PUBLIC DISCLOSURE AUTHORISED CARIBBEAN DEVELOPMENT BANK TWO HUNDRED AND SIXTY-SECOND MEETING OF THE BOARD OF DIRECTORS TO BE HELD IN BARBADOS JULY 17, 2014 PAPER BD 50/14 NATURAL DISASTER MANAGEMENT - REHABILITATION AND RECONSTRUCTION (DECEMBER 2013 TROUGH EVENT) ST. VINCENT AND THE GRENADINES (President’s Recommendation No. 883) 1. The attached Staff Report appraises a proposal for a loan to the Government of St. Vincent and the Grenadines (GOSVG). The expected outcome of the Project is improved Windward and Vigie Highway corridors and enhanced institutional capacity for planning, design and risk reduction. This is to be achieved through the restoration and rehabilitation of bridges and damaged sections of the feeder road network, and the Windward and Vigie Highways, and the rehabilitation of river defences along the Yarabaqua and Caratal rivers. 2. On the basis of the Report, I recommend: (a) a loan to GOSVG of an amount not exceeding the equivalent of nine million, and forty-six thousand United States dollars (USD9.046 mn) representing 80% of the project cost, consisting of: (i) an amount from the Ordinary Capital Resources of the Caribbean Development Bank (CDB), not exceeding USD5.529 mn; and (ii) an amount from CDB’s Special Funds Resources (SFR) not exceeding USD3.517 mn; and (b) a grant to GOSVG of an amount not exceeding USD221,000 from CDB’s SFR for use by GOSVG in financing the cost of equipment for rainfall and stream flow measurement, and training of hydrological technicians; on the terms and conditions set out and referred to in Chapter 6 of the Report. 3. Funds are available within CDB’s existing resources and/or borrowing programme for the relevant disbursement period.

Natural Disaster Management – Rehabilitation and ... · public disclosure authorised caribbean development bank staff report on natural disaster management rehabilitation and reconstruction

Embed Size (px)

Citation preview

PUBLIC DISCLOSURE AUTHORISED

CARIBBEAN DEVELOPMENT BANK

TWO HUNDRED AND SIXTY-SECOND MEETING OF THE BOARD OF DIRECTORS

TO BE HELD IN BARBADOS

JULY 17, 2014

PAPER BD 50/14

NATURAL DISASTER MANAGEMENT - REHABILITATION AND RECONSTRUCTION

(DECEMBER 2013 TROUGH EVENT) – ST. VINCENT AND THE GRENADINES

(President’s Recommendation No. 883) 1. The attached Staff Report appraises a proposal for a loan to the Government of St. Vincent and the

Grenadines (GOSVG). The expected outcome of the Project is improved Windward and Vigie Highway

corridors and enhanced institutional capacity for planning, design and risk reduction. This is to be achieved

through the restoration and rehabilitation of bridges and damaged sections of the feeder road network, and

the Windward and Vigie Highways, and the rehabilitation of river defences along the Yarabaqua and

Caratal rivers.

2. On the basis of the Report, I recommend:

(a) a loan to GOSVG of an amount not exceeding the equivalent of nine million, and forty-six

thousand United States dollars (USD9.046 mn) representing 80% of the project cost,

consisting of:

(i) an amount from the Ordinary Capital Resources of the Caribbean Development

Bank (CDB), not exceeding USD5.529 mn; and

(ii) an amount from CDB’s Special Funds Resources (SFR) not exceeding USD3.517

mn; and

(b) a grant to GOSVG of an amount not exceeding USD221,000 from CDB’s SFR for use by

GOSVG in financing the cost of equipment for rainfall and stream flow measurement, and

training of hydrological technicians;

on the terms and conditions set out and referred to in Chapter 6 of the Report.

3. Funds are available within CDB’s existing resources and/or borrowing programme for the relevant

disbursement period.

PUBLIC DISCLOSURE AUTHORISED

CARIBBEAN DEVELOPMENT BANK

STAFF REPORT

ON

NATURAL DISASTER MANAGEMENT REHABILITATION AND RECONSTRUCTION

(DECEMBER 2013 TROUGH EVENT)

ST. VINCENT AND THE GRENADINES

Considered at the Two Hundred and Sixty-Second Meeting of

the Board of Directors on July 17, 2014.

(BD50/14)

Officer-in-Charge - Deidre Clarendon

Projects Department

Division Chief - Andrew Dupigny

Economic Infrastructure Division

JULY 2014

This Document is being made publicly available in accordance with the

Bank’s Information Disclosure Policy. The Bank does not accept

responsibility for the accuracy or completeness of the Document.

Any designation or demarcation of, or reference to, a particular territory or geographic area in this Document

is not intended to imply any opinion or judgment on the part of the Bank as to the legal or other status of any

territory or area or as to the delimitation of frontiers or boundaries.

This Report was prepared by a Team comprising:

Merlyn Combie, Operations Officer/Coordinator; Anne Marie Chandler, Operations Officer (Social Analyst); Leah Bobb-

Semple, Legal Counsel; Patrick Kendall, Consultant Economist; Yuri Chakalall, Disaster Risk Management Specialist;

Albert Gillings, Operations Officer (Civil Engineer); and Karene Daniel, Coordinating Secretary.

AO - Administrative/Accounting Officer

BMCs - Borrowing Member Countries

BRAGSA - Roads, Building and General Services

CC - Climate Change

CCRIF - Caribbean Catastrophic Risk Insurance Facility

CDB - Caribbean Development Bank

CIMH - Caribbean Institute for Meteorology and Hydrology

CPA - Country Poverty Assessment

CWSA - Central Water and Sewerage Authority

DDMC - District Disaster Management Committee

DiMSOG - Disaster Management Strategy and Operational Guidelines

DRM - Disaster Risk Management

DRR - Disaster Risk Reduction

EMMP - Environmental Management and Mon

ERG - Emergency Relief Grant

EU - European Union

GDP - Gross Domestic Product

GGLA - Government Guarantee of Loan Act

GOSVG - Government of St. Vincent and the G

IDC - Interest During Construction

IMF - International Monetary Fund

IRL - Immediate Response Loan

ISP - Implementation Support Plan

mn - million

MTW - Ministry of Transport and Works

NCB - National Competitive Bidding

NDC - National Disaster Coordinator

NEC - National Emergency Council

NEDM - National Emergency and Disaster Management

NEEC - National Emergency Executive Committee

NEMO - National Emergency Management Organisation

NPDP - National Physical Development Plan

OCR - Ordinary Capital Resources

OIE - Office of Independent Evaluation

p.a. - per annum

PBL - Policy Based Loan

PC - Project Coordinator

PE - Project Engineer

PLW - Project Launch Workshop

PMD - Project Management Division

CURRENCY EQUIVALENT

Dollars ($) throughout refer to Eastern Caribbean Dollars (XCD) unless otherwise stated.

USD1.00 = XCD2.70

XCD1.00 = USD0.37

ABBREVIATIONS

Authority

PMH - Project Manager Hydrology

PPES - Project Performance Evaluation System

PT - Project Team

SFR - Special Funds Resources

SVG - St. Vincent and the Grenadines

TA - Technical Assistance

TOR - Terms of Reference

UOF - Use of Funds

USD - United States Dollars

WB - World Bank

(ii)

MEASURES AND EQUIVALENTS

1 hectare (ha)

1 kilometre (km)

=

=

2.47 acres

0.621 mile (mi)

1 square kilometre (km2) = 0.386 square mile (mi2)

1 metre (m) = 3.281 feet (ft)

1 millimetre (mm)

1 square metre (m2)

= =

0.039 inch (in)

10.756 square feet (ft2)

TABLE OF CONTENTS

COUNTRY DATA: ST. VINCENT AND THE GRENADINES

LOAN AND PROJECT SUMMARY

1. INTRODUCTION

2. THE PROJECT

3. RISK ASSESSMENT AND MITIGATION

4. THE BORROWER AND EXECUTING AGENCY

5. JUSTIFICATION AND BENEFITS

6. TERMS AND CONDITIONS

APPENDICES

1.1

1.2 1.3

2.1 2.2

2.3

2.4

2.5 2.6 2.7 2.8 2.9 2.10 2.11

2.12

2.13 2.14 4.1

SUMMARY OF DAMAGE AND LOSSES CAUSED BY DECEMBER 2013

TROUGH EVENT

SOCIAL AND GENDER CONTEXT

SUMMARY OF PREVIOUS CDB-FUNDED DISASTER MANAGEMENT

PROJECTS IN ST. VINCENT AND THE GRENADINES, 1986-2013

DETAILS OF THE PROJECT

DRAFT TERMS OF REFERENCE - TECHNICAL ASSISTANCE FOR

TRAINING OF TECHNICIANS IN HYDROLOGY TO USE, MANAGE AND

MAINTAIN ST. VINCENT AND THE GRENADINES’ NATIONAL

NETWORK OF RAINFALL AND RIVER FLOW MONITORING STATIONS

DRAFT TERMS OF REFERENCE – CONSULTANCY SERVICES FOR A

REHABILITATION AND UPGRADE STUDY FOR VIGIE HIGHWAY AND

ASSOCIATED BRIDGES

DRAFT TERMS OF REFERENCE – CONSULTANCY SERVICES TO

UNDERTAKE LANDSLIDE RISK ASSESSMENT, SLOPE STABILISATION

AND REMEDIAL DESIGN STUDY FOR ST. VINCENT’S NORTH

WINDWARD HIGHWAY CORRIDOR

PROJECT COST, FINANCING AND PHASING PLAN

DRAFT PROJECT IMPLEMENTATION SCHEDULE

IMPLEMENTATION SUPPORT PLAN

ESTIMATED QUARTERLY DISBURSEMENT SCHEDULE

PROJECT MANAGEMENT ORGANISATIONAL CHART

DRAFT TERMS OF REFERENCE - PROJECT TEAM

DRAFT TERMS OF REFERENCE - CONSULTING ENGINEERING

SERVICES FOR DESIGN REVIEW AND CONSTRUCTION SUPERVISION -

IMMEDIATE MITIGATION WORKS

DRAFT TERMS OF REFERENCE - CONSULTING ENGINEERING

SERVICES FOR DESIGN REVIEW AND CONSTRUCTION SUPERVISION -

INFRASTRUCTURE REHABILITATION AND UPGRADE

PROCUREMENT PLAN

REPORTING REQUIREMENTS

THE EXECUTING AGENCY FOR THE GRANT

FIGURE

1. PROJECT LOCATION MAP

COUNTRY DATA: ST. VINCENT AND THE GRENADINES

2009 2010 2011 2012 2013 PER CAPITA GDP (current market prices; $) 18,187 18,143 17,853 18,135 18,764

GROSS DOMESTIC PRODUCT (GDP) GDP at Current Market Prices ($mn)

Demand Components:

Consumption Expenditure

1,822.3

1,912.2

1,839.7

1,931.9

1,828.1

1,911.0

1,875.0

2,009.0

1,959.4

2,017.4

Gross Domestic Investment 438.6 464.0 440.4 443.1 519.8

Exports of Goods and Non-factor Services 519.2 494.6 493.6 508.6 526.0

Imports of Goods and Non-factor Services 1,047.7 1,050.8 1,016.9 1,085.7 1,103.8

Gross Domestic Savings Ratio (4.9) (5.0) (4.5) (7.1) (3.0)

Sectoral distribution of current GDP (%) Agriculture 6.6 6.7 6.4 7.2 5.8

Mining & Quarrying 0.3 0.3 0.3 0.2 0.2

Manufacturing 5.5 5.7 5.9 6.5 4.5

Utilities 4.6 4.4 4.2 4.9 4.1

Construction 9.6 9.1 9.3 8.3 9.2

Transport & Communication 14.7 14.6 14.4 13.9 14.6

Hotels & Restaurants 2.2 1.8 2.1 2.0 2.2

Wholesale & Retail Trade 14.9 14.9 15.0 14.6 15.5

Financial & Business Services 22.9 22.4 22.3 21.3 23.6

Government Services 16.5 17.7 17.8 19.6 19.2

Other Services 3.6 3.7 3.5 2.8 2.4

Less Imputed Service Charge 1.3 1.3 1.2 1.3 1.3

GDP at Current Factor Cost ($mn) 1,524.1 1,555.8 1,596.1 1,645.8 1673.3

GDP at constant 2006 Prices ($mn) 1,419.2 1,387.2 1,391.0 1,412.2 1456.6

Annual rate of growth in GDP (%) (2.0) (2.3) 0.3 1.5 3.1

MONEY AND PRICES ($ mn)

Consumer prices (av. annual % change)

0.4

1.5

1.7

1.0

0.8

Money supply (M1; annual % change) (7.6) (3.9) (4.0) 5.8 4.1

Total domestic credit(net) 1,029.3 891.9 906.7 959.5 998.9

Private sector (net) 936.4 953.3 971.4 1,034.3 1,047.8

Public sector (net) 86.4 (68.0) (92.6) (74.8) (48.9)

Non-bank financial institutions (net) 6.5 6.7 27.9 … …

Estimated Tourism Expenditure (USD mn) 90.1 86.2 95.3 92.0 92.3

CENTRAL GOVERNMENT FINANCES ($ mn) /3 Current Revenues 466.5 483.8 462.5 472.6 462.6

Current Grants 0.0 0.0 0.0 0.0 0.0

Current Expenditures 469.8 473.2 495.2 488.9 491.6

Current Account Surplus/ (Deficit) (3.3) 10.6 (32.7) (16.3) (29.0)

Capital Revenue and Grants 78.4 15.2 46.6 32.0 Capital Expenditure and Net Lending 106.0 78.4 63.0 54.2 60.4

Overall Surplus/ (Deficit) (30.9) (52.6) (49.1) (38.5) (89.4)

BALANCE OF PAYMENTS (USD mn) Merchandise Exports (f.o.b) 53.4 45.0 43.4 47.8 53.4

Merchandise Imports (c.i.f) 293.8 297.7 292.3 315.0 333.5

Trade balance (240.4) (252.7) (248.9) (267.2) (280.1)

Net Balance on services account 44.7 47.1 55.0 53.4 49.3

Income (net) (13.0) (17.4) (12.9) (3.8) (3.7)

Transfers (net) 11.4 10.0 7.9 24.8 24.2

Current Account Balance (197.3) (213.0) (198.9) (192.8) (210.3)

TOTAL PUBLIC DEBT (USD mn) Total public debt 428.2 445.8 458.6 501.4 539.5

Domestic debt outstanding 212.8 168.0 173.4 225.4 243.3

Long term … … … … …

Short term … … … … …

External debt outstanding 215.4 277.8 285.2 276.0 296.2

Debt Service 26.2 26.5 27.6 26.9 25.3

Amortisation 17.8 20.6 19.0 19.1 18.4

Interest Payments 8.4 7.9 8.6 7.8 6.9

External debt service as % of exports of goods and services 13.6 14.5 15.1 14.3 13.0

Total debt service as % of current revenue 21.6 25.4 25.0 24.9 28.8

AVERAGE EXCHANGE RATE Dollar(s) per US dollar 2.7 2.7 2.7 2.7 2.7

Data for 2012 are provisional.

COUNTRY DATA: ST. VINCENT AND THE GRENADINES

2009 2010 2011 2012 2013

POPULATION Mid-Year Population ('000) 100.2 101.4 102.4 103.4 104.4

Population Growth Rate (%)

Crude Birth Rate

Crude Death Rate

Infant Mortality Rate

1.2

1.0

1.0

1.0

EDUCATION

Net School Enrollment Rate (%)

Primary 87.4 89.4 … …

Secondary 77.3 98.0 … …

Pupil-Teacher Ratio Primary 17 16.0 … …

Secondary 17 18.0 … …

LABOUR FORCE

Unemployment Rate (%)

Male

Female

Participation Rate (%)

Male

Female

COUNTRY DATA: ST. VINCENT AND THE GRENADINES

1980 1990 2000 2010

INDICATORS OF HUMAN DEVELOPMENT

HEALTH

Life Expectancy at Birth (years) 67.1 70.4 69.6 70.0

Male 65.0 68.0 … 66.0

Female 70.4 72.0 … 74.0

Dependency Ratio 1.0 0.8 … …

Male 1.0 0.8 … …

Female 0.9 0.8 … …

Human Development Index … … 0.755 0.761

HOUSING AND ENVIRONMENT

Households with piped water (%) 37.8 53.8 … …

Households with access to flush toilets (%) 24.0 33.2 … …

Households with electricity (%) 37.3 66.8 … …

Environmental strategy or action plan (year prepared): 2004

Source(s): ECCB Research Dept, International Monetary Fund (IMF)

… not available

Data as at June 10, 2013

LOAN AND PROJECT SUMMARY

Financial Terms and Conditions

Borrower: Government of St.

Vincent and the

Grenadines(GOSVG)

Amortisation Period: (i) Ordinary Capital

Resources (OCR) (ii) Special Funds

Resources (SFR)

17 years (following grace

period)

20 years (following grace

period)

Implementing

Agency:

Ministry of Transport

and Works (MTW) Grace Period: (i) OCR (ii) SFR

5 years

5 years

Disbursement Period: October 30, 2014 – May 31, 2017

Source Amount (i) OCR – Loan

(ii) SFR – Loan

(iii) Grant

USD5.529 mn

USD3.517 mn

USD0.221 mn

Interest Rate: (i) OCR

(ii) SFR

3.95% per annum (p.a.) variable

2.5% p.a. fixed

Counterpart XCD5.621 mn

USD2.082 mn

Commitment Fee: 1% p.a. on the undisbursed

balance of the OCR portion of the

Loan, commencing from the 60th

day after the date of the Loan

Agreement

Total: USD11.350 mn Risk Management

Country Rating: n/a

Outlook: n/a

Limit: n/a

Overall Project/ Entity

Score:

Public Sector Lending

Approvals:

Disbursements:

Repayments:

Undisbursed:

Outstanding Loans:

Availability (Adjusted for Approvals):

Availability (Adjusted for Approvals and

Disbursements):

$268.8 mn

$230.9 mn

$94.0 mn

$39.2 mn

$136.9mn

n/a

n/a

Incremental Capital Adequacy Charge: n/a

Office of Risk Management Commentary:

This information is withheld in accordance with one or more of

the exceptions to disclosure under the Bank’s Information

Disclosure Policy.

- ii -

Project Summary

Project Outcome and Description:

The outcome of the project is improved Windward and Vigie Highway corridor resilience and enhanced

institutional capacity for planning, design and risk reduction.

The Project consists of the following components:

(a) Land Acquisition.

(b) Immediate Mitigation Works: Restoration of critical infrastructure at high risk of failure along

Windward and Vigie Highways, including slope and embankment stabilisation, bridge repairs

and construction.

(c) Rehabilitation and Upgrade Works: Road embankment and slope improvement; construction and

rehabilitation of river defences; and rehabilitation of sections of the feeder road network.

(d) Technical Assistance (TA) consisting of:

(i) Landslide Risk Assessment, Slope stabilisation and Remedial Design Study for selected

sections along the north Windward Highway corridor.

(ii) Rehabilitation and Upgrade Study for approximately 6 km of the Vigie Highway,

including 3 bridges:

(e) Hydrometric Equipment and Training of hydrological technicians.

(f) Engineering Services.

(g) Project Management.

CDB/Special Development Fund (SDF) Contributions To Country Outcomes – Key Outputs:

Social and Economic Infrastructure:

Bridges upgraded/reconstructed: 5

Secondary roads built or upgraded: 3.2 km

River training works: 40 m

Project Beneficiaries: 21,285

Exceptions to CDB Policies:

None

Gender Marker Summary:

Gender

Marker

Analysis Data Engagement Response Score Score Code

1 1 0 0 2.0 MM

MM, Marginal Gender Mainstreaming: limited potential to contribute to gender equality.

1. INTRODUCTION

BACKGROUND

1.1 Over a 24-hour period between December 24 and 25, 2013, an unseasonal low-level trough system

moving westward towards the Windward Islands chain, interacted with a mid to upper-level trough system

moving in a south to north direction (the December 2013 Trough Event). Heavy precipitation, high winds

and thunderstorm activity was generated along the eastern boundary of the trough as a result of this

interaction. The passage of the trough and accompanying torrential rainfall resulted in significant river,

flash flooding and landslide damage to mainland St. Vincent. Damage was sustained on both windward

and leeward sides of the island.

1.2 In the aftermath of extreme rainfall arising from the December 2013 Trough Event, Caribbean

Development Bank (CDB) assistance to GOSVG included: (a) an Immediate Response Loan (IRL) in the

amount of USD750,000 and (b) an Emergency Relief Grant (ERG) in the amount of USD200,000. These

funds were to assist GOSVG in the conduct of damage assessments, provision of emergency relief supplies

and humanitarian assistance, cleaning and clearing debris, as well as restoring essential services.

1.3 By letter dated February 20, 2014, GOSVG formally applied to CDB for a loan to assist in financing

a project for the rehabilitation and reconstruction of infrastructure destroyed by landslides, debris flows,

and flash and river floods resulting from the effects of the December 2013 Trough Event. The Project is of

high priority for GOSVG and is consistent with CDB’s Strategic Objective of supporting inclusive growth

and sustainable development in its Borrowing Member Countries (BMCs). The Project is also consistent

with CDB’s Corporate Priorities of promoting environmental sustainability. It is also consistent with the

strategic theme of the eighth cycle of SDF of promoting Environmental sustainability and Climate Change.

CDB, in its Country Strategy for St. Vincent and the Grenadines (2014-2018), indicated that the Bank

would support interventions that would contribute to strengthening of management capacity and the

reduction of risks in critical areas. This included support to improve climate and natural hazard resilience

of physical infrastructure.

1.4 The Project is being appraised under CDB’s Disaster Management Strategy and Operational

Guidelines (DiMSOG). The Guidelines allow the use of a Staff Report1/ to facilitate accelerated processing of loan applications.

Damage Assessment and Affected Areas

1.5 Local rainfall measurements indicate that peak rainfall intensity occurred over the 3-hour period

between 9:00 p.m. and 12:00 a.m. on December 24, 2013. Observed rainfall accumulations ranged between

163 millimetres (mm) to 312 mm at Belle Isle and Rabacca stations. Rainfall intensities were highest in

the northeastern quadrant of St. Vincent, with rainfall gauges in this area recording a maximum intensity

of 278 mm per 3-hour period. Expert opinion classified the 3-hour rainfall intensity as in excess of a

100 year return period event. Nine fatalities and 34 persons with injuries were recorded, with 3 persons

still missing.

1.6 Government declared as disaster areas, the villages of: Francois; Retreat; Vermont; Dubois; Hog

Hole; Cane Vale; Pembroke; Spring; Rose Bank; Dark View; Petit Bordel; Chateaubelair; Fitz-Hughes;

Richmond Vale; Gordon; Cumberland; and Troumaca; on the Leeward side of the island, and South Rivers,

O’Briens Valley and Spring Village, Georgetown on the Windward side. The combined impacted

1/ A Staff Report is an abbreviated appraisal report with emphasis on the impact of the event and the Government’s recovery

programme. The calculation of financial and economic rates of return as applicable for normal lending is omitted.

- 2 -

population for these areas is reported as 12,769 persons. The disaster declaration identified the event as a

level 2 disaster; a classification which indicates that national emergency response and recovery capacities

are not overwhelmed, but are limited and specialised regional and/or external assistance was requested.

1.7 Flood damage and landslides significantly impacted the transport, electricity and water sectors.

Several bridges were destroyed, roadways undermined, two hydropower-generating facilities were

disabled, and water services were cut to more than 50% of the population, due to the loss of transmission

pipes throughout the country. By January 6, 2014, service had been restored to 90% of the affected

population. Significant damage to residential housing was experienced and damage assessment reported

an estimated 662 homes damaged, of which 122 were completely destroyed. Communities most severely

affected included: Vermont; Troumaca; Spring Village; and Cumberland on the Leeward side of the island,

and South Rivers on the Windward side. (See Table 1.1). There are currently some 90 persons still in

shelters.

TABLE 1.1: HOUSING INFRASTRUCTURE AFFECTED

Level

Description

Number of

Houses

1 No significant damage – structure useable, requires minor repairs 396

2 Minor damage but structure cannot be occupied until repaired 144

3 Structure not usable and cannot be occupied until after major repairs 61

4 Structure condemned 61

Total 662

Source: Rapid Damage and Loss Assessment, January 16, 2014

1.8 Overall losses and damage are estimated at USD108.4 mn, equivalent to 15% of the 2012 gross

domestic product (GDP). Losses in the transport sector were estimated at USD82.6 mn2/or 76% of the total

losses. Damage and loss to the water, electricity generation and distribution sectors was estimated at USD4.5 mn and USD8.6 mn dollars, respectively. Estimated damage sustained at the Milton Cato

Memorial Hospital in the capital, Kingstown was USD2 mn.

1.9 The impact on the agricultural sector was primarily due to the disruption in transport access services

through the primary, tertiary and feeder road network. Agricultural production in the northern-affected

areas such as Georgetown and Sandy Bay, comprises primarily banana, root crops and vegetables. Loss of

crops and livestock and damage to agricultural feeder roads amounted to USD1.4 mn and this was unevenly

distributed across the island. Agriculture Region 3, which includes the North Windward district of the

island (Georgetown and Sandy Bay), suffered the greatest losses from the event, accounting for some 37.1%

of the total sector’s recorded damages. A detailed summary of damage and losses is presented in

Appendix 1.1.

1.10 In addition to sites located within the declared disaster areas, CDB staff visited other locations

which were also impacted by the December 2013 Trough Event. These areas included bridges at Union

along the Windward Highway; Yambou along the Vigie Highway; and Red Dog along the Teviot River.

The Yarabaqua and Caratal Rivers are both in need of river defences. In addition, feeder roads in the north

2/ Source: Rapid Damage and Loss Assessment undertaken by the World Bank (WB) with support from the European Union (EU)

in the Framework of the African, Caribbean and Pacific Group-EU Natural Disaster Risk Reduction Program managed by the

Global Facility for Disaster Risk Reduction (January 2014).

- 3 -

east of the island between Overland and Sandy Bay were visited. Sections of the Windward Highway3/ at

Orange Hill, Touruma and Magum/Overland were undermined from erosion, slope failure, and the loss of

retaining structures. Post-trough impact, bi-directional traffic flow along these sections has been

constrained to a single lane, and the risk of imminent total failure is high.

MACROECONOMIC CONTEXT

1.11 The economy of St. Vincent and the Grenadines (SVG) is small and open with a narrow resource,

production and export base, high import dependence and extreme vulnerability to external shocks, such as

the recent global recession; spikes in fuel and food prices; volatility in capital flows and natural disasters,

including hurricanes, volcanic eruptions, floods and droughts. Given the foregoing constraints and

vulnerabilities, accelerating and sustaining growth has become more difficult in the context of a more

competitive and dynamic global economy and inadequate resources to effect timely structural adjustments.

Nevertheless, as indicated by the construction of the new airport, SVG is determined to restructure its

economy, following the collapse of the banana industry, pivoting towards the further development of a

service-based economy with tourism at its centre.

1.12 Current indications are that SVG’s economy is continuing to rebound from the effects of the recent

global recession. Following average annual contraction of 1.7% between 2008 and 2010, GDP growth

accelerated from 0.3% in 2011 to 3.1% in 2013. This has occurred amidst the continuing downside risks

within dominant trading partners, notably the United States of America and the EU. While growth has

steadily improved, the continuing weakness in fiscal performance (current account, primary and overall

deficits) and the accumulation of public sector debt remain a concern.

1.13 The economic outlook is one of cautious optimism. The average annual growth forecast for the

medium term is approximately 3% with relatively stronger performance projected in 2017-2018. While the

December 2013 Trough Event would have slowed the growth trajectory somewhat, the expectation is that

the economy will continue to expand in the medium term. The forecast is premised on the gradual acceleration of the global economic recovery which, together with the completion of the Argyle

International Airport, brings expectations of some improvement in tourism sector performance; robust

investment tourism activity in the Grenadines; and an acceleration in public sector investment, given current

estimates of external grants (USD50 mn, mainly EU funds) and external loans (USD48.1 mn) over the 2013

to 2015 period including CDB loans4/.

DISASTER RISK MANAGEMENT

Emergency Management

1.14 The framework for disaster preparedness, response, planning, mitigation, and management was

established by the National Emergency and Disaster Management Act (2006), (the NEDM Act). This is

executed through the National Emergency Management Organization (NEMO), consisting of a National

Emergency Council (NEC), National Emergency Executive Committee (NEEC), and District Disaster

Management Committees (DDMC). The NEC is chaired by the Prime Minister and is composed of

ministers, permanent secretaries, district representatives and key ex-officio members from government

agencies, and corporations. The NEEC monitors progress on national disaster policy implementation and

provides technical implementation supervision on behalf of the NEC. DDMC’s function at the local level

3/ The Windward Highway is a two-lane wide, critical north-south coastal transit corridor for eastern St. Vincent, connecting rural

northern and central settlement areas to the capital Kingstown.

4/ National Economic and Social Development Plan, p.134.

- 4 -

and operate to implement planning and disaster response operations in their respective districts.

Additionally, local disaster committees have been organised to operate at the community level.

1.15 According to SVG’s National Disaster Plan (2005), upon the declaration and/or imminent threat of

a disaster, the National Emergency Operations Centre is activated under the direction of the Prime Minister,

by the National Disaster Coordinator (NDC) or designate. NDC is responsible for coordination of all

response and relief activities under the NEDM Act. Management and coordination of emergencies in SVG

is complicated by the spatial dispersion of the country, which comprises some 32 islands and cays.

1.16 SVG has had catastrophic insurance for hurricanes and earthquakes with the Caribbean

Catastrophic Risk Insurance Facility (CCRIF) since the inception of the Facility in 2007. The December

Trough Event did not generate wind speeds significant enough to trigger a CCRIF payout to GOSVG under

its tropical cyclone policy coverage. Had GOSVG procured policy cover under CCRIF’s new excess

rainfall product, it may have been eligible for a payout dependent on the rainfall parametric trigger points

selected under such policy cover.

Disaster Risk Reduction

1.17 Hazard analysis and experience shows that SVG is vulnerable to a variety of rapid onset hazards

including hurricane, storm surge, terrestrial flooding, volcanic eruption, earthquake, landslide, rock-fall,

tsunami and slow onset hazards such as drought. SVG is exposed to a number of anthropogenic hazards

such as marine traffic accidents and oil/chemical spills. SVG is located in a seismically active zone along

the eastern margin of the Caribbean tectonic plate. This, along with the location of La Soufriere, one of the

more active volcanoes in the Region, on the northern portion of the mainland St. Vincent, renders the island

particularly vulnerable to shallow seismic activity.

1.18 St. Vincent is characterised by steep inland topography with much of the population being

concentrated in coastal communities that are vulnerable to extreme wave events and storm surges as well

as flash flooding from riverine overflow and terrigenous runoff, associated with intense or high volume

precipitation events.

1.19 Disaster risk is likely to be further exacerbated by climate change (CC) and climate variability

trends. Consistent with the projected global median, CC models have forecasted that SVG will undergo

both warming and drying trends, with more frequent heat waves, droughts and high intensity rainfall events.

Increases in mean sea surface temperatures are also expected to increase storm intensities as well as storm

surges.

1.20 SVG is challenged in terms of data collection for rainfall and water level monitoring in its rivers.

Greater and more spatially representative network coverage is required for both rainfall gauges and water

level monitors. The Water Resources Management Unit (WRMU) of the Central Water and Sewerage

Authority (CWSA) maintains the largest active network of rainfall and water level monitoring stations on

the island. CWSA is a statutory corporation established in 1970, under the revised CWSA Act of 1991. A

total of six (two rainfall and four river flow) Central Water and Sewerage Authority (CWSA) maintained

monitoring stations were lost as a result of the passage of the December 2013 Trough Event. Capacity

deficits in both the current national network coverage and the quality of data collected by existing field

instrumentation, limit the development of resilient site specific infrastructure design, flood hazard,

emergency management and reduction plans. These deficits also restrict the potential for development of

early warning systems. Network coverage in the north of the island is particularly limited.

1.21 The challenges in data capacity, quality and management at the national level further impacts

analysis of hydro-meteorological data at a regional level, a function that is executed by the Caribbean

- 5 -

Institute for Meteorology and Hydrology (CIMH). CIMH maintains an archive of meteorological and

hydrological data from member countries of the Caribbean Meteorological Organisation, including SVG.

On behalf of GOSVG, CWSA currently and routinely provides hydro-meteorological data to CIMH.

1.22 GOSVG recognises that Disaster Risk Management (DRM) and disaster risk reduction (DRR) are

key elements in its sustainable development strategy. GOSVG’s DRM agenda is guided by the NEDM

Act, and the National Disaster Plan. GOSVG is a signatory and subscribes to the regional results-based

CARICOM Enhanced Comprehensive Disaster Management Framework (2014-2024). National progress

in hazard mapping has been limited but is improving, and sector mainstreaming of DRR in policies, plans

and in practical implementation is still in early development. NEMO has been successful in increasing the

public’s sensitisation and awareness of natural hazards and the need for individual and household

preparedness. GOSVG has been able to develop building code legislation as well as conduct standardised

vulnerability assessments of the health sector.

1.23 Over the period 2011 to 2013, GOSVG benefited from $5 mn of WB-financed disaster reduction

interventions under the Hurricane Tomas Emergency Recovery Loan. Under the Loan: (i) three schools

and three community centres, used as public emergency shelters, were rehabilitated; (ii) 30 metres of river

defence/bank stabilisation was constructed; (iii) 17 GOSVG officials were trained in Geographic

Information Systems mapping; and (iv) seven hazard maps were produced. GOSVG is expected to further

benefit from the findings of a flood risk reduction and hydraulic study for several windward watersheds

which is currently underway as part of the CDB-financed Hurricane Tomas RRL approved by the Board of

Directors in July 2011. This TA is expected to enhance GOSVG’s capacity to better manage flood hazards

through risk mapping, and the identification of cost-effective remedial civil works and non-structural

mitigation for drainage improvement. In May 2014, WB approved some USD35.6 m for a Regional

Disaster Vulnerability Reduction Project Loan in response to the impact of the December 2013 Trough

System. GOSVG is expected to benefit from this Facility, with impacted sites on the Leeward side of the

island, being targeted.

1.24 With support from the WB Regional Disaster Vulnerability Reduction Programme (RDVRP) and

Climate Investment Fund, Pilot Programme for Climate Resilience, GOSVG is currently developing a new

national physical development plan (NPDP) for the period 2014 to 2024, for which the methodological

framework has been elaborated. Building future resilience to natural hazards and CC is identified as a key

strategic planning priority to be addressed in the development of NPDP, going forward.

SOCIAL CONTEXT

1.25 The project sites are located on the eastern side of the island, in the Census Division of Sandy Bay,

Georgetown, Marriaqua, and Bridgetown. Preliminary documentation from the 2012 population and

housing census of SVG, recorded an aggregate population of 21,285 persons resident in the 4 electoral

districts (See Table 1.2). Communities in these districts, are located in sections of the island where the

highest concentrations and most severe states of poverty were recorded during the 2008 Country Poverty

Assessment (CPA). Poverty in Georgetown and Sandy Bay was recorded at 55.6%, Marriaqua, almost 30%

(29.6%), while poverty in Bridgetown was recorded at 24.0%.

- 6 -

TABLE 1.2: HOUSEHOLD POPULATION BY ENUMERATION DISTRICT

Census Division

Population

Male Female Total

Sandy Bay 1,374 1,232 2,606

Georgetown 3,596 3,453 7,049

Marriaqua 3,916 3,882 7,798

Bridgetown 1,958 1,874 3,832

TOTAL 10,844 10,441 21,285

1.26 Communities in the Project catchment areas display similar characteristics at varying levels (see

Appendix 1.2 for details). Residents are still recovering from the adverse impacts of the December 2013

Trough Event. For some, recovery has been extremely slow, having not recovered from previous shocks

to the island’s economy, including the impacts of previous natural disasters.

1.27 The vulnerability of both the Vigie and Windward Highways is a result of the island’s topography,

coupled with poor settlement, agriculture and development practices. The Windward Highway connects all

communities on the eastern half of the island to the principal centre of economic and social services and

the centre of commerce, in Georgetown and Kingstown. The Vigie Highway is a south-west to north-east

oriented transport corridor linking Kingstown to the Windward Highway at Peruvian Vale. It also provides

redundancy to the main north-south Windward Highway offering the central and north windward

communities north of Peruvian Vale a shorter, alternative cross-country route of accessing Kingstown, the

capital. En route to Kingstown, the Vigie Highway traverses an urban commercial settlement node, locally

known as “Mespo” (Marriaqua) at a complex junction of four roads, and three river-spanning bridges

(Teviot, Zenga & Yambou). The junction is a busy, high traffic area, at which a health centre, abattoir,

police station, doctor’s office, community centre, church, and school are located. Three secondary schools

and three primary schools are located within a 0.5 km radius of the junction. Physically, the junction serves

as a central transport hub, for school children and other commuters, into Kingstown as well as to more rural

areas.

1.28 Marriaqua and Bridgetown are in the Agriculture Region, Region 2. Marriaqua is particularly

important as Mesopotamia Valley, the breadbasket of St. Vincent is located in Marriaqua. Mespotamia

Valley is very fertile, with farmlands where root crops, fruits, vegetables and spices are grown. The area

is essential to food security in the country. Sections of the Valley are heavily prone to flooding, land

slippage and rock falls, exacerbated by human factors such as the dumping of waste in the water ways,

lack of river maintenance, squatting on river banks for settlement and agricultural activity, and irresponsible

farming practices on steep slopes. Most of the essential services of Marriaqua are located in the major flood

zone where the Zenga, Teviot and Yambou meet.

GENDER CONTEXT

1.29 There was no reliable social or sex disaggregated data presented on the impact of the event. This

makes attempts to formulate a vulnerability profile of different groups of men and women in the targeted

project areas difficult. NEMO confirmed that the poor in SVG are considered the most vulnerable to natural

disasters. The 2008 poverty assessment described persons living in poverty and most vulnerable to poverty

as persons from rural communities, especially the banana farming population, persons from large families,

and members of female single parent/female headed households. It is expected that recommendations and

- 7 -

data collected from the Country Gender Assessment currently being conducted in SVG will be used to

construct baseline data for the project.

1.30 Unsustainable development practices and poor living conditions, contributed to the intensity of

destruction and loss, as well as the capacity of the population on the eastern side of the island to recover

from the event. These conditions persist and recurrent events of this nature, have resulted in irreversible

social dislocation for a number of households. Mitigation measures to reduce land slippage and flooding

are essential to minimize these adverse impacts, promote economic growth, and for poverty reduction in

affected areas. These measures will however need to be accompanied by holistic interventions that monitor

and mitigate social practices that will affect the sustainability of the interventions implemented, supporting

the need for studies in project sites that raise the greatest concerns.

PREVIOUS CDB-FUNDED DISASTER MANAGEMENT PROJECTS

1.31 CDB has approved a total of USD15.94 mn for disaster management projects and related activities

in SVG over the period 1986-2013. Appendix 1.3 presents a listing of projects undertaken over that period.

In 2011, the largest intervention so far, was approved. This was a Rehabilitation and Reconstruction Loan

(RRL) amounting to USD12.6 mn, to assist with the rehabilitation and reconstruction of critical

infrastructure damaged by Hurricane Tomas.

1.32 Although the Loan Agreement was signed in November, 2011, conditions precedent to first

disbursement were not satisfied until January 2013, with the first date of disbursement being March 2, 2013.

This delay in implementation was due to a number of reasons, including difficulty experienced in procuring

a Project Coordinator (PC), a condition precedent to first disbursement. GOSVG had great difficulty in

attracting suitable candidates, based on the remuneration package proposed. Having exhausted available

avenues, GOSVG sought to fill the position through secondment of staff. Since the appointment of PC

in 2013, some progress has been made. Tender documents have been prepared for some of the works

packages, and bids are due by the end of June 2014. It is expected that construction of works will start in

the third quarter of 2014. Of the two TA’s which were components of the RRL, one, the Coastal Study of

Sandy Bay and Dark View, has been completed, and the resulting recommendations are being used to

inform the design of two capital projects, one under the RRL (Tomas), and another being funded by the

World Bank. The Final Report for the other TA, “A Hydraulic Assessment for Flood Risk Reduction” is

expected in the third quarter of 2014.

LESSONS OF EXPERIENCE

1.33 The lessons of experience that apply to this Project have been taken from the Assessment of CDB

Natural Disaster Risk Management Assistance for its BMCs5/, the Country Assessment Report for SVG6/

and the recent experience with the RRL for the Hurricane Tomas event. The key lessons learned are

summarised as follows:

(a) human resource constraints contribute to the slow pace of project implementation and the

effectiveness of the intervention; and

5/ Le Groupe-conseil baastel Itee and Environmental Solutions Limited. Assessment of the Caribbean Development Bank's Natural

Disaster Risk Management Assistance for its Borrowing Member Countries – (1998-2006). April 2009.

6/ Le Groupe-conseil baastel Itee and Environmental Solutions Limited. Assessment of the Caribbean Development Bank's Natural

Disaster Risk Management Assistance for its Borrowing Member Countries – (1998-2006). Country Assessment Report -

St. Vincent and the Grenadines. October 2008.

- 8 -

(b) infrastructure DRM projects and TA provide an opportunity to raise awareness with respect

to the connection between DRM and development activities and to strengthen risk

reduction capacity, and this contributes to the sustainability of the intervention.

1.34 The lessons reflected in the Project design are as follows:

(a) the project management arrangements address MTW’s staffing limitations through the

establishment of a dedicated project team in the Ministry’s Project Management

Division (PMD), to be funded from loan resources. This team will be responsible for

project implementation, reporting and monitoring. The team will help to address the

Ministry's technical human resource capacity constraints; In addition, given the difficulty

in recruiting a PC for the last RRL, the proposed remuneration package has been enhanced

in order to attract a PC with the requisite skills to implement the project.

(b) institutional strengthening and TA components will support and strengthen capacity in

SVG for effective management of landslide hazards as well as improving the capacity for

better management of flood risk hazards.

2. THE PROJECT

OUTCOMES

2.1 The outcome of the Project is: Improved Windward and Vigie Highway corridor resilience and

enhanced institutional capacity for planning, design and risk reduction.

2.2 This is to be achieved through: (a) restoration of road sections and bridge structures with immediate

risk of failure on the Windward Highway and the Vigie Highway; (b) the reconstruction of critical

infrastructure on the Windward corridor to higher standards using information from current studies;

(c) undertaking a rehabilitation and upgrade study of a section of the Vigie Highway; (d) undertaking a

landslide risk assessment and slope stabilisation study along sections of the North Windward Highway

corridor; and (e) providing equipment for rainfall and stream flow monitoring and for training in hydrology.

A Design and Monitoring Framework summarising the characteristics of the Project is presented in

Table 2.1.

RATIONALE

2.3 Landslides, rock and debris flows, river and flash floods were the major causes of damage and

losses, fatalities and injuries, during the December 2013 Trough Event. There remains an immediate threat

of failure to critical infrastructure along both the Vigie and Windward Highways. Along the Vigie highway,

sections at high risk are the Yambou, Teviot and Zenga Bridges and the road embankment at Glenside.

Along the Windward highway, embankment sections at Tourama, and Magum have failed and threaten the

total collapse of the road. Urgent intervention is needed to address these sections.

2.4 The Windward Highway is a critical north-south coastal transit corridor for eastern St. Vincent,

connecting rural northern and central areas to the capital, Kingstown. Redundancy is limited along this

corridor and, where available, is restricted to some secondary and agricultural feeder roads oriented parallel

to and inland of the Highway. As a consequence of landslides that occurred along the North Windward

Highway at Orange Hill, Touruma and Magum, access to and egress from the poor and vulnerable

communities of North Windward is threatened.

- 9 -

2.5 The Vigie Highway is a critical transportation corridor that meanders through the Mesopotamia

community crossing three rivers, the Yambou, the Teviot and the Zenga. The Yambou, Teviot and Zenga

Bridges are located in very close proximity to public institutions such as a health centre, three primary

schools and a police station. The Teviot and Zenga bridge crossings are major elements in the transportation

link which enables residents from the poor and vulnerable communities of Marriaqua to access transport.

Hydraulic models from a current CDB-financed study7/ indicate overtopping of all three bridge structures for rainfall events with a 1 in 25-year frequency which is consistent with what occurred during the

December 2013 Trough Event. All three structures sustained major structural damage as a result of high

velocity flows and transported boulders and debris and are in urgent need of remedial works.

2.6 Some of the feeder roads in the north and central windward districts were severely damaged, thus

affecting the transportation of produce to the Kingstown markets. In addition, since some of the feeder

roads provide redundancy8/ within the North Windward Highway corridor, the failure of these roads, as

well as that of critical parts of the Highway as occurred during the December 2013 Trough Event, resulted

in many northern communities becoming inaccessible.

2.7 A number of rainfall gauges and water level monitoring stations maintained by CWSA were lost

during the December 2013 Event. These exacerbated the problem faced by GOSVG in terms of data

collection for rainfall and water-level monitoring of the rainfall gauges. Capacity deficits in both the current

national coverage and the quality of data collected by existing field instruments limits the availability of

site specific design information. This information is critical for flood hazard, emergency management and

reduction plans, as well as for facilitating the development of early warning systems.

LOCATION OF THE PROJECT

2.8 The Project Location Map is presented at Figure 1.

PROJECT DESCRIPTION

2.9 The Project consists of the following:

(a) Land: Land acquisition of approximately 370 m2 of private property to facilitate slope and

embankment rehabilitation at the Magum site adjacent to the North Windward Highway.

(b) Works Package 1a and 1b: Immediate Mitigation Works: Restoring of critical

infrastructure at high risk of failure. This includes:

(i) slope and embankment stabilisation and rehabilitation works at selected critical

sites along Windward and Vigie Highways;

(ii) reinstallation of guardrails and carrying out structural repairs to bridges at

Yambou, Teviot and Zenga bridges on the Vigie Highway and bridge rehabilitation

at Union on the Windward Highway; and

(iii) Construction of a bridge at Red Dog in Mesopotamia.

7/ Hydraulic Assessment and Flood Risk Reduction Study.

8/ Alternative roadways.

TABLE 2.1: DESIGN AND MONITORING FRAMEWORK

- 10 -

Narrative Summary Objectively Verifiable Indicators Means of Verification Assumptions/Accountabilities

1. IMPACT:

Contribute to increased resilience to natural disasters in

the transport and agricultural sectors in St Vincent.

1. Sectoral and other losses associated with

flood and landslide hazards reduced from 15% of GDP to 10% by December 2018.

1. SVG’s Annual Statistical and

Economic Reports.

2. Macro Socio-Economic and

Environment Assessments of

damage and loss caused by weather-related events.

1. Stable macro-economic environment.

2. OUTCOMES:

(a) Improved Windward and Vigie Highway corridor resilience and enhanced institutional capacity for

planning, design and risk reduction.

1. Reduction in the number of working days lost

at impacted sections due to landside and flood-

related traffic disruptions, by 50% by January

2018.

2. 50% of study recommendations used by

GOSVG by 2018.

3. 50% increase in hydro-meteorological data

capture, use and analysis by GOSVG agencies

1. MTW reports.

2. NEMO damage assessments 3. MTW design reports

4. CDB’s ex-post evaluation reports.

5. Hydrometric equipment inventory

6. Post disaster socio-economic

damage and loss assessments.

7. Project Completion Reports (PCR).

1. GOSVG support for comprehensive

disaster management strategies and

plans.

2. GOSVG implements recommendations of risk assessment study.

3. GOSVG commitment and availability of resources to implement recommendations.

3. OUTPUTS:

Infrastructure Works:

1. Infrastructure Works at imminent risk of failure

rehabilitated.

2. Infrastructure Works reconstructed and upgraded.

3. Essential Hydrometric Equipment Installed.

1. Works Package 1 along the Windward and

Vigie Highway completed by December 31,

2015.

2. Work Package 2 in the Windward Districts completed by February 2017.

3. Work Package 3 along the North Windward Highway completed by September 2016.

4. Hydrometric equipment installed by June

2015.

1. Site inspections. 2. Consultant’s Supervision

Reports.

3. PC’s reports. 4. Final Report of Risk Assessment

Studies.

5. Engineering Consultant’s PCR.

1. MTW adequately maintains project

infrastructure.

2. Infrastructure works effectively completed.

TA – Studies:

1. Recommendations for enhanced rehabilitation and

upgrade of 6 km of transportation corridor of the Vigie Highway.

Final consultancy report completed by

September 2015.

Project Coordinator Report. 3. GOSVG accepts recommendations of

landslide risk assessment study.

2. Recommendations for enhanced resiliency to landslide

and slope instability selected sites along the North Windward Highway.

Final risk assessment studies on landslide and

slope instability completed by September 2015.

PC’s Report. 4. GOSVG accepts recommendations of landslide and slope instability study.

Certified staff in Hydrology. 1. Issued CIMH Mid-level certificate in

Hydrology – one Technician.

2. Issued CIMH diploma in Hydrology – one

Technician.

Certificate received. Deployment of trained persons in appropriate positions.

TABLE 2.1: DESIGN AND MONITORING FRAMEWORK - 1

1 -

Narrative Summary Objectively Verifiable Indicators Means of Verification Assumptions/Accountabilities

4. Activities/Inputs $’000 1. Consultant’s Monthly Progress

Reports.

2. Project Manager’s reports.

3. CDB Site supervision visits.

4. Quarterly Reports on Investment

Costs.

5. CDB disbursement records.

1. GOSVG counterpart contribution available.

2. No major adverse weather

conditions.

3. Timely requests for disbursement of

funds.

Item Total

CDB

GOSVG OCR GRANT SFR

1. Infrastructure 17,603 11,271 - 2,577 3,755

2. Services 7,098 - 556 5,585 957

Sub-Total 24,701 11,271 556 8,162 4,701

3. Contingencies 4,664 2,724 41 990 909

4. Financing Charges 1,279 934 - 344 -

Total Project Cost 30,644 14,929 597 9,496 5,621

Project Outcome Indicators

Baseline

2014 Year 1 Year 2 Year 3

Report and

Frequency

Responsibility for

Data Collection

1. Reduction in costs for infrastructure damage due to flooding and 21 mn 0 5 7 Annual MTW landslide events in project areas.

2. Reduction in the number of working days lost due to landsides related 3 0 2 1 Annual MTW

traffic disruptions. 3. Hydrology equipment installed (rainfall and water level monitoring

gauges) by June 2015.

16 26 34 Annual MTW

Intermediate Results for Components: (%) (%) (%)

Component 1: Infrastructure Works

- 40 60 100 Progress Reports PC 1. Works Package 1 along the Windward and Vigie Highway completed

by December 31, 2015.

2. Work Package 2 in the Windward Districts completed by February - 40 60 100 Progress Reports PC

2017.

3. Work Package 3 along the North Windward Highway completed by - 40 60 100 Progress Reports PC

September 2016.

4. Hydrometric equipment Installed by June 2015 - 50 100 Progress Reports PC

Component 2: TA

- 70 100

-

Supervision Reports PC 5. Rehabilitation and Upgrade Study for the La Croix to Peruvian Vale

section of the Vigie Highway.

6. Risk assessment studies to identify feasible recommendations on - 70 100 Supervision Reports PC

managing landslide and capacity building for MTW.

- 12 -

(c) Works Packages 2: Infrastructure Rehabilitation and Upgrade: This comprises:

(i) construction and rehabilitation of river defences along sections of Caratal and

Yarabaqua rivers; and

(ii) rehabilitation of 3.2 km of agriculture feeder roads;

(d) Works Packages 3: Infrastructure Rehabilitation and Upgrade – Orange Hill: This

comprises road embankment and slope improvement at Orange Hill on the Windward

Highway;

(e) TA consisting of:

(i) Landslide Risk Assessment, Slope Stabilisation and Remedial Design Study for

selected sites along the North Windward corridor. The selected sites are: Orange

Hill; Soldier Hill; Windblow; Owia; Bloody Bridge Point Hill; Boat Bay; and

Spring;

(ii) Consultancy Services for the Preparation of a Rehabilitation and Upgrade Study

for 6 km of road from La Croix to Peruvian Vale along the Vigie Highway

including associated bridges;

(iii) Institutional Strengthening, including the procurement of hydrologic equipment

for rainfall and stream flow measurement for use by the Water Resources Unit

based at CWSA; and training of hydrological technicians;

(iv) Engineering consultancy Services for the design of the infrastructure works and

supervision during construction; and

(v) Project Management - a project team within MTW’s PMD to manage the

implementation of all activities related to the Project.

2.10 Further details of the Project are presented in Appendix 2.1. Draft Terms of References (TOR) for

the Training of Hydrological Technicians. Consultancy Services for undertaking a Rehabilitation and

Upgrade Study for Vigie Highway and Associated Bridges, and Landslide Risk Assessment and Slope

Stabilisation Study are set out at Appendices 2.2, 2.3 and 2.4, respectively.

DESIGN CONSIDERATIONS

2.11 Appropriate local and international design standards and guidelines will be used in the design of

roads, drainage elements, river defence, and retaining structures. These will be prepared by suitably

qualified and experienced engineering consultants under the supervision of MTW.

2.12 The inputs for the design for the La Croix to Peruvian Vale section of the Vigie Highway would be

informed by the evidence-based decisions made by MTW after receiving recommendations from the

Hydraulic Assessment and Flood Risk Reduction Study currently being executed under CDB’s Natural

Disaster Management RRL Hurricane Tomas/North Windward Project, due to be completed by the third

quarter of 2014.

2.13 The proposed Landslide Risk a Slope Stability TA when completed is also expected to propose

long-term mitigation measures to the potential impact of landslides along the Windward Highway.

- 13 -

PROJECT COST

2.14 The Project is estimated to cost $30.644 mn. Estimates of the cost for rehabilitating and

reconstructing roads, bridges, and river defenses, are based on tender prices for similar work currently

being carried out in SVG. CDB staff have reviewed these estimates and are satisfied that they are

reasonable and have appropriate levels of contingencies. Table 2.2 presents a summary of the estimated

costs of the project components and the details of the cost, financing and phasing of the Project are

provided at Appendix 2.5.

TABLE 2.2: SUMMARY OF PROJECT COST AND FINANCING

Item

Total

CDB

GOSVG OCR SFR GRANT

1. Infrastructure 17,603 11,271 2,577 - 3,755

2. Services 7,098 - 5,585 556 957

Sub-total 24,701 11,271 8,162 556 4,712

3. Contingencies 4,664 2,724 990 41 909

4. Financing Charges 1,279 934 345 - -

Total Project Cost 30,644 14,929 9,497 597 5,621

USD Equivalent 11,350 5,529 3,517 221 2,082

% Financing 100 49 31 2 18

FINANCING

2.15 The Project will be financed by:

(a) a loan from CDB to GOSVG of an amount not exceeding the equivalent of

USD9.046 mn representing 80% of the project cost, comprising USD5.529 mn from

CDB's OCR and USD3.517 mn from CDB's SFR, to assist with financing the

infrastructure works, TA, engineering services, project management and finance

charges;

(b) a grant of USD221,000 from CDB’s SFR to fund institutional strengthening; and

(c) counterpart funding of the equivalent of USD2.082 mn to assist with financing the cost

of the infrastructure works, TA, engineering services, and project management.

The proposed OCR loan is repayable in 22 years, inclusive of a grace period of 5 years. The OCR

interest rate is variable and is currently 3.95%. A commitment charge of 1% p.a. is payable on the

undisbursed balance of the OCR loan from on the sixtieth day after the date of the Loan Agreement.

The SFR portion of the loan is repayable in 25 years, inclusive of a grace period of 5 years. The SFR

interest rate is fixed at 2.5% p.a.

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

- 14 -

IMPLEMENTATION

2.16 The Project will be implemented by MTW’s PMD. The project will be implemented over a

36- month period commencing September 2014, and ending May 2017. The proposed Project

Implementation Schedule is presented in Appendix 2.6 and the Project Implementation Support Plan is

set out at Appendix 2.7.

DISBURSEMENT

2.17 Disbursement of the Loan will be made in accordance with CDB’s Guidelines for the

Withdrawal of Proceeds of the Loan. It is expected that the first disbursement from the Loan will

be made by October 30, 2014, in respect of Project Management. The Loan is expected to be fully

disbursed by May 31, 2017. An Estimated Quarterly Loan Disbursement Schedule is presented at

Appendix 2.8.

2.18 Disbursement of CDB Grant funds for the provision of training for CWSA hydrological

technicians will be made subject to providing that formal identification of candidate students for the

CIMH mid and Diploma-level technician training programme. It is expected that first disbursement of

the Grant will be made by March 31, 2015, and is expected to be fully disbursed by August 31, 2016.

PROJECT MANAGEMENT

2.19 All major roads, drainage and infrastructure construction works are the responsibility of

MTW. PMD, within MTW, reports directly to the Chief Engineer who reports to the Permanent

Secretary, MTW. PMD is organised into project teams responsible for the implementation of civil

and building projects funded through external agencies. It is proposed that the project management

function be housed in the existing PMD within MTW. Based on the current workload of PMD, and

further to discussions between CDB and MTW, it is the opinion of CDB staff that an additional Project

Team (PT), comprising a Project Coordinator (PC) (as team leader), one Project Engineer (PE), a Project

Manager Hydrology (PMH) and an Administrative/Accounting Officer (AO), will be required to

effectively manage the proposed Project. CDB will finance the PC, and PE and GOSVG will provide

the AO. The qualifications and experience of PT must be acceptable to CDB as well as any persons

subsequently engaged or assigned to posts with PT.

2.20 It is condition precedent to first disbursement of the loan that GOSVG select and engage in accordance with the procurement procedures applicable to the loan, the services of PC. PC will report to the Chief Engineer of MTW and will be responsible for coordinating, monitoring and managing all aspects of the implementation of the project.

2.21 The PT will manage all aspects of the implementation process, including supervision of engineering consultants, the procurement of hydrology equipment and securing training of two staff members of CWSA. GOSVG shall procure that CWSA assign PMH. PMH will facilitate the work of the suppliers to make available relevant information and to facilitate the completion of the exercise. PMH will act as a liaison between the suppliers and GOSVG officials and report to the PC. The PC will provide a report to CDB confirming equipment supplied and installed. GOSVG will be responsible for providing suitable accommodation, transportation, office equipment and supplies for PT. The proposed management structure is presented in Appendix 2.9. 2.22 It will also be a condition precedent to disbursement, in respect of construction works, that

GOSVG select and engage, in accordance with the procurement procedures applicable to the Loan, the

- 15 -

services of one PE, whose qualification and experience is acceptable to CDB. The PE will report to PC,

with specific responsibilities for assisting PC with supervising the consultants and managing the

implementation of construction works under the Project. The TOR for the PC, PE and AO are set out at

Appendix 2.10.

CONSULTANCY SERVICES

2.23 GOSVG will be required, before any disbursements for the construction works, to engage

consultants in accordance with the procurement procedures applicable to the Loan for the

engineering services required in relation to the works as specified in Appendices 2.11, 2.12 and 2.4.

2.24 It will be a condition precedent to the disbursement with respect to the immediate mitigation

works (Works Package 1a and 1b) that GOSVG engage consultants, whose qualifications and

experience are acceptable to CDB, to provide the engineering services specified in Appendices 2.11.

2.25 It will also be a condition precedent to the disbursement with respect to the infrastructure

rehabilitation and upgrade works (Works Package 2 that GOSVG engage consultants whose

qualifications and experience are acceptable to CDB, to provide the engineering services specified in

Appendices 2.12.

2.26 GOSVG will also be required, to engage the services of Consultants for each TA in

accordance with the procurement procedures applicable to the Loan. The cost of these services will be

financed by CDB. (Responsibilities of these Consultants are set out at Appendices 2.3 and 2.4). It will

be condition precedent to the disbursement with respect to the infrastructure rehabilitation and upgrade

works (Works Package 3 – Orange Hill) that GOSVG engage consultants whose qualifications and

experience are acceptable to CDB, to provide the engineering services specified in Appendices 2.4

PROCUREMENT

2.27 Procurement of capital works and consultancy services will be in accordance with

CDB’s DiMSOG. The Procurement Plan is provided at Appendix 2.13.

ENVIRONMENTAL ASSESSMENT

2.28 The Project is not anticipated to have any significant adverse environmental impacts including impacts on critical or other natural habitats. The works proposed involve de-silting; retraining and stabilising distal sections of the Caratal and Yarabaqua Rivers; controlling erosion; rehabilitating feeder roads; constructing retaining structures and stabilising slopes along existing roadways; and reconstructing bridges at: Union River along the Windward Highway; Yambou River along the Vigie Highway; and Red Dog along the Teviot River. Slope stabilisation and flood management measures will result in positive impacts through reduction of public safety risk, livelihood loss, property and environmental damage.

2.29 The Project will contribute positive long-term development impact, by improving institutional and technical capacity for landslide risk assessment and slope stabilisation along the primary road network in the north windward area. Improved capacity is expected through enhanced mapping, analysis and assessment of: slope stability, drainage and geotechnical conditions, levels of risk, primary and secondary causal factors of slope movement, and development of cost effective slope stabilisation, protection and landslide remediation measures. Further, the Project will upgrade and expand the national network of water level and rainfall monitoring stations in SVG, and improve institutional capacity for monitoring to: better manage flood hazard risk; enhance evidence-based physical planning; and provide data to facilitate more optimal, site-specific design of future mitigation

- 16 -

infrastructure. The rehabilitation and upgrade study for the Vigie Highway and associated bridges is expected to identify climate vulnerabilities, appropriate least- cost resilience measures and levels of acceptable risk that will deliver a degree of climate proofing over the expected design life of the proposed highway improvement.

2.30 The potential adverse environmental impacts related to the proposed works which are likely

to occur during the construction period include:

(a) pollution from fugitive dust emissions during loading, unloading and the transportation

of construction material;

(b) noise pollution;

(c) improper disposal of waste, excavated construction spoil and silt material;

(d) contamination and siltation of riverine and marine environments due to runoff from

river- training activities;

(e) erosion and sedimentation from exposed surfaces during construction;

(f) traffic delays; and

(g) public and worker safety.

2.31 Construction-related adverse environmental impacts which are likely to occur are expected to

be short term and can be effectively managed with the adoption of appropriate mitigation measures

during construction, supplemented by effective monitoring and supervision during implementation.

The project design process will include an analysis of alternatives for construction works that will be

reviewed for potential impacts and enhanced environmental sustainability. A draft Environmental

Management and Monitoring Plan (EMMP) will be prepared by the Engineering Consultants during the

detailed design stage. Appropriate provisions of the EMMP, which are designed to mitigate the

construction impacts, will be included in the technical specifications of the bid documents and itemised

for contractor pricing in the Bills of Quantities of the bidding documents for the various works

contracts. Contractors will be required to identify and develop operational plans on how they propose to

implement the works.

2.32 The technical specifications to be included in the bidding documents for the works, will

include, but not be limited to, requirements for: (i) management of waste, construction materials and silt,

including transportation and disposal; (ii) siltation control; (iii) noise and dust abatement; (v) traffic

management; and (v) health and safety considerations.

ENVIRONMENTAL MONITORING

2.33 During construction, the Supervising Engineering Consultants will be required to monitor and

report on the contractors’ operations for conformance with the mitigation measures stipulated in the contract

documents. CDB staff will provide general oversight of the environmental aspects of project

implementation.

- 17 -

PERFORMANCE EVALUATION RATING

2.34 The existing composite performance rating based on CDB’s Project Performance

Evaluation System (PPES) has been estimated at 6.0. This is a highly satisfactory rating. The details of

the ratings of the PPES are presented in Table 2.3.

TABLE 2.3: PROJECT PERFORMANCE EVALUATION

Criteria Score Justification

Strategic

Relevance

7.0 The Project is of high priority for GOSVG as it contributes to the

country's recovery efforts following the passage of the December 24-25,

2013 trough event whilst reducing risks associated with landslide and

flood hazards.

Poverty

Relevance

6 The rehabilitation of critical economic infrastructure will facilitate the

restoration of feeder roads and the enhancement of livelihoods of the

farming community in the project area. The area has the highest poverty

level in the country and a population that is vulnerable to landslides and

flooding. The Project will contribute to a reduction in the vulnerability

by minimizing the losses suffered by households during such events.

Some employment for skilled and unskilled labour will be realized during

the construction period.

Efficacy 6 The Project is highly likely to meet its stated physical and institutional

objectives. The designs for the roads, bridges and river defences, will

take into account the need for rehabilitated infrastructure to be able to

withstand similar heavy rainfall events; in addition, through the provision

of training and hydrologic equipment, the Project will contribute towards

reducing the country's vulnerability to heavy rainfall events.

Cost Efficiency 5 Under DiMSOG, a Staff Report omits the calculation of financial and

Economic Rates of Return as applicable for normal lending. However,

the engineering design process will facilitate the selection of least-cost,

technically feasible options for achieving the project objectives.

Institutional

Development

Impact

6 The TA components of the Project will enhance GOSVG’s, and in

particular MTW’s, ability to manage landslide risks and improve the

effectiveness of GOSVG’s disaster response systems.

Sustainability 5.5 The infrastructure works will be designed with adequate protection

measures to mitigate damage from future natural disasters. Whilst budget

constraints may limit GOSVG’s ability to fulfill its overall maintenance

mandate, the Project is not likely to increase GOSVG’s maintenance

burden.

Overall

Performance

6

Highly Satisfactory

MONITORING AND REPORTING

2.35 PC will be responsible for monitoring and reporting on the outputs of the Project, and for

finalising the Design and Monitoring Framework set out in Table 2.1. It will be a condition of the Loan

that GOSVG shall furnish, or cause to be furnished to CDB, the reports listed in Appendix 2.14 to this

Report, in such form or forms as CDB may require, not later than the times specified therein for so

doing.

- 18 -

MAINTENANCE

2.36 It will be a condition of the Loan that GOSVG adequately maintains the infrastructure

financed under the Project. As a further condition of the Loan, GOSVG, through MTW, will be required to

undertake annual condition assessments of the project infrastructure, commencing no later than six

months after the certificate of practical completion, or equivalent, is issued by the engineering

consultants. The assessments shall be conducted under the supervision of the Chief Engineer, MTW.

Further, GOSVG shall no later than December 31 of each year, commencing in 2018, provide CDB

with a 3-year maintenance plan for the project infrastructure and shall provide the resources required

for the maintenance of the project infrastructure in accordance with the funding indicated in the 3-year

maintenance plan.

2.37 It will be a condition of the Loan that GOSVG/CWSA shall routinely maintain all water level

and rain gauge monitoring equipment financed with CDB grant resources and cause the same to be kept in

good condition and repair; providing the resources necessary to implement the maintenance works

required.

2.38 It will be a further condition that CWSA shall share hydrometric data collected with,

and/or generated by, the CDB-financed water level and rain gauge monitoring equipment with other key

GOSVG agencies including but not restricted to: MTW; Ministry of Physical Planning: Ministry of

Agriculture; as well as with CIMH.

3. RISK ASSESSMENT AND MITIGATION

3.01 The overall risk of the proposed project, as presented in Table 3.1 below, can be assessed as minor.

TABLE 3.1: SUMMARY OF KEY RISKS AND MITIGATION MEASURES

Risk Type Description Mitigation Measures

Operational Recruitment of PC: Delay in procuring PC with

requisite skills set.

This problem was encountered in implementation

of last RRL to SVG. The budget for PMU has been

increased so as to attract persons with the right

skills set.

Construction Risk: 1. Limited number of eligible

local contractors and low

interest from international

contractors may delay

implementation of project.

2. Risk of cost overruns or

time delays due to lack of

geotechnical and subsurface

data may increase the scope

of work.

Because of the relatively small project cost

components, regional or international contractors

may not be willing to bid. The project components

have been packaged in such a manner as to attract

bidders from outside SVG.

Cost estimates are based on recent tender prices in

SVG. In addition, adequate contingencies have

been provided to ensure the completion of the

proposed components.

- 19 -

Risk Type Description Mitigation Measures

Maintenance Risk:

Inadequate maintenance of

project infrastructure due to

budgetary constraints. This

could lead to a reduced design

life.

In the short and medium term, the infrastructure

rehabilitated under this project, is expected to lead

to a decrease in the current maintenance

requirements at the project sites. In addition,

maintenance of infrastructure in SVG is the

responsibility of BRAGSA*, who normally give

priority to highways and critical roadways, when

scheduling maintenance.

Natural Disaster Risk The implementation of works

to be undertaken, will be

extremely sensitive to adverse

weather conditions.

The scheduling of construction will take this into

account, and work in those sensitive areas will be

carried out outside the traditional hurricane season.

The Contractor is also required to take out

insurance against such an eventuality.

* BRAGSA - Roads, Building and General Services Authority

4. THE BORROWER AND EXECUTING AGENCY

GENERAL

4.1 The Borrower is GOSVG and the Executing Agency for the Grant is CWSA.

THE BORROWER

4.2 GOSVG may, pursuant to Section 3(1) of the Loans (Caribbean Development Bank) Act 1973

of SVG [the Loans (CDB) Act], in such manner and on such terms and subject to such conditions as

may be agreed between GOSVG and CDB, borrow from CDB from time to time such sums as may be

required by GOSVG. Any agreement between GOSVG and CDB in respect of sums borrowed under this

power must be made in the name of GOSVG and may be signed on behalf of GOSVG by the Minister

responsible for Finance or by any person authorised thereto in writing by that Minister. A copy of such

agreement must be laid before the House of Representatives as soon as possible after it is concluded.

4.3 Pursuant to Sections 3(6) and 10(4) of the Loans (CDB) Act, all amounts required for the

repayment of any sums borrowed by GOSVG from CDB under Section 3(1) of the Loans (CDB) Act,

or guaranteed under Section 7 of the Loans (CDB) Act, and all interest and other charges on such sums

are charged upon, and payable out of, the Consolidated Fund of SVG. Under Section 7(2) of the

GGLA where any sum becomes payable by GOSVG pursuant to a guarantee or undertaking given under

Section 5, that sum shall be charged on the Consolidated Fund and the Minister shall direct payment

to come out of that Fund accordingly.

THE EXECUTING AGENCY

4.4 CWSA was established by Section 3 of the Central Water and Sewerage Authority Act, 1991

(No. 17 of 1991) of SVG (the Act) to manage, construct, operate and maintain works in relation to the

supply of water and the disposal of sewage in SVG. CWSA is a body corporate with perpetual

succession and a common seal, with power to sue and to be sued in its corporate name, and to

exercise such powers and perform such duties as are conferred and imposed on it by the Act. Further

details of the legal status of CWSA are set out in Appendix 4.1.

- 20 -

FISCAL PERFORMANCE

4.5 As a result of the steep decline in revenues and expanded social pressures for protection of the

poor and the vulnerable against the effects of the recession, the current, primary and overall budgetary

balances all deteriorated during the height of the recession, and for the most part have continued to

be in deficit. The current account deficit averaged 1.5% of GDP during 2008 to 2013. The overall

budgetary deficit averaged 2.3% of GDP during the period, reaching 6.1% of GDP in 2013, while the

primary deficit averaged 1.2% of GDP, reaching 3.7% of GDP in 2013. Driven by continuing

weaknesses in the fiscal accounts, but also in part by borrowing related to the new international

airport, public sector debt rose from 57.1% of GDP in 2008 to 74.3% of GDP in 2013, trending away

from the ECCU target of 60% of GDP by 2020.

4.6 Corrective action is imperative to minimise the risk of further fiscal and debt deterioration

in the context of an uncertain global economic environment; the additional fiscal pressures arising

from the December 2013 Trough Event; and the continuing threat of natural hazards, which will likely

intensify in severity and frequency as a result of CC. Enhanced fiscal space is also needed to enable

effective policy responses to the various challenges of attaining accelerated, sustainable and inclusive

growth.

4.7 Barring further significant shocks to the economy, current CDB projections suggest that

the attainment of a primary surplus of 2% of GDP within the medium term will be adequate to place

GOSVG’s finances on a more sustainable path. During the International Monetary Fund (IMF)

Article IV Mission 2011, GOSVG committed to a primary surplus of approximately 2.0% by 2016, to

place public sector debt on the path of attainment of the ECCU goal of 60% of GDP by 2020 (See

Table 4.1). While GOSVG has not yet formulated and embarked on a comprehensive fiscal

consolidation programme, it has been engaged in a number of initiatives to contain the fiscal

imbalances, such as price increases in non-tax revenue items; the restructuring of the property tax and

the consolidation of the public sector pension systems.

TABLE 4.1: MEDIUM-TERM MACROECONOMIC PROJECTIONS

(2014-18)

Item 2012 2013R

2014P 2015 2016 2017 2018

Output and Prices

Real GDP Growth (%)

Consumer prices (end of period)(%)

Central Government Finances Total Revenue and Grants Current Revenue

o/w Tax Revenue

Capital Revenue and Grants

Total Expenditure and Net Lending

o/w Current Expenditure

Current Account Balance

Overall Balance

Primary Balance

Central Government Debt

Total Public Sector Debt

1.5 3.1

0.9 1.0

(% of GDP)

26.2 26.7

24.6 23.6 21.2 20.0

1.7 3.1

28.2 32.8

25.4 25.1

-0.8 -1.5

-2.0 -6.1

0.3 -3.7

59.5 64.2

72.2 74.3

2.5

2.0

27.0

24.6 21.3

2.4

33.0

26.0

-1.4

-6.0

-3.0

69.8

80.8

3.0

2.0

27.6

25.4 22.4

2.2

31.6

24.6

0.8

-4.0

-0.9

67.2

78.5

3.0

2.0

28.5

26.5 23.5

2.0

29.3

24.2

2.3

-0.8

2.1

61.8

74.5

3.5

2.0

29.0

27.0 24.0

2.0

29.1

24.0

3.0

-0.1

2.5

56.2

70.6

3.5

2.0

29.0

27.0 24.0

2.0

29.2

24.0

3.0

-0.2

2.2

51.2

65.0

Source: CDB, IMF, GOSVG Estimates.

R=revised; P=Preliminary.

- 21 -

5. JUSTIFICATION AND BENEFITS

SOCIOECONOMIC BENEFITS

5.1 The Project is a category B project and has the potential for some limited adverse social

impacts but these can be readily mitigated with the implementation of land use restrictions to alter

existing land use practices in the project areas. The positive social impacts far outweigh the negative

consequences of the intervention.

5.2 The Project will build resilience in the communities of the affected areas and at Union, Caratal

and O’Brien Valley, in particular, to future natural hazards, and reduce their vulnerability to

landslides and flooding. With the damage sustained in the feeder road system, farmers in the area face

many challenges in the transportation and marketing of their produce, and this has had a negative impact

on farm incomes. The rehabilitation of the feeder roads will facilitate revitalisation of the agriculture

sector in the project areas thus contributing to the restoration of livelihoods in those communities.

5.3 The Project will reduce the risk that the damaged sections of the roads in the North

Windward corridor currently pose to road users. A number of sections of the Highway have been

affected by slope failure with a critical section at Orange Hill creating a bottleneck for Kingstown-

bound traffic. Slope stabilisation measures included in the Project will improve safety and ensure that

those areas remain open to traffic during and after adverse weather conditions, reducing further

economic losses to householders along the corridor. In addition to the contribution to safety for road

users, the slope stabilisation and road rehabilitation activities of the Project, are expected to facilitate

the restoration of economic and social activities to pre-event levels.

5.4 Although the Project would benefit the entire population, the primary beneficiaries include

the resident population in the Project areas, estimated at approximately 21,285 persons, almost equally

divided between males and females. The Project will also provide short-term employment opportunities

during the construction phase, for semi-skilled and unskilled male and female workers, and increased

business for suppliers of construction materials and locally-sourced products. During planning, design

and construction of the sub-projects, there could be employment opportunities for professional, skilled

and unskilled labor. Traditionally, unskilled labour for projects of this nature are sourced locally.

Women from the community will be encouraged to secure employment at project sites to mitigate

inequalities that exist with respect to access to labour in the construction sector.

MACROECONOMIC IMPACT ASSESSMENT

5.5 The impact of the project on GDP growth is projected to be positive in the short to medium

term, as a result of the investment in the construction sector and the rise in demand for construction sector

inputs. The project is also likely to impact GDP growth via the restoration of transport capability

which would contribute to the normalisation of productive sector activity in the various sectors,

including agriculture. The increase in economic activity will lead to a rise in much need employment

opportunities and, over time, can contribute to a reduction in poverty. As a result of projected

increase in economic activity, the expectation is that there will be a positive contribution to fiscal

performance through an increase in revenues. The short-run balance of payments impact is projected

to be neutral with increase in project- related import expenditure compensated by the inflow of project

resources, though this will likely be offset somewhat by secondary import consumption effects. In the

medium to long term, the expectation is that the project can lead to some improvement in the balance

of payments through facilitation of a return to normalcy in the exports sectors.

- 22 -

6. TERMS AND CONDITIONS

6.1 The proposed financing for this Project is as follows:

(1) a loan to GOSVG of an amount not exceeding the equivalent of nine million and forty-

six thousand United States dollars (USD9,046,000) to assist GOSVG in financing the

provision of technical assistance and the rehabilitation and reconstruction of critical

infrastructure damaged by the passage of the December 2013 Trough Events: and

(2) a grant to GOSVG for use by CWSA of an amount not exceeding the equivalent of

two hundred and twenty one thousand United States dollars (USD221,000) (the

Grant) to finance technical assistance for institutional strengthening, as described the

TOR at Appendix 2.2 and for the procurement of equipment (the TA Component),

(together the Project).

6.2 It is recommended that CDB lend to GOSVG an amount not exceeding the equivalent of

nine million and forty-six thousand United States dollars (USD9,046,000)(the Loan) consisting of:

(a) an amount from CDB's SFR not exceeding the equivalent of three million five

hundred and seventeen thousand United States dollars (USD3,517,000) (the

SFR Portion); and

(b) an amount from CDB's OCR not exceeding the equivalent of five million five

hundred and twenty-nine thousand United States dollars (USD5,529,000) (the

OCR Portion) to assist GOVSG in financing the Project,

on CDB's standard terms and conditions and on the following terms and conditions:

(1) Repayment: Repayment of the Loan will be made:

(a) in the case of the SFR Portion, in eighty (80) equal or approximately equal

and consecutive quarterly instalments commencing five (5) years after the date

of the Loan Agreement.

(b) in the case of the OCR Portion, in sixty eight (68) equal or approximately

equal and consecutive quarterly instalments commencing five (5) years after the

date of the Loan Agreement.

(2) Interest: Interest shall be payable quarterly:

(a) at the rate of two decimal five percent (2.5%) p.a. (fixed) on the amount of the

SFR Portion withdrawn and outstanding from time to time; and

(b) at the rate of three decimal nine-five percent (3.95%) p.a. (variable) on the

amount of the OCR Portion withdrawn and outstanding from time to time.

(3) Commitment Charge: A commitment charge at the rate of one percent (1%) p.a. shall

be payable on the amount of the OCR Portion unwithdrawn from time to time. Such

charge shall accrue from the sixtieth (60th) day after the date of the Loan Agreement and

shall be payable quarterly.

- 23 -

(4) Disbursement:

(a) The first disbursement of the Loan shall be made by October 30, 2014, and

the Loan shall be fully disbursed by May 31, 2017, or such later dates as CDB

may specify in writing.

(b) Except as CDB may otherwise agree:

(i) the Loan shall be used to finance the components of the Project

allocated for financing by CDB as shown in the financing plan for the

Project up to the respective limits specified therein; and

(ii) total disbursements of the Loan shall not exceed in the aggregate

eighty percent (80%) of the cost of the Project.

(c) The Loan shall not be used to meet any part of the cost of the Project which

consists of identifiable taxes and duties.

(5) Procurement: Procurement shall be in accordance with the procedures set out and/or

referred to in the Loan Agreement or such other procedures as CDB may from time to

time specify in writing. The Procurement Plan approved by CDB is set out at Appendix

2.13 to this Report. Any revisions to this Plan shall require CDB’s prior approval in

writing.

(6) Condition Precedent to First Disbursement of the Loan:

The PC referred to in sub-paragraph 12(c) (i) below shall have been engaged.

(7) Condition Precedent to Disbursement with respect to Construction Works:

The PE referred to in sub-paragraph 12(c) (ii) shall have been engaged.

(8) Condition Precedent to Disbursement with respect to the Immediate

Mitigation Works:

The consultant referred to in sub-paragraph 12(e) (i) shall have been engaged.

(9) Condition Precedent to Disbursement with respect to Infrastructure

Rehabilitation and Upgrade Works:

The consultant referred to in sub-paragraph 12(e) (ii) shall have been engaged.

(10) Condition Precedent to Disbursement with respect to Infrastructure

Rehabilitation and Upgrade Works- Orange Hill:

The consultant referred to in sub-paragraph 12(e) (iii) (bb) shall have been engaged.

- 24 -

(11) Condition Precedent to Disbursement with respect to Construction Works at the Magnum Site:

The land required for the Project shall have been vested in GOSVG, free from all

encumbrances, stipulations or conditions which may adversely affect the Project, or

alternatively GOSVG shall have made arrangements satisfactory to CDB to enter

into possession of such lands for the purpose of the Project.

(12) Other Conditions:

(a) Except as CDB may otherwise agree, GOSVG shall implement the Project

through PMD of MTW.

(b) GOSVG shall contribute to the Project an amount of not less than the

equivalent of two million and eighty-two thousand United States dollars

(USD2,082,000.00) which shall be expended in a timely manner, on the

components of the Project designated for financing by GOSVG, as shown

in the financing plan for the Project, unless CDB shall otherwise specify in

writing.

(c) GOSVG shall in accordance with the procurement procedures applicable to

the Loan, select and engage for the duration of the Project, and exclusively

to the Project:

(i) a PC who shall lead PT and shall be responsible for coordinating,

monitoring and managing all aspects of the implementation of the

Project, including the duties and responsibilities set out in the TOR

at Appendix 2.10. PC shall report to the Chief Engineer of MTW; and

(ii) a PE who shall report to PC, and shall be responsible for assisting PC

with supervising the engineering consultants and managing the

implementation of the construction works, including the duties and

responsibilities set out in the TOR at Appendix 2.10.

(d) GOSVG shall:

(i) establish, and for the duration of the Project, maintain a PT within

PMD of MTW with overall responsibility for managing all aspects of

the implementation of Project including the duties and responsibilities

set out in the TOR at Appendix 2.10;

(ii) ensure that, for the duration of the Project, PT has suitable office

accommodation, transportation office equipment, supplies and

adequate administrative support ;

(iii) assign, for the duration of the Project, as AO, a person whose

qualifications and experience are acceptable to CDB and who shall

report to PC and shall carry out the duties and responsibilities set out in

the TOR at Appendix 2.10. The qualifications and experience of any

person subsequently assigned to the position of AO shall be acceptable

to CDB; and

- 25 -

(iv) procure that CWSA assign, for the duration of the Project, as

PMH, a person whose qualifications and experience are acceptable

to CDB and who shall report to PC and shall carry out the duties

and responsibilities set out in the TOR at Appendix 2.10. The

qualifications and experience of any person subsequently assigned to

the position of PMH shall be acceptable to CDB.

(e) GOSVG shall, in accordance with the procurement procedures applicable to

the Loan, select and engage:

(i) competent and experienced Engineering Consultant to carry out the

services outlined in the TOR at Appendix 2.11;

(ii) competent and experienced Engineering Consultant to carry out the

services outlined in the TOR at Appendix 2.12; and

(iii) competent and experienced Consultants to carry out the services:

(aa) in respect of the Rehabilitation and Upgrade Feasibility

Study outlined in the TOR at Appendix 2.3;

(bb) in respect of the Landslide Risk Assessment Slope

Stabilisation and Remedial Design Study outlined in the

TOR at Appendix 2.4;

(together the TA Studies) and

(iv) competent and experienced contractors to carry out the construction

works under the Project.

(f) GOSVG shall:

(i) keep the facilities financed by CDB under the Project in good repair

and condition;

(ii) through MTW undertake annual condition assessments of the

project infrastructure, commencing no later than six (6) months

after the certificate of practical completion (or equivalent) is issued

by the Engineering Consultants. The assessments shall be conducted

under the supervision of the Chief Engineer, MTW; and

(iii) keep the roads, works and other infrastructure financed from the Loan,

or cause the same to be kept, in good repair and condition and shall,

commencing in 2018, no later than December 31 in each year,

provide CDB with a 3-year maintenance plan (the Maintenance

Plan) for the project infrastructure. GOSVG shall provide the

resources required for the maintenance of the project infrastructure in

accordance with the funding indicated in the Maintenance Plan.

- 26 -

(g) GOSVG shall:

(i) except as CDB may otherwise agree, furnish or cause to be furnished

to CDB, the reports listed in Appendix 2.14 in such form or forms as

CDB may require, not later than the times/periods specified therein for

so doing;

(ii) carry out the Project at all times with due diligence and efficiency,

with management personnel whose qualifications and experience

are acceptable to CDB, and in accordance with sound, technical,

environmental, financial and managerial standards and practices; and

(iii) ensure that hydrometric data collected with and generated by the

CDB financed equipment shall be shared with all relevant GOSVG

agencies, including, but not restricted to, MTW; Ministry of Physical

Planning; the Ministry of Agriculture and the Caribbean Institute

for Metrology and Hydrology;

(iv) institute and maintain organisational, administrative, accounting and

auditing arrangements for the Project acceptable to CDB; and

(v) within a timeframe acceptable to CDB implement such of the

recommendations arising out of the TA Studies as may be acceptable

to CDB.

6.3 It is also recommended that CDB make a grant to GOSVG of an amount not exceeding

the equivalent of two hundred and twenty one thousand United States dollars (USD221,000) (the

Grant) from CDB’s SFR to assist CWSA in financing the TA Component on CDB’s standard terms

and conditions and on the following terms and conditions:

(1) Disbursement:

(a) Except as CDB may otherwise agree, and subject to sub-paragraph (b)

below, disbursement of the Grant shall be paid as follows:

(i) an amount not exceeding fifty thousand United States dollars

(USD50,000) shall be paid to CWSA as an advance (the Advance)

on account of expenditures in respect of the Project, after receipt of

CDB of:

(aa) a request in writing from CWSA for such funds; and

(bb) evidence acceptable to CDB that the conditions precedent to

first disbursement at paragraph (3) below have been

satisfied;

(ii) the balance of the Grant shall be paid to CWSA periodically after

receipt by CDB of an account and documentation, satisfactory to CDB,

in support of expenditures incurred by CWSA with respect to the

TA Component, provided however that CDB shall not be under any

obligation to make:

- 27 -

(aa) the first such payment until CDB shall have received an

account and documentation, satisfactory to CDB, in support

of expenditures incurred by CWSA with respect to the

Advance; and

(bb) payments exceeding two hundred thousand United States

dollars (USD200,000) of the Grant until CDB shall have

received a certified statement of the expenditures incurred

by GOSVG and proof that appropriate and adequate

insurance has been obtained for the equipment procured in

respect of and in connection with the TA Component.

(b) The first disbursement of the Grant shall be made by March 31, 2015, and

the Grant shall be fully disbursed by August 31, 2016, or such later dates as

may be specified in writing by CDB.

(2) Procurement:

(a) Procurement of goods and services financed by the Grant shall be in

accordance with the procedures set out and/or referred to in the Grant

Agreement or such other procedures as CDB may from time to time specify in

writing.

(b) The Procurement Plan set out in Appendix 2.13 has been approved by CDB for

the purposes of the TA Component. Any revisions to this Plan shall require

CDB’s prior approval.

(3) Conditions Precedent to First Disbursement:

(a) All the conditions precedent to first disbursement of the Loan shall be satisfied.

(b) CWSA shall provide CDB with evidence acceptable to CDB that suitable

candidates have been identified for the mid and diploma level technician

training programme.

(4) Other Conditions:

(a) Except as CDB may otherwise agree, GOSVG shall carry out the TA

Component through CWSA.

(b) GOSVG shall make the proceeds of the Grant available to CWSA for

financing the TA Component of the Project.

(c) Except as CDB may otherwise agree, CWSA, in collaboration with the PT for

the Project, shall in accordance with the procurement procedures applicable

to the Grant, procure the goods and services in accordance with the TOR at

Appendix 2.2 to this Report.

(d) Except as CDB may otherwise agree, CWSA shall:

(i) meet or cause to be met:

(a) the cost of the items designated for financing by it in the

Budget in Appendices 2.2 of this Report (the Budget);

- 28 -

(b) any amount by which the cost of the of the TA Component

exceeds the estimated costs set out in the Budget; and

(c) the cost of any other items needed for the purpose of, or in

connection with, the TA Component; and

(ii) and shall provide all other inputs required for the punctual and

efficient carrying out of the TA Component not being financed by

CDB.

(e) Except as CDB may otherwise agree, CWSA shall keep the equipment

financed from the Grant, or cause the same to be kept, in good repair and

condition and shall provide the necessary resources to adequately carry out

maintenance of the equipment.

(f) CDB shall be entitled to suspend, cancel or require a refund of the Grant or

any part thereof if the Loan or any part thereof is suspended, cancelled or

called in.

APPENDIX 1.1

SUMMARY OF DAMAGE AND LOSSES

CAUSED BY DECEMBER 2013 TROUGH EVENT

(USD ‘000)

Item

Damage

Losses

Total

Impact

% of

Total Impact

Productive Sector 118 73 192 .002%

Tourism 118 52 171 -

Education - 15 15 -

Industry and Commerce - 6 6 -

Social Sectors 3,204 222 3,426 2.3%

Health 1,831 222 2,053 2%

Agriculture 1,373 0 1,373 1.3%

Infrastructure 83,020 21,740 104,766 96.7%

Transport 67,863 14,733 82,602 76.2%

Water and Sewerage 3,149 1,320 4,469 4%

Electricity 5,208 3,348 8,556 7.9%

Housing 6.800 2,339 9,139 8.4%

Total 86,347 22,036 108,384 100

Source: Global Facility for Disaster Reduction and Recovery estimates, based on county data and information.

APPENDIX 1.2

SOCIAL AND GENDER CONTEXT

1. SOCIAL CONTEXT

1.1 The Project target areas are located on the eastern side of the island in four Census Divisions: Sandy

Bay; Georgetown; Bridgetown; and Marriaqua. The Physical Planning Unit, Ministry of Housing, Informal

Human Settlements, Physical Planning and Land and Surveys, has a different description of the geographic

districts in SVG, Table 1 shows the relationship between the census divisions and the project areas by the

Ministry’s districts.

TABLE 1: CENSUS DIVISIONS, DISTRICTS AND PROJECT SITES

Districts Census Division Project Sites

North Windward Sandy Bay

Georgetown

Boat Bay, Point Hill, Bloody Bridge, Owia,

Windblow, Soldier Hill, Spring Gutter

Touruma, Magnum, Orange Hill

North Central Windward Georgetown (southern end) Caratal River

South Central Windward Bridgetown Yarabaqua River

North Union River

Vigie Highway (Glenside to Peruvian Vale)

Marriaqua Marriaqua Vigie Highway (La Croix to Mesopotamia)

Yambou River Bridge

Teviot and Zenga Bridges

1.2 Although project areas are located outside of the formally declared disaster areas for the December

Trough System, they are concentrated in segments of the island where the highest concentration and most

severe states of poverty were recorded during the 2008 CPA (See Figure 1 for ease of reference).

Sandy Bay

1.3 Communities in Sandy Bay are located along the northern windward coast, and as a result have

historically suffered disproportionately greater losses from severe weather events. Poverty levels in Sandy

Bay are explained by its low resilience to shocks, such as natural hazards; and its geographic location and

remoteness. Although Sandy Bay has the potential for a thriving agriculture industry as the only place in

the western hemisphere where a high grade of arrowroot can be grown, the industry is restricted by the

uncertainty of access to markets. This is affected by frequent losses in road connectivity due to slope

instability along strategic points of the Windward Highway1/. High transportation costs for residents and farmers from Sandy Bay also restrict growth and development options in its communities, and have

contributed to migration, especially of young men, from the area.

1/ Boat Bay, Pointe Village, Owia, Wind Blow, Soldier Hill, and Fancy.

APPENDIX 1.2 Page 2

FIGURE 1: VULNERABILITY IN 2008 BY CENSUS DIVISION

SANDY BAY

GEORGETOWN

Source: 2008 CPA - SVG

1.4 Preliminary findings from the 2012 population census show patterns that support population drift

out of Sandy Bay. The census recorded a population of 2,576 persons in 662 households in Sandy Bay, a

decline from 2,805 in 2001. However, the number of households remained the same. Population figures

also documented a significant decline in the male population compared to the female population. In 2012,

the population consisted of 1,374 males and 1,232 females, compared to 1,508 males and 1,297 females in

2001. From this one could infer that the area may have an increase in female-headed households since the

last poverty assessment, a demographic group associated with high levels of poverty in SVG. Detailed

analysis of the 2012 population census will confirm this. Sandy Bay is home to the Garifuna people,

descendants of the Carib Community or indigenous people on the island. The communities in Sandy Bay

are therefore of significant historic importance to the country.

1.5 The population of Sandy Bay is still recovering from the impacts of the December Trough Event,

while also recovering from severe weather events of the recent past. Apart from property damage,

APPENDIX 1.2 Page 3

livelihoods have also been affected as a result of the Event. Given these challenges, it is expected that

poverty levels and intensity would have increased in Sandy Bay since the last CPA.

Georgetown

1.6 Preliminary figures from the 2012 population census documented 7,049 persons living in

Georgetown, i.e. some 3,596 males and 3,453 females resident in 2,188 households. Poverty in Georgetown

is explained by a history of heavy reliance on agriculture, particularly sugar and bananas. The reluctance

by farmers in Georgetown to move to other more viable activities means there has been minimal recovery

from the decline of both industries. Attempts to encourage banana farmers to switch to plantains have met with limited success. The December 2013 Trough Event aggravated challenges for new plantain farmers

and created added hardships for farming households. Table 2 shows damages and losses in the crop

subsector and the disproportionate losses to farmers from Region 32/, especially in the cash crops, bananas,

plantains and root/tubers. This would have a significant impact on the household incomes of the affected

farmers.

1.7 Farmers in Region 3 also keep livestock to supplement incomes between crop harvests. This

subsector suffered significant losses with livestock loss recorded at 845 animals, an estimated value of

$378,090. Overall losses to the livestock industry for the country was 1,843 animals, an estimated cost of

$873,435.

TABLE 2: DAMAGE/LOSSES TO THE CROP SUBSECTOR

Category

Number of Farmers Affected

Estimated

Damage in

Region 3

(ECD)

Estimated

Damage in

SVG

(EC000,000) Region 1 Region 2 Region 3

Bananas 11 0 52 430,905 452,395

Plantains 33 1 249 1,806,820 1,902,760

Vegetables 146 20 48,350 442,610

Fruit/tree crops 42 2 52 131,390 264,150

Roots and Tubers 161 14 245 904,145 1,291,535

Other crops 30 13 32 130,190 248,700

1.8 In addition to heavy reliance on agriculture, a number of other factors affect the wellbeing of the

residents in Georgetown. These include factors that affect the resilience of public and private infrastructure

to natural hazards including, but not limited to: the topography of the area; aging/unmaintained public and

private infrastructure; and unplanned agriculture and settlement practices on marginal lands.

1.9 The Windward Highway connects all communities on the eastern half of the island to the principal

center of commerce, economic and social services. Its connectivity is therefore critical to the

economic/social wellbeing and development of the eastern towns and districts on the island. The corridor

is supported by a series of agricultural feeder roads and/or tertiary roads. However, the highway and its

feeder roads are very vulnerable to landslides, and damage from rock falls. Some of the most vulnerable

sections of this corridor are located in Georgetown. Like Sandy Bay, communities in Georgetown are

frequently cut off from social and economic services during severe weather conditions. This adversely

impacts livelihoods, affecting daily commute and the transportation of goods and services required for the

agriculture sector. Loss of connectivity also slows down recovery efforts, intensifying the adverse impacts

2/ Region 3 consist of the Electoral Districts of Sandy Bay and Georgetown.

APPENDIX 1.2 Page 4

of such events on households. During the December 2013 Tough Event, intense rainfall converted rapidly

into a major flood which led to damage and destruction to public and private infrastructure, while landslides

blocked the Highway and damaged some of the feeder roads in Georgetown.

Marriaqua and Bridgetown

1.10 The Yambou, Zenga, and Teviot Rivers as well as the Vigie Highway from La Croix to Peruvian

Vale span the electoral districts of Marriaqua and Bridgetown. These two districts are densely populated.

Preliminary results from the 2012 population census document a population of 7,798 persons in Marriaqua

(3,916 males and 3,882 females) and 3,832 persons living in Bridgetown (1,958 males and 1,874 females).

1.11 Marriaqua and Bridgetown are in the agriculture region, Region 2. Marriaqua is particularly

important, as Mesopotamia Valley, the breadbasket of St. Vincent, is located there. Mespotamia Valley is

very fertile with farmlands producing root crops, fruits, vegetables and spices. The area is essential to food

security in the country.

1.12 Residents of Mesopotamia Valley are heavily dependent on agriculture. Livelihoods in the Valley

face disruptions as sections of the Valley are prone to flooding, land slippage and rock falls. The area’s

vulnerability is however exacerbated by unsustainable development practices: the dumping of waste in the

water ways; poor river maintenance; squatting on river banks for settlement and agricultural activity; and

farming on steep slopes. The major flood zone, where the Zenga, Teviot and Yambou Rivers meet, can be

described as a town centre. A number of essential and community services are located in the area including

primary and secondary educational facilities, food distribution centres, a police station, churches, two major

burial grounds, medical facilities (a government polyclinic and two private practitioners), agriculture

marketing facilities, the government slaughter house that services all livestock farmers in Marriaqua,

commercial services, and a gas station. The latter is located on the river Bank. The area is also a

transportation hub for all the communities in Bridgetown and Marriaqua.

2. GENDER CONTEXT

2.1 There was no reliable social or sex disaggregated data presented on the impact of the event.

Attempts to formulate a vulnerability profile of different groups of men and women in all the project areas

failed because of the scarcity of reliable data broken down by sex, age, geographic location and other socio-

economic groups. The poor in SVG are considered the most vulnerable to natural disasters. The 2008

poverty assessment described persons living in poverty and most vulnerable to poverty as persons from

rural communities, especially the banana farming population, persons from large families, and members of

female single parent/female-headed households. NEMO confirmed that persons from these groups were in

greatest need of shelter and humanitarian aid after the event, especially members of female-headed

households. It is expected that recommendations and data collected from the Country Gender Assessment,

currently being conducted in SVG, will be used to construct baseline data for the project.

3. CONCLUSION

3.1 The December 2013 Trough Event was a natural hazard but the social impacts and the intensity of

these impacts were the result of poor development choices and socio-economic conditions in the affected

areas. Farming practices, settlement patterns, land use management, poverty status and other social

inequalities all contributed to the destruction, losses and the ability of the population to recover from the

event. Rapid impact assessments of the event revealed that different groups in the society suffered

disproportionately from the event. Characteristics of the social groups hardest hit by the system included

the poor and vulnerable, those living in vulnerable sections of the island, and farmers. Discussions with

NEMO also suggest that members from single parent female households may have suffered great losses.

APPENDIX 1.2 Page 5

The eastern side of the island was severely affected, and was the slowest to recover from the event.

Recovery time was hindered by land slippage, rock falls and damage to roads from severe flooding in a

number of its districts. This placed the eastern communities at a greater disadvantage when compared with

the rest of the island. Recurrent severe weather events have resulted in irreversible social dislocation for a

number of households in the project areas. Mitigation measures to reduce land slippage and flooding are

essential to poverty reduction and economic development in affected areas, but must be accompanied by

holistic interventions that monitor and mitigate social practices that would affect the sustainability of the

mitigation interventions employed.

APPENDIX 1.3

SUMMARY OF PREVIOUS CDB-FUNDED DISASTER MANAGEMENT PROJECTS

IN ST. VINCENT AND THE GRENADINES, 1986-2013

(USD '000)

Loan or Grant No.

Approval Date

Project Description

Amount

Approved 43/SFR-STV

December 11, 1986

Emergency loan to assist with the

rehabilitation of infrastructure damaged by

Hurricane Danielle.

463

56/SFR-STV

January 14, 2000

IRL to assist with the costs related to storm

surge damage to property and infrastructure

arising from Hurricane Lenny and Use of

Funds (UOF) for project supervision.

520

58/SFR-STV

October 10, 2002

IRL to assist with the cleaning and clearing

of areas affected by Hurricane Lili and for

emergency restoration of essential services

damaged by the hurricane, and UOF for

consultancy to assist with project

supervision.

520 GA21/STV

February 25, 2005

ERG to Caribbean Disaster Emergency

Relief Agency for Hurricane Ivan

emergency relief in SVG.

100

GA24/STV

November 22, 2010

ERG to Caribbean Disaster Emergency

Management Agency to assist with the costs

associated with carrying out damage

assessments and providing emergency relief

supplies.

200

61/SFR-STV

December 23, 2010

IRL to assist with the cleanup of debris, the

clearing of roads and the restoration of

access along critical road links damaged by

Hurricane Tomas and TA grant for project

supervision.

770 17SFR/OR-STV

July 18, 2011

RRL to assist with the rehabilitation and

reconstruction of critical infrastructure, and

the upgrading of damaged by Hurricane

Tomas in October 2010, and improvement

of emergency shelters impacted by

Hurricane Tomas and Torrential rainfall in

April 2011.

12,622

62SFR-STV

December 24, 2013

IRL to assist with the cleanup of debris, the

clearing of roads, and the restoration of

areas affected by the December 2013

Trough system.

750

Total

15,945

APPENDIX 2.1

DETAILS OF THE PROJECT

1. INFRASTRUCTURE WORKS

1.1 This component includes the reconstruction and/or rehabilitation of infrastructure damaged by

December 2013 floods. The description of the proposed works to be funded by CDB are summarised in

the Table 1 below. The Project provides for engineering consultancy services to prepare detailed designs

and cost estimates.

TABLE 1: DETAILED DESIGNS AND ESTIMATED COST

Location

Description of Proposed Works

Estimated Cost

($ '000)

North Windward Watershed Clearing Works

London Jack Feeder Road Construction of bridge and retaining walls.

Lauders-Lowmans Main

Road

Construction of river defence to Union River and stablisation of

the slope.

Sandy Bay Construction of approximately 300 ft of coastal defense

Dark View Construction of nearly 18 ft high reinforced concrete sea wall

extending around 270 ft along the Dark View lower

embankment.

Campden Park and

Mespotamia

Reconstruction and/or rehabilitation of emergency shelters to

meet the standards established by NEMO. Works include roof

reconstruction, floor replacement, installation of fixtures and

fittings, electrical work, and the installation of generators and

water tanks.

Windward Highway Reconstruction and/or rehabilitation of the following four

bridges along the highway:

(a) Byrea Bridge - reconstruction of the bridge and

wing−walls; rehabilitation of the road pavement to the

bridge and construction of a bypass road;

(b) Grand Sable River - demolition and reconstruction of the

bridge inclusive of wing-walls and the pavement;

(c) Caratal - construction of bridge wing-walls and installation

of bridge rails; and

(d) Miss Jane River - installation of bridge rails and underpining

wing-walls.

Construction of gabion river defence systems for the:

Grand Sable River; Miss Jane River, Caratal River and Langley

Park River.

Congo and Jennings Valley

Roads

Rehabilitation of road pavement, wing-walls, bridge abutments,

construction of retaining walls drains, demolition and

construction of bridge, inclusive of wing-walls.

Location Description of Proposed Works Estimated

Cost

($ 000)

Perservance and O'Brien's

Valley

Construction of three single span bridges, inclusive of

wing−walls and bridge furniture and river defence systems.

Gorse Mountain Road Grade and stabilise earthen feeder roads, construct gabion

retaining walls and upgrade earthen road to concrete with

associated drains.

Total

2. TECHNICAL ASSISTANCE

2.1 This component consists of procurement of equipment, training and consultancies:

(a) Supply of Hydrological instrumentation and training:

(i) Supply of Rain Gauges, Automatic Water Level Monitoring Equipment1/

and Hydrological Data Assistants

Supplying, insuring, shipping, and delivering the hydrological equipment

identified in Table 2 to CWSA.

TABLE 2: HYDROLOGICAL EQUIPMENT TO BE SUPPLIED AND INSTALLED

Equipment Amount

Tipping Bucket Rain Gauges 8

Automatic Water Levels 10

Hydrological Digital Assistants 2

Lead Gel Batteries 12V/27Ah 10

Conductivity Meters 2

(ii) Installation, Commissioning and Handover of Rain Gauges, Automatic

Water Level Monitoring Equipment and Hydrological Data Assistants

Installing, commissioning and handover of the rain gauges, and water level

monitoring equipment supplied at the locations identified by the CWSA Water

Resource Unit.

(b) Rehabilitation and upgrade study for Vigie Highway and associated bridges; and

(c) Landslide Risk Assessment, Slope Stabilisation and Remedial Design Study for North

Windward Corridor.

The estimated cost for both the consultancies and the Institutional Strengthening is $

________________

1/ Equipment specifications are provided in Annex 1

APPENDIX 2.1

Page 2

3. ENGINEERING CONSULTANCIES

3.1 There shall be two engineering consultancy components. Each component shall consist of:

(a) Design Services, including the preparation of detailed design drawings and tender

documentation; and

(b) Construction Supervision Services, including the evaluation of tenders, contract

administration, construction supervision, preparation of progress reports, certification of

payments and inspection services during the defects liability period. The estimated cost of

this component is $

4. PROJECT MANAGEMENT

4.1 The costs associated with transportation, office equipment and supplies, as well as office space

for the accommodation of PT, and the cost of AO are included in GOSVG’s counterpart contribution.

CDB will finance the cost of PC and one PE. This component is estimated to cost $

5. LAND ACQUISITION

5.1 This component comprises the acquisitions 370 m2 of land located at Magum on the North

Windward Highway. This cost of this component is $

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.2

DRAFT TERMS OF REFERENCE

TECHNICAL ASSISTANCE FOR TRAINING OF TECHNICIANS IN HYDROLOGY

TO USE, MANAGE AND MAINTAIN ST. VINCENT AND THE GRENADINES’

NATIONAL NETWORK OF RAINFALL AND RIVER FLOW MONITORING STATIONS

1. BACKGROUND

1.1 Over a 24-hour period between December 24 to 25, 2013, an unseasonal low-level trough system

moving westward towards the Windward Island chain, interacted with a mid to upper level trough system

moving in a south to north direction. Heavy precipitation, high winds and thunderstorm activity was

generated along the eastern boundary of mid to upper-level trough as a result of this interaction. Peak

rainfall intensity occurred over the 3-hour period between 9:00 p.m. and 12:00 a.m. on the evening of

December 24, 2013. Observed rainfall accumulations ranged between 163 millimetres (mm) to 312 mm at

Belle Isle and Rabacca stations in St. Vincent. Rainfall intensities were highest in the northeastern quadrant

of St. Vincent with rainfall gauges in this area recording a maximum intensity of 278 mm per 3-hour period

Expert opinion classified the 3 hour rainfall intensity as in excess of a 100 year return period event..

1.2 The passage of the trough and accompanying extreme rainfall resulted in significant river, flash

flooding and landslide damage to mainland St. Vincent. The Government of St. Vincent and the Grenadines

(GOSVG) has approached the Caribbean Development Bank (CDB) for a loan to rehabilitate and

reconstruct infrastructure damaged as a consequence of the Trough Event.

1.3 A total of six (2 rainfall and 4 river flow) Central Water and Sewerage Authority (CWSA)

maintained monitoring stations were lost as a result of the passage of the December 2013 Trough Event.

1.4 St. Vincent and the Grenadines (SVG) is challenged in terms of data collection for rainfall and

water level monitoring in it rivers. Greater and more spatially representative network coverage is required

for both rainfall gauges and water level monitors. Of necessity, the optimal performance of such a network

also demands management and maintenance by a skilled cadre of technicians trained in hydrology.

1.5 Capacity deficits in current national network coverage, availability of higher trained technicians

and the quality of data collected by existing field instrumentation constrains the adequacy of information

required to develop more resilient site specific infrastructure design; flood hazard, emergency management

and reduction plans; as well as potentially for facilitating the development of early warning systems.

Network coverage in the north of the island is particularly limited. Where instrumentation was available

only monthly rainfall records were collected between 1979, to 1996. Between 1996 to the present, hourly

rainfall data is collected.

1.6 The challenges in data capacity, quality and management at the national level further impacts

analysis of hydro-meteorological data at a regional level scale, a function that is executed by the Caribbean

Institute for Meteorology and Hydrology (CIMH). CIMH maintains an archive of meteorological and

hydrological data from member countries of the Caribbean Meteorological Organization including SVG.

The archive consists of hourly synoptic and daily climatological data collected at airport stations,

independent climatological/agro-meteorological stations, monthly rainfall, and stream flow data from water

agencies.

1.7 Under the World Bank’s Regional Disaster Vulnerability Reduction Project (2011-2016) in

St. Vincent, GOSVG has benefited from the provision of meteorological equipment including rain gauges.

Despite this provision, gaps in coverage remain.

APPENDIX 2.2 Page 2

1.8 Existing instrumentation is currently maintained by the SVG Meteorological Office, Ministry of

Agriculture, Fisheries, Industry and Rural Transformation, and the (CWSA). Presently CWSA actively

maintains the largest network of rainfall (20 No.) and water level monitoring (2 No.) stations and has a staff

of 4 persons within their water resources unit. These persons are assigned in teams of two each to manage

and maintain monitoring stations on the leeward and windward sides of the island respectively.

1.9 CDB’s consultation with GOSVG stakeholders on the mission to appraise the rehabilitation and

reconstruction loan request revealed a desire for grant financing to support the extension of and upgrading

to the national instrumentation network for rainfall measurement, river-flow and water level monitoring as

well as for higher training of technicians in hydrology.

2. OBJECTIVE

2.1 The objective of the technical assistance (TA) is to provide higher training technicians in hydrology

to use, monitor and service an upgraded1/ and expanded the national network of water level and rainfall

monitoring stations in St. Vincent in order to facilitate better management of flood hazard risk; enhanced evidence-based physical planning; and data provision for site-specific design of mitigation infrastructure.

3. SCOPE OF WORK

3.1 The scope of services includes, but is not limited to:

(a) Training of one Technician in Hydrology to World Meteorological Organization

Equivalent Mid-Level Hydrological Technical Course Qualification at CIMH:

Provide training to one GOSVG identified personnel in operational hydrology.

(b) Training of one Person to Diploma in Hydrology level Qualification at the CIMH:

Provide training to one GOSVG identified personnel to theoretical and practical aspects

of hydrology to higher Diploma level.

4. IMPLEMENTATION ARRANGEMENTS

4.1 CIMH shall be the institution providing the training. GOSVG shall nominate two personnel

directly involved in the monitoring and maintenance of its national hydrometric instrumentation network

with the required qualifications and experience to the CIMH hydrological training programme, facilitating

the training leave necessary. GOSVG nominated personnel shall liaise with the CIMH regarding the

application procedures and the commencement of training. It is further expected that the persons receiving

higher technician training in hydrology under this TA will conditionally be directly involved in the

monitoring and maintenance of the hydrometric equipment supplied by CDB grant finance.

1/ Under separate TA with CDB grant financing it is expected that GOSVG will benefit from the supply and installation of 8 No.

Tipping Bucket Rain Gauges; 10 No. Automatic Water Level Monitors; and 2 No. Hydrological Digital Assistants.

APPENDIX 2.2 Page 3

5. QUALIFICATIONS AND EXPERIENCE

5.1 For entry into the CIMH Hydrological Technician training programme, GOSVG personnel

identified to be trained in operational hydrology will require minimum entry qualifications of four GCE

(Ordinary Level) or CXC (General Proficiency - Grades I, II & III) Certificates, including English Language

and Mathematics. Physics would be an asset.

5.2 For entry into the CIMH Higher Diploma in Hydrology, GOSVG personnel identified to be trained

in theoretical and practical hydrology will require minimum entry qualifications of the Hydrological

Technicians Certificate or several years’ practical experience in the field of hydrology.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.3

DRAFT TERMS OF REFERENCE

CONSULTANCY SERVICES FOR A REHABILITATION AND UPGRADE STUDY

FOR VIGIE HIGHWAY AND ASSOCIATED BRIDGES

1. INTRODUCTION

1.1 The Government of St. Vincent and the Grenadines (GOSVG) has applied to the Caribbean

Development Bank (CDB) for technical assistance (TA) to undertake a feasibility study for the

rehabilitation of 6 km of the Vigie Highway between Crick Corner to Peruvian Vale together with the

associated bridges: Teviot, Zenga and Yambou Bridges. The Study is a component of a loan to rehabilitate

and reconstruct infrastructure damaged as a consequence of the December 24-25, 2013 Trough System.

1.2 Over a 24-hour period between December 24 to 25, 2013, an unseasonal low-level trough system

moving westward towards the Windward Island chain, interacted with a mid to upper-level trough system

moving in a south to north direction. Heavy precipitation, high winds and thunderstorm activity was

generated along the eastern boundary of the mid to upper-level trough as a result of this interaction. Peak

rainfall intensity occurred over the 3-hour period between 9:00 p.m. and 12:00 a.m. on the evening of

December 24, 2013. Observed rainfall accumulations ranged between 163 millimetres (mm) to 312 mm at

Belle Isle and Rabacca stations in St. Vincent. Rainfall intensities were highest in the north-eastern

quadrant of St. Vincent with rainfall gauges in this area recording a maximum intensity of 278 mm per

3hour period.

1.3 The passage of the trough and accompanying torrential rainfall resulted in significant river flooding

and landslide damage to mainland St. Vincent. Nine fatalities and 34 persons with injuries were recorded.

Damage was sustained on both windward and leeward sides of the island. As a result of the extreme rainfall,

flash flooding, slope failures and debris flows triggered by the trough event, St. Vincent experienced

extensive damage to roads, bridges, river defences, drainage, water intake and distribution infrastructure,

agriculture, settlements and residential housing. During the storm, a total of 21% of bridges on the island

were affected, with 24 bridges (13% of all bridges) damaged and 14 bridges being completely destroyed.

Estimated damage to bridges and roadways is approximately USD7.9 mn.

1.4 Three of the major bridges affected by the Trough Event are the Yambou, Teviot and Zenga

Bridges, which suffered scour and structural damage to their foundations, as a result of high velocity flows.

Hydraulic models indicates overtopping of all 3 bridge structures for a 1 in 25-year return period, consistent

with the December 2013 Trough System. Sections of the Vigie Highway parallel to the Yambou River,

were undermined from erosion, slope failure, and the loss or damage of retaining structures, where present.

1.5 The Vigie Highway is south-west to north-east oriented transport corridor linking Kingstown to

the Windward Highway at Peruvian Vale. It provides redundancy to the main north-south Windward

Highway offering central and north windward communities north of Peruvian Vale a shorter, alternative

cross-country route of accessing Kingstown, the capital. En route to Kingstown, the Vigie Highway

traverses an urban commercial settlement node, locally known as “Mespo” (Marriaqua) at a complex

junction of four roads, and three river spanning bridges (Teviot, Zenga & Yambou). The junction is a busy,

high traffic area, at which a health-centre, abattoir, police station, doctor’s office, community centre,

church, and school are located. Three secondary schools and three primary schools are located within a

0.5 km radius of the junction. Physically, the junction serves as a central transport hub, for school children

and other commuters, into Kingstown as well as to more rural areas.

APPENDIX 2.3 Page 2

1.6 The bridges, channel embankments, and existing river defences at this junction have suffered scour

and structural damage to their foundation from the Trough Event and several past river flood events. Where

the Vigie corridor parallels the Yambou River, several sections have been undermined through erosion,

slope failure and the loss/damage of retaining structures. Between Crick Corner (La Croix) and Peruvian

Vale, the Vigie Highway corridor also traverses and is encroached by steep slopes of varying geological

composition and stability. At the Jack Hill section, the road foundation was observed moving and the

surface treatment has been sheared away under the influence of sub-surface water and/or the soil

composition.

1.7 Recognizing the needs for: maintaining network redundancy; building resilience; addressing slope

stability/landslide risk; reducing flood risk; enhancing hydraulic capacity; remedying disrepair; improving

vertical and horizontal alignments; reducing commuter travel time and increasing safety; GOSVG has

targeted the Vigie Highway and its associated bridges, for upgrade and rehabilitation.

1.8 The GOSVG has, through the Ministry of Transport and Works (MTW) in house efforts, developed

detailed designs and estimates of quantities from Crick Corner to “Mespo”. Between “Mespo” to Peruvian

Vale, detailed designs have yet to be developed. Financing has already been secured by the GOSVG from

the Republic of China and from the European Union, for phased Vigie Highway upgrade from Vigie to the

Crick Corner (La Croix).

2. OBJECTIVE

2.1 The objective of the consultancy is to provide GOSVG with appropriate climate change sensitive

technically and economically feasible options for the upgrade of 6 km of roadway, including 3 bridges,

along the Vigie Highway, and preparing final designs and bidding documents for the selected options. This

will be achieved through the assessment of conditions at the project sites, identifying cost effective remedial

civil works and designing long-term structural solutions that build resilience to future natural hazard events.

3. SCOPE OF SERVICES

3.1 The services shall be carried out in accordance with generally accepted standards of professional

practice, following recognized engineering and management principles and practices. The Consultants’

scope of work is understood to cover all activities necessary to accomplish the stated objectives. All

important data and calculations should be presented in sufficient detail to permit verification.

3.2 The scope of services to be provided by the Consultant(s) will include, but not be limited to:

Phase 1

(a) Collecting, reviewing and analysing all relevant available data, including inter alia Final

Report of the Hydraulic Assessment for Flood Risk Reduction1/, meteorological, landslide risk, geological and hydraulic information, topographical maps, and any other information

relevant to the assignment;

1/ This Hydraulic Assessment Report is a TA output financed by the CDB Rehabilitation and Reconstruction (Hurricane

Tomas/North Windward) Loan approved in July 2011. The Report is expected to provide preferred options for bridge design,

river defense and bridge approaches. The hydraulic study will provide flood elevation, peak discharge and map the spatial

area of flooding from the 25, 50 and 100-year return period flood events.

APPENDIX 2.3 Page 3

(b) Conducting extensive field surveys and investigations to suitably inform the design

process, in particular:

(i) soil and geotechnical surveys;

(ii) road and bridge condition assessment surveys;

(iii) topographical surveys;

(iv) hydraulic surveys;

(v) location of above and underground utilities; and

(vi) traffic surveys and forecasts to the year 2030, taking into consideration, inter alia,

average daily traffic, land use plans, average annual traffic growth (include basis

for growth rate assumed).

(vii) road safety audit.

(c) developing and presenting long-term design options for the project sites including the

bridges and their approaches;

(d) identifying climate vulnerability of the design options. Factors to be considered should

include: increases in the frequency and/or intensity of extreme precipitation leading to

more frequent flooding events; increased river flows. Based on this analysis the consultants

should identify adaptation/ resilience building options;

(e) identifying climate risks which cannot be adapted within the scope of the Project, that

should be subject to future investigation, action and/or studies;

(f) reviewing and documenting potential environmental, social, and climate impacts. All data

should be disaggregated by sex to ensure all perspectives are captured;

(g) preparing preliminary designs, implementation schedule and estimate of resources needed,

including base costs, life cycle costs, physical and price contingencies for the development

of each design option proposed; and

(h) carrying out appropriate least-cost analyses on each design option to justify preferred

options;

3.3 Contingent upon GOSVG and CDB’s prior review and approval of the proposed preferred options:

(a) preparing detailed designs and specifications as necessary for all civil and structural works

installations. The detailed specifications will be produced in accordance with accepted

international standards;

(b) preparing bills of quantities and detailed cost estimates for the proposed works, based on

the designs and specifications above. The detailed specifications will be produced in

accordance with accepted international standards. Current costs for similar works in

St. Vincent and the Grenadines will be used as the basis for all unit rates and detailed

costings;

APPENDIX 2.3 Page 4

(c) preparing standard bidding documents for the contract to allow GOSVG to solicit bids from

prequalified international, regional and local contractors or joint ventures of

local/regional/international contractors. In this regard, the Consultant(s) are referred to

CDB’s Standard Bidding Documents for Procurement of Works;

(d) preparing an assessment of the environmental impacts of the preferred option. It should

include an assessment of baseline environmental conditions, as well as relevant policies,

legislation and regulation which have implications for successful implementation of the

design. This should also include the identification of significant ecological and physical

impacts, the recommendation of necessary mitigation measures and estimates of the

associated costs both during implementation and over the project life;

(e) conducting a Social Impact Assessment of the preferred option. Particular attention should

be paid to the following:

(i) demographic and socio-cultural characteristics of the resident population in the

project areas;

(ii) impact of works on stakeholders, recommended mitigation measures, and

monitoring indicators;

(iii) impact of any land acquisition and redevelopment on local residents and

businesses; and

(iv) socioeconomic benefits of the project to stakeholders.

Participatory methodologies should be utilised in data gathering and action planning

with all stakeholders. This should include workshops or other forms of stakeholder

consultation to discuss recommendations.

(f) conducting an Economic Assessment of the preferred option using the HDM IV model, to

identify the relevant costs and benefits. In performing this analysis, the Consultant(s) will

be required to carry out the following:

(i) develop a complete input data set for performing HDM quantitative analyses of

the road improvement options;

(ii) select a set of possible maintenance and construction policies and define the

strategies to be employed;

(iii) provide detailed calculations of any exogenous costs/benefits for input into the

model;

(iv) Calibrate HDM IV model for St. Vincent conditions.

(g) Conduct appropriate cost-benefit analyses of the preferred bridge design options,

specifically taking into consideration: climate change adaptation/natural hazard risk

reduction measures, over the design life of the project. Benefits and costs to be considered

should include but not be restricted to reduction in future damages and/or losses (losses

avoided);

APPENDIX 2.3 Page 5

(h) developing procurement arrangements to ensure:

(i) adherence to CDB’s procurement guidelines; and

(ii) compliance with local laws and standards.

3.4 In the conduct of the services, the Consultant will collaborate with the MTW.

4. REPORTING REQUIREMENTS AND DELIVERABLES

4.1 The Consultant(s) will present six (6) copies of reports, four (4) copies to GOSVG and two (2)

copies to CDB. Electronic submissions of all reports should also be made in pdf format. These reports are

as follows:

Inception Report

(a) The Inception Report will be presented 30 days after the signing of the contract, and it will

include:

(i) initial findings including any comments on these Terms of Reference (TOR);

(ii) consultants’ detailed work schedule and methodology;

(iii) a programme for the use of resources including personnel, equipment, materials,

etc.;

(iv) a proposed outline for the final report; and

(v) design criteria to be employed.

(b) GOSVG and CDB will provide comments on this Report within two (2) weeks of receipt

of the Report and the consultants will adjust the on-going work according to the comments

received.

Draft Interim Report

(a) The Interim Report will be presented no later than 90 days after the signing of the contract,

and it will:

(i) present the results of the surveys conducted;

(ii) present preliminary designs and analyse the design options under consideration;

(iii) estimate construction costs and life cycle costs of the design options, including all

discounted and undiscounted costs and benefits;

(iv) based on least-cost analysis, provide a clear recommendation for the preferred

design option that should be undertaken, supported by a programme of works for

its implementation.

APPENDIX 2.3 Page 6

(b) GOSVG and CDB will provide comments on this Report within two (2) weeks of receipt

of the Report and the consultants will adjust the on-going work according to the comments

received.

Interim Report

Within two (2) weeks of receipt of comments from GOSVG and CDB on the Draft Interim Report,

the Consultant(s) shall present the Interim Report.

Draft Final Report

(a) The Draft Final Report will be submitted 60 days after agreement between CDB and

GOSVG on the recommendations arising out of the Interim. The Report should present:

(i) detailed designs and cost estimates; and;

(ii) bidding documents.

(b) GOSVG and CDB will provide comments on this Report within two (2) weeks of receipt

of the Report and the Consultant(s) will adjust the on-going work according to the

comments received.

Final Report

Within two (2) weeks of receipt of comments from GOSVG and CDB on the Draft Final Report,

the Consultant(s) shall present the Final Report.

5. IMPLEMENTATION ARRANGEMENTS

5.1 GOSVG will appoint a Project Coordinator (PC). The PC will facilitate the work of the

Consultant(s) and make available all relevant studies, reports and data, relevant to completion of the

exercise and will act as liaison between the consultants and GOSVG officials and stakeholders.

6. QUALIFICATIONS AND EXPERIENCE

6.1 The consulting team should consist of persons having appropriate professional and academic

qualifications, and a minimum of 8 years’ relevant experience in the areas of structural engineering,

geotechnical engineering, hydraulic engineering, hydrology and hydrological assessment, disaster risk

management, financial and economic analysis, environmental assessment, and social assessment. Post

graduate qualifications in the required fields as well as specific experience in the Caribbean will be an asset. 7. DURATION

7.1 The Consultancy is to be implemented over a period of seven months.

APPENDIX 2.3 Page 7

8. LABOUR, SCHEDULING AND COSTS

8.1 In estimating person-month requirements and cost of the services, the Consultant(s) should ensure

that the proposal takes full account of all fees and direct expenses required to fulfil the above requirements

and the following items:

(a) consultant’s remuneration;

(b) consultant’s out-of-pocket expenses;

(c) support staff services;

(d) equipment hire;

(e) communication costs;

(f) report production costs;

(g) contract documentation production costs;

(h) supervision costs; and

(i) survey costs.

9. COMMENTS BY THE CONSULTANT(S)

9.1 The Consultant(s) may make comments on, and suggestions for, improvements to these TOR. The

financial implications, if any, of these recommendations should be indicated separately in the Financial

Proposal.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.4

DRAFT TERMS OF REFERENCE

CONSULTANCY SERVICES TO UNDERTAKE LANDSLIDE RISK ASSESSMENT,

SLOPE STABILISATION AND REMEDIAL DESIGN STUDY FOR ST. VINCENT’S

NORTH WINDWARD HIGHWAY CORRIDOR

1. BACKGROUND

1.1 Government of St. Vincent and the Grenadines (GOSVG) has approached Caribbean

Development Bank (CDB) for technical assistance (TA) to finance a landslide risk assessment and slope

stabilisation study for sections of the Windward Highway corridor at: (i) Spring (ii) Orange Hill; (iii)

Sandy Bay to Aqueduct; (iv) Roway to Point; (v) Owia; (vi) Bloody Bridge: (vii) Windblow; and (viii)

Soldier Hill; as a component of the loan to rehabilitate and reconstruct infrastructure damage as a

consequence of the December 24-25, 2013 Trough System. Slopes at several of these locations are

susceptible to failure as a consequence of a combination of: their angles of repose; soil composition;

prevailing land use practices; drainage; and marine erosion.

1.2 The Windward Highway is a critical north-south coastal transit corridor for eastern St. Vincent

connecting rural northern and central settlement areas to the capital, Kingstown. Redundancy is limited

along this corridor, and where available is restricted to some secondary and agricultural feeder roads

oriented parallel and inland of the Highway. Partial or total section failure along the Windward Highway

manifests significant negative economic and social impact as a consequence of the interruption in the

normal flow of goods and services.

1.3 Over a 24-hour period between December 24 to 25, 2013, an unseasonal low-level trough system

moving westwards towards the Windward Islands chain, interacted with a mid to upper-level trough

system moving in a south to north direction. Heavy precipitation, high winds and thunderstorm activity

was generated along the eastern boundary of mid to upper-level trough as a result of this interaction.

Peak rainfall intensity occurred over the three-hour period between 9:00 p.m. and 12:00 a.m. on the

evening of December 24, 2013. Observed rainfall accumulations ranged between 163 millimetres (mm)

to 312 mm at Belle Isle and Rabacca Stations in St. Vincent. Rainfall intensities were highest in the

northeastern quadrant of St. Vincent with rainfall gauges in this area recording a maximum intensity of

278 mm per 3-hour period.

1.4 The passage of the trough and accompanying torrential rainfall resulted in significant river

flooding and landslide damage to mainland St. Vincent. Nine fatalities and 34 persons with injuries were

recorded. Damage was sustained on both the windward and leeward sides of the island. As a

consequence of slides along the terminal sections of the coastal corridor, access to and egress from the

communities of Owia and Fancy was severed. During this period, relief supplies had to be airlifted in.

1.5 The extreme rainfall, flash flooding, slope failures and debris flows triggered by the trough

system in St. Vincent caused extensive damage to roads, bridges, river defense, drainage, water intake and

distribution infrastructure, agriculture, settlements and residential housing. A critical and significant

section of the Kingstown inbound of the Windward Highway at Orange Hill, in the vicinity of the

Agriculture Research Institute, was impacted by slope failure as a consequence of the trough event.

APPENDIX 2.4 Page 2

1.6 The transport sector was severely affected with estimated damage and loss of eighty-two million

six hundred thousand United States dollars (USD82.6 mn)1/.

1.7 The island is characterised by steep topography and large ravines with land rising from sea level

to 800 m or more over a distance of 3 to 6 km. Slopes are often at angles close to the angle of repose for

the substrata and, as such, only small changes in stability conditions are required to bring such slopes

close to failure. Often rainfall is the principal triggering mechanism for landslides along zones of

weakness, e.g. where soil interfaces with bedrock. Main soil movement types include rock fall, landslides

and debris flows.

1.8 Positive impacts are expected to accrue from the implementation of slope stabilisation measures

that will help to reduce human and livelihood loss, as well as property and environmental damage. In

addition, the Project is expected to have a long-term beneficial impact by improving institutional capacity

for landslide risk assessment and increasing awareness regarding slope management, stabilisation and

safe land use.

2. OBJECTIVE

2.1 The objective of the TA is to reduce landslide risk to identified critical sections of the Windward

Highway of mainland St. Vincent, through the analysis and assessment of slope stability, drainage and

geotechnical conditions, mapping levels of risk, identification of primary and secondary causal factors of

slope movement, and development cost effective slope stabilisation, protection and landslide remediation

measures. The Project is expected to enhance the capacity of GOSVG to manage landslide hazards.

3. SCOPE OF WORK

3.1 The scope of services includes, but is not limited to:

Hazard and Vulnerability Analysis

(a) Demarcation and agreement of critical hot-spots in consultation with the Ministry of

Transport and Works (MTW).

(b) Review of past road sector maintenance plans and any future transportation sector

development plans.

(c) Characterisation of the hazard and vulnerabilities of the agreed critical hotspots to

landslides/slope failures, factoring in:

(i) past landslide assessment studies, inventories and maps;

(ii) available topographic and survey data;

(iii) consequences and probabilities - the primary roads and their associated

infrastructure at risk; the relative socio-economic importance of the road; the

importance and relevancy of the road in the context of the transport sector; and in

facilitating access;

1/ Source: Rapid Damage and Loss Assessment undertaken by the World Bank with support from the European

Union in the Framework of the ACP-EU Natural Disaster Risk Reduction Program managed by the Global

Facility for Disaster Risk Reduction (January 2014).

APPENDIX 2.4 Page 3

(iv) current landslides and slope instability potential;

(v) geomorphologic and geotechnical factors such as size, shape, volume, run-out

distance, movement and material types, activity/state, damage corridor width,

paths, drainage, soil stratigraphy, relevant primary and secondary triggering

factors, and probability of failure;

(vi) site specific geotechnical and survey assessments at critical sites; and

(vii) available climate change information.

Risk Assessment

(d) Site specific assessment of the risks to the identified hotspots in consultation with MTW

and other relevant key line agencies.

(e) Characterisation of the probability of occurrence/failure, potential for loss and

development of a priority ranking system in the risk assessment exercise.

Comparison of Slope Stabilisation Design Options

(f) Identification and comparison of cost-effective optional measures and necessary

supervisory engineering services for slope management, slope stabilisation, protection

and slope failure/landslide remediation, at agreed critical sites.

(g) Cost estimation and cost-benefit analysis of agreed slope stabilisation, protection and/or

remediation works at existing critical and highly vulnerable sites.

Preparation of Preliminary Designs

(h) Preparation of preliminary designs, cost and quantity estimates for GOSVG, agreed slope

stabilisation and remedial works.

Site Specific Surveys and Geotechnical Investigations for Identified Critical Priority Sites

Requiring Slope Stabilisation, Roadway Remediation and/or Sea Defences

(i) Implementing appropriate site specific surveys and geotechnical investigations to inform

the preparation of detailed site specific designs, quantities and cost estimates for

identified critical priority sites requiring slope stabilisation, road remediation and/or sea

defences.

Preparation of Site Specific Detailed Designs, Drawings, Quantities and Cost Estimates for

Identified Critical Priority Sites Requiring Slope Stabilisation, Road Remediation and/or

Sea Defences.

(j) Development and preparation of detailed designs, drawings, quantity and cost estimates

for identified critical priority sites requiring slope stabilisation, road remediation and/or

sea defences.

APPENDIX 2.4 Page 4

Preparation of Slope Stabilisation, Road Remediation and/or Sea Defences Bid Documents

for Identified Critical Priority Sites

(k) Preparation of standard bid documents for slope stabilisation, road remediation and/or sea

defences for Identified Critical Priority Sites.

Development of Landslide Risk Management Systems and Risk Mapping

(l) Design, development and/or updating of digital landslide risk inventories in consultation

with and input from MTW.

(m) Recommendation and costing of design elements for a new, or update of an existing,

landslide information data management system.

(n) Development of an appropriately scaled landslide risk map in relation to the Windward

Highway.

Development of a Plan for Long-Term Landslide Risk Management and Slope Protection

(o) Identification of critical elements, and development of a practical plan for managing

longer-term landslide risk, and slope protection in consultation with MTW and other

relevant key stakeholders.

Stakeholder Workshops/Consultations

(p) Conducting consultative and participatory stakeholder meetings periodically at

appropriate points of the Project, with key transport sector users and stakeholders,

ministerial departments and agencies including, but not restricted to, public works,

planning, finance, forestry, agriculture, National Emergency Management Organisation,

water utilities, civil society, e.g. community groups, and any other relevant parties,

regarding their perspectives, concerns, perceived current needs and preferred options in

terms of future primary road network vulnerability reduction, maintenance, and enhanced

use.

(q) Liaising with the entities identified at (p) above with respect to determining other

planned, programmed, or ongoing initiatives, to reduce duplication and to optimise

complementarities relative to the scope of this Project.

(r) Surveying and collecting data in the field where information gaps exist.

Landslide Risk and Slope Management Training

(s) Delivery of a workshop training session on landslide risk and slope management, slope

stabilisation and protection, including drainage and storm-water management and

maintenance for MTW technicians and other key GOSVG stakeholders using the

December 2013 Trough Event experience as a case study.

APPENDIX 2.4 Page 5

4. SITE SUPERVISION FOR ORANGE HILL SITE

4.1 The consultants will be required to develop a phased programme of works; prepare a draft

Environmental Management and Monitoring Plan; assist MTW in the evaluation of tenders, including the

preparation of tender reports; assist MTW in negotiation of contracts for the construction works; conduct

technical inspection and supervision of construction of works for compliance with contract documents;

consult and advise MTW on matters arising during implementation of infrastructure works;

environmental monitoring during construction; certify work done for payment; prepare monthly reports

on the progress of the works, indicating any engineering difficulties affecting their efficient and timely

execution, commencing one month after the start date as defined in the construction contract; revise

designs to meet unforeseen conditions which may arise during construction; issue certificate of

completion to the contractor upon completion of construction contract; prepare a completion report on

construction of the project, and as-built drawing, within three months after the date of issue of certificate

of practical completion of the Project.

5. IMPLEMENTATION ARRANGEMENTS

5.1 MTW will appoint a Project Coordinator (PC). The PC will facilitate the work of the

Consultant(s) and make available all relevant studies, reports and data relevant to completion of the

exercise and will act as liaison between the Consultant(s) and GOSVG officials and stakeholders.

6. QUALIFICATIONS AND EXPERIENCE

6.1 The Consulting team should consist of persons having appropriate professional and academic

qualifications, a minimum of 8 years’ relevant experience in the areas of geotechnical, road,

drainage/hydraulic, and coastal engineering; disaster risk management; financial analysis; community

education and in the application of community participatory methods. Specific experience in the

Caribbean will be an asset.

7. REPORTING ARRANGEMENTS/OUTPUTS

7.1 The Consultant(s) will be required to submit the following number of reports to GOSVG and

CDB within the time periods indicated:

(a) Three (3) and two (2) copies respectively, of an inception report describing the

approaches proposed to be taken to prepare and deliver the scope of works outlined

within two weeks of the start of the consultancy. GOSVG and CDB will provide

comments on this report within two weeks of receipt of the report and the Consultant(s)

will adjust the ongoing work according to the comments received.

(b) Three (3) and two (2) copies respectively, of a Draft Feasibility and Preliminary Design

Options Report which contains a risk analysis, risk mapping and design options report

covering cost-effective priority slope stabilisation, slope management, landslide

remediation and sea defence works, within three months of the start of the consultancy.

GOSVG and CDB will provide comments on this report within two weeks of receiving

the report. The consultants will revise the report within one month of receipt and in

accordance with the comments received. Five (5) and two (2) copies respectively of the

Final Feasibility and Preliminary Design Options Report must be submitted to GOSVG

and CDB.

APPENDIX 2.4 Page 6

(c) Three (3) and two (2) copies respectively, of a Draft Geotechnical and Survey Report for

Critical Priority Sites within four months of the start of the consultancy. GOSVG and

CDB will provide comments on this report within two weeks of receiving the report. The

Consultant(s) will revise the report within one month of receipt and in accordance with

the comments received. Three (3) and two (2) copies respectively of the Final

Geotechnical and Survey Report for Critical Priority Sites must be submitted to GOSVG

and CDB.

(d) Three (3) and two (2) copies respectively, of a Draft Critical Priority Slope Stabilisation,

Road Remediation and Sea Defences Detailed Designs, Drawings, Quantities and Cost

Estimates and Bid Document report within five months of the start of the consultancy.

GOSVG and CDB will provide comments on this report within two weeks of receiving

the report. The Consultant(s) will revise the report within one month of receipt and in

accordance with the comments received. Three (3) and two (2) copies respectively of the

Final Critical Priority Slope Stabilisation, Road Remediation and Sea Defences Detailed

Designs, Drawings, Quantities and Cost Estimates and Bid Document report must be

submitted to GOSVG and CDB.

(e) Three (3) and two (2) copies respectively, of a Draft Landslide Risk Management and

Slope Protection Plan within six months of the start of the consultancy. GOSVG and

CDB will provide comments on this report within two weeks of receiving the report. The

Consultant(s) will revise the report within one month of receipt and in accordance with

the comments received. Three (3) and two (2) copies respectively of the Final Landslide

Risk Management and Slope Protection Plan must be submitted to GOSVG and CDB.

8. MANPOWER, SCHEDULING AND COSTS

8.1 In estimating person-month requirements and cost of the services, the Consultant(s) should ensure

that the proposal takes full account of all fees and direct expenses required to fulfil the above

requirements and the following items:

(a) consultant’s remuneration;

(b) consultant’s out-of-pocket expenses;

(c) support staff services;

(d) equipment hire;

(e) communication costs;

(f) report production costs;

(g) contract documentation production costs;

(h) supervision costs; and

(i) survey costs.

APPENDIX 2.4 Page 7

9. COMMENTS BY THE CONSULTANTS

9.1 The Consultant(s) are requested to make comments on, and suggestions for, improvements to

these Terms of Reference. The financial implications, if any, of these recommendations should be

indicated separately in the Financial Proposal.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

p

APPENDIX 2.5

PROJECT COST, PHASING AND FINANCING PLAN

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

AP

PE

ND

IX 2

.6

ID Task Name

1 CDB Board Approval

2 Sign Loan Agreement

3 Selection and Engagement of PC

4 Advertising REOI

5 Shortlisting and Final Selection

6 Contract Period

7 Project Launch Workshop

8 Compliance with Other Conditions Precedent

9 Project Implementation

10 Engineering Services (Immediate Mitigation)

11 Selection and Engagement of Consultants

12 Tender Document Preparation 1b

13 Tender Document Preparation 1a

14 Construction Supervision

15 Project Completion Report

16 Defects Liability Period Monitoring

17 Civil Works (Immediate Mitigation 1b)

18 Tender Period

19 Construction

20 Defects Liability Period

21 Civil Works (Immediate Mitigation 1a)

22 Tender Period

23 Construction

24 Defects Liability Period

25 Engineering Services (Rehabilitation and Upgrade)

26 Selection and Engagement of Consultants

27 Tender Document Preparation

28 Construction Supervision

29 Project Completion Report

30 Defects Liability Period Monitoring

31 Civil Works (Package 2)

32 Tender Period

33 Construction

34 Defects Liability Period

35 Civil Works (Package 3)

36 Tender Period

37 Construction

38 Defects Liability Period

39 Institutional Strengthening (Training)

40 Contract Period

41 Landslide Risk Assessment Study

42 Selection and Engagement of Consultants

43 Contract Period

44 Vigie Highway Rehab and Upgrade Study

45 Selction and Engagement of Consultant

46 Contract Period

47 Project Completion Report

48 Exit Workshop

DRAFT PROJECT IMPLEMENTATION SCHEDULE

14 2015 2016 2017 2018

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 7/16

8/20

2/5

6/20

7/20

5/21

Task Milestone Summary Progress

Natural Disaster Management - Rehabilitation and Reconstruction

(December Trough System) - ST. VINCENT AND THE GRENADINES

APPENDIX 2.7

IMPLEMENTATION SUPPORT PLAN

1. CDB has been the principal partner for GOSVG in the financing of road infrastructure projects,

particularly on the main road network. This experience, strengthened by the satisfactory progress being

made on implementing the ongoing South Leeward Highway Project, provides a sound background for

providing implementation support to GOSVG. The implementation support will be provided as part of

CDB’s project supervision functions and will include, among other things:

(a) reviewing implementation progress and achievement of project outcomes;

(b) addressing implementation issues;

(c) monitoring systems to ensure their continued adequacy through monitoring reports;

audit reports and field visits; and

(d) monitoring changes in risks and compliance with legal agreements, as needed.

The Implementation Support Plan (ISP) will be reviewed at least once a year to ensure that it continues to

meet the implementation support needs of the Project. In addition to reviewing implementation progress,

the ISP aims at providing technical support to the BMC in the achievement of the results.

2. The strategy for implementation support has been developed based on the design of the Project, its

risk profile, and an assessment of the Borrower and Executing Agency. The strategy remains a flexible

tool that may be amended during project implementation in response to the changing needs of the Project

and the Borrower/Implementing Agency.

Strategy and Approach for Implementation Support

3. Supervision of the Project will be undertaken by a team comprising the lead

supervisor (Civil Engineer), supported by legal counsel and specialists in the areas of environment/disaster

risk management; procurement; financial analysis; and social analysis. Formal supervision and field visits

will be undertaken semi-annually. The first formal supervision activity will be the Project Launch

Workshop (PLW). The objective of PLW is to review the implementation arrangements, train the project

management in the use of CDB’s fiduciary management and procurement systems, and discuss project

supervision issues. PLW is scheduled for the third quarter of 2014, and arrangements will be finalised in

consultation with GOSVG. The training provided during PLW on the Bank’s financial management and

procurement procedures and guidelines will be augmented during the semi-annual supervision visits, and

support will be provided on a timely basis to respond to the client’s needs.

4. The Supervision Coordinator will coordinate CDB’s team to ensure that project implementation is

consistent with the requirements as specified in the Procurement Plan, Terms and Conditions, and other

legal documents. The Supervision Team will prepare annual Project Supervision Reports identifying the

status of project implementation and any issue requiring the resolution of management. On the completion

of the Project, or after 90% of the funds have been disbursed, Staff will conduct an Exit Workshop to assess

project results, discuss implementation issues, and identify lessons. A draft PCR will be prepared and

discussed with the client during the Exit Workshop. The final PCR will be validated by the Office of

Independent Evaluation (OIE). Staff will prepare a management response to the OIE’s Validation Report.

The Validation Report and Management’s response will be presented to the Audit and Post-Evaluation

Committee.

APPENDIX 2.7 Page 2

TABLE 1: STAFF SKILLS REQUIRED

Period

Focus

Skills and Resources Estimate

July –

December

2014

Specific (1) Project Launch Workshop.

(2) Support in satisfying Conditions

Precedent.

(3) Provide procurement support for

preparation of draft

prequalification documents,

bidding documents, requests for

proposals, draft procurement

notices etc. and also with respect to

resolving procurement bottlenecks,

and similar issues.

General

(1) Monitor project management

arrangements

(2) Monitor Project Budgeting and

Allocations.

(3) Monitor Project Results

Framework.

(4) Provide technical support to PC

and Implementing Agency.

(5) Monitor TA activities, including

review of TA reports

(6) Preparation of annual Project

Supervision Report.

(7) Review and certification of

requests for disbursement.

(8) Review of Monthly and Quarterly

Reports from Implementing

Agency

Lead Project 5 weeks

Supervisor

Legal Counsel 2 weeks

Financial 0.5 weeks

Analyst

Environmental 1 week

Specialist

Social 2 week

Specialist Procurement 1 week

Specialist

Administrative 1 week

Assistant

Divisional 0.5 week

Secretary

APPENDIX 2.7 Page 3

Period

Focus

Skills and Resources Estimate

January –

December

2015

Specific (1) Provide support for procurement of

Contractors for works packages;

(2) Review of evaluation reports, and draft

contracts for works and consultants.

General (1) Monitor Project Budgeting and

allocations.

(2) Monitor Project Physical Works

progress and quality, including field

trips.

(3) Monitor Project Results Framework (4) Provide technical support to PC and

Executing Agency.

(5) Preparation of annual Project

Supervision Report.

(6) Review and certification of requests for

disbursement.

(7) Review of TA reports. (8) Review of Monthly and Quarterly

Reports.

Lead Project Supervisor

Legal Counsel

Financial Analyst

Environmental Specialist

Social Specialist

Administrative Assistant

Divisional Secretary

8 weeks

0.5 weeks

0.5 week

0.5 week

3 weeks

2 weeks

1 week

January –

May

2016

General (1) Monitor Project Budgeting and

allocations.

(2) Monitor Project Physical Works

progress and quality, including field

trips.

(3) Monitor Project Results Framework (4) Provide technical support to PC and

Executing Agency.

(5) Preparation of annual Project

Supervision Report.

(6) Review and certification of requests for

disbursement.

(7) Review of TA reports. (8) Review of Monthly and Quarterly

Reports.

Lead Project Supervisor

Legal Counsel

Financial Analyst

Environmental Specialist

Social Specialist

(including Gender)

Administrative Assistant

Divisional Secretary

10 weeks

0.5 weeks

0.5 weeks

2 weeks

3 weeks

1 week

0.5 week

APPENDIX 2.7 Page 4

Period

Focus

Skills and Resources Estimate

June-

December

2016

Specific (1) Review PC and consultants final

reports.

(2) Conduct Exit Workshop and complete

PCR.

General

(1) Monitor reporting on infrastructure

during Defects Liability Period.

(2) Review and certification of requests for

disbursement.

(3) Review of TA reports.

Lead Project Supervisor 3 weeks

Legal Counsel 1 week

Financial Analyst 2 weeks

Environmental Specialist 1 week

Social Specialist 1.5 weeks

(including Gender)

Administrative Assistant 1 week

Divisional Secretary 0.5 week

APPENDIX 2.8

ESTIMATED QUARTERLY DISBURSEMENT SCHEDULE

($'000)

Year Quarter

No.

OCR

SFR

Finance

Charges

Total

Cumulative

2014 4 0 161 1 161 161

Sub-total

0 161 1 161 161

2015 1 1,302 1,168 49 2,518 2,680

2 1,302 1,168 66 2,536 5,215

3 1,302 1,168 83 2,553 7,768

4 1,297 1,168 101 2,565 10,333

Sub-total 5,202 4,671 299 10,172 10,333

2016 1 1,665 852 119 2,636 12,970

2 1,665 852 138 2,655 15,624

3 1,665 852 156 2,673 18,298

4 1,665 852 175 2,692 20,990

Sub-total 6,660 3,409 588 10,657 20,990

2017 1 694 911 189 1,794 22,784

2 1,439 0 202 1,641 24,425

3 0 0 0 0 24,425

4 0 0 0 0 24,425

Sub-total

2,133 911 391 3,435 24,425

Total 13,995 9,152 1,279 24,425 24,425

APPENDIX 2.9

PROJECT MANAGEMENT ORGANISATIONAL CHART

Permanent Secretary - MTW

Chief Engineer

Senior Assistant Secretary

Office of the Chief Engineer Electrical Inspectorate

Project Management Division Project Manager -

Hydrology (CWSA)

General

Administration Project

Coordinator

Project Engineer

Engineering Consultants TA Consultants Administrative/

Accounting Officer

Contractors -

Infrastructure Works

APPENDIX 2.10

DRAFT TERMS OF REFERENCE

PROJECT TEAM

1. PROJECT COORDINATOR

1.1 The Project Coordinator (PC) will report to the Chief Engineer, Minister of Transport and Works.

He/she will be responsible for coordinating and monitoring all aspects of the implementation of the Project.

PC shall be assigned exclusively to the Project and will be supported by one Project Engineer (PE), an

Administrative/Accounting Officer (AO) and administrative staff. PC’s duties will include, but will not be

limited to:

(a) revising the Results Monitoring Framework, including the collection of baseline data, for

the Project;

(b) managing the selection and engagement of technical assistance consultants and supervising

these consultancies;

(c) evaluation of bids and recommendation of the awards for the Engineering Consultants and

construction contracts;

(d) overseeing the Engineering Consultancy and construction contracts;

(e) cost control;

(f) expedition of the submission to Caribbean Development Bank (CDB) of claims for

disbursement/reimbursement;

(g) liaison with CDB on all technical and administrative aspects of the Project;

(h) preparation and submission to CDB of a Quarterly Report on the Investment Cost of the

Project in the form specified by CDB, within two weeks after the end of each calendar

quarter, commencing with the quarter following the commencement of the assignment;

(i) keeping separate accounts for project-related expenditures and disbursement activities;

(j) submission to CDB within two days after the end of each fortnight, of fortnightly progress

spreadsheet prepared by PE;

(k) submission to CDB, within two weeks after the end of each month, of monthly reports

prepared by the Engineering Consultants;

(l) submission to CDB of annual report showing the level of road maintenance at the end of

the preceding year;

(m) submission to CDB of completion report within three months after the date of issue by the

Engineering Consultants of a certificate of practical completion of the contract; and

(n) preparation and submission to CDB of a Project Completion Report, within three months

after practical completion of the works.

APPENDIX 2.10

Page 2

1.2 Prospective candidates should have a minimum of the following qualifications:

(a) a Masters Degree or equivalent in Civil Engineering, Construction Management or Project

Management with a minimum of 10 years’ experience in the management and

implementation of civil engineering projects; or

(b) a Bachelors Degree or equivalent in Civil Engineering, Construction Management or

Project Management with a minimum of 15 years’ experience in the management and

implementation of civil engineering projects.

2. PROJECT ENGINEER

2.1 PE will report to PC and will mainly be responsible for assisting PC with the implementation of

infrastructure works. His/her duties will include, but will not be limited to:

(a) assisting PC with the supervision of the engineering consultants, including review of the

monthly reports prepared by the Engineering Consultants;

(b) assisting PC with the management and administration of the construction contracts;

(c) preparation of the fortnightly progress spreadsheets within two days after the end of each

fortnight for submission to PC; and

(d) any other duties assigned by PC.

2.2 Prospective candidates must be civil engineers with a minimum of the following qualifications:

(a) a Master’s Degree or equivalent in a civil engineering discipline, Project Management,

Construction Management or related subject, together with a minimum of five years’

experience in engineering design and supervision, including road works, or project

implementation; or

(b) a Bachelor’s Degree in civil engineering and a minimum of eight years’ of suitable

experience in engineering design and supervision, including road works or project

implementation.

3. PROJECT MANAGER HYDROLOGY

3.1 Central Water and Sewerage Authority (CWSA) shall appoint a Project Manager

Hydrology (PMH). PMH will report to PC and will mainly be responsible for assisting PC with, the

implementation of the supply and installation of Hydrometric Equipment equipment. His/her duties will

include, but will not be limited to:

(a) Facilitation of the work of the suppliers to make available relevant information and to

facilitate the completion of the exercise. The PMH will act as a liaison between the

suppliers and GOSVG officials.

APPENDIX 2.10

4. ADMINISTRATIVE/ACCOUNTING OFFICER

Page 3

4.1 AO will report to PC and will mainly be responsible for keeping accounting records and preparing

financial statements on expenditures for the Project Team (PT) and disbursement claims for Contractors

and Engineering Consultants for submission to CDB. AO will also be responsible for the administrative

duties of the PT. His/her duties will include, but will not be limited to:

(a) prepare requests for disbursements from the financing agencies;

(b) prepare monthly financial statements and supporting schedules;

(c) prepare financial information for special reports for internal and external use;

(d) review and track details of all claims from consultants and contractors; and

(e) any other administrative duties assigned by PC.

4.2 AO is expected to have a Bachelor’s Degree in accounting or related field and a minimum of two

years’ experience in administration/accounting is required, in addition to proficiency in computer skills,

including use of spreadsheets, database management and word processing. Good written and oral

communications skills are required. Prior project-related experience would be an asset.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.11

DRAFT TERMS OF REFERENCE

CONSULTING ENGINEERING SERVICES FOR DESIGN REVIEW AND CONSTRUCTION

SUPERVISION – IMMEDIATE MITIGATION WORKS

1. BACKGROUND

1.1 The Government of St. Vincent and the Grenadines (GOSVG) has applied for financing from the

Caribbean Development Bank (CDB) towards the cost of rehabilitation and reconstruction of

infrastructure damaged as a consequence of a trough event which occurred over a 24-hour period from

December 24 to 25, 2013. An unseasonal low-level trough system moving westwards towards the

Windward Islands chain, interacted with a mid to upper-level trough system moving in a south to north

direction generated heavy precipitation, high winds and thunderstorm activity along its eastern boundary.

Peak rainfall intensity occurred over the three-hour period between 9:00 p.m. and 12:00 a.m. on the

evening of December 24, 2013. Observed rainfall accumulations ranged between 163 millimetres (mm)

to 312 mm at Belle Isle and Rabacca Stations in St. Vincent. Rainfall intensities were highest in the

northeastern quadrant of St. Vincent with rainfall gauges in this area recording a maximum intensity of

278 mm per 3-hour period.

1.2 The passage of the trough and accompanying torrential rainfall resulted in significant river

flooding and landslide damage to mainland St. Vincent. Nine fatalities and 34 persons with injuries were

recorded. Damage was sustained on both windward and leeward sides of the island. As a result of the

extreme rainfall, flash flooding, slope failures and debris flows triggered by the weather system,

St. Vincent experienced extensive damage to roads, bridges, river defences, drainage, water intake and

distribution infrastructure, agriculture, settlements and residential housing. During the storm, a total of

21% of bridges on the island were affected, with 24 bridges (13% of all bridges) damaged and 14 bridges

being completely destroyed. Estimated damage to bridges and roadways was approximately USD7.9 mn.

1.3 The Ministry of Transport and Works (MTW) has prepared designs for works to infrastructure

requiring immediate repair in order to restore an adequate level of service to the surrounding

communities. Consulting services are required for the review of the designs, for the provision of

assistance to GOSVG in managing the procurement of the contractor(s) for the works, and for supervision

of construction.

2. OBJECTIVE

2.1 The objectives of the assignment are as follows:

(a) to ensure that designs for the bridge and road rehabilitation works are completed in

accordance with the highest practicable local and international engineering and design

standards to provide solutions with the lowest life-cycle costs that satisfy the design

criteria;

(b) to ensure that high quality construction is achieved and to ensure that all work is carried

out in full compliance with the engineering design, technical specifications and other

contract documents; and

(c) to provide support to the executing agency in the execution of its project management

functions, including its monitoring and evaluation functions.

APPENDIX 2.11

Page 2

2.2 GOSVG, in an effort to provide the necessary infrastructural support for the economic and social

development of the project areas, is desirous of engaging qualified and experienced Consultant(s) to be

responsible for the design and supervision of the execution of works financed by CDB, inclusive of the

following:

(a) slope stabilisation and associated rehabilitation of road works at selected critical sites

along the North Windward and Vigie Highways;

(b) rehabilitation works to four bridges and adjacent roadways along the North Windward

and Vigie Highways; and

(c) reconstruction works to one bridge.

3. SCOPE OF WORK

3.1 The consultancy services will be undertaken in respect of works to the following:

(a) rehabilitation of bridges and associated river defence works at:

(i) Union River Bridge, along Windward Highway;

(ii) Yambou, Teviot and Zenga Bridges, along Vigie Highway;

(b) construction of a new bridge, the Red Dog Bridge, in Mesopotamia; and

(c) road rehabilitation works, including rehabilitation of road embankments and slope

stabilisation, at selected sites along the Windward Highway, including Tourama, Magum,

and Mespo, along Yambou River.

3.2 In the conduct of this work, the Consultant(s) shall collaborate with the government agencies

responsible for project development and implementation. Participatory methodologies should be utilised

in data gathering and action planning with all stakeholders. The Consultant(s) shall be solely responsible

for the analysis and interpretation of all data received and collected, the timely completion of the designs

and reports and the effectiveness of contractor supervision.

3.3 The Consultant(s) shall be responsible for collecting, reviewing and analysing all relevant data

available, including, inter alia, design and maintenance data for the existing infrastructure; previous

studies; meteorological, hydrological and hydraulic information; potential climate change impacts;

topographical data; existing and proposed land use; and any other information relevant for the

assignment.

3.4 The Consultant(s) will be required to verify that the design undertaken by MTW has been

undertaken in accordance with the highest practicable standards, and to the extent required, has been

informed by sufficiently extensive field surveys and investigations, including:

(a) site investigation and geotechnical surveys;

(b) road and bridge condition inspection surveys;

APPENDIX 2.11

Page 3

(c) topographical surveys;

(d) location of utilities; and

(e) hydraulic surveys.

3.5 The Consultant(s) shall ensure that with regard to bridges to be rehabilitated or constructed,

evaluation and design of the bridge works has been undertaken in accordance with guidelines published

by the American Association of State Highway and Transportation Officials (AASHTO) or similar

authoritative international guidelines acceptable to GOSVG and CDB;

3.6 With regard to new bridge and culvert structures, the consultant will ensure that alternative design

options have been developed and considered utilising approved national standards, relevant AASHTO

specifications and guidelines or other authoritative, international design standards/references acceptable

to GOSVG and CDB. The alternatives will assume a minimum 75-year structural design life for new

structures, and will adhere to guidance by AASHTO, as follows:

(i) backwater will not significantly increase flood damage to property upstream of the

crossing;

(ii) velocities through the structure(s) will not damage either the road facility or increase

damages to adjacent property;

(iii) maintain the existing flow distribution to the extent practicable;

(iv) pier spacing and orientation, and abutment designed to minimize flow disruption and

potential scour;

(v) foundation design and/or scour countermeasures to avoid failure by scour;

(vi) under clearance at structure(s) designed to pass anticipated debris;

(vii) minimal disruption of ecosystems and values unique to the floodplain and stream;

(viii) provide a level of traffic service compatible with that commonly expected for the class of

highway and compatible with projected traffic volumes; and

(ix) provide appropriate safety features on the bridges and their approaches.

3.7 The Consultant(s) will also be required to:

(a) prepare a draft Environmental Management and Monitoring Plan;

(b) assist GOSVG to prepare bills of quantities and detailed cost estimates for the proposed

works, based on the designs and specifications above. Current costs for similar works in St. Vincent and the Grenadines will be used as a basis for all unit rates and detailed costings;

APPENDIX 2.11

Page 4

(c) assist GOSVG to prepare standard bidding documents for the contract to allow

solicitation of bids from contractors in accordance with CDB’s Guidelines for

Procurement. In this regard, the Consultant(s) are referred to CDB’s Standard Bidding

Documents for Procurement of Works.

(d) assist MTW in the evaluation of tenders, including the preparation of tender reports;

(e) assist MTW in negotiation of contracts for the construction works;

(f) conduct technical inspection and supervision of construction works for compliance with

the contract documents;

(g) consult and advise MTW on matters arising during implementation of infrastructure

works;

(h) provide environmental monitoring during construction;

(i) certify work done for payment;

(j) prepare monthly reports on the progress of the works, indicating any engineering

difficulties affecting their efficient and timely execution, commencing one month after

the start date as defined in the construction contract;

(k) revise designs to suit unforeseen conditions which may arise during construction;

(l) issue certificates of completion to the contractor upon completion of the construction

contract;

(m) design, and submit to MTW, a Maintenance Manual for the Project infrastructure within

one month of the date of issue of a certificate of practical completion, including activities,

budgets and other resources required for implementation of a maintenance plan; and

(n) prepare a Completion Report on construction of the Project, and as-built drawings, within

three months after the date of issue of a certificate of practical completion of the Project.

4. IMPLEMENTATION ARRANGEMENTS

4.1 MTW will appoint a Project Coordinator (PC). The PC will facilitate the work of the

Consultant(s) and make available all relevant studies, reports and data, relevant to completion of the

exercise and will act as liaison between the Consultant(s) and GOSVG officials and stakeholders.

5. QUALIFICATIONS AND EXPERIENCE

5.1 The consulting team should consist of persons having appropriate professional and academic

qualifications and a minimum of 8 years’ relevant experience in the areas of civil engineering, road and

bridge design, structural engineering, drainage and/or hydraulic engineering, sea defences, environmental

engineering, disaster risk management, financial analysis and construction supervision. Specific

experience in community development in the Caribbean will be an asset.

APPENDIX 2.11

Page 5

6. COMMENTS BY THE CONSULTANTS

6.1 The Consultant(s) are requested to make comments on, and suggestions for, improvements to

these Terms of Reference. The financial implications, if any, of these recommendations should be

indicated separately in the Financial Proposal.

7. DURATION OF THE CONSULTING ASSIGNMENT

7.1 The assignment is expected to be conducted over a period of approximately three (3) years.

8. REPORTING REQUIREMENTS

8.1 The Consultant(s) will present six (4) copies of each report, three (4) copies to MTW and one (1)

copy to CDB. The reports shall also be submitted in “pdf” format as complete documents, as well as in

Microsoft Word and Excel and/or other formats used in their creation. Copies of all data used in the

preparation of the reports shall also be submitted to CDB. These reports are as follows:

(a) Inception Report: - The Inception Report will be presented within 14 days after the

signing of the contract, and it will include:

(i) Initial Findings.

(ii) Consultants’ detailed work schedule and methodology, including the schedule

and scope of all surveys, investigations, and tests, etc. to be conducted.

(iii) A programme for the use of resources including personnel, equipment, and

materials, etc.

(iv) Proposed outlines for the future reports.

(v) Design and review criteria to be employed, including identification of all

technical standards and procedures to be used.

(b) Design Review Report - The report will, inter alia, present the results of the design

review, including any proposed revision to existing designs; present the alternatives

considered for the project sites; and recommend the preferred options. Survey results,

together with all design assumptions, calculations, technical justifications and estimated

costs are to be presented for approval by GOSVG and CDB no later than six (6) weeks

after the signing of the contract.

(c) Monthly Reports: - The Consultant(s) will, no later than the specified date of each month,

prepare a progress report for each works contract summarising the work accomplished for

the preceding month. The report will outline any problems encountered (administrative,

technical or financial) and give recommendations on how these problems may be

overcome. The reports will detail progress of on-going works, include analysis and

summaries of all test results, and shall record the status of payment of all contractors

monthly certificates, of all claims for cost or time extensions, and of actions required of

MTW, other GOSVG agencies, or other stakeholders to permit unconstrained works

implementation.

APPENDIX 2.11

Page 6

(d) Contract Completion Reports: - The Consultant(s) will prepare a comprehensive

Contract Completion Report for each of the construction contracts, which reach

substantial completion during the period of the services. These reports, which

must be submitted immediately after the Taking Over of each contract, shall

summarise the method of construction, the construction supervision performed,

actual implementation progress and costs, compared to planned progress and

costs, quality assurance and quality control results, technical issues addressed,

and recommendations for future projects of similar nature to be undertaken by the

Employer.

(e) Project Completion Report: - The Consultant(s) will prepare a single Project

Completion Report to consolidate information from the Contract Completion

Reports.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.12

DRAFT TERMS OF REFERENCE

CONSULTING ENGINEERING SERVICES FOR DESIGN REVIEW AND CONSTRUCTION

SUPERVISION – INFRASTRUCTURE REHABILITATION AND UPGRADE

1. BACKGROUND

1.1 The Government of St. Vincent and the Grenadines (GOSVG) has approached the Caribbean

Development Bank (CDB) for rehabilitation and reconstruction of infrastructure damaged as a

consequence of the December 24 to 25, 2013 trough event.

1.2 Over a 24-hour period between December 24 to 25, 2013, an unseasonal low-level trough system

moving westwards towards the Windward Islands chain, interacted with a mid to upper-level trough

system moving in a south to north direction. Heavy precipitation, high winds and thunderstorm activity

was generated along the eastern boundary of the mid to upper-level trough as a result of this interaction.

Peak rainfall intensity occurred over the three-hour period between 9:00 p.m. and 12:00 a.m. on the

evening of December 24, 2013. Observed rainfall accumulations ranged between 163 millimetres (mm)

to 312 mm at Belle Isle and Rabacca Stations in St. Vincent. Rainfall intensities were highest in the

northeastern quadrant of St. Vincent with rainfall gauges in this area recording a maximum intensity of

278 mm per 3-hour period.

1.3 The passage of the trough and accompanying torrential rainfall resulted in significant river

flooding and landslide damage to mainland St. Vincent. Nine fatalities and 34 persons with injuries were

recorded. Damage was sustained on both windward and leeward sides of the island. As a result of the

extreme rainfall, flash flooding, slope failures and debris flows triggered by the December 2013 Trough

Event, St. Vincent experienced extensive damage to roads, bridges, river defences, drainage, water intake

and distribution infrastructure, agriculture, settlements and residential housing. During the storm, a total

of 21% of bridges on the island were affected, with 24 bridges (13% of all bridges) damaged and 14

bridges being completely destroyed. Estimated damage to bridges and roadways is approximately

USD7.9 mn.

2. OBJECTIVE

2.1 GOSVG, in an effort to provide the necessary infrastructural support for the economic and social

development of the project areas, is desirous of engaging qualified and experienced Consultant(s) to be

responsible for the design and supervision of the execution of works financed by CDB, inclusive of the

following:

(a) River Defence works at the selected sections of the Caratel River and the Yarabaqua

River along the North Windward;

(b) rehabilitation and upgrade of feeder roads in the North Central, and North Windward

districts and

(c) Embankment and slope rehabilitation and upgrade at Magum, North Windward.

3. SCOPE OF WORK

3.1 In the conduct of this work, the Consultant(s) shall collaborate with the government agencies

responsible for project development and implementation. Participatory methodologies should be utilised

in data gathering and action planning with all stakeholders. The Consultants shall be solely responsible

APPENDIX 2.12

Page 2

for the analysis and interpretation of all data received and collected, the timely completion of the designs

and reports and the effectiveness of contractor supervision.

3.2 The Consultant(s) will be required to:

(a) review and collect relevant data and conduct appropriate interviews in order to identify

all the factors to be considered in the design of the various project components;

(b) undertake an assessment of the project components to be constructed or rehabilitated;

(c) prepare detailed designs, cost estimates and tender documents for all infrastructure

works;

(d) develop a phased programme of works;

(e) prepare a draft Environmental Management and Monitoring Plan;

(f) assist the Ministry of Transport and Works (MTW) in the evaluation of tenders, including

the preparation of tender reports;

(g) assist MTW in negotiation of contracts for the construction works;

(h) conduct technical inspection and supervision of construction works for compliance with

the contract documents;

(i) consult and advise MTW on matters arising during implementation of infrastructure

works;

(j) environmental monitoring during construction;

(k) certify work done for payment;

(l) prepare monthly reports on the progress of the works, indicating any engineering

difficulties affecting their efficient and timely execution, commencing one month after

the start date as defined in the construction contract;

(m) revise designs to suit unforeseen conditions which may arise during construction;

(n) issue certificates of completion to the contractor upon completion of the construction

contract;

(o) design, and submit to MTW, a Maintenance Manual for the Project infrastructure within

one month of the date of issue of a certificate of practical completion, including activities,

budgets and other resources required for implementation of a maintenance plan; and

(p) prepare a Completion Report on construction of the Project, and as-built drawings, within

three months after the date of issue of a certificate of practical completion of the Project.

APPENDIX 2.12

Page 3

4. IMPLEMENTATION ARRANGEMENTS

4.1 MTW will appoint a Project Coordinator (PC). The PC will facilitate the work of the

Consultant(s) and make available all relevant studies, reports and data, relevant to completion of the

exercise and will act as liaison between the consultants and GOSVG officials and stakeholders.

5. QUALIFICATIONS AND EXPERIENCE

5.1 The consulting team should consist of persons having appropriate professional and academic

qualifications and a minimum of 8 years’ relevant experience in the areas of civil engineering, road and

bridge design, structural engineering, drainage and/or hydraulic engineering, sea defences, environmental

engineering, disaster risk management, financial analysis and construction supervision. Specific

experience in community development in the Caribbean will be an asset.

6 COMMENTS BY THE CONSULTANTS

6.1 The Consultant(s) are requested to make comments on, and suggestions for, improvements to

these Terms of Reference. The financial implications, if any, of these recommendations should be

indicated separately in the Financial Proposal.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.13

PROCUREMENT PLAN

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.14

REPORTING REQUIREMENTS

Reports Frequency Deadline for Submission

Implementation: 1. Progress Report Spreadsheet on

project implementation prepared by

PE submitted by PC.

Fortnightly

Within two days after the end of each

fortnight until project implementation is

completed, commencing one fortnight

after the start date as defined by MTW.

2. Progress Reports on project

implementation prepared by

Engineering Consultants

Monthly Within one month after the end of each

calendar month until project

implementation is completed,

commencing one month after the start

date as defined by MTW.

3. Report on Baselines for the

Monitoring Indicators prepared by

PC.

- Within three months of engagement of

PC.

4. Report on the shortlists for the TA

consultancies to be prepared by PC. - Within two weeks of the submission

deadline for the proposals.

5. Evaluation Report of the TA

Proposals by PC.

- Within three weeks of the closing date

for the proposals.

6. Reports on the Investment Costs of

the Project prepared by PC. (Sample

Guidelines presented in attached

Annex)

Quarterly Two weeks after the end of each quarter

until project implementation is

completed, commencing with the

quarter following the appointment of

PC.

7. Report on the progress of the TA

consultancies prepared by the PC.

- As specified in each TOR.

8. Project Implementation Completion

Report prepared by PC.

- Within three months of completion of

practical completion of the Project.

Operation:

9. Reports on Monitoring Indicators

Annually

By December 31, commencing in 2018.

10. Three-year maintenance plan for the

project infrastructure, including

reports of condition assessments of

project infrastructure.

Annually By December 31, commencing in 2018.

AN

NE

X T

O A

PP

EN

DIX

2.1

4

QUARTERLY REPORT ON INVESTMENT COST OF PROJECT

($'000)

Elements of Project

Expenditure

for this

Quarter

Cumulative

Expenditure

to date

Projected Expenditure

for the Quarter Estimated

Expenditure

to Complete

Project

Latest

Estimate of

Expenditure

Project

Estimate

as per

Appraisal

Report

Variance

Favourable/

(Adverse)

Comments/

Reasons for Adverse

Variance and

Financing Proposal to

Meet Cost Overrun Ending Ending Ending

(1) (2) (3) (4)1 (4)2 (4)3 (5) (6) (7) (8) (9)

1. Infrastructure 17,603

2. Services 7,098

Base Cost 24,701

3. Contingencies 4,664

4. Finance Charges1,279

Total Project Cost 30,644

USD Equivalent 11,350

ANNEX TO APPENDIX 2.14

Page 2

GUIDELINES FOR COMPLETION OF

REPORT ON PROGRESS OF INVESTMENT COST

1. Elements of Project - The elements of the Project as outlined in the Appraisal Report must be

recorded in this column. If it becomes necessary to further sub-divide the main elements of

the project, then the sub-elements should be grouped to facilitate the determination of the

expenditure related to the main elements identified in the Appraisal Report.

2. Expenditure for this Quarter - The expenditure incurred in the quarter to which the report

relates in respect of each element of the project must be recorded in this column.

3. Cumulative Expenditure to Date - The expenditure incurred in respect of each element of the

project from the commencement of the project to the end of the quarter to which the report

relates must be recorded in this column.

4. Projected Expenditure for Quarter - An estimate of the expenditure to be incurred in each of

the next three quarters must be recorded in the columns 41, 42, and 43.

5. Estimate of Expenditure to complete Project - This column should be completed only in

respect of those elements of the project, construction/installation of which stretches beyond

three quarters from the end of the quarter to which the report relates. Where a project extends

over more than one year - four quarters - an estimate of the expenditure to be incurred in the

period subsequent to the year must be recorded in this column.

6. Latest Estimate of Expenditure - The amounts to be recorded in this column should be

derived by adding columns 3, 4123, and 5. The amounts recorded in this column should be the

best estimate of expenditure to be incurred in respect of each element of the project. These

amounts may be less or greater than the appraised expenditure.

7. Project Estimates as per Appraisal Report - The estimate of expenditure to be incurred in

respect of each element of the project, as outlined in the Appraisal Report, must be recorded

in this column.

8. Variance - The difference between columns 6 and 7 must be recorded in this column. Where

the amount in column 6 is less than that in column 7, a favourable variance results. An

adverse variance results where the amount in column 6 is greater than that in column 7.

9. Comments - An explanation should be given for each variance which is more than 10% of the

project estimates as per Appraisal Report.

APPENDIX 4.1

THE EXECUTING AGENCY FOR THE GRANT

1. LEGAL STATUS

1.1 CWSA was established by Section 3 of the Central Water and Sewerage Authority Act, 1991

(No. 17 of 1991) of SVG (the Act) to manage, construct, operate and maintain works in relation to the

supply of water and the disposal of sewage in SVG. CWSA is a body corporate with perpetual succession

and a common seal, with power to sue and to be sued in its corporate name, and to exercise such powers

and perform such duties as are conferred and imposed on it by the Act.

2. POWERS

2.1 The powers conferred by the Act with respect to the management of water and sewage include inter

alia the operation of facilities and equipment for the use, treatment, processing and disposal of waste; the

investigation of water resources and the consumption and demand of water. CWSA is also expressly

empowered, with the approval in writing of the Cabinet, to purchase by private treaty or compulsorily

acquire land in accordance with the Land Acquisition Act for any purpose connected with the discharge of

its functions.

3. MANAGEMENT

3.1 The powers of CWSA are exercised through the Board of Directors which is appointed by the

Minister and consists of a Chairman and Deputy Chairman, a representative from each of the following:

Ministry of Health; Ministry of Agriculture; a resident of Kingstown; a resident of a district other than

Kingstown; and a representative of the business community or hotel industry.

4. GOVERNMENT CONTROL

4.1 The Minister exercises control over the appointment of the members of the Board of Directors and

the remuneration payable to the members of the staff of CWSA. The Minister may, also, after consultation

with the Chairman of the Board of Directors, gives directions of a general or specific nature relating to the

policy to be followed by the Board of Directors in the performance of the functions of CWSA, and the

Board of Directors is required to give effect to such directions.

FIGURE 1

PROJECT LOCATION MAP

11

6

5

13

12

9

10

8

1

4

2, 3, 7

FIGURE 1

Page 2

Locations: Work Package 1 Work Package 2 Work Package 3

1. Union River Bridge – Windward Highway 2. Yambou River Bridge – Vigie Highway 3. Teviot and Zenga Bridges – Vigie Highway 4. Red Dog Bridge – Marriaqua District 5. Tourama – North Windward Highway 6. Magum – North Windward Highway 7. Glenside (Along the Yambou River) – Vigie Highway

8. River Defence: Yarabaqua River - Windward Highway 9. River Defence: Caratal River – North Windward district 10. Feeder Road: Gracefield Mountain Road – North Central District 11. Feeder Road: Roway Mountain Road – North Windward District 12. Feeder Road: Bower Mountain Road – North Windward District 13. Feeder Road: Ferguson Mountain Road – North Central District

14. Orange Hill – North Windward Highway

TA – Studies 1. LaCrox to Peruvian Vale (6km) – Vigie Highway

TA - Studies 2. Landslide Risk Assessment – Study Areas:[(i) Spring (ii) Orange Hill; (iii) Sandy Bay to Aqueduct; (iv) Roway to Point; (v) Owia; (vi) Bloody Bridge: (vii) Windblow; and (viii) Soldier Hill;]