45
NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) Distribution and Consumer Services Directorate BIDDING DOCUMENT FOR Design, Planning, Engineering, Procurement (Manufacturing/Supply), Construction/Erection, Testing, Commissioning and Five Years of Operation & Maintenance of 25 MWp Grid Tied Solar Farms (EPC Contract) Single-Stage, Bidding Procedure IDA Cr.: Credit No. 5566-NP Project Name: Grid Solar and Energy Efficiency Project Issued on: ………………… Invitation for Bids No.: GSEEP/ICB-071/72-01 ICB No.: GSEEP/ICB-071/72-01 Employer: Nepal Electricity Authority Country: Nepal VOLUME II-PART 2 OF 2 April 2015 Acronyms The Project Manager Grid Solar and Energy Efficiency Project Distribution and Consumer Services Directorate Nepal Electricity Authority Durbarmarg, Kathmandu, Nepal Tel.: +977-1-4153145 Fax.: +977-1-4153146 E-mail: [email protected]

NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal)

Distribution and Consumer Services Directorate

BIDDING DOCUMENT

FOR Design, Planning, Engineering, Procurement (Manufacturing/Supply),

Construction/Erection, Testing, Commissioning and Five Years of Operation &

Maintenance of 25 MWp Grid Tied Solar Farms

(EPC Contract)

Single-Stage, Bidding Procedure

IDA Cr.: Credit No. 5566-NP

Project Name: Grid Solar and Energy Efficiency Project

Issued on: …………………

Invitation for Bids No.: GSEEP/ICB-071/72-01 ICB No.: GSEEP/ICB-071/72-01

Employer: Nepal Electricity Authority

Country: Nepal

VOLUME II-PART 2 OF 2

April 2015

Acronyms

The Project Manager

Grid Solar and Energy Efficiency Project

Distribution and Consumer Services Directorate

Nepal Electricity Authority

Durbarmarg, Kathmandu, Nepal

Tel.: +977-1-4153145

Fax.: +977-1-4153146

E-mail: [email protected]

Page 2: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Table of Contents

1. General Description of Project Sites

2. General Survey Report of Selected Project Sites

Page 3: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Name of the Project: Grid Solar and Energy Efficiency Project Location: Development Region: Central Development Region Zone: Bagmati and Narayani District: Nuwakot and Makwanpur

S.No. Description of Hydropower plants

Location Co-ordinates District

Northing Easting

1 Devighat

1.1 Raatmatey Area Charghare VDC 27O 52’ 58.47” 85O 7’ 29.78” Nuwakot

1.2 Keraghari Area Charghare VDC 27O 52’ 47.67” 85O 7’ 23.67” Nuwakot

1.3 Staff Quarter Area Bidur Municipality

27O 53’ 43.32” 85O 8’ 15.65” Nuwakot

1.4 Forebay Ground Charghare VDC 27O 53’ 23.43” 85O 7’ 59.94” Nuwakot

2 Trisuli

2.1 Area 2 Bidur Municipality

27O 56’ 35.56” 85O 9’ 28.36” Nuwakot

3 Kulekhani I

3.1 Markhu Markhu VDC 27O 37’ 8.87” 85O 9’ 2.61” Makwanpur

Topographical Survey

Page 4: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Site Location

The following images shows the areas within the premises of Devighat Hydropower Plant,

Trisuli Hydropower Plant and Kulekhani I Hydropower Plant where the installation of the Grid

Solar Power Plant will take place.

Fig 1: Site Location of different Hydropower Plants

Page 5: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Fig 2: Location of Raatmatey, Keraghari, Staff Quarter area and Forebay ground in Devighat

Hydropower Plant

Page 6: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Fig 3: Location of Markhu in Kulekhani I Hydropower Plant

Control Survey

For the international reference a Global Positioning System was followed using the

sophisticated GPS instrument to find the easting, northing and elevation of the stations in the

field. Benchmarks were established by painting to be identified as permanent structure.

Using a Total Station an open traverse was carried establishing new stations covering

entire survey area of project area. Topcon Total Station with least count 1" for measuring

horizontal angles and standard reflecting prism of an accuracy ± 5ppm was used.

Detail Topographical Survey

Various categories of survey under this heading were conducted to obtain information

and parameters necessary for the design purposes.

While surveying we located all existing right of way property lines and easement

including type size and bearings. Existing structures such as buildings, fences retaining

wall, Roads, trees, electric poles and other details were accurately described.

Page 7: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Survey Data processing and Mapping Works

Following survey standards, a complete check of survey data was made. “Softwel Dtm”

software was used for plotting the points and generating the minor contours at interval of 1 m

followed by major contours at interval of 5 m with annotation.

All the existing features such as road, buildings, trees, rivers, walls, Kholsi (Water

Stream), cliff, rock, boulder, high flood level, water level, bridges etc. were identified and the

crossing axis alignment was assumed to generate the cross-sections. The detailed topographical

map of related location was plotted as per the required standards and scale and

presented in the following pages.

Prakash
Highlight
Prakash
Typewritten text
Prakash
Typewritten text
The plotted topographical maps with the contour intervals of 1 m is presented in the A3 size paper to have an overall view and as the extend of survey area is large , the scale of the map is not the one as required in general.
Page 8: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 9: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 10: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 11: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 12: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 13: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 14: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Shadow Analysis

Shadow Analysis is a tool for analyzing daylight conditions. Analyses are presented in the

form of colorful pictures – different colors denote different amount of exposure to sun

light. Shadow Analysis helps understand daylight conditions. PV arrays should be installed

in a shade-free location. To get the information about the shading of the sunlight on the

selected areas of the three hydropower plants, shadow analysis was performed.

A site assessment involves determining whether the location of the PV array will be

shaded, especially between the hours of 9 a.m. and 4 p.m. solar time (the study was conducted

from 7 AM to 6 PM). This is important, as the output of PV modules may be significantly

impaired by even a small amount of shading on the array.

In the present study, shadow analysis was conducted from real field data where shadow zone

was identified from 7 AM to 6 PM in one hour intervals. The resulting data was presented in

form of shadow map given below:

Page 15: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 16: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 17: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 18: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 19: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 20: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 21: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 22: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 23: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 24: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 25: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 26: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Prakash
Typewritten text
NEPAL ELECTRICITY AUTHORITY
Page 27: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

This volume presents details of geotechnical investigation of the three existing hydropower

plants where solar panel will be placed.

1 General Description

1.1 Site description

There are three sites in the project. Three hydropower stations: Devighat, Trishuli and Kulekhani

I. The site location map of all sites in google earth is shown in Fig. 1.

Fig. 1: Site location of different hydropower stations

Accurate locations of the site along with its surrounding information along with the location of

bore holes are shown in Figs 2 to10.

Geotechnical Survey

Page 28: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Fig. 2: Location of Raatmatay, Keraghari, Staff quarer area and Forebay ground, Devighat

hydropower plant site

Fig.3 Raatmatay area, Devighat

Page 29: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Fig. 4: Keraghari, Devighat

Fig. 5: Staff quarter area, Devighat

Page 30: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Fig. 6: Forebay area, Devighat

Fig. 7: Location map, Trishuli hydropower plant

Page 31: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Fig. 8: Area 2, Trishuli

Page 32: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Fig. 10: Markhu, Kulekhani with bore hole positions

2 General Geology, Geomorphology and Seismicity

2.1 General Geology and Geomorphology

Geologically, Nepal has been divided into five different zone such as Terai zone, Sub-Himalaya,

Lesser Himalaya, Higher Himalaya and Tibetan Tethys zone as shown in the geological map of

Nepal in Fig. 11.

The present sites Devighat, Trishuli lies in lesser Himalaya zone composed of Kn (Kuncha) rock

group which is composed of bedded schists, phyllites, metasandstones and quartzites. However,

at site, these rocks are completely weathered upto a depth of 4m and residual soil is only found at

sites. Similarly, Markhu, Kulekhani site also lies in lesser Himalaya zone but composed of

Bhimphedi group (Bh) rocks. Bh group mainly consists of schists and quartzites. At site,

however, only residual soil in the form of clay, clay with gravel and gravel with sand were found.

The location of sites in geological map is shown in Fig. 12.

Page 33: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Fig 11: Geological map of Nepal (Dahal 2006)

Fig. 12: Site location in geological map

2.2 Seismicity

Due to Tectonic Forces, Himalayan zones and the neighboring areas are seismically very active.

Most of epicenters of earthquakes are found to be located in the unstable zones. The frequency

and intensity of earthquakes are found at the weakness of the crust such as major faults, major

bends or major acres. Location of Nepal in the Himalaya along with major tectonic boundary and

various longitudinal zones of the Himalaya are shown in Fig 13.

Page 34: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Seismic hazard map of Nepal is also shown in Fig 14. Figure 14 shows that earthquake with a

peak acceleration of 0.3-0.5g may occur in 50 years, making the country very vulnerable to

earthquake.

Fig 13 Location of Nepal in the Himalaya along with major tectonic boundary and various

longitudinal zones of the Himalaya (Bhandary et al. 2013)

Fig 14 Seismic hazard map of Nepal (source: USGS)

3 Geotechnical Survey

3.1 Methodology

3.1.1 Field work Procedure

Page 35: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes

where it was applicable to the maximum depth of 20m from the ground level and SPT were taken

at every 1m intervals and are recorded. Borehole logs were prepared at the site on the basis of the

visual observation of the soil obtained from the boreholes. The boreholes logs are attached to the

annexes are later verified by lab test results.

3.1.2 In-situ Tests

Field works involved Percussion Drilling mechanism for drilling and sampling of the boreholes

in the proposed area to the depth of 4m from the ground levels and SPT were taken at every 1m

intervals and are recorded. Borehole logs were prepared at the site on the basis of the visual

observation of the soil obtained from the boreholes. The boreholes logs are attached to the

annexes are later verified by lab test results.

Standard Penetration Test (SPT):

It consists of driving a Split Spoon Sampler with an outside dia. of 50 mm into the soil at the

base of borehole. Driving is accomplished by a drop of hammer weighing 63.5 kg falling freely

through a height of 750 mm onto the drive head. First of all the spoon is driven 150mm into the

soil at the bottom of the borehole. It is then driven further 300mm and the number of blows (N

values) required to drive this distance is recorded.

Fig 17 Standard Penetration Test Procedures

Page 36: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Table 3: Relation of N value to Relative Density and friction angle for granular soils

N value Relative Density Friction Angle

0-4 Very loose 26-30

4-10 Loose 28-34

10-30 Medium Dense 30-40

30-50 Dense 33-45

Over 50 Very Dense <50

Fig 18 Angle of shearing resistance for different SPT N value

Table 4: Relationship of N Value to Strength and Consistency for Cohesive Soils

N value Consistency Strength Qu

<2 Very Soft < 25

2-4 Soft 25-50

4-8 Medium Stiff 50-100

8-15 Stiff 100-200

15-30 Very Stiff 200-400

>30 Hard 400-800

Page 37: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

3.1.3 Sampling

(i) Disturbed Sample:

Before any sample was taken, the borehole was cleaned up of loose disturbed soil deposited

during drilling operation. The samples which were obtained from bailer and in the SPT tubes

were preserved as representative disturbed samples for finding out physical properties. The

samples thus obtained were placed in airtight double plastic bags, labeled properly for

identification and later transported to the lab for analysis.

(ii) Undisturbed Sample:

Undisturbed samples were extracted using thin Shelby tube sampler. The moisture content was

maintained as natural.

3.2 Laboratory Tests

Disturbed and Undisturbed samples were collected and transported to the laboratory for the

following tests.

Sieve analysis

Natural Moisture Content

Bulk density and Dry Density

Specific Gravity

Direct shear test

Consolidation test

Unconfined compression test

4 Observation and Results

4.1 Field Investigation Results

The drilling works were carried out from the ground level to a depth of 4 m. The major soil

profiles in each bore log are shown in Table 5:

Page 38: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Table 5: Major soil profile in each bore logs

Site/Area BH No Depth Soil type

Devighat/Ratamatey 1

0-4m

Reddish clay

2

Devighat/Keraghari

1

2

Devighat/ Staff

quarter area

1 0-2m

2-4m

Sand with gravel

Gravel with boulders 2

3

4

Devighat/ Forebay 1 0-2m

2-4m

Gravel with sand

Gravel with sand and boulder Trishuli/ Area2 1 0-2m

2-4m

Sand with gravel and fines

Gravel with sand and boulders 2

Trishuli/ Reservior

pond

1 0-1m

1-4m

Sand with fines

Sand with gravel and boulders

2 0-2m

2-4m

Sand with gravel and fines

Gravel with sand and fines

3 0-1m

1-4m

Gravel with sand and fines

Gravel with sand and boulders 4

Kulekhani/Markhu 1 0-2m

2-4m

Clay with gravel

Gravel with boulders

2 0-3m

3-4m

Clay with sand and gravel

Blackish medium stiff clay

Measured Standard Penetration Test (SPT) values are found in the range of 5 to more than 50 in

the in-situ soil strata at different levels. Standard Penetration Tests (SPT) was conducted on each

bore holes at 1m interval, starting the first test at 1m. Laboratory test such as grain size

distribution, dry unit weight, natural moisture content, specific gravity, Shear strength properties

of soil samples were conducted on disturbed soil samples extracted with standard procedure

using Shelby (thin wall) tubes and from bailer. The bore log profile is shown in Appendix I.

4.1.1 Ground Water Table

Ground water tables (GWT) were not found during the soil investigation works. As the site has

water only during the rainy season, during soil investigation, the water table in the bore hole was

not observed.

Page 39: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

4.2 Laboratory Investigation Results

4.2.1 Index Properties

The result of physical and index properties of soil samples collected from different depths are

presented in the attached summary sheet.

The grain size distribution curves of soil sample are classified as USCS Soil Classification

System in which most of the soil fall in ML groups. Specific Gravity determination on selected

soil samples is in the range of 2.32 to 2.70.

Natural moisture content of soil is approximately 9-36%. Liquid limit of soil is in the range of

31-47. Soil samples are low to medium plastic silts and clay.

4.2.2 Strength Parameters

Unconfined compression tests were conducted on undisturbed samples. Unconfined compressive

strength for the tested samples was in the range of 75 to 275 KN/m2. Corresponding undrained

shear strengths are in the range of 37.5-137.5 KN/m2 for the tested samples. Cohesion and

friction angle of the tested cohesionless samples were in the range of 0-30.2 KN/m2 and 5.6-

38.2°, respectively.

5 Bearing Capacity Analysis

5.1 General

Bearing capacity of footing is the ultimate load that the soil can take without shear failure or

excessive settlement. Thus the foundation should be designed against both shear failure and

excessive settlement. In this report, the allowable settlement of soil is taken as 25mm. If the

allowable settlement increases, the bearing capacity will increase accordingly. For the foundation

of solar panel, isolated or strip footing may be used.

5.2 Depth of Foundation

The depth of foundation is governed mainly by factors like scour depth, depth to ground freeze

and the nature of the subsoil strata to place the foundation. The types of foundation analyzed

comprise an open foundation. The depths used in the analysis are 2m from ground position.

Page 40: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

5.3 Computation of Bearing Capacity in soils

The bearing capacity analysis has been carried out for foundation soil at 2.0 m depth from

ground. In the analysis, both shear failure and settlement criteria are taken into account. The

bearing capacity analysis was carried out based on the results of SPT N-value. The open

foundation is a large footing extending over a great area.

5.3.1 Cohesionless soil

The well-known Teng’s equation has been used to compute bearing capacity of soil on the basis

of shear failure criteria. The width of foundation used in the analysis is varied. For solar panel,

either isolated footing or strip footing can be used.

The following equation is used to determine bearing capacity from shear failure criteria.

qfns WDNBWNq )100(67.022.0 22 (1)

The bearing capacity of open foundation for cohesionless soils can also be obtained using

settlement criteria as explained by different researchers below:

i. Teng (1969) based on the curves developed by Terzaghi and Peck (1948)

2

2 0.3( / ) 35( 3)

2p d w

Bq KN m N F R

B

(2)

where qp is the net allowable bearing pressure for allowed settlement of 25 mm, N is the

corrected SPT, B is the width of the footing, Rw is the water table correction factor (Rw= 1+z2/B),

where z2 is the depth of water table from footing level, Fd is the depth factor (Fd = 1+0.2*D/B ≤

1.2)

ii. Meyerhof (1956)

For B > 1.2m, for open foundations

2

2 0.3( / ) 8p d w

Bq KN m N F R

B

(3)

Fd is given by Fd = 1 + 0.33 D/B ≤ 1.33.

Page 41: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Experimental results have shown that Teng’s and Meyerhof’s equations for bearing capacity

(BC) are too conservative. Bowles (1988) has increased BC by 50 % and given by:

iii. Teng’s Equation (modified)

2

2 0.3( / ) 53( 3)

2p d w

Bq KN m N F R

B

(4)

Eq. (3) is also proposed by Teng for 40 mm settlement.

iv. Meyerhof’s Equation (modified)

2

2 0.3( / ) 12.5p d w

Bq KN m N F R

B

(5)

For the settlement of 40 mm, net allowable bearing pressure is given by:

''

25p p

Sq q (6)

v. Bearing Capacity from IS Code (2950 – 1956):

I.S. 2950 – 1956 gives the code of practice for design and construction of raft foundation:

For 25mm settlement,

qsafe (KN/m2) = 17.5 (N – 3)RW (7)

vi. Bearing Capacity from IS Code (6403 – 1971):

I.S. 6403 – 1971 accepted Teng’s equation for 40 mm settlement, without depth factor, given by

2

2

2

0.3( / ) 55( 3)

2p w

Bq KN m N R

B

(8)

vii. Peck’s method

Peck’s method is also considered for analysis for evaluation of safe bearing pressure of footing.

The safe bearing pressure is evalauted as:

NSCq wnp 41.0 (9)

where

Cw= water table correction factor given by

Cw = 0.5 + 0.5 × Dw / (Df + B)

Page 42: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

Using the relationships suggested above the analysis was carried out. The results of analysis are

summarized in Table No. 2.

5.3.2 Cohesive soil

To calculate the bearing capacity of cohesive soil, Both the Terzaghi’s method and Skempton’s

method will be used. The bearing capacity equations are:

Terzaghi’s net ultimate bearing capacity equation is:

L

BCq

nu3.017.5 (10)

Similarly, Skempton’s net ultimate bearing capacity is given by:

cnuCNq (11)

5.2B

Dfor 2.012.015 f

)(

L

B

B

DN

f

recC (12)

The safe bearing capacity is obtained by dividing net ultimate bearing capacity by factor of

safety, FS (=3).

The calculated bearing capacity with major soil type is shown in Table 6.

Table 6 – Computation of Bearing Capacity of Foundation

Site/Area BH No Major soil type SPT value

(N)

Depth

(D)

Width (B) Net Allowable

Bearing Capacity

(qna, KN/m2)

Devighat/Ratamatey 1 Cohesive (silt,

clay)

6 2m 1m 68

2 Cohesive (silt,

clay)

7 2m 1m 80

Devighat/Keraghari

1 Cohesive (silt,

clay)

7 2m 1m 80

2 Cohesive (silt,

clay)

7 2m 1m 80

Devighat/ Staff quarter

area

1 Cohesionless

(sand, gravel)

40 2m 1m 323

2 Cohesionless

(sand, gravel)

33 2m 1m 262

3 Cohesionless

(sand, gravel)

30 2m 1m 236

4 Cohesionless

(sand, gravel)

26 2m 1m 198

Devighat/ Forebay 1 Cohesionless

(sand, gravel)

50 2m 1m 411

Trishuli/ Area2 1 Cohesionless

(sand, gravel)

50 2m 1m 411

Page 43: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

2 Cohesionless

(sand, gravel)

50 2m 1m 411

Kulekhani/Markhu 1 Cohesive (silt,

clay)

5 2m 1m 57

2 Cohesive (silt,

clay)

5 2m 1m 57

Fig 19: Open foundation bearing capacity sample calculation (Trishuli/ reservoir pond/ BH-2)

KN/m2

Page 44: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

6 Recommendation

Geotechnical profile along different bore hole shows both cohesive soils and cohesionless soils at

different depths. The depth of foundation can be kept as 2m and either the isolated footing

(rectangular/ square, size 1-2m) or the strip footing (width = 1-2m) can be adopted. The

recommended bearing capacity for different sites along with dominant soil profile is as follows:

Site/ Area Soil type Recommended

bearing capacity (KN/m2)

7 References:

USGS (United State Geological Survey):

http://earthquake.usgs.gov/earthquakes/world/nepal/gshap.php

Bhandary, NP; Yatabe R; Dahal RK; Hasegawa S and Inagaki H (2013): Areal distribution of

large scale landslides along highway corridors in central Nepal. Georisk: Assessment and

Management of Risk for Engineered Systems and Geohazards,

DOI:10.1080/17499518.2012.743377

Dahal, R., K., 2006, Geology for Technical Students, Bhrikuti Academic Publications,

Kathmandu, Nepal, 756p.

Devighat/ Raatmatay Cohesive (silt, clay) 68

Devighat/ Keraghari Cohesive (silt, clay) 80

Devighat/ Staff quarter area Cohesionless (sand, gravel) 198

Devighat/ Forebay ground Cohesionless (sand, gravel) 411

Trishuli/ Area 2 Cohesionless (sand, gravel) 411

Kulekhani/ Markhu Cohesive (silt, clay) 57

Page 45: NEPAL ELECTRICITY AUTHORITY€¦ · Field works involved percussion Drilling mechanism for drilling and sampling of the boreholes where it was applicable to the maximum depth of 20m

USCS

Coarse to

mediumFine

% % % % % % % % gm/cc gm/cc KN/m2 c (kPa) φ°

1 0-1m CL 89 47 33 14 32.1 1.82 1.38 2.32 75.4

2 0-1m CL 76 45 33 12 29.6 1.78 1.37 2.45 95.7

1 0-1m CL 80 42 33 9 25.4 1.69 1.35 2.55 92.4

2 0-1m CL 83 42 35 7 27.8 1.72 1.35 2.49 85.9

1 0-1m CL 75 35 24 11 32.4 1.58 1.19 2.56 15 32.4

2 1-3m SP 34 1 17.8 1.92 1.63 2.67 0 33.2

3 1-2m SP 36 1 15.4 1.87 1.62 2.62 0 31.8

4 1-2m SP 38 1 16.2 1.72 1.48 2.66 0 30.9

Devighat/ Forebay 1 0-2m GP 83 1 12.8 1.69 1.50 2.67 0 35.2

1 0-1m SP 29 5 13.4 1.81 1.60 2.64 2 36

2 1-2m SP 29 4 15.6 1.76 1.52 2.68 1.2 35.9

1 2-3m CL 86 43 26 17 34.2 1.68 1.25 2.59 150.8

2 2-3m CL 82 43 25 18 29.8 1.59 1.22 2.52 172.4

3 2-3m CL 88 43 27 16 35.9 1.72 1.27 2.55 275.4

4 2-3m CL 87 44 26 18 34.6 1.82 1.35 2.61 200.4

1 0-1m SM 23 31 NA 15.2 1.86 1.61 2.64 15.4 9.8

2 2-3m SM 34 33 NA 16.4 1.88 1.62 2.62 30.2 5.6

Specific

Gravity

Unconfined

compression

strength (2m

depth UD)

Liquid

Limit

Plastic

Limit

Plasticity

Index

Classi-

fication

System

Gravel

Dry

Density

Sand Silt &

Clay

77

61

66

66

68

14

18

Direct shear test (at

2m depth UD sample)

11

24

20

Trishuli/ Area2

Trishuli/ Area5

Percentage of Atterberg LimitsNatural

Moisture

content

Moist

Density

Kulekhani/Markhu

63

Devighat/Keraghari

Devighat/ Staff

quarter area25

65

12

Depth (m)BH NoSite/Area

Devighat/Ratamate

17

16

13

Project: Soil Investigation Works for Nuwakot Beltar Site

Location : Nuwakot, Makwanpur