Natick Public SchoolsTechnology UpdateSeptember 11, 2006

Dennis Roche, CISA

Director of Technology

Page 2: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Technology Update 2006 -2007

• Technology Vision

• Summer 2006 Update

• Updated Technology Plan

• Challenges & Goals

Page 3: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Technology Vision

• Implement best of breed solutions from K-12, higher education and the business world.

• Create an open environment that embraces multiple platforms and multiple clients.

• Allow use of personal computing devices and in safe and secure fashion.

Page 4: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Technology Department Mission

• Establish and maintain a reliable and secure technology infrastructure.

• Provide technical support and on-going training to all faculty and staff.

• Manage third party technology vendors and service providers.

• Collaborate with faculty, staff and administrators on new technologies.

Page 5: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Summer 2006 Update

• New Technology Staff– Steve McGrath, Help Desk Manager– LaKisha Wilson, Technician– Chris Kiepert, Web & Data Base Administrator

• Open Positions– Technical Support Specialist– Network Administrator

Page 6: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

New On-Line Resources

QuickTime™ and aTIFF (Uncompressed) decompressor

are needed to see this picture.

QuickTime™ and aTIFF (Uncompressed) decompressor

are needed to see this picture.

QuickTime™ and aTIFF (Uncompressed) decompressor

are needed to see this picture.

Page 7: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology
Page 8: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology
Page 9: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

First Class

• Rebuilt a server with internal hardware redundancy (Hardware level RAID) to maximize uptime.

• Upgraded First Class Server Software to current release.

• Ran Repair Utilities on First Class Data Base.• Conferences within First Class re-organized.• New SPAM filter implemented.

Page 10: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Backend Server Work & Computer Room

• All servers relocated main computer room at Natick High School.

• All MAC servers upgraded to newest version of Operating System.

• New storage, backup and fiber switches purchased and installed. New faculty currently on new storage solution.

• New dedicated electrical service installed and protected by electrical generator.

Page 11: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Elementary Software

• Re-installed 500 elementary computers with a standard suite of software.

• MicroSoft Office now available to all faculty.

• Students have access to Appleworks, Inspiration, Kid Pix, Neighborhood Map Machines, Sammy’s Science House and the Internet.

Page 12: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Business & Science Departments

• Business Lab A107 cabled and added to network.

• Cabling for managed wired access points completed in the S wing. Access points to be configured and piloted later in the school year.

• Licenses for Microsoft Windows XP and Office 2003 purchased for student use.

Page 13: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Nurses Upgrade

• Phased out Citrix Server based solution which was only required to provide a Windows application to MAC clients.

• Replaced all Nurses machines with PCs which greatly decreased login time and minimize printing issues.

• Worked with Town IT Department on upgrading SNAP Data Base and providing access.

Page 14: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Technology PlanYear 1 - FY06

Project Original

Estimate Actual Status

Rebuild Network Servers & Domain75,000 105,444 In Process

MS Office Tools 33,000 0 Complete

NHS Business & Science Labs 28,000 20,189 Complete

Wiring Closets 46,000 0 Deferred

Email System SPAM Filter 0 4,721 Complete

Anti-Spyware & Policy based Content Filter 0 16,208 Evaluating

Funding Summary

Beginning Balance 10,800

Town Meeting Funding 182,000

Total 192,800 146,562

Balance 46,238

Page 15: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Steps to Rebuild Network Servers & Domain

1. Production Environment

2. New Storage & Backup Infrastructure

3. Domain Controller Replacement

4. Windows & MAC Integration

Page 16: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Production EnvironmentStep 1

• By end of 2005 - 2006 School Year, 36 MAC OSX and 11 Windows Servers centralized at Natick High School.

• Rebuilt and repurposed 6 existing servers to retired 6 of the oldest servers.

• Additional memory and internal hard drives purchased to sustain existing environment until data migration conducted.

• Rebuilt 2 Servers for DNS.

• All MAC OSX servers upgraded to latest version of MAC OSX (10.4.7) to ease migration process and secure backup of directory information.

• Production environment currently consists of 18 MAC OSX and 7 Windows Servers.

Page 17: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

New Storage and Backup Infrastructure

Step 2• Purchased and installed new storage, backup library and

fiber optic switches.

• (9) existing servers rebuilt & repurposed to serve as file servers to storage arrays. Additional servers to be rebuilt as we migrate. Each server can manage 100-150 active connections.

• Purchased and installed fiber optic cards in all servers for optimum access to storage arrays.

• New faculty added to new storage system this school year.

Page 18: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Domain Controller ReplacementStep 3

• Purchased (2) additional MAC servers to continue testing without impacting production.

• Conducted tests of rebuilding new domain controller from scratch.

• Purchased block of phone and on-site support consulting time with Apple to verify approach and minimize disruption.

Page 19: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Windows & MAC IntegrationStep 4

• An Active Directory environment is our long term goal to achieve seamless integration of MAC and Windows clients.

• A second migration will be required to achieve this goal after completion of the current migration.

Page 20: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Technology PlanYear 2 - FY07

ProjectOriginal

Estimate

Revised

Estimate

Rebuild Network Servers & Domain - Step 30 50,000

Wiring Closets 50,000 50,000

Website Development 50,000 25,000

Student Information System 150,000 200,000

Equipment Replacement 100,000 50,000

Automated Communication System 20,200 25,000

Total 370,200 400,000

Page 21: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Technology PlanYear 3 - FY08

ProjectOriginal

Estimate

Revised

Estimate

Rebuild Network Servers & Domain - Step 40 50,000

Wiring Closets 0 50,000

Classroom Technologies 100,000 100,000

Equipment Replacement 200,000 200,000

Total 300,000 400,000

Page 22: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Challenges for 2006 - 2007

• Nurses Upgrade & Science Department Wireless Pilot delayed due to Network Administrator departure.

• Printing at Elementary Schools limited.• Can’t add new Lilja faculty to network due MAC

Manager Data Base Issue. • Email problem with SPAM filter and Comcast

blacklisting us.• Login issues at Wilson Middle School - Discovered loose

connections on a stack of switches in a wiring closet.

Page 23: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Current High Priority Issues

• Fifth and Sixth graders not able to access home directories.

• Pending Patron Upload to Library Circulation Systems delaying book circulation.

• Java Programming class - students unable to run compiled applications.

Page 24: Natick Public Schools Technology Update September 11, 2006 Dennis Roche, CISA Director of Technology

Summary of Goals for 2006 - 2007

• Complete data migration to new storage device, rebuild servers and domain controller.

• Separate Website from First Class and redesign district level and school level sites.

• Upgrade wiring closets based on priority and need.• Complete due diligence on SIS system and

implement best solution. • Implement emergency notification system.• Pilot interactive white board solution.