NASA Ares I-X Flight Test plans

Embed Size (px)

Citation preview

  • 8/14/2019 NASA Ares I-X Flight Test plans

    1/31

  • 8/14/2019 NASA Ares I-X Flight Test plans

    2/31

  • 8/14/2019 NASA Ares I-X Flight Test plans

    3/31

    IAC-07-D2.6.04 - Ares I-X Flight TestThe Future Begins Here

    Figure 2. Ares I-X (right) follows NASA's tradition of incremental development through flight testing, whichhas included the Mercury, Gemini, and Saturn programs (left).

    Mission Overview

    The Ares I-X Flight Test Vehicle (FTV) willincorporate a mix of flight and mockup hardware(Figure 3), reflecting a mass and weight similarto the operational Ares I. It will be powered by afour-segment solid rocket motor currently in theSpace Shuttle inventory, and will be modified toinclude a fifth spacer segment that makes thebooster approximately the same size and weightas the five-segment SRB. The vehicle alsofeatures a new recovery system, including newmain parachutes. The new main chutes are 150

    feet (47.7 m) across, compared to 136 feet (41.4m) across for the Shuttle. Ares I-X will be thefirst flight test of new main parachutes for Ares I.

    The Ares I-X flight profile will closelyapproximate the flight conditions that Ares I willexperience through Mach 4.5, at an altitude ofabout 130,000 feet (39,600 m) and through amaximum dynamic pressure (Max Q) ofapproximately 800 pounds per square foot (38.3kPa) (Figure 4). By basing refinements of theAres I vehicle design on Ares I-X information,NASA moves one step closer to full-up test asyou fly scenarios. Each future flight will bestaged to affect future milestone reviews. Ares I-X supports the Ares I Critical Design Review(CDR), scheduled for 2010.

  • 8/14/2019 NASA Ares I-X Flight Test plans

    4/31

    IAC-07-D2.6.04 - Ares I-X Flight TestThe Future Begins Here

    Orion CrewModule / Launch

    Abort System

    Avionics (internalthroughout vehicle)

    Upper StageSimulator

    Figure 3. The Ares I-X provides an early opportunity to test the flight configuration of the Ares I crewlaunch vehicle.

    Four-segmentMotor

    FirstStage

    Roll ControlSystem

    First StageAvionics Module

    (internal)

    SeparationPlane

    Simulated FifthSegment

  • 8/14/2019 NASA Ares I-X Flight Test plans

    5/31

    IAC-07-D2.6.04 - Ares I-X Flight TestThe Future Begins Here

    The Ares I-X mission will be NASAs firstflight test of a new human exploration vehiclesince 1981. As such, it returns the agency to itshistory as a pioneering organization, taking ontechnical risks to develop new space hardware.The five primary test objectives for the Ares I-Xflight test include:

    Demonstrating the ascent flight controlsystem performance with dynamicallysimilar hardware.

    Demonstrating separation between thefirst and upper stage.

    Characterizing and mitigating the rolltorque due to first stage (FS) motorperformance and aerodynamic forces.

    Testing the first stage parachute recoverysystem and separation/entry dynamics.

    Validating assembly and processing flow,

    as well as launch and recovery operations.

    These objectives are all attainable using acombination of existing flight hardware andsimulator hardware equipped withenvironmental, acceleration, and other sensors.

    Ares I-X provides the first opportunity to testnew assembly, integration, and test (AIT)functions at Kennedy Space Center (KSC).

    When vehicle elements begin arriving at KSC byOctober 2008, they will be moved to theAssembly and Refurbishment Facility (ARF),where developmental flight instrumentation (DFI)will be integrated and the upper stage simulator(USS) segments will be stacked in smallersuper stacks to support final assembly of thevehicle in the Vehicle Assembly Building (VAB).

    The vehicle will be launched from KSCLaunch Complex (LC) 39B, which will be used

    as a backup launch-on-demand facility for theShuttle during the servicing mission (STS-125)in October 2008. Once STS-125 is completed,LC 39B will be transferred to the Ares Projectsfor use on the flight test. Because of its Shuttle-ready state, LC 39B will need to be modifiedslightly to support Ares I-X until a full tear-down

    Ground Operations personnel to access theinside of the vehicle prior to launch. The groundsupport systems also include an environmentalcontrol system (ECS) to keep the avionics andground staff cool prior to liftoff. The ECS willhave a T-0 disconnect connection between theground systems and the Flight Test Vehicle(FTV), which remains intact until the first stageignition command (T-0) is issued.

    Work continues on Ares I-X design andhardware fabrication. All of the individualelements are undergoing or have completed

    CDRs, which were followed by a two-partintegrated vehicle CDR in March and July 2008.

    Progress on Mission Hardware and Facilities

    The Ares I-X mission was authorized toproceed in spring 2006. Given its rapiddevelopment cycle, hardware design andmanufacturing have occurred nearly

    simultaneously to meet the launch date. Thus,while the CDR began in March 2008, much ofthe flight hardware was already well through thefabrication process. The CDR was completedsuccessfully July 24. The various hardwareelements are on schedule to begin deliveries toKSC by October 2008.

    First Stage

    As noted earlier, the first stage (Figure 5) isusing a four-segment solid rocket motor from theShuttle inventory. New forward structures arebeing manufactured by a contractor partner.These new structures will be heavier than theAres I hardware and will be made mostly ofsteel. The frustum and aeroshell on theoperational Ares I will not be reused and will bemade of carbon composites. The Ares I forward

    skirt and forward skirt extension will be made ofaluminum.

  • 8/14/2019 NASA Ares I-X Flight Test plans

    6/31

    IAC-07-D2.6.04 - Ares I-X Flight TestThe Future Begins Here

    FrustumThe frustum connects the firststage to the upper stage. Machining on thefrustum was completed in June 2008.

    Forward Skirt ExtensionThe forwardskirt extension, which houses the MainParachute Support System (MPSS), isscheduled to be delivered to the ARF in late July2008. The Ares I-X separation plane will bebetween the frustum and the forward skirtextension (Figure 6). A field test of theseparation system was conducted at ATKs

    Promontory site in July 2008. Work also beganon installing MPSS hardware in July.

    Forward SkirtThe forward skirt, whichhelps Ares I-X match the outer mold line of AresI, is due to be delivered to the ARF in late July2008.

    Figure 6. The test of the forward skirtextensions separation system verified the

    effectiveness of the linear shaped charge and itsshock effects.5th Segment Simulator (5SS)The

    structure of the fifth segment simulator (alsocalled 5SS or the XL segment) is 10 percent

    complete. The 5SS (Figure 7) houses the FirstStage Avionics Module (FSAM), the FlightTermination System (FTS), and othercomponents. The first of the 5SS componentsarrives at the ARF in July 2008, with additionalsections delivered in August 2008.

    First StageAvionics Module(FSAM) S & A and

    CRD Panel

    Aft

    Segment

    CenterSegment

    Forward

    Segment

    AccessDoor

    Systems Tunnel

    Connector Panels

    Flight Safety

    System (FSS)Antenna

    Clevis-TangInterface

    BoltedInterfaceLadder /

    Cable Tray

    S-BandAntenna

    C-Band

    Antenna

    Hybrid andDirectionalCoupler Panel

    AccessDoor

    ECS

    Ports

    Batteries and

    C-BandController

    HeaterCableModule

    C-Band

    Transponder

  • 8/14/2019 NASA Ares I-X Flight Test plans

    7/31

    IAC-07-D2.6.04 - Ares I-X Flight TestThe Future Begins Here

    installed. The aft skirt for Ares I-X, whenoperational, will include eight BDMs and fourBTMs. A recent lean event at KSC helpedincrease the schedule margin for the skirt,resulting in a delivery to the RPSF by as muchas one month earlier than originally scheduled.The aft skirt is currently scheduled to bedelivered to the RPSF in October 2008.

    Figure 8. The aft skirt, while Shuttle-legacyhardware, will have hardware added to meet the

    requirements of Ares I-X.

    Separation and DecelerationFivesuccessful drop tests of the parachute system(Figure 9) have been completed so far. Twoadditional tests are planned before April 2009.

    Ares I-X will be the first qualification flight test ofthe new 150-foot-diameter main parachutes.

    Figure 9. The main parachutes are in the process of fabrication and drop testing.

    Avionics

    Ares I-X will carry four types of avionicshardware:

    commands between the Atlas Vcomponents and the solid-propellant first

    erational Flight

    stage

    Developmental Flight Instrumentation(DFI) and Op

  • 8/14/2019 NASA Ares I-X Flight Test plans

    8/31

    IAC-07-D2.6.04 - Ares I-X Flight TestThe Future Begins Here

    launch date. Table 1 below lists the activitiesand delivery dates for the avionics.

    Table 1. Anticipated delivery dates for Ares I-X avionics

    Component(s)Current Status (As

    Appropriate)Anticipated

    Completion/DeliveryATVC CDR completed June 2007

    Fabrication under wayOctober 2008

    FSAM CDR completed April 2008 October 2008

    Flight Software CDR completed March 2008Test Readiness Review

    completed April 2008

    March 2009

    Ground Software (GroundControl, Command, andCommunications/GC3)

    Formal testing under way Delivery to KSC October 2008Installation in MLP by May 2009

    Systems Integration LaboratoryVehicle Flight Control TestingFlight Simulation Testing

    OngoingOngoing

    October 2008May 2009

    OFI / DFI Sensors andHarnesses

    Sensors acquired or on orderUndergoing Table Top Reviews

    as completed

    Cable Harnesses

    CM/LAS October 2008USS October 2008FS October 2008

    OFI HarnessesFS/USS October 2008

    Fault Tolerant Inertial NavigationUnit (FTINU)

    Qualification testing completeDelivered to United Launch

    Alliance in March 2008

    Delivery to KSC March 2009

    SDA Fabrication begun December2007

    August 2008

    Upper Stage Simulator

    The USS (Figure 10) is made up of cylindricalsegments that will be stacked and integrated atKSC for launch. The USS segments are beingfabricated by NASA personnel at GlennResearch Center (GRC) in Ohio. As notedearlier, GRC is completing the assembly of

    these segments, along with their internalstructures (Figure 11).

  • 8/14/2019 NASA Ares I-X Flight Test plans

    9/31

    IAC-07-D2.6.04 - Ares I-X Flight TestThe Future Begins Here

    Figure 11. This image shows the interior ofthe USS

    The USS is a mass simulator. It provides themajority of adjustable ballast for the vehiclesmass, center of gravity (CG), and moment ofinertia distribution. The 2-inch- (5-centimeter)thick ballast plates are approximately 7,000pounds (lbs.) (3,175 kilograms (kg)) each. The

    US-1 segment holds 16 plates 2 plates,equaling approximately 112,000 lbs. (50,802 kg)The US-7 segment holds 5 plates 2 plates,weighing approximately 35,000 lbs. (15,875 kg)The total adjustable ballast is around 147,000lbs. (66,678 kg). These ballast plates simulatethe mass of the liquid hydrogen and liquidoxygen that would normally be present in theupper stage propellant tanks in Ares I.

    The USS is designed with 11 segments: 5common segments (US-2, 3, 4, 5, 6), 2adjustable ballast segments (US-1 and 7), and 4complex segments (Interstage (IS)-1 and IS-2,Spacecraft Adapter (SA), and Service Module(SM)).

    Each segment is approximately 9.5 feet (2.9m) tall to accommodate manufacturing andtransportation constraints. Outer Mold Line(OML) protuberances are all bolted on and

    assembled on individual segments prior toshipping except the Ullage Motors (4x) and RollControl System (RoCS) Modules (2x) located onthe US-1 segment. These items will be shippedseparately. An internal access door on US-1 andplatforms and ladders provide access to theentire USS, the FS Frustum, and CM/LAS.

    USS has successfully completed threeCritical Design Reviews, which were ordered bysegment complexity, with the Charge 1segments being the least complex and Charge3 incorporating the Roll Control System and

    avionics. Charge 1 hardware has already beenfabricated. Charge 2 is due to be completed onschedule. Charge 3 hardware fabrication hasbeen started. Manufacturing processes andprocedures have been successfullydemonstrated. Most of the USS hardware is dueto be shipped to KSC by October 2008.

    Roll Control System

    The active roll control system (RoCS)provides rotational azimuth control forperforming a 90-degree roll maneuver to orientthe vehicles telemetry antennas after liftoff. Italso will mitigate against adverse roll torques(self- and aero-induced) during ascent. Thenumber of RoCS pulses will be measured inflight and will help inform the RoCS for the finalAres I design. The Roll Control System is anintegral, modular, bi-propellant propulsionsystem housed in the USS Interstage segment(Figure 12). The RoCS uses off-the-shelf andgovernment-furnished equipment (GFE)componentsincluding nitrogen tetroxide andmonomethyl hydrazine propellant tanks, heliumpressurization tanks, and engine nozzles. ThisGFE was harvested from Peacekeeper missiles,then re-integrated into a system for RoCS.

  • 8/14/2019 NASA Ares I-X Flight Test plans

    10/31

    IAC-07-D2.6.04 - Ares I-X Flight TestThe Future Begins Here

    Duty cycle testing for RoCS was conductedat the White Sands Test Facility in late 2007,and fuel tanking and detanking tests wereperformed at KSC in early 2008. This verificationtesting, performed at Hypergol MaintenanceFacility (HMF):

    Demonstrated loading pressurant andpropellant (using de-ionized water) intoPeacekeeper tanks/fill valve configuration

    Used HMF GSE planned for RoCS flightmodule loading

    Verified and validated procedures andhardware well in advance of actualpropellant loading in flight modules.

    The RoCS team is focused on completinghardware fabrication and integrating it into themodules, while working verification activities inparallel, leading to a Hardware AcceptanceReview early September 2008. The RoCS teamhas high confidence that it will meet its deliveryschedule for the 2009 launch.

    Crew Module / Launch Abort System Simulator

    Like the USS, the CM/LAS portion of Ares I-X will be simulator hardware (Figure 13). Theseforward sections differ slightly from the currentiteration of the Ares I design because Ares I-X

    was baselined during an earlier design analysiscycle (DAC). However, the CM/LAS will stillprovide critical information about aerodynamicand acoustic loads on the Orion crew

    exploration vehicle. A total of 362 DFI sensorswill be placed on and in the forward structures.The data from these sensors will be transmittedto the ground via telemetry. The sensors mightalso provide visibility into the thrust oscillationissue Ares I is studying. The CM/LAS CDR wascompleted in mid-March 2008. Hardwaredrawings have been completed, and thehardware itself is being fabricated. NASAsLangley Research Center (LaRC) is responsiblefor CM/LAS design and fabrication, installation

    and checkout of DFI, plus handling groundsupport equipment (GSE).

    Figure 13. The Ares I-X CM/LAS simulatorcompleted its CDR in February 2008.

    The CM/LAS structure consists of severalprimary components, including the Orion crewmodule (CM) simulator, the LAS nozzles, thenosecone, and a transition structure between

    the mast and the CM known colloquially as aparty hat (Figure 14).

  • 8/14/2019 NASA Ares I-X Flight Test plans

    11/31

    IAC-07-D2.6.04 - Ares I-X Flight TestThe Future Begins Here

    The GO and CM/LAS teams are workingtogether to ensure hardware integration andoperations in the Vehicle Assembly Building(VAB) once the CM/LAS arrives at KSC inNovember 2008. The LAS Tube segment(Figure 15) is currently being fabricated, as arethe attachments for the simulated motor nozzles.Upon completion of the tube, assembly ofCM/LAS party hat will commence.

    Figure 15. The LAS tube section is in themidst of fabrication.

    Ground Systems / Ground Operations (GS/GO)

    The Ares I-X flight will provide valuableexperience for the KSC Ground Systems andGround Operations teams in integrating,

    stacking, and launching Ares I. Most of theground systems to be built for Ares I-X haveundergone a 90 percent review and begunfabrication. Among the activities to be addressedare:

    Transporting the vehicle elements toKSC

    Loading RoCS propellants in theHypergol Maintenance Facility (HMF)

    Processing the vehicle in the ARF and

    RPSF Stacking the vehicle in the VAB Conducting vehicle rollout, and launch

    and recovery operations.

    The USS segments and CM/LAS will beassembled into five stacks and the DFI will betested in VAB High Bay 4. This will includeintegrating the first stage 5

    thspacer segment

    and forward structures into Stack 1. The FSsegments and the stacks will be integrated inHigh Bay 3. The baseline schedule includes tendays for integrated testing. Closeoutsexceptfor the Lower 5SS door (Ordnance Access)arecompleted prior to rolling to the pad (Figure 16).

  • 8/14/2019 NASA Ares I-X Flight Test plans

    12/31

  • 8/14/2019 NASA Ares I-X Flight Test plans

    13/31

    National Aeronautics and Space Administration

    www.nasa.gov

    Stephan R. DavisDeputy Mission Manager

    2009 International Astronautical Conference

    Stephan R. DavisDeputy Mission Manager

    2009 International Astronautical Conference

    Ares I-X

    Flight TestThe Future

    Begins Here

    Ares I-X

    Flight TestThe Future

    Begins Here

  • 8/14/2019 NASA Ares I-X Flight Test plans

    14/317465.2National Aeronautics and Space Administration

    Constellation Manifest

    Deliver crew and cargo formissions to InternationalSpace Station (ISS) and to

    Moon and beyond

    Continuing progress towarddesign, component testing,and early flight testing

    Ares I Crew Launch Vehicle Will carry 6 crew to ISS, 4 toMoon

    First flight test 2009

    Initial Operating Capability 2015

    Ares V Cargo Launch Vehicle

    Will launch Earth departure stageand Altair lunar lander to lowEarth orbit for lunar missions

    Largest launch vehicle ever

    designed

    Will begin detailed developmentwork in 2011

  • 8/14/2019 NASA Ares I-X Flight Test plans

    15/31

  • 8/14/2019 NASA Ares I-X Flight Test plans

    16/317465.4National Aeronautics and Space Administration

    Vehicle Overview

    Combines proven space flight andsimulated hardware

    Space flight hardware includes:

    Four-segment solid rocket booster (SpaceShuttle)

    Atlas V-based avionics

    Roll control system (Peacekeeper)

    Separation system (Space Shuttle)

    Parachutes deceleration system (SpaceShuttle)

    Booster deceleration and tumble motors(Space Shuttle)

    Developmental flight instrumentation

    Simulator hardware

    Upper stage

    Orion crew module

    Launch abort system

    Fifth segment of booster

    Simulated FifthSegment

    Orion Crew Module/ Launch Abort

    System Simulator

    Four-segmentMotor

    Upper StageSimulator

    FirstStage

    Avionics (internalthroughout vehicle)

    Roll ControlSystem

    Separation PlaneFirst StageAvionics Module

    (internal)

  • 8/14/2019 NASA Ares I-X Flight Test plans

    17/317465.5National Aeronautics and Space Administration

    Ares I-X Flight Test Objectives

    P(1) Demonstrate control of a dynamicallysimilar, integrated Ares I/Orion, usingAres I relevant ascent control algorithms

    P(2) Perform an in-flight separation/stagingevent between a Ares I-similar First Stageand a representative Upper Stage

    P(3) Demonstrate assembly and recovery of

    a new Ares I-like First Stage element at KSC

    P(4) Demonstrate First Stage separationsequencing, and quantify First Stageatmospheric entry dynamics, and

    parachute performance

    P(5) Characterize magnitude of integratedvehicle roll torque throughoutFirst Stage flight

  • 8/14/2019 NASA Ares I-X Flight Test plans

    18/317465.6National Aeronautics and Space Administration

    Ares I-X Development Flight Test

  • 8/14/2019 NASA Ares I-X Flight Test plans

    19/317465.7National Aeronautics and Space Administration

    First Stage

    Heritage Hardware

    4 Segment Reusable Solid Rocket Motor

    (RSRM) w/Nozzle

    Thrust Vector Control (TVC)

    Flight Termination System (FTS)

    Nose Cap w/Thrusters

    Booster Separation Motors (BSMs)

    Modified Heritage Hardware

    Shuttle Derived Avionics

    Aft Skirt

    New Developments for Ares I-X

    Fifth Segment Simulator (5SS)

    Forward Skirt (FS)

    Forward Skirt Extension (FSE)

    Main Parachute Support Structure (MPSS)

    Frustum

    Ares I Designs

    Parachutes

    FTS Extension to Aft Segment

    Managed at the NASA Marshall Space

    Flight Center, Huntsville, AL

  • 8/14/2019 NASA Ares I-X Flight Test plans

    20/317465.8National Aeronautics and Space Administration

    Avionics

    Primary avionics subsystems:

    FSAM (located in First Stage fifthsegment)

    Guidance & Control System

    Ground Command, Control, andCommunication (GC3)

    Managed at the NASA MarshallSpace Flight Center, Huntsville, ALFirst Stage Avionics Module (FSAM) (Lockheed

    Martin Space Systems (LMSS))

    Atlas V System Integration Lab(SIL) (LMSS)

    Ascent Thrust Vector Controller (ATVC)(Honeywell International)

    RedundantRate Gyro

    (RRGU)

    Fault TolerantInertial

    Navigation Unit(FTINU)

    RedundantRate Gyro

    (RRGU)

  • 8/14/2019 NASA Ares I-X Flight Test plans

    21/317465.9National Aeronautics and Space Administration

    Avionics Progress

    Component(s) Current Status (As Appropriate) Anticipated

    Completion/DeliveryATVC CDR completed June 2007 Oct-08

    Fabrication under way

    FSAM CDR completed April 2008 Oct-08

    Flight Software CDR completed March 2008 Mar-09

    Test Readiness Review completed April2008

    Ground Software (Ground Control,Command, and Communications/GC3)

    Formal testing under way Delivery to KSC October 2008Installation in MLP by May 2009

    Systems Integration Laboratory

    Vehicle Flight Control Testing Ongoing Oct-08Flight Simulation Testing Ongoing May-09

    OFI / DFI Sensors and Harnesses Sensors acquired or on order Cable Harnesses

    Undergoing Table Top Reviews ascompleted

    CM/LAS July 2008

    USS October 2008FS October 2008

    OFI Harnesses

    FS/USS October 2008

    Fault Tolerant Inertial Navigation Unit

    (FTINU)

    Qualification testing complete Delivery to KSC March 2009

    Delivered to United Launch Alliance inMarch 2008

    SDA Fabrication begun December 2007 Aug-08

  • 8/14/2019 NASA Ares I-X Flight Test plans

    22/317465.10National Aeronautics and Space Administration

    Upper Stage Simulator (USS)

    USS is a mass and Outer MoldLimit (OML) simulator

    Hardware includes:

    Interstage (IS) Simulator

    Upper Stage (US) Simulator

    Spacecraft Adapter (SA) Simulator

    Service Module (SM) Simulator

    Developed at the NASA Glenn

    Research Center, Cleveland, OH

    SM

    SA

    US-7

    US-6

    US-5

    US-4

    US-3

    US-2

    US-1

    IS-2

    IS-1

    USS to CM/LAS Interface

    Service Module

    Spacecraft Adapter

    Ballast

    Avionics in US-1 & US-7DFI throughout

    Ballast

    Internal Access Doorand ECS Service Panel

    USS to RoCS Interface

    Interstage

    USS to FS Interface

  • 8/14/2019 NASA Ares I-X Flight Test plans

    23/317465.11National Aeronautics and Space Administration

    USS Internal Access Concept

    Provides access from the Frustumto the CM/LAS

    Door in the IS-1 segment

    Internal access platforms and ladders

    Provides Environmental ControlSystem (ECS) ductwork to maintain asafe work temp, air flow andcontrolled humidity

    Internal access door

    Common accessplatforms with railings

    Ballast platform

    IS-1 Segment

    FS Frustum

  • 8/14/2019 NASA Ares I-X Flight Test plans

    24/317465.12National Aeronautics and Space Administration

    Roll Control System (RoCS)

    Provides post-launch 90-degree roll

    and mitigation against adverse roll

    torques

    Modular propulsion system housedin the Ares I-X USS Interstage

    Proven space hardware harvested

    from Peacekeeper 4th Stage

    Managed at the NASA Marshall

    Space Flight Center, Huntsville, AL

  • 8/14/2019 NASA Ares I-X Flight Test plans

    25/317465.13National Aeronautics and Space Administration

    Instrumented for 924 measurements

    Thermal

    Structures

    GNC/Trajectory

    Aero

    Shock

    Cameras strategically located

    Data to be retrieved via telemetry and a datarecorder box that is recovered from the FirstStage after flight

    Managed at the NASA Langley ResearchCenter, Hampton, VA

    Development Flight Instrumentation (DFI) and Video

    Camera 3-1

    Camera 3-2

    Camera 4-1

    Camera 3-3

    Orion Crew Module/

  • 8/14/2019 NASA Ares I-X Flight Test plans

    26/317465.14National Aeronautics and Space Administration

    Orion Crew Module/Launch Abort System (CM/LAS) Simulator

    Outer mold limit (OML)

    resembles earlier Ares I

    design due to flight test

    schedule

    Developmental flight

    instrumentation sensors

    will measure

    aerodynamic and

    acoustic loads

    Developed at the NASA

    Langley Research Center,

    Hampton, VA

    Vehicle Assembly Building

  • 8/14/2019 NASA Ares I-X Flight Test plans

    27/317465.15National Aeronautics and Space Administration

    Vehicle Assembly Building(VAB) Operations

    The Upper Stage Simulator (USS) segments and Orion CrewModule/Launch Abort System (CM/LAS) will be assembledinto stacks and Development Flight Instrumentation (DFI)tested in VAB Hi-Bay 4

    The First Stage segments and stacks will be integrated inHi-Bay 3

  • 8/14/2019 NASA Ares I-X Flight Test plans

    28/317465.16National Aeronautics and Space Administration

    Hi-Bay 3 Stacks in VAB

    LOX Ballast

    Stack 1XL/S/SE/Frustrum/IS-1/IS-2

    Stack 2US-1

    Stack 3US-2/US-3/US-4/US-5

    Stack 4US-6/US-7

    Stack 5SA/SM/CM/LAS

    LH2 Ballast

  • 8/14/2019 NASA Ares I-X Flight Test plans

    29/317465.17National Aeronautics and Space Administration

    Pad 39B at NASA Kennedy Space Center, FL

    Lightning Mastraised 100ft

    Vehiclestabilizationconceptshown

  • 8/14/2019 NASA Ares I-X Flight Test plans

    30/31

    7465.18National Aeronautics and Space Administration

    Summary

    Ares I-X is the firstflight of NASAs newConstellation Program

    Ares I-X is adevelopmental testflight to supportthe Ares I

    Ares I-X is ontrack for 2009 launchdate

    For more information,see

    http://www.nasa.gov/ares

  • 8/14/2019 NASA Ares I-X Flight Test plans

    31/31