BIN: Locality: QUEENS No Flags have been issued during this inspection Number of Spans: Type of Inspection: Eugene T. Grant Date: FOCH BLVD Structure Information Upendra Wagley, P.E. 069000-1 1055640 Inspection Date City of NEW YORK This Structure is not a Ramp Report Reviewed by: Postings (As of Inspection Date): May 29, 2015 Approximate Year Built: Reviewer Signature: Upendra Wagley 11 Feature Carried: Typical or Main Span Type: County: 2 - NORTHEAST Region: 2 Structure is wholly or partially owned or maintained by New York State Department of Transportation Posted Vertical Clearance Under: Eugene T. Grant, P.E. 073380-1 5.681 Computed Condition Rating: Action Items There are no vulnerability reviews recommended November 12, 2015 Not Posted No Further Investigation Requested General Report Printed: Not Posted Not Posted July 17, 2015 Posted Vertical Clearance On: 678I678IX5M11011 Signature Information No Diving Inspection Requested Inspection Signature: General Recommendation: Bridge Inspection Report New York State New York State Inspection Overview Structure Inspected By: Date: 02 - Stringer/Multi-Beam or Girder Department of Transportation Feature Crossed: 1948 Inspector & Reviewer Information 6 Orientation: Load Posting: 7/16/15 2:29 PM Page 1 of 24

New York State Department of Transportation Bridge Inspection … · 2015. 5. 29. · 05/29/2015 12:00 PM 04:00 PM 79 Sunny 05/26/2015 12:00 PM 03:00 PM 82 Sunny Page 7 of 24. BIN:

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

  • BIN: Locality:QUEENS

    No Flags have been issued during this inspection

    Number of Spans:

    Type of Inspection:

    Eugene T. Grant

    Date:

    FOCH BLVD

    Structure Information

    Upendra Wagley, P.E. 069000-1

    1055640

    Inspection Date

    City of NEW YORK

    This Structure is not a Ramp

    Report Reviewed by:

    Postings (As of Inspection Date):

    May 29, 2015

    Approximate Year Built:

    Reviewer Signature:

    Upendra Wagley

    11Feature Carried:

    Typical or Main Span Type:

    County:

    2 - NORTHEAST

    Region:

    2Structure is wholly or partially owned or maintained by New York State Department of Transportation

    Posted Vertical Clearance Under:

    Eugene T. Grant, P.E. 073380-1

    5.681Computed Condition Rating:

    Action Items

    There are no vulnerability reviews recommended

    November 12, 2015

    Not Posted

    No Further Investigation Requested

    General

    Report Printed:

    Not Posted

    Not Posted

    July 17, 2015

    Posted Vertical Clearance On:

    678I678IX5M11011

    Signature Information

    No Diving Inspection Requested

    Inspection Signature:

    General Recommendation:

    Bridge Inspection Report

    New York State

    New York State Inspection Overview

    Structure Inspected By:

    Date:

    02 - Stringer/Multi-Beam or Girder

    Department of Transportation

    Feature Crossed:1948

    Inspector & Reviewer Information

    6

    Orientation:

    Load Posting:

    7/16/15 2:29 PM

    Page 1 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    Structure RatingsAbutment Elements Begin Abutment End Abutment

    4Joint with Deck 46Bearings, Bolts, Pads 64Seat and Pedestals 46Backwall 66Stem (Breastwall) 67Erosion or Scour 79Footings 98Piles 85Recommendation 5

    Wingwall Elements Begin Abutment End Abutment7Walls 79Footings 97Erosion or Scour 78Piles 8

    Channel ElementsStream Alignment 8Erosion and Scour 8Waterway Opening 8Bank Protection 8

    Approach ElementsDrainage 7Embankment 8Settlement 7Erosion 8Pavement 6Guide Railing 8

    Page 2 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    Span Ratings

    Element Sub Element 1 2

    Deck Elements Wearing Surface 6 6Curbs 6 6Sidewalks & Fascias 6 6Railings & Parapets 6 6Scuppers & Downspouts 8 8Gratings 8 8Median 8 8

    Superstructure Deck Structural 5 5Primary Members 6 6Secondary Members 6 6Paint 5 5Joints 8 8Recommendation 6 6

    Pier Bearings, Bolts, Pads 6 8Pedestals 7 8Top of Cap or Beam 7 8Stem Solid Pier 6 8Cap Beam 8 8Pier Columns 8 8Footings 9 8Erosion or Scour 7 8Piles 8 8Recommendation 6 8

    Utilities Lighting 7 7Sign Structures 5 5Utilities & Supports 6 6

    Page 3 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    NBI Deck Condition:

    NBI Superstruct Condition:

    NBI Substruct Condition:

    NBI Channel Condition:

    NBI Culvert Condition:

    8

    8

    8

    N

    N

    Federal NBI RatingsFederal Inspection Findings

    Special Emphasis RequirementsSpecial Emphasis Inspection RequirementsNon-Redundant/Fracture Critical Members: No

    Pin and Hangers: No

    Fatigue-Prone Welds: No

    Non-Categorized Fatigue-Prone Details: No

    NoOther (Specified in Text):

    Special Emphasis Detail NotesNone

    Special Emphasis Certification:

    Special Emphasis Certification

    Hands-On Inspection Waived/Exception:

    Note:

    No

    No

    Page 4 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    Inspection Notes

    1. BIN Plate is located at Begin Abutment and is in good condition.

    2. Stone facing at both Abutment Stems, Wingwalls and Pier nose were inspected and found tobe in good condition.

    3. Debris / Land Use form has been prepared and attached to this report.

    4. The underside of the structural deck is covered with SIP forms in all Bays, except for Bay 6and is in satisfactory condition.The Underside of the fascias and concrete deck in Bay 6 werevisualy inspectected and approximately 20% was sounded. No loose concrete was found.

    There are no photographs referenced for this commentGENERAL COMMENT

    At the top of the deck, the Begin Abutment Joint sealer material over the Westbound lanes ispushed out across the length and shredded for 1.5' long over the right lane. On the Eastboundlanes, there is only minor debris accumulation.

    Below the deck, there is sign of leakage on several Bays, as water and rust stains are presenton the Backwall.

    Rating is downgraded to 4.

    Referenced Photos: 1,2Abutment - Joint with Deck - Begin - Rated 4

    At the top of the deck, the End Abutment Joint has minor debris accumulation across its length.The bridge side concrete header has minor edge spalls along the armor angle edge.

    Below the deck, there is sign of leakage on several Bays, as water and rust stains are presenton the Backwall.

    Rating is downgraded to 4.

    Referenced Photos: 2,4Abutment - Joint with Deck - End - Rated 4

    The top of the Bridge Seat has pigeon droppings up to 4" high at various locations. Thiscondition can trap moisture and cause deterioration of the Begin Abutment bridge elements.

    Referenced Photos: 3Abutment - Seat and Pedestals - Begin - Rated 4

    The top of the Bridge Seat has pigeon droppings up to 4" high at various locations. Thiscondition can trap moisture and cause deterioration of the End Abutment bridge elements.

    Referenced Photos: 3Abutment - Seat and Pedestals - End - Rated 4

    Page 5 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    The underside of the structural deck is covered with SIP forms in all Bays, except for Bay 6. TheSIP forms exhibit minor corrosion with leaching efflorescence at scattered locations, mainly inBays 3, 4, 5, 7, and 8.

    The Underside of the fascias and concrete deck in Bay 6 were visualy inspectected andapproximately 20% was sounded. No loose concrete was found.

    Referenced Photos: 5Span 1-Superstructure - Deck Structural - Rated 5

    The Sign Structure attached to Span 1, left fascia, exhibits paint peeling and rust with minorcorrosion on the supporting angles and plates.

    Referenced Photos: 6Span 1-Utilities - Sign Structures - Rated 5

    The underside of the structural deck is covered with SIP forms in all Bays, except for Bay 6. TheSIP forms exhibit minor corrosion with leching efflorescence at scattered locations, mainly inBays 3, 4, 5, 7, and 8.

    The Underside of the fascias and concrete deck in Bay 6 were visualy inspectected andapproximately 20% was sounded. No loose concrete was found.

    Referenced Photos: 5Span 2-Superstructure - Deck Structural - Rated 5

    The Sign Structure attached to Span 2, right fascia, exhibits paint peeling and rust with minorcorrosion on the supporting angles and plates.

    Referenced Photos: 6Span 2-Utilities - Sign Structures - Rated 5

    Additional Inspection NotesDiving ReferenceThere was no dive referenced for this inspection.

    Overloads ObservedNo overload vehicles were noted during this inspection.

    Notes to Next Inspector

    There were no notes to the next inspector recorded for this inspection.

    No improvements were observed during this inspection.

    Improvements Observed

    Page 6 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    Staff Present During InspectionField Notes

    BIN Plate and Fencing information

    No Snow Fence.

    A Pedestrian Fence is present.

    The BIN Plate is in OK condition.

    Team Leader: Upendra WagleyAssitant Team Leader: Paul Taveras

    Inspection Time & Permit RequirementsTime Required to Inspect Bridge:

    Lane Closure Usage:

    No railroad flagging required

    By Contractor for 9 Hours

    11 Hours

    Railroad Flagging Time:

    Detailed Time & WeatherField Date Arrival Departure Temp (F) Weather Conditions

    12:00 PM 04:00 PM 84 Partly Sunny05/27/201512:00 PM 04:00 PM 79 Sunny05/29/201512:00 PM 03:00 PM 82 Sunny05/26/2015

    Page 7 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    Inspection PhotographsPhoto #1Top of the deck at begin

    abutment, looking rightBegin Abutment Jointsealer material over theWestbound lanes is pushedout across the length andshredded for 1.5' long overthe right lane.

    15_1055640_0003.jpgPhoto Number: 1 Photo Filename:

    Photo #2End abutment, bays 4 and5, looking aheadSigns of leakage asevidenced by water andrust stains on the backwall.Begin abutment similar.

    15_1055640_0011.JPGPhoto Number: 2 Photo Filename:

    Page 8 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    Photo #3End abutment, bay 8,looking ahead and leftAccumulation of pigeondroppings on the bridgeseat. Begin abutment issimilar.

    15_1055640_0012.JPGPhoto Number: 3 Photo Filename:

    Photo #4Above the deck at endabutment, looking leftEnd Abutment Joint hasminor debris accumulationacross its length. Thebridge side concreteheader has minor edgespalls along the armorangle edge.

    15_1055640_0001.JPGPhoto Number: 4 Photo Filename:

    Page 9 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    Photo #5Span 1, bays 4 and 5,looking aheadSIP forms exhibit minorcorrosion with leachingefflorescence at scatteredlocations. Span 2 is similar.

    15_1055640_0025.JPGPhoto Number: 5 Photo Filename:

    Photo #6Span 2, right fascia, lookingback and leftThe Sign Structure exhibitspaint peeling and rust withminor corrosion on thesupporting angles andplates. Similar condition onleft fascia of span 1.

    15_1055640_0014.JPGPhoto Number: 6 Photo Filename:

    Page 10 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    Inspection SketchesSketch Filename: 15_BD240 (BIN 1055640).jpg

    Sketch Filename: 15_BD240 (BIN 1055640).jpg

    Page 11 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    Standard Photographs1055640_LOCATION_MAP.JPG

    Page 12 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    1055640_QUAD_MAP.JPG

    Page 13 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    AbutmentBegin.JPG

    Page 14 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    AbutmentEnd.JPG

    Page 15 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    ApproachBegin.JPG

    Page 16 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    ApproachEnd.JPG

    Page 17 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    ElevationLeft.JPG

    Page 18 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    ElevationRight.JPG

    Page 19 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    F2andF3CrossedLeft.JPG

    Page 20 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    F2andF3CrossedRight.JPG

    Page 21 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    FramingSpan1.JPG

    Page 22 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    Pier1.JPG

    Page 23 of 24

  • BIN: 1055640 Bridge Inspection ReportInspection Date: May 29, 2015

    WingwallEndLeft.JPG

    Page 24 of 24

    Structure InformationStructure RatingsSpan RatingsFederal Inspection FindingsSpecial Emphasis RequirementsInspection NotesGENERAL COMMENTAbutment - Joint with Deck - BeginAbutment - Joint with Deck - EndAbutment - Seat and Pedestals - BeginAbutment - Seat and Pedestals - EndSpan 1-Superstructure - Deck StructuralSpan 1-Utilities - Sign StructuresSpan 2-Superstructure - Deck StructuralSpan 2-Utilities - Sign Structures

    Additional Inspection NotesField NotesInspection PhotographsPhoto #1Photo #2Photo #3Photo #4Photo #5Photo #6

    Inspection SketchesSketch Filename: 15_BD240 (BIN 1055640).jpg

    Standard Photographs1055640_LOCATION_MAP.JPG1055640_QUAD_MAP.JPGAbutmentBegin.JPGAbutmentEnd.JPGApproachBegin.JPGApproachEnd.JPGElevationLeft.JPGElevationRight.JPGF2andF3CrossedLeft.JPGF2andF3CrossedRight.JPGFramingSpan1.JPGPier1.JPGWingwallEndLeft.JPG