New Offshore Wind Tenders in Denmark
New Offshore Wind Tenders in Denmark
1,450 MW before 2020
New Offshore Wind Tenders in Denmark
Presentation today
Danish ambitions on future offshore wind power
Lisbeth Nielsen Danish Energy Agency
Two new offshore tenders: 400 MW at Horns Rev and 600 MW at Kriegers Flak
Peter SehestedtDanish Energy Agency
Tender of 450 MW nearshore projects
Tone MadsenDanish Energy Agency
Pre-investigations and grid connection
Betina Haugaard Heron Energinet.dk
New Offshore Wind Tenders in Denmark
Denmarks’ ambitious green energy policy
Ambitious green energy policy: long-term goal for 2050 – independence of fossil fuels
Stable regulatory framework to 2020
Offshore wind broad political support – 95 % of the Danish Parliament
Effects in 2020 50 percent of our electricity consumption from wind power
New Offshore Wind Tenders in Denmark
New Offshore Wind projects in Denmark
Horns Rev 3: 400 MWKriegers Flak: 600 MW
Tender for 450 MW near shore wind farms
50 MW turbines for research and development
New Offshore Wind Tenders in Denmark
Preparing for the future
New Offshore Wind Tenders in Denmark
The Danish offshore approach
Planning and pre-investigations
Predictable income
DEA is one stop shop
Grid connection – large scale and near shore
A track record of political stability
No requirement for local content
Transparent and flexible tender process
New Offshore Wind Tenders in Denmark
Integration of wind power
Strong interconnectors
A well functioning international market for electricity
Flexible electricity consumption
New Offshore Wind Tenders in Denmark
Horns Rev 3 and Kriegers Flak
The sites chosen for tender ranked the highest in the economic ranking
The most attractive sites
Horns Rev 3
Kriegers Flak
New Offshore Wind Tenders in Denmark
Horns Rev 3 400 MW in the North Sea
Denmark's 14th offshore wind farm
Local competences and network of suppliers
North Sea has good wind conditions
Sea depths of less than 20 metres
New Offshore Wind Tenders in Denmark
Kriegers Flak 600 MW in the Baltic Sea
Denmark's largest offshore wind farm
Located in the Baltic Sea close to borders of Sweden and Germany
Will also be linked to the German farm - power can be led to both countries
Good wind conditions
Kriegers Flak
New Offshore Wind Tenders in Denmark
We are transparent
Tendering for Horns Rev 3 and Kriegers Flak:
Dialogue and negotiation
New Offshore Wind Tenders in Denmark
Common timeline both projects
2013February to April 2013
Pre-technical dialogue
From May 2013 Technical dialogue
New Offshore Wind Tenders in Denmark
From M
ay:
Tech
nical d
ialogue
Febru
ary to April:
Pre-tech
nical d
ialogue
September 2013 Contract notice
Horns Rev 3 timeline
2013 2014 … 20202015
29 November 2013 Deadline for prequalification
2 September 2014Deadline for preliminary tenders
1 December 2014Deadline for binding tenders
Early 2015Concession contract and construction permit
From 1 January 2017 Guaranteed connection to the grid
Early 2020Full operation of offshore farm
New Offshore Wind Tenders in Denmark
29 Nove
mber 2013
Deadlin
e for p
re-qualifica
tion
September 2
013
Contract
notice
2 September 2
014
Deadlin
e for p
reliminary
tenders
1 December 2
014
Deadlin
e for b
inding tenders
Early
2015
Concessi
on contra
ct and
constr
uction perm
it
From 1 Ja
nuary 2017
Guaranteed connecti
on to th
e grid
Early
2020
Full o
peration of o
ffshore fa
rm
From M
ay:
Tech
nical d
ialogue
Febru
ary to April:
Pre-tech
nical d
ialogue Horns Rev 3 timeline
2013 2014 … 20202015
New Offshore Wind Tenders in Denmark
From M
ay:
Tech
nical d
ialogue
Febru
ary to April:
Pre-tech
nical d
ialogue
February 2014 Contract notice
29 April 2015Deadline for preliminary tenders
31 August 2015 Deadline for binding tenders
From 1 July 2018 Guaranteed connection to the grid
Early 2020Full operation of offshore farm
Kriegers Flak timeline
2013 2014 … 20202015
29 April 2014 Prequalification
September/October 2015 Concession contract and construction permit
New Offshore Wind Tenders in Denmark
29 April 2014
Prequalifica
tion
Febru
ary 2014
Contract
notice
29 April 2015
Deadlin
e for p
reliminary
tenders
31 Augu
st 2015
Deadlin
e for b
inding tenders
September/O
ctober 2
015
Concessi
on contra
ct and
constr
uction perm
it
From 1 Ju
ly 2018
Guaranteed connecti
on to th
e grid
Early
2020
Full o
peration of o
ffshore fa
rm
From M
ay:
Tech
nical d
ialogue
Febru
ary to April:
Pre-tech
nical d
ialogue Kriegers Flak timeline
2013 2014 … 20202015
New Offshore Wind Tenders in Denmark
Nearshore wind projects
Smålandsfarvandet
North Sea (north)
North Sea (south)
Sæby
Sejerøbugten
Bornholm
Total of 450 MW
Each farm max. 200 MW
New Offshore Wind Tenders in Denmark
Nearshore wind projects
The tendering model will be published this year
Dialogue and negotiation
Call for tenders September 2015
Pre-investigations: Geological, EIA and MetOcean
Grid connection
Local joint ownership
New Offshore Wind Tenders in Denmark
The Danish TSO - Energinet.dk
Independent public enterprise – owns and operates highways of energy (electricity and gas)
Energinet.dk is to ensure security of supply
Our finances must break even – non-profit
We develop a more flexible power system
New Offshore Wind Tenders in Denmark
Roles of Energinet.dk in OWF
Finance, construct and operate platform and sea cable
Bringing power from new OWF ashore and strengthen grid
Secure that grid connection is available in due time
During the last year requested by DEA to conduct pre-investigations and EIA for future offshore wind farms
New Offshore Wind Tenders in Denmark
Investigations conducted until now- Horns Rev 3 and Kriegers Flak
UXO-deskstudy (Unexploded Ordnance on/below seabed)
Geophysical investigations in wind farm areas
Geotechnical tender
EIA-surveys initiated
New Offshore Wind Tenders in Denmark
App. 190 km2 pre-investigation area
Horns Rev 3
New Offshore Wind Tenders in Denmark
Horns Rev 3 project facts
Distance to shore 10 – 30 km
Distance to harbour 25 – 55 km
Mean wind speed 9.8 m/s
Water depth 10 – 20 m
Seabottom Sand
Tide Yes, 1 – 2 meter
New Offshore Wind Tenders in Denmark
App. 250 km2 pre-investigation area
Kriegers Flak
Kriegers Flak
110 km2
69 km2
New Offshore Wind Tenders in Denmark
Kriegers Flak project facts
Distance to shore 15 km from Møn
Distance to harbour 20 – 40 km
Mean wind speed 9.5 m/s
Water depth 15 – 30 m
Seabottom Sand and residual sediments (from moraine/till deposits) – risk of boulders
Tide No
New Offshore Wind Tenders in Denmark
Grid Connections
Energinet.dk establish the offshore platform, the sub-sea cable and the onshore grid connections
The developer is responsible for inter-array cabling in the OWF and connecting to the platforms
OWF will be connected to the platforms at 33 or 66kV
Expenses of Energinet.dk is paid by Danish consumers; not the developer/owner of the OWF’s
Construction of the platforms will be initiated in 2014 and finalized in 2016/2018
New Offshore Wind Tenders in Denmark
Upcoming events
Follow updated information at
www.ens.dk/offshorewind
Kick-off meeting for the tendering process
May 2013
Technical information meeting in Copenhagen
27th of February 2013
New Offshore Wind Tenders in Denmark
You can find us at the Danish pavilion
1,450 MW before 2020