31
COURSE-NCP 30 ASSIGNMENT COURSE TITLE Site Organisation and Management

NCP 30 - Site ion and Management

Embed Size (px)

Citation preview

Page 1: NCP 30 - Site ion and Management

COURSE-NCP 30

ASSIGNMENT

COURSE TITLE

Site Organisation and Management

Page 2: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

ASSIGNMENT

1. Course No. - NCP 30

2. Course Title - Site Organisation and Management

3. Assignment No. - Four

4. Date of Dispatch - _____________________________

5. Last date of receipt of Assignment - _____________________________

At CODE office

ASSIGNMENT

Your company has been awarded a prestigious contract of building 500 m

length pre-stressed concrete bridge on a national highway crossing the major river.

Due to cultivation on both sides of highway, very restricted space of only 100 M in

width and 300 m in length is available on both sides of highway.

To mobilize the site, your management asked you to house 350T of cement,

300T of steel, 2 size II crawlers – Tractor Dozer, one mobile crane, one JCB, ten

dumpers. Labour force of 100 men n addition to site office complete with

communication set up.

Discuss your plan to organize the site, draw lay out sketch showing all details.

Wind direction is from West to East and Bridge direction is East to-West.

Page 3: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

PRE - MOBILIZATION STUDIES: -

Once the contract is signed by the company, the project execution would start. A

detail plan for mobilization is prepared and manpower as well as plant and equipment

allocation is forecasted and provision is made for the same. As a handing over of a

site and other formalities such as bank guaranties, mobilization advance would take

place in due course, the time required to complete this formalities would be use foe

the project study, take of f plan and organizing the site mobilization.

Page 4: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

SITE ORGANISATION CHART: Sit

PROJECT MANAGER

SR. EXECUTION ENGINEER

ADMIN. INCHARGE

JR. SERVICES ENGINEER

JR. BILLING ENGINEER

JR. ESTIMATION ENGG.

SUPERVISORS EXECUTION INCHARGE

ESTIMATION ENGINEER

ACCOUNT & BILLING ENGINEER

SERVICES MANAGER

ELECTRICIAN

JR. QA /QC ENGINEER

QA /QC ENGINEER

JR. PLANNING ENGINEER PLANNING & COORDINATION ENGINNER

RESIDENT ENGINEER / GENRAL PROJECT MANAGER

STORE MANAGER

ADMIN. ASST.

SAFETY & HEALTH DEPT.

STORE ASST. MECHANIC

JR. SAFETEY ENGG.

SAFRTY ASST.

PLUMBER.

Page 5: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

Depending upon the nature of work, category of work, size & stages of completion of

work organize site staffing appropriate manner is very important. Due to there is a

involvement of much more agencies like client / owner, consultant, subcontractor,

vendor / supplier, local authorities, traffic problems on highway we need proper co-

ordination, involvement, good understanding amongst all project team.

1. Project manager: As shown in organization chart project manager is leader

for all activities and effective communication system. Resident engineer is

reporting to the project manager.

2. Resident engineer: The resident engineer is support to the project manager but

all functional in charge / heads of all departments is directly reporting to the

resident engineer. The main scope of resident engineer is to keeping co-

ordination in all the staff, site related person, subcontractor, consultant, and

supplier.

Following diff department works under supervision of resident engineer.

3. Planning dept.:

Responsibility - Plan each and every work activity as per time limit given by

the client making bar chart material schedule, making labor schedule, making

plant, machinery schedule, achieving better quality in min cost is the main aim

of this dept.

Personnel structure & reporting system – Jr. planning engineers also

appointed for helping planning engineer and make, design basic plans, ideas

and reports to planning engineer.

Page 6: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

4. Execution dept.:

Responsibility – Execution of work as per drawing plans and specification is

main work of execution dept. In this department Sr. execution engineer and

gang of Jr.Engg. is appointed.

Personnel structure & reporting system - In execution department jr. engineer,

supervisor under inspection of sr.execution engineer does checking of work

progressing on site. Sr. engineer reports to execution manager.

5. Store dept.:

Responsibility – Inspection of material and goods coming on site, intimate or

instruct to respective dept. (material ordered by) maintaining material inward,

outward registers making GRN, storing and housing all material on site in

proper place as per the site condition and handover material to contractor as per

their requirement, keeping their records is the main work of store dept.

Personnel structure & reporting system - In this dept store manager is the

head of our site and storekeeper and store asst. will help and report to store

manager.

6. Quality dept.:

Responsibility – Checking of all material coming on site ,testing of all the

material as per requirement ( lab test ) Making or verifying mix design of

material going to use for site execution ,inspection and checking of all activities

of execution work regarding quality norms and condition, testing of work

executed like sample testing ( cube testing ) non destructive testing making of

Page 7: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

audit report maintaining material testing, mix design, concrete testing, audit

test registers on site is the main work of this dept.

Personnel structure & reporting system - Quality engineer is the head of this

dept. Jr. engineer and quality assistance will help to Quality engineer.

7. Quantity surveying dept.:

Responsibility – Checking of all drawing and specification regarding site,

estimating and surveying quantity of each work activity separately, calculating

material required quantity, labor required quantity for each and every item is

the main work of this dept.

Personnel structure & reporting system - Quantity estimation engineer is the

head of this dept. Jr. engineer will help to estimation engineer. All basic plans

and calculation Jr. engineer make and report to sr. engineer under supervision

of estimation engineer.

8. Account / Billing dept.:

Responsibility – Checking of all bill quoted by sub contractor or contractor

(R.A. bills or final bills) as per their site executed work, making of payment of

contractors and subcontractors is the main work of billing dept.

Keeping total money expenditure regarding site, checking of departmental

labor bill making payment of all site office related staff and helper is the main

work of account dept.

Personnel structure & reporting system - Billing engineer is the head of this

dept. Jr. billing engineer will help to billing engineer. All bills primarily

Page 8: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

checking with execution engineer making changes as per Jr. Engineer does

requirement. In account dept. one Jr. Accountant help to account in charge.

9. Services Dept.:

Responsibility – Our site is huge type of construction therefore there is

requirement of no of services delay due to absence of any services is very

dangers. Arrangement of electrical supply, water supply, making or repairing of

any construction equipment and machinery, electrical equipment, is the main

work of this dept.

Personnel structure & reporting system - Quantity In this dept. all types of

skilled workers and supervisor like plumber, electrician, mechanic, welder, is

working under supervision of Jr. Engineer and Jr. Engineer is directly report to

the services engineer.

10. Safety and health Dept.:

Responsibility – Making safety working environment, safety all site worker

and staff, improving and applying all safety instruction on site is the main work

of this dept. Cleaning of site office maintains and cleans all site awareness,

cleaning of labor camp periodically, making arrangement of good drinking

water, good latrine / w.c. Facility on site is the main work of health dept.

Personnel structure & reporting system - Safety engineer and Jr. Safety

engineer’s work as per site condition and safety supervisor help to Jr.engineer.

Page 9: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

11. Administration Dept.:

Responsibility –Supervision and arrange all site office requirements/

facility’s, supervision on site security guards, checking there registers, keeping

site off inward and outward is the main work of this dept. Admin. In charge

and there asst. are responsible for this work.

Project Communication

2.1 INTRODUCTION

The performance of any project can be evaluated from the daily reports

and other correspondence, that it maintains. Well framed reporting systems

serve as an effective tool of information, which if compiled, documented and

analyzed, provides a record on the project for 'future reference.

The management can adopt certain systems to control the progress of a

project. The documentation required, acts as an effective tool of control over

the overall performance of every individual, from the engineer, the site staff,

consultants to the architect, involved in these systems. The procedure for

documentation of the in-house and outside correspondence, at different stages

of work, is standardized, In this chapter we discuss some of these procedures

and the methods of correspondence, that facilitate the working and help gain

overall control over the staff and systems.

2.2 PROJECT COMMUNICATION WITH HEAD QUARTER

- All correspondence is related to the progress of the site work.

- Correspondence from the site to Head Office is an important

communication channel for the senior management.

- The required frequency of reports and the correspondence from the site

to Head office is directly proportional.

- Daily correspondence

- Fortnightly correspondence

- Monthly correspondence

Page 10: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

DAILY CORRESPONDENCE

- This is the day to day reporting to the Head Office by the Project Engineer or

site in-charge.

- The Project Engineer should leave the site, half an hour prior to the closing

time for reporting to the Head Office.

- If many sites are in progress, all site engineers, reporting to the Head Office,

should note down the time of their respective reporting and departure.

- The documents should be collected in their respective site trays at the H.O.

(1) D.P.R. (DAILY PROGRESS REPORT)

(Refer Format No. 1.1)

- It is a very important report.

- It is in a tabular format, indicating the actual work completed at the site on a

particular day, the quantity of cement bags consumed per building and the

ratio of cement bags/sq.m.

- D.P.R. of the previous day should be written and submitted immediately on

the next day.

- Work program of each building, for the next day, should be written separately.

- The arrival time of the contractor's labour and the departmental labour is noted

separately.

- Every D.P.R. must carry the name of the site, date and should be duly signed

by the senior engineer and the Project Engineer.

- The D.P.R. is a tool for the higher authorities / Chief Engineer to check the

activities of the day.

(2) MATERIAL INWARD REPORT

(Refer Format No.1.2)

- This report deals with the opening and closing balance of cement, empty bags,

sanla, lime, blocks etc.

- It gives information of all the materials received and is attached with the

challans from suppliers.

- Supplier's challan should contain the following information

Page 11: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

- Supplier's name

- Challan number

- Date

- Site

- Site stamp with the storekeeper's signature

- Quantity of material! measurement of truck

- Time

- Signature of the driver

- Name, class, type, quality and quantity of the materials received

- On every challan, the measurement of the truck, receiving time and the vehicle

number must be noted.

- The challan for the material received, should be stamped on the other side,

along with the Project Engineer's signature.

- It makes records of all material received. Material transferred from site to site

can also be noted with the IO.C. No. and the M.T.R. No.

(3) M.T.R. (MATERIAL TRANSFER RECEIPT)

(Refer Format No. 1.3)

It is the receipt for any material transferred from one site to the other. It notes down

the quantity along with the S.R.P. (Stock register page) No. and the M.T.R. No.

(4) MATERIAL ISSUE SLIP

- This slip is used by the site engineer/supervisor for issuing materials to the

contractor / departmental labourer from the store.

- The storekeeper must not issue any material without the material issue slip.

The Engineer must carry an issue slip book with him while on site.

- The material issue slip has the following advantages

- It helps control all work activities, since every material is issued by the

engineer. Materials can be utilized properly.

Page 12: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

- Entry of the personnel in the store can be controlled.

- Material reconciliation for a particular work in a particular building

can be done. Signature of contractor /representative confirms the

acceptance of materials.

(5) DAILY STORE CONSUMPTION REPORT

(Refer Format No. 1.5)

- It notes the material issued to the contractor along with the date, particulars,

quantity and the building where it is used. It also gives details like who issued

it, to whom and the S.R.P. No.

- This report should be kept at the site along with the original issue slip.

- It is to be written by the storekeeper.

- It is useful in record updating and reporting to the Head office.

(6) DAILY (DEPARTMENTAL) LABOUR SLIP

- This report records the details of labourers, directly appointed by the company

as departmental labourers. These details are recorded by the supervisor.

- The Engineer should check the sites where these labourers work.

- The report gives self explanatory description of the work done by the

departmental labourers along with their designations. It should be signed by

the site engineer and the Project Engineer.

- The report enables in the verification and preparing of the weekly cash bill of

departmental labour.

(7) MEMO DETAILS

- Avoid issuing a memo to contractors. If at all it is to be written ensure that it is

signed by the contractor and is forwarded to Head office for necessary action.

- Memo notes can be sent to contractors for deduction of payment from his bill,

for reasons like non-fulfillment of work as per the agreement, failure in

maintaining the work schedule, wastage of material or instructions regarding

the program of work, improvement in quality etc.

Page 13: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

- It should be sent in duplicate to the Head Office.

- After the Chief Engineer signs the memo, a copy should go to the contractor

and the other to the respective division for necessary actions.

WEEKLY CORRESPONDENCE

(1) CASH BILLS

- Cash bills should be submitted to the Head Office every week on pre-arranged

day.

(2) SETTLEMENT OF ACCOUNTS

- On account' money can be given to the site engineer depending on the

expenses that might be incurred during the coming week.

- Cash voucher receipt (Refer Format No. 13.10) should be made with complete

narration and supporting documents. It should be forwarded to the Head

Office on a pre-arranged day and should be adjusted against the imprest

amount.

(3) INDENT (REQUISITION)

Indent is a printed format to raise demands for materials required at the site.

It can be submitted twice a week to the purchase department through the Chief

Engineer.

(4) PENDING INDENT

- Pending indents are re-submitted when the material for indents submitted

earlier has not been received, nor has the information regarding their supply

been received from the purchase department.

- They should be submitted on a fortnightly basis.

FORTNIGHTLY REPORTING

- Submit updated RA. bills every fortnight to the Head Office.

Page 14: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

- RA. bills could be a labour bill for RC.C., masonry, tiling, plumbing etc.

- Customer enquiry report should be submitted every 15 days to the sales

department.

MONTHLY REPORTING

The site should send the following reports to the Head Office every month on a fixed

day.

(1) MONTHLY MATERIAL CONSUMPTION REPORT

- This statement records the total material consumption during a particular

month and sent to the Head Office for verification.

- IT gives an idea of the total receipt, previous balance, updated stock,

consumption during the month, and transfer to other sites etc.

(2) MONTHLY CEMENT CONSUMPTION REPORT

- This report records the opening balance every day, cement received, total

stock, consumption per day, transfer to any other site (+/-), closing stock and

S.RP. No. It is submitted to the Head Office.

(3) ELECTRIC METER READING REPORT

- Every construction site has an electric meter on site.

- Large projects will have more than one electric meter.

- If the bills are more than expected, it might be due to wrong feeding of the

meter reading. Have it cross-checked with the reading noted down by the site

staff.

- Approach the Electricity Board for getting the bill corrected according to the

actual reading.

- This helps in avoiding excess payments for electricity.

(4) WATER METER READING REPORT

- Maintain records for water supplied by the Municipal Corporation.

Page 15: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

- This report helps calculate the total consumption of water at the construction

site for a given month. Also the bills received from the Municipal Corporation

can be cross checked.

- These readings will help calculate the constant of water charges per sq.m/s.ft.

of built-up an for future estimations.

(5) MACHINERY AND INSTRUMENT REPORT

- Construction sites have construction machineries and instruments such as

concrete mixer, lift, vibrator, diesel engine, dumpy level, theodolite etc.

- Ongoing work at different sites can make very difficult to find out the

conditions of machineries at each site.

- Machinery report helps in maintaining all the machines at all times.

- These reports are to be sent to the maintenance division every month, along

with details of the machine, make/type, numbers, H.P., phase condition of the

machines, causes for maintenance, estimated cost of repairs etc.

(6) EXCESS MATERIAL LIST

- Excess material list indicates the material available at the site, not required for

a certain period and time.

- In such cases, the material can be utilized at another site.

- The report should be sent to the purchase department through the Chief

Engineer, to cater to the requirements of another site instead of purchasing

new materials.

(7) CONSTRUCTION PROGRESS CHART

- This report should be prepared every month for each site.

- It records and helps calculate the work progress of each activity, for a

particular building, as a percentage.

- The percentage derived, is based on the average calculation of the estimated

expenses for each activity.

- This chart is very important for the management.

Page 16: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

- The quantum of the work completed during the month, for each site/ each

building, can be justified and total funds used can also be compared and

justified using this chart.

- Over and above this report, a monthly report should be prepared by the Chief

Engineer and forwarded to the Directors.

- It should contain the relevant information regarding the progress of project.

Details of this report are as follows

- It should be submitted by the Chief Engineer on a fixed day, every

month.

- It should include details of all the work completed at the site, during

that month.

- Possession dates should also be given along with this report.

- Reasons for the delay of work, if any, should be mentioned.

- The report should be submitted to the Director to inform him of the

progress of work at the site.

(8) CUBE TESTING REPORT

- Apart from these reports, the site staff should send concrete cubes

taken during concreting work to the testing laboratory for testing

purposes, as and when required.

- Test cubes should be sent with all information.

- Records should be maintained at site and a copy of cube testing report

should be sent to Head Office for office record purpose.

2.3 REPORTING SYSTEM

- The site in-charge should report to the Chief

- Engineer each evening. .

- Site in-charge should leave the site half an hour prior to the closing hour for

reporting to the C.E..

- Apart from this, he should discuss the following aspects of the daily schedule -

Page 17: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

- Progress of work

- The next day's program

- Accidents (if any)

- Visits of the top management.

- Decisions/ drawings required from the architect/ consultants

- Receipt of material, storage and requirement of urgent material (if any)

- Thefts/disputes at the site

- Rejection of materials

- Water /electricity supply failure/machine failure

- Quality of materials

- Any other related points

NOTE:

The site engineer should collect the required certificates/documents during the site

visits of the Architect and submit a copy to the Head Office.

2.4 CORRESPONDENCE FROM SITE TO STRUCTURAL DESIGNER

- For any corrections after checking the working drawings with the RC.C.

drawings, the site incharge should directly contact the structural designer after

informing the C.E.

- The structural designer should be contacted for,

- Checking the strata/trial pit

- Checking the reinforcement before the concreting of slabs

- Checking of reinforcement for O.H.W.T./ U.G.W.T. / septic

tanks/other critical work Queries regarding RC.C. drawings

- Checking the strength and stability of a particular member of the

structure after casting

- For the structural details required for any rectification work

NOTE: The site engineer should collect the required certificates/documents during

the site visits of the RC.C. designer and submit a copy to the Head Office.

Page 18: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

2.5 CORRESPONDENCE TO OTHER CONSULTANTS

(1) ELECTRICAL CONSULTANT

The site in-charge should contact the electrical consultant for,

- Estimation of cabling work/layout and to give requirement of cables

- Checking the layout of LT. room

- During slab concreting

- During road work for electrical conduiting.

- For installation of meter for construction purposes and shifting of meter while

the work is in progress

- To supervise installation of the meter.

- During the development work/street lighting work etc.

- Checking of material specifications

- Checking of work samples

NOTE: The site engineer should collect the required certificates/documents during

the site visits of the consultant and submit a copy to the Head Office.

(2) PLUMBING CONSULTANT

The plumbing consultant should be contacted after receiving all the drawings,

- To discuss practical difficulties of the drawing.

- To show the sample collection of plumbing pipes, fittings and accessories.

- To check and certify water and drainage stacks, details using different testing

methods like pressure testing, smoke testing etc.

- To get the corrections done if any changes occur due to extra amenity/practical

difficulties.

- To check the water supply grid development work, drainage line development

work and storm water drainage work.

- To collect actual measurements on site for preparing record drawings.

- For all queries confirmation from municipal authorities.

2.6 CORRESPONDENCE FROM SITE TO SUBCONTRACTOR

The site in-charge should discuss and enter all the points in the memo book/letter. A

copy should be sent to the Head Office as a record.

Page 19: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

- Progress of work

- Quality of work

- Program of work

- Preparation of RA. bills

- Work out material requirement at various stages and estimates for the

same

- Explanations regarding the drawings

- Confirmation of rates other than given in the agreement

- Extra amenity information (if any)

- Memo/Instruction for bad quality of completed work

- Site cleaning.

- Misuse of material, control of wastage, minor wastage memos

- Misbehaviour of labourers

- Planning of labour hutments and discipline.

- Material stacking at the site by the contractor

- Termination of contract through the Head Office, if required

2.7 CORRESPONDENCE FROM HEAD OFFICE TO SITE

This includes all documents received from the Head Office to the site

- Circulars

- Minutes of meeting

- Issue of drawings and contractor's

- agreements

- Specifications

- Extra amenity debit/credit notes of modifications

- I.O.C. from purchase department

- Copy of cash payment bill

- Work order copies

- Decisions regarding any queries by the site, through higher authorities

- Queries regarding bills, quality report, challans etc. from the account

department

Page 20: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

- Instructions regarding seminars, site visits etc.

- Briefings about new policy matters of the management.

2.8 CORRESPONDENCE FROM H.O. TO SUBCONTRACTOR /

SUPPLIERS

This is includes discussions between the subcontractors and the management for-

- Work speed

- Balance work.

- Quality of work.

- Site meetings.

- Payment status

- Issue of cheques

- Memos for bad quality

- Control of wastage

- Mistakes at site

- Other disciplinary actions

- Work program

- Legal formalities

- Any other problems of the subcontractors

3. LAYOUT

Good site layout is important to improve productivity. You need to arrange

your construction site in such a way as to make it function as efficiently as possible.

With bad layout, time and materials are wasted through double handling.

Transport and handling of materials always cost money. Every time you more a stack

of bricks around your site, the real cost to you increases. One of the reasons for slow

progress and high cost of construction projects is the lack of site planning, including

poor site layout.

Page 21: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

The layout plan of the site will depend upon two main factors: the methods

and sequence of operations to be employed in carrying out he work, and the space

available. The methods and sequence will have been considered at the time that the

estimate and tender were prepared. When the contract is awarded, you should take

another careful look at these ideas before preparing a detailed site layout plan.

These plans must be prepared in advance and they must be prepared by

someone with good planning skills and experience. It is often easier to save money

through planning than by raising site productivity, but these savings can only be

obtained if you take enough time to think about all the possible alternatives before

deciding on how to layout the site.

Contract documents: The contract document for the proposed project is voluminous and contains the

following documents:

a) Notice inviting tender. b) Information and instructions to tenderer. c) General conditions of contract. d) Special conditions of contract. e) Schedule of quantitative and cost.

f) Tender drawings. g) Specification for works.

h) Forms for bank guarantee in respect of earnest money. i) Performance guarantee.

j) Mobilization advance etc. k) Hypothecation deeds for construction equipment.

l) Tender related correspondence and the letter of award/acceptance.

Page 22: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

While the provisions existing in various clauses of the different sections of the

document have their own independent intent, meaning and interpretation, a proper

management of the contract is set up for interpretation of individual clauses in

harmony with others, so that it is in the interest of efficient and timely execution of

work. This is applicable both to the client and the contractor.

For the proposed work, work below ground is allotted as cost plus percentage rate

and for work above ground it is allotted as item rate contract. It is also assumed that

the contract drawn up is fair and equitable and takes into account requirements of

client and possible difficulties that may be experienced by the contractor in his

operations.

SITE CLEARANCE Before setting up of enabling works, it is necessary to make the site clear from various

aspects such as: -

Any stockpile of irrelevant material laid on site.

Any machinery, equipment or vehicle not related to proposed site work.

Plant, vegetation or crops of reasonable height in the proposed site area.

Depending upon the direction of wind mentioned, provision of temporary unit

such as barrier is made on the west side of the bridge to avoid accumulation of

unnecessary dust & rubbish materials.

Removal of small pebbles, sharp edge stones, loose soil material from the

surface of site area.

Demolition of any previous temporary structure present on the site.

CONSTRUCTING INFRASTRUCTURAL FACILITIES

The following infrastructure facilities should be constructed for the proposed

bridge site:

1) Temporary roads should be leveled and a sufficient base course should be

provided to cope with the traffic that is unlikely to use them.

Page 23: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

2) Regular power supply should be made available from the grid passing

nearby Or electric power will have to be generated by installing diesel-

penetrating sets at the site.

3) Water supply can be arranged by providing underground storage tank and

distribution through a pumping system and overhead tank.

For sewage disposal, septic tank should be provided and if it is not sufficient it

may be necessary to provide oxidation pond.

Site camps are erected on site for resident engineers & persons working on

site. These are in the form of light steel or wooden structure, which are mounted on

skid beams or wheels, so that they can be moved as and when required. These are

provided with electrical, plumbing and sanitary fixture, and the system becomes

operational at site by plugging into the electrical and water supply.

The site is also provided with the latest possible communication technology,

such as cellular phone, Internet, intranet, wan etc.

ORGANIZING UTILITIES

All the utilities and resources available on the proposed bridge should be

organized properly so as to avail the maximum benefit.

Storeroom containing ‘A’ class items should be provided by a watchman’s

cabin adjacent to it.

Steel should stacked in open yard, protected by fencing. The utility yard

should be attached to the steel yard by a common fencing.

Aggregates should be stacked as near as possible to the batching plant or

concrete mix, so as to avoid unnecessary movement and double handling of material.

Camp for persons working on site should be located on one side of the site for

avoiding dust and noise, generated on site.

Store rooms:- Store rooms should be constructed in a place where access for

unloading of materials is easier, which leads to safety of the work forces.

Toilets, latrines should be constructed downwind with proper slope for

drainage.

Page 24: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

Specialist shops like steel bender, carpenter, and block makers should be

located/constructed near to their stores or mixer, inside crane radius.

SECURITY :

The proposed bridge site should be secured against possible thefts and damage

causing loss to the governing authority. It should be secured for:

Loss of material, mobile machinery or equipment, at night times or at times

when work is not in progress. 2 nos. of watchmen, each working for a 12-hour shift

will serve for this purpose.

Confidential information prevailing outside the organization: This can be

prevented by storing the confidential data in systems and records, approachable only

to the top management with the M.D. keeping the password key.

All the document, paperwork related to site work should be properly stored in

cupboards under the jurisdiction of a reliable accountant/clerk, acting as a common

person to all the concerned departments.

All the persons working on site, should be well secured against thefts, robbery,

political influence & undue pressure of higher authorities. Also the personnel working

on site should be secured against any sort of mishap or accident, likely to occur due to

negligence of safety conditions.

Reconciliation of materials:

A daily checkup should be done on site specially for the stores, from the

Storekeeper. There are three ways to find out how much money the company is losing

because of damage and deterioration of materials.

a) Looking carefully around the site and checking through the site, usually

shows example of poor placing and storage of materials.

b) Comparing figures given in orders, receipts and issues, and checking of

remaining stocks.

c) Measuring the work done and calculating the materials used.

3

Page 25: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

5. MOBILIZATION :

Departmental Staff: -

i) Before mobilizing staff members like engineers, supervisors and workmen, it

is necessary to construct and prepare proper accommodation such as

residential quarters & workmen’s hut with accurate fencing/boundary wall

around the project.

ii) Security check post should be fixed at gates, with guiding instructions to the

security person for receiving & issuance of men, materials & machinery.

iii) Departmental site office shall be erected at proper location i.e. free from any

noise, dust, easily accessible from all directions of site. Also the location

should not obstruct movement of men, materials & machinery.

iv) The departmental staff should be mobilized at least 3 days prior to

commencement of work & a mandatory visit of the complete site should be

arranged for the entire department (technical & non- technical) so as to get

acquainted with the site area for convenience in working.

v) The departmental staff shall be informed well in advance about the

mobilization date by a formal notice, and on that particular date, the entire

staff shall be mobilized by means of conveyance arranged. i.e. Bus, for people

residing in the range of 100 km. & trains for people exceeding the range of

100 km.

Contractors: i) Contractors should be informed with a formal notice, after the allotment of work

(i.e. Contract) for mobilization of their staff, machineries & other required resources.

ii) It is the duty of contractor to get himself & his resources mobilized well in

advance before the initiation of work i.e. before the actual execution of work starts

i.e. around a week before, so as to avoid inconvenience to the client & the

subcontractors.

Page 26: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

iii) After mobilizing on site physically, he should impart instruction & guidelines to

his staff & sub contractors about the proposed work & thereby the work line of

action. He should also, make his staff well acquainted with the site area & arrange

his machinery in consultation with the client’s engineer so as to avoid unnecessary

wastage of time & materials.

SUBCONTRACTORS:

i) For the proposed work, the contractor has appointed subcontractors related

to various stages of work such as:

Labors for prestressing work.

Labors for placement of tendons.

Labors for casting work.

Labors for disposal of scrap & wastage.

ii) The contractors should arrange the mobilization of subcontractor &

possibly it should be according to his planned mobilization so as to get

himself & the sub-contractors ensured about the adequacy of resources &

information required for the execution of work.

iii) In case of any requirement from the contractor’s side, the subcontractor

should intimate him, well before the work starts so that the contractor will

arrange for it or arrange for a suitable alternative, after consulting with the

clients engineer.

Mobilisation also includes carrying out enabling works, some of which are mentioned

below:

Enabling works

Under works of this category, structures and appurtenants which facilitate undertaking

the actual project work are included. In the Master Control Network and planning for

the project details of enabling work would be included. The extent of enabling work

would vary depending the size and nature of the project. On a large project costing a

Page 27: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

few hundred crores, the enabling work itself could form into a mini- project. The

enabling works would include the following items:

i) Fencing/boundary wall around the project, fixing security check post and gates.

ii) Site Office

iii) Camp for accommodating Engineers, Supervisors, and Workmen.

iv) Store for materials

v) Construction Plant and equipment

vi) Static plant such as concrete batching plant, pre-cast concrete element plant, block

making plant, hot mix plant.

vii) Mobile plant such as Trucks, Dumper, Bulldozer Grader, Vibratory and

pneumatic Road Roller, Bitumen sprayer Transit mixer, Concrete Pump,

Crane, front end loader, compressor. These Plant and Equipment are mobile,

and can be shifted from place to place on regular basis.

Stores and suppliers:

Storage areas should be located near to the static plants. For storage of 350

tons of cement, stacking yards should be covered with shed. But here as the cement is

to be used in large quantity for concreting by batching plant and prestressed element

plant, so it is stored in bulk in vertical silos. Also 300 tons of steel is to be stored

which can be stored in open yards with proper fencing and near to bar bender’s

workshop. Care should be taken that water does not get accumulated in this yard and

there is proper slope to drain the rain water. Stone metal and sand can be stored in

open yards, stacked in heaps with proper fencing so that the material does not gets

mix up with the outer material.

The suppliers in the vicinity of talegaon should be invited on site by a formal

notice and a meeting should be held up with the consultation of clients engineer and

contractor, specifying the suppliers clearly about the following factors:

1. quantity of material.

2. quality of material.

Page 28: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

3. terms and conditions of contract.

4. mode of transportation.

5. delivery at a short notice.

The suppliers should make the above factors clear in a formal quotation and submit it

to the organization. The department will further scrutinize the quotations of various

suppliers and allot the same to the most optimum supplier.

Workshop

For the maintenance of plant and equipment both static and mobile, it is necessary to

have a workshop which will undertake the maintenance, repair, overhauling and

major replacement of equipment. Workshop is geared up to, carry out preventive and

scheduled maintenance which is essential to keep the break-down of equipment to

bare minimum. The workshop should have facilities for servicing, carrying out

general repair, engine over-haul, calibration of Diesel Pump etc. Workshop should

have a small machine shop attached with lathes, drilling machine, welding, boring

machine, painting, denting, sheet metal work etc. It is also to be equipped with auto-

electrical repair, battery charger, tyre repair etc.

QUERIES: For the proposed bridge site near talegaon, certain queries are searched and

found for arranging materials required for the construction of prestressed bridge

such as:

1) At a distance of 10 kms. from the site, strata below the ground i.e. around 3m

below ground is found adequately hard so as to be used as aggregate after

processing it in crushers.

2) Also at a distance of 25 kms. from the site, along the coastal side, natural sand

is available in plenty known as river sand, which is screened and used as

required.

Page 29: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

3) If transportation cost is affordable, then in between Lonavla & Khopoli,

abundant of hard rock, boulder & stones are available, which can be used at

various construction stages of prestressed concrete bridge.

Stores and stacking yards

In the project site, sufficient covered stores or open storage is necessary for

maintaining the material in good condition. Cement is usually supplied in bags, which

is stored at the site in covered shed. The sheds are constructed with brick wall, IPS

floor, tubular structure trusses, roofing with sheets. Bags not exceeding 10 are stacked

one over another. If more than 10 bags are stacked then the lower bags tend to set,

making cement non-usable. In case cement is used in large quantities for concreting

by the batching plant, and pre-cast element plant, is stored in bulk in vertical silos.

The silos are filled up by a pneumatic pump fixed on the cement bulk carrier. From

the silo cement is conveyed into the mixer of the batching plant and pre-cast element

plant, through a screw conveyor.

Services

The site camp is to be provided with services like electric supply, sewage disposal,

communication, telephone. In case regular power supply is available from the grid, it

can be tapped and necessary substation with transformer installed at site. If grid power

is not available then, it may be necessary to generate own power by installing diesel

penetrating se1s at the sets. Water supply can similarly be tapped, if water lines are

passing near by in the vicinity, by providing underground storage tank and

distribution through a pumping system and over head tank. In case water mains are

not available, tube well could be bored for water. Necessary treatment of water to

make it safe for intended consumption will have to be carried out. For sewage

disposal, since the camp is only for a temporary duration septic tank, could be

provided. If it is a large site, and enough land is available, then it may be possible to

provide an oxidation pond for sewage disposal. The effluent from the pond could be

used for horticultural purposes of the site.

Page 30: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

In order to carry out the enabling work which is required at the very initial stage of

the project itself, it may be desirable for the organization, to set up a 'crack team'

which can go in advance to the site and build up all the temporary structures, services

required for the enabling works. This will cut down the time required by the main

project team, on their arrival at the site, and they could embark upon straight-away on

execution of the main project. Such a 'crack team' can move from project to project

for the organization, and they would be well trained in carrying out this activity. On

the other hand, if project team assigned with the main work, is to first build up the

enabling works, a lot of time is lost for the project.

On most international project, and on some major projects within country, of structure

being adopted for the site camp are of portable nature. These are in the form of light

steel or wooden structure, which are mounted on skid beams or wheels, and can be

moved to the camp site, at a very short notice. The Port cabins are provided with

electrical, plumbing and sanitary fixture, and the system becomes operational at site

by plugging into the electrical and water supply. Through the initial cost of the system

may be more but over a period of time it would become economically viable since the

structure can be shifted to site, where as, if the camp is built with conventional

materials. like steel, concrete, the cost would be higher in the longer run, besides the

extra time required to build the Camp.

TRANSPORTATION:

The proposed bridge site is at Talegaon, located 35 kms away from Pune. The

means of transportation are as follows:

i) For staff workers & engineers, not residing on site, a minibus is arranged

by the organization for their daily conveyance.

ii) In case of emergencies, such as fatal accident or injury on site, the

organization has arranged an ambulance in the form of omni-van with

small stretcher laid inside the van.

Page 31: NCP 30 - Site ion and Management

NCP 30 - Site Organisation and Management

[Type text]

iii) For immediate or unexpected requirement of material o site, 2 standby

trucks are arranged for conveyance of material on site from around the

vicinity of 100 kms from site.

iv) For receiving consultants and executives from the nearest terminal, an

automobile such as Scorpio or Qualis is arranged by the organization.

All the expenses required for the above conveyance are added into the total cost of the project as contingencies.

Bibliography/Readings Construction site organization management (NICMAR)