2
NONCONFORMITY REPORT for Construction (NCR) SADARA MFC Project NCR NO. NCR –TCC- MECH-0012 DATE 02 JUNE 2013 PROJECT NO. Supplier / Dept. DWG/REV. NO or REFERENCE SPECIFICATION As per RT8 S-6500-01 P.O No. / ITEM No. LOCATION E-W MAIN PIPE RACK COLUMN INSP.SHEET/ CHECK LIST NO. NONCONFORMITY :During surveillance at site on 02 June 2013 ,it was noted that TCC welder (welder ID NO 51) Was welding without proper wind protection. This violation is already entered in the log book Dated 02 MAY 2013. Attachment : DISPOSITION : □ Re-grade □ Repair □ Rework □ Reject Use-As-Is CONTRACTOR Issued by : Date & Signature: Reviewed by: Date & Signature : Approved by : Date & Signature: ROOT CAUSE : CORRECTIVE ACTION PLAN BY SUBCONTRACTOR : Attachment : Prepared by : Date & Signature: Reviewed by : Contractor QC Engineer Approved by : Contractor QC Manager COMPLETION DUE DATE : APPROVED BY CONTRACTOR FOR CORRECTIVE ACTION PLAN : Approved by Contractor SQCM : Date & Signature : PREVENTIVE ACTION : Prepared by : Date & Signature: Reviewed by : Contractor QC Engineer Approved by : Contractor QC Manager VERIFICATION OF IMPLEMENTATION BY CONTRACTOR : □ ACCEPT REJECT OTHERS

NCR FORM(rev 3).docx

Embed Size (px)

Citation preview

NONCONFORMITY REPORT for Construction (NCR)SADARA MFC Project

NCR NO.NCR TCC- MECH-0012DATE02 JUNE 2013

PROJECT NO.Supplier / Dept.DWG/REV. NO or REFERENCESPECIFICATIONAs per RT8 S-6500-01

P.O No. / ITEM No.

LOCATIONE-W MAIN PIPE RACK COLUMNINSP.SHEET/CHECK LIST NO.

NONCONFORMITY :During surveillance at site on 02 June 2013 ,it was noted that TCC welder (welder ID NO 51) Was welding without proper wind protection. This violation is already entered in the log book Dated 02 MAY 2013.

Attachment :

DISPOSITION : Re-grade Repair Rework Reject Use-As-Is

CONTRACTOR Issued by : Date & Signature: Reviewed by: Date & Signature : Approved by : Date & Signature:

ROOT CAUSE :

CORRECTIVE ACTION PLAN BY SUBCONTRACTOR :

Attachment :

Prepared by : Date & Signature: Reviewed by : Contractor QC Engineer Approved by : Contractor QC Manager

COMPLETION DUE DATE :

APPROVED BY CONTRACTOR FOR CORRECTIVE ACTION PLAN :

Approved by Contractor SQCM : Date & Signature :

PREVENTIVE ACTION :

Prepared by : Date & Signature: Reviewed by : Contractor QC Engineer Approved by : Contractor QC Manager

VERIFICATION OF IMPLEMENTATION BY CONTRACTOR : ACCEPT REJECT OTHERS

INSPECTED BY : APPROVED BY : CONFORMED :Inspector: Date & Signature : Contractor SQCM: Date & Signature : Company QR: Date & Signature: