Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
NEC4 – WHAT HAS CHANGED FOR PROFESSIONAL CONSULTANTS
20 February 2018
INTRODUCTION TO CHANGES
English (United Kingdom)
3
“This new and updated NEC4 Contract embraces the digital changes that are
happening in the construction industry, especially around BIM ...”
Intended to bring PSC more into line with other NEC contracts.
INTRODUCTIONNEC4 PROFESSIONAL SERVICE CONTRACT (PSC)
NEW TERMINOLOGY & KEY CHANGES
English (United Kingdom)
5
NEC3 PSCProfessional Services Contract
NEC4 PSCProfessional Service Contract
He / his It / Its
Employer Client (except Supply Contract)
Scope Scope
Risk Register Early Warning Register
Risk and Insurance Liabilities and Insurance
Parent Company Guarantee Ultimate holding guarantee (X4)
Partnering Multi-party collaboration (X12)
Adjudicator’s Contract Dispute Resolution Service Contract
TERMINOLOGY CHANGES
English (United Kingdom)
6
• 11 (11) The Parties are the Client and the Consultant.
And functions previously attributed to Client are now attributed to Service
Manager, e.g.
• 15.1 The Consultant and the Service Manager give an early warning ...
• 15.2 The Service Manager prepares a first Early Warning Register
• 10.1 The Parties and the Service Manager shall act as stated in this contract.
• 10.2 The Parties and the Service Manager act in a spirit of mutual trust and co-
operation.
OTHER CHANGES : SERVICE MANAGER
English (United Kingdom)
7
• Service Manager now discharges functions of Client (formerly Employer)
• 40.1/40.2 - Consultant operates a quality management system which complies
with the Scope and provides the Service Manager with a quality policy statement
and quality plan for acceptance.
• New to 40.2: “A reason for not accepting a quality policy statement or quality
plan is that it does not allow the Consultant to Provide the Service”.
• 41 – Correcting Defects
• 42 – Accepting Defects (New)
OTHER CHANGES : QUALITY MANAGEMENT
English (United Kingdom)
8
• Consultant indemnity (old 80.1) deleted.
• Replaced by
• 80 - Client’s Liabilities
• 81 - Consultant’s Liabilities
• 82 –
– 82.1 and 82.2 – Costs which either Party has paid or will pay (to Others, in the case of
the Consultant) as a result of an event for which the other Party is liable is paid by
that other Party
– 83.3 – Contributory negligence and similar defences preserved (for each Party)
LIABILITIES AND INSURANCE (CLAUSE 8)
English (United Kingdom)
9
• 83.1 Client provides insurances (if any) as stated in Contract Data
• 83.3 New wording for Consultant PL cover:
• “Loss of or damage to property and liability for bodily injury to or death of a person (not
an employee of the Consultant) arising from or in connection with the Consultant
providing the Service”.
• Minimum amount of cover: “The amount of cover stated in the Contract Data for any one
event with cross liability so that the insurance applies to the Parties separately”. (New)
LIABILITIES AND INSURANCE
English (United Kingdom)
10
• 84 – Insurance Policies: Consultant required to provide certificates signed
by the Consultant’s insurer or insurance broker.
• 85 – Default provision: If the Consultant does not provide a certificate,
the Client may insure that risk, and recover cost from the Consultant.
• 86 – Insurance by the Client
LIABILITIES AND INSURANCE
English (United Kingdom)
11
Clause 87 - Cap on liability – as stated in Contract Data, subject to excluded matters:
• delay damages (if applicable – x7)
• consultant’s share if option C applies
• infringement “of the rights of Others”
• loss or damage to TPP and death or bodily injury to third parties (not employees).
Option X18 – If stated in Contract Data, caps may be applied to:
18.2 – Indirect or consequential loss
18.3 – Liability for Defects that are not found until after the defects date
18.4 – Liability for a matter unless details are notified to the Consultant before the
“end of liability date.”
LIMITATION OF LIABILITY
English (United Kingdom)
12
Option X8: - Collateral Warranties are now “undertakings to Others”
- the form is set out in the Scope
- the Client sends the “undertaking to the Consultant, who must sign
and return within three weeks.
- no provision of Third Party Rights schedule
Option X9: - No change: If used, Consultant’s copyright vests in the Client.
OTHER CHANGES
English (United Kingdom)
13
X10 – Information Execution Plan (X10. 4)
- Project Information
- Information Model and Information Model Requirements
- Information Providers
X10.2 – Collaboration between the Consultant and other Information Providers.
X10.3 – The Consultant and the Service Manager give an early warning of any matter which could adversely
effect the creation or use of the Information Model.
X10.6 – The Client owns the Information Model and the Consultant’s rights over Project Information except as
stated in the Information Model Requirements.
X10.7 – Consultant is only liable if it has not used skill and care in providing its Project Information.
OTHER CHANGES: INFORMATION MODELLING
English (United Kingdom)
14
• Clause 5: Updated payment procedures, including provision for the
Service Manager to make an assessment of the final amount due, and to
clarify any final payment that is due.
• Clause 6: Compensation Events
• New exceptions to 60.1 (1) – Client instructed change of scope
• New compensation events
– 60.1 (9) An event which is a Client Liability
– 60.2 (13) Correction of Defect for which the Consultant is not liable
– 60.1 (14) Service Manager gives an instruction to correct information
provided by Client
– 60.1 (15) Notification that a quotation for a proposed instruction is
not accepted
– 60.1 (16) Any additional events stated in Contract Data part one.
PAYMENT PROVISIONS AND COMPENSATION EVENTS
English (United Kingdom)
15
• Option G now removed
• Only three main Options:
• A – Priced Contract with Activity Schedule
• C – Target Contract – the activity schedule is only used to adjust the
Prices when compensation events occur and subsequently for
calculating the Consultants share after completion.
• E – Cost reimbursable contract (no pricing document/activity schedule)
• New Schedule of Cost Components and Short Schedule of Cost
Components.
MAIN OPTION CLAUSES
English (United Kingdom)
16
- No major alarms for Consultants and their Professional Indemnity and
other insurers
- Helpful clarification of roles and liabilities of Client and Consultant.
- Introduction of Service Manager
- Updated payment arrangements and costs schedules
- Z clauses still likely!
SUMMARY
kennedyslaw.com
@KennedysLaw
linkedin.com/company/Kennedys
facebook.com/KennedysTrainees
NEC4 – ENGINEERING & CONSTRUCTION CONTRACT
What has changed for the project manager?
English (United Kingdom)
19
NEC3 NEC4
He / his It / Its
Employer Client (except Supply Contract)
Works Information Scope
Risk Register Early Warning Register
Risk and Insurance Liabilities and Insurance
Parent Company Guarantee Ultimate holding guarantee (X4)
Partnering Multi-party collaboration (X12)
Adjudicator’s Contract Dispute Resolution Service Contract
TERMINOLOGY CHANGES
English (United Kingdom)
20
INTRODUCTION
Contract Set-Up / Early Contract
• Early Contractor Involvement
• Early Warning Register
• Scope (drafting points)
Administering the Contract
• Deemed Acceptance
• Programmes
• Payment
• Quality Management
• Compensation Events
End of Contract / Dispute
• Final Assessment
• Dispute Avoidance
SECTION 1: GENERAL
English (United Kingdom)
22
• The Scope may now specify the use of a particular communication
system. PM to ensure it follows any specified system.
• In relation to Contractor communications to be accepted by the PM, if
the PM does not accept it now has to state the reasons ‘in sufficient
detail to enable the Contractor to correct the matter’.
• If the PM or the Supervisor delegates an action under clause 14.2, the
notification must now ‘contain the name of the delegate and the details
of the actions being delegated or any cancellation of delegation’.
Communications (Clause 13 & 14)
English (United Kingdom)
23
The Scope should specify:
• a particular communication system (clause 13.2)
• the form of programme to be used (clause 31.2)
• requirements for the quality management system (clause 40.1)
Scope
English (United Kingdom)
24
• PM prepares the Early Warning Register (first within 1 week of the
starting date). See clause 11.2(8) for definition of EWR.
• First Early Warning Meeting held within 2 weeks of the starting date
• Subsequent Early Warning Meetings must be held regularly at ‘no longer
interval’ than stated in the Contract Data
• After each meeting, the PM updates the Early Warning Register to record
any decisions made at the meeting and re-issues within one week
• More generally, early warnings should be given by the Contractor and the
PM of any matter that may increase the Contractor’s total cost.
Early Warning (Clause 15)
English (United Kingdom)
25
• New clause 16 introduces a value engineering mechanism into the core
clauses.
• The Contractor may make a proposal to change the Scope to make a
saving. The PM has to liaise with the Contractor and the Client about this
and respond within 4 weeks.
• The PM can give any reason for not accepting the proposal.
• In Options A & B there is an incentive for the Contractor to make such
proposals (clause 63.12). The Contractor’s share of the cost saving is
calculated by reference to the “value engineering percentage” stated in
the Contract Data.
Contractor’s Proposals(Clause 16)
SECTION 2: CONTRACTOR’S MAIN RESPONSIBILITIES
English (United Kingdom)
27
• Appointment of a sub-contractor is now subject to the PM
accepting both the sub-contractor and the sub-contract
documents unless:
– The proposed sub-contract is an NEC Contract which has
not been amended other than in accordance with the
additional conditions of contract or
– The PM has agreed no submission is required
PM needs to be aware of amendments to proposed sub-contract
Sub-contracting (Clause 26)
SECTION 3: TIME
English (United Kingdom)
29
PROGRAMME
• If a
programme is
not identified
in the Contract
Data, the
Contractor
submits a first
programme to
the PM within
the period
stated in the
Contract Data
• Within 2 weeks
of submission
the PM notifies
the Contractor
of acceptance
or reasons why
it is not
accepted.
• If the PM does
not notify
acceptance or
non-
acceptance
within time
allowed,
Contractor can
notify PM of
failure
• If the PM still
fails to
respond for a
further 1 week
after
notification,
the
programme is
deemed
accepted.
• The consequences
of the Contractor
failing to submit
an acceptable
programme remain
the same – money
deducted from
interim payments.
No programme?
Deemed acceptance
Contractor to notify failure
PM’s Response
Submission
English (United Kingdom)
30
• Either party (Contractor or PM) can now propose acceleration
• Re-draft of clause so that a general agreement is now reached between
the PM and the Contractor in relation to acceleration in principle (rather
than PM instructing a quote to be provided only to find that the
Contractor does not want to accelerate)
• New timescale - the Contractor has three weeks to provide a quotation
and the PM must reply within a further three weeks
Acceleration (Clause 36)
SECTION 4: QUALITY MANAGEMENT
English (United Kingdom)
32
• New requirement in ECC (reflects the Professional Services Contract)
• Contractor must maintain quality management system stipulated in Scope
• Contractor provides the PM with (1) a quality policy statement; (2) a
quality plan (within the time stated in the Contract Data) for acceptance
• If Contactor fails to comply with the quality plan, the PM can instruct it
to do so. This instruction would not be a compensation event.
Quality Management (Clause 40)
SECTION 5: PAYMENT
English (United Kingdom)
34
• Application for payment is a must (clause 50.2 & 50.4)
• If no application, the sum due is the lesser of:
– the amount the PM assesses as due; and
– The amount due at the previous assessment.
(opportunity for a negative assessment by the PM)
• Certainty of Defined Cost – clause 50.9 – see flow chart
– Rolling process of review and verification
– Significant point for PM
PAYMENT
English (United Kingdom)
35
Certainty of Defined CostCLAUSE 50.9 OPTIONS C - F
• Contractor
decides when
Defined Cost is
ready to be
submitted
• Contractor
notifies PM
when each
part has been
finalised and
make records
available for
PM’s review
• PM take lead
in reviewing
• PM can accept
the costs,
request more
detail or notify
errors
• PM must
respond within
13 weeks of
submission
• Contractor
required to
submit any
further
information
required
within 4 weeks
or PMs
request.
• PM has a
further 4
weeks to
review and can
either: accept
costs as
correct, or
notify the
Contractor of
the correct
assessment of
that part of
Defined Cost.
• If the PM fails to
respond within the
time stated, the
Contractor’s
assessment will be
treated as correct.
Treated as correct
Further review by PM
Re-submission by Contractor
Review by PMSubmission by Contractor
English (United Kingdom)
36
Finality of assessments(CLAUSE 53) – New full provision
• The PM assesses and
certifies a final
payment, if due, within
a specified period
following issue of the
Defects Certificate or
termination certificate
• The Contractor may
issue its own
assessment of the final
amount due if the PM
fails to do so within
the required time
period
• The assessment is
conclusive as to the
final amount due
unless either party
invokes the dispute
resolution procedures
in clause 53.3 within
the required
timescales.
CONCLUSIVITYCONTRACTOR ASSESSMENT
PM ASSESSMENT
English (United Kingdom)
37
Schedule of Cost Components & Fee:
• All contracts include SCC – used to assess Defined Cost
• SSCC removed from main options C, D & E (just one SSC)
• Subcontractors – Defined Cost is cost paid, not actual cost
• Working Areas Overhead removed and items paid as Defined
Cost
• SSCC used in main options A&B and adopts pre-priced
approach for people. People overhead removed
• Only one fee percentage (sub-contracted fee percentage has
been scrapped)
PAYMENT
SECTION 6: COMPENSATION EVENTS
English (United Kingdom)
39
• New CEs:
– payment for producing quotations that are not instructed
(clause 60.1(20)) – the PM will need to assess the cost of
this work;
– additional CEs can be listed in Contract Data (clause
60.1(21))
COMPENSATION EVENTS
English (United Kingdom)
40
• Notifying CEs – 1 communication (not 2)
• Introduction of ‘dividing date’ (clause 63.1)
– date on which forecast Defined Cost switches to
actual DC
– Programme for assessing delay is that which is
current on the dividing date
• Proposed instructions – consolidated in clause 65
Compensation Events
RESOLVING AND AVOIDING DISPUTES
English (United Kingdom)
42
• Options - W1 and W2 remain but with amendments, new Option W3
– W1 (Construction Act does not apply) – Senior Reps, adjudication,
tribunal
– W2 (Construction Act does apply) – Senior Reps and/or adjudication,
tribunal
– W3 (Construction Act does not apply) – Dispute Avoidance Board (DAB),
tribunal
PM will be the party who briefs the Senior Reps or the Dispute Avoidance
Board and who will need to effect any decisions made
Resolving and Avoiding Disputes
English (United Kingdom)
43
• New Option W3 in the ECC only, to appoint a standing Dispute Avoidance
Board (DAB) as an alternative to adjudication.
• This is primarily designed for use on major international projects where
dispute adjudication boards and increasingly, dispute avoidance boards,
are a common feature.
• The DAB consists of 1 or 3 members who are appointed at the start of the
project.
• The DAB makes regular visits to the project site so that it is familiar with
the project before a dispute arises.
Resolving and Avoiding Disputes Dispute Avoidance Board (DAB)
English (United Kingdom)
44
• If the parties are not able to settle the potential dispute with the DAB’s
help, the DAB provides a non-binding recommendation for resolving it.
• The DAB process is mandatory if option W3 is selected. A dispute cannot
be referred to the tribunal (courts or arbitration) for final determination
unless it has first been referred to the DAB.
• The parties may accept the recommendation of the DAB. Alternatively, if
either party is dissatisfied with the recommendation, it must give notice
of intention to refer the dispute to the tribunal within four weeks of the
date the DAB notifies its recommendation.
Resolving and Avoiding Disputes Dispute Avoidance Board (DAB)
SECONDARY OPTION CLAUSES
English (United Kingdom)
46
New secondary option X22 – introduces ECI for Options C&E of EEC
Benefits perceived as:
• Reducing tender costs
• Shorter project timescales
• Allowing early identification, management / mitigation, allocation and
pricing of risks
• Encouraging collaboration across project team
• Enabling client to retain control of project during early stages
Where this secondary option is selected, it will have a significant impact on
the role of the PM at procurement stage.
Early Contractor Involvement
SUMMARY OF CHANGES
English (United Kingdom)
48
There should be no fundamental issues with clients moving from NEC3 to
NEC4.
However, the areas that will continue to cause difficulty are:
The Project Manager not operating the contract mechanisms properly - The
PM has a central role in administering the ECC and it is critical that the PM
understands the NEC philosophy and has the skills and resources to fulfil the
duties required. PMs need to ensure they are fully familiar with the changes
(some timescales which could cause issues).
Incomplete or inaccurate Scope - It is critical that the Scope is complete and
accurate, especially since the Contract does not address how inadequacies
(as opposed to ambiguities / inconsistencies) in the Scope are to be handled
Summary
English (United Kingdom)
49
KENNEDYS - GLOBAL
English (United Kingdom)
50
CONSTRUCTION CONTACTS
Sarah MaylorPartner
Sheffield & London
T: +44 114 253 2050
M: +44 7584 471 888
James ShawPartner
London
T: +44 20 7667 9275
M: +44 7775 918 438
Helen JohnsonSenior Associate
Sheffield
T: +44 114 253 2052
M: +44 7584 471 889