Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Document of
The World Bank
FOR OFFICIAL USE ONLY
Report No: PAD1512
INTERNATIONAL DEVELOPMENT ASSOCIATION
PROJECT PAPER
ON A
PROPOSED ADDITIONAL GRANT
IN THE AMOUNT OF SDR 2.0 MILLION
(US$2.8 MILLION EQUIVALENT)
TO THE
REPUBLIC OF HAITI
FOR A
INFRASTRUCTURE AND INSTITUTIONS EMERGENCY RECOVERY PROJECT
October 28, 2016
Transport and ICT Global Practice
Latin America and the Caribbean Region
This document is being made publicly available prior to Board consideration. This does
not imply a presumed outcome. This document may be updated following Board
consideration and the updated document will be made publicly available in accordance
with the Bank’s policy on Access to Information.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
CURRENCY EQUIVALENTS
(Exchange Rate Effective: October 17, 2016)
Currency Unit = Haitian Gourds
64.7 HTG = 1 USD
0.73000 SDR = 1 USD
FISCAL YEAR
October 1 – September 30
ABBREVIATIONS AND ACRONYMS
AF Additional Financing
BRH Haiti Central Bank (Banque de la République d’Haiti)
CIAT Inter-ministerial Committee for Territorial Planning (Comité Interministériel
d'Aménagement du Territoire)
CNMP Procurement Regulatory Agency (Commission Nationale des Marches Publics)
CPF Country Partnership Framework
CS-CCA Supreme Audit Institution (Cour Supérieure des Comptes et du Contentieux
Administratif)
GoH Government of Haiti
ICB International Competitive Bidding
IDA International Development Association
IDB Inter-American Development Bank
IGF Financial Inspectorate (Inspection Générale des Finances)
IHSI Haitian Statistics Institute
IIERP Infrastructure and Institutions Emergency Recovery Project
IMF International Monetary Fund
MEF Ministry of Economy and Finance (Ministère de l’Economie et des Finances)
MPCE Ministry of Planning and External Cooperation (Ministère de Planification et
Coopération Externe)
MTPTC Ministry of Public Works, Transportation and Communication (Ministère de
Travaux Publics, Transport et Communications)
NCB National Competitive Bidding
NGO Non-Governmental Organization
OM Operations Manual
OCPAH Association of Chartered Public Accountants of Haiti (Ordre des Comptables
Professionnels Agréés d’Haiti)
PCU Project Coordination Unit (Unité de Coordination de Projet)
PDO Project Development Objective
PEFA Public Expenditure and Financial Accountability
PIMAP Public Investment Management Action Plan
PFM Public Financial Management
PFMRAP Public Financial Management Reform Action Plan
PPA Project Preparation Advance
QCBS Quality Cost Based Selection
3
SBD Standard Bidding Document
SDR Special Drawing Rights
SYSDEP Expenditure Information System (Système d’Informatisation des Dépenses)
SYSGEP Public Investment Information System (Système de Gestion de Projets)
UCE Central Execution Unit (Unité Centrale d’Exécution) (PCU of MTPTC)
UCP Project Coordination Unit (Unité de Coordination de Projet – UCP-MEF)
ULCC Anticorruption Agency (Unité de Lutte Contre la Corruption)
USAID United States Agency for International Development
Vice President: Jorge Familiar
Country Director: Mary Barton-Dock
Senior Global Practice Director:
Acting Practice Manager:
Pierre Guislain
Gylfi Palsson
Task Team Leaders: Pierre Xavier Bonneau,
Mamadou Lamarane Deme
4
HAITI
INFRASTRUCTURE AND INSTITUTIONS EMERGENCY RECOVERY PROJECT –
ADDITIONAL FINANCING
CONTENTS
........................................................................................................................ 9
.................................................. 10 A. Country Context ......................................................................................................... 10
B. Sectoral and Institutional Context .............................................................................. 12
C. Consistency with CPF ................................................................................................ 12
D. Parent and First Additional Financing Project Background ....................................... 13
E. Status of Implementation ............................................................................................ 13
F. Rationale for Additional Financing, Project Restructuring and Additional Benefits . 14
............................................................................................................ 14 A. Proposed Changes Data Sheet .................................................................................... 15
B. Revised Financing Plan .............................................................................................. 21
C. Results Framework ..................................................................................................... 21
D. Institutional Arrangements ......................................................................................... 21
E. Social, Environmental and Fiduciary ........................................................................ 21
F. Amendment to Financing Agreement ......................................................................... 22
......................................................................................................... 22
..................................................................................... 23
................................... 25
....................................................................................... 39
.................................................................................... 40
..................................................................... 41
......................... 44
5
ADDITIONAL FINANCING DATA SHEET
Haiti
Second Additional Financing for Infrastructure & Institutions Emergency Recovery (P156049)
LATIN AMERICA AND CARIBBEAN
GTI04
Basic Information – Parent
Parent Project ID: P120895 Original EA Category: A - Full Assessment
Current Closing Date: 31-Dec-2016
Basic Information – Additional Financing (AF)
Project ID: P156049 Additional Financing
Type (from AUS): Scale Up
Regional Vice President: Jorge Familiar Proposed EA Category: A
Country Director: Mary A. Barton-Dock Expected Effectiveness
Date: 8-Feb-2017
Senior Global Practice
Director: Pierre Guislain Expected Closing Date: 31-Dec-2017
Acting Practice
Manager: Gylfi Palsson Report No: PAD1512
Team Leader(s):
Pierre Xavier
Bonneau,Mamadou
Lamarane Deme
Borrower
Organization Name Contact Title Telephone Email
Ministry of Economy and
Finance, MEF Lys Faucher
Head of
UCP
011-509-3701-
7662 [email protected]
Project Financing Data - Parent (Infrastructure & Institutions Emergency Recovery-
P120895) (in USD Million)
Key Dates
Project Ln/Cr/TF Status Approval
Date Signing Date
Effectiveness
Date
Original
Closing Date
Revised
Closing Date
P120895 IDA-H5510 Effectiv
e 18-Mar-2010 22-Mar-2010 23-Apr-2010 30-Jun-2013 31-Dec-2016
P120895 IDA-H8120 Effectiv
e 27-Sep-2012 06-Nov-2012 05-Feb-2013 30-Jun-2016 31-Dec-2016
Disbursements
Project Ln/Cr/TF Status Currency Original Revised Cancelled Disburse
d
Undisbu
rsed
%
Disbursed
P120895 IDA-H5510 Effectiv XDR 41.90 41.90 0.00 41.90 0.00 100.00
6
e
P120895 IDA-H8120 Effectiv
e XDR 23.30 23.30 0.00 13.22 10.08 56.75
Project Financing Data - Additional Financing Second Additional Financing Infrastructure
& Institutions Emergency Recovery (P156049)(in USD Million)
[ ] Loan [ ] Grant [X] IDA Grant
[ ] Credit [ ] Guarantee [ ] Other
Total Project Cost: 2.80 Total Bank Financing: 2.80
Financing Gap: 0.00
Financing Source – Additional Financing (AF) Amount
BORROWER/RECIPIENT 0.00
IDA Grant 2.80
Total 2.80
Policy Waivers
Does the project depart from the CAS in content or in other significant respects? No
Explanation
Does the project require any policy waiver(s)? No
Explanation
Bank Staff
Name Role Title Specialization Unit
Pierre Xavier Bonneau Team Leader
(ADM
Responsible)
Program Leader Program Leader LCC8C
Mamadou Lamarane
Deme
Team Leader Program
Manager
CO-TTL LCRRF
Prosper Nindorera Procurement
Specialist (ADM
Responsible)
Senior
Procurement
Specialist
Sr. Procurement Specialist GGO04
Fabienne Mroczka Financial
Management
Specialist
Sr. Financial
Management
Specialist
Sr. Financial Management
Specialist
GGO22
Aboubacar
Magassouba
Team Member Consultant Procurement Specialist GGO04
Asli Gurkan Safeguards
Specialist
Senior Social
Development
Specialist
Senior Social Development
Specialist
GSU04
Jacqueline Beatriz
Veloz Lockward
Counsel Paralegal Paralegal LEGLE
7
Malaika Becoulet Team Member E T Consultant Transport & Disaster Risk
Management Analyst
GTI04
Margaret Patricia
Henley Barrett
Team Member Consultant Urban & Disaster Risk
Management Specialist
GTI04
Ignacio Jauregui Counsel Country Lawyer Senior Counsel LEGLE
Isabella Micali-
Drossos
Counsel Senior Counsel Senior Counsel LEGLE
Andrianirina Michel
Eric Ranjeva
Team Member Finance Officer Finance Officer WFALA
Faly Diallo Team Member Finance Officer Finance Officer WFALN
Locations
Country First Administrative
Division
Location Planned Actual Comments
Haiti Departement de
l'Ouest
Port-au-Prince X X
Haiti Republic of Haiti
Institutional Data
Parent ( Infrastructure & Institutions Emergency Recovery-P120895 )
Practice Area (Lead)
Transport & ICT
Contributing Practice Areas
Macro Economics & Fiscal Management
Cross Cutting Topics
[ ] Climate Change
[ ] Fragile, Conflict & Violence
[ ] Gender
[ ] Jobs
[ ] Public Private Partnership
Sectors / Climate Change
Sector (Maximum 5 and total % must equal 100)
Major Sector Sector % Adaptation Co-
benefits %
Mitigation Co-
benefits %
Transportation Urban Transport 35
Water, sanitation and flood protection Flood protection 20
Public Administration, Law, and
Justice
Public administration-
Financial Sector
20
Water, sanitation and flood protection Wastewater Collection
and Transportation
15
8
Public Administration, Law, and
Justice
Central government
administration
10
Total 100
Themes
Theme (Maximum 5 and total % must equal 100)
Major theme Theme %
Social protection and risk management Natural disaster management 100
Total 100
Additional Financing Second Additional Financing Infrastructure & Institutions Emergency
Recovery (P156049)
Practice Area (Lead)
Transport & ICT
Contributing Practice Areas
Governance, Macro Economics & Fiscal Management
Cross Cutting Topics
[ ] Climate Change
[ ] Fragile, Conflict & Violence
[ ] Gender
[ ] Jobs
[ ] Public Private Partnership
Sectors / Climate Change
Sector (Maximum 5 and total % must equal 100)
Major Sector Sector % Adaptation Co-
benefits %
Mitigation Co-
benefits %
Public Administration, Law, and
Justice
Public administration-
Financial Sector
100
Themes
Theme (Maximum 5 and total % must equal 100)
Major theme Theme %
Public sector governance Public expenditure, financial
management and procurement
100
Total 100
Consultants (Will be disclosed in the Monthly Operational Summary)
Consultants Required ?Consultants will be required
9
1. This Project Paper seeks the approval of the Executive Directors to provide an additional
grant in the amount of SDR 2.0 million (US$2.8 million equivalent) to the Republic of Haiti for
the Infrastructure and Institutions Emergency Recovery Project (IIERP – P120895; IDA Grant
Nos. H551-0-HT; H812-0-HT).
2. On October 3, 2016, a category IV Hurricane, Matthew, hit Haiti and caused a large-scale
disaster and a humanitarian emergency. The Bank is providing an immediate response to this
hurricane through existing IDA operations, including this proposed Additional Financing (AF) as
well as a proposed Providing Education of Quality in Haiti Project (P155191). The AF and
Education project were prepared prior to the disaster but, given their scope and location of
investments, will help address impacts. Specifically, this proposed second additional grant
would finance new activities aimed at supporting governance and public financial management
(PFM) (Component 1), which is a critical need in the context of the current emergency, as well
as complete ongoing road rehabilitation works. The resources would also cover the financing gap
due to the depreciation of the SDR allocation.
3. The proposed Additional Financing (AF) (P156049, Grant No. IDA- D1360-HT) would
also involve a level two project restructuring, which would include:
(i) an extension of the closing date of the Project by 12 months, from December 31,
2016 to December 31, 2017, to allow for the completion of additional activities
deriving from the recently adopted Public Financial Management Reform Action Plan
(PFMRAP) under Component 1, and the rehabilitation of the road between Cap
Haitian and Labadie under Component 2 of the parent Project;
(ii) dropping the EDH (Power Utility) financial statements audit (now covered by the
IDA-financed Rebuilding Energy Infrastructure and Access Project (P127203), the
WIMAX backup of the Central Bank payment system network and the Civil Service
census, all under Component 1; these freed resources would remain within
Component 1 to cover new activities stemming from the PFMRAP and the Public
Investment Management Action Plan (PIMAP);
(iii) dropping the Rehabilitation of Aviation Safety Equipment, works for the
rehabilitation of the road between Milot and Cap Haïtien, and mineral extraction, all
under Component 2, due to shifting government priorities and use of domestic
resources for these activities;
(iv) reallocation of funds to reflect those activities already completed and the discrepancy
between planned expenditures versus actual expenditures; and
(v) modifications to the PDO Level and Intermediate Level Results Indicators to monitor
the results expected from the modified activities.
4. This is the second AF to the IIERP. The first additional grant in the amount of SDR 23.3
million (US$35.0 million equivalent), complemented the parent grant of SDR 41.9 million
(US$65 million equivalent), and financed the scale-up of activities of the parent Project. With
10
the proposed second AF, the level of International Development Association (IDA) funding for
the Project would increase from SDR 65.2 million (US$100 million equivalent) to SDR 67.2
million (US$102.8 million equivalent). The proposed second AF would not entail any change to
the project development objective or its institutional and implementation arrangements.
A. Country Context
5. Haiti’s geography, people, and history provide it with many opportunities. The third
largest Caribbean nation by area and population (10.4 million), Haiti shares the island of Kiskeya
with the Dominican Republic. In addition to an illustrious early history, as the first independent
nation in the region and the first nation in the world to be led to independence by former slaves,
Haiti benefits from proximity and access to major markets, a young labor force, a dynamic
diaspora, and substantial geographic, historical, and cultural assets. The country possesses
untapped markets and a pent-up demand for the private sector to explore, including in
agribusiness, light manufacturing, and tourism.
6. Yet Haiti remains the poorest country in the Western Hemisphere and one of the poorest
countries in the world, with a 2014 GDP per capita of US$824. Almost 60 percent of the
population lives below the national poverty line and inequality is high, with wealth and
economic opportunity concentrated around Port-au-Prince.[1]
Access to basic services is limited,
particularly in rural areas, which has translated into low human development indicators (Haiti
ranks 168th out of 187 countries in the Human Development Index).
7. Six years after the catastrophic earthquake of 2010, reconstruction efforts have yielded
tangible progress. The earthquake killed an estimated 230,000 people (including scores of
professionals and public servants) and displaced 1.5 million, causing damages and losses of 120
percent of GDP.[2]
Reconstruction followed in the wake of the humanitarian effort, and progress
has been made in several areas. Extreme poverty fell from 31 percent to 24 percent between
2000 and 2012, infrastructure and private sector activity have expanded, and health and
education indicators have improved over the same period, thanks in part to substantial expansion
of donor assistance after the earthquake and to sustained levels of remittances from the Haitian
Diaspora. Nevertheless, Haiti remains extremely vulnerable to natural disaster with 96 percent of
the population at risk. On average, each disaster costs 2 percent per GDP per year, and
occasionally much more.
8. On October 3, 2016, Hurricane Matthew, a category IV hurricane, landed in Haiti and
caused a large scale disaster affecting over 2.1 million people (almost 1/5 of the population) and
leaving almost 1.4 million people in need of lifesaving assistance in the southern part of the
country. Winds speeds up to 140 mph and torrential rain for 48 hours (around 1,016 mm)
triggered widespread flooding and numerous landslides and caused severe damage to all sectors -
[1]
The national consumption-based poverty line is US$1.98 per day, and the Gini coefficient is the highest in Latin
America at 0.6. These results are presented in Investing in People to Fight Poverty in Haiti (World Bank 2015). [2]
These results are presented in the Haiti Country Partnership Framework (Report No.98132-HT).
11
water, electricity, education, health, food security, and livelihoods - particularly in the South
Grand-Anse, and Nippes departments. The disaster also resulted in heavy damage to road
infrastructure and buildings with thousands of houses flooded and without roofs as well as
destruction of major bridges and roads. Substantial damage was also sustained in the agricultural
sector with up to 80 to 90 percent losses of crops in some areas, including staple food, tree crops,
and livestock. An upward of 500 schools are also estimated to have been destroyed and
approximately 3,000 schools damaged, thus disrupting school for nearly over 470,000 children
of ages six to fourteen. An uptake of suspected cholera cases has been reported in the affected
departments where facilities were heavily damaged.
9. The hurricane has also exacerbated an already fragile state, where political uncertainty
and a deteriorating economic environment were threatening post-earthquake gains. Nearly
simultaneous municipal, parliamentary, and presidential elections in 2015 exacerbated
underlying divisions in society, and contested election results in the late 2015 led to the
appointment of a transitional government. Elections were rescheduled for October 9, 2016 and
November 27, 2016. However, the damage sustained during the Hurricane Matthew triggered
further postponement of the elections to November 20, 2016 and January 29, 2017.
10. Matthew is also expected to compound major economic challenges. Despite robust
macroeconomic management, Haiti has seen limited growth, low revenue generation, and
declining external financing (from aid and concessional borrowing), driven by shifts in
international priorities and deteriorating global and regional economic conditions.[3]
Moreover,
an ongoing drought over the last three growing seasons has increased food insecurity,
contributed to high inflation of domestic food prices and caused a contraction of the agricultural
sector, which employs the majority of the poor. Taken together, these factors contribute to a
decline in available resources for service delivery from the State and to increasing difficulty for
households, who bear a large share of education and health costs, to cover such expenses,
threatening the progress made in human development and poverty reduction. According to
preliminary estimates, damages and losses caused by Matthew will likely amount 22 percent of
GDP. It is also expected that the restoration of agriculture in the areas affected is likely to be
very challenging. These developments are likely to further hamper domestic resources
mobilization and increase Haiti’s reliance on official development assistance and remittances.
11. In terms of both immediate disaster response and long-term recovery, support from
Haiti’s partners for improvements in governance is critical, since weak public sector
management is one of the key constraints to quality public service delivery, including in disaster
recovery management. The Bank Systematic Country Diagnostic revealed that Haiti’s dismal
developmental results can easily be attributed to many factors, including primarily the limited
capacity of the Government to steer economic and social development, combined with persistent
political instability and frequent natural disasters. These challenges translate into: (i) poor
governance; (ii) absence of accountability; and, (iii) weak institutional capacity compounded by
outsourcing of key public service delivery in social sectors (Education, Health, Water,
Sanitation, etc.) to donors and NGOs, especially after the 2010 earthquake. However, with
massive aid inflows in sharp decrease six years after the earthquake, the Government has begun
[3]
Details are discussed in the Haiti Systematic Country Diagnostic (SCD) referenced below.
12
work to increase efficiency and effectiveness in the use of available resources to better deliver on
public services, and understands that an overhaul of PFM institutions, systems and processes is
needed to support these efforts.
B. Sectoral and Institutional Context
12. The January 2010 earthquake further deepened the existing governance challenges by
severely diminishing already weak government capacity. Countries that have experienced major
natural disasters need assistance to restore the main functions of the State. Institution building is
a gradual and difficult process and a precondition for lasting change in Haiti. It can only be
achieved with strong and sustained commitment from Government, Donors, and Partners.
Despite demonstrating improvements in macroeconomic management in the last several years,
weaknesses in public sector management remain and hamper sustained economic growth and
poverty reduction. The impact of Hurricane Matthew on the country may also worsen the
situation and deepen these challenges.
13. Public Financial Management (PFM) capacity has been severely undermined following
the 2010 earthquake. Before the disaster, and with donors’ assistance, the country was trying to
overcome serious shortcomings in PFM, including lack of transparency and accountability in the
management of public resources, and limited institutional and organizational capacity. After the
quake, government efforts supplemented by donors support, especially from the Bank, helped in
restoring key financial management functions, and thereafter in forging the building blocks for
sustained PFM institutional development. In that regard, the Government devised and adopted a
Public Financial Management Reforms Action Plan (PFMRAP) in May 2014, which includes six
main areas related to budget management, treasury management, external controls, revenue
mobilization, financial decentralization, and financial information systems. In December 2014,
with Bank support, the Government also completed a review of the Public Investment
Management (PIM) system, and endorsed a PIM Action Plan (PIMAP) organized around 10
measures to strengthen public investment planning, programming, budgeting, execution, and
monitoring in the upcoming three years. Implementation of the PFMRAP and PIMAP is
underway under the GoH leadership and coordination.
14. As learned from the 2010 earthquake and previous emergencies in Haiti, prioritization,
accountability and efficiency in the management of public resources and delivery of services, as
well as appropriate use and effectiveness of donor assistance are key following a disaster. In that
perspective, the proposed second AF and restructuring would continue to support the
implementation of the PFMRAP and the PIMAP, building institutional capacity and public
financial management systems to improve public expenditures planning, budgeting, tracking,
accounting and reporting; public procurement; investment planning; controls in the use of public
resources; and by establishing a culture of transparency and accountability that aims to reduce
corruption.
C. Consistency with CPF
15. The proposed second AF is fully aligned with the Country Partnership Framework (CPF)
for Haiti (FY16-FY19), discussed by the Board of Executive Directors on September 29, 2015
(Report No. 98132-HT). Activities to be financed by the proposed second AF would contribute
13
to the strategic objective of promoting inclusive growth and to the cross-cutting objective of
strengthening governance and helping Haiti to mitigate the impact of natural disasters.
D. Parent Project and First Additional Financing Background
16. Parent Project Grant (H551-0-HT): The original IIERP in the amount of SDR 41.9
million (US$65 million equivalent) was approved on March 1, 2010, and became effective on
April 23, 2010. The original closing date of the project was June 30, 2013.
17. First Additional Financing (H812-0-HT): The first Additional Financing to the IIERP in
the amount of SDR 23.3 million (US$35 million equivalent) was approved by the Executive
Board of Directors on September 27, 2012. The AF became effective on February 5, 2013, and
the closing date was June 30, 2016.
18. Project Restructuring: The project closing date was extended once by 36 months with
the first Additional Financing to June 30, 2016, and again by 6 months to December 31, 2016
with the Project Restructuring in June 2016, for a total cumulative extension of 54 months. The
extension allowed for the completion of the remaining activities to strengthen public financial
management under Component 1, and for the continued rehabilitation of the road between Cap
Haïtien and Labadie under Component 2.
19. The Project Development Objective (PDO) is to support the Recipient in its sustainable
recovery efforts from the effects of the Emergency, through selected interventions aiming at
contributing to rebuilding key institutions and infrastructure. The PDO of the parent Project was
slightly revised under the first AF to remove the word “early” before “recovery efforts.”
Additionally, project activities were expanded under the first AF. The achievement of the PDO
is supported by the following project components: (1) restoring key economic and financial
functions of the recipient, (2) emergency rehabilitation of selected public infrastructure, and (3)
institutional support, reconstruction planning and project management. The proposed second AF
will support Component 1 of the Project, as described in the Financing Agreement.
E. Status of Implementation
20. The implementation of the IIERP is proceeding reasonably well, with both the
Implementation Progress (IP) and Development Objective (DO) rated consistently over the last
twelve months as “Moderately Satisfactory”. The Project has also demonstrated substantial
compliance with key loan covenants, including audit and financial management reporting
requirements. The parent Project has disbursed a total of US$64.5million (equivalent to 100
percent) and the Additional Financing has disbursed a total of US$20.39 million (equivalent to
58.26 percent) as of October 10, 2016. The Project has complied with all environmental, social
and fiduciary safeguard requirements, and both financial management and procurement have
been carried out in accordance with the Bank’s Financial Management and Procurement
Guidelines. Component 1 of the parent Project and first AF assisted the government in achieving
the full re-establishment (through relocation and physical structure rehabilitation), and thereafter
operationalization (through provision of goods, equipment and technical assistance) of key
government financial institutions. The first AF also supported the preparation and adoption of
14
the new PFMRAP, as well as the PIMAP, both of which address PFM reforms in a strategic and
coordinated approach.
F. Rationale for Additional Financing, Project Restructuring and Additional Benefits
21. The Government of Haiti (GoH) officially requested additional financing from the World
Bank to offset the impact of the recent drop in the SDR/$ exchange rate which resulted in a
financing gap estimated at US$0.5 million for Component 1. The proposed AF would also
finance an increase in costs of ongoing activities under Component 1 of the Project due to minor
cost overruns for the construction of the airport customs office and additional needs arising from
the implementation of the PFMRAP and PIMAP, especially those related to the implementation
of the Information Technology Roadmap activities. More specifically, the proposed AF would
continue to support institutional capacity building and public financial management systems in
order: (i) to improve public expenditures planning, budgeting, tracking, accounting and
reporting; public procurement; investment planning; controls in the use of public resources; and
(ii) to foster a culture of transparency and accountability that aims to reduce corruption.
22. The proposed AF would provide the opportunity to effectively align the project activities
with key PFM reforms activities set out in the PFMRAP and PIMAP agreed upon with the GoH
and with donors interested in PFM reforms (see Annexes 4 and 5 for more details).
Scope of the Additional Financing
23. The proposed second AF would provide additional financing to support Component 1
(Restoring Key Economic and Financial Functions of the Recipient) of the Project with the
additional SDR 2.0 million (US$2.8 million equivalent). The existing PDO and other project
components remain relevant and there would be no change under the proposed AF.
24. This AF would also include a Level Two Restructuring with changes captured in
subsequent sub-sections.
Closing Date
25. The proposed second AF and restructuring would extend the closing date of the parent
Grant and the Additional Financing by 12 months from December 31, 2016 to December 31,
2017. The financing agreements of the parent Project and the first AF would be amended
accordingly. This extension would allow for the completion of the IT Roadmap as well as
PFMRAP and PIMAP activities supported under Component 1, and the rehabilitation of the road
between Cap Haitian and Labadie under Component 2.
15
Project Components
26. Component 1 – Restoring Key Economic and Financial Functions of the Recipient:
Under this component, some activities initiated with the parent Project, including the WIMAX1
backup of the Central Bank payment network and the Électricité d'Haïti (EDH) financial
statements preparation and audit2 would be dropped. The available resources released from these
discontinued activities (around US$2 million) and the residual envelope from the first AF
(US$1.6 million) would be mobilized to finance activities related to the implementation of the
PFMRAP and PIMAP. In addition to supplementing funding for cost overruns for the customs
building contract, and ongoing project activities that are already well aligned with the six priority
areas set out in the PFMRAP, the proposed second additional grant and restructuring will enable
the project to finance additional PFMRAP and PIMAP reform needs, such as: (i) public
investment management planning, programming, budgeting, execution and monitoring; (ii)
progressive introduction of an updated and more integrated financial management information
system in line with the IT Roadmap adopted by the government in 2013 and supported by
various donors (United States Agency for International Development (USAID); European Union
(EU); and Inter-American Development Bank (IDB); and (iii) PFMRAP and PIMAP reforms
coordination and management. Annex 4 details how these new activities were selected and how
all project activities are re-aligned to support PFMRAP and PIMAP implementation moving
forward.
27. Component 2 – Emergency Rehabilitation of Selected Public Infrastructure: The
proposed restructuring would also involve changes to activities under Component 2. Activities
under Sub-Component 2.1 – Rehabilitation of Aviation Safety Equipment of the first additional
grant would be dropped from the project due to shifting government priorities and use of national
funding for these activities. Additionally, in subcomponent 2.3, the remaining funds would be
used to finance the ongoing rehabilitation of the Road from Cap Haitian to Labadie, as originally
planned. The works for the rehabilitation of the road between Milot and Cap Haitian would be
limited to spot interventions in the urban area of Milot instead of a full rehabilitation, as the
rehabilitation of the main segment of the road would be performed by the GoH with national
budget resources.
28. Component 3 – Institutional Support, Reconstruction Planning and Project Management:
No change.
29. The Operational Manual would be updated to reflect the above changes.
A. Proposed Changes Data Sheet
Summary of Proposed Changes
1 The WIMAX was supposed to be deployed 6 months after the earthquake, as an emergency activity. However, its
completion was delayed for years by various implementation issues and the Central Bank meanwhile found
alternative ways to cope with its destroyed payment network. 2 EDH financial statements preparation and audit activity was transferred to the Bank-financed Rebuilding Energy
Infrastructure and Access Project (P127203), approved in FY13.
16
The proposed second additional grant is necessary to a scale-up PFM support through additional activities
and to cover the financing gap due to the depreciation of the SDR allocation and some cost overruns in the
Parent Project. . The Government of Haiti (GoH) officially requested additional financing from the World
Bank for this purpose and to offset the impact of the sharp drop in the SDR/$ exchange rate which resulted
in a financing gap of US$0.5 million for Component 1. The proposed AF would also finance additional
needs arising from the implementation of the PFMRAP and PIMAP, especially those related to the
implementation of the Information Technology Roadmap activities and an increase in costs of ongoing
activities under Component 1 due to costs overruns for the construction of the airport customs office. The
proposed AF would extend the closing date of the Project by 12 months, from December 31, 2016 to
December 31, 2017 and allow for changes in some PDO Level and Intermediate Level Results Indicators
to monitor the results expected from the modified activities. The financing agreements of the parent
Project and the first AF would be amended to be in line with the AF2.
Change in Implementing Agency Yes [ ] No [ X ]
Change in Project's Development Objectives Yes [ ] No [ X ]
Change in Results Framework Yes [ X ] No [ ]
Change in Safeguard Policies Triggered Yes [ ] No [ X ]
Change of EA category Yes [ ] No [ X ]
Other Changes to Safeguards Yes [ ] No [ X ]
Change in Legal Covenants Yes [ X ] No [ ]
Change in Loan Closing Date(s) Yes [ X ] No [ ]
Cancellations Proposed Yes [ ] No [ X ]
Change in Disbursement Arrangements Yes [ ] No [ X ]
Reallocation between Disbursement Categories Yes [ X ] No [ ]
Change in Disbursement Estimates Yes [ X ] No [ ]
Change to Components and Cost Yes [ X ] No [ ]
Change in Institutional Arrangements Yes [ ] No [ X ]
Change in Financial Management Yes [ ] No [ X ]
Change in Procurement Yes [ X ] No [ ]
Change in Implementation Schedule Yes [ ] No [ X ]
Other Change(s) Yes [ ] No [ X ]
Development Objective/Results PHHHDO
Project’s Development Objectives
Original PDO
The Project Development Objective is to support the Recipient in its early sustainable recovery efforts
from the effects of the Emergency, through selected interventions aiming at contributing to rebuilding key
institutions and infrastructure
Current PDO (revised in first AF) PHCURRPDO
17
The Revised PDO is to support the Recipient in its sustainable recovery efforts from the effects of the
Emergency, through selected interventions aiming to rebuilding key institutions and infrastructure.
Change in Results Framework PHHCRF
Explanation:
The Results Framework would be adjusted to reflect the change and impact of project activities under
Component 1 and Component 2. Three new indicators were added under Component 3 to capture results
of activities financed by the parent Project and first AF which were previously not captured. See Annex 1
for details.
Compliance
Covenants - Additional Financing (Second Additional Financing Infrastructure & Institutions
Emergency Recovery - P156049)
Source of
Funds
Finance
Agreement
Reference
Description of
Covenants Date Due Recurrent Frequency Action
Conditions
Source Of Fund Name Type
IDAT Update of Operations Manual Effectiveness
Description of Condition
The Recipient has prepared and adopted, in form and substance satisfactory to the Association, the
Operations Manual.
Risk PHHHRISKS
Risk Category Rating (H, S, M, L)
1. Political and Governance High
2. Macroeconomic Substantial
3. Sector Strategies and Policies Substantial
4. Technical Design of Project or Program Moderate
5. Institutional Capacity for Implementation and Sustainability Moderate
6. Fiduciary Substantial
7. Environment and Social Moderate
8. Stakeholders Moderate
9. Other
OVERALL Substantial
Finance
Loan Closing Date - Additional Financing (Second Additional Financing Infrastructure &
Institutions Emergency Recovery - P156049)
Source of Funds Proposed Additional Financing Loan Closing Date
18
IDA Grant 31-Dec-2017
Loan Closing Date(s) - Parent ( Infrastructure & Institutions Emergency Recovery -
P120895 )
PHHCLCD
Explanation:
The proposed additional financing would also extend the closing date of the Project and first two grants
(IDA-H5510 and IDA-H8120) by 12 months from December 31, 2016 to December 31, 2017, to coincide
with the closing date of the additional grant. The financing agreements of IDA-H5510 and IDA-H8120
would be amended accordingly. This extension would allow for the completion of the IT Roadmap as well
as PFMRAP and PIMAP activities under Component 1, and the rehabilitation of the road between Cap
Haitian and Labadie under Component 2.
Ln/Cr/TF Status Original Closing
Date
Current Closing
Date
Proposed Closing
Date
Previous Closing
Date(s)
IDA-
H5510 Effective 30-Jun-2013 30-Jun-2016 31-Dec-2017
30-Jun-2016,
31-Dec-2016
IDA-
H8120 Effective 30-Jun-2016 30-Jun-2016 31-Dec-2017
30-Jun-2016,
31-Dec-2016
Change in Disbursement Estimates (including all sources of Financing)PHHCDE
Explanation:
Additional funds will be disbursed in support of the project.
Expected Disbursements (in USD Million)(including all Sources of Financing)
Fiscal Year 2016 2017 2018
Annual 0.80 1.30 0.70
Cumulative 0.80 2.10 2.80
Allocations - Additional Financing (Second Additional Financing Infrastructure & Institutions
Emergency Recovery - P156049)
Source of
Fund Currency
Category of
Expenditure
Allocation Disbursement %(Type
Total)
Proposed Proposed
IDAT XDR
Goods, works, non-
consulting services,
consultants’ services, and
Operating Costs for Part
1 of the Project
2.00 100.00
Total: 2.00
Reallocation between Disbursement Categories PHHRBDC
Explanation:
The disbursement tables of the first two grants (IDA-5510 and IDA-H8120) would be revised to reallocate
funds between different disbursement categories. The accompanying revised Procurement Plan can be
found in Annex 2. The indicative financing plan by component is shown below in Tables 1 and 2.
Ln/Cr/TF Currency Current Category of Allocation Disbursement %(Type
19
Expenditure Total)
Current Proposed Current Proposed
IDA-H5510 XDR GO/CW/Non-CS/CS/OP
Part 1
6,440,000.0
0
5,320,319.0
0 100.00 100.00
IDA-H5510
GO/CW/Non-CS/CS Part
2
22,510,000.
00
23,450,330.
00 100.00 100.00
IDA-H5510 GO/CW/Non-CS/CS/OP
Part 3
3,220,000.0
0
3,587,321.0
0 100.00 100.00
IDA-H5510 PPF REFINANCING 9,650,000.0
0
9,542,030.0
0 0.00 0.00
IDA-H5510 Unallocated 80,000.00 0.00 100.00 100.00
IDA-H5510 Designated Account 0.00 0.00 0.00 0.00
IDA-H5510 Designated Account 0.00 0.00 0.00 0.00
IDA-H5510 UN Advances 0.00 0.00 0.00 0.00
IDA-H5510 UN Advances 0.00 0.00 0.00 0.00
Total: 41,900,000.
00
41,900,000.
00
IDA-H8120 XDR GO CW NCS CS OP Part
1 b,c,d,e,f
7,989,000.0
0
7,989,000.0
0 100.00 100.00
IDA-H8120
GO CW NCS CS Part 2
c,d,e
13,514,000.
00
13,514,000.
00 100.00 100.00
IDA-H8120 GO CW NCS CS OP Part
3 a,b,c,d,g,h
1,797,000.0
0
1,797,000.0
0 100.00 100.00
IDA-H8120 Designated Account 0.00 0.00 0.00 0.00
IDA-H8120 Designated Account 0.00 0.00 0.00 0.00
Total: 23,300,000.
00
23,300,000.
00
Components
Change to Components and Cost PHHCCC
Explanation:
The Government of Haiti (GoH) officially requested additional financing from the World Bank to offset
the heavy impact of the sharp drop in the SDR/$ exchange rate which resulted in a financing gap of
US$0.5 million for Component 1. The proposed additional grant would also finance an increase in costs of
ongoing activities under Component 1 of the project due to costs overruns for the construction of the
airport customs office and additional needs arising from the implementation of the PFMRAP and PIMAP,
especially those related to the implementation of the Information Technology Roadmap activities.
This additional grant would also involve a project restructuring, which would include: (i) an extension of
the closing date of the Project by 12 months, from December 31, 2016 to December 31, 2017, to allow for
20
the completion of additional activities deriving from the recently adopted PFMRAP under Component 1,
and the rehabilitation of the road between Cap Haitian and Labadie (ii) dropping the EDH (Power Utility)
financial statements audit, the WIMAX backup of the Central Bank payment system network and the Civil
Service census, all under Component 1; these freed resources would remain within Component 1 to cover
new activities stemming from the PFMRAP and PIMAP; (iii) dropping of Rehabilitation of Aviation
Safety Equipment and the works for rehabilitation of the road between Milot and Cap Haitien, and
reference to mineral extraction in the Financing Agreement, all under Component 2, due to shifting
government priorities and use of alternative funding for these activities; (iv) a reallocation of funds to
reflect those activities already complete and the discrepancy between planned expenditures versus actual
expenditures; and (v) modifications to the PDO Level and Intermediate Level Results Indicators to
monitor the results expected from the modified activities.
Current Component
Name
Proposed Component
Name
Current Cost
(US$M)
Proposed
Cost (US$M) Action
Project Preparation
Advance
Project Preparation
Advance 15.00 15.00 No Change
1. Restoring Key
Economic and Financial
Functions of the
Recipient
1. Restoring Key
Economic and Financial
Functions of the
Recipient
10.00 24.80 Revised
2. Emergency
Rehabilitation of
Selected Public
Infrastructure
2. Emergency
Rehabilitation of Selected
Public Infrastructure
35.00 55.30 Revised
3. Institutional Support,
Reconstruction Planning
and Project Management
3. Institutional Support,
Reconstruction Planning
and Project Management
5.00 7.70 Revised
Total: 65.00 102.80
Other Change(s) PHImplemeDel
Implementing Agency Name Type Action
Change in Procurement
Explanation:
Procurement arrangements will not change, but two additional procurement methods have been added and
reflected in the Financing Agreements: Selection of UN agencies (UNOPS) and Single-source procedures
for the Selection of Individual Consultants.
Appraisal Summary
Economic and Financial Analysis PHHASEFA
Explanation:
No change.
Technical Analysis PHHASTA
Explanation:
No change.
21
Social Analysis PHHASSA
Explanation:
No change.
Environmental Analysis
Explanation:
No change.
Risk
Explanation:
No change.
B. Revised Financing Plan
30. The proposed restructuring would involve a reallocation of funds to reflect those
activities already complete and the discrepancy between planned expenditures versus actual
expenditures. The accompanying revised Procurement Plan can be found in Annex 3. The
indicative financing plan by component is detailed in Annex 2, Tables 1 and 2.
C. Results Framework
31. The Results Framework would be adjusted to reflect the changes and impact of project
activities under Component 1 and Component 2. Three new indicators were added under
Component 3 to capture results of activities financed by the first grant (IDA-H5510) which were
previously not captured. In addition, Component 1 indicators related to Public Expenditure and
Financial Accountability (PEFA) would be dropped and replaced since the PEFA exercise was
not undertaken in 2013-2014 (as was expected) nor is it planned in the coming years.
Furthermore, the PEFA Report and indicators are currently being reviewed and updated at the
global level. See Annex 1 for details on proposed changes to the Results Framework.
D. Institutional Arrangements
32. The proposed second additional grant would be implemented using the institutional
framework, procurement, financial management and disbursement arrangements in place under
the parent IIERP and first additional grant, all of which are working well and have the capacity
to absorb additional funds. Both financial management and procurement have been carried out
in accordance with the Bank’s Financial Management and Procurement Guidelines, and there
would be no changes to either financial management or procurement arrangements of the Project
beyond the Operation Manual updating. Procurement arrangements will not change, but two
additional procurement methods have been added and reflected in the Financing Agreements:
selection of UN agencies (UNOPS) and single-source procedures for the selection of individual
consultants.
E. Social, Environmental and Fiduciary
22
33. The Project has complied with all social, environmental and fiduciary safeguard
requirements.
34. The OPs triggered under the parent Project include: OP 4.01 Environmental Assessment,
OP 4.04 Natural Habitats, OP 4.09 Pest Management, OP 4.11 Physical Cultural Resources and
OP 4.12 Involuntary Resettlement). No additional Safeguard policies would be triggered under
the second additional grant. The activities that triggered the Environmental Assessment
Category A rating under the parent Project and first additional grant are now completed. The
rating would be maintained, however, as Category A until project closure. No additional
activities proposed in the second AF under Component 1 would require an update to the
Environmental and Social Management Framework (ESMF), Environmental Management Plan,
(EMPs) or Resettlement Action Plans (RAPs) that were prepared and cleared by the Bank for the
debris processing, canal cleaning, bridge, and road works financed under the parent Project.
There are no new activities proposed under Component 2 or 3, and the existing safeguard
documents (specifically the EMPs and the Rapid Social Assessment) will continue to apply to
the remaining activities. A RAP for the Cap-Labadie road was prepared, consulted, and disclosed
on March 9, 2016 on both the Bank’s external website and locally on the Ministry of Public
Works, Transport, Energy and Communications website, and is currently being implemented.
35. The Project´s capacity to manage safeguards has proven satisfactory. The implementing
agency has a dedicated social and environmental cell that has successfully identified, mitigated,
and resolved safeguards issues across the project´s interventions. The Bank has also carried out
several workshops to strengthen the client´s local environmental and social capacity.
36. An audit for IIERP would be conducted annually. Each audit of the Financial Statements
for the Project shall cover the period of one fiscal year of the Recipient. The last audit shall cover
a period, which can be of more or less than 12 months to include the grace-period. The report
for the audit for each such period would be submitted to the Bank no later than four months after
the end of such period.
37. There are no overdue audit reports for the Project.
F. Amendment to Financing Agreement
38. The proposed second additional grant and Restructuring would involve an amendment to
the Financing Agreements of the parent Project grant (H-551-0-HT) and the first additional grant
(H-812-0-HT) to include all activities defined under Parts 1, 2 and 3 of the parent Project.
Presently, these activities are limited to Part 1 (b, c, d, e, f), Part 2 (b, c, d, e, f) and Part 3 (a, b, c,
d, g, h). These amendments would align project activities between the two grants. It would
finance the additional activities as described above and accommodate cost overruns on activities
under the parent Project and the first additional grant.
39. The overall risk of the proposed Project is Substantial (based on the Systematic
Operations Risk-rating Tool – SORT). Two key risks remain relevant to the proposed second
23
AF: (i) the political and governance risk of ongoing instability in leadership due to delayed
elections may cause unexpected changes in the Government’s policy objectives; and (ii)
fiduciary risk, which is heightened by the emergency resulting from the Hurricane. These risks
will continue to be managed through active dialogue and consensus-building with stakeholders
around the Government’s PFM Reform Action Plan, in which strong emphasis is placed on
strengthening PFM systems, and through its implementation. In addition, the Government is
working with Bank support to strengthen project management arrangements for accounting and
control of resources. Risk with regard to Institutional Capacity for Implementation and
Sustainability is considered moderate. The MEF has improved its technical capacity to steer and
manage the project activities and PFM reforms with support from the Bank. Longstanding and
successful implementation of activities under the parent Project and additional grant
demonstrates effective risk mitigation for other risks.
40. Activities financed under the proposed additional grant are expected to benefit the
general population as a result of support to key public financial institutions.
41. All activities that triggered the Environmental Assessment Category “A” rating under the
parent Project have been completed and this proposed AF would not finance any new activities
of that nature. No additional risks are expected as a result of the proposed additional grant and
the proposed additional grant builds upon strong prior experience under IIERP. Nevertheless,
consistent with the parent Project rating, the overall risk rating of the proposed AF is assessed as
“Substantial”. The risk ratings are captured below in the SORT.
Risk Categories Rating (H, S, M or L)
1. Political and governance High
2. Macroeconomic Substantial
3. Sector strategies and policies Substantial
4. Technical design of project or program Moderate
5. Institutional capacity for implementation and sustainability Moderate
6. Fiduciary Substantial
7. Environment and social Moderate
8. Stakeholders Moderate
9. Other
Overall Substantial
42. Communities and individuals who believe that they are adversely affected by a World
Bank (WB) supported project may submit complaints to existing project-level grievance redress
mechanisms or the WB’s Grievance Redress Service (GRS). The GRS ensures that complaints
received are promptly reviewed in order to address project-related concerns. Project affected
communities and individuals may submit their complaint to the WB’s independent Inspection
24
Panel which determines whether harm occurred, or could occur, as a result of WB non-
compliance with its policies and procedures. Complaints may be submitted at any time after
concerns have been brought directly to the World Bank's attention, and Bank Management has
been given an opportunity to respond. For information on how to submit complaints to the World
Bank’s corporate Grievance Redress Service (GRS), please visit
http://www.worldbank.org/GRS. For information on how to submit complaints to the World
Bank Inspection Panel, please visit www.inspectionpanel.org.
25
HAITI: Second Additional Financing to the Infrastructure and Institutions Emergency Recovery Project
Results Framework
Revisions to the Results
Framework
Comments/
Rationale for Change
PDO
Parent Project (PAD) Changes with First Additional
Financing – Current
Proposed Changes
To support the Recipient in its early
sustainable recovery efforts from the effects
of the Emergency, through selected
interventions aiming at contributing to
rebuilding key institutions and
infrastructure.
To support the Recipient in its
sustainable recovery efforts from the
effects of the Emergency, through
selected interventions aiming at
contributing to rebuilding key
institutions and infrastructure.
No change.
PDO indicators
Parent Project (PAD) Changes with First Additional
Financing – Current
Proposed Changes
Estimated number of people benefiting from
repaired infrastructure (including the
proportion of women)
No change. No change.
Project influenced the reconstruction
planning process for Port-au-Prince and
surrounding affected areas so that public
consultation mechanisms are strengthened.
No change. No change.
MEF restored internal control and audit, and
able to process payroll.
No change. No change.
Project beneficiaries.
No change. No change.
Of which female (beneficiaries) No change. No change.
Intermediate Results indicators
Parent Project (PAD) Changes with First Additional
Financing – Current
Proposed Changes
Project Preparation Advance
Number of individuals receiving and using No change. Activity complete. Activity complete.
26
immediate recovery supplies.
Component 1: Restoring key economic and financial functions of the Recipient
Intermediate Result 1: Quality and comprehensive government accounts reports are produced and submitted within the legal timeframe to the Supreme Audit
Institution. They include data on both recurrent and capital expenditures.
Quality and timeliness of annual financial
statements (PI 25)
New. Dropped and replaced by new indicator
below.
This indicator (PI 25) is too broad to
capture the actual impact of the project
activities in this domain. The project
provided support to Treasury through the
purchase of accounting software
(general ledger account) which helped to
produce annual financial statements. The
project planned to support better
accounting and monitoring of public
expenditure through a new accounting
system. In addition, it is not clear that a
new PEFA will be completed any time
soon. PEFA Report and Indicators are
also going under transition toward an
updated version.
Scope, nature and follow-up of external
audit (PI 26)
New. Dropped and replaced by new indicator
below.
Too broad to account for the limited
activity done under the project in this
domain, and a new PEFA will not be
done before the closing of the project.
PEFA Report and Indicators are also
going under transition toward an updated
version.
The MEF established and operationalized
four (04) accounting posts (postes
comptables) to control budget expenditures
in line ministries.
New. This indicator is a proxy to measure
improvement in internal control as it was
intended in the original indicator.
Number of months elapsed between the end
of a fiscal year and actual submission of the
consolidated government general accounts
for external audit to CSC/CA.
New. The indicator is taken from the CSI (7.3)
and adjusted to account for project
activities in support of Treasury for the
preparation and submission of
government financial statements to
CSC/CA within the statutory timeframe.
Number of days elapsed between the
submission of the government general
accounts to CSC/CA and the submission of
. New. This new indicator is also taken from the
Core sector Indicators (8.3) and adjusted
to account for the capacity building
27
the audit report of the government general
accounts to MEF by the CSC/CA.
activities support to CSC/CA to improve
its control performance of public
expenditures.
Legislative scrutiny of the annual budget
law (PI 27)
Dropped. The project does not support any activity
related to Parliament.
Legislative scrutiny of external audit reports
(PI 28)
Dropped. The project does not support any activity
related to Parliament.
Intermediate Result 2: Key government budgetary and financial functions are fully restored
Payment system: The processing of public
servants salaries is fully restored and the
registry of civil servants is updated.
Revised. Payroll PEFA Indicators: PI-18 Revised (and Activity Completed). Payment system: The processing of
public servants salaries is fully restored
and the registry of civil servants is
updated.
Original indicator was met early in the
parent Project. Updated indicator in first
AF to be better aligned with the 2011
PEFA report. However, PI-18 is
complex and includes 4 broad sub-
dimensions (degree of integration and
reconciliation between Payroll and
personal records; timeliness of changes
to personal records; internal controls of
changes to personal records and payroll;
and existence of payroll audits) that the
project does not support. Hence, the
second AF aims to revert to the initial
indicator, which was actually completed
with project support.
Number of Public Financial Management
entities back in operation following the
earthquake.
New (Activity complete). This ad-hoc output indicator is intended
to capture the project’s multiple
activities and realizations to restore key
PFM entities and functions such as (i)
budget preparation (DGB and DEE); (ii)
government expenditure processing and
payment (Treasury); (iii) revenue
collections (DGI and AGD); and (iv)
control of the use of public resources
(CSC/CA, IGF, ULCC, CNMP)
Intermediate Result 3: Public investment projects management improved
Percentage of investment projects included
in the PIP in the six agreed pilot ministries,
which are evaluated ex-ante by the UEPs
according to official guidelines.
New. This new indicator is taken from CSI
(10.1) and adjusted to account for
project activities to improve public
investment management based on the
PIM report.
28
Intermediate result 4: Small customs office is built and operational
Small Customs Building is built and used to
provide services to the public.is operational,
complying with international social and
environmental standards.
Revised: Small Customs Building is
built and used to provide services to the
public.
Slightly revised to clarify the indicator
definition.
Component 2: Emergency Rehabilitation of Selected Public Infrastructure Km of roads rehabilitated or repaired to
agreed standards. (IDA CORE
INDICATOR)
No change. No change.
Number of infrastructure built with due
attention paid to sustainability as well as
social and environmental aspects.
No change. No change.
Estimated number of days of work
generated by infrastructure repair or
reconstruction.
Estimated number of days of work
generated by infrastructure repair or
reconstruction disaggregated by gender.
No change.
Truitier Debris Processing Facility is
operational, complying with international
social and environmental standards and
support implementation of all stakeholders
efforts for debris removal.
No change.
No change. Activity Complete.
Aviation safety equipment is strengthened
to support air traffic accordingly to
international standards. Compliance of
procured goods for aviation safety
infrastructure in line with Standards and
Recommended Practices (SARP) of ICAO.
New.
Dropped. Activity dropped due to change in
government priorities.
All bridge reconstruction or repairs financed
under the project include seismic stops or
equivalent design solutions aiming at
improving the resilience to future disasters.
No change. No change.
Component 3: Institutional Support, Reconstruction Planning and Project Management:
Crisis governance institutions received
institutional strengthening support.
Key services of MTPTC received
institutional strengthening support to be
able to handle reconstruction process, Technical Unit for Building Evaluations
and Dissemination of Best Practices of
Construction (BTB) is created and
operational and leads dissemination of
repair, retrofit, and construction best
No change.
29
practices.
Number of building structural damage
assessments
New. New. Included to account for the results
achieved through the development of the
BTB.
Number of masons and engineers trained in
paraseismic construction
New. New. Included to account for the results
achieved through the development of the
BTB.
Number of technical reference guidelines
regarding paraseismic
construction prepared under the project
New. New. Included to account for the results
achieved through the development of the
BTB.
CIAT has become an institution capable of
influencing the reconstruction planning
process with due attention being paid to
social and environmental issues.
No change. No change.
Reconstruction planning alternatives
consulted with relevant stakeholders.
No change. No change.
Fiduciary agent hired. No change. No change. Activity Complete.
30
REVISED PROJECT RESULTS FRAMEWORK
Project
Name:
Second Additional Financing and Restructuring
Infrastructure & Institutions Emergency Recovery (P156049)
Project
Stage: Additional Financing Status: FINAL
Team
Leader(s): Pierre Xavier Bonneau
Requesting
Unit: LCC8C Created by: Margaret Patricia Henley Barrett on 10-Jun-2015
Product
Line: IBRD/IDA
Responsible
Unit: GTI04 Modified by: Margaret Patricia Henley Barrett on 24-Oct-2016
Country: Haiti Approval FY: 2016
Region: LATIN AMERICA AND
CARIBBEAN
Lending
Instrument: Investment Project Financing
Parent Project
ID: P120895
Parent Project
Name: Infrastructure & Institutions Emergency Recovery (P120895)
Project Development Objectives
Original Project Development Objective - Parent:
The Project Development Objective is to support the Recipient in its early sustainable recovery efforts from the effects of the Emergency, through
selected interventions aiming at contributing to rebuilding key institutions and infrastructure
Current Project Development Objective – First Additional Financing (AF1):
The Revised PDO is to support the Recipient in its sustainable recovery efforts from the effects of the Emergency, through selected interventions
aiming to rebuilding key institutions and infrastructure.
Proposed Project Development Objective – Second Additional Financing (AF2):
No change.
Results
Core sector indicators are considered: Yes Results reporting level: Project Level
Project Development Objective Indicators
Status Indicator Name Core Unit of Measure Baseline Actual(Current) End Target
No Change MEF restored internal control
and audit, and able to process
Yes/No Value No Yes Yes
Date 09-Jan-2016 31-Dec-2016
31
payroll. Comment
No Change Estimated number of people
benefiting from repaired
infrastructure
Number Value 700000.00 800000.00
Date 09-Jan-2016 31-Dec-2016
Comment
No Change Project influenced the
reconstruction planning process
for Port-au-Prince and
surrounding affected areas so
that public consultation
mechanisms are strengthened.
Yes/No Value No Yes Yes
Date 09-Jan-2016 31-Dec-2016
Comment
New Project beneficiaries
Number Value 0.00 2000.00
Date 09-Jan-2016 31-Dec-2016
Comment Has been present
since beginning
of project, but
was not included
in RF in Portal.
New Of which female (beneficiaries)
Percentage Value 50.00
Sub Type
Supplemental
Intermediate Results Indicators
Status Indicator Name Core Unit of Measure Baseline Actual(Current) End Target
Marked for
Deletion
PI-25 Quality and timeliness of
annual financial statements
Text Value D+ Not available C
Date 01-Jun-2015 30-Jun-2016
Comment This indicator (PI
25) is too broad to
capture the actual
impact of the
project activities
in this domain.
32
The project
provided support
to Treasury
through the
purchase of
accounting
software (general
ledger account)
which helped to
produce annual
financial
statements. The
project planned to
support better
accounting and
monitoring of
public
expenditure
through a new
accounting
system. In
addition, it is not
clear that a new
PEFA will be
completed any
time soon.
Marked for
Deletion PI-26 Scope, nature and
follow-up of external audit
Text Value D+ Not available C
Date 01-Jun-2015 30-Jun-2016
Comment Too broad to
account for the
limited activity
done under the
project in this
domain, and a
33
new PEFA will
not be done
before the
closing of the
project. PEFA
Report and
Indicators are
also going under
transition
toward an
updated version.
Marked for
Deletion PI-27 Legislative scrutiny of
the annual budget law
Text Value D+ Not available C
Date 01-Jun-2015 30-Jun-2016
Comment The project does
not support any
activity related
to Parliament.
Marked for
Deletion PI-28 Legislative scrutiny of
external audit reports
Text Value D+ Not available C
Date 01-Jun-2015 30-Jun-2016
Comment The project does
not support any
activity related
to Parliament.
Marked for
Deletion
Aviation safety equipment in
strengthened to support air
traffic accordingly to
international standards.
Yes/No Value No No No
Date 01-Sep-2013 30-Jun-2016
Comment Activity
dropped due to
change in
government
priorities.
34
No Change Number of Individuals
receiving and using immediate
recovery supplies.
Number Value No 50,000 50,000
Date 01-Feb-2016 01-Feb-2016
Comment Activity
complete.
New MEF established and
operationalized four accounting
posts (postes comptables) to
control budget expenditures in
line ministries
Number Value 4.00 4.00
Date 09-Jan-2016 31-Dec-2016
Comment This indicator is a
proxy to measure
improvement in
internal control as
it was intended in
the original
indicator.
New Number of months elapsed
between the end of a fiscal year
and actual submission of the
consolidated government
general accounts for external
audit to CSC/CA
Number Value 9.00 7.00
Date 24-Sep-2015 31-Dec-2016
Comment The indicator is
taken from the
CSI (7.3) and
adjusted to
account for
project activities
in support of
Treasury for the
preparation and
submission of
government
financial
statements to
CSC/CA within
the statutory
timeframe.
New Number of days elapsed
Number Value 0.00 120.00 15.00
35
between the submission of the
government general accounts to
CSC/CA and the submission of
the audit report of the general
accounts to MEF by the
CSC/CA
Date 09-Jan-2016 31-Dec-2016
Comment This new
indicator is also
taken from the
Core sector
Indicators (8.3)
and adjusted to
account for the
capacity building
activities support
to CSC/CA to
improve its
control
performance of
public
expenditures.
Revised Payment system: The
processing of public servants
salaries is fully restored and the
registry of civil servants is
updated.
Yes/No Value No Yes Yes
Date 09-Feb-2011 09-Feb-2011
Comment Activity
complete.
New Number of Public Financial
Management entities back in
operation following the
earthquake
Text Value 9 entities and FM
main functions
(budget
preparation;
revenue
collection; payroll
and salary
payments;
external and
internal controls
9 entities and
FM main
functions
(budget
preparation;
revenue
collection;
payroll and
salary payments;
external and
internal controls
Date 24-Sep-2015 31-Dec-2016
Comment
36
New Percentage of investment
projects included in the PIP in
the six agreed pilot ministries
which are evaluated ex-ante by
the UEPs according to official
guidelines.
Percentage Value 0.00 50.00
Date 09-Jan-2016 31-Dec-2016
Comment
Revised Small Customs Building is
built and used to provide
services to the public.
Text Value 0 No. Building is
under
construction.
Yes, Complete
and operational.
Date 09-Jan-2016 31-Dec-2016
Comment
No Change Roads rehabilitated, Rural
Kilometers Value 0.00 90.00 100.00
Date 31-Dec-2017 31-Dec-2016
Comment
No Change Number of infrastructure built
with due attention paid to
sustainability as well as social
and environmental aspects.
Number Value 107.00 118.00
Date 09-Jan-2016 31-Dec-2016
Comment
No Change Estimated number of days of
work generated by
infrastructure repair or
reconstruction disaggregated
by gender.
Number Value 45000.00 50000.00
Date 09-Jan-2016 31-Dec-2016
Comment
No Change Truitier Debris Processing
Facility is operational,
complying to international
social and environmental
standards and support
implementation of all
stakeholders efforts for debris
removal.
Yes/No Value No Yes Yes
Date 01-Oct-2013 31-Dec-2016
Comment Activity
complete.
No Change All bridge reconstruction or
Yes/No Value No Yes Yes
37
repairs financed under the
project include seismic stops or
equivalent design solutions
aiming at improving the
resilience to future disasters
Date 10-Jun-2015 31-Dec-2016
Comment
Revised Key services of MTPTC
received institutional
strengthening support to be
able to handle reconstruction
process, Technical Unit for
Building Evaluations and
Dissemination of Best Practices
of Construction
Yes/No Value No Yes Yes
Date 09-Jan-2016 31-Dec-2016
Comment
New Number of building structural
damage assessment
Number Value 0.00 430000.00 430000.00
Date 24-Sep-2015 31-Dec-2016
Comment
New Number of masons and
engineers trained to
paraseismic construction
Number Value 0.00 12000.00 14000.00
Date 24-Sep-2015 31-Dec-2016
Comment
New Number of technical reference
guidelines for paraseismic
construction prepared under
the project
Number Value 0.00 4.00 4.00
Date 24-Sep-2015 31-Dec-2016
Comment
No Change CIAT has become an
institution capable of
influencing the reconstruction
planning process with due
attention being paid to social
and environmental issues
Yes/No Value No Yes Yes
Date 10-Jun-2015 31-Dec-2016
Comment Activity
complete.
No Change Reconstruction planning
alternatives have been
Yes/No Value No Yes Yes
Date 02-Feb-2012 31-Dec-2016
38
consulted with relevant
stakeholders
Comment Activity
complete.
No Change Fiduciary agent has been hired
Yes/No Value No Yes Yes
Date 06-Feb-2012 31-Dec-2016
Comment Activity
complete.
39
HAITI: Second Additional Financing to the Infrastructure and Institutions Emergency
Recovery Project
Table 1: Project Components and Detailed IDA Allocation Revisions (in SDR millions)
Components/Activities Project Costs (SDR m.)
Parent Reallocated 1st
AF 2nd
AF Total
(reallocated + 1st AF + 2
nd AF)
Expense Category 1
Component 1: Restoring Key
Economic and Financial Functions
of the Recipient
6.44 5.32 7.99 2.0 15.21
Expense Category 2
Component 2: Emergency
Rehabilitation of Selected Public
Infrastructure
22.51 23.45 13.51 0 36.96
Expense Category 3
Component 3: Institutional
Support, Reconstruction Planning
and Project Management
3.22 3.59 1.80 0 5.39
Expense Category 4
Project Preparation Advance
9.65 9.54 0 0 9.54
Expense Category 5
Unallocated
0.080 0 0 0 0
Total 41.90 41.90 23.30 2.0 67.20 *Expenditure categories have been modified to include the entire parts of the Project as in the amended AF1 FA, for consistency with
the revised Project Description.
Table 2: Allocation of Proceeds (SDR)
Category of
Expenditure
Allocation % of Financing
Parent/Current Parent Revised 1stAdditional
Financing
2nd
Additional
Financing &
Restructuring
Parent Current Revised
(1) Goods, Works, non-
consulting services,
Consultant’s Services,
and Operating costs for
Part 1 of the Project
6,440,000 5,320,31 7,989,000 2,000,000
100% 100% 100%
(2) Goods, Works, non-
consulting services,
consultants’ services for
Part 2 of the Project
22,510,000 23,450,330 13,514,000
0
100% 100% 100%
(3) Goods, Works, Non-
consultant services,
consultants’ services, and
Operating Costs for Part 3
of the Project
3,220,000 3,587,321 1,797,000 0 100% 100% 100%
(5) Refund of Preparation
Advance
9,650,000 9,542,030 0 0
(6) Unallocated 80,000 0 0 0 Amount payable pursuant to
Section 2.07 of the General
Conditions
41,900,000 23,300,000 67,200,000
40
HAITI: Second Additional Financing to the Infrastructure and Institutions Emergency
Recovery Project
Contract (Description) Est.
Cost/Real
Cost
(US$)
Procureme
nt /
Selection
Method
Planned
Contract
signature
date
Planned Completion
Date
Comment
Component 1 – Restoring Key Economic and Financial Functions of the Recipient
Construction of small customs building at the airport. 1,925,000 ICB December
2013
January 2016 Signed,
ongoing
Equipment of small customs at airport 650,000 LC Oct 2015 January 2016
Accountability and efficiency:
supply chain of fiscal reporting and execution and
linking systems (IT Blue-Print and BRH);
assist Treasury (DGT) and links to sector ministries;
support accounting profession (OCPAH);
operationalize public investment systems
implementation units in ministries (MPCE-UEPs);
improve internal and external audit and control
(CSCCA/IGF); and
8,200,000 QCBS,
Individual
Consultants
Oct 2012-
end of
project
October 2017
Transparency and participation:
enhance public access to government information &
data (eGov);
improve data collection, statistics and records
management;
support anticorruption activities of the Anticorruption
Agency (Unite de Lutte Contre la Corruption –
ULCC) and improve its links to procurement (CNMP)
2,100,000 QCBS,
Individual
Consultants
Oct 2012-
end of
project
October 2017
Project Management/ studies or training to strengthen
Haiti’s governance and institutional capacity
1,100,000 QCBS,
Individual
Consultants
Oct 2012-
end of
project
October 2017
Component 2 – Emergency Rehabilitation of Selected Public Infrastructure
Road
Rehabilitation:
Labadie - Cap
Haitien
Design 100,000 Direct
Contracting
Complete
Supervision 500,000 QCBS Contract signed July 2015
to end of project
Works 7,200,000 ICB Contract signed,
December 2015 to end of
project
RAP and social technical assistance
and compensation
150,000 QBS Complete
Sub project for local community 150,000 Direct
contracting
February 2016 to
December 2016
Component 3 – Institutional Support, Reconstruction Planning and Project Management
Technical Assistance to MTPTC (multiple contracts) 500,000 QCBS,
3CV
February 2016 to end of
project
Goods & Equipment – Datacenter (multiple contracts) 200,000 LC, direct
contracting
July 2016
Small Office Building for MTPTC/BTB services 300,000 LC3 July 2016
41
HAITI: Second Additional Financing to the Infrastructure and Institutions Emergency
Recovery Project
1. The project restructuring and second additional grant is an opportunity for the Bank to
realign the IIERP activities with the PFMRAP adopted by the GoH in May 2014. This Annex
provides an overview and update on the country’s overall PFM reforms implementation, how the
Bank contributed to PFM achievements to date through the IIERP, and how IIERP activities
would be realigned to help the country meet its PFMRAP objectives.
A. Overall PFM Reforms Context and Implementation
2. The Bank Systematic Country Diagnostic4 for Haiti revealed that Haiti’s dismal
developmental results can easily be attributed to many factors, including primarily the limited
capacity of the GoH to steer economic and social development, combined with persistent
political instability and frequent natural disasters. These challenges translate into: (i) poor
governance; (ii) absence of accountability; and, (iii) weak institutional capacity compounded by
outsourcing of key public service delivery in social sectors (Education, Health, Water,
Sanitation, etc.) to donors and NGOs, especially after the earthquake.
3. However, with massive aid inflows (especially the Venezuelan supported Petro-caribe
program) in sharp decrease six years after the earthquake, the government is working to increase
efficiency and effectiveness in the use of available resources, to better deliver on public services.
There is now broad consensus within the GoH of the need to overhaul PFM institutions, systems
and processes to support these efforts.
4. Following years of protracted and ad-hoc PFM reform activities, the government decided
to adopted a comprehensive PFMRAP in May 2014, with Bank support, to address PFM sector
issues more strategically and more systematically, streamline reform measures and move toward
long term goals.
5. The PFMRAP covers six areas, namely: (i) Revenue Mobilization; (ii) Budget
Management and internal controls; (iii) Treasury management and Accounting; (iv) External
Controls and Audit; (v) Financial Information Management System; and (vi) Local Government
Finance.
6. From its own assessment of the PFMRAP execution recently undertaken (December
2015), the GoH noted mixed overall results:
• Two areas (Treasury and Accounting and FMIS) have shown some promising
progress with the establishment of the Treasury Single Account and the initial steps
taken to upgrade and integrate budget and treasury information systems;
4 Haiti Systematic Country Diagnostic: Opportunities For All, May 2015, The World Bank
42
• Others, such as Revenue Mobilization and Budget Management and internal controls,
have been somewhat active with the adoption of multiyear reforms plans in Tax and
Customs Administration and, in Public Investment Management (PIM); and,
• Whereas the reforms activities in the last two areas (External controls and local
government finance) did not progress as expected, despite some ad-hoc outstanding
initiatives in external audit.5
7. Additionally, through newly established coordination and monitoring mechanisms, the
GoH was, for the first time, able to better lead the PFM reforms processes and activities.
Meanwhile, all major donors including the Bank; European Union (EU); United States Agency
for International Development (USAID); Inter-American Development Bank (IDB);
International Monetary Fund (IMF); and Canada are also working more closely together to align
with the PFMRAP objectives and activities, in order to avoid duplication and boost synergies.
B. Bank support in the PFM sector
8. The Bank has been involved in strengthening economic governance and PFM in Haiti
since before the earthquake, given the importance of public sector management to developmental
issues.
9. Following the earthquake, the Bank increased its support to PFM activities through two
combined approaches involving Development Policy Operations (DPO) and Technical
Assistance operations.
10. Various DPOs were initiated to provide emergency support and governance and
institutional capacity building in public sector in general, and PFM sector in particular. DPOs
yielded fewer results than anticipated since most of the prior PFM measures did not last.
Building on lessons learned, a new multiyear operation is currently in preparation for the next
three year period and is expected to yield more impact and results in the PFM sector.
11. Technical Assistance operations were undertaken immediately after the earthquake in
2010. IIERP helped to restore critical PFM functions including budgeting, accounting, payroll
and external controls through provision of buildings, equipment, training, and consultants
services to MEF units and some key institutions such as the CS-CCA; the Procurement
Regulatory Agency (Commission Nationale des Marches Publics – CNMP) and the ULCC.
12. After the initial phase (Parent Project), the first additional grant included a second TA
operation, to consolidate the initial phase results and assist the GoH to address more structured
and longer term issues linked to PFM. PFMRAP, prepared and adopted with support from the
Bank in May 2014, is based on these findings.
5 CSCCACSC/CA undertook its first ever review of annual budget spending for FY13-14, and Petro-Caribe program
and the reports received wide press coverage
43
13. The proposed second additional grant and restructuring would focus on activities
expected to increase the GoH’s PFM operational effectiveness while paving the way for more
accountability of public officials and their use of public resources.
14. To this end, the second additional grant will be strictly aligned to support PFMRAP
implementation (See Annex 4 for further detail on the realignment of project activities to support
the PFMRAP), especially in promising areas which are critical to building the basic blocks of a
robust PFM system, namely: (i) investment budget management reforms with the establishment
of Coordination and Planning Unit (Unité d’étude et de Programmation – UEP) in line
ministries; and strategic planning as well as budgeting and programming at the MPCE and MEF
levels; (ii) TSA set-up; (iii) upgrading and integration of Financial Management Information
Systems; (iv) strengthening of internal and external controls; and (v) procurement etc.
Conversely, some important activities included under the Parent Project have been dropped,
namely the WIMAX network at the Central Bank, due to delays and lack of relevancy; and, EDH
financial statement preparation and audit, due to its transfer to the Bank-financed Rebuilding
Energy Infrastructure and Access Project (P127203), approved in FY2013.
44
HAITI: Second Additional Financing to the Infrastructure and Institutions Emergency Recovery Project
PFMRAP PRIORITY AREAS IIERP (PARENT & 1st AF) ONGOING
ACTIVITIES
IIERP (2nd
AF) REVISED ACTIVITIES
1. Mobilization of internal and external resources
1.1 Tax Revenue Generation
1.2 Customs Revenue Generation Construction of Customs Airport Facility Maintained and ongoing
1.3 Mobilization of External Resources
1.4 Mobilization of Other Resources
2. Overall Budget Management
2.1 Macroeconomic Framework of the
Budget Law Support to macroeconomic capacity building activities
(Economic Studies Department-DEE)
Maintained and ongoing
EDH Financial Statements preparation and audit Dropped. Transferred to Rebuilding Energy Infrastructure and Access
Project (P127203).
2.2 Strategic Planning Support to Ministry of Plan (MPCE) planning capacity
building activities (not defined)
Revised to support activities derived from the 2014 PIM Report approved
recommendations (Support to six Line Ministries Planning Units Capacity
Building Action Plan)
2.3 Financial Programming and
Budgeting Support to Ministry of Plan (MPCE) programming and
Budgeting activities (not defined)
Revised to support activities derived from the 2014 PIM Report approved
recommendations (Support to MPCE and six Line Ministries Planning
Units Capacity Building Action Plan)
2.4 Budget execution procedures and
internal control
Support to Internal Audit Unit (Inspection Generale
des Finances-IGF)
Maintained and ongoing
Support to Ministry of Economy and Finance (MEF) and MPCE through
PIM Report approved recommendations: “Streamlining and simplifying
budget spending execution procedures”
2.5 Procurement Support to the National Tender Board (CNMP) broadly
defined
Maintained and ongoing
2.6 Program Budget and Results Based
Management
3. Treasury and Accounting
3.1 Treasury Single Account
Support to the TSA establishment (not defined) Revised to support setting-up of 8 Accounting Units in line ministries and
training of accountants
3.2 Cash Management
Restoration of the Central Bank (BRH) payment
network through a WIMAX network
Dropped because of lack of progress and establishment of alternative
payment system networks by BRH
3.3 Management of Public Debt
3.4 Deployment of the Accounting Units Revised to support setting-up of 8 Accounting Units in line ministries and
45
PFMRAP PRIORITY AREAS IIERP (PARENT & 1st AF) ONGOING
ACTIVITIES
IIERP (2nd
AF) REVISED ACTIVITIES
in Line Ministries training of accountants
3.5 Accounting - Finance Support to MEF and MPCE through PIM Report approved
recommendations: “Extending the use of SYSDEP as an accounting
system for capital project expenditure included in the PIP”
Support to private accounting through professional
association (Organisation des Comptables
Professionnels et Auditeurs de Haiti-OCPAH)
strengthening
Maintained and ongoing
4. Local Governance Finances
4.1 Budget of local authorities
4.2 Mobilizing local resources
4.3 Accounting for local authorities
4.4 Monitoring of local authorities
5. External control
5.1 External Monitoring by the CSC-CA Support to the Supreme Audit Institution (Cour
Supérieure des Comptes et du Contrôle Administratif-
CS-CCA) broadly defined
Maintained and ongoing
Support to Anti-corruption Agency (ULCC) Maintained and ongoing (very small amount remaining)
6. Financial Management Information System
6.1 Steering and Control
Support to IT Roadmap Supervision, Implementation, Monitoring and
Updating
6.2 Technical dimension
Support to IT Roadmap Implementation: procurement and provision of
the overall integrated accounting and budget management information
system
6.3 Support and common reference Support to IT Roadmap Implementation: procurement and provision of
cross-cutting applications (data warehouse management software; security
software; etc.)
Support to IT Roadmap Implementation: strengthening of the IT Unit
capacity (work space, equipment, and staffing)
6.4 Communication
7. PFMRAP Preparation and Implementation
7.1 PFM Reforms Management Support to the PFMRAP preparation and adoption Support to the PFMRAP Steering Committee capacity building program
and activities (work space, equipment, and staffing)
7.2 Fiduciary Management Support to UCP- MEF (fiduciary) Maintained and ongoing