Waisale V 4.30pm; September 29, 2017
Namara Village Microgrid Project WORK PROGRESS UPDATE REPORT
PAGE 1
Brief Summary
The Namara Micro Grid project work has commenced from 28 August 2017 and was
scheduled to complete by end of October 2017. Civil works which is the first phase of
construction is currently underway and is yet to be completed and is expected to be
completed by first week October. However, the second phase of work which is the delivery
of house wiring materials has been done and house wiring is already underway and as of
to date (29/09/17 @ 4.30am), 30 houses has already been wired.
The house wiring that is currently underway includes the installation of 2 lights (2 feet
LED lights and frames) and 1 power point with switches but excludes the installation of
meter boxes. Meter boxes will be installed once all smart meters are inserted inside the
meter boxes. This will be done later as soon as all underground supply main and service
main with its various pillar boxes are installed.
As of now, the Omega team is awaiting Woojin Industrials System Co. Limited to provide
confirmation on queries regarding the connection point (Main Connection/Distribution
Board) from the PV Array side, Generator side and Load Side before commencing with
the laying of the main distribution line/cable. Mr. Kang is awaiting response from his head
office in Korea.
As for the Civil works, platforms/concrete foundation for the 2 containers has completed
and the 2 containers (ESS container and Operational container) have already been placed
on top of the foundations. The concrete foundation for the generator house is also complete
and generator has already been placed on top of its foundation. However the generator
house is near completion and will be completed sooner.
Below is the summary and evidence of the work currently underway at Namara:
1.) Civil Works
a.) Construction of Concrete Foundation for ESS container and Operational container
PAGE 2
b) Construction of Solar Arrays Foundation
PAGE 3
c) Construction of Generator/Power House
d) Digging of Underground Cable Trenches
PAGE 4
e) Fencing of the main VMG site
f) Construction of drainage
PAGE 5
2.) Electrical Works
a) Supply of House wiring material and House wiring works
PAGE 6
OBSERVATION AND RECOMMENDATIONS
1. The company has managed to undertake house wiring installation for 30 households.
As mentioned from above; all materials for house wiring works is currently on site. The
company can now be paid on the delivery of house wiring materials.
2. The foundation for the Solar Array is still in progress and is expected to complete by
mid next week probably on 4th September 2017. It will be a 3 set of Solar Array and
one of the array platform has been constructed already. The other two will be completed
by 4th September 2017.
3. The completion of the drainage work and fencing work should also finish by end of
next week but focus will be on the fencing work then drainage later. As of now, both
this work is being done concurrently.
4. The generator/ power house will be completed most probably by end of next week.
More time was focused on the making of the air ventilation window since it was made
on site rather than having ready-made vents as the case with many of DOE,s Generator
projects. Currently, the structure and noggins is been painted with wood prime paint.
PAGE 7
CONCLUSION
The company can now be paid with the delivery of house wiring materials and pillar boxes.
The have already completed house wiring for 30 households and all house wiring is
expected to be completed by next week.
This report was made at 4.30pm on 29/09/17.