Cofraplus 60 - Composite floor metal decking
110 - Metal Decking
N E001 - Key Plan (Note: All installations should comply with the recommendations contained in MCRMA Techinical Papers N 12 & 14; BS3200 and other relevant national standards)
Metal decking Arval Globalfloor Cofraplus 60 cold rolled steel decking for composite floors
Panel reference Arval Cofraplus
Manufacturer
R
R
ArcelorMittalImmeuble Innovatis, 1-5 rue Luigi Cherubini
La Plaine Saint Denis Cedex 93212FRANCEweb site: www.arcelormittal.com/arval
Please enquire for production capacities from ArcelorMittal Construction in other countries
H008
H010
H005H004
H007
H006
H003
H009
LU1035
Design span length Design span length
Internalsupportbeam
Ex
ternalsupportbeam
Externalsupportbeam
Overhanging edge abutment
Standard edge abutment
Overhangingendabutment
Standardendabutment
Deck cantilever
please consult
Edge trimmer beam
Edge trimmer beam
H012
H011
5/27/2018 NBS-E60-100E (Cofraplus 60)
2/13
110 - Metal deckingProfile referencel Cofraplus 60, 1035mm (France only) & 828mm (other countries) cover widths available
Material ArcelorMittal Construction galvanized grade S 320 G & S 350 G steel sheet to EN10326
Nominal thickness 0.75mm; 0.88mm; 1.00mm & 1.25mm as required to suit load/span requirements of the design
Soffit finish Plain galvanized steel (Z275) to EN10169-3 or Colorissme to standard colour chart is availableon request - please consult our Technical Department
NBS - E60
Cofraplus 60 - Composite floor metal decking
N E002 - Prolile section (Note: All installations should comply with the recommendations contained in MCRMA Techinical Papers N 12 & 14; BS3200 and other relevant national standards)
Overall floor depth 100mm minimum to 280mm maximum
Maximum sheet length 12000mm
Options Cofraplus 60 is also available pre-perforated in the troughs at centers to suit shear studs(Cofraplus 60P) please consult our Technical Department for feasibiliy:-
Cofraplus 60 concrete floor deck
Standard coating
LU 1035
62
101 207
58
Cofraplus 60 concrete floor section
Hilti ENP2 21 L 15 shot fired nails or 5.5mmCofraplus 60 floor deck
Concrete depth minimum 100mm
HMin
Anti-crack mesh
D
58
diameter self drilling screws depending onwind uplift in temporary condition
Cofraplus 60C concrete floor deck
101 207
Alternatively LU 828
Cofraplus 60C concrete floor section
H min = 42mm or 50mm if the slabis acting compositely with a beamor as a diaphragm
Used only as lost shuttering where
no composite beam action required
5/27/2018 NBS-E60-100E (Cofraplus 60)
3/13
NBS - E60
Cofraplus 60 - Composite floor metal decking
N E003 - End detail 1 (Note: All installations should comply with the recommendations contained in MCRMA Techinical Papers N 12 & 14; BS3200 and other relevant national standards)
End bearing 50mm minimum when bearing on concrete or steel, 75mm minimum when bearing on other materials
Edge bearing 50mm minimum
Sealing laps End laps - not necessarySide laps - not necessary
Configuration Mainly double span. In some cases single span (please consult our Technical department)
Attachment As clause 280
Accessories Shear connectors, end & edge closers (1.2mm to 2.0mm), flashings, filler blocks etc
110 - Metal deckingProfile referencel Cofraplus 60, 1035mm (France only) & 828mm (other countries) cover widths available
Material ArcelorMittal Construction galvanized grade S 320 G & S 350 G steel sheet to En10326
Nominal thickness
Soffit finish Plain galvanized steel (Z275) to EN10169-3 or Colorissme to standard colour chart is availableon request - please consult our Technical Department
0.75mm; 0.88mm; 1.00mm & 1.25mm as required to suit load/span requirements of the design
Cofraplus 60 floor deck
End support beam
Dimension X
Min 1.2mm thick edge trim fixed to decking sheet
Restraint straps at 621mm centres
Maximum cantilever (Dimension X) 500mm. Greater cantilevers require temporay propsand additional reinforcement or steelwork brackets connected to the universal beam
Steel stud (19mm with 51mm head) on centreline of beam
58
wind uplift in temporary conditiondiameter self drilling screws depending onHilti ENP2 21 L 15 shot fired nails or 5.5mm
Profile filler to prevent concrete egress
5/27/2018 NBS-E60-100E (Cofraplus 60)
4/13
NBS - E60
Cofraplus 60 - Composite floor metal decking
N E004 - End detail 2 (Note: All installations should comply with the recommendations contained in MCRMA Techinical Papers N 12 & 14; BS3200 and other relevant national standards)
End bearing
Edge bearing 50mm minimum
Sealing laps End laps - not necessarySide laps - not necessary
Configuration Mainly double span. In some cases single span (please consult our Technical department)
Attachment As clause 280
Accessories Shear connectors, end & edge closers (1.2mm to 2.0mm), flashings, filler blocks etc
110 - Metal deckingProfile referencel Cofraplus 60, 1035mm (France only) & 828mm (other countries) cover widths available
Material ArcelorMittal Construction galvanized grade S 320 G & S 350 G steel sheet to En10326
Nominal thickness
Soffit finish Plain galvanized steel (Z275) to EN10169-3 or Colorissme to standard colour chart is availableon request - please consult our Technical Department
0.75mm; 0.88mm; 1.00mm & 1.25mm as required to suit load/span requirements of the design
Cofraplus 60 floor deck
End support beam
Min 1.2mm thick edge trim fixed to decking sheet
Restraint straps at 621mm centres
Maximum cantilever (Dimension X) 500mm. Greater cantilevers require temporay propsand additional reinforcement of steelwork brackets connected to the universal beam
Dimension X
Cantilever dimension
For cantilevers over 150mm additional reinforcement is required
25 minimum from restraint strapfixing to edge of beam
Steel stud (19mm with 51mm head)
20mm minimum from edge of flange to side of steel stud
58
wind uplift in temporary conditiondiameter self drilling screws depending onHilti ENP2 21 L 15 shot fired nails or 5.5mm
Profile filler to prevent concrete egress
50mm minimum when bearing on concrete or steel, 75mm minimum when bearing on other materials
5/27/2018 NBS-E60-100E (Cofraplus 60)
5/13
NBS - E60
Cofraplus 60 - Composite floor metal decking
N E005 - End detail 3 (Note: All installations should comply with the recommendations contained in MCRMA Techinical Papers N 12 & 14; BS3200 and other relevant national standards)
End bearing
Edge bearing 50mm minimum
Sealing laps End laps - not necessarySide laps - not necessary
Configuration Mainly double span. In some cases single span (please consult our Technical department)
Attachment As clause 280
Accessories Shear connectors, end & edge closers (1.2mm to 2.0mm), flashings, filler blocks etc
110 - Metal deckingProfile referencel Cofraplus 60, 1035mm (France only) & 828mm (other countries) cover widths available
Material ArcelorMittal Construction galvanized grade S 320 G & S 350 G steel sheet to En10326
Nominal thickness
Soffit finish Plain galvanized steel (Z275) to EN10169-3 or Colorissme to standard colour chart is availableon request - please consult our Technical Department
0.75mm; 0.88mm; 1.00mm & 1.25mm as required to suit load/span requirements of the design
Cofraplus 60 floor deck
Dimension X
1.5mm thick edge trim fixed to decking sheet
Restraint straps at 600mm centres
Maximum cantilever (Dimension X) 500mm. Greater cantilevers require temporay propsand additional reinforcement of steelwork brackets connected to the universal beam
Perimeter wall
25 Edge trim leaving room for 25mm korkpak joint
Steel stud (19mm with 51mm head) on centreline of beam
58
End support beam
wind uplift in temporary conditiondiameter self drilling screws depending onHilti ENP2 21 L 15 shot fired nails or 5.5mm
Profile filler to prevent concrete egress
50mm minimum when bearing on concrete or steel, 75mm minimum when bearing on other materials
5/27/2018 NBS-E60-100E (Cofraplus 60)
6/13
NBS - E60
Cofraplus 60 - Composite floor metal decking
N E006 - Support detail 1 (Note: All installations should comply with the recommendations contained in MCRMA Techinical Papers N 12 & 14; BS3200 and other relevant national standards)
End bearing
Edge bearing 50mm minimum
Sealing laps End laps - not necessarySide laps - not necessary
Configuration Mainly double span. In some cases single span (please consult our Technical department)
Attachment As clause 280
Accessories Shear connectors, end & edge closers (1.2mm to 2.0mm), flashings, filler blocks etc
110 - Metal deckingProfile referencel Cofraplus 60, 1035mm (France only) & 828mm (other countries) cover widths available
Material ArcelorMittal Construction galvanized grade S 320 G & S 350 G steel sheet to En10326
Nominal thickness
Soffit finish Plain galvanized steel (Z275) to EN10169-3 or Colorissme to standard colour chart is availableon request - please consult our Technical Department
0.75mm; 0.88mm; 1.00mm & 1.25mm as required to suit load/span requirements of the design
Cofraplus 60 floor deck
Internal support beam
Deck to be butt jointed over centreline of beam
Steel stud (19mm with 51mm head)
50mm minimum
25mm minimum from edge of flange to side of steel stud
Steel studs in pairs or staggered where a butt joint occurs
58
Hilti ENP2 21 L 15 shot fired nails or 5.5mmdiameter self drilling screws depending onwind uplift in temporary condition
Profile filler to prevent concrete egressProfile filler to prevent concrete egress
50mm minimum when bearing on concrete or steel, 75mm minimum when bearing on other materials
5/27/2018 NBS-E60-100E (Cofraplus 60)
7/13
NBS - E60
Cofraplus 60 - Composite floor metal decking
N E007 - Support detail 2 (Note: All installations should comply with the recommendations contained in MCRMA Techinical Papers N 12 & 14; BS3200 and other relevant national standards)
End bearing
Edge bearing 50mm minimum
Sealing laps End laps - not necessarySide laps - not necessary
Configuration Mainly double span. In some cases single span (please consult our Technical department)
Attachment As clause 280
Accessories Shear connectors, end & edge closers (1.2mm to 2.0mm), flashings, filler blocks etc
110 - Metal deckingProfile referencel Cofraplus 60, 1035mm (France only) & 828mm (other countries) cover widths available
Material ArcelorMittal Construction galvanized grade S 320 G & S 350 G steel sheet to En10326
Nominal thickness
Soffit finish Plain galvanized steel (Z275) to EN10169-3 or Colorissme to standard colour chart is availableon request - please consult our Technical Department
0.75mm; 0.88mm; 1.00mm & 1.25mm as required to suit load/span requirements of the design
Cofraplus 60 floor deck
Floor decking to centreline of beam
Restraint straps at 621mm centres
Min 1.2mm thick edge trim fixed to decking sheet
Cofraplus 60 floor deck
Edge trim fixed to align with edge of beam
Floor decking with a minimum 50mm bearing
RSA to be wide enough to provide sufficient bearing and allowfixing of deck without fouling top flange of beam above
RSA ledger
58
58
Internal support beam
Hilti ENP2 21 L 15 shot fired nails or 5.5mmdiameter self drilling screws depending onwind uplift in temporary condition
diameter self drilling screws depending onwind uplift in temporary condition
Hilti ENP2 21 L 15 shot fired nails or 5.5mm
Steel stud (19mm with 51mm head) on centreline of beam
Profile filler to prevent concrete egress
50mm minimum when bearing on concrete or steel, 75mm minimum when bearing on other materials
5/27/2018 NBS-E60-100E (Cofraplus 60)
8/13
NBS - E60
Cofraplus 60 - Composite floor metal decking
N E008 - Support detail 3 (Note: All installations should comply with the recommendations contained in MCRMA Techinical Papers N 12 & 14; BS3200 and other relevant national standards)
End bearing
Edge bearing 50mm minimum
Sealing laps End laps - not necessarySide laps - not necessary
Configuration Mainly double span. In some cases single span (please consult our Technical department)
Attachment As clause 280
Accessories Shear connectors, end & edge closers (1.2mm to 2.0mm), flashings, filler blocks etc
110 - Metal deckingProfile referencel Cofraplus 60, 1035mm (France only) & 828mm (other countries) cover widths available
Material ArcelorMittal Construction galvanized grade S 320 G & S 350 G steel sheet to En10326
Nominal thickness
Soffit finish Plain galvanized steel (Z275) to EN10169-3 or Colorissme to standard colour chart is availableon request - please consult our Technical Department
0.75mm; 0.88mm; 1.00mm & 1.25mm as required to suit load/span requirements of the design
50mm minimum when bearing on concrete or steel, 75mm minimum when bearing on other materials
Cofraplus 60 floor deck
Floor decking to centreline of beam
Restraint straps at 621mm centres Min 1.2mm thick edge trim fixed to decking sheet
Edge trim fixed to align with center of beam
RSA to be wide enough to provide sufficient bearing and allowfixing of deck without fouling top flange of beam above
58
Internal support beam
diameter self drilling screws depending onwind uplift in temporary condition
Hilti ENP2 21 L 15 shot fired nails or 5.5mm
Steel stud (19mm with 51mm head) on centreline of beam
Profile filler to prevent concrete egress 25mm minimum from edge of
flange to side of steel stud
Steel stud (19mm with 51mm head) Cofraplus 60C floor deck
wind uplift in temporary conditiondiameter self drilling screws depending onHilti ENP2 21 L 15 shot fired nails or 5.5mm
5/27/2018 NBS-E60-100E (Cofraplus 60)
9/13
NBS - E60
Cofraplus 60 - Composite floor metal decking
N E009 - Edge detail 1 (Note: All installations should comply with the recommendations contained in MCRMA Techinical Papers N 12 & 14; BS3200 and other relevant national standards)
Accessories Shear connectors, end & edge closers (1.2mm to 2.0mm), flashings, filler blocks etc
End bearing
Edge bearing 50mm minimum
Sealing laps End laps - not necessarySide laps - not necessary
Configuration Mainly double span. In some cases single span (please consult our Technical department)
Attachment As clause 280
Accessories Shear connectors, end & edge closers (1.2mm to 2.0mm), flashings, filler blocks etc
110 - Metal deckingProfile referencel Cofraplus 60, 1035mm (France only) & 828mm (other countries) cover widths available
Material ArcelorMittal Construction galvanized grade S 320 G & S 350 G steel sheet to En10326
Nominal thickness
Soffit finish Plain galvanized steel (Z275) to EN10169-3 or Colorissme to standard colour chart is availableon request - please consult our Technical Department
0.75mm; 0.88mm; 1.00mm & 1.25mm as required to suit load/span requirements of the design
50mm minimum when bearing on concrete or steel, 75mm minimum when bearing on other materials
Min 1.2mm thick edge trim fixed to decking sheet
Restraint straps at 600mm centres
Maximum cantilever (Dimension X) 500mm. Greater cantilevers require temporay propsand additional reinforcement of steelwork brackets connected to the universal beam
Dimension X
Cantilever dimension
For cantilevers over 150mm additional reinforcement is required
Steel stud (19mm with 51mm head)
5825mm minimum from edge of
flange to side of steel stud
Hilti ENP2 21 L 15 shot fired nails or 5.5mmdiameter self drilling screws depending onwind uplift in temporary condition
Cofraplus 60C floor deck
Edge beam
5/27/2018 NBS-E60-100E (Cofraplus 60)
10/13
NBS - E60
Cofraplus 60 - Composite floor metal decking
N E010 - Edge detail 2 (Note: All installations should comply with the recommendations contained in MCRMA Techinical Papers N 12 & 14; BS3200 and other relevant national standards)
End bearing
Edge bearing 50mm minimum
Sealing laps End laps - not necessarySide laps - not necessary
Configuration Mainly double span. In some cases single span (please consult our Technical department)
Attachment As clause 280
Accessories Shear connectors, end & edge closers (1.2mm to 2.0mm), flashings, filler blocks etc
110 - Metal deckingProfile referencel Cofraplus 60, 1035mm (France only) & 828mm (other countries) cover widths available
Material ArcelorMittal Construction galvanized grade S 320 G & S 350 G steel sheet to En10326
Nominal thickness
Soffit finish Plain galvanized steel (Z275) to EN10169-3 or Colorissme to standard colour chart is availableon request - please consult our Technical Department
0.75mm; 0.88mm; 1.00mm & 1.25mm as required to suit load/span requirements of the design
50mm minimum when bearing on concrete or steel, 75mm minimum when bearing on other materials
Cofraplus 60C floor deck
1.5mm thick edge trim fixed to decking sheet
Restraint straps at 600mm centres
Dimension required
Steel stud (19mm with 51mm head) centreline of beam
58
Steel stub as designed by engineer
Hilti ENP2 21 L 15 shot fired nails or 5.5mmdiameter self drilling screws depending onwind uplift in temporary condition
Edge beam
wind uplift in temporary conditiondiameter self drilling screws depending onHilti ENP2 21 L 15 shot fired nails or 5.5mm
5/27/2018 NBS-E60-100E (Cofraplus 60)
11/13
NBS - E60
Cofraplus 60 - Composite floor metal decking
N E011 - Edge detail 3 (Note: All installations should comply with the recommendations contained in MCRMA Techinical Papers N 12 & 14; BS3200 and other relevant national standards)
End bearing
Edge bearing 50mm minimum
Sealing laps End laps - not necessarySide laps - not necessary
Configuration Mainly double span. In some cases single span (please consult our Technical department)
Attachment As clause 280
Accessories Shear connectors, end & edge closers (1.2mm to 2.0mm), flashings, filler blocks etc
110 - Metal deckingProfile referencel Cofraplus 60, 1035mm (France only) & 828mm (other countries) cover widths available
Material ArcelorMittal Construction galvanized grade S 320 G & S 350 G steel sheet to En10326
Nominal thickness
Soffit finish Plain galvanized steel (Z275) to EN10169-3 or Colorissme to standard colour chart is availableon request - please consult our Technical Department
0.75mm; 0.88mm; 1.00mm & 1.25mm as required to suit load/span requirements of the design
50mm minimum when bearing on concrete or steel, 75mm minimum when bearing on other materials
Cofraplus 60C floor deck1.5mm thick edge trim fixed to decking sheet
Restraint straps at 600mm centres
Dimension Y
58
Closure plate in 2mm flat steel strip to suit remainder of floor area to a maximum of 245mm
Hilti ENP2 21 L 15 shot fired nails or 5.5mmdiameter self drilling screws depending onwind uplift in temporary condition
Hilti ENP2 21 L 15 shot fired nails or 5.5mmdiameter self drilling screws depending onwind uplift in temporary condition
Edge beam
5/27/2018 NBS-E60-100E (Cofraplus 60)
12/13
NBS - E60
Cofraplus 60 - Composite floor metal decking
N E012 - Hole detail (Note: All installations should comply with the recommendations contained in MCRMA Techinical Papers N 12 & 14; BS3200 and other relevant national standards)
End bearing
Edge bearing 50mm minimum
Sealing laps End laps - not necessarySide laps - not necessary
Configuration Mainly double span. In some cases single span (please consult our Technical department)
Attachment As clause 280
Accessories Shear connectors, end & edge closers (1.2mm to 2.0mm), flashings, filler blocks etc
110 - Metal deckingProfile referencel Cofraplus 60, 1035mm (France only) & 828mm (other countries) cover widths available
Material ArcelorMittal Construction galvanized grade S 320 G & S 350 G steel sheet to En10326
Nominal thickness
Soffit finish Plain galvanized steel (Z275) to EN10169-3 or Colorissme to standard colour chart is availableon request - please consult our Technical Department
0.75mm; 0.88mm; 1.00mm & 1.25mm as required to suit load/span requirements of the design
Min 1.2mm thick edge trim fixed to decking sheet
Maximum cantilever (Dimension X) 500mm. Greater cantilevers require temporay propsand additional reinforcement of steelwork brackets connected to the universal beam
Edge trim leaving room for 25mm korkpak joint
Steel stud (19mm with 51mm head) on centreline of beam
58
Profile filler to prevent concrete egress
Additonal support angle (1.2mm min)where hole size exceeds 500mm
Additonal reinforcement in concrete slabdependent on slab design, hole size & loading
Cofraplus 60 floor deck
50mm minimum when bearing on concrete or steel, 75mm minimum when bearing on other materials
5/27/2018 NBS-E60-100E (Cofraplus 60)
13/13
200 - Fixing decking210 Structure Check that the structure is in a suitable state to receive the decking before commencing fixing.
Subcontractor must confirm acceptance to Main Contractor and CA.
230 Isolating tape Of a type recommended for the purpose by decking manufacturer. Apply to interfaces betweendissimilar metals which would otherwise be in contact.
240 Fire resisting fillers Provided by ArcelorMittal Construction to accurately match decking profile. Length of fillers are equal towidth of supports unless specified otherwise. Fill every profile above specified supports, bonding intoposition with adhesive recommended by ArcelorMittal Construction.
260 Fixing decking Cut sheets to give clean, true lines with no distortion and without damage to any protective coating.Remove burrs and any lubricant. Cut openings in sheets for outlets, vent pipes, flues, etc.to the minimumsize necessary and at locations of minimum stress in service. Reinforce edges of openings with stiffeningpatch, pressed steel angles or structural trimmers depending on size of opening. Drill all holes. Remove alldrilling swarf, dust and any other foreign matter before placing any membranes or insulation. Protectsheets during fixing and up to Practical Completion against mechanical damage, corrosion anddisfigurement. Rectify any defects as quickly as possible to minimise damage and nuisance. Placetemporary support props on suitable base supports to spacing required by design. Ensure props are tight
to u/s of decking but not over tightened so as to deform bottom trough of deck and cross brace if required.
NBS - E60
Cofraplus 60 - Composite floor metal decking
N E013 - Fixings generally (Note: All installations should comply with the recommendations contained in MCRMA Techinical Papers N 12 & 14; BS3200 and other relevant national standards)
280 Attachment Self-drilling, self-tapping screws anti-corrosion coated according to manufacturer's recommendations,or HILTI ENP2 shot fired nails. Fix decking to every support through trough of profile. The number offasteners per trough per support is to be determined by analysis of out of plane and in plane loads againstselected fastener capacity. Provide support to corrugations at periphery including galvanised steel supportcomponents off edge beams as necessary.
282 Attachment The method of attachment of the metal profiled sheet decking floor and accessories must be sufficientto resist the wind loads applied to the floor before pouring the concrete in accordance withBS EN1991-1-4:2005 & A1:2010
290 Cold formed Material: Galvanised steel thickness/gauge: 1.2mm for depths up to 110mm; 1.5mm for depths between120mm & 140mm & 2.0mm for depths greater than 150mm. Finish/Colour to match steel decking profile.
Workmanship as section Z11.
Fix to decking floor support with blind rivets or stitcher screws generally at 300mm centres.
We can also offer supply and installation of 19mm diameter through deck welded shear studsor Hilti X-HVB shear connectors.
Shear connectors, end & edge closers (1.2mm to 2.0mm), flashings, filler blocks etc
Metal accessories