Naveen Rengasamy Contact: 0091-9789162729 / e-mail: [email protected] Seeking assignments in Project Execution (Construction / Commissioning) with a leading organization of repute preferably in Engineering / Construction sector Project Management skills Planning, Scheduling and continuous monitoring of engineering projects for successful completion with ensure quality and maintaining within the allotted budget. Initiate the project kick off meeting and translate the client requirements to the team members involved in the project. Continuous monitoring of project progress by developing progress report for each projects and keep client updated on the work progress. Preparation of project planning schedule with key milestones and develop detailed deliverable wise planning. Initiate and organize periodic project review meetings to liaise between client and internal engineering team and ensured the project is moving in the right direction. Single point responsibility in relation with the client. Cross functional engineering management and effective co-ordination to bridge the communication gap between internal team members. Identification and preparation of Variation order for the additional scope of work initiated by client from the original contract. Monitoring & Control of Engineering Man-hours to ensure it is in line with the allotted project man-hours. Liaise periodically with clients on key technical, quality and delivery issues. Motivate the project team members, identification the right resources to accomplish the project goals within the delivery time. Handled projects worldwide with various multinational clients in the Onshore & Offshore Oil & Gas Industry. Managed the daily execution of construction operations, supply chain operations and ensuring on time delivery of materials to match the operation schedule at the site. Co-ordinate with clients, sub-contractors, suppliers and internal teams like Engineering, Design, and Operations for effective Supplier Development and knowledge transfer with in the project team. Managed and controlled the project operations to meet the project operation schedule at the site and also ensured smooth flow of work schedule without time delay.

Naveen Curriculum vitae Project Engineer latest - Copy

Embed Size (px)

Citation preview

Page 1: Naveen Curriculum vitae Project Engineer latest - Copy

Naveen RengasamyContact: 0091-9789162729 / e-mail: [email protected]

Seeking assignments in Project Execution (Construction / Commissioning) with a leading organization of repute preferably in Engineering / Construction sector

Project Management skills

Planning, Scheduling and continuous monitoring of engineering projects for successful completion with ensure quality and maintaining within the allotted budget.

Initiate the project kick off meeting and translate the client requirements to the team members involved in the project.

Continuous monitoring of project progress by developing progress report for each projects and keep client updated on the work progress.

Preparation of project planning schedule with key milestones and develop detailed deliverable wise planning.

Initiate and organize periodic project review meetings to liaise between client and internal engineering team and ensured the project is moving in the right direction.

Single point responsibility in relation with the client.

Cross functional engineering management and effective co-ordination to bridge the communication gap between internal team members.

Identification and preparation of Variation order for the additional scope of work initiated by client from the original contract.

Monitoring & Control of Engineering Man-hours to ensure it is in line with the allotted project man-hours.

Liaise periodically with clients on key technical, quality and delivery issues.

Motivate the project team members, identification the right resources to accomplish the project goals within the delivery time.

Handled projects worldwide with various multinational clients in the Onshore & Offshore Oil & Gas Industry.

Managed the daily execution of construction operations, supply chain operations and ensuring on time delivery of materials to match the operation schedule at the site.

Co-ordinate with clients, sub-contractors, suppliers and internal teams like Engineering, Design, and Operations for effective Supplier Development and knowledge transfer with in the project team.

Managed and controlled the project operations to meet the project operation schedule at the site and also ensured smooth flow of work schedule without time delay.

Following up with the sub-contractors and suppliers to deliver good quality products/service at the right place at the right time

Inventory control and management through continuous improvement and regular monitoring.

Projects

Jan’15 to till date with DANWAY electrical & mechanical engineering, as Senior Project EngineerProject: Additional Butane Storage Tank Package A & B (BELLELI/DUGAS)

Key Result Areas:

Page 2: Naveen Curriculum vitae Project Engineer latest - Copy

Preparation of instrument data sheet, hook up drawings, System block drawings (DCS/ESD/F&G), layout drawings (Instrument/JB/F&G), I/O list, loop drawings,

Assigning junction box for the AI, AO, DI and DO signals systems wise and in each area by considering the spare. Procurement of instruments, impulse tubing, tube fittings, cables, cable glands with respect to NEC standards Co-ordination with DUGAS and PRACSI for tie-in works with the existing DCS (YAMATAKE). Participate in HAZOP study along with DUGAS for the plant F&G detection device location finalization. In-charge for Butane gas compressors with Aux. lube oil skids, 1st & 2nd stage scrubbers, separator, accumulator,

condenser, feed pumps, transfer pumps, 3.3kv jetty loading pump, storage tank. Installed the Honeywell Enraf Radar type, Servo type tank gauging system with VITO temperature probe. Independently did pump temperature relay (TR 600) testing and closed the FAT punch points. Loop test, functional test, instrument calibration, ESD/Control Valve stroke test (by using nitrogen). Coordinate with TYCO, ELLIOT and PRACSI to expedite the deliverables on time to site.

May’13 to Jan’15 with DANWAY electrical & mechanical engineering, as Senior Project EngineerProject: Al Sufouh transit system TRAM project (ALSTOM/RTA)

Key Result Areas: Skilfully performing installation of TIS track devices (Route request loops, Priority request loops, Eurobalise, AVLS-

Balogh, Axle counters, Traffic lights, tram signals, CCTV cameras & DCS antennas). In-charge for the installation for tram station devices(PID, VBS, Kiosk, Loud speaker, Ambient microphone, Paging unit

microphone, WIFI Bases) Overseeing the installation of TIS cubicles/panels with their cabling in stations and depot. In-charge for the Fibre optic and information & command cables installation, testing & termination. Monitoring the construction method to be applied according to contract specification and optimistically utilizing the

resource and completing the task in given time window. Preparation of fortnightly / monthly progress reports and updating the management. Updating the planning dept. and amending the program as per site condition. Materials procurement and site requisition through SAP system. Certified by APAVE to prepare the authorization of electricians operating in LV & HV and certified by Eurolink for Risk

Assessment.

Jan’12 to May’13 with DANWAY electrical & mechanical engineering, as Senior Project EngineerProject: Inter Refinery Pipeline-II project (DAEWOO/TAKREER) with oil storage capacity of 16 x 56,000m³

Key Result Areas: Skilfully performing installation of Level transmitters, level gauges, flow transmitters, fire & gas devices, CCTV, PAGA,

telecom system and their cabling activities Overseen the DCS, ESD and F&G Tie-in works inside existing plant, as an authorized Permit holder in brown field. Monitoring the construction method to be applied according to contract specification and estimating the resource

requirements to be utilized for the project. Procured the E&I cable glands for the complete project as per hazardous classification and design specifications. Updating the management with construction work status and projected plan. Gone to the bottom of constraints and overcome many on-site bottle neck obstacles. Deftly updating the program weekly / monthly and generating the project completion report.

Dec’10 - Dec’11 with DANWAY electrical & mechanical engineering, as Project EngineerProject: Abu Dhabi International Airport Expansion Project (ANNCG/ADAC)

Key Result Areas: Ascertained the preparation of engineering drawings (AutoCAD) for the air field lights, Visual docking guidance

system, high mast lights and LV power DBs. Overseen the installation of airfield ground lights, Jet fuel hydrant systems, fuel line measurement instruments with all

aerodrome safety procedures. Completed the E&I Tie-in works of Jet fuel hydrant system in existing ADNOC jet fuel pumping station. Provided project management update using Primavera P6. Handled the Electrical system design and field execution of entire electrical installation works as per specifications Managed the sub-contractors (CCH, BAYANAT, SAFEGATE & PROLOGIX) for the airport IT upgrade and

synchronization with the existing airport systems.

Page 3: Naveen Curriculum vitae Project Engineer latest - Copy

Dec’08-Dec’10 with DANWAY electrical & mechanical engineering, as Instrumentation EngineerProject: Fujairah F2 Independent Water & Power Project 2000MW combined cycle (ALSTOM/FAPCO)

Key Result Areas: Managed overall instrument installation for 5Nos. Of ALSTOM Gas Turbines (5x250MW GT26B) & 3Nos. Of ALSTOM

Steam Turbines (2x350MW & 1x180MW). Handled the specialized GT & ST sensors, instruments, JBs and prefab. vendor cablings. In-charge for the wiring & loop checking for the GT’s EGATROL and ST’s TURBOTROL control systems. Maintained the installation and inspection status of Power train instruments and I&C cables. Provided the total plant instrumentation status and constraints to the management for weekly meeting/review. Supported the QA/QC team to handover the system wise commissioning turnover package.

Dec’07-Dec’08 with DANWAY electrical & mechanical engineering, as Instrumentation EngineerProject: Fujairah F1 Extension power plant 220MW (BEMCO/FICHTNER)

Key Result Areas: Handled the instrument calibration, installation of GE Gas Turbines (1x220MW GE Frame9A) instruments, Mark VI

control cabinets, accessory skids instruments, Generator devices, turbine cooling systems instruments, Air Intake system skid & instruments.

In-charge for the cabling of HRSG (Nooter Eriksen) skid instruments, feed water system pumps, HP/LP steam line MOVs/instruments and ESD systems.

Handled the Fuel gas compressor and regulation skids instrument installation and cabling. In-charge for the installation of DCS panel, MCC panels, LV panels. Maintained the calibration, installation and inspection status of all instruments and plant I&C cables. Supported the management by providing the total instrumentation status with constraints and their solutions.

Academic Details

B.Tech. in Electronics and Instrumentation Engineering from SASTRA University in May 2007 (1st Class) Diploma in Electronics and communication Engineering from Bharathidasan University in April 2004 (1st Class)

Certifications

APAVE Certified: Preparation for the authorization of electricians operating in Low voltage and High voltage. EUROLINK SAFETY Certified: Risk Assessment.

IT Skills

Ms Office Tools Word, Excel and PowerPointDesign Tools AutoCAD (2011)ERP software's Primavera P6, SAP

Personal Details

Date of Birth 30th May 1985Nationality IndianLanguages Known English, Hindi, Tamil and MalayalamPassport number G0154419Driving license 2017801 (UAE)

Reference

Mr. Prabhakaran, Lead Electrical Engineer, ALSTOM Power, Email - [email protected]; Mob: +971 50 7268494

Mr. Rajan, Senior Engineer I&C, DEWA, Email – [email protected]; Mob:+971 50 2984698

Mr. Soy Anto, Instrument Engineer, Fitchner, Email – [email protected]; Mob:+971 50 7898132

Mr. BERKANE Oucheikh, TIS Manager, ALSTOM Transport, dxb. E-mail - [email protected]