    NICMAR CODE 2013-14 ASSIGNMENT1 NCP22- Construction Personnel Management

    Submitted by: Murali Krishna Naidu, Reg No 213-05-11-11534-2153 Page 2

    Resolving site problem and enhancing output of workforce

    Name of the Project:

    3 k.m. Long Tunnel

    1.Introduction:

    ABC company bagged a project to construct a tunnel of 3 k.m long in a remote

    mountainous place where living or working conditions are very remote from main

    residential place, congestive, unworthy and unhygienic. As the nature of work in a

    tunnel, the risk of lives is very high from the safty point of view. As the entry of

    the tunnel is on a foot of hill, establishment of labour camps, dwellings for the

    skilled, unskilled workers is difficult and focricbly, they are to be located in the

    nearest town. As the work site is far from residential location, no rest rooms,

    workers get frustrated very frequently after working for small hours. The

    movement of the workers in the tunnel is restricted and hence, makes the worker

    to constraint himself from free movement. People with a habit of smoking will get

    annoyed and show their uneasiness on the fellow workers without any reason. For

    any small untoward mishap, workers get agitated, yell against the Project Manager

    and in the absence of any Personnel Officer and Safty Officer, the things would

    become worse. Project Manager being head of the project, involved mainly on the

    mobilization of resources and transforming the output into making payment

    certificates, will never able to allot time to see the ground conditions.

    The non living conditions lead to un healthyness of the workers, seeking

    temporary relief through consumption of liquor, indebtedness, prejudice,

    jealousness, etc destabilizing the harmony among the people. When such a

  • 8/13/2019 NICMAR-Assignment_NCP22_1

    3/10

    NICMAR CODE 2013-14 ASSIGNMENT1 NCP22- Construction Personnel Management

    Submitted by: Murali Krishna Naidu, Reg No 213-05-11-11534-2153 Page 3

    condition prevails, the top level managers, officers being able to afford the price,

    will be away from the scene of instability and thus catalyses the total

    pandemonium at work site. When workforce is living in such a condition, the result

    will be loss of time and quality of work.

    2. Problems identified:

    Thus we can summarise the site problems into the following categories viz.,

    absenteeism due to unhealthy conditions, absenteeism due to consumption of

    liquor leading to quarrels & conflicts between work groups, unwanted accidents at

    site, technical problems due to lack of timely attendance by supervision staff.

    Various reasons could be made attributable for the aforesaid problems and

    identify the needs and ways and measures to fulfill them through a thorough

    assessment.

    3. Needs and fulfillment plan:

    a) Lack of Planning of manpower management:

    We can say deficit in manpower management if the following norms/feastures are

    visible:

    No activity based work sharing plan for both skilled and unskilled personnel No responsibility assigned to work force at any stage/level No communication system between different departments in the project No future plan for bridging gaps of deficit manpower at peak work season No recognition of achievements of work force by means of any kind of

    gestures by the organization

  • 8/13/2019 NICMAR-Assignment_NCP22_1

    4/10

    NICMAR CODE 2013-14 ASSIGNMENT1 NCP22- Construction Personnel Management

    Submitted by: Murali Krishna Naidu, Reg No 213-05-11-11534-2153 Page 4

    To overcome the above mentioned conditions, the following measures are to be

    implemented.

    A well defined organization structure is made with the followingrequirements of the project

    o Scope of project is mainly earthwork based tunneling using heavyboring machinery which involves personnel from the trades of civil

    and mechanical engineering. Hence, it requires unskilled workers also

    to support the technical managers as wells as supporting

    superviors/foremen

    o The work is to be carried out in a season otherthan monsoon seasonto control seepage of water. Normally, in the non monsoon season,

    the availability of unskilled workers is abundant. To supervise the

    unskilled workers, at every stage, a responsible foremen/work

    supervisor is planned so that they will not be made into non

    performing work groups

    o The activities are scheduled and assigned with defined duration ofeach task. Unless there is a mechanical failure or breakdowns, the

    stipulated activities could be performed within time. As the work

    schedules are made tight, the workers will be offered to work in

    shifts to gain working time in a day.

    o In addition to the normal personnel department who takes care aboutwelfare of the workers, an experienced Occupational Safty and

    Health Officer also needed in the project team.

  • 8/13/2019 NICMAR-Assignment_NCP22_1

    5/10

    NICMAR CODE 2013-14 ASSIGNMENT1 NCP22- Construction Personnel Management

    Submitted by: Murali Krishna Naidu, Reg No 213-05-11-11534-2153 Page 5

    With the above requirements, the following organizational structure is

    made to achieve more task oriented project team.

    ORGANISATION STRUCTURE

    b) Improving Working conditions at site:

    Work site shelters for different levels of organistion structure would beconstructed to give relief for the workers after attending work

    The shelters will be provided with good ventilation and illuminationconditions.

    Drinking Water will be provided at all important work places

    Project

    Manager

    Manager

    Admn&

    Finance

    Manager

    Accounts

    Manager

    Constructio

    n (Civil)

    Manager

    Constructio

    n

    Manager

    Constructio

    n (Electrical)

    Site

    Engineers

    Foremen /

    Supervisor/

    Surveyors

    Unskilled

    Workers

    Safty

    Officer

    Personnel

    Officer

    Personnel

    Executive

    Mechanic

    al

    Worksho

    Site

    Engineers

    Foremen/Te

    chnician/

    Mechanic

    Operators

    / Drivers

    Site

    Engineers

    Foremen /

    Mechaincs /

    Technicians

    Unskilled

    workers

    Unskilled

    workers

    Accounta

    nts

    Quality

    Control

    Lab

    Lab

    Assistant

    Field

    Assistants

  • 8/13/2019 NICMAR-Assignment_NCP22_1

    6/10

    NICMAR CODE 2013-14 ASSIGNMENT1 NCP22- Construction Personnel Management

    Submitted by: Murali Krishna Naidu, Reg No 213-05-11-11534-2153 Page 6

    Communication facility shall be provided for the workers to contact theirfamilies from the residing place so that they will feel a sense of security.

    If possible, commutation of workers from the residential location to workspots shall be arranged along with the technical personnel to build team

    spirit among the members of the teams.

    C) Welfare of workers:

    Common entertainment halls to view television or movies so that theworkers will be occupied at all awakening times

    Food plaza to provide breakfast, lunch and dinner to the workers atsubsidised price would be provided. If possible, they may be provided at

    free of cost as workers time and health is very important at the location.

    This may not be costlier than the value of time during breakdown of

    activities and amount of liquidated damages imposed by the client at later

    stages when the project is behind the intended completion date.

    For all workers in shifts at work locations would be provided with on sitelunch/dinner packets to save commutation between site and dining halls.

    This could be achieved with the available resource persons and machinery.

    Routine and periodical health check up system is planned with the help oflocal consulting doctors in most common sicknesses.

    A dedicated and qualified Health Worker would be engaged to attend roundthe clock supervision of all health requirements, escorting the workers to

    hospitals or dispensaries in near town.

  • 8/13/2019 NICMAR-Assignment_NCP22_1

    7/10

    NICMAR CODE 2013-14 ASSIGNMENT1 NCP22- Construction Personnel Management

    Submitted by: Murali Krishna Naidu, Reg No 213-05-11-11534-2153 Page 7

    Comprehenssive All Risk Worker Insurance Policy will be taken from reputedinsurance company to cover any fatalities in the work site.

    d) Avoiding Liquor availability at site:

    Consultation would be made with the local government authorities tocontrol illegal and illicit alcohol trafficking in the area.

    Employees and workers will be informed that any unauthorized consumptionof liquor would be penalized and suitable disciplinary action would be

    initiated.

    Consumption of alcohol by unskilled workers will be controlled by enforcingsuitable arrangements for breathing test at work gates before the enter the

    work sites.

    To avoid consumption, the identified worker groups will be engaged withsocial activities like gardening, cleaning for which they will be given

    incentives.

    Regular de-addition camps would be planned to motivate the workers toadopt good health practices

    e) Storage of materials:

    As the nature of work involves with tunneling in hard rock, necessity of blasting

    using explosives would be there and thereby, handling, processing, operating the

    blasting activities involves high risk of life of workers. The following actions are

    planned to minimize the risks and mishaps.

  • 8/13/2019 NICMAR-Assignment_NCP22_1

    8/10

    NICMAR CODE 2013-14 ASSIGNMENT1 NCP22- Construction Personnel Management

    Submitted by: Murali Krishna Naidu, Reg No 213-05-11-11534-2153 Page 8

    All blasting operations would be carried out by a licensed explosivespecialist under the direct supervision of the safety officer.

    All work locations would be displayed with caution boards and sign boardsinforming the workers about the intended blasting operations.

    All explosive materials would be stored as per BSI standards and regularmaterial account check will be conducted to control any mis utilization.

    Quality materials like explosives, conductors will be procured to achieve100% blasting avoiding accidents due to delay blasts leading to fatality.

    f) Seepage of water:

    Seepage of water is a main concern in the construction of tunnels. This

    phenomenon will delay the process of making punctures in the horizontal rock

    strata and may cause loss to the company if mechanical boring equipment is used

    completely for the excavation of rock. Water flow in the cleavage lines of the

    stratifications and unless controlled, the moisture may sometimes loosen the roof

    of the tunnel to make the portion of earth to slip and close the tunnel. The

    following actions are proposed to control the damages:

    The topography of the area under which the tunnel is planned is analysedand proposed with suitable drainage system to let out any surface flows

    immediately away from the work zones

    Work methodology programs will be prepared and submitted to the clientfor approval to avoid any damage in claim at later stage

  • 8/13/2019 NICMAR-Assignment_NCP22_1

    9/10

    NICMAR CODE 2013-14 ASSIGNMENT1 NCP22- Construction Personnel Management

    Submitted by: Murali Krishna Naidu, Reg No 213-05-11-11534-2153 Page 9

    Lean and dry working season will be planned to take up high risk zones toavoid any smallest seepages.

    If possible cement gunniting will be done at suitable locations to avoildseepage through stratifications.

    g) Roof spalling:

    Roof spalling or collapsing of top of tunnel portion is a commonly expected

    outcomes at any stage of work till the tunnel surfaces are tied with proper

    cementing materials.

    The parameters for spalling such as type of formation of rock, foliations inthe rock, homogeneity of rock formation etc would be thoroughly examined

    Loose materials would be removed at the time of boring/excavations Cement/Concrete gunniting will be applied to the tunnel top surfaces

    wherever loose pockets are attended

    Appropriate supporting ribs with steel or good timber props will be done atregular intervals to arrest any future spalling

    Advance procurement of all support materials will be planned and kept atsite to meet the demand at any hour of time

    h) Conclusion:

    The management is requested to make a disaster management team headed

    by a responsible person at Director level to take any direct decisions at crucial

    hours of occurance of any mishap to gain the confidence of fellow workers.

  • 8/13/2019 NICMAR-Assignment_NCP22_1

    10/10

    NICMAR CODE 2013-14 ASSIGNMENT1 NCP22- Construction Personnel Management

    Submitted by: Murali Krishna Naidu, Reg No 213-05-11-11534-2153 Page 10

    All the management levels in the organization structure will be given with

    suitable roles and responsibility charts to act in time and achieve a well defined

    work output.

    A weekly work review meeting will be organized and work out put will be

    quantified to get verified by the head of the projects to mitigate any lapses or

    gaps in the progress. After consulting with construction managers, suitable

    corrective measures will be proposed to the Directors for bridging the gaps and

    take their permission to implement in the forthcoming weeks such that the project

    would be completed in time and with good quality.

    Frequent visits by the Directors will enhance the feelings of togetherness

    among the workers and there by every work groups will be alerted to complete

    their assigned roles or tasks.

    Interactions with family members of workers on a most celebrated day like

    formation date of company, would give security feeling among the workers and

    their family members.

    With the above working and possible measures, the output of the work

    groups could be enhanced.

    Bibliogrphy & References:

    1. NICMAR Session book2. Ogranisational Management by Koontz and Odoneal, McGraw Hill Publishers3. Management in construction industry by Prof KN Vaid NICMAR Publications.

    Submitted by :

    Murali Krishna Naidu,SODE Reg No. 213-05-11-11534-2153