Neighbourhood Forum
01 August 2018
• Feedback from the last meeting
• What’s been happening in the last 2 weeks
• Vibration impact
• Surveys done to date
• Highways work
• Amendments to the scheme
• Questions
• Opportunity to question experts 1:1
Agenda for this evening
Feedback from the last meeting
• Visit to Westaway Court
• Speak to Parish about parking for Metro Apartments
residents – meeting 15 August
• Speak to Jersey Employment Trust about disabled
access concerns – meeting next week
• Confirm the extent of surveys on surrounding properties
What’s been happening in the last two
weeks
• Meetings with neighbours
• Amendments to planning application (coming up later)
• Lessons learned from St Peter
• Scoping condition surveys (coming up next)
• Phasing of early works
• Main scheme design
• Westaway Court engineering designs
• Basement design discussion
Vibration impact
Neighbourhood Vibration Phase 1
Comparison of Vibration
Potential vibration effect without mitigation• Identify risks to each specific department• Develop specific control and mitigation strategy• Communication & scheduling• Physical measures (primary & Secondary)
Air quality, noise & vibration – control and mitigation
Where we’ve done this before
Royal Albert Hall London
Bristol Royal Infirmary
Bexley Wing St James’s Leeds
Combined University Hospital ManchesterPrincesshay Exeter
Milton Court London
Existing hospital and Kensington Place properties
Environmental protection barrier
Demolition traffic routes
Existing
Changed
Construction
Traffic Flow
Construction/EmergencyTraffic only
Open to traffic outside of
Working hours
Traffic management during works
Surveys and Highways
Surveys
Survey Type Complete/Anticipated Completion Date
Lidar survey Complete
Below ground services (GPR) Complete except for remote highways and junctions
Topographical Survey Complete except for remote highways and junctions
Drainage CCTV Final phase of jetting and survey to be completed and services drawing updated. Anticipate one week of site works. To be completed ASAP
Acoustics A number of surveys completed. New scheme will be assessed to inform further surveys required
Vibration A number of surveys completed. New scheme will be assessed to inform further surveys required
Ground Investigation
BH101 Borehole complete. Monitoring July and August
BH102 Borehole complete. Monitoring July and August
BH103 Borehole complete. Monitoring July and August
BH104 Borehole complete. Monitoring July and August
BH105 Borehole complete. Monitoring July and August
BH106 Borehole complete. Monitoring July and August
BH107 Borehole complete. Target date for monitoring August/September
BH108 Borehole complete. Monitoring July and August
BH109 Incomplete. Target date post-demolition
BH110 Incomplete. Target date post-demolition
BH111 Incomplete. Target date post-demolition
BH112 Incomplete, target date end of May 2018
Water Monitoring As noted above
Gas Monitoring As noted above
Electrical Surveys To be defined during Stage 2 design
Mechanical surveys To be defined during Stage 2 design
Asbestos Survey On vacation of buildings to be demolished
Condition Surveys Prior to any works commencing
Structural surveys MSCP in August 2018
Traffic Surveys Complete
Westaway Court
N
People’s Park junction
Signalise junction to enable construction
traffic
Key
Location of highway/ junction works
Kensington Place
Acquisition of properties, surveys and soft strip
Removal of traffic calming measures prior to
demolition
Westaway Court
Asbestos survey
Soft strip
Patriotic Street MSCP
Modifications for additional staff car and
motorcycle parking
Service road, Westaway Court, Sutherland Court,
Kensington Place Properties
Ground Investigation
St Elmo
Soft strip and temporary propping
Demolition, including footway closure
All properties on construction route (dock to site and
back) - condition surveys All highway works to be agreed with DfI Streetworks and Highway Maintenance
Relevant highways and junctions - Topographical and
services survey
Esplanade/Kensington Place
Amend junction to enable construction
traffic
First physical works
Gloucester/Newgate
Street
Drainage connection
Gloucester Street Car Park
Staff car parking to be relocated to PSMSCP and
car park cleared and plant etc. installed
Amendments to the scheme
Amendments to the scheme
Amendments to the scheme
Questions and answers