All main Bulgarian railway sections are included in the comprehensive network
Intermodal terminals – Sofia, Plovdiv, Varna, Burgas, Ruse, Vidin, Lom, Dragoman, Svilengrad and Gorna Oryahovitsa
TEN-T Comprehensive Network
Ongoing projects2007-2013
• Plovdiv-Svilengrad Railway Electriffication & Upgrading of Corridors IV and IX
• Phase 1 – Kruomovo - Parvomai: Contractor Terna – Greece
– Contract value: 99 792 441 € – financing under ISPA programme
• Phase 2 – Parvomai – Dimitrovgrad: Contractor Astaldi – Italy
– Contract value : 68 000 000 € – financing under ISPA programme
• Phase Systems – Plovdiv-Svilengrad-turkish border: Contractor Thales-Alcatel-Lucent – Austria
– Contract value : 35 557 047, 06 € – financing under ISPA programme
• Phase 3 – Svilengrad – turkish border: Contractor OHL ŽS – Czech Republic
– Contract value: 69 999 666 BGN without VAT – financing under Operational Programme on Transport
• Phase 4 – Dimitrovgrad - Svilengrad: completed tender procedure, expected contract signing on 3 implementation positions.
Ongoing projects 2007-2013
• Rehabilitation of Railway Infrastructure along Sections of the Plovdiv-Burgas Railway Line
• Total investment value: 316 968 850,42 BGN without VAT
• Main contractor: G.S.F. S.p.A – SK 13 – Trace Railinfra
• Modernization of the railway section Septemvri-Plovdiv
• LOT 1 – Septemvri – Pazardzhik: Contractor Swietelsky – RVP Köhne
• LOT 2 – Pazardzhik – Stamboliyski: Contractor IGA Rail Infra
• LOT 3 – Stamboliyski – Plovdiv: Contractor Porr Bau GmbH
• Total contracts value: 157 860 835,75 BGN without VAT
Ongoing projects 2007-2013
• Construction of an Intermodal terminal in South-Central planning region of Bulgaria
• Forthcoming activities
– Preparation of Detailed Structural Plan and Plot Plan for expropriation procedures
– Technical design
– Construction
• Indicative budget: 16 166 249 BGN without VAT
• Design and implementation of geographical information system (GIS) for the NRIC needs
• Total investment value: 12 000 000 BGN
• Main Contractor: Consortium „EuroGeoRail“
• Project completion date: April 2011
2014-20202014-2020 priority implementation projects priority implementation projects
The projects are grouped in to A, B and V direction for effective management and operability achievement
National Railway Infrastructure Company
Group A projects – To the direction Dragoman-Sofia-Plovdiv-Svilengrad and Plovdiv-Burgas part of the transeuropean transport corridors IV, IIIV and X;
1. Modernization of Sofia – Dragoman Railway Line
• Preparation of Environmental impact assessment (EIA) report and technical design: 2007-2013
• Construction: 2014 – 2020
• Indicative budget: 132 260 000 €
2. Modernization of Sofia – Plovdiv Railway Line
• Technical design for Sofia – Septemvri railway section : 2007-2013
• Preparation of Environmental impact assessment (EIA) report of Elin-Pelin – Septemvri railway section: 2007-2013
• Construction of Sofia – Septemvri railway section : 2014 – 2020
• Indicative budget: 1 081 000 000 €
National Railway Infrastructure Company
Group A projects – To the direction Dragoman-Sofia-Plovdiv-Svilengrad and Plovdiv-Burgas part of the transeuropean transport corridors IV, IIIV and X;
3. Projects of Plovdiv – Burgas section completion – Corridor VIII• Indicative budget: 82 700 000 €• Including projects:
• Construction of optic cable along Plovdiv-Burgas railway line, indicative budget:15 512 000 €. Construction: 2014-2020;
• Introduction of interlockings in Karnobat-Burgas section, indicative budget: 5 466 000 €. Construction: 2014-2020;
• Development of Burgas Railway Junction, indicative budget: 20 000 000 €. Design and construction: 2014-2020;
• Rehabilitation of Plovdiv-Orizovo railway section, indicative budget: 30 677 000 €. Construction: 2014-2020;
• Modernization of sections along Plovdiv-Burgas railway line (Orizovo – Mihaylovo, Yambol – Zimnitsa, etc.), indicative budget: 10 000 000 €, Technical design: 2007-2013. Construction: 2014-2020;
National Railway Infrastructure Company
Group B projects – To the direction Vidin-Sofia-Radomir-Kulata part of the transeuropean transport corridor IV;
1. Modernization of Vidin-Sofia Railway Line
• Preparation of Environmental impact assessment (EIA) report and technical design: 2007-2013
• Construction of separate sections along the route will start in 2014-2020 programming period:
• Modernization of Vidin – Medkovets railway section 62,5 км;
• Modernization of Medkovets – Ruska Byala/Mezdra railway section 84,3 км;
• Modernization of Ruska Byala/Mezdra – Stolnik railway section 76,3 км;
2. Modernization of Sofia –Pernik – Radomir Railway Line
• Technical design: 2007-2013
• Construction: 2014 – 2020
• Indicative budget: 359 576 884 €
National Railway Infrastructure Company
Group V projects – Passangers and freights intermodality projects
1. Development of Sofia Railway Junction
• Technical design: 2007-2013
• Design and construction: 2014 – 2020
• Indicative budget: 309 847 000 €
2. Construction of an Intermodal terminal in Sofia
• Indicative budget: 31 345 000 €
• IProject preparation will be implemented in 2007-2013
3. Construction of an Intermodal terminal in Central-Nord planning region of Bulgaria-Ruse
• Fisibility study and preliminary design: 2007-2013
• Design and construction: 2014 – 2020