15
WE DO BIG THINGS NEW 840 MWe CCGT UNIT AT THE POČERADY POWER PLANT

NEW 840 MWe CCGT UNIT AT THE POČERADY POWER PLANT · 15/2/2012 Start of the Gas Turbines and Steam Turbine assembly ... LP steam quantity 27 kg/s ... NEW 840 MWe CCGT UNIT AT THE

Embed Size (px)

Citation preview

WE DO BIG THINGS

NEW 840 MWe CCGT UNITAT THE POČERADYPOWER PLANT

A WORD OF INTRODUCTION

WE DO BIG THINGS

The fact that ŠKODA PRAHA Invest is constructing the fi rst CCGT power plant in the Czech Republic in Počerady for the ČEZ Group attests to the important role of our Company as an advanced EPC contractor for power generation units and to our readiness to face these challenging projects.

The construction of this CCGT power plant is, without any doubt, an outstanding project both for us and for all participating contractors under our leadership. This new area of power engineering has a great future when con-sidering the growth in energy production from renewable sources and the increasing need to diversify production sources.

Ing. Daniel JiřičkaGeneral Director

ŠKODA PRAHA Invest

ABOUT THE LOCATION, ABOUT THE PROJECTABOUT THE LOCATION

The Počerady power plant, where the new combined cycle unit will be located, is situated near the Počerady municipality in the Ústí nad Labem Region, roughly in the centre of a triangle formed by the towns of Louny, Žatec, and Most. There are fi ve coal units with a unit output of 200 MWe currently operating on the power plant premises. It is notable that this power plant was built by ŠKODA PRAHA from 1970 to 1977.

ABOUT THE PROJECT

The project is a part of renewal of the ČEZ Group production capacity in the Czech Republic, directed by ŠKODA PRAHA Invest as its EPC Contractor.

This project is based on the construction of a new ČEZ Group power production unit, the fi rst of its kind in the Czech Republic: a CCGT power plant (PPC) with an output of 840 MWe. The EPCContractor of the entire project and construction is ŠKODA PRAHA Invest; the Investor is ČEZ.

What makes the CCGT exceptional is its high operating availability, output, and environmental friendliness.

The new unit is to achieve an output of 840 MWe (depending on atmospheric conditions). This is a modern, well-tested and worldwide utilised power generation concept that is highly effi cient in comparison with coal units thanks to basic confi guration of its main components: internal combustion turbines, with steam genera-tors that supply steam to the steam turbine using the waste heat contained in the exhaust gases of the turbines. The Investor expects a maximum economic return on the investment from this new unit. This will be expressed in both a high effi ciency of the unit under steady-state operation and in its opera-ting characteristics, particularly a suffi cient starting speed, the ability to rapidly change output, and the ability to operate in by-pass mode through steam turbine bypass stations.

This is the fi rst CCGT unit designed and supplied by ŠKODA PRAHA Invest as a whole. Working on this project, we were still able to fully utilise our experience gained during previous technically successful projects in Egypt (New Talkha and El Kureimat, 750 MW, both completed in 2010), in which our Company served as the main contractor of critical pipework, the control system, the feeding and condensate extraction pumps and other auxiliary equipment and also EPC supply of a peak-load gas unit with an output of 45 MW in Kladno.

THE PROJECT IN DATES

15/9/2008 Conclusion of the EPC Delivery Contract between

ŠKODA PRAHA Invest and ČEZ

30/11/2008 Decision made on the technological solution

25/6/2009 Contracts for the main technological units concluded

22/9/2009 EIA approval

2/9/2010 Decision on construction site made — legally effective date

15/10/2010 Submission of the Work “Raw Water Supply Line“

25/11/2010 Submission of the Work “Service Building“

15/1/2011 Legally effective date of the Integrated permission for the Počerady

power plant equipment

1/4/2011 Start of construction

15/5/2011 Submission of the Work “Construction Site Installations“

30/6/2011 Cable Duct, completion of the part behind the Main Generating Unit

21/8/2011 Start of the Exhaust-heat Boilers assembly

24/10/2011 Start of the foundation of the Gas Turbine 1 and 2

23/12/2011 Start of the foundation of the Steam Turbine and noise control measures

15/2/2012 Start of the Gas Turbines and Steam Turbine assembly

29/2/2012 Delivery of the Control System to the building site

2/4/2012 Start of the assembly of connecting piping in the Main Generating Unit

23/8/2012 Completion of the Gas Turbines assembly

21/9-16/10/2012 Implementation of cleaning operations

8/11/2012 The fi rst ignition of the Gas Turbine 1

26/1/2013 The fi rst start-up of the Steam Turbine

19/3/2013 Readiness of all systems for comprehensive testing

30/6/2013 Handover of the Work to the Customer (PAC)

BASIC TECHNICALPARAMETERS

The key condition for determining the parameters of the basic CCGT unit was the selection of the main PPC technology suppliers, particularly of the gas turbine. SIEMENS was selected as the gas turbine supplier, the steam generators package was awarded to SES Tlmače and the steam turbine package to ŠKODA POWER. The suppliers listed were chosen based on a competitive tender launched in the second half of 2008 and completed by conclusion of the contracts in the middle of 2009.

FOLLOWING THE SUBSEQUENT OPTIMISATION, THE PPC PARAMETERS AS PART OF THE ELABORATION OF PROJECT DOCUMENTATION WERE SET AS FOLLOWS:

THE DESIGNING STAGE

The decision on construction of a new CCGT unit using a part of the existing premises of the Počerady power plant was taken in 2008. Construction works began on April 1, 2011, and the power plant is planned to be handed over to the Customer on June 30, 2013.

In 2007, the Investor identifi ed several possible locations for the construction of the CCGT unit. The Investor issued the Project Plan prepared on the basis of a number of support materials and feasibility studies in May 2008. This became the primary document for the preparation of the Design and Investment Preparation sta-ges. Among others, the Investor chose a multi-shaft design with two gas turbines (GT) and one steam turbine (ST) as the basic arrangement of the CCGT unit. He also decided on the implementation of one natural-draught cooling tower instead of forced-draught cooling towers, and he selected the overall layout option on the premises of the present Počerady power plant.

ŠKODA PRAHA Invest fulfi lled the role of Architect / Engineer for the Project from the beginning of its deve-lopment, respectively the role of EPC Contractor responsible for the Preliminary Design stage.

ATMOSPHERIC CONDITIONS

Ambient temperature 10 °C Relative humidity 70 %Air pressure 987 mbar

NATURAL GAS

LHV (15°C) 49.49 MJ/kgTemperature upstream GT 130 °C Quantity 2× 14.6 kg/s

EXHAUST GASES AT THE GT OUTLET

Temperature 576.4 °CQuantity 2× 686.5 kg/s

STEAM UPSTREAM THE STEAM TURBINE

HP steam quantity 141.9 kg/sHP steam temperature 550 °C HP steam pressure 128.4 barIP steam quantity 172.4 kg/sIP steam temperature 548 °C IP steam pressure 28.1 barLP steam quantity 27 kg/sLP steam temperature 290 °C LP steam pressure 4 bar

GUARANTEED PARAMETERS

Gross effi ciency 58.4 %Gross output at generators‘ terminals 838 MWeCHP consumption 13 MWeNOX, CO emissions 40 mg/Nm3

Note: HP = high-pressure, IP = intermediate pressure, LP = low-pressure

TECHNOLOGICAL CONCEPT

FUELThe fuel is combusted in two gas turbines connected to generators producing electrical energy. Waste heat contained in the exhaust gases released from the gas turbines is utilised as a heat source for two waste heat boilers producing steam for one steam turbine (CHP). Its generator produces another part of the CCGT power output. In this confi guration each generator generates about 1/3 of the total unit power output. Steam parameters are comparable with the parameters of subcritical coal power plants. A steam turbine working with steam of such parameters is a standard design.

BOILERThe waste heat boiler is designed as a three-pressure design with reheating, a standard design for a unit of this size ensuring maximum effi ciency at reasonable investment costs. For the maximum utilisation of the exhaust gas heat the fi nal boiler heating surfaces are a low-pressure economisers and a condensate preheating exchanger upstream the inlet of the feeding tank.

CONDENSERThe steam turbine condenser is cooled in a tower circuit with one natural-draught cooling tower. Water circu-lation is provided by two 50% cooling water pumps.

The boilers are not equipped with a by-pass stack and the separate operation of gas turbines is not possible. To prevent a sudden shutdown of the gas turbines (and the consequent considerable decrease of their ope-ration life) caused by a shutdown of the steam turbine, the by-pass stations are dimensioned to 100% of the steam output of the boilers and steam fl ows directly through them to the condenser.

WIRING DIAGRAM

MACHINERY PART

GAS TURBINESGas turbines SIEMENS, type SGT5 - 4000F, are fi eld-tested units designed for the provision of safe, highly reliable, effi cient, and low-cost electricity. The construction characteristics of the main components were carefully assessed, resulting in an optimal harmonisation of investment costs with equipment performance as well as with its effective operation and maintenance. Exhaust gases produced by the equipment are minimised by using a Siemens dry Hybrid Burner Ring with low NOx emission.

STEAM TURBINEThe ŠKODA Steam Turbine with an output of 270 MW has a two-casing design (HP + IP, and LP part) with a condenser below the LP part. It is installed together with the generator on a monolithic concrete foundation.

COOLING SYSTEMCooling of the steam turbine condenser is provided by cooling pumps in a 2× 50% confi guration. The pumps actually exceed this value and have regulation capabilities suffi cient to ensure the operation of both gas turbines with a reduced output in the event of an outage of one of them. The pumps' output is controlled by the rotation of their impeller blades. The pumps are oriented vertically for suction from a wet sump. The2× DN1800 supply piping joined into a 1x DN2400 pipe leading to the condenser and subsequently to the cooling tower is made of fi bre reinforced plastic and led through a compacted backfi ll. In exposed areas under roads, the piping is protected from above by a reinforced-concrete slab. Cooling water piping in the Machine Hall near the compensators and non-return valves is made of steel protected by an internal coating. The tower water branch in front of the condenser entry leads cooling water to cool the internal cooling circuit. This circuit is fi lled with demineralised water with a corrosion inhibitor.

EXHAUST-GAS STEAM BOILERSExhaust-gas boilers using waste heat from the gas turbines have a three-pressure design with reheating without additional heating. These are cylindrical horizontal boilers with natural circulation with the exhaust gas fl owing in a horizontal plane while the coils of the individual heating surfaces are oriented vertically.

COMPRESSOR SECTION

CUTOUT VIEW OF INTERNAL COMBUSTION TURBINE (Source: SIEMENS)

COMBINED BURNEREXPANSION SECTION

EXHAUST GAS STEAM BOILER 1 COOLING SYSTEM LAYOUT

3D MODEL OF STEAM TURBINE UNIT WITH ACCESSORIES

ELECTRICAL SYSTEMS, HOME CONSUMPTION

The system of the CCGT home consumption has operating, reserve, and emergency sources at its disposal. The transition between operating and reserve sources and the connection of emergency sources is performed automatically.

Operation of the CCGT home consumption system is provided by branch transformers powered by gas turbi-ne generator outlets. These branch transformers supply two independent sections of 6kV switchgear stations. Reserve supply of the 6kV switchgear stations is to be accomplished from the present common 6kV switch-gear for units 5 and 6 of the Počerady power plant. The emergency supply of secure power supply appli-ances, i.e. a power supply during the loss of both operating and reserve sources, is to be ensured from independent emergency sources - accumulator batteries and 0.4kV diesel-generator. The 6kV switchgears will supply the main 6kV drives and 6/0.42kV home consumption transformers for the technology and civil electrical installation. The majority of MV and LV switchgears are situated in four fl oors of a separate building designated for the control rooms and switchgears. Cable routes are led from the building cable area (-3.5 m level) around the Main Generating Unit.

The concept of cabling and cable routes complies with the PPC fi re safety solution and also includes inte-grated fi re resistant cable systems that retain their function in the event of fi re.

Note: MV = medium voltage, LV = low voltage

CONNECTION TO GRID

The electrical output of the PPC will be connected to the grid by a 400kV V468 line to the Výškov Switchgear.

The output of each PPC generator will be connected separately through the generator circuit breaker and its own output transformer into the corresponding array of the encased 400kV switchgear. The encased switch-gear utilises GIS (gas insulated switchgear) technology - SF6 gas insulation - and is located in a separate dedicated building near the line.

Connection of the generators to the output transformers is designed using encased cables including connecti-on to branch transformers and excitation transformers. Connection of the output transformers to the encased switchgear is realised by 400kV single-core cables. For these cables, a cable route is to be constructed directly adjacent the output transformer site and the encased switchgear building. The encased 400kVswitch-gear is equipped with three inlet arrays that will be fi tted with 400kV output circuit breakers which will ensure independence of the individual outlets in case of partial failure while at the same time enabling control of the CHP consumption generators. A disconnector is installed in the outlet array of the 400kV encased switchgear on the V468 line. The outside part of the 400kV switchgear includes a portal for connecting V468 line cables which constitutes the battery limit with the grid as a component of the PPC Work.

Both the outside and the encased part of the switchgear are equipped with instrument transformers for pro-tection, synchronisation, and measurement. Commercial and verifi cation measurement for invoicing is also provided there.

CONNECTION OF THE MAIN GENERATING UNIT BUILDINGSTO THE OUTPUT TRANSFORMERS

CONNECTION TO GRID

ADJUSTMENTSTO THE EXISTING POWER PLANTUNITS

The Počerady power plant operates fi ve units with an output of 200 MWe. The units, respectively their pairs (-, 2), (3, 4), (5, 6), are connected through triple-wound unit transformers T401, T402, T403 via 400kV lines (V467, V468, V469) to the Výškov Switchgear. Disconnectors are located only at the 400kV side of the unit transformers. Line cut-out switches are on the Výškov side. 400kV V468 line, which serves the existing units 3 and 4, will be released in advance for connection of the new CCGT unit to the grid. These units will be connected to V467 line which is currently in use of unit 2. Concerning internal unit connections and con-nection to the 400kV grid, a new generator triplet will be created from the existing unit pairs.

SINGLE-LINE DIAGRAM

TECHNOLOGY PROCESS CONTROL

The technology process control will be based on modern programmable equipment of a high industry stan-dard, communicating together through communication buses to ensure functionality, reliability, performance, resistance to environmental infl uences and quality assurance requirements.

The automatic technology process control system will allow the listing of the event sequence during break-downs, long-term archiving of measured technological process values, process equipment diagnostics, and other support functions.

A unifi ed distributed control system connected to autonomous control systems for gas turbines, steam turbine, and a chemical water treatment plant will be used for PPC technology control as a whole. With these linked systems, the control system is designed to constitute one integrated system able to optimally and automatically control the Main Generating Unit and other power plant technology nodes both during stable and transient operating conditions.

The individual systems will be connected at the level of automation and application buses, through HW sig-nals, and via communication connections. The critical components of the system and its power supply will be redundant to achieve high operational system reliability. Standard protection methods will be implemented to protect the control system against external attack. To ensure high operation safety, the part of the control system and protection circuits will be produced with the required security level to ensure the reliability of security functions.

deliv

ered

by

E F

PR

deliv

ered

by

E F

PR

deliv

ered

by

E F

PR

V

PN

Tun

nel

Con

nect

ion

to th

ird p

arty

sys

tem

to

be

clar

ified

App

licat

ion

Hig

hway

Oth

er S

uppl

ier

xxx

ST

Aut

omat

ion

Hig

hway

Opt

iona

l: Pe

rfor

man

ceM

onito

ring

TC

Shift

Sup

ervi

sor

TC

His

toria

n / E

ngin

eerin

g

TC

Col

or L

aser

Prin

ter

Opt

ion

:Pe

rfor

man

ce M

onito

ring

Serv

er

Cen

tral C

ontro

l Roo

m -

CC

R

Ele

ctric

al

Are

a

Wat

er

Trea

tmen

tA

rea

HR

SG

Are

a

CM

104

CM

104

CM

104

Non

Red

unda

nt S

eria

l Lin

k:M

V S

witc

hgea

r PR

OFI

BU

SS

witc

hyar

d IE

C 6

1850

Lin

kC

isco

Lin

kC

EM

S (M

OD

BU

S –

TC

P/IP

)…

Red

unda

nt S

eria

l Lin

k:PS

09

Elec

trica

lsPS

10

APC

S PS

12

Com

pres

sor s

tatio

nPS

06,

16,

18

CH

UV

PS 2

1 M

odifi

catio

ns in

the

exis

ting

bloc

ksC

entra

l Dis

patc

h, P

TIS,

DAM

ATIC

, Č

EPS

Scope by Siemens

Scope by others

BO

P / T

CS

Ope

rato

r

TC52''

Ele

ctric

al B

uild

ing

SPPA

-T30

00A

uS (r

ed)

SPPA

-T30

00A

uS (r

ed)

SPPA

-T30

00A

uS (r

ed)

RA

ID

BO

P / T

CS

Ope

rato

r

TC52''

BO

P / T

CS

Ope

rato

r

TC

SPPA

-T30

00

Dat

a lo

gger

Turb

ine

cont

rol

Turb

ine

gove

rno

Fast

I/O

mod

ule

AuS

(red

)Sp

ecia

l Sys

tem

s

I/O m

odul

es

Flam

e m

onito

rin

Spee

d m

onito

rin

Turb

ine

Trip

Sy

AuS

(red

)SP

ecia

l Mea

ssur

Wob

be

AR

GU

S

AR

GU

S

AuS

(red

)ET

200

I/O m

odul

es

I/O m

odul

es

I/O m

odul

es

I/O m

odul

es

ET20

0

I/O m

odul

es

I/O m

odul

es

I/O m

odul

es

SPPA

-T30

00

I/O

Cab

inet

SPPA

-T30

00

I/O

Cab

inet

2x2x

2x

SPPA

-T30

00

I/O

Cab

inet

G1C

JT01

SFC

G1C

JT01

SEE

SPPA

-T30

00

Dat

a lo

gger

Turb

ine

cont

rol

Turb

ine

gove

rno

Fast

I/O

mod

ule

AuS

(red

)Sp

ecia

l Sys

tem

s

I/O m

odul

es

Flam

e m

onito

rin

Spee

d m

onito

rin

Turb

ine

Trip

Sy

AuS

(red

)SP

ecia

l Mea

ssur

Wob

be

AR

GU

S

AR

GU

S

AuS

(red

)ET

200

I/O m

odul

es

I/O m

odul

es

I/O m

odul

es

I/O m

odul

es

ET20

0

I/O m

odul

es

I/O m

odul

es

I/O m

odul

es

M

Fiel

d D

evic

es

G1C

JT01

SEE

Profibus

M

Fiel

d D

evic

esG

T G

2

M

Fiel

d D

evic

esG

T G

1

xxx

ST

M

Fiel

d D

evic

esST

Gas

Tur

bine

1S

team

Tur

bine

HW

HW

HW

HW

HW

HW

ACC

S

OT

xxx

ST

CM

104

CM

104 to c

larif

y

ApS

(red

)

Pow

er C

ontro

l Cen

ter -

PC

CP

ower

Con

trol C

ente

r -P

CC

Profibus

G1U

BA0

1G

2UBA

01

Fire

wal

l

GP

SG

PS

WIN

-TS

TC

Dem

ilita

rized

Zo

ne

Terminal Server

Fire

wal

l

SIE

ME

NS

Rem

ote-

Ser

vice

Dat

a Se

rver

Firewall

Acc

ess

Serv

er

G1U

BA02

G2U

BA0

2

Gas

Tur

bine

2

Rou

ter

WIN

-TS

LAN

WIN

-TS

LAN

BW

Las

er P

rinte

rA

larm

Prin

ter

Larg

e Sc

reen

py

g

Plan

tM

anag

emen

t Sy

stem

Opt

iona

l:

Firewall

OT

ApS

OT

OT

ApS

Rou

ter

Rou

ter

CONTROL SYSTEM ARCHITECTURE

CIVIL PART

The architectural and civil layout design has been determined by technological requirements and complies with noise protection and fi re safety requirements as well as with environmental limits.

THE CRITICAL CIVIL STRUCTURES ARE:· The Main Generating Unit (Machine Halls for Steam and Internal Combustion Turbines)· The Natural-Draught Cooling Tower· The Cooling Water Pumping Station and the Fire Fighting Water Pumping Station· The Encased Switchgear Building· The Make-up Water Treatment Plant

The Boiler House, Machine Halls for Steam and Internal Combustion Turbines, Control Rooms, Switchgears, Compressor Station and piping areas objects constitute a structurally single compact Main Generating Unit.The Main Generating Unit layout is composed of individual operating parts, its main dimensions being approx. 151.1 x 82.6 m. The individual parts of the Main Generating Unit are placed at different heights. The total built-up area is 8,367 m2 (excluding stack foundations and cooling pits). Foundations, footings, underground areas and ducts will be constructed of reinforced-concrete; above-ground structures will be made of steel.There are underground cable areas below the switchgears under part of the Main Generating Unit. The space is composed of a concrete sump upon which the structure of control rooms is founded. The foundation is shal-low, composed of a foundation slab, the cable space ceiling is a slab-and-girder monolithic type in accordance with the requirements for fl oor openings and it is supported by concrete pillars.

COOLING TOWER STEAM TURBINE MACHINE HALLGAS TURBINE

MACHINE HALLS

COOLING AND FIRE FIGHTINGWATER PUMPING STATIONS ADMINISTRATION BUILDING EXHAUST-GAS BOILERS

LAYOUT GROUND PLAN

VIEW OF THE MAIN GENERATING UNIT, COOLING WATER PUMPING STATION,AND COOLING TOWER FROM THE NORTH

OPERATING ATTRIBUTES

A distinct feature of all CCGT plants is the dependence of their output on external conditions, i.e. on air tem-perature, altitude and relative humidity. The most signifi cant is the infl uence of temperature, where the output of the gas turbines declines considerably with the increasing ambient temperature while the parameters of released exhaust gases change and affects the steam part of the combined cycle. This is caused in particular by the change of mass fl ow through the inlet air compressor due to the changing specifi c density of air.

PPC OUTPUT DEPENDENCE ON AMBIENT TEMPERATURE

305 MW

300 MW

295 MW

290 MW

285 MW

280 MW

275 MW

270 MW

265 MW

260 MW

255 MW

250 MW

245 MW

240 MW

870 MW

860 MW

850 MW

840 MW

830 MW

820 MW

810 MW

800 MW

790 MW

780 MW

770 MW

760 MW

750 MW

740 MW

GT, STOUTPUT

UNITOUTPUT

AMBIENT TEMPERATURE

-10 -5 0 5 10 15 20 25 30

GT OUTPUTST OUTPUTUNIT OUTPUT

WE ARE AN EPC CONTRACTOR AND DEVELOPER OF INVESTMENT PROJECTS IN THE ENERGY SECTOR

We are the largest Czech engineering contractor able to deliver power generation projects from the design through implementation and assembly to commissioning and securing of both warranty and extended warranty service. We also supply balance of plant. We provide service tasks.

We are active primarily in conventional and nuclear power, but also in heating plants, CCGT power plants and renewable energy sectors.

We are implementing the Czech industrial project of the decade, the Renewal of the ČEZ Group productioncapacity. As part of this project we are performing the comprehensive and environmentally benefi cial renewal of the Tušimice II and Prunéřov II power plants; we are constructing a new production unit with supercritical steam parameters in the Ledvice power plant and a new CCGT plant in the Počerady power plant. We are also implementing complex delivery projects for nuclear power plants as well as output improvement projects and nuclear unit modernisation. We also operate in the fi eld of renewable energy sources.

We excel in a strong professional know-how that we have been building under the ŠKODA PRAHA trademark for 60 years. During that time, we have delivered more than one hundred power generation units with a total output of 40,000 MW to 25 countries around the world. We deliver energy generation works that stand out due to their high technological quality, effi ciency, reliability, and are environmentally friendly.

VISIONIS THE FIRST STEPTO ACTION

WE DO BIG THINGS

NEW 840 MWe CCGT UNITAT THE POČERADY POWER PLANT

APRIL 1, 2011

WE DO BIG THINGS

www.spinvest.cz