NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
NAWCAD LAKEHURST STATS 11 October 2018
Presented to: Lakehurst Small Business RoundtablePresented by: Dawn Chartier, Deputy Director OSBP
2NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
NAWCAD LAKEHURST TARGETS VS. ACTUALS
FY18 ACTUALS
NAWCAD LKE FY15 NAWCAD LKE FY16 NAWCAD LKE FY17 as of 01 Oct 18
Prime Contracting
Total Dollars 788,908,981$ 1,219,134,318$ 1,419,286,092$ 1,572,372,953$
Small Business 48.967% 46.068% 40.690% 52.549%
Target 43.400% 48.000% 38.000% 38.000%
Dollars 386,306,884$ 561,626,874$ 577,507,258$ 826,273,512$
SMALL DISADVANTAGED BUSINESS 7.558% 6.968% 6.155% 9.337%
Target 9.360% 7.500% 7.000% 7.000%
Dollars 59,625,532$ 84,951,383$ 87,356,900$ 146,809,703$
VETERAN-OWNED SB 10.077% 8.348% 7.999% 8.062%
Dollars 79,497,894$ 101,768,386$ 113,528,262$ 126,767,844$
SERVICE-DISABLED VETERAN-OWNED SB 2.854% 2.361% 3.075% 2.751%
Target 8.500% 3.000% 3.000% 3.000%
Dollars 22,512,475$ 28,781,505$ 43,645,226$ 43,262,821$
WOMAN-OWNED SB 7.855% 8.117% 6.886% 10.067%
Target 7.000% 7.500% 8.0000% 7.0000%
Dollars 61,967,569$ 98,957,881$ 97,725,130$ 158,284,535$
HIST. UNDERUTILIZED BUSINESS ZONE SB 3.206% 1.068% 0.537% 0.678%
Target 1.710% 3.000% 1.200% 1.000%
Dollars 25,293,357$ 13,020,263$ 7,625,321$ 10,668,076$
VOSB has no set target from DoD.
Data derived from FPDS-NG Small Business Achievements by Awarding Organization
3NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• FY18 SBIR/STTR Phase I 706 actions $58,285,309.17
SBIR/STTR Phase II 840 actions $207,817,982.11
Total SBIR/STTR Phase I & II 1,546 actions $266,103,291.28
SBIR/STTR Phase III 296 actions $224,826,784.73
SBIR/STTR STATS
4NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
AIR 4.8 Labs/Capabilities Overview
11 October 2018Presented to: Small Business Round Table
Presented by: Vik Gumber
5NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Core SE & ALRE Science & Technologies
• Electromagnetics – Technologies that improve reliability & maintainability, reduce weight & volume and reduce energy loss and are specifically focused on EMALS/AAG.
• Diagnostics of Avionics – Novel approaches for avionics diagnostics that reduce “false alarm” rates, improve diagnostic coverage, and reduce acquisition and support costs.
• Networks, Information Systems & Intelligent Agents – Enable more rapid and efficient data transmission, providing the right information to the decision-makers at the right time.
• Prognostics & Health Monitoring of Mechanical Systems – Sensors, instrumentation, controls and prognostics algorithms to reduce the maintenance burden for legacy equipment, particularly steam catapults.
• Cameras, Displays, Optics – Develop and transition technologies for improved visual landing aids and improved situational awareness for aviation personnel aboard ships.
• Robotics – Reduce workload on sailors while maintaining safe operations and reducing total ownership cost.
6NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Labs/Capabilities
• SE & ALRE Design and Analysis Lab - Provides rapid response to SE and ALRE related fleet needs through the use of state-of-the-art automated design tools, sophisticated modeling & analysis andrapid prototyping using Additive Manufacturing.
• Fleet Aviation Maintenance Organic Support (FAMOS) Lab –Provides rapid engineering support to fleet aviation maintenance both ashore and afloat. The Lab is able to quickly and effectively respond to fleet needs through a variety of capability such as product development, testing, troubleshooting, engineering change proposal (ECP) and engineering investigation (EI) support.
• Aircraft Engine Test Systems (AETS) Lab – Provides the capability to conduct systems engineering, in-service engineering, design and development, prototyping, testing and training functions for both hardware and software of the JETI/SETI/TPTI Engine Test Systems.
• Integrated Diagnostics and Automated Test Systems (IDATS) Lab – Provides fleet support through the diagnosis of avionics systems, testability analysis and the development of next-generation automatic test equipment (ATE) products.
7NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Labs/Capabilities (cont’d)
• Integrated Support Equipment Avionics (ISEA) Lab – Provides a "One Stop Shop" for PMA/Platform O & I level Avionics Peculiar Support Equipment (PSE) Platform requirements with an operations-centric focus to meet fleet needs. It provides the platform with a streamlined life-cycle solution including Cybersecurity and Software Support Activity Solutions (SSA), while leveraging our many in-house resources at Lakehurst.
• Circuit Card Test and Repair Systems (CCTARS) Lab – Supports the fleet operational readiness through the development of high-quality diagnostic test routines for the test and repair of circuit cards. This lab provides the fleet with real-time technical support for hardware, software, test routines and troubleshooting.
• Carrier Analysis Lab – Conducts analysis and optimization of the flight deck and hangar to improve operability, functionality, and sortie generation rate. This lab is the only capability outside of on-the-job-training to provide Aircraft Handling Officers with familiarity and informal training on operational deck flow efficiencies.
• Collaborative Research, Engineering, Analysis and Testing in Immersive Virtual Environment (CREATIVE) Lab – Supports research and development of analytical, informational, and educational Virtual Reality (VR), Mixed Reality (MR), and Augmented Reality (AR) products for the Support Equipment/Aircraft Launch and Recovery (SE/ALRE) community. This includes design/deployment of SE/ALRE maintenance (VR/MR/AR), visualization (VR), decision (VR/MR/AR), and familiarization (VR) aids for the Naval Aviation Enterprise (NAE).
8NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Labs/Capabilities (cont’d)
• Aviation Data Management And Control System Integration (ADMACS) Lab – Supports development, testing and providing life cycle support for data management systems for air and flight operations and aviation centers aboard aircraft carriers. This lab is capable of creating a mock-up of air operations, Carrier Air Traffic Control Center (CATCC), primary flight control, flight deck and hangar deck control spaces to simulate shipboard configuration environments, allowing the accomplishment of real-time workflow.
• Robotics and Intelligent Systems Engineering (RISE) Lab -Conducts research in the areas of robotics, automation, system health management, and artificial intelligence. Resident multidisciplinary teams of PhD and MS level SMEs help solve innovative ideas in the field of robotics, machine vision, signal processing, controls, neural networks and stochastic optimization techniques, as applied to Aircraft Launch and Recovery Equipment (ALRE) and Naval Aviation SE.
• ALRE Technology Integration Center (A-TIC) – Provides the capability to replicate ALRE shipboard environment including Navy network connections and provides for a land-based, real-time opportunity to test and integrate ALRE systems prior to their installation aboard a ship.
9NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Labs/Capabilities (cont’d)
• Electro-Optical Laboratory (EOL) and Laser Lab – Provides equipment and tools to conduct radiometric measurements and evaluation of lighting and optical systems, including night vision compatible lighting (Lasers up to Class IV; and meets National Institute of Standards and Technology (NIST) traceability requirements).
• Photometric Lab – Provides the capability to measure, analyze and characterize radiometric and photometric properties of light sources and filters, as well as the capability to design, evaluate and support all shipboard lighting systems used in the Aircraft Launch and Recovery Equipment (ALRE) platforms.
• Visual Landing Aids (VLA) Lab – Provide support for fleet VLA systems by maintaining the latest service change configuration of currently deployed VLA systems. The lab is also used to develop, fabricate and troubleshoot system problems. Current VLA systems include: Improved Fresnel Lens Optical Landing System (IFLOLS), Manually Operated Visual Landing System (MOVLAS), Long Range Line-Up System (LRLS), marking and lighting fixtures, Landing Signal Officer Display System (LSODS), Integrated Launch and Recovery Television Surveillance (ILARTS) system, Horizon Reference Set (HRS), Vertical Short Take-Off and Landing (VSTOL) system, Helicopter Operations and Surveillance System (HOSS) and various other electronic systems.
10NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Labs/Capabilities (cont’d)
• Aircraft Wiring System Integration (AWSEIL) Lab – Provides a variety of research, design engineering and prototype fabrication services including hardware/software development and testing, electrical and mechanical aircraft wiring support equipment design, in-service engineering support and applied research.
• Automatic Test Equipment (ATE) Software Center Lab -Provides a tri-service electronics maintenance environment with the goals of improving weapon systems reliability, increasing situational awareness and reducing the logistics footprint through data cleansing, advanced diagnostics and prognostics, metrics reporting, and trend identification.
• Support Equipment Engineering Lab (SEEL) – Provides capabilities such as inspection, reverse engineering, prototyping, and conducting engineering investigations on various Naval Aviation Support Equipment Systems, to provide rapid response and support to the fleet. This lab also offers the space, tools, and equipment to perform hands-on engineering related work for actively worked projects.
• Advanced Deck Handling Technology Evaluation Center (ADHaTEC) - The center will have the ability to test performance/ operation of Deck Handling technologies (DHT) for Shipboard Robotic Systems (SRS) in a real-world environment with Hardware-in-the-loop and real world environment conditions/ parameters (i.e. weather, full scale physical distances, etc.).
11NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Labs/Capabilities (cont’d)
• Materials Engineering Lab (4.3) - Provides comprehensive materials analysis including failure analysis, part selection analysis, and Engineering Investigation (EI) support for Aircraft Launch and Recovery Equipment (ALRE) and Support Equipment (SE) systems.
• Aviation Information Systems Development Lab (AISDL) -Provides the tools, re-configurability options and support to ensure the quality and integrity of new system capabilities prior to production delivery to the ship. The lab has the capability to perform a variety of critical pre-installation events to ensure safe and efficient operations.
• Moriah Wind System Lab - Provides in-service support for more than 50 U.S. Navy, U.S. Coast Guard and Military Sealift Command ships on which the Moriah Wind System is currently installed. This lab functions to test newly developed software prior to deployment to the fleet and software acceptance testing prior to fleet acceptance.
• Integrated Support Environment (ISE) Lab - Provides support to key decision makers, the fleet, engineers, logisticians and program management, by automating pertinent information flow at their finger tips, based on data from various analytical tools and actionable metrics. The lab utilizes specialized software to provide a thorough analysis of the data being collected, which allows for data mining, data cleansing, processing and modeling to identify and visualize trends.
12NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Labs/Capabilities (cont’d)
• AAG, EMALS & Launcher In-Service Lab - Supports its mission by conducting Engineering Investigations (EI) on catapult and arresting gear equipment and inspections and functional testing on new catapult related procurements and catapult circuit cards (i.e., Digital End Speed Indicator (DESI) Master Processor Circuit Board, Capacity Selector Valve (CSV) Controller Circuit Board, Digital Clock Timer (DCT) Timing Board, and the Low Loss Launch Valve Semi-Automatic Lubrication System (LLV SALS)). In addition, the lab conducts research and development on new projects.
• Aviation Shipboard Operations Modeling and Simulation (ASOMS) Lab - Provides a means by which to virtually duplicate products and processes, and immerse them in operational environments by integrating a mix of system simulations and actual systems. The lab applies modeling & simulation, visualization and analysis throughout the systems’ life cycles in order to facilitate safer, more effective and cost-efficient programs and products.
• Cybersecurity Vulnerability Assessment Laboratory (CVAL) – Provides system analysis including requirements, architectures and attack surface; Vulnerability Assessments via system/network scanning; Adversarial assessments including stand-alone penetration testing and penetration testing in the USS Secure distributed environment; Independent Software Assurance for both in-house developed code and that acquired from vendors; Cyber training including SE/ALRE best practices, pen testing, cyber war games, software assurance; R&D for integration of new technologies/configurations into SE/ALRE Programs of Record (PORs); S&T for new cyber concepts which include building custom intrusion detection and penetration testing tools for avionics buses, and conducting an AoA for secure network communication through message validation techniques.
13NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Small Business Opportunities
• Provide resources to assist government personnel in the labs
• Assist the Gov’t in solving specific technology requirements
Small Business Innovation Research (SBIR) projects
219 Funded projects
Commercial Service Agreements
• Business can apply for Congressional Plus-Up opportunities and then partner with the Gov’t
• Business can form CRADAs or Commercial Service Agreements with the labs/facilities to collaborate on technologies and/or testing efforts
• Partner with Academia on Small Business Technology Transfer (STTR) efforts
• Assist labs with small purchase procurements
• Partner with Big Business on niche capabilities in order to assist the gov’t to meet their requirements
14NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Support Equipment Engineering
Successes and OpportunitiesAIR 4.8.6
11 October 2018Presented to: Small Business Round Table
Presented byThomas Donnelly, Division Head
15NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Support Equipment Engineering
• The Navy currently has over 100,000 items of support equipment with operational and maintenance activities worldwide.
• AIR 4.8.6 is the Technical Authority for all Navy and Marine Corps Support Equipment (SE) used afloat and ashore to support fixed and rotary wing aircraft and is responsible for the Design, Development, Testing and In-Service Support of all SE required for aircraft operations, including both Common Support Equipment (CSE) and Peculiar Support Equipment (PSE).*
* Except for 4.8.4 Automatic Test Equipment (ATE) and select PSE
16NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
486 Facts and Figures
• 4 National Locations– Lakehurst (280)
– Pax River (22)
– Point Mugu (51)
– China Lake (26)
• 5 Det Locations
– Indy (11)
– Norfolk (5)
– New River (2)
– Fort Worth (2)
– St. Louis (6)
• 466 Work Years• 383 Civilians
• 2 Military
• 81 WYs CSS
• Customers• 23 PMA’s
• 5 PMS’s
• JSF JPO
• Army & Air Force
• FMS Customers
• CSA Customers
17NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
What We Do
• Design, Develop & Procure New GSE – CSE & PSE
– “Yellow Gear”
– Non-Consolidated Automated Support System (CASS) Automatic Test Equipment (ATE)
• SE Test & Evaluation
• Installation Design, Planning, & Execution
• Fleet Introduction
• In-Service Engineering Support
– Develop and Issue Tech Directives
– Investigate Naval Aviation Maintenance Deficiency Reports
– Real Time Fleet Tech Support
18NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
CSE vs PSE
PMA-260
Common Support Equipment (CSE) – Comprised of only those general purpose items supplying or measuring broad parameters of physical properties that are known to be established in the using service’s inventory (i.e. ground electrical, pneumatic, and hydraulic power units; towing, hoisting, and fueling devices; signal generation devices; and voltage, amperage, and phase measuring devices). The application of SE items to other end items, systems, or components does not, in itself, justify or classify the items as CSE.
Weapon System PMAs
Peculiar Support Equipment (PSE) – An item of SE that must be designed and developed in conjunction with the development of a specific weapon system and does not meet the criteria of CSE.
19NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
SE Commodities and Equipment Types
Handling, Servicing, Inspection
Aircraft Handling Vehicles
Aircraft Crash Salvage
Electrical Servicing
Hydraulic Servicing
Hydraulic Maintenance
Aircraft Maintenance Platforms
Life Support
Cryogenics
Non-Destructive Inspection
Corrosion Control
Armament
Armament Loading
Armament Transport
Propulsion
Engine Test Systems
Engine Maintenance
Pollution Prevention
Painting/Surface Preparation
Washing Operations
Aircraft Maintenance Equipment/
Operations
Facility Recycling
Avionics & Weapons Tester
Commodities
Electronic Warfare
Weapons Control
Communications
Electro-Optics
Software Loading
Navigation
Maintenance Data Processing
Instrumentation
Radar
Automatic Test Equipment (ATE) & Test Program Sets (TPSs)
Hybrid Consolidated Automated Support System (CASS) &
Platform TPSs
EO CASS & Platform TPSs
HP CASS & Platform TPSs
CNI CASS & Platform TPSs
RF CASS & Platform TPSs
RTCASS
eCASS
20NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Handling SE Commodity
Shipboard Helo Handler (SHH)
Shipboard Tow TractorSD2 Spotting Dolly
Large Land-based Tow Tractor (LLTT)
21NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Servicing SE Commodity
Large Land Based Air Conditioner
Static Frequency Converter on F-35
Corrosion Control Cart on MV-22
Oxygen Cart on C-130
ET-110 Engine Trailer on F/A-18
22NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Inspection SE Commodity
SpectrometerStationary Penetrant Inspection Unit
Boroscopes
23NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Armament SE Commodity
Linkless Ammunition
Loading System
Power Drive Unit
AERO 51E Munitions Trailer with P-8A
Single Hoist Ordnance Loading System
Organic Airborne Mine Counter Measures,
USS Independence (LCS-2)
Loading M61A1 Palletized Gun System
into F/A-18
24NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Crash and Salvage SE Commodity
P25A Environmental Test
P25A during Fire Pit Test
Testing A/S32A-36A Crash Crane on MH-60S
Testing A/S32-35 Crash Crane on F/A-18
P25A during Fire Pit Test
25NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Propulsion SE Commodity
26NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Automatic Test Equipment SE Commodity
Reconfigurable Transportable Consolidated
Automated Support System (RTCASS)
eCASS High Power
eCASS with Panel Interface
Device (PID)
RTCASSCASS w/Operation Test
Program Set
27NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Successes and Opportunities
Aviation Support Equipment (SE) and Aircraft Launch and Recovery Equipment (ALRE) Installation and Alteration Support Services at Shipboard and Shorebased Sites
Contract Information: Cost Plus Fixed Fee, Small Business, Indefinite Delivery/Indefinite Quantity (IDIQ) Contract
Contractors: Epsilon Systems Solutions, Prism Maritime, Delphinus, Superior Marine Solutions
Awarded: June 2015 in the amount of $29M including options
Description: The contractor provides an Alteration Installation Team (AIT) consisting of qualified personnel to perform shipboard and shorebased installations of SE and ALRE. These services include work in the following areas: Quality Assurance, Structural, Welding, Non-Destructive Testing, Electrical/Electronics, Piping/Plumbing, Heating, Ventilation, and Air Conditioning (HVAC), Lighting, Fire Alarm/Suppressions systems, Fire Watch, Paint Testing/Abatement, Painting, Decking/Floor Covering, Lagging/Insulation, Local Area Network (LAN)/Fiber Optic Systems, Telephone Systems, Proofload Testing, Packaging and Shipping, and Debris/Hazardous Material Disposition. The resultant contract has a period of performance of one (1) base year and four (4), twelve (12) month options. The solicitation received 4 offers and the award was made to all four.
28NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Successes and Opportunities
Aviation Support Equipment (SE) Engineering and Technical Support Services
Contract Information: Small Business, Cost Plus Fixed Fee
Contractor: TPS Associates
Awarded: June 2018 in the amount of $10M including options over 5 years
Description: Provide Design Engineering and Technical Services in support of the acquisition of Support Equipment (SE) systems for assigned aircraft avionics equipment, and other military equipment, as assigned. Perform technical data collection and evaluation in support of test requirements analyses, in conjunction with review of hardware and software specifications, in order to ensure SE capability / suitability for a particular weapon system, avionic subsystem, or other equipment. The resultant contract has a period of performance of one (1) base year and four (4), twelve (12) month options.
29NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Successes and Opportunities
SEED Engineering and Technical Support Services
Contract Information: Cost Plus Fixed Fee, Full and Open, Indefinite Delivery/Indefinite Quantity (IDIQ) Contract
Contractors: MTG Services, Inc. (Small Business)
Awarded: March 2016 in the amount of $38.7M including options
Description: The contractor provides engineering and technical services in the following areas: Fighter and Vertical/Short Takeoff and Landing (VSTOL) and Special Missions Aircraft, Avionics Program Support, Aircraft Servicing, Tool Control and Pollution Prevention, Reliability Maintainability and Integrated Diagnostics (R,M & ID), Six Sigma Support, PSE/CSE Hardware and Software Development and ISE Support, Support Equipment (SE) Installations Engineering, Propulsion SE, Aircraft and Armament Handling SE, Aircraft Servicing SE, Module Test and Repair and Miscellaneous Engineering Efforts across multiple NAVAIR sites. The resultant contract has a period of performance of one (1) base year and four (4), twelve (12) month options. The solicitation received 1 offer and the award was made.
30NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Success and Opportunities
Service Life Extension to Aircraft Armament Equipment – DOTC-INIT 311
Contract Information: Cost Plus Fixed Fee, Full and Open Competition via DOTC – DoD Ordnance Technology Consortium
Contractors: SAIC
Awarded: January 2016 in the amount of $2.8M including options
Description: To successfully execute their missions; the armed forces require the service life extension of the fielded bomb racks and launchers that are beyond their original anticipated service life. Instead of discarding legacy launchers, the goal of this program is to reduce the cost and increase safety of AAE through the enhancement of existing equipment. The Precision Guided Training Round (PGTR) is a developmental store that is structurally similar to the Laser Guided Training Round (LGTR) that requires a new method of carriage and release on the F/A-18A-D/E/F. The program support disciplines consist of Program Management, Electrical Design, Software Engineering, prototype development, and test. The resultant order has a period of performance of 46 months with an acquisition strategy for this procurement of a Cost Plus Fixed Fee (CPFF) Level of Effort (LOE) Task Order. The Award of this contract was made to a large business however Small Business is currently performing 61% of the tasking. Small Businesses include: Advent Precision, Inc., Avans Machine, Inc., Celltron, Colbert Manufacturing, Inc., Engineered Test Services, CNC Industries, Coldwell, Delta Electronics Manufacturing, Garrity Tool Company, Graphic Products, Inc., IBC Coating Technologies, Lee Spring Company, Klinge Enameling, Marvin Engineering, Midwest Military Fasteners, PEI Genesis, Powel Electronics, SEA Wire & Cable.
31NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Successes and Opportunities
Test Equipment Joint Application and Additional Weapon Support – DOTC-INIT 195
Contract Information: Cost Plus Fixed Fee, Full and Open Competition via DOTC – DoD Ordnance Technology Consortium
Contractors: SAIC
Awarded: January 2017 in the amount of $9.3M including options
Description: The scope of this initiative is to leverage the technology development of USN/USMC test equipment, modernize candidate equipment, and then adapt it to meet requirements for other U.S. Military services. New weapons such as the Small Diameter Bomb (SBD) II are planned to be employed on new and existing platforms such as the Joint Service F-35, the US Air Force (USAF) F-16, A-109, F-15, the US Navy/Marine Corps (USN/USMC) F/A-18, AV-8B, P-8 and existing and future Remotely Piloted Aircraft (RPA). However, current test and test equipment in the Joint Services doesn’t possess the capability to test these interfaces and ensure the platform can safely load and reliably launch these weapons. The program support disciplines consist of Program Management, Electrical Design, Software Engineering, prototype development, and test. The resultant order has a period of performance of 28 months with an acquisition strategy for this procurement of a Cost Plus Fixed Fee (CPFF) Level of Effort (LOE) Task Order. The Award of this contract was made to a large business however it is anticipated that Small Business will perform 30% of the tasking. Small Businesses include: CAMtek, EMA Design Automation, Engineered Test Services (ETS) and Total Phase Inc.
32NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Successes and Opportunities
CDI Marine Engineering and Technical Support Services
Contract Information: Cost Plus Fixed Fee, Full and Open Competition via SEAPORT-e
Contractors: CDI Marine
Awarded: March 16, 2018 in the amount of $43.50M including options
Description: The contractor shall provide engineering and technical support services
associated with the acquisition, design, development, fielding and sustainment of aircraft
support systems and equipment such as Automated Test Equipment (ATE), Operational
Test Program Sets (OTPSs), Consolidated Automated Support System (CASS) Ancillary
Equipment, General Purpose Test Equipment (GPETE) and other avionics Support
Equipment (SE).The support services required herein will primarily be in support of Naval
Aviation systems and equipment. However, it is anticipated that tasking on this order may
come from other Department of Defense (DoD) organizational elements, Foreign Military
Sales (FMS) cases, and, non-DoD government activities. The resultant contract has a
period of performance of one (1) base year and four (4), twelve (12) month options. Of
note, there is no requirement or obligation for small business however the prime has a
small business plan with five vendors.
33NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Success and Opportunities
Micro-Purchases for Supplies and Services (Credit Card)
Contract Information: Various (i.e. FEDMALL, Furniture BPA’s)
Contractors: Various
Awarded: Throughout the Fiscal year. Approximately $600K/Year
Description: Procure supplies below the $5K credit card threshold to include; office furniture and office supplies; Commercial-Off-The-Shelf (COTS) parts for design and prototyping; service below the $2.5K credit card threshold such as calibration and repairs.
34NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
AIR-1.0 Programs Division Small Business Opportunities
11 October 2018
Presented to: Lakehurst Small Business Roundtable
Presented by: Jim Deffler, AIR-1.0 Programs Division Head & PMA260 Site Lead
35NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Provide cost effective aviation Common Support Equipment (CSE) & Mobile Maintenance Facility (MMF) equipment in support of Fleet operations and maintenance activities.
• Deliver CSE & MMF equipment that has successfully passed all necessary testing.
Contractor performance, environmental, EMI, shock & vibration testing
Government suitability & supportability testing
Mission Statement
36NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Deliver CSE & MMF equipment with full Integrated Logistics Support (ILS) in place.
Technical Manuals
Operator & Maintenance Training
Spares on Shelf
Calibration Support
Mission Statement
37NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Product Lines
Avionic CSE Mobile Maintenance
Facilities
Non-Avionics CSE
In support of PMA260 Aviation
Support Equipment Program
Office, provides flight line and
intermediate maintenance level
test equipment & automated
test equipment for aircraft
avionics systems.
In support of the NAVAIR MMF
Program Office provides top
quality engineering design
solutions, production efforts
and life cycle logistics in
support of the Fleet’s MMF
inventory and our Navy and
Marine Corps customer
requirements.
Maule
Engine Test Cells
MMF Shelters
Environmental Control Units
In support of PMA260 Aviation
Support Equipment Program
Office, provides CSE for the
movement, servicing, and
maintenance/repair of all USN
and USMC aircraft and engine
systems as well equipment for
the transportation and handling
of all munitions.
Aircraft Handling
Equipment
Aircraft Servicing
Equipment
Flight Line
Test EquipmentI-Level Bench Top
Test Equipment
Automated Test EquipmentOrdnance Trailers &
Weapons Skids
38NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: 2000 Gal Liquid Oxygen Tanks
Anticipated Future Requirements
Requirement Description:A Build-to-Print effort for the production of replacement 2,000 gallon tanks to store and dispense liquid oxygen at Navy & Marine Corps shore based activities. The tank shall contain a vaporizer to convert the liquid oxygen to gaseous oxygen at 2,500 psi to allow for oxygen support of all Navy and Marine Corps aircraft.
39NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: 2000 Gal Liquid Oxygen Tanks
Anticipated Quantity or Period of Performance: Estimate a total quantity of 46 units to be ordered between FY19 and FY22. Solicitation will be for a base year plus option years.
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Competitive Small Business Set-Aside.
Anticipated Solicitation/RFP Release Date: 1st Qtr FY19
Current Contract Number: N/A
Anticipated Future Requirements
40NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Aircraft Engine Component Test Stand (AECTS) Replacement
Requirement Description: The AECTS Replacement will address obsolescence, sustainment challenges, cybersecurity, new aircraft generator support requirements & integrate multiple platform peculiar hardware and original equipment manufacturer proprietary software into one common test bench. This will be a design, development & production effort for the replacement AECTS along with all associated integrated logistics support.
Anticipated Future Requirements
41NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Aircraft Engine Component Test Stand (AECTS) Replacement
Anticipated Quantity or Period of Performance: Estimate 30 units + 1 shock unit between FY19 and FY24.
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Full & Open Competition
Anticipated Solicitation/RFP Release Date: 2nd Qtr FY19
Current Contract Number: N/A
Anticipated Future Requirements
42NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Diesel & Electric Servicing Platform (Man Lifts)
Requirement Description: Design, development, test & production of diesel & electric powered man lifts and all associated integrated logistics support required to provide Fleet technicians access to areas on large aircraft 20 feet to 50 feet above the ground during shore based maintenance.
Anticipated Future Requirements
43NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Diesel & Electric Servicing Platform (Man Lifts)
Anticipated Quantity or Period of Performance: Estimate a total quantity of 107 units to be ordered between FY20 and FY24. Solicitation will be for a base year plus option years.
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Full & Open Competition
Anticipated Solicitation/RFP Release Date: 2nd Qtr FY19
Current Contract Number: N/A
Anticipated Future Requirements
44NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: AN/USM-713 Signal Generator Test Set (SGTS)
Requirement Description: Design, development, test & production of upgrade kits & all associated integrated logistics support to address obsolescence issues in the AN/USM-713 SGTS, a portable flight line test set that performs Insertion Loss, Return Loss, Voltage Standing-Wave Ratio (VSWR) & Distance-To-Fault measurements on aircraft Radio Frequency (RF) transmission lines, in-line components and antennas.
Anticipated Future Requirements
45NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: AN/USM-713 Signal Generator Test Set (SGTS)
Anticipated Quantity or Period of Performance: Estimate a total quantity of 101 upgrade kits to be ordered between FY19 and FY21.
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Small Business Sole Source.
Anticipated Solicitation/RFP Release Date: 2nd Qtr FY19
Current Contract Number: N/A
Anticipated Future Requirements
46NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: ADU-980/E Cradle, Ground Handling Equipment
Requirement Description: This is a planned build-to-print effort for the production of ADU-980/E Cradles to transport bomb racks and launchers both ashore and afloat on existing Navy & Marine Corps munitions trailers. It will replace the AERO-83A Munitions Adapter.
Anticipated Future Requirements
47NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: ADU-980/E Cradle, Ground Handling Equipment
Anticipated Quantity or Period of Performance: A total of 334 ADU-980/E Cradles are expected to be ordered between FY19 and FY23 with 652 additional units to be procured in FY24 and beyond.
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Competitive Small Business Set-Aside
Anticipated Solicitation/RFP Release Date: 3rd Quarter of FY19
Current Contract Number: N/A
Anticipated Future Requirements
48NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: 1553 Data Bus Network Tester
Requirement Description: Design, development, test & production of a portable, rugged, battery-powered on-aircraft tester & all associated integrated logistics support. for isolating faults on transmission lines of various aircraft data buses. The DBNT will replace the obsolete 1553 Data Bus Network Tester and provide additional capability to support all new and emerging aircraft data bus types (Ethernet, ARINC-429, Firewire)
Anticipated Future Requirements
49NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: 1553 Data Bus Network Tester
Anticipated Quantity or Period of Performance: Estimate a total quantity of 203 units to be ordered between FY20 and FY23. Solicitation will be for a base year plus option years.
Anticipated Contract Type: Market research currently underway to finalize acquisition strategy.
Anticipated Solicitation/RFP Release Date: 3rd Quarter of FY19
Current Contract Number: N/A
Anticipated Future Requirements
50NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Particle Counters
Requirement Description: Design, development, test & production of particle counters and all associated integrated logistics support required by Fleet technicians for measuring particle contamination in hydraulic fluids in support of the Navy Hydraulic Fluid Contamination Program.
Anticipated Future Requirements
51NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Particle Counters
Anticipated Quantity or Period of Performance: A total of 705 particle counters are expected to be ordered between FY19 and FY24
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Full & Open Competition
Anticipated Solicitation/RFP Release Date: 3rd Quarter of FY19
Current Contract Number: N/A
Anticipated Future Requirements
52NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: A/S32A-108 Replacement Mobile Electric Power Plant (MEPP)
Requirement Description: Design, development, test & production of a self-contained, diesel engine driven, towable ground power unit and all associated integrated logistics support required to generate electrical power for most fleet aircraft. Provides multiple power outputs to support aircraft maintenance as follows: 90KVA, 115VAC, three phase, 400Hz and 28VDC (28KW).
Anticipated Future Requirements
53NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: A/S32A-108 Replacement Mobile Electric Power Plant (MEPP)
Anticipated Quantity or Period of Performance: Estimate a total quantity of 528 units to be ordered between FY20 and FY24. Solicitation will be for a base year plus option years.
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Competitive Small Business Set-Aside
Anticipated Solicitation/RFP Release Date: 4th Quarter of FY19
Current Contract Number: N/A
Anticipated Future Requirements
54NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: X-ray Apparatus Replacement
Requirement Description: Design, development, test & production of a replacement X-Ray Apparatus & all associated integrated logistics support required by Fleet Non-Destructive Inspection technicians to verify the internal structural integrity of aircraft by inspecting for fatigue cracks, porosity, and Foreign Object Damage.
Anticipated Future Requirements
55NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: X-ray Apparatus Replacement
Anticipated Quantity or Period of Performance: Estimate 99 units between FY20 and FY22
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Full & Open Competition
Anticipated Solicitation/RFP Release Date: 4th Quarter of FY19
Current Contract Number: N/A
Anticipated Future Requirements
56NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Shipboard Oxygen Cleaning System
Requirement Description: Design, development, test and production of an Ultrasonic Cleaning System (UCS) and all associated integrated logistics support to provides the Fleet a shipboard capability to clean components required to be “oxygen clean”.
Anticipated Future Requirements
57NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Shipboard Oxygen Cleaning System
Anticipated Quantity or Period of Performance: Estimate a total of 12 units between FY21 and FY22.
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Full & Open Competition
Anticipated Solicitation/RFP Release Date: 2nd Quarter of FY20
Current Contract Number: N/A
Anticipated Future Requirements
58NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: 1,500 Pound Towable Utility Crane Replacement
Anticipated Future Requirements
Requirement Description: Design, development, test & production of a replacement Towable Utility Crane & all associated integrated logistics support required by Fleet maintainers to remove aircraft canopies, ejection seats and other aircraft components weighing up to 1,500 pounds during aircraft maintenance.
59NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: 1,500 Pound Towable Utility Crane Replacement
Anticipated Quantity or Period of Performance: Estimate 214 units between FY21 and FY25.
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Full & Open Competition
Anticipated Solicitation/RFP Release Date: 2nd Quarter of FY20
Current Contract Number: N/A
Anticipated Future Requirements
60NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Fiber Optic Time-Domain Reflectometer (FOTDR)
Requirement Description: The FOTDR will be used to find the distance to a fault in a fiber optic system. It will show the relative loss of signal power over the optical path and identify the location of these losses to the point of the fault. Effort will be for the design, development & production of the FOTDR and all associated integrated logistics support.
Anticipated Future Requirements
61NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Fiber Optic Time-Domain Reflectometer (FOTDR)
Anticipated Quantity or Period of Performance: Estimate a total quantity of 41 units to be ordered between FY21 and FY23. Solicitation will be for a base year plus option years.
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Full & Open Competition
Anticipated Solicitation/RFP Release Date: 3rd Quarter of FY20
Current Contract Number: N/A
Anticipated Future Requirements
62NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
Small Business Opportunities
11 October 2018
Presented to: Lakehurst Small Business Roundtable
Presented by: Brian Barr
63NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: LED Centerline/Tramline lights
Requirement Description: This is an SBIR development to replace the Fiber optic Centerline lights (FOCL) in carriers & the Tramline lights on large deck amphibious assault ships. The FOCL design is becoming obsolete, difficult to maintain and is not inherently Night Vision Device (NVD) compatible.
Anticipated Quantity or Period of Performance: 6 test units over an 18 month period
Anticipated Contract Type: SBIR Phase 2.5 – sole source
Anticipated Solicitation/RFP Release Date: October 2019
Current Contract Number: N68335-13-C-0059, SBIR topic N102-132.
Anticipated Future Requirements
64NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: LSODS ECP-345 Kit
Requirement Description: Purchase a total of approx. 10 kits containing custom and cots equipment.
Anticipated Quantity or Period of Performance: 10 over 2 year period, Dec 2020 to Dec 2022
Anticipated Contract Type: FFP
Anticipated Solicitation/RFP Release Date: RFP release targeted August 2019 / Award December 2020
Current Contract Number: TBD
Anticipated Future Requirements
65NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Wire Rope Abrasion Testing
Requirement Description: Testing service contract for abrasion testing of the Navy’s arresting gear wire rope. Total efforts include construction of a wire rope abrasion tester featuring Composition L (MIL-PRF-24667C) non-skid and abrasion testing of GFE provided wire rope samples over it
Anticipated Quantity or Period of Performance: Solicitation will be for a base year plus option years. Base year will consist of wire rope abrasion tester production and the testing of 10 samples. Option years (4) will consist of tester upkeep and up to 10 more samples per year.
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Competitive Small Business Set-Aside
Anticipated Solicitation/RFP Release Date:
1st Quarter of FY19
Current Contract Number: N/A
Anticipated Future Requirements
66NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: 2 Bend-Over-Sheave (BOS) Wire Rope Fatigue Testing
Requirement Description: Testing service contract for 2-BOS wire rope fatigue testing of the Navy’s arresting gear wire rope. Total efforts include commercial testing of wire rope fatigue with GFE provided wire rope samples.
Anticipated Quantity or Period of Performance: Solicitation will be for a base year plus option years. Base year will consist of fatigue testing 52 samples. Option years (4) will consist of testing up to 50 more samples per year.
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Competitive Small Business Set-Aside
Anticipated Solicitation/RFP Release Date: 1st Quarter of FY19
Current Contract Number: N/A
Anticipated Future Requirements
67NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Mark 7 Arresting Gear Main Engine Cylinder (MEC)
Requirement Description: Build-to-print procurement of Mark 7 Arresting MECs – ALRE Critical Safety Item, requires Flight Safe considerations and Source Approval Requests (SARs). 43 series steel, 16+ feet in overall length
Anticipated Quantity or Period of Performance: Solicitation will be for a base year plus option years. Base year will consist of 2 MEC prototypes. Option years (4) will consist of delivery up to 6 MECs per year.
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Competitive Small Business Set-Aside
Anticipated Solicitation/RFP Release Date: 1st Quarter of FY19
Current Contract Number: N/A
Anticipated Future Requirements
68NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: EAF AM2 Repair and Refurbishment
Requirement Description: A Build-to-Print effort for the Repair and Refurbishment associated with the four (4) types of EAF AM2 Mat Packages (F-71, F-72, F-73, and F-78). The Refurbishment of AM-2 matting is for the reapplication of non-skid coating material on the matting.
Anticipated Quantity or Period of Performance: A total of 30,000 AM2 mats are estimated to be refurbished between FY19 and FY23
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Competitive Small Business Set-Aside
Anticipated Solicitation/RFP Release Date: 1st Quarter of FY19
Current Contract Number: N68335-14-D-0008
Anticipated Future Requirements
69NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: EAF Land-Based Arresting Gear Logistics and Supply Support
Requirement Description: This contract will provide Contractor Logistics Support (CLS) and Hardware procurement support for the M31 Marine Corps Expeditionary Arresting Gear System (MCEAGS). The contract will also provide logistics and engineering support for other land-based arresting gear platforms (e.g., E28 Land-based Arresting Gear)
Anticipated Quantity or Period of Performance: EAF team plans to release a 5-year contract to provide support starting in FY19.
Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Sole Source Alaska Native Corporation (ANC)
Anticipated Solicitation/RFP Release Date: 4th Quarter FY19
Current Contract Number: M31 Hardware BOA – N68335-17-G-0003; M31 CLS BOA – N68335-16-G-0045
Anticipated Future Requirements
70NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
70
70
Anticipated Future
Requirements• Requirement Title: 10 KVA and 50 KVA Batteries
• Requirement Description: These batteries are used to energize the
UPS cabinets which in turn act as a backup source of power to various
AAG equipment such as Dynamic Control System. Subsequently, this will
allow the individual AAG components to complete its mission of recovering
aircraft in the event of loss of ship's power.
• Anticipated Quantity or Period of Performance: It is the intent to
order 174 10KVA and 58 50KVA Batteries in FY19.
• Anticipated Contract Type: Firm Fixed Price; Limited Competition
• Anticipated Solicitation/RFP Release Date: 1st Quarter of FY19
• Current Contract Number: N/A
71NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Mk 7 Mod 4 Arresting Gear Packing
Requirement Description: Build-to-print production of a packing assembly to be utilized in the sheave damper cylinder.
Anticipated Quantity: 20
Anticipated Contract Type: Firm Fixed Price, Full and Open
Anticipated Solicitation/RFP Release Date: 2nd Quarter FY19
Current Contract Number: N/A
Anticipated Future Requirements
72NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
72
Anticipated Future
Requirements• Requirement Title: Uninterrupted Power Supply (UPS)
Batteries
• Requirement Description: Batteries are used to energized the UPS
cabinets which in turn act as a backup source of power to various EMALS
and AAG equipment such as the Prime Power Interface Subsystem and
Dynamic Control Systems. This will allow the individual EMALS and AAG
components to complete its mission of launching and recovering aircraft in
the event of loss of ship’s power.
• Anticipated Quantity or Period of Performance: The intent is to
order 29 and 79 batteries for AAG and EMALS respectively in FY19.
• Anticipated Contract Type: Firm Fixed Price; Sole Source
• Anticipated Solicitation/RFP Release Date: 1st Quarter of FY19
• Current Contract Number: N/A
73NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
73
Anticipated Future
Requirements• Requirement Title: Water Hammer Arrestor
• Requirement Description: The Water Hammer Arrestor is designed to
reduce the magnitude of pressure spikes that occur upon the rapid closing of
isolation valves to an AAG liquid-cooled component.
• Anticipated Quantity or Period of Performance: It is the intent to
order 4 for AAG in FY19.
• Anticipated Contract Type: Firm Fixed Price; Sole Source
• Anticipated Solicitation/RFP Release Date: 1st Quarter
of FY19
• Current Contract Number: N/A
74NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Mk 7 Arresting Gear Floating Piston
Requirement Description: Build-to-print manufacture of prototype and potential follow-on production of newly designed Accumulator Floating Piston cage and glide ring
Anticipated Quantity: 80
Anticipated Contract Type: Firm Fixed Price, Full and Open
Anticipated Solicitation/RFP Release Date: Prototype: 3rd
Quarter FY19; Follow-on TBD
Current Contract Number: N/A
Anticipated Future Requirements
75NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: Mk 7 Arresting Gear Fluid Cooler
Requirement Description: Design, Test, manufacture of prototype and potential follow-on production of newly designed Fluid Cooler
Anticipated Quantity: 40
Anticipated Contract Type: Firm Fixed Price, Full and Open
Anticipated Solicitation/RFP Release Date: Prototype: 1st Quarter FY20; Follow-on TBD
Current Contract Number: N/A
Anticipated Future Requirements
76NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Launcher Bolt Locks:
Requirement Description: Shock and vibration associated with aircraft launch cause attaching catapult hardware to loosen, even with the use of lockwire. New cap screws with positive locking devices will solve this problem. Hardware kits will be procured and distributed to the fleet for installation.
Anticipated Quantity or Period of Performance: Hardware for 40+ shipboard and shore based catapults along with appropriate spares
Anticipated Contract Type: Small Business FFP
Anticipated Solicitation/RFP Release Date: Dec 18
Current Contract Number: None
Anticipated Future Requirements
77NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
77
Anticipated Future
RequirementsRequirement Title: AAG and EMALS Software Support Activity
Requirement Description: Procurement, configuration,
installation, design, and documentation of assets for AAG and EMALS software support lab to include COTS IT equipment, racks, networking hardware, test equipment, furniture, and any other equipment required for development and testing of AAG and EMALS software.
Anticipated Quantity or Period of Performance:
Estimate period of performance FY19-23.
Anticipated Contract Type: Small Business Set-Aside;
CPFF
Anticipated Solicitation/RFP Release Date: 2nd Quarter of FY19
Current Contract Number: N/A
78NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: AV-8B Foreign Object Damage (FOD) Mitigation PSE
• Requirement Description: AV-8B’s are historically FOD prone necessitating pre-operational maintenance to the runaways and surrounding Flightline areas. This includes high power pad, hangars, taxi ways and mooring paddock. Procurement, maintenance, storage, training and potential enhancements are essential to the success of AV-8B FOD Mitigation efforts.
• Anticipated Quantity or Period of Performance: Current evaluation effort on-going, once finalized this effort will require: PoP to be three years at two (2) fixed CONUS locations with capability to support 4 Forward Operating Bases (FOB).
• Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Cost Plus Type Contract
• Anticipated Solicitation/RFP Release Date: 2nd Quarter FY19
• Current Contract Number: N/A
Anticipated Future Requirements
79NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
• Requirement Title: AV-8B SE Reconciliation
• Requirement Description: The Global War on Terrorism (GWOT) increased OPTEMPO has degraded critical common and peculiar support equipment. Increased maintenance requirements have resulted in lack of accurate reporting of assets and service capability resulting in Non and Partial Mission Capability in support of combat operations. Impacts include replacement, overhaul, obsolescence and lack of maintenance driving need for replacement and major overhaul of SE.
Anticipated Future Requirements
• Anticipated Quantity or Period of Performance: Current inspections of Fleet SE has already identified hundreds of missing items with large numbers of assets missing components or in need of contractor overhaul.
• Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm-Fixed Price
• Anticipated Solicitation/RFP Release Date: 4th Quarter FY19
• Current Contract Number: N/A of assets missing components or in need of contractor overhaul.
80NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
80
Anticipated Future Requirements
• Requirement Title: OBOGS Air Source Tester
• Requirement Description: The OBOGS Air Source Tester will replace the ACS Test Set, P/N 74D410141-1003. It includes one 0-200 PSI pressure gauge required to measure the pressure of the OBOGS Air Source. The tester also includes a four foot hose and two adapters.
• Anticipated Quantity or Period of Performance: Estimate a total quantity of 110 units to be ordered in FY19.
• Anticipated Contract Type: Firm Fixed Price; Small Business Set-Aside.
• Anticipated Solicitation/RFP Release Date: 3rd Quarter of FY19
• Current Contract Number: N/A
Anticipated Future Requirements
81NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
81
• Requirement Title: Shock Servicing Gauge Set
• Requirement Description: The Shock Servicing Gauge Set fills a need to interface between the nitrogen servicing unit and the landing gear and tailhook servicing valves to measure nitrogen pressure and to add or remove nitrogen to obtain the required pressures.
• Anticipated Quantity or Period of Performance: Estimate a total quantity of 234 units to be ordered in FY19.
• Anticipated Contract Type: Firm Fixed Price; Small Business Set-Aside.
• Anticipated Solicitation/RFP Release Date: 3rd Quarter of FY19
• Current Contract Number: N/A
Anticipated Future Requirements
82NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
82
• Requirement Title: F/A-18 E-G Brake Spacer
• Requirement Description: The F/A-18 E-G Brake Spacer is used when the Multiple Disk Brake is removed from the aircraft to allow towing capability. The spacer is assembled onto the MLG Axle Assembly, where the brake would normally be located.
• Anticipated Quantity or Period of Performance: Estimate a total quantity of 134 units to be ordered in FY19.
• Anticipated Contract Type: Firm Fixed Price; Small Business Set-Aside.
• Anticipated Solicitation/RFP Release Date: 2nd Quarter of FY19
• Current Contract Number: N/A
Anticipated Future Requirements
83NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
83
• Requirement Title: IRST Program Loader Set (PLS) Cable
• Requirement Description: IRST PLS Cable required for loading IRST Operational Flight Program (OFP) via PLS. The IRST PLS cable will load an OFP for the IRST Sensor via the Ethernet bus in the IRST Test Port.
• Anticipated Quantity or Period of Performance: Estimate a total quantity of 10 units to be ordered FY19.
• Anticipated Contract Type: Competitive Small Business Set-Aside
• Anticipated Solicitation/RFP Release Date: 1st Quarter of FY19
• Current Contract Number: N/A
Anticipated Future Requirements
84NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
84
• Requirement Title: MIDS/JTRS PLS S/W Loading Cable Set
• Requirement Description: A Build-to-Print effort for the production of cable assembly sets to enable “O” and “I” level maintenance activates to load Operational Flight Program S/W to the MIDS/JTRS WRA’s.
• Anticipated Quantity or Period of Performance: Estimate a total quantity of 146 units to be ordered in FY19. .
• Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Competitive Small Business Set-Aside
• Anticipated Solicitation/RFP Release Date: 1st Quarter of FY19
• Current Contract Number: N/A
Anticipated Future Requirements
85NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
85
• Requirement Title: F/A-18E/F & EA-18G Wrap Around Test (WAT) Automatic Wire Test Set (AWTS) Test Program Set (TPS)
• Requirement Description: A Build-to-Print effort for production of WAT AWTS TPS to provide Fleet Intermediate Level (I-level) automated diagnostics testing & all associated integrated logistics support of F/A-18E/F & EA-18G WAT cables, reduced repair turnaround time, and avoid exhaustive repair.
• Anticipated Quantity or Period of Performance: Estimate a total quantity of 18 units to be ordered between FY19 and FY22.
• Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Competitive Small Business Set-Aside
• Anticipated Solicitation/RFP Release Date: 3rd Quarter of FY19
• Current Contract Number: N/A
Anticipated Future Requirements
86NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
86
• Requirement Title: Fire Control System Test Set, TS-4457A
• Requirement Description: A Build-to-Print effort for production & all associated integrated logistics support to address obsolescence issues in the TS-4457, Fire Control System Test Sets, an I-level electronic test set used to perform maintenance built-in-test (MBIT) on the F/A-18A-F and EA-18G Command Launch Computer, CP-1001C/AWG CLC, which goes into the aircraft.
• Anticipated Quantity or Period of Performance: Estimate a total quantity of 34 units to be ordered between FY20 and FY22.
• Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Competitive Small Business Set-Aside
• Anticipated Solicitation/RFP Release Date: 4th Quarter of FY19
• Current Contract Number: N/A
Anticipated Future Requirements
87NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
87
• Requirement Title: F/A-18 GCU POWER SUPPLY (PS1) TESTER
• Requirement Description: Production and delivery of the Power Supply Tester (PST) to perform testing of F/A-18 Aircraft Generator Converter Unit (GCU) power supply (PS1) modules.
• Anticipated Quantity or Period of Performance: A total quantity of 27 production
units to be ordered on FY19 with a period of performance of 12 months.
• Anticipated Contract Type: Firm Fixed Price; Small Business Technology Transfer (STTR) Phase III
• Anticipated Solicitation/RFP Release Date: 2nd Quarter of FY19
• Current Contract Number: N68335-18-C-0158
Anticipated Future Requirements
88NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
88
• Requirement Title: AN/ALQ-249 Pod Storage Rack
• Requirement Description: This is a planned build-to-print effort for the production of 20 prototype and 140 production AN/ALQ-249 Pod Storage Racks to store NGJ MB Pods both ashore and afloat in planned storage facility at NAS Whidbey Island, WA and existing Navy CVNs.
• Anticipated Quantity or Period of Performance: A total of 160 ALQ-249 Pod Storage Rack are expected to be ordered between FY19 and FY21 with TBD additional units to be procured in FY22 and beyond.
• Anticipated Contract Type: Indefinite Delivery/Indefinite Quantity (IDIQ); Firm Fixed Price; Competitive Small Business Set-Aside
• Anticipated Solicitation/RFP Release Date: 2rd Quarter of FY19
• Current Contract Number: N/A
Anticipated Future Requirements
89NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
PEO(A) and PEO(U&W) SE Programs
11 October 2018
Presented to: Lakehurst Small Business Roundtable
Presented by: Tom Knudsen
90NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
PID number N68335-17-RFPREQ-PMA-275-0391
Sole Source to Tri-tool to support FMS requirements
Government has neither the drawings or the rights to use them in a competitive acquisition
Tube Cutter set is a self-contained set of tools and accessories designed to cut aircraft hydraulic tubing
Tri-tool provides the only item found that is able to meet the V-22 cutting requirements for all sized titanium tubing
V-22 SE Procurements
91NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
PID number N68335-17-RFPREQ-PMA-275-0563
Micro spot welder- required to provide capability to maintainers aboard ship to weld V-22 aircraft components
Competitive acquisition
Bid samples requested and received from vendors for evaluation
Evaluation in process to down-select to one welder that satisfies V-22 and shipboard capability requirements
V-22 SE Procurements
92NAVAIR Public Release 2018-874
Distribution Statement A - Approved for public release; distribution is unlimited, as submitted under NAVAIR Public
PID Number: N68335-18-RFPREQ-PMA-266-0022
Requirement Description: Heliporters
Anticipated Quantity or Period of Performance: 4-year POP
Anticipated Contract Type: Sole Source
Anticipated Solicitation/RFP Release Date: 2nd Quarter Fiscal Year 2019
Current Contract Number: N/A
MQ-8C Support Equipment