24
NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist – Olsson Associates

NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Embed Size (px)

Citation preview

Page 1: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

NDEQ Industrial Storm Water

General Discharge PermitPresentation for: Nebraska Aviation Symposium

January 27, 2011

By: Bill Imig, Environmental Scientist – Olsson Associates

Page 2: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Permit Applicability

• Sector S- Air Transportation Facilities

• SIC codes 4512-4581

451 Air Transportation, Scheduled, and Air Courier Services

4512 Air Transportation, Scheduled

4513 Air Courier Service

4522 Air Transportation, Non-scheduled

4581 Airports, Flying Fields, and Airport Terminal Services

Page 3: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Covered ActivitiesStorm water discharges from those portions of the air

transportation facility that are involved in: • Aircraft maintenance – includes rehabilitation, mechanical

repairs, painting, fueling• Equipment cleaning• Deicing operations

Page 4: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Activities Not Allowed under the Permit

• Discharges of wash water

• Discharges of deicing chemicals during dry weather

Page 5: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

No Exposure Certification• All industrial materials and activities are protected from

exposure to rain, snow, or runoff• Industrial materials or activities include:

– Material handling equipment– Industrial machinery– Raw Materials– Products (Fuel, Oil, etc)– Waste Products

• Exceptions– Drums, Barrels, Tanks that are sealed and not leaking– Adequately maintained vehicles used for material handling

Page 6: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

No Exposure Checklist• Using, storing or cleaning industrial machinery or

equipment or areas where residuals from industrial machinery or equipment remain and are exposed to storm water

• Materials or residuals from spills exposed to storm water• Materials or products from past industrial activities• Material handling equipment (except adequately

maintained vehicles)• Materials or products during loading/unloading or

transporting activities

Page 7: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

No Exposure Checklist• Materials or products stored outdoors (except products

intended for outdoor use where exposure to storm water does not result in discharge of pollutants

• Materials contained in open, deteriorated or leaking storage drums, barrels, tanks and similar containers

• Materials or products handled/stored on roads or railways owned or maintained by the permittee

Page 8: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

No Exposure Checklist• Waste materials (except waste in covered, non-leaking

containers (dumpsters)

• Application or disposal of process wastewater

• Particulate matter or visible deposits of residuals from roof stacks and or vents not otherwise regulated (under an air quality permit) and evident in storm water

Page 9: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

2011 Draft Permit

• Replaces existing permit first issued 1997

• NDEQ will hold a public hearing February 22, 2011

• Final permit target date is April 1, 2011

• Most Significant Changes– T&E Species Impact Evaluation for New or Expanded

Dischargers– Impaired Waters, Class A, Class B– Discharge Monitoring (Visual and Benchmark)

Page 10: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Implementation Timeline

Will be pushed back pending issuance of the permit

Source: NDEQ

Page 11: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Limitations on Coverage

• Non-storm water discharges

• T&E Species and Critical Habitat Protection

• New or Expanded discharges to Impaired Waters, Class A

and B Resource Waters, Drinking Water Supplies

Page 12: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Allowable Non-Storm Water • Allowable non-storm water discharges

– Fire fighting– Fire suppression system flushing– Potable water line flushing except chlorination– Condensate from air conditioners, coolers, etc.– Irrigation drainage from agricultural lands– Landscape irrigation w/ approved application of fertilizer, etc.– External building wash down without detergents– Groundwater and spring water– Foundation drains if not contaminated with process water– Windblown mist from cooling towers

Page 13: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

T&E Species Evaluation

• If you are a new or expanded discharger coverage

under general permit is only available if storm

water does not adversely impact listed species and

habitat.

• NDEQ has prepared a 9 point checklist to

determine if discharge has potential to impact

T and E Species.

Page 14: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Impaired, Class A &B, and Drinking Water Supply

• New or Expanded Discharge to Impaired Water

– Meet TMDLs if established

• New or Expanded discharge to class A – not eligible under the general

permit

• New or Expanded discharge to class B – prior written approval from

NDEQ

• New or Expanded discharge to Drinking Water – prior written approval

from NDEQ

Page 15: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Source: NDEQ

Impaired Waters

Page 16: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Class A & B State Resource Waters and Drinking Water

Source: NDEQ

Page 17: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Benchmark Monitoring

• Deicing Season- Collect samples during timeframe under which deicing activities occur (usually October – April)• At all Outfalls that collect runoff from deicing areas• Collect 4 separate samples during deicing season

Source: NDEQ

Page 18: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Benchmark Monitoring Results

• If average of first 4 values < benchmark – done sampling

for permit term

• If average > benchmark need to reevaluate BMPs &

controls. Make revisions and continue monitoring

• Or determine no further reductions are economically

practicable or achievable and notify NDEQ

Page 19: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Contents of SWPPP

• Pollution Prevention Team

• Site Description – locations, activities, drainage, outfalls, etc.

• Site Map – submit copy to NDEQ with NOI

• Identify Potential Pollutants – Materials storage, Operational

Activities that are exposed to storm water

• Control Measures

• Schedules and Procedures

• Documentation

Page 20: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Schedules and Procedures - Controls

• Good housekeeping schedule

• Maintenance procedures schedule

• Spill prevention and response

• Training

Page 21: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Schedules and Procedures – Monitoring and Inspections

• Benchmark Monitoring – Seasonal during deicing operations

• Visual Assessment of Storm Water discharge– At least Quarterly

• Routine Inspections – Monthly during deicing season (usually

October – April)

• Comprehensive Inspection – Annual (during periods of deicing

operations if possible)

Page 22: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Documentation• T&E species evaluation

• Discharge to Impaired or State Resource Water

authorization

• NOI

• NDEQ acknowledgment letter

• Best Management Practices

• Inspections

• Reports

• Corrective Action

• Monitoring Results (visual , benchmark)

Page 23: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Reporting• Non-compliance which may endanger health or

environment within 24-hours.

• Corrective Action – record within 24 hours, document

actions within 14 days, report to NDEQ in 30 days

• Spill / Release reporting (per Title 126, Ch. 18)

• Upon NDEQ request

Page 24: NDEQ Industrial Storm Water General Discharge Permit Presentation for: Nebraska Aviation Symposium January 27, 2011 By: Bill Imig, Environmental Scientist

Questions?