Upload
hoangnhu
View
218
Download
0
Embed Size (px)
Citation preview
Nyngan Cobar Water Supply Scheme
Cobar Water Treatment
Macquarie River
Bogan River
Nyngan Weir & PS
Cobar Water
Board Storage
Town reticulation
Existing Water Treatment Plant (WTP)
• 4 ML/d
• Built in early 1960s
• Horizontal flow clarifier + sand filtration
Issues
• Limited capacity
• Process deficiencies
• Signs of structural deterioration
• Some WHS issues
• Manual operation
• Investigation revealed refurbishment not economical
A new Water Treatment Plant
• Council decided to build a new WTP
• $8M grant received from government
• Sought help from Public Works Advisory (PWA)
• PWA commenced investigation
• Number of challenges encountered
New WTP – Required Level of Service
• Increased capacity - 8 ML/d
• Minimum: Australian Drinking Water Guidelines
• Capable of treating mixed water from different sources
• Capable of handling up to 450 NTU
Key Challenge 1: Raw Water Source and Treatability
Macquarie River Bogan River
Algae
Cobar bulk
storage
High turbidity
Key Challenges cont’d
• Anaerobic conditions in the rising main causing taste & odour
• Iron; manganese
• Lack of representative raw water samples for lab trials
Solution
Blending Unit
with Instruments
SCADA
Telemetry
RW Balance
Tank
(existing)
Settling
• Selective Withdrawal
• Variable Speed Drives (VSDs)
Floatation (DAF)
+ Filters Clear Water
Reservoir
(existing) VSDs for
Nyngan pumps
MF/Tu
MF/Tu
Tu
Agreed Design
Raw Water
Reservoir
PAC
Contact
Tank
Flocculation
Chambers
Lamella
Clarifier DAFF
Re-
Flocculation
Zone
UV
unit Clear Water
Storage Tank Treated
Water Pumps
Million
Gallon Tank
(MGT) Retic
PAC KMnO4
Sludge Lagoons
(x2)
Supernatant
Return PS
Cobar Water
Storage
Blending
Unit From
Nyngan
Raw Water
Transfer Pumps
New work
Existing facilities
Cl2
Fluoride/
Soda ash Coag/
Poly
Main selection criteria of new site
• Close to existing raw water / clearwater reservoirs
• Hydraulics
• Environmental issues
• Land ownership
• Construction difficulties
• Road access
• Above 100 year flood line
Key Challenge 2 cont’d
Selected Site
Location 3A
• 9 sites were investigated
• Land exchange with mine
• About 700m from the
existing raw water /
clearwater reservoirs
• All expected criteria met
except shallow rock
Clearwater
Reservoir
(MGT )
Existing WTP
Key Challenge 3: Skills of Operational Staff
• High turnover of permanent operational staff
• New WTP process will be different to existing process
Solution
• New staff including Water and Wastewater Engineer
• Operator training in the contract – 3 programs in 12 months
• Fluoride course/DPI Water Operator TC
Key Challenge 4: Funding
• PWA’s revised concept
• Concept agreed with Council/stakeholders
• New estimate $15.5M
• Only $8M in hand
Funding Solution
• Decided to seek additional funding
• PWA assisted with the funding application
• Council/PWA/DPI Water discussions with Funding Authorities/INSW
• Secured additional $7.5M (total $15.5M)
Tender
• A Design and Construct open tender
• Mandatory Pre-tender site meeting
• 15 companies attended with six WTP contractors
• Three tenders received
Conclusion
• Holistic approach
• Addressed all major concerns
• Robust process
• Tender was awarded in June 2017
• Total project cost within the estimate
• Due for completion in June 2018
Acknowledgements
• Staff of Cobar Shire Council, special thanks to Stephen Taylor, Director of Engineering Services
• Infrastructure NSW
• Staff of DPI Water, special thanks to Bill Ho, Manager Water & Sewerage
• My colleagues - the great bunch of supporters:
Glenn Fernandes - Senior Process Engineer
Mounir Tayyar – Senior Process Engineer
Graham Attenborough – Director, Infrastructure Services
Hendrik van Rhijn – Director Engineering, Water & Wastewater
Janet Moule - Project Officer
Glen Edgtton – Manager Business Process
Kim Nguyen – Process Engineer
David Watson & staff of PWA Dubbo Office
Thank you
Jay Ariyawanse Senior Process Engineer
Public Works Advisory | Department of Finance, Services and Innovation p 02 9372 7893 e [email protected] | www.publicworksadvisory.nsw.gov.au Level 13, McKell Building, 2-24 Rawson Place Sydney NSW 2000