NH DEPARTMENT OF TRANSPORTATION * DIVISION OF PROJECT DEVELOPMENT

ADVERTISING SCHEDULE

Federal Fiscal Years

2018-2019

n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
August 1, 2014
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Rectangle
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text
July 2018
n46lbd
Typewritten Text
n46lbd
Typewritten Text
n46lbd
Typewritten Text

Project Previous Ad Date Revised Ad Date Explanation

Statewide 40803 July 10, 2018 July 17, 2018

Project delayed by Project Development (Highway

Design) to complete contract proposal

Laconia 16144 June 26, 2018 July 24, 2018

Project delayed by Project Development (Bridge

Design) to address Right-of-Way (ROW)

clearance

Ossipee 14749 July 10, 2018 July 24, 2018

Project delayed by Project Development (Highway

Design) to complete contract proposal

Litchfield 29733 August 14, 2018

New project through Turnpike Bureau for building

demolition

Hopkinton 41303 November 6, 2018 August 14, 2018

Project advanced by Project Development (Bridge

Design) within bridge perservation program

Statewide 41614 January 22, 2019 September 11, 2018

Pavement preservation project advanced by

Project Development (Highway Design)

Alexandria 15937 August 21, 2018 October 16, 2018

Project delayed by Project Development (Highway

Design) to address wetland permit clearance

Warren 41738 September 4, 2018 December 11, 2018

Project delayed by Project Development (Highway

Design) to address wetland permit and ROW

clearance

Lebanon 25821 October 23, 2018 January 8, 2019

Project delayed by Project Development (Bridge

Design) to coordinate with City infrastructure

projects

Lebanon 41191 November 3, 2020 March 19, 2019

Project advanced by Project Development (Bridge

Design) for funding under HB 1817

Bedford-Merrimack

16100 November 6, 2018 November 12, 2019

Project delayed by Turnpikes to allow for

Legislative study on AET

Advertisement Schedule Changes for NHDOT Managed Projects

from June 2018 to May 2019

07/02/18Print Date: 2018 Page 1 of 11

Fiscal Year

2018

NH 123A Replace Red List Bridge carrying NH 123A over Bowers Brook (113/064)[Bridg-T3-4-Rehab-Rcn, None-Bridge, None-Highway]

NH 113 Bridge Replacement of bridge carrying NH 113 over Bearcamp River[Bridg-T3-4-Rehab-Rcn, None-Bridge]

NH 114 Replace Kanakis salted well[WELLS]

NH Route 1A Interim repairs to the Hampton Harbor bascule lift bridge carrying NH 1A over Hampton River[BET-BMT-BD, Bridg-HIB-Main-Pres]

US 302/NH 16 Preservation BWC overlay from US 302/NH 16 intersection to Conway/Bartlett Town Line[Pave-T2-Preserve]

St. Gaudens Road Reconstruct 3,750 feet of Saint Gaudens Road from NH Route 12A to the Visitor's Center[FLAP]

Various Preservation response to stabilize various bridges from scour.[BRPPI *, Bridg-T1-2-Main-Pres, Bridg-T3-4-Main-Pres]

SOUTH RD Repair Giard salted well by installing Jaswell Seal[WELLS]

Old County Road Replace Riners salted well[WELLS]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

ACWORTH 16301 X-A001(226)

TAMWORTH 16239 X-A001(205)

WEARE 41496A

SEABROOK - HAMPTON 41510 X-A004(658)

CONWAY 41335 X-A004(600)

CORNISH 40296 X-A004(378)

STATEWIDE 27287 X-A003(473)

DEERFIELD 41496D

DUBLIN 41496B

Project Name / Number

October Monthly Total

November Monthly Total

$1,234,600

$2,499,700

$19,700

$432,800

$1,891,800

$638,800

$994,600

$13,700

$20,600

$0

$0

$0

$432,800

$1,891,800

$127,800

$994,600

$0

$0

10-Oct-17

17-Oct-17

17-Oct-17

14-Nov-17

28-Nov-17

28-Nov-17

28-Nov-17

05-Dec-17

05-Dec-17

$3,754,000

$3,958,000

$0

$3,447,000

NH DEPARTMENT OF TRANSPORTATION * DIVISION OF PROJECT DEVELOPMENT

ADVERTISING SCHEDULE

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

October 2017

November 2017

December 2017

Contact Person: Joseph Adams

Contact Person: Joseph Adams

Contact Person: Roger Appleton

Contact Person: Bob Landry

Contact Person: Tobey Reynolds

Contact Person: Ron Grandmaison

Contact Person: David Scott

Contact Person: Roger Appleton

Contact Person: Roger Appleton

07/02/18Print Date: 2018 Page 2 of 11

Fiscal Year

2018

NH 10 Replace Stanhope salted well[WELLS]

Mill Street Replace Red List Bridge carrying Mill Street over Abd RR & multi-use trail (Br No 215/158)[Bridg-T3-4-Rehab-Rcn, None-Bridge]

I-95, NH 16, US 3, FEET, I-293 and I-93 Statewide Striping[TRR *]

Woodbury Ave. , Market St., Granite St. Upgrade 5 existing traffic controllers and interconnects on Woodbury Ave. Market St. and Granite St[CMAQ *, NON-PAR (other)]

Various Roadway resurfacing, various locations in District 1 for CY 2018/FY 2019.[Pave-T2-Maintain, Pave-T2-Preserve, Pave-T2-Resurf, Pave-T3-4-Maintain, Pave-T3-4-Preserve, Pave-T3-4-Resurf]

Various Resurfacing various Tier 2, 3, and 4 roadways in District 1.[Pave-T3-4-Maintain, Pave-T3-4-Preserve, Pave-T3-4-Resurf]

Various Roadway resurfacing, various locations in District 2 for CY 2018/FY 2019.[Pave-T2-Maintain, Pave-T2-Resurf, Pave-T3-4-Maintain, Pave-T3-4-Preserve, Pave-T3-4-Resurf]

Various Resurfacing various Tier 2, 3, and 4 roadways in District 2.[Pave-T2-Maintain, Pave-T2-Resurf, Pave-T3-4-Maintain, Pave-T3-4-Preserve, Pave-T3-4-Resurf]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

ORFORD 41496C

HAVERHILL 16238 X-A001(204)

STATEWIDE STRIPING (TURNPIKES) 41099

PORTSMOUTH 29781 X-A004(304)(LPA)

DISTRICT 1 16161G

DISTRICT 1 41651

DISTRICT 2 16162G

DISTRICT 2 41652

Project Name / Number

First Quarter Total

December Monthly Total

January Monthly Total

$22,000

$1,176,800

$326,100

$1,410,500

$4,114,100

$2,624,400

$3,843,100

$1,877,200

$0

$1,176,800

$0

$496,400

$0

$0

$0

$0

05-Dec-17

19-Dec-17

09-Jan-18

05-Feb-18

06-Feb-18

06-Feb-18

06-Feb-18

06-Feb-18

$1,233,100

$326,100

$1,176,800

$0

$8,945,100 $4,623,800

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

December 2017

January 2018

February 2018

Contact Person: Roger Appleton

Contact Person: Joseph Adams

Contact Person: David Smith

Contact Person: Tom Jameson

Contact Person: Eric Thibodeau

Contact Person: Eric Thibodeau

Contact Person: Eric Thibodeau

Contact Person: Eric Thibodeau

07/02/18Print Date: 2018 Page 3 of 11

Fiscal Year

2018

Various Roadway resurfacing, various locations in District 3 for CY 2018/FY 2019.[Pave-T2-Maintain, Pave-T2-Resurf, Pave-T3-4-Maintain, Pave-T3-4-Preserve, Pave-T3-4-Resurf]

Various District 3 Paver Spot Drag Shim.[Pave-DrgShm]

Various Resurfacing various Tier 2, 3, and 4 roadways in District 3.[Pave-T3-4-Maintain, Pave-T3-4-Rehab, Pave-T3-4-Resurf]

Various District 3 Paver Spot Drag Shim.[Pave-DrgShm]

Various Roadway resurfacing, various locations in District 4 for CY 2018/FY 2019.[Pave-T3-4-Maintain, Pave-T3-4-Preserve, Pave-T3-4-Rehab, Pave-T3-4-Resurf]

Various District 4 Paver Spot Drag Shim.[Pave-DrgShm]

Various Roadway resurfacing, various locations in District 5 for CY 2018/FY 2019.[Pave-T2-Maintain, Pave-T2-Rehab, Pave-T2-Resurf, Pave-T3-4-Maintain, Pave-T3-4-Preserve, Pave-T3-4-Resurf]

Various Roadway resurfacing, various locations in District 6 for CY 2018/FY 2019.[Pave-T2-Maintain, Pave-T2-Resurf, Pave-T3-4-Maintain, Pave-T3-4-Preserve, Pave-T3-4-Resurf]

Various District 6 Paver Spot Drag Shim.[Pave-DrgShm]

Spaulding Turnpike and I-95 Eastern Tpk Resurfacing:NH16 MM 9.2-12.7;Indian Brook Dr;Ramps @ NH16 Exit 9 & I-95 Exit 3 Ramps[TRR *]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

DISTRICT 3 16163G One Contract With 40933

DISTRICT 3 40933 One Contract With 16163G

DISTRICT 3 41653 One Contract With 41653A

DISTRICT 3 41653A One Contract With 41653

DISTRICT 4 16164G One Contract With 40934

DISTRICT 4 40934 One Contract With 16164G

DISTRICT 5 16165G

DISTRICT 6 16166G One Contract With 40936

DISTRICT 6 40936 One Contract With 16166G

DOVER-PORTSMOUTH 41098

Project Name / Number

$1,845,200

$151,800

$3,151,600

$215,600

$4,822,100

$396,500

$4,106,900

$3,532,500

$346,300

$3,031,000

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

06-Feb-18

06-Feb-18

06-Feb-18

06-Feb-18

06-Feb-18

06-Feb-18

06-Feb-18

06-Feb-18

06-Feb-18

06-Feb-18

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

February 2018 Contact Person: Eric Thibodeau

Contact Person: Eric Thibodeau

Contact Person: Eric Thibodeau

Contact Person: Eric Thibodeau

Contact Person: Eric Thibodeau

Contact Person: Eric Thibodeau

Contact Person: Eric Thibodeau

Contact Person: Eric Thibodeau

Contact Person: Eric Thibodeau

Contact Person: David Smith

07/02/18Print Date: 2018 Page 4 of 11

Fiscal Year

2018

F. E. Everett Turnpike Central Tpk Resurfacing: I-293 mm 5.8-11.4, Exit 5 Ramps Manchester, Exit 10 & 11 Ramps Merrimack[TRR *]

Mine Falls Park Construct multi-use path and pedestrian bridge over the Nashua Canal (14-08TAP)[NON-PAR (other), TA *, TE *]

NH 101 and I-293 Pavement Preservation NH 101 and I-293 including ramps at I-293, Kilton Road and US 3.[GRR *, Pave-T1-Preserve]

South Main St Replace Riendeau salted well[WELLS]

Main Street Replace Price salted well[WELLS]

NH 122 Replace Burns salted well[WELLS]

I-89 I-89 from just south of exit 7 north to just south of exit 8. Includes exit 7 ramps[Pave-T1-Preserve]

Retroreflective Backplates-Various (Part3) Upgrade signal heads with retroreflective backplates at approximately 192 intersections statewide.[HSIP *]

Various Tier 2 West Resurfacing Tier 2 roadways[GRR *, Pave-T2-Maintain, Pave-T2-Preserve, Pave-T2-Rehab]

Various - Lilacs Establishment of Lilacs throughout the state[NON-PAR (dot)]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

MANCHESTER-MERRIMACK 41097

NASHUA 40429 X-A004(400)(LPA)

BEDFORD 41174 X-A004(556)

BROOKLINE 41496G

HARRISVILLE 41496F

HOLLIS 41496E

HOPKINTON-WARNER 41216 X-A004(568)

STATEWIDE 41338 X-A004(602)

STATEWIDE 41534 X-A004(661)

STATEWIDE 41733

Project Name / Number

February Monthly Total

$4,594,200

$545,600

$4,175,400

$19,700

$19,700

$19,400

$1,559,500

$484,800

$4,717,500

$59,700

$0

$385,600

$4,175,400

$0

$0

$0

$1,559,500

$484,800

$4,717,500

$0

06-Feb-18

20-Feb-18

27-Feb-18

06-Mar-18

06-Mar-18

06-Mar-18

06-Mar-18

06-Mar-18

13-Mar-18

13-Mar-18

$44,784,000 $5,057,400

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

February 2018

March 2018

Contact Person: David Smith

Contact Person: Tom Jameson

Contact Person: Tobey Reynolds

Contact Person: Roger Appleton

Contact Person: Roger Appleton

Contact Person: Roger Appleton

Contact Person: Ron Grandmaison

Contact Person: Lee Baronas

Contact Person: Tobey Reynolds

Contact Person: Tobey Reynolds

07/02/18Print Date: 2018 Page 5 of 11

Fiscal Year

2018

US 1 Resurface US 1 from the northern end of Urban Compact north 7.7 miles.[Pave-T2-Rehab]

I-93 & NH 101 - Crackseal Crack Seal Tier 1 including ramps[Pave-T1-Preserve]

Various Tier 2 - BWC Pave Bonded Wearing Couse [GRR *, Pave-T2-Preserve]

Various Tier 2 East Pavement resurfacing on Tier 2 roadways[GRR *, Pave-T2-Maintain, Pave-T2-Preserve, Pave-T2-Rehab]

Various Schools in Portsmouth Bicycle lanes on Lafayette Road and Middle Street.[NON-PAR (other), SRTS]

All Provide shielding for poor bridge decks overhighway traffic [Bridg-T1-2-Main-Pres, Bridg-T3-4-Main-Pres, TRR *]

NH 101A & NH 101 Reconstruction of EB ramps at NH 101 and NH 101A[Other Fed Aid]

Various - Wildflower Establishment of Native Wildflower plantings statewide[NON-PAR (dot)]

Catamount, Oneida, Tilton Hill Roads Elementary& Middle Schools at Catamount, Oneida, Tilton Hill[SRTS]

Main St. Bicycle & pedestrian improvements on Main St./other streets around Pollard School - INFRASTRUCTURE[SRTS]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

HAMPTON-PORTSMOUTH 41215 X-A004(567)

STATEWIDE 41279 X-A004(577)

STATEWIDE 41527 X-A004(660)

STATEWIDE 41550 X-A004(662)

PORTSMOUTH 28757 X-A003(791)(LPA)

STATEWIDE 41611 X-A004(709)

AMHERST 10136C X-A001(264)

STATEWIDE 41732

PITTSFIELD 21188 X-A002(127)(LPA)

PLAISTOW 40312 X-A004(363)(LPA)

Project Name / Number

Second Quarter Total

March Monthly Total

$4,465,200

$583,700

$4,769,400

$4,843,300

$242,300

$1,628,100

$1,488,300

$196,800

$445,900

$314,800

$4,465,200

$583,700

$4,769,400

$4,843,300

$167,800

$1,465,300

$1,488,300

$0

$445,900

$314,800

20-Mar-18

20-Mar-18

20-Mar-18

27-Mar-18

02-Apr-18

03-Apr-18

10-Apr-18

17-Apr-18

24-Apr-18

24-Apr-18

$21,541,900 $21,423,400

$66,652,000 $26,480,800

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

low-bid

March 2018

April 2018

Contact Person: Tobey Reynolds

Contact Person: Ron Grandmaison

Contact Person: Tobey Reynolds

Contact Person: Tobey Reynolds

Contact Person: John Corrigan

Contact Person: Bob Landry

Contact Person: Jennifer Reczek

Contact Person: Tobey Reynolds

Contact Person: John Corrigan

Contact Person: John Corrigan

07/02/18Print Date: 2018 Page 6 of 11

Fiscal Year

2018

Rail Trail Construct approximatly 3,000' of multi-use path along the existing M&L rail corridor. (14-40TA)[NON-PAR (other), TA *, TE *]

OAK STREET Bridge Replacement-Oak St over Sugar River-Br. #103/136[MOBRR *, SAB *]

NUDD ROAD Bridge Rehabilitation-Nudd Rd over Bearcamp River-Br. #108/333-Phase II-Whittier Covered Bridge[NHCBP*]

NH 106 NH 106 Improvements to enhance traffic operations/safety from Clough Hill Road to Shaws Road[Ear-NH042, Ear-NH061, NON-PAR (dot), None-Highway]

I-293 EB & WB Bridge Preservation efforts for the bridges carrying I-293 EB & WB over Merrimack River[BRPPI *, Bridg-HIB-Main-Pres, Pave-T1-Preserve]

Various Permanent pavement repairs to damage due to October 29, 2017 Storm event

[Emergency-FHWA]

Various Permanent pavement repairs to damage due to October 29, 2017 Storm event[Emergency-FHWA]

I-95 Bridge girder painting along Turnpike facilities.[TRR *]

Various Pavement Rehabilitation: Somerset Parkway, NH101A, NH130, & NH111 (FedAid Eligible City Maintained)[Ear-NH003, NON-PAR (other)]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

SALEM 40432 X-A004(403)(LPA)

NEWPORT 16109 X-A001(136)(LPA)

OSSIPEE 23818 X-A002(771)(LPA)

LOUDON - CANTERBURY 29613 X-A004(201)

BEDFORD - MANCHESTER 40731 X-A004(475)

DISTRICT 1 (ER FED AID) 41871 X-A004(766)

DISTRICT 2 (ER FED-AID) 41739 X-A004(765)

HAMPTON 40603

NASHUA 41049 X-A004(543)(LPA)

Project Name / Number

April Monthly Total

May Monthly Total

$408,600

$1,854,700

$801,000

$2,631,800

$4,648,300

$643,700

$570,400

$1,365,800

$4,013,300

$321,900

$1,483,700

$640,800

$2,631,800

$4,648,300

$515,000

$456,300

$0

$3,920,300

24-Apr-18

15-May-18

15-May-18

29-May-18

05-Jun-18

05-Jun-18

05-Jun-18

05-Jun-18

15-Jun-18

$4,724,800

$5,287,500

$4,204,000

$4,756,300

low-bid

low-bid

low-bid

April 2018

May 2018

June 2018

Contact Person: Tom Jameson

Contact Person: C.R. Willeke

Contact Person: C.R. Willeke

Contact Person: Keith Cota

Contact Person: Bob Landry

Contact Person: Ron Grandmaison

Contact Person: Ron Grandmaison

Contact Person: David Smith

Contact Person: C.R. Willeke

07/02/18Print Date: 2018 Page 7 of 11

Fiscal Year

2018

Tier 2 Cable Replacement Replace Cable Guardrail on Tier 2 Roadways, targeting highervolume roads first.[HSIP *]

US 3 Bridge Rehabilitation, Superstructure Replacement, carrying US 3 over NH Railroad (Red List)[Bridg-T1-2-Rehab-Rcn, None-Bridge]

NH 16 / NH 25 NH 16/NH 25; Replace three RedList bridges, 137/299, 137/297, 152/268 & Resurface approx 3.2 miles.[Bridg-T1-2-Rehab-Rcn, NON-PAR (other), None-Bridge, Pave-T2-Rehab]

NH 18 NH 18, superstructure replacement for bridge carrying NH 18 over Lafayette Brook (BrNo 089/099)[Bridg-T3-4-Rehab-Rcn, None-Bridge]

Route 28 Resurface to maintain riding surface[Pave-T2-Rehab, Pave-T2-Resurf]

I-89 Resurfacing from Exit 11 north to 12A including the ramps at Exit 11 and 12.[Pave-T1-Preserve, Pave-T1-Resurf]

Various - F-Unit and Cable Replacement Replace substandard F-Unit guardrail terminals and substandard cable guardrail.[HSIP *]

I-89 I-89 pavement preservation, SB MP 26.9 to25.9 1.5" overlay.[Pave-T1-Preserve]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

STATEWIDE 40803 X-A004(493)

LACONIA 16144 X-A001(150)

OSSIPEE 14749 X-A000(490)

FRANCONIA 24497 X-A002(899)

EPSOM-CHICHESTER-PITTSFIELD-BARNSTEAD 41613 X-A004(701)

NEW LONDON 41219 X-A004(569)One Contract With 41061

STATEWIDE 41269 X-A004(576)

SUTTON 41061 X-A004(547)One Contract With 41219

Project Name / Number

Third Quarter Total

June Monthly Total

July Monthly Total

$1,162,500

$1,395,000

$16,020,800

$1,627,500

$4,231,500

$1,674,000

$930,000

$423,200

$1,162,500

$1,395,000

$3,853,100

$1,627,500

$4,231,500

$1,674,000

$930,000

$423,200

17-Jul-18

24-Jul-18

24-Jul-18

31-Jul-18

07-Aug-18

07-Aug-18

07-Aug-18

07-Aug-18

$11,241,500

$20,205,800

$9,539,900

$8,038,100

$21,253,800 $18,500,200

June 2018

July 2018

August 2018

Contact Person: Tobey Reynolds

Contact Person: Joseph Adams

Contact Person: Victoria Chase

Contact Person: Joseph Adams

Contact Person: Ron Grandmaison

Contact Person: Ron Grandmaison

Contact Person: Tobey Reynolds

Contact Person: Ron Grandmaison

07/02/18Print Date: 2018 Page 8 of 11

Fiscal Year

2018

US 302 Reconstruct railway-highway crossing, roadway approaches & protective devices (Bartlett 364-655V)[RR-RCS *]

East Street Const. Sidewalks along East Street and improve Bobby Woodman Trail for non-motorized use (14-21TAP)[TA *]

Dover Community Trail Const multi-use path to connect 2 portions of the Dover Community Trail, which are gaps (14-27TAP)[TA *]

NH Route 111 (Kingston Road) Widen shoulders to 5' on Kingston Road (NH Route 111) for approximately 1.1 miles. (14-26TAP)[NON-PAR (other), TA *]

Rush Rd,Maple St,Prospect St, Hall Ave Const appr 3,135' of 5' wide sidewalk along Rush Rd,Maple St,Prospect St,Hall Ave. (14-39TAP)[TA *]

US202, NH 9 US 202/NH 9 Bridge Preservation efforts for two bridges carrying US202 over various features.[Bridg-T1-2-Main-Pres]

Ami Brown Road Construct 11,695' of shared lane and bike lane markings. (14-42TAP) Ped crossing Improve at Rte 9[TA *]

Bancroft Hwy (US 3) and Derry Road (NH 102)Demolition of State owned buildings[TPK *]

Rail Trail Construct multi-use path along Baker St, Brown Ave, Dubisz St, and Sundial Ave. (14-25TAP)[TA *]

NH 123A NH 123A OVER WARREN BROOK - REPLACE SINGLE SPAN BRIDGE.[Bridg-T3-4-Rehab-Rcn, None-Bridge]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

BARTLETT 41439 X-A004(640)

CLAREMONT 40435 X-A004(405)(LPA)

DOVER 40437 X-A004(407)(LPA)

EXETER 40436 X-A004(406)(LPA)

HENNIKER 40440 X-A004(409)(LPA)

HOPKINTON 41303 X-A004(592)

KEENE 40439 X-A004(408)(LPA)

LITCHFIELD 29733

MANCHESTER 40428 X-A004(399)(LPA)

ALSTEAD 20817 X-A002(091)

Project Name / Number

$511,500

$456,200

$293,900

$877,500

$331,000

$2,348,300

$303,800

$0

$632,600

$1,488,000

$511,500

$365,000

$235,100

$586,700

$264,800

$2,348,300

$243,000

$0

$506,100

$1,488,000

14-Aug-18

14-Aug-18

14-Aug-18

14-Aug-18

14-Aug-18

14-Aug-18

14-Aug-18

14-Aug-18

14-Aug-18

21-Aug-18

August 2018 Contact Person: Melodie Esterberg

Contact Person: Tom Jameson

Contact Person: Tom Jameson

Contact Person: Bob Hudson

Contact Person: Tom Jameson

Contact Person: David Scott

Contact Person: Tom Jameson

Contact Person: David Smith

Contact Person: Tom Jameson

Contact Person: David Scott

07/02/18Print Date: 2018 Page 9 of 11

Fiscal Year

2018

Various T2 East(2) Pavement Resurfacing on Tier 2 Roadways[Pave-T2-Maintain, Pave-T2-Preserve, Pave-T2-Rehab]

Various Tier 2 & 3 Replace cable guardrail and F terminal units on Tier 2 & 3 roads.[HSIP *]

NH 11 / 103 NH 11 & 103 / Bowen St: improve access management at existing signalized intersection[HSIP *, NON-PAR (dot), NON-PAR (other)]

Various Tier 2 Replace cable guardrail and F terminal units on Tier 2 roads.[HSIP *]

Various Tier 2 North Roadway resurfacing on Tier 2 highways[Pave-T2-Maintain, Pave-T2-Preserve, Pave-T2-Rehab, Pave-T2-Resurf]

Various Sign replacements and compliance upgrades due to condition[USSS *]

US Rte 302 Culvert rehabilitation/replacement[BET-DRG-HQ, CRDR *, NON-PAR (dot)]

I-393 Culvert preservation for three CMPs[CRDR *]

NH 16 Widening and reconstruction between NH 110A and Dummer Pond Road[None-Highway]

US 1 By-Pass Culvert Rehabilitation, US 1 By-Pass over Hodgson Brook Br No 192/106[Bridg-T1-2-Rehab-Rcn, None-Bridge]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

STATEWIDE 41612 X-A004(700)

CARROLL-WHITEFIELD-JEFFERSON 41781 X-A004(747)

CLAREMONT 25621 X-A003(140)

COLEBROOK-DIXVILLE 41783 X-A004(748)

STATEWIDE 41604 X-A004(697)

STATEWIDE 41805 X-A004(755)

BETHLEHEM 26763 X-A004(296)

CONCORD-PEMBROKE 41267 X-A004(575)

DUMMER - CAMBRIDGE - ERROL 16304 X-A001(231)

PORTSMOUTH 27690 X-A003(589)

Project Name / Number

August Monthly Total

$1,418,300

$930,000

$344,100

$930,000

$3,608,400

$421,300

$697,500

$465,000

$5,301,000

$930,000

$1,418,300

$930,000

$309,700

$930,000

$3,608,400

$421,300

$697,500

$465,000

$5,301,000

$930,000

21-Aug-18

28-Aug-18

28-Aug-18

28-Aug-18

28-Aug-18

28-Aug-18

04-Sep-18

04-Sep-18

04-Sep-18

04-Sep-18

$22,153,600 $21,424,900

August 2018

September 2018

Contact Person: Ron Grandmaison

Contact Person: Kirk Mudgett

Contact Person: Mike Dugas

Contact Person: Kirk Mudgett

Contact Person: Ron Grandmaison

Contact Person: Lee Baronas

Contact Person: Tobey Reynolds

Contact Person: Tobey Reynolds

Contact Person: Jennifer Reczek

Contact Person: Joseph Adams

07/02/18Print Date: 2018 Page 10 of 11

Fiscal Year

2018

Fiscal Year 2018 Total

NH 28 Bypass English Range Road / Scobie Pond Road intersection safety improvements[HSIP *]

Various T2 West (2) Resurfacing Tier 2 Roadways to preserve riding surface[Pave-T2-Maintain, Pave-T2-Preserve, Pave-T2-Rehab, Pave-T2-Resurf]

NH 12 NH 119 intersection safety improvements[HSIP *]

BEDFORD ROAD Bridge Replacement-Bedford Rd over Baboosic Brook-Br. #113/159[MOBRR *, SAB *]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

DERRY 24861 X-A002(975)

STATEWIDE 41614 X-A004(702)

FITZWILLIAM 16211 X-A001(191)

MERRIMACK 15841 X-A004(550)(LPA)

Project Name / Number

Fourth Quarter Total

September Monthly Total

$1,116,000

$4,919,700

$623,100

$3,855,700

$1,116,000

$4,919,700

$623,100

$744,000

11-Sep-18

11-Sep-18

18-Sep-18

18-Sep-18

$17,908,000 $14,796,300

$60,267,400

$157,118,300

$44,259,300

$93,864,100

September 2018 Contact Person: Mike Dugas

Contact Person: Ron Grandmaison

Contact Person: Mike Dugas

Contact Person: Bob Hudson

07/02/18Print Date: 2018 Page 11 of 11

HAVERHILL 41297 X-A004(587)

CONCORD 41704 X-A004(717)

ROCHESTER 41849 X-A004(762)

BARNSTEAD 41301 X-A004(591)

TILTON-SANBORNTON 41787 X-A004(749)

LINCOLN-FRANCONIA 41052 X-A004(544)

Project Name / Number

NH 25 NH 25 over Oliverian Brook - Preservation efforts, Haverhill Br No 067/092[Bridg-T1-2-Main-Pres]

I-89 Painting I-89 bridges in Concord[Bridg-T1-2-Main-Pres]

NH 125 NH 125 corridor safety improvements[HSIP *]

NH28 NH 28 Bridge Preservation efforts for 2 brs carrying NH 28 over the Suncook River & Beauty Hill Rd[Bridg-T1-2-Main-Pres]

I-93 Pavement preservation with associated evaluations of drainage and guardrail I-93 MM 57.2 to 60.9[Pave-T1-Preserve, Pave-T1-Resurf]

I-93 Bonded Wearing Course Preservation fromMP 105.9 to 111.5 including exits 34B and 34C.[Pave-T1-Preserve, Pave-T1-Resurf, Pave-T3-4-Resurf]

Project Description

17-Jul-18

28-Aug-18

28-Aug-18

18-Sep-18

18-Sep-18

25-Sep-18

Target Ad Date

$713,300

$1,785,600

$372,000

$629,100

$3,162,000

$2,145,200

Approx. Contract Amt.

$713,300

$1,785,600

$372,000

$629,100

$3,162,000

$2,105,200

Federal Dollars

ON-SHELF PROJECTS

Fiscal Year 2018

On-Shelf Projects 2018 Total $8,807,200 $8,767,200

Contact Person: David Scott

Contact Person: David Scott

Contact Person: Mike Dugas

Contact Person: David Scott

Contact Person: Ron Grandmaison

Contact Person: Ron Grandmaison

On Shelf Projects Advertising are subject to availability of funding.In addition these projects are subject to STIP Amendments to bring them into the current fiscal year.

07/02/18Print Date: 2019 Page 1 of 9

Fiscal Year

2019

NH 104 NH 104 250' west of Berry Rd. rehabilitate/replace a 66" & 60" CAP [CRDR *]

NH 10 NH 10 replacement of 3'x4' concrete boxculvert [CRDR *]

I-93 Exit 1 to Exit 5 - Construct 4th lane northbound and southbound[Other Fed Aid, TIFIA]

NH 16 Repair failed roadway slope along NH 16 abutting the Magalloway River[BET-DRG-HQ, FLAP, NON-PAR (dot)]

NH 25 NH 25 over Oliverian Brook - Preservation efforts, Haverhill Br No 067/092[Bridg-T1-2-Main-Pres]

NH28 NH 28 Bridge Preservation efforts for 2 brs carrying NH 28 over the Suncook River & Beauty Hill Rd[Bridg-T1-2-Main-Pres]

NH 11 Stone/CMP Culvert Replacement [BET-DRG-HQ, NON-PAR (dot)]

Maple Avenue, Disnard and Bluff Elementary School REPLACE SIDEWALKS ON BELDING AND MYRTLE STREETS, NEAR ELEMENTARY SCHOOLS[NON-PAR (other), SRTS]

East Side Road Saco River Covered Bridge Scour Protection effort [BRPPI *, Bridg-T3-4-Main-Pres, NHCBP*]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

ALEXANDRIA 15937 X-A001(047)

LEBANON 15717 X-A000(906)

SALEM TO MANCHESTER 14633J A004(438)

ERROL 41069 X-A004(565)

HAVERHILL 41297 X-A004(587)

BARNSTEAD 41301 X-A004(591)

ALTON 41352

CLAREMONT 28693 X-A003(767)(LPA)

CONWAY 25103 X-A003(039)

Project Name / Number

October Monthly Total

$213,900

$332,500

$9,765,000

$744,000

$713,300

$629,100

$465,000

$313,900

$744,000

$213,900

$332,500

$292,400

$0

$713,300

$629,100

$0

$313,900

$744,000

16-Oct-18

16-Oct-18

16-Oct-18

23-Oct-18

23-Oct-18

30-Oct-18

06-Nov-18

06-Nov-18

06-Nov-18

$12,397,800 $2,181,200

NH DEPARTMENT OF TRANSPORTATION * DIVISION OF PROJECT DEVELOPMENT

ADVERTISING SCHEDULE

October 2018

November 2018

Contact Person: Tobey Reynolds

Contact Person: Tobey Reynolds

Contact Person: Wendy Johnson

Contact Person: Tobey Reynolds

Contact Person: David Scott

Contact Person: David Scott

Contact Person: Tobey Reynolds

Contact Person: John Corrigan

Contact Person: Bob Landry

07/02/18Print Date: 2019 Page 2 of 9

Fiscal Year

2019

Charlotte Avenue Elementary School Constructnew sidewalk, reconstruct crosswalk to meet ADA standards.[NON-PAR (other), SRTS]

Stinson Lake Road Improve 4200 feet of Stinson Lake Road in the Town of Ellsworth, NH, within the WMNF [FLAP]

NH 1B Preservation efforts on NH 1B bridges over Piscataqua Estuary in Portsmouth and New Castle[Bridg-T3-4-Main-Pres]

NH 125 NH 125 corridor safety improvements[HSIP *]

US 3 Ramp from 11A Rehab or replace existingfailing 84" CMP under SB on Ramp to US 3 fromNH 11A[CRDR *]

US 2 Bridge Replacement, US 2 over Connecticut River (Roger's Ranger's Bridge)[Bridg-T1-2-Rehab-Rcn, NON-PAR (Vermont), None-Bridge]

NH 38, NH 9 Intersection safety improvements -install Intersection Conflict Warning Systems in two locations[HSIP *]

NH 101 NH 123 intersection safety improvements[HSIP *]

NH 202A (WALNUT STREET) INTERSECTION IMPROVEMENTS TO IMPROVE SAFETY THROUGH STRAFFORD SQ, NORTH MAIN, & WASHINGTON ST[MUPCA*, NON-PAR (other)]

US 3 Silver Lake Road intersection safety improvements[HSIP *]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

NASHUA 28739 X-A003(786)(LPA)

ELLSWORTH 40874 X-A004(514)

PORTSMOUTH - NEW CASTLE 41253 X-A004(574)

ROCHESTER 41849 X-A004(762)

GILFORD 41655 X-A004(710)

LANCASTER, NH - GUILDHALL, VT 16155 A001(159)

PELHAM-CHESTERFIELD 29338 X-A004(016)One Contract With 15698, 29358

PETERBOROUGH 15698 X-A000(890)One Contract With 29338, 29358

ROCHESTER 14350 X-A000(320)(LPA)

TILTON 29358 X-A004(055)One Contract With 15698, 29338

Project Name / Number

November Monthly Total

$93,000

$380,800

$2,325,000

$372,000

$437,100

$10,955,400

$139,500

$111,600

$4,174,000

$46,500

$93,000

$68,600

$2,325,000

$372,000

$437,100

$0

$139,500

$111,600

$520,800

$46,500

06-Nov-18

13-Nov-18

13-Nov-18

20-Nov-18

27-Nov-18

27-Nov-18

11-Dec-18

11-Dec-18

11-Dec-18

11-Dec-18

$16,086,200 $4,353,600

November 2018

December 2018

Contact Person: John Corrigan

Contact Person: Jennifer Reczek

Contact Person: Bob Landry

Contact Person: Mike Dugas

Contact Person: Kirk Mudgett

Contact Person: Bob Landry

Contact Person: Mike Dugas

Contact Person: Mike Dugas

Contact Person: Bob Hudson

Contact Person: Mike Dugas

07/02/18Print Date: 2019 Page 3 of 9

Fiscal Year

2019

NH Route 118 Stabilize river embankment and reconstruct roadway incl. drainage and guardrail work as needed[Emergency-FHWA]

US 302 US 302 OVER CONWAY LAKE OUTLET- REPLACE BRIDGE [Bridg-T1-2-Rehab-Rcn, NON-PAR (dot), None-Bridge]

I-93 Pavement preservation with associated evaluations of drainage and guardrail I-93 MM 57.2 to 60.9[Pave-T1-Preserve, Pave-T1-Resurf]

Cornish Toll Bridge Road Cornish Windsor Covered Bridge Scour Mitigation[BRPPI *, Bridg-T3-4-Main-Pres, NHCBP*, NON-PAR (Vermont)]

US 4 Bridge Replacement, for Bridge carrying US 4 over Bunker Creek (Br No 145/116)[Bridg-T1-2-Rehab-Rcn, None-Other]

Mascoma Street Bridge Rehabiliatation, for RedList Bridge carrying Mascoma Street over I-89 (Br No 103/116)[Bridg-T3-4-Rehab-Rcn, None-Bridge]

I-93 Pavement preservation with associated evaluations of drainage and guardrail I-93 MM 67.6 to 75.0[GRR *, Pave-T1-Preserve, Pave-T1-Resurf]

NH 16, NH 25, NH 41 Intersection improvementsat NH 41 with NH 16 including NH 25.[None-Highway]

District 1 Horizontal Curves Horizontal curve signing project - Two lane roads in D1[HSIP *]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

WARREN 41738 X-A004(728)

CONWAY 15864 X-A001(161)

TILTON-SANBORNTON 41787 X-A004(749)

CORNISH, NH - WINDSOR, VT 25067 A003(035)

DURHAM 16236 A001(202)

LEBANON 25821 X-A003(201)

NEW HAMPTON - ASHLAND 41674 X-A004(713)

OSSIPEE 13910 X-A000(110)

STATEWIDE 28134 X-A003(695)

Project Name / Number

First Quarter Total

December Monthly Total

$651,000

$2,883,000

$3,162,000

$2,325,000

$3,720,000

$3,406,600

$5,766,000

$930,000

$558,000

$520,800

$0

$3,162,000

$2,048,800

$3,720,000

$3,406,600

$5,766,000

$930,000

$558,000

11-Dec-18

18-Dec-18

18-Dec-18

08-Jan-19

08-Jan-19

08-Jan-19

08-Jan-19

08-Jan-19

08-Jan-19

$11,167,600 $4,501,200

$39,651,600 $11,036,000

December 2018

January 2019

Contact Person: Ron Grandmaison

Contact Person: David Scott

Contact Person: Ron Grandmaison

Contact Person: Bob Landry

Contact Person: Keith Cota

Contact Person: Joseph Adams

Contact Person: Ron Grandmaison

Contact Person: Victoria Chase

Contact Person: Mike Dugas

07/02/18Print Date: 2019 Page 4 of 9

Fiscal Year

2019

District 6 Horizontal Curves (Urban) Horizontal curve signing project - Two lane urban roads in D6[HSIP *]

I-89 Pavement joint south of exit 8 to pavement joint north of exit 9 Includes Exits 8 and 9[Bridg-T1-2-Main-Pres, Pave-T1-Rehab]

US302,NH 18,NH116 Preservation efforts on 5-span bridge carrying US302,NH 18,NH116 overI-93.[Bridg-T1-2-Main-Pres]

US 3 US 3 OVER CONE BROOK - 059/089 - REHABILITATE BRIDGE[Bridg-T1-2-Rehab-Rcn]

I-95, NH 16, FEET and I-93 Striping of Turnpike facilities[TRR *]

NH 32 Study and implement recommendations of 2013 Road Safety Audit[HSIP *]

Maplewood Ave Pan Am Railways, reconstruct railway-highway crossing, roadway approaches and protective devices[RR-RCS *]

BRADFORD CENTER ROAD Bridge Rehab-Bradford Center Rd over West Branch of Warner River-Br. #140/144-Bement Covered Br[NHCBP*, SAB *]

I-93 I-93 pavement resurfacing with associatedevaluations of drainage and guardrail (MM 83.2to 88.2)

[Pave-T1-Preserve, Pave-T1-Resurf]

I-89 and NH 101 Crackseal 2019 Crack Seal Full width I-89 MM 36.3 to 43.6, NH MM 101 102.1 to 109.4 and MM 124.6 to 132.4.[Pave-T1-Preserve, Pave-T1-Resurf]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

STATEWIDE 28139 X-A003(700)

WARNER 40512 X-A004(422)

BETHLEHEM 41901 X-A004(771)

COLUMBIA 16302 X-A001(227)

STATEWIDE STRIPING 41487

SWANZEY 40485 X-A004(415)

PORTSMOUTH 40908 X-A004(518)

BRADFORD 23819 X-A002(772)(LPA)

CAMPTON-THORNTON 41903 X-A004(773)

STATEWIDE 41327 X-A004(594)

Project Name / Number

January Monthly Total

$325,500

$12,473,200

$1,641,500

$930,000

$344,100

$744,000

$395,300

$1,015,600

$1,878,600

$813,800

$325,500

$12,473,200

$1,641,500

$930,000

$0

$744,000

$355,700

$494,300

$1,878,600

$813,800

08-Jan-19

08-Jan-19

15-Jan-19

15-Jan-19

15-Jan-19

15-Jan-19

16-Jan-19

17-Jan-19

29-Jan-19

29-Jan-19

$37,267,200 $36,086,000

January 2019 Contact Person: Mike Dugas

Contact Person: Tobey Reynolds

Contact Person: David Scott

Contact Person: David Scott

Contact Person: David Smith

Contact Person: Mike Dugas

Contact Person: Melodie Esterberg

Contact Person: C.R. Willeke

Contact Person: Ron Grandmaison

Contact Person: Ron Grandmaison

07/02/18Print Date: 2019 Page 5 of 9

Fiscal Year

2019

South Main St. , Mason Road Const. Sidewalks on Rte 130, Const 60 foot Ped bridge over Nissitissit River and sidewalk to beach [TA *]

Various Resurfacing various tier 2, 3, and 4 roadways in District 1.[Pave-T2-Resurf, Pave-T3-4-Rehab, Pave-T3-4-Resurf]

Various Resurfacing various tier 2, 3, and 4 roadways in District 2.[Pave-T2-Resurf, Pave-T3-4-Rehab, Pave-T3-4-Resurf]

Various Resurfacing various tier 2, 3, and 4 roadways in District 3.[Pave-T2-Resurf, Pave-T3-4-Rehab, Pave-T3-4-Resurf]

Various Resurfacing various tier 2, 3, and 4 roadways in District 4.[Pave-T2-Resurf, Pave-T3-4-Rehab, Pave-T3-4-Resurf]

Various Resurfacing various tier 2, 3, and 4 roadways in District 5.[Pave-T2-Resurf, Pave-T3-4-Rehab, Pave-T3-4-Resurf]

Various Resurfacing various tier 2, 3, and 4 roadways in District 6.[Pave-T2-Resurf, Pave-T3-4-Rehab, Pave-T3-4-Resurf]

FEET, I-93 and US 3 Rehabilitation of Turnpike pavements[TRR *]

I-95 and NH 16 Pavement rehabilitation along Turnipkes[TRR *]

US 202 RECONSTRUCT US ROUTE 202 @ MAIN STREET INTERSECTION INCLUDING BOULDER RETAINING WALL STABILIZATION[Other Fed Aid]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

BROOKLINE 41364 X-A004(607)(LPA)

DISTRICT 1 16161H

DISTRICT 2 16162H

DISTRICT 3 16163H

DISTRICT 4 16164H

DISTRICT 5 16165H

DISTRICT 6 16166H

MERRIMACK-MANCHESTER-NASHUA 41485

PORTSMOUTH-ROCHESTER 41486

PETERBOROUGH 14772A X-A000(535)(LPA) & One Contract With 14933

Project Name / Number

$590,600

$4,523,200

$4,059,100

$4,220,800

$4,379,900

$3,764,700

$2,743,900

$2,855,100

$2,855,100

$3,255,000

$472,400

$0

$0

$0

$0

$0

$0

$0

$0

$3,255,000

05-Feb-19

05-Feb-19

05-Feb-19

05-Feb-19

05-Feb-19

05-Feb-19

05-Feb-19

05-Feb-19

05-Feb-19

06-Feb-19

February 2019 Contact Person: Tom Jameson

Contact Person: Ron Grandmaison

Contact Person: Ron Grandmaison

Contact Person: Ron Grandmaison

Contact Person: Ron Grandmaison

Contact Person: Ron Grandmaison

Contact Person: Ron Grandmaison

Contact Person: David Smith

Contact Person: David Smith

Contact Person: C.R. Willeke

07/02/18Print Date: 2019 Page 6 of 9

Fiscal Year

2019

MAIN STREET MAIN STREET BRIDGE REPLACEMENT OVER CONTOOCOOK RIVER - 092/089 {Red List}[MOBRR *, SAB *]

I-93 Bonded Wearing Course Preservation fromMP 105.9 to 111.5 including exits 34B and 34C.[Pave-T1-Preserve, Pave-T1-Resurf, Pave-T3-4-Resurf]

I-93 Mainline, State Line to Exit 1 NB & SB[Other Fed Aid]

Peverly Hill Rd. Const. new sidewalk and striped bicycle shoulders and associated drainage along Peverly Hill Road.[CMAQ *, NON-PAR (other)]

South Manchester Rail Trail Construct Multi-usepath along the abandoned rail corridor from Gold St. to Perimeter Road[CMAQ *, Ear-NH022]

DW Highway to FE Everett Construct Multi-use path in the town of Merrimack for approximatly 2,500LF. (14-15TAP)[TA *]

I-89 NB & SB Rehab of the I-89 NB & SB over US 4 & NH 10 bridges and preservation efforts for the Mascoma River[4R, Bridg-T1-2-Main-Pres, Bridg-T1-2-Rehab-Rcn]

Cottage Street, Mill Street, South Street, Meadow Street Const sidewalks along CottageSt, Mill St, South St, Meadow St, Mt. Eustis Rd, Bronson St[TA *]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

PETERBOROUGH 14933 X-A002(107)(LPA) & One Contract With 14772A

LINCOLN-FRANCONIA 41052 X-A004(544)

SALEM TO MANCHESTER 13933A A004(435)

PORTSMOUTH 20258 X-A002(061)(LPA)

MANCHESTER 29811 X-A004(311)(LPA)

MERRIMACK 40300 X-A004(357)(LPA)

LEBANON 41191 X-A004(559)

LITTLETON 41362 X-A004(605)(LPA)

Project Name / Number

Second Quarter Total

February Monthly Total

March Monthly Total

April Monthly Total

$4,650,000

$2,145,200

$12,276,000

$1,063,700

$1,197,200

$451,100

$7,812,000

$781,200

$3,720,000

$2,105,200

$12,276,000

$340,400

$957,800

$360,800

$0

$625,000

06-Feb-19

19-Feb-19

19-Feb-19

05-Mar-19

12-Mar-19

17-Mar-19

19-Mar-19

01-May-19

$52,318,600

$10,524,000

$0

$21,828,600

$1,659,000

$0

$100,109,800 $59,573,600

February 2019

March 2019

April 2019

May 2019

Contact Person: C.R. Willeke

Contact Person: Ron Grandmaison

Contact Person: Wendy Johnson

Contact Person: Tom Jameson

Contact Person: Tom Jameson

Contact Person: Bob Hudson

Contact Person: Joseph Adams

Contact Person: John Corrigan

07/02/18Print Date: 2019 Page 7 of 9

Fiscal Year

2019

Rail Trail Const. Rail Trail along abandoned railroad bed from Mammoth Road to Lake ShoreAvenue[TA *]

Various Replace cable guardrail and F terminal units on Tier 2 and 3 roads[HSIP *]

Various Replace cable guardrail and F terminal units on Tier 2 and 3 roads[HSIP *]

NH 12 NH 12 & NORTH STREET INTERSECTIONRELOCATION {MUPCA AND Demo ID NH039 & NH059}[Ear-NH027, Ear-NH030, Ear-NH039, Ear-NH047, Ear-NH059, MUPCA*]

NH 16 Pavement rehabilitation along NH 16 fromNH 28 northerly 1.1 miles.[None-Highway]

Brattleboro Road Construct Sidewalks along Brattleboro Road.[TA *]

Various Replace cable guardrail and F terminal units on Tier 2 and 3 roads[HSIP *]

NH 28 NH 28 reconstruction of intersection with North Barnstead Road/North Road[Ear-NH069, None-Highway]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

MANCHESTER 41361 X-A004(604)(LPA)

STATEWIDE 41897 X-A004(767)

STATEWIDE 41898 X-A004(768)

CLAREMONT 13248 X-MGS-STP-X-0131(039)(LPA)

OSSIPEE 10431 X-MGS-NHS-X-T-0271(032)

HINSDALE 41365 X-A004(615)(LPA)

STATEWIDE 41899 X-A004(769)

BARNSTEAD-ALTON 14121 X-A000(208)

Project Name / Number

Third Quarter Total

May Monthly Total

June Monthly Total

July Monthly Total

$795,600

$1,116,000

$1,116,000

$3,361,600

$2,604,000

$443,000

$1,116,000

$3,773,700

$636,400

$1,116,000

$1,116,000

$2,689,300

$2,604,000

$354,400

$1,116,000

$3,773,700

01-May-19

04-Jun-19

18-Jun-19

20-Jun-19

25-Jun-19

08-Jul-19

09-Jul-19

16-Jul-19

$1,576,800

$8,197,600

$5,332,700

$1,261,400

$7,525,300

$5,244,100

$9,774,400 $8,786,700

May 2019

June 2019

July 2019

Contact Person: Tom Jameson

Contact Person: Kirk Mudgett

Contact Person: Kirk Mudgett

Contact Person: C.R. Willeke

Contact Person: Victoria Chase

Contact Person: John Corrigan

Contact Person: Kirk Mudgett

Contact Person: Don Lyford

07/02/18Print Date: 2019 Page 8 of 9

Fiscal Year

2019

Fiscal Year 2019 Total

NH Route 16 Bridge Rehab, for Red List Bridge carrying NH 16 over Ellis River (Br No 144/056)[Bridg-T1-2-Rehab-Rcn, Bridg-T3-4-Rehab-Rcn, None-Bridge]

I-89 NB & SB Superstructure Replace & Widening, I-89 NB & SB over Connecticut River (Br No 044/103 & 044/104)[Bridg-HIB-Rehab-Rcn, NON-PAR (Vermont), None-Bridge]

NH 28 RECONSTRUCT DEPOT INTERSECTION NH28 (BROADWAY) AND NH 97 (MAIN STREET) ADD TURN LANES ON NH28 MUPCA[Ear-NH072, MUPCA*, Other Fed Aid]

NH 119 Reconstruction of the bridges over the Connecticut River[Bridg-HIB-Rehab-Rcn, NON-PAR (Vermont), None-Bridge]

Project DescriptionTarget Ad Date

Approx. Contract Amt.

Federal Dollars

JACKSON 27709 X-A003(593)

LEBANON, NH - HARTFORD, VT 16148 A001(154)

SALEM 12334 X-STP-X-5399(011)(LPA)

HINSDALE, NH - BRATTLEBORO, VT 12210C A004(152)

Project Name / Number

Fourth Quarter Total

August Monthly Total

September Monthly Total

$1,395,000

$33,108,000

$2,924,000

$37,355,300

$1,395,000

$0

$2,339,200

$0

06-Aug-19

27-Aug-19

06-Sep-19

17-Sep-19

$34,503,000

$40,279,300

$1,395,000

$2,339,200

$80,115,000

$229,650,800

$8,978,300

$88,374,600

August 2019

September 2019

Contact Person: Joseph Adams

Contact Person: Bob Landry

Contact Person: C.R. Willeke

Contact Person: Don Lyford

07/02/18Print Date: 2019 Page 9 of 9

SANBORNTON-NEW HAMPTON 41705 X-A004(718)

CONCORD-ASHLAND-CAMPTON 41706 X-A004(719)

CONCORD-HOPKINTON 41703 X-A004(716)

OSSIPEE 29315 X-A003(995)

Project Name / Number

I-93 Painting I-93 bridges between Sanbornton and New Hampton[Bridg-T1-2-Main-Pres]

I-93 Painting I-93 bridges in Concord, Ashland, and Campton[Bridg-T1-2-Main-Pres, Bridg-T3-4-Main-Pres]

I-89 Painting I-89 bridges between Concord and Hopkinton[Bridg-T1-2-Main-Pres, Bridg-T3-4-Main-Pres]

NH 28 NH 28 / NH 171 intersection safety improvements[HSIP *]

Project Description

08-Jan-19

15-Jan-19

13-Aug-19

10-Sep-19

Target Ad Date

$1,962,300

$2,334,300

$2,371,500

$418,500

Approx. Contract Amt.

$1,962,300

$2,334,300

$2,371,500

$418,500

Federal Dollars

ON-SHELF PROJECTS

Fiscal Year 2019

On-Shelf Projects 2019 Total $7,086,600 $7,086,600

Contact Person: David Scott

Contact Person: David Scott

Contact Person: David Scott

Contact Person: Mike Dugas

On Shelf Projects Advertising are subject to availability of funding.In addition these projects are subject to STIP Amendments to bring them into the current fiscal year.

Project Previous Ad Date Revised Ad Date Explanation

Statewide 40803 July 10, 2018 July 17, 2018

Project delayed by Project Development (Highway

Design) to complete contract proposal

Laconia 16144 June 26, 2018 July 24, 2018

Project delayed by Project Development (Bridge

Design) to address Right-of-Way (ROW)

clearance

Ossipee 14749 July 10, 2018 July 24, 2018

Project delayed by Project Development (Highway

Design) to complete contract proposal

Litchfield 29733 August 14, 2018

New project through Turnpike Bureau for building

demolition

Hopkinton 41303 November 6, 2018 August 14, 2018

Project advanced by Project Development (Bridge

Design) within bridge perservation program

Statewide 41614 January 22, 2019 September 11, 2018

Pavement preservation project advanced by

Project Development (Highway Design)

Alexandria 15937 August 21, 2018 October 16, 2018

Project delayed by Project Development (Highway

Design) to address wetland permit clearance

Warren 41738 September 4, 2018 December 11, 2018

Project delayed by Project Development (Highway

Design) to address wetland permit and ROW

clearance

Lebanon 25821 October 23, 2018 January 8, 2019

Project delayed by Project Development (Bridge

Design) to coordinate with City infrastructure

projects

Lebanon 41191 November 3, 2020 March 19, 2019

Project advanced by Project Development (Bridge

Design) for funding under HB 1817

Bedford-Merrimack

16100 November 6, 2018 November 12, 2019

Project delayed by Turnpikes to allow for

Legislative study on AET

Advertisement Schedule Changes for NHDOT Managed Projects

from June 2018 to May 2019