Town and Country Road Neighborhood Streetscape Neighborhood Traffic Management Program 1 Public Works Committee of City Council March 24, 2015

Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Town and Country Road Neighborhood Streetscape

Neighborhood Traffic Management Program

1

Public Works Committee of

City Council

March 24, 2015

Page 2: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Presentation Overview

• Brief project background

• Overview of design concept

• Review of previous speed hump proposal

• Discussion of proposed treatment D (neighborhood traffic circle at Kingsley Rd.)

• Slides are available for all other treatments

2

Page 3: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Project Location

3

Page 4: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Project Timeline

• November 5, 2013 – #6 on priority list adopted by Council (minor traffic calming)

• January 16, 2014 – Information session (10 attendees)

• February 6, 2014 – Successful petition submitted (89% support)

• May 29, 2014 – Minor traffic calming preliminary design meeting (23 attendees)

• August 7, 2014 – Minor traffic calming design pre-marked

• September 18, 2014 – Neighborhood streetscape proposal meeting (18 attendees)

• October 20, 2014 – Neighborhood design review (21 attendees)

• February 5, 2015 – Treatments pre-marked

• March 3, 2015 – City Council Public Design Review

• Today – Public Works Committee of City Council 4

Page 5: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Traffic Study • Northbound (north of Kingsley)

– 50.8 mph 85th percentile – 45.6 mph 50th percentile – 70.2 mph maximum – 2994 vehicles per day

• Northbound (south of Misskelly) – 46.8 mph 85th percentile – 42.3 mph 50th percentile – 80.3 mph maximum – 3147 vehicles per day

• Southbound (north of Kingsley) – 47.9 mph 85th percentile – 43.4 mph 50th percentile – 72.1 mph maximum – 2050 vehicles per day

• Southbound (south of Misskelly) – 42.5 mph 85th percentile – 38.9 mph 50th percentile – 80.3 mph maximum – 2068 vehicles per day

5

Page 6: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Design Overview

6

Page 7: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Previously Proposed Speed Humps

7

Four Locations: • Spaced ~600 feet apart • Design speed 25 mph

Page 8: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Location D: Kingsley

(Facing North) 8

Page 9: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Location D: Kingsley

Neighborhood Traffic Circle

• Conclusively limits speed

• Proven safety record

• Generally less expensive than other intersection treatments

• Limits left turns by very large vehicles

9

Page 10: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Example Neighborhood Traffic Circle

10

Location: Knox St. and Dollar Ave. (NW of Duke University in Durham)

Page 11: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Circle Design

11

Without Curb and Gutter (approximate)

With Curb and Gutter (approximate)

Corners would be built ~27’ back to back.

Page 12: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Large Vehicle Routes

12

9

16

16

Only Kingsley Road is affected. Stars are Raleigh Fire Department Stations

Page 13: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Visualization: Existing

(Facing South) 13

Page 14: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Visualization: Proposed

(Facing South) 14

Page 15: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Potential Alternatives for Kingsley Road

• Circle without curb and gutter

• Circle with curb and gutter on corners

• Mini roundabout (completely mountable)

• Speed hump(s)

• Speed message sign

• Short section of improved street opens up many more alternatives

15

Page 16: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Location A: Ravenglass

(Facing Northwest) 16

Page 17: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Location A: Ravenglass

17

Page 18: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Location B: ~5050 Town & Country

(Facing North) 18

Page 19: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Location C: Misskelly

(Facing North) 19

Page 20: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Location C: Misskelly

20

Page 21: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Location E: Tuscany Woods

(Facing North) 21

Page 22: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Location E: Tuscany Woods

22

Note: During pre-marking, it was determined that there is not sufficient width to include landscaping on the median.

Page 23: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Location F: Millbrook

(Facing North) 23

Page 24: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Location F: Millbrook

24

Page 25: Neighborhood Traffic Management Program...•Slides are available for all other treatments 2 Project Location 3 Project Timeline • November 5, 2013 – #6 on priority list adopted

Next Steps

• Council authorization to proceed

• Final design to be developed by Public Works

25