA) recommended maximum
45 LAeq,Period (dBA) recommended acceptable
50 LAeq,Period (dBA) recommended maximum
40 LAeq,Period (dBA) recommended acceptable
45 LAeq,Period (dBA) recommended maximum
98, 99, 100, 102, 103, 104, 105, 106A, 106B, 107, 108, 109, 110
* 97
INP Intrusive 43 LAeq,15 minute (dBA) 35 LAeq,15 minute (dBA) 35 LAeq,15 minute (dBA)
INP Amenity 50 LAeq,Period (dBA) recommended acceptable
55 LAeq,Period (dBA) recommended maximum
45 LAeq,Period (dBA) recommended acceptable
50 LAeq,Period (dBA) recommended maximum
40 LAeq,Period (dBA) recommended acceptable
45 LAeq,Period (dBA) recommended maximum
112, 113, 114, 115, 117, 118, 119, 120, 122, 123, 125, 126, 127, 128, 129, 130, 132, 133, 138, 139, 140, 159, 181B, 181C, 182B, 183, 184B
* 19B, 19C, 111, 116, 121, 124, 131, 162
INP Intrusive 40 LAeq,15 minute (dBA) 35 LAeq,15 minute (dBA) 35 LAeq,15 minute (dBA)
INP Amenity 50 LAeq,Period (dBA) recommended acceptable
55 LAeq,Period (dBA) recommended maximum
45 LAeq,Period (dBA) recommended acceptable
50 LAeq,Period (dBA) recommended maximum
40 LAeq,Period (dBA) recommended acceptable
45 LAeq,Period (dBA) recommended maximum
All others INP Intrusive 35 LAeq,15 minute (dBA) 35 LAeq,15 minute (dBA) 35 LAeq,15 minute (dBA)
INP Amenity 50 LAeq,Period (dBA) recommended acceptable
55 LAeq,Period (dBA) recommended maximum
45 LAeq,Period (dBA) recommended acceptable
50 LAeq,Period (dBA) recommended maximum
40 LAeq,Period (dBA) recommended acceptable
45 LAeq,Period (dBA) recommended maximum
All privately-owned land
Industry Standard
40 LAeq,15 minute (dBA) on more than 25% of the land
40 LAeq,15 minute (dBA) on more than 25% of the land
40 LAeq,15 minute (dBA) on more than 25% of the land
Notes: Day: the period from 7:00 am to 6:00 pm Monday to Saturday; or 8:00 am to 6:00 pm on Sundays and public holidays
Evening: the period from 6:00 pm to 10:00 pm
Night: the remaining periods.
* Denotes land which was vacant at the time of preparing this assessment but would attract the stated criteria should sensitive receptors are established on the subject land in the future.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 54
5.2 ASSESSMENT METHODOLOGY
The INP states that intrusiveness and amenity criteria have been developed to protect at least
90% of the population living in the vicinity of the industrial noise sources from the adverse
effects of noise for at least 90% of the time (Environment Protection Authority [EPA], 2000).
Provided the criteria in the INP are achieved, it is unlikely that most people would consider the
resultant noise levels excessive.
In those cases where the criteria are not achieved, it does not automatically follow that all
people exposed to the noise would find the noise unacceptable. Equally, even where criteria
are achieved, there will be a small proportion of the affected population who may still find the
noise unacceptable. In subjective terms, exceedances of the project-specific noise
assessment criteria can generally be described as follows:
Negligible: noise level increase <1 dBA (not noticeable).
Marginal: noise level increase 1 to 2 dBA (not noticeable by most people).
Moderate: noise level increase 3 to 5 dBA (not noticeable by some people but
may be noticeable by others).
Appreciable: noise level increase >5 dBA (noticeable by most people).
Table 5.3 presents terminology that has historically been used to describe zones of noise or
noise impact for mining and similar projects.
Table 5.3
Project Noise Impact
Assessment
Criteria Noise Criteria
“Noise Management Zone” “Noise
Affectation
Zone” Marginal Moderate
Intrusiveness
LAeq,15 minute Refer Table 5.1 1 to 2 dBA above
project-specific
criteria
3 to 5 dBA above
project-specific
criteria
> 5 dBA above
Project-
specific criteria Amenity
LAeq,Period Refer Table 5.1
5.3 CRITERION FOR THE PREVENTION OF SLEEP DISTURBANCE
WITHIN RESIDENCES
To protect people against being awoken from their sleep, the EPA recommends that 1-minute
LA1 noise levels (effectively, the LA,max or maximum noise level) should not exceed the
background noise level by more than 15 dBA when measured or computed at the location of a
building façade. The “sleep disturbance” criterion is only applicable to night-time (10.00 pm to
7.00 am) operations.
Where the existing rating background level (RBL) is less than 30dBA, the INP states that a
minimum RBL of 30 dBA should be adopted. Given this, the sleep disturbance criterion when
assessed external to any surrounding noise sensitive receptors (Figure 3.1) is 45 dBA
LA1,1 minute.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 55
5.4 WORLD HEALTH ORGANISATION CRITERIA TO PROTECT THE
HEALTH OF THE SURROUNDING COMMUNITY
The NSW INP has been developed to regulate noise from industrial sources such as mining
projects. Among the INP’s stated objectives is to “protect the community from excessive
intrusive noise and preserve amenity for specific land uses”. The policy is primarily aimed at
controlling noise annoyance rather than noise which could directly affect health. Levels at
which direct health effects, such as noise induced hearing loss, may occur are much higher
than criteria which to limit noise annoyance effects.
The World Health Organization (WHO), in “Guidelines for Community Noise” (WHO, 1999),
considered many direct and indirect health implications of excessive noise, using a definition of
“health effects” that includes impacts such as annoyance. Among the effects1 considered by
the guidelines were:
interference with speech perception;
hearing impairment;
sleep disturbance;
annoyance; and
effects on social behaviour.
Considering the above health effects, the WHO guidelines set out values deemed appropriate
for the protection of the community. The LAeq,8hour values prescribed for dwellings are:
35 dBA internally for the protection of speech intelligibility and limiting noise to
cause moderate annoyance; and
30 dBA inside bedrooms to protect a person’s ability to sleep (applicable during
the night time only).
These guideline values correspond to external goal levels of 40-45 dBA (applying a 10 dB
attenuation from outside to inside with windows partly open), which exceed the INP derived
intrusiveness criteria identified in Table 5.2.
With regard to night-time noise and its effects on a person’s ability to sleep, the WHO (Europe)
has published Night Noise Guidelines (NNG) for Europe (WHO Europe, 2009). This guideline
presents alternative assessment criteria to those presented in the WHO’s Guidelines for
Community Noise (WHO, 1999) on the basis of more recent and more relevant research. The
NNG recommends an LAeq approach to the assessment of night noise, averaged over all night
time periods for a one-year period.
On the basis of the health effects considered by the studies founding the NNG, the guideline
concludes that the recommended night noise guideline value to protect health is the A-
weighted night time noise level averaged over a one-year period – Lnight,outside – 40 dBA, with an
interim target of Lnight,outside 55 dBA. Note that the WHO assumes an outside to inside
attenuation of 15-21 dB. This outside to inside attenuation relates to cultural and regional
differences, such as percentage of open windows and building construction, and is more
readily accepted as 10 dB in Australia.
1 For more information on these effects consult the guidelines.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 56
Therefore in Australia the WHO’s NNG targets would be nearer to Lnight,outside 35 dBA, with an
interim target of Lnight,outside 50 dBA to maintain the same noise level at the occupant’s ear. This
can be directly compared with an INP intrusiveness criterion of Lnight,outside = 35dBA (although
the intrusiveness criterion is generally calculated on a per-season basis rather than over an
entire year). For the Rocky Hill Coal Project assessment, the intrusiveness criterion of LAeq,15min
35 dBA (applied to a 10% exceedance limit) is more stringent than both interim and long-term
WHO targets.
Considering the above, we consider that the INP derived criteria summarised in Table 5.2
represent noise levels that would typically protect the surrounding community from health
impacts associated with noise.
5.5 CRITERIA FOR THE ASSESSMENT OF LOW FREQUENCY NOISE
(INCLUDING INFRASOUND)
5.5.1 Introduction
Low frequency noise has the potential to cause annoyance, even at A-weighted levels which
may not themselves be considered annoying. Low frequency noise is typically defined as
frequencies within the audible range below 100 Hz.
For low frequency noise, the INP recommends that an assessment be conducted in terms of
the difference between C and A weighted levels of noise from the source, and if a 15 dB
difference or more exists, a correction of 5 dB should be applied.
Current research suggests that this approach of applying a penalty based upon the difference
between C-weighted and A-weighted noise levels may be inappropriate. Broner (2011)
suggests that “the (C-A) level difference is only an appropriate starting metric for indicating
when a potential [Low Frequency Noise (LFN)] problem may become a significant source of
annoyance to the public”. Broner also suggests that “if it is necessary to utilise a (C-A) sound
pressure level difference at all, it is recommended that a (C-A) difference of at least 20 dB be
used to indicate the presence of a potential LFN noise problem.”
Furthermore, Leventhall (2003) states that the use of a (C-A) difference is not suitable when
the noise levels are low, since the low frequencies may then be below threshold of hearing
levels. In addition, a (C-A) difference only accounts for noise within the audible range. It has
been suggested that infrasound, i.e. “sound” below the audible range (below 20 Hz), can
negatively impact wellbeing. The DEFRA approach discussed below includes third-octave
frequencies as low as 10 Hz and thus considers some infrasound.
Therefore, on the basis of the current evidence, we conclude that the INP approach of applying
a 5 dBA penalty when C-weighted levels exceed A-weighted levels by 15 dB is inadequate for
the assessment of low frequency noise as it is defined by an unduly stringent (C-A) level
difference and also because it neglects the absolute magnitude of the noise. More appropriate
approaches, and the approach adopted for this assessment, are discussed in Sections 5.5.2
to 5.5.4.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 57
5.5.2 DEFRA Approach
The UK Department for Environment, Food and Rural Affairs (DEFRA) has developed a new
procedure to assess low frequency noise. The proposed criteria and assessment procedure
are detailed in the following publications:
Proposed criteria for the assessment of low frequency noise disturbance, 2005,
Prepared for DEFRA by Dr Andy Moorhouse, Dr David Waddington, Dr Mags
Adams; and
Procedure for the assessment of low frequency noise complaints, 2005, Prepared
for DEFRA by Dr Andy Moorhouse, Dr David Waddington, Dr Mags Adams.
A measurement of Leq, L10 and L90 is taken in third octave bands between 10Hz and 160Hz,
within a potentially-affected residence. If the Leq taken over a time when the noise is said to be
present exceeds the reference spectrum in Table 5.4, it may indicate a source of low
frequency noise that could cause disturbance. The character of the sound should be checked,
if possible, by playing back an audio recording at an amplified level.
Table 5.4
Proposed Reference Curve for Assessment of Low-Frequency Noise
Hz 10 12.5 16 20 25 31.5 40 50 63 80 100 125 160
dB, Leq 92 87 83 74 64 56 49 43 42 40 38 36 34
If the noise occurs only during the daytime, then a 5dB relaxation may be applied to all third
octave bands. Similarly, if the noise is steady, then a 5dB relaxation may be applied to all third
octave bands. A noise is considered steady if either of the conditions below is met:
L10 – L90 <5dB; or
the rate of change of sound pressure level (fast time weighting) is less than 10dB
per second.
The above parameters are evaluated and compared with the above reference spectrum, with
an exceedance of the reference curve requiring the reduction of the low frequency noise level.
Though this methodology represents the latest research into the assessment of low frequency
noise, it is impractical to implement at an impact assessment stage of a project as it relies on
precise knowledge of the prevailing noise levels at each receptor and also the acoustic
properties of each residential dwelling.
5.5.3 A Simple Outdoor Criterion
It is more convenient for predictive assessments to be undertaken using outdoor criteria.
Broner (2011) recommends the following criteria for the assessment of low frequency noise,
based on a review of “many case histories and the literature”.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 58
Table 5.5
Outdoor Criteria for the Assessment of Low Frequency Noise
Sensitive Receptor Range Criteria Leq (dBC)
Residential
Night time or plant operation 24/7 Desirable 60
Maximum 65
Daytime or Intermittent (1-2 hours) Desirable 65
Maximum 70
Commercial/ Office/ Industrial
Night time or plant operation 24/7 Desirable 70
Maximum 75
Daytime or Intermittent (1-2 hours) Desirable 75
Maximum 80
Note: Night-time is taken to be the same as that defined by the INP (i.e. 10.00pm-7.00am). Daytime is taken to represent the remaining period from 7.00am-10.00pm (i.e. Day and Evening periods under INP)
A 5 dBC penalty is suggested if the C-weighted sound pressure level (SPL) is fluctuating by +/-
5 dBC. The C-weighted criteria are to apply in addition to the ordinary A-weighted criteria.
From Table 5.5, the appropriate “desirable” criteria would be 65 dBC and 60 dBC during the
day and night periods respectively.
5.5.4 Adopted Low Frequency Noise Approach
In practice, it is difficult to assess low-frequency noise at the planning stage of a project. The
outdoor criteria promulgated by Broner (2011) (Section 5.5.3) and the dBA-dBC difference test
detailed in the INP serve as useful screening criteria to identify whether low-frequency noise is
likely to be a source of annoyance. As such, these criteria are adopted as screening criteria
for the Rocky Hill Coal Project.
While the third-octave spectral analysis suggested by DEFRA represents current best-practice,
it is of little use at the EIS stage. For the purpose of evaluating low-frequency noise and
infrasound once the Proposal is operational, and thus when measurements can be undertaken
at receptors, we recommend that the DEFRA approach be adopted.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 59
6 . O P E R ATI O N A L N O I S E A S S E S S M E N T
6.1 NOISE MODELLING METHODOLOGY
Operational noise levels at nearby receptors have been calculated using the Environmental
Noise Model (ENM) prediction model (a proprietary computer program from RTA Technology
Pty Ltd). This modelling software has been accepted by the EPA for use in environmental
noise assessments. The assessment models the total noise at each receptor from the
operation of the Proposal. Total predicted operational noise levels are then compared with the
relevant operational noise criteria presented in Table 5.2.
6.1.1 Noise Assessment Scenarios
Noise modelling was undertaken for:
day and evening operating scenarios for Year 0.5 which effectively equates to the
site establishment and construction phase; and
day, evening and night operating scenarios for mining Years 2.5, 4.25, 7.75
and 13.
These years were chosen as they represent each of the distinct phases of the Proposal. Each
scenario modelled incorporates was developed in consultation with the mine planer to reflect
the nominated production schedules and require restrictions upon equipment operations. It will
remain up to the Applicant through the real-time monitoring program to establish the exact
number and type of equipment in use at any one time and their location. In brief, there would
be flexibility for more equipment to be operated in areas with substantial topographic shielding
than in areas with lesser topographic or no shielding.
For each relevant scenario and time period, noise levels are calculated for three cases:
mine operation without operation of either the overland conveyor or the Rail
Load-out Facility;
mine operation in conjunction with the overland conveyor; and
mine operation in conjunction with the Rail Load-out Facility.
The first case represents the majority of the operating time. As described in Sections 6.4.3
and 6.4.4, both the overland conveyor and the Rail Load-out Facility will operate for up to
approximately 30hrs and 17hrs of the time week respectively, and times when they would
operate simultaneously would be very rare.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 60
The EPA assessment requirements provided to the DP&I for inclusion with the DGRs
requested noise modelling to be undertaken in Years 1, 3, 5, 7, 9, 11, 13, 15, 17 and 20. The
selected scenarios above closely resemble the requested scenarios for the early stages of the
mine’s life, up to Year 7. This represents the period when the mine would be most dynamic.
Beyond Year 7.75, the majority of mining-related activity would be confined to the Main Pit. In
the intervening period between Year 7.75 and Year 13, the Main Pit would be progressively
developed northwards, with backfilling occurring in the southern portions. During the period
between the cessation of projected coal extraction activities (Year 14) and the end of the
mine’s life, operational mobile plant numbers would decrease.
Between the end of coal extraction activities and the end of the completion of all pit backfilling,
activities would progress towards the surface again, producing a similar scenario to that
assessed by Year 0.5, though having less mobile plant. Therefore, we consider that the
assessed scenarios adequately represent the range of mine operations requested by the EPA.
The outcomes are presented in Section 6.4.
6.1.1.1 Extraction Operations
Overburden Management
Based on the drilling results, it is anticipated that the upper weathered section of the profile
within each open cut pit would be amenable to free-digging or removal by scrapers, with the
underlying consolidated material requiring blasting prior to its removal. Blasted overburden will
be removed via excavator and haul truck.
Overburden will initially be removed from the open cut pits and used to create visibility (and
noise shielding) barriers. Once these initial barriers are completed, further overburden would
be transported to overburden emplacement areas, primarily behind the barriers. The barriers
would be progressively extended northwards with the placement of overburden behind the
barriers also moving northwards. When pits are sufficiently developed to permit emplacement
of overburden within the pits, in-pit placement would be undertaken tactically enabling noise-
sensitive haul routes not to be used during adverse meteorological conditions. Overburden
placement would be undertaken using haul trucks and dozers.
Coal Recovery
The coal exposed in each open cut pit would be removed by excavator and transported by
haul truck to the ROM coal stockpile adjacent to the CHPP. Some coal may be dozed or
scraped off due to the steep dips of the seams. Limited low energy blasting may also be
undertaken to fracture the coal exposed in the pit floor once the main floor level is achieved,
thereby potentially enabling the excavator to remove up to a further 15m of coal down the dip
of the seam without any substantial additional overburden removal.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 61
6.1.1.2 CHPP
A 12ha pad will incorporate the CHPP buildings, workshop and associated facilities, and ROM
and product coal stockpiles. The pad would be on the western side of the Mine Area, east of
and adjacent to the western and northern visibility barrier. The pad would be constructed to an
elevation of approximately 115m AHD, i.e. approximately 25m to 40m below the top of the
adjacent western and northern visibility barrier, using cut and fill methods to maximise the
visual and acoustic benefits of the adjacent visibility barrier.
With the exception of the crushing station, rejects stockpile or bin and thickener, the major
plant components would be enclosed within two buildings with a combined floor area of
approximately 1,500m2. The main building would have an overall height of approximately 21m,
with the smaller building which contains the belt filters having a height of approximately 6m.
The CHPP building would be shielded visually and acoustically to the north, west and
southwest by the western and northern visibility barrier. Furthermore, cladding would be
installed on the upper decks, as a minimum, in order to further reduce noise.
The CHPP will be designed such that it is not a significant contributor to the total Mine Area
noise at the most affected receptors. Based on measurements of similar facilities, Wilkinson
Murray considers that a SWL of 110 dBA is achievable for the CHPP, and this has been
included in noise modelling scenarios for periods that the CHPP is proposed to be operational.
6.1.1.3 Overland Conveyor and Rail Load-out Facility
All coal products would be transported to an export terminal at the Port of Newcastle. The
dispatch of coal would involve a two-stage process within the Site. Firstly, product coal would
be conveyed via an overland conveyor to a surge bin and train load-out (TLO) bin within the
Rail Load-out Facility, and secondly, the loading of coal from the TLO bin into trains to be
transported from the Site to the Port of Newcastle. Both activities would operate independently
of each other given sufficient storage capacity would be available in the surge bin and TLO bin
to load one train.
Loading of coal onto the overland conveyor would be achieved by bulldozer or front-end loader
pushing the desired product or product mix from the product coal stockpile into below ground
pan feeders or a similar recovery system which would deposit the coal onto the overland
conveyor.
The products would be conveyed to the Rail Load-out Facility using the overland conveyor at a
rate of approximately 1,500tph.
The coal products would initially be delivered to the surge bin after which they would be
conveyed to the TLO bin at a rate of approximately 3,500tph. Transfer of coal products from
the product coal stockpile would cease once both bins are full.
Trains with a nominal capacity of 3,000t would arrive at the train loop and, after leaving the
North Coast Railway Line, would approach the TLO bin on the uphill grade, thereby enabling
loading to be carried out under tension and minimising shunt/coupling noise. The empty
wagons would be sequentially filled, with the telescopic loading chute lowered to a pre-
determined loading position at the commencement of filling.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 62
Loading of the wagons would be completed within a period of approximately 1.5 hours. The
train would then leave the rail loop at its allocated time to return to the Port of Newcastle.
6.1.2 Meteorological Data used for Noise Predictions
6.1.2.1 Modelling Methodology
The INP generally directs the use of a single set of adverse meteorological data in the
assessment of noise impacts (EPA, 2000). However, for noise modelling in this and other
projects, Wilkinson Murray has adopted the more rigorous approach of predicting noise levels
at nearby receptors for a range of meteorological conditions based on meteorological data
obtained for the locality. The noise modelling presented in this assessment is based on
meteorological data from the GRL meteorological station for the period November 2010
through October 2011. Statistical occurrences of meteorological conditions are then used to
calculate a 10th percentile exceedance noise level (i.e. the level that is exceeded 10% of the
time), which is then compared with relevant criteria.
This alternative assessment procedure involves significantly greater computational complexity
than the use of a single set of meteorological conditions. However, we believe it provides a
more rigorous method of assessing noise exposure, and one that is more easily understood by
the community. In the present case, because meteorological conditions are often more
adverse than the “default” adverse conditions specified the INP, the use of a 10th percentile
exceedance noise level results in a more conservative (that is, a higher) predicted noise level
than would be obtained by strict application of the INP. The approach of using the 10th
percentile calculated noise level as a measure of noise impacts has been accepted by the EPA
for previous similar mining project assessments.
6.1.2.2 Wind Speed and Direction
The data for wind direction and wind speed are classified into eight directional intervals and
five speed intervals (between 0.5 m/s and 3 m/s - with all other instances of wind speed
ascribed as “calm”) in accordance with the INP.
6.1.2.3 Temperature Inversions
Temperature profiles were provided by Pacific Environment Limited. The temperature profiles
for the Gloucester Valley in the vicinity of the Site were extracted from a diagnostic
meteorological model. From these temperature profiles, the temperature inversion strength
(an input parameter into the ENM calculation) was determined by the temperature gradient
between the 10m and 100m heights. This is considered to be a more reliable method than
estimating inversion strength from the Pasquil-Gifford stability class using the method detailed
in Appendix E of the INP. In particular, the Pasquil-Gifford method would limit the possible
inversion strengths to 3°C/100m, whereas using the model outputs, inversion strengths of up
to 8°C/100m were found (although occurrences of inversion strength over 6°C/100m were
rare).
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 63
Figure 6.1 presents the calculated occurrence of temperature inversions throughout the year.
Temperature inversions are clearly expected to be a feature of the area and their prevalence is
such that they would likely dictate the 10th percentile noise level (which is used for comparison
with criteria). The relative prevalence of temperature inversions among seasons is as
expected, with winter exhibiting temperature inversions far more often than summer and the
intermediate seasons, spring and autumn.
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
20%
Day Evening Night
Ind
ivid
ual
Invers
ion
Str
en
gth
s (
co
lum
ns)
-20%
-10%
0%
10%
20%
30%
40%
50%
To
tal
Invers
ion
Occu
rren
ce (
lin
e)
3
4
5
6
7
8 or greater
Total (3 or greater)
Figure 6.1 Percentage Occurrence of Varying Strength Temperature Inversions (°C/100m)
Figure 6.2 shows the predicted percentage occurrence of temperature inversion strengths
equal to or greater than 3°C/100m, in winter. Notably, temperature inversions greater than
4°C/100m are predicted to occur during 39% of the night-time periods, and temperature
inversions greater than 3°C/100m are predicted to occur during 9% of the evening periods. It
is these conditions that will dictate the 10th percentile noise levels for these periods. Had the
Pasquil-Gifford stability class method suggested by the INP been used, temperature inversions
greater than 4°C/100m would not have been considered. In this respect, the methodology
adopted in this assessment is considered more conservative.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 64
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
20%
Day Evening Night
Ind
ivid
ual
Invers
ion
Str
en
gth
s (
co
lum
ns)
-10%
0%
10%
20%
30%
40%
50%
60%
70%
To
tal
Invers
ion
Occu
rren
ce (
lin
e)
3
4
5
6
7
8 or greater
Total (3 or greater)
Figure 6.2 Percentage Occurrence of Temperature Inversions 3.0°C/100m or Greater During Winter
Data from the GRL meteorological station, including temperatures at 2m and 10m from the
ground, were used to investigate the time distribution of temperature inversion conditions. Note
that these data are not considered as reliable as the modelling data used for estimating the
strength of inversions (because they are from a single site and cover a limited range of
heights) but, because these data have better time resolution, they allow understanding of the
temporal pattern of inversion formation. This is particularly important during the evening, as it
can indicate the time at which an inversion will generally begin to become apparent.
The data are for winter only (21 May to 12 July) and therefore represent the worst case for
inversions. The data show that, if the inversion strength is less than 3°C/100m for the hour
beginning 6:00pm, then there is only a 20% chance that the strength will exceed 3°C/100m
over the evening. Conversely, if the inversion strength exceeds 3°C/100m for the hour
beginning 6:00pm, the average for the evening was always above that value.
Our conclusion is that under a monitoring regime requiring changes to operations depending
on meteorological conditions, the likely outcome is that operations would be allowed or not
allowed for an entire evening period based on conditions in the early evening, rather than
being allowed for the early part of the period but not later.
6.1.2.4 Final Modelling Conditions
Modelling of operational noise impacts included consideration of 133 meteorological conditions
during the day and evening periods, and 173 during the night-time period. These were derived
from a full set of 240 conditions – eight wind directions (45° segments); six wind speeds (0.5
m/s bins between 0m/s and 3 m/s); and five temperature inversion strengths (none and
3°C/100m to 6°C/100m in 1°C/100m increments) – after removing combinations that occur so
infrequently as to have no impact on the 10th percentile noise level.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 65
6.2 INVESTIGATION OF FEASIBLE AND REASONABLE NOISE
MITIGATION MEASURES
The Site’s proximity to surrounding noise-sensitive receptors dictated that noise mitigation and
management measures be considered from the outset.
Where feasible and reasonable, proposed operations within the Site have been modified to
reduce potential noise emissions. The noise management measures adopted for all stages of
the Proposal include the following.
Selection of noise-attenuated mobile equipment and/or the implementation of
additional hard controls.
Establishment of a 25m-40m high (above ROM coal pad level) western and
northern visibility barrier extending the length of the western boundary and much
of the northern boundary of the Mine Area. This measure should be implemented
as soon as practicable, with the majority of work being completed during the
construction phase.
Progressive development of central and eastern visibility barriers ahead of
proposed overburden placement.
Progressively filling behind (to the east of) the central and eastern visibility
barriers so that shielding is maximised.
Positioning haul routes as much as possible on the northern and western sides of
open cut pits in order to maximize shielding provided by each pit.
Positioning the northern haul road in cut during Years 2.25 to 4.25 and/or behind
a barrier of subsoil to maintain an 8m vertical separation between the road
surface and the top of the barrier to minimise acoustic exposure to the north.
Positioning the southern haul road as close as possible to the western and
northern visibility barrier and, in the segment rounding south of the Main Pit,
positioning the haul road in cut and behind a barrier so as to create a nominal 8m
vertical separation.
Establishment of 5m high (above road level) barriers on the northern and western
sides of elevated haul routes such as those along the eastern visibility barrier.
Maintaining topsoil and subsoil stockpiles close to operational areas to maximise
shielding.
Implementing active noise management systems whereby (in conjunction with
real-time monitoring) reduced and/or revised operations are undertaken during
adverse meteorological conditions.
Reduced or restricted operations during evening and night-time periods.
Mitigating conveyor noise at the source through selection of quiet systems and,
as a minimum partially enclosing the overland conveyor in exposed locations.
Locating the train load-out bin within the Rail Load-out Facility in deep cut,
thereby maximising shielding.
The assessment has been based on the above mitigation and management measures.
Measures that are specific to individual stages of the mining operations are discussed
Section 6.4.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 66
Further measures to manage noise impacts at those residences nominated to be located
within either the noise management zone or noise affectation zone are outlined in
Section 6.10.
6.3 FLEET LIST AND SOUND POWER LEVELS
Table 6.1 presents the list of equipment, plant sound power levels and the period of operation
of plant (i.e. day/evening or night) used during the various periods of mine operations. The
sound power levels given in Table 6.1 are conservative in that they are based on plant
operating at maximum capacity for an entire 15 minutes.
The equipment operating in each scenario has been matched with the anticipated material
movement (overburden and ROM coal) for each of the distinct phases. If the ROM coal
production rate is increased to the maximum of 2.5 Mtpa from the 2Mtpa considered in the
modelled scenarios, this would be achieved through a reduction in overburden movement. As
such the mobile equipment would remain essentially unchanged and predicted levels would be
very similar to those of the assessed scenarios.
It is noted that the two types of haul trucks to be used on site each have a sound power level
of 113dB(A). As such, the Applicant would be able to use either type of truck on the assessed
haul routes.
Table 6.1
Indicative Mobile Equipment List
Year 1 Years 2 – 4 Years 5 – 8 Years 9 – 14
Overburden Moved (Annual bcm) 6 554 000 7 848 000 – 8 466 000
12 353 000 – 13 424 000
9 367 000
Coal Extracted (Annual t) 600 000 1 330 000 – 1 700 000
1 983 000 – 2 000 000
2 000 000
Type Model SWL
(dB(A))
Year 1 Year 2 – 4 Year 5 – 8 Year 9 – 14
D E D E N D E N D E N
Drill Rotary SKF12 118 1 1 1 1 1 2 2 0-1 2 2 2
Excavator 40t (345D) 107 1 0 1 0 0 1 0-1 0-1 1 1 0
120t (PC1250) 115 1 0 1 0-1 0 1 1 0-1 1 1 1
200t (994-200) 116 1 1 1 1 0 1 1 0-1 1 1 0-1
350t (EX3600) 116 1 1 1 1 0-1 1-2 1-2 0-2 2 2 0-2
Haul truck Cat 789XQ and Haulmax
113 8 6-8 9-12 6-12 3-4 12-14 12-14 8-13 15-16 15-16 4-6
Scraper 657G 114 3 0 3 0 0 1-3 0 0 1 0 0
Grader 14M 108 1 1 1 1 1 1-2 1-2 1 1-2 1-2 1
Front end Loader
Cat 988 112 0 0 1 0-1 0 1 1 0-1 1 1 0
Bulldozer D10/D11 111/113 2 1 3 1-2 0-1 3 3 2 3 3 1-2
Rubber Tyred 844RTD
111 1 1 1 1 0 1-2 1-2 0 2 2 0-1
Water Cart
Road Truck and Cat 777C
107 114
2 1-2 2 1-2 1-2 2 2 2 2 2 1-2
Bobcat 107 0 0 1 0-1 0 1 1 0-1 1 1 0
D = Day E = Evening N = Night
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 67
The INP includes a number of “modifying factors” which may result in adjustment to the
effective sound power level of noise sources. The factors that may potentially be relevant in
this case are for tonal, impulsive and low-frequency noise.
In the case of tonal noise, the only significant potential sources are reversing alarms. In this
respect, GRL has committed to using broad-band reversing alarms for all equipment used on
the site.
For impulsive noise, the most important potential sources are impacts occurring during train
loading. Much of the impact noise will be mitigated by ensuring that all loading of wagons will
be undertaken under tension, as noted in Section 6.4.4. Any residual impulsive noise would
form a relatively minor part of the total noise emission from the Site, and the overall noise as
heard at privately-owned residences would not meet the definition of “impulsive” noise in the
INP.
As required by the EPA, low-frequency noise is considered separately and in detail in
Section 6.5, using more sophisticated assessment techniques than those in the INP. There it
is concluded that additional impacts due to low-frequency noise content are unlikely.
6.4 PREDICTED OPERATIONAL NOISE LEVELS
6.4.1 Introduction
The predicted 10th percentile LAeq,15 minute operational noise levels at each receptor are
presented in the following subsections for each of the modelled scenarios.
Following initial investigations, an active noise management strategy was determined for each
of the five operational scenarios, under which operations would be restricted under certain
meteorological conditions, with unrestricted operations at all other times. This was determined
on the basis of maximising the noise benefit of the strategy while minimising the disruption to
all on-site operations and was undertaken in consultation with the Applicant’s mine designers
and planners. The restrictions on operations, together with the predicted percentage of time
within each season during which the restrictions would be likely are presented in Tables 6.2,
6.4, 6.6, 6.8 and 6.9. The applicable restrictions are shown separately for each stage. Noise
levels were calculated assuming these restrictions are in place, and the 10th percentile
exceedance value was calculated at each receptor over all seasons. The maximum 10th
percentile value in any season is then compared with relevant criteria. Predicted noise levels
are rounded to the nearest 1 dBA.
With regard to evaluating predicted results against criteria, the rationale detailed in Section 5.2
is applied herein. The results tables (i.e. Tables 6.3, 6.5, 6.7, 6.9, 6.11, 6.12 and 6.13) are
presented using the following convention.
Light Green – predicted to be within criteria.
Yellow – predicted to exceed criteria by 2 dB or less, which represents a level
difference which is unlikely to be perceptible by most people. These predictions
are also within the accepted error associated with the modelling process, which
typically is slightly conservative. These receptors represent those in the “Noise
Management Zone”.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 68
Orange dots – predicted to exceed criteria by 3-5 dB, which represents a
moderate exceedance. These receptors also represent those in the “Noise
Management Zone”.
Pink/Rose striped – predicted to exceed by greater than 5 dB. These receptors
represent those in the “Noise Affectation Zone”.
Noise contours have been produced from a single adverse meteorological condition and are
indicative of the 10% exceedance level. For this reason, there may be some discrepancy
between noise contours and discrete receptor predictions in the figures and tables presenting
results. In all cases, the discrete receptor predictions presented in the tables should be relied
upon over the noise contours. In presenting noise contours, the 35 dBA contour is highlighted
as the “typical criterion”, as it represents the most stringent noise criterion for the majority of
potentially-affected privately-owned receptors.
6.4.2 Mining Operations
6.4.2.1 Year 0.5
This scenario represents the early stages of the Proposal. Though this stage is akin to a
“construction” stage, the Interim Construction Noise Guideline (ICNG) states that activities
such as bulk earthmoving etc., which are consistent with the operational activities of the mine,
should be assessed against operational noise criteria detailed in the INP. This is the approach
which has been taken in the present section. There will also be activities associated with
construction of the overland conveyor and Rail Load-out Facility that are clearly distinct from
operational noise sources within the Mine Area, and these are assessed in Section 8 under the
ICNG’s guidelines for construction noise.
Some aspects of this stage necessitate mobile plant operating in exposed locations whilst
constructing noise mitigation barriers. It is proposed to control noise emissions during this
construction as much as possible through active noise management, however temporarily
elevated noise levels would at times be unavoidable. The EPA has, in the past, accepted
exceedances associated with such activities which are required to provide a subsequent
environmental benefit.
The main earthmoving activities undertaken during this stage primarily relate to:
stripping topsoil and subsoil;
removal of overburden; and
transportation and placement of overburden to form the western and northern
and eastern visibility barriers.
The active noise management strategy determined for this scenario is detailed in Table 6.2.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 69
Table 6.2
Active Noise Management Strategy Year 0.5
Meteorological Conditions and/or Times
Activities / Measures
Percentage Occurrence
Aut
%
Spr
%
Sum
%
Win
%
Daytime
E / SE / S wind >0.5m/s or NE wind >1.5m/s; or
Temperature inversions > 3.0°C/100m.
Do not operate scrapers in exposed areas (as indicated in Figure 6.3); and
Operate [Rubber Tyred Dozer] and [Drill Rig] in location shielded to the north and west (e.g. not atop the western barrier).
14 9 13 15
Evening
All met conditions
Operate a reduced fleet comparable to Figure 6.5.
Operate [Rubber Tyred Dozer] and [Drill Rig] in location shielded to the north and west (e.g. not atop the western barrier).
100 100 100 100
Evening
E / SE wind >1.5m/s or S wind >2m/s;
Temperature inversions > 3.0°C/100m with E / SE wind >1.5m/s or S wind >2m/s;
Temperature inversions > 4.0°C/100m with NE / E / SE wind >0.5m/s or S wind > 1m/s; or
Temperature inversions > 5.0°C/100m.
Do not operate D11.
15 16 14 19
Night-time No significant night operations. -
Figure 6.3 and Figure 6.5 respectively show the locations of the mobile plant for the purpose
of noise modelling the Year 0.5 Day and Evening scenarios. No activities are proposed during
the night-time period.
Figure 6.4 and Figure 6.6 respectively present the predicted noise levels for the Year 0.5 Day
and Evening scenarios. Each of the dots represents a receptor and the colour of the dot
indicates the predicted noise level (see figure legend for ranges). Noise levels for the
maximum of all seasons for each period are shown (e.g. for the day period, the maximum of
autumn day, spring day, summer day and winter day noise levels are shown).
Table 6.3 presents a summary of predicted noise levels at the six receptors predicted to
experience exceedances of criteria. Predictions for each time period and season are
presented.
Predicted noise levels for all receptors are included in Appendix 2.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 70
Figure 6.3 Year 0.5 Day Plant Layout
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 71
Noise contours have been produced from a single adverse meteorological condition and are indicative of the 10% exceedance level.
Figure 6.4 Year 0.5 Day – Predicted 10% Exceedance LAeq,15min (dBA)
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 72
Figure 6.5 Year 0.5 Evening Plant Layout
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 73
Noise contours have been produced from a single adverse meteorological condition and are indicative of the 10% exceedance level.
Figure 6.6 Year 0.5 Evening – Predicted 10% Exceedance LAeq,15min (dBA)
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 74
Table 6.3
Year 0.5 Noise Levels for Receptors where Exceedances are Predicted
Residence No.
Criteria (Day/Eve)
Predicted 10% Exceedance LAeq,15min (dBA)
Summer Autumn Winter Spring
Day Evening Day Evening Day Evening Day Evening
6 35 / 35 39 33 39 36 39 37 38 34
18 35 / 35 39 39 39 38 39 38 38 39
19A 35 / 35 38 39 37 38 38 38 36 39
56A 35 / 35 35 37 35 35 35 36 34 36
154 35 / 35 37 36 37 36 37 36 36 36
193 35 / 35 37 37 37 37 37 37 36 37
< Criterion Criterion to Criterion + 2dB Criterion + 3dB to Criterion + 5dB > Criterion + 5dB
The results show that in the worst-case season for all modelled receptors:
noise levels are predicted to be within criteria at the majority of noise-sensitive
receptors;
during the daytime, noise levels at two privately-owned receptors (154 and 193)
are predicted to exceed the criteria by less than 2 dB (yellow), and three
privately-owned receptors (6, 18, and 19A) by 3-5 dB (orange dots); and
during the evening, noise levels at four privately-owned receptors
(6, 56A, 154 and 193) are predicted to exceed criteria by less than 2 dB (yellow),
and two privately-owned receptors (18 and 19A) by 3-5 dB (orange dots).
It should be noted that these results indicate a typical worst case snapshot of the construction
period, when it would be necessary to operate the mobile plant in unshielded positions,
particularly during the construction of the western and northern visibility barrier.
The modelled Year 0.5 scenario reflects a time when the western visibility barrier is partially
constructed and its construction is progressing northward. It is anticipated that this scenario
will be representative of noise emissions for the majority of the visibility barriers construction.
However, more elevated noise levels may be experienced by receptors to the north when
construction is at its most northern extent. Predictions indicate that noise levels in Avon River
and Thunderbolt Estates during these periods could be approximately 1 dBA greater than
those presented for the Year 0.5 scenario. As with all operations at the mine, the noise
emissions will be managed through the use of real-time noise monitoring and management,
however, some exceedances may be temporarily unavoidable as the construction of this
critical noise mitigation feature is undertaken. It is proposed that construction activities on the
northern section of the barrier exceeding operational noise criteria, which would be undertaken
over a maximum period of six months, will be undertaken within EPA standard construction
hours (Section 8.1). Any work outside these standard construction hours will be managed
within operational noise criteria through the proposed real-time noise monitoring system.
Given the prevalence of winds from the north east in summer and, to a lesser extent in spring,
to the extent practicable, barrier construction activities in the north should be programmed
during these seasons or during periods when noise propagation is away from the residences in
the Avon River and Thunderbolt Estates.
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 75
6.4.2.2 Year 2.5
This scenario represents the early stages of significant coal recovery. The active noise
management strategy determined for this scenario is shown in Table 6.4.
Table 6.4
Active Noise Management Strategy Year 2.5
Meteorological Conditions and/or Times
Activities / Measures
Percentage Occurrence
Aut
%
Spr
%
Sum
%
Win
%
Day
S wind >0.5m/s, NE / E / SE wind >1m/s or NE wind >2.5m/s; or
Temperature inversions > 3°C/100m.
Do not operate scrapers in exposed areas (as indicated in Figure 6.7).
16 12 13 18
Evening
All met conditions
Operate a reduced fleet comparable to Figure 6.9. 100 100 100 100
Night
All met conditions
Operate a reduced fleet comparable to Figure 6.11. 100 100 100 100
Figure 6.7, Figure 6.9 and Figure 6.11 respectively show the locations of the mobile plant for
the purpose of noise modelling for the Year 2.5 Day, Evening and Night scenarios.
Figure 6.8, Figure 6.10 and Figure 6.12 respectively present the predicted noise levels for the
Year 2.5 Day, Evening and Night scenarios. Each of the dots represents a receptor and the
colour of the dot indicates the predicted noise level (see figure legend for ranges). Noise
levels for each season for each period are shown (e.g. for the day period, the maximum
autumn day, spring day, summer day and winter day noise levels are shown).
Table 6.5 presents a summary of predicted noise levels at the three receptors predicted to
experience exceedances of criteria. Predictions for each time period and season are
presented.
Predicted noise levels for all receptors are included in Appendix 2.
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 76
Figure 6.7 Year 2.5 Day Plant Layout
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 77
Noise contours have been produced from a single adverse meteorological condition and are indicative of the 10% exceedance level.
Figure 6.8 Year 2.5 Day – Predicted 10% Exceedance LAeq,15min (dBA)
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 78
Figure 6.9 Year 2.5 Evening Plant Layout
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 79
Noise contours have been produced from a single adverse meteorological condition and are indicative of the 10% exceedance level.
Figure 6.10 Year 2.5 Evening – Predicted 10% Exceedance LAeq,15min (dBA)
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 80
Figure 6.11 Year 2.5 Night Plant Layout
SPECIALIST CONSULTANT STUDIES GLOUCESTER RESOURCES LIMITED Part 1: Noise, Vibration and Blasting Assessment Rocky Hill Coal Project
Report No. 806/04
1 - 81
Noise contours have been produced from a single adverse meteorological condition and are indicative of the 10% exceedance level.
Figure 6.12 Year 2.5 Night – Predicted 10% Exceedance LAeq,15min (dBA)
GLOUCESTER RESOURCES LIMITED SPECIALIST CONSULTANT STUDIES
Rocky Hill Coal Project Part 1: Noise, Vibration and Blasting Assessment
Report No. 806/04
1 - 82
Table 6.5
Year 2.5 Noise Levels for Receptors where Exceedances are Predicted
Res. No.
Criteria (D/E/N)
Predicted 10% Exceedance LAeq,15min (dBA)
Summer Autumn Winter Spring
D E N D E N D E N D E N
6 35 / 35 / 35 41 39 39 41 40 40 41 40 42 41 39 40
7 35 / 35 / 35 34 32 33 35 35 36 35 36 37 34 34 35
23 35 / 35 / 35 39 36 37 39 38 39 39 38 40 38 37 38
< Criterion Criterion to Criterion + 2dB Criterion + 3dB to Criterion + 5dB > Criterion + 5dB
The results show that in the worst-case season for all modelled receptors:
noise levels are predicted to be within criteria at the majority of noise-sensitive
receptors;
during the daytime, noise levels at one privately-owned receptor (23) are
predicted to exceed the criteria by 3-5 dB (orange dots) and another privately-
owned receptor (6) by greater than 5 dB (pink/rose striped);
during the evening, noise levels at one privately-owned receptor are predicted to
exceed criteria by less than 2 dB (yellow), and two privately-owned receptors (6
and 23)by 3-5 dB (orange dots); and
during the night, noise levels at one privately-owned receptor (7) are predicted to
exceed criteria by less than 2 dB (yellow), one privately-owned receptor (23) by
3-5 dB (orange dots) and another privately-owned receptor (6) by greater than
5 dB (pink/rose striped).