7/31/2019 Nagari to Mohazari Road 1
1/52
Estimated Cost Rs. 1500000.00
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part
1 Km 0/000 to 0/600 in Gadchiroli Taluka & Dist. Gadchiroli.
G O V E R N M E N T O F M A H A R A S H T R A
P.W. CIRCLE , GADCHIROLI
P.W. DIVISION NO. 1, GADCHIROLI
UNDER I.A.P. BUDGET 12 -13
7/31/2019 Nagari to Mohazari Road 1
2/52
ESTIMATE
DIVISION : PUBLIC WORKS DIVISION NO.I ,
GADCHIROLI
SUB-DIVISION : PUBLIC WORKS SUB-DIVISION NO.1,
GADCHIROLI
SANCTIONED ESTIMATE NO:
FUND HEAD :
MAJOR HEAD :
MINOR HEAD :
SERVICE HEAD :
DEPARTMENTAL HEAD :
Estimate is framed in the office of the Executive Engineer, Public Works Division
No. I , Gadchiroli for the probable expenses that will be incurred on
AMOUNT: Rs. 1500000.00
Administrative Approval under No.: Date:
Technically Sanctioned under No.: Date:
Estimate Prepared by: S. G. Allewar (A.E.II)
Estimate checked by:
General Description
Attached Seperatly
Assistant Engineer Gr. 1
P.W. Sub-Division No. 1,
Gadchiroli
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part 1 Km 0/000 to 0/600 in
Gadchiroli Taluka & Dist. Gadchiroli.
7/31/2019 Nagari to Mohazari Road 1
3/52
GENERAL REPORT
Amount of Estimate:- Rs. 1500000.00
Authority :- This work is proposed in IAP budget Progrmme 2012-13 for Rs. 15.00 Lakhs.
vide letter of Shri. Marotrao S. Kowase, M.P. Gadchiroli - Chimur no.
M.P.L.A.D. / G.D. / 1558/2012/ Dt. 21/04/12
Introduction & necessity:-
Nagari village is situated on S.H. - 275 i.e. Bejorpalli Parsewada
Aheri Chamroshi Gadchiroli Armori Wadsa Balagath Road about 1.20 Km
away. The existing earthen road is constructed under E.G.S. but no metelling of
this road in constructed in any programme. Mohazai village is situated on R/S
of S.H. - 275. Due to existing earthen road the people of Nagari Village found it
very difficult to go agriculture field & main road during rainy season.
Also there are agriculture field on both side of road, due to
construction of this road the farmers also get facility for transporting of
agriculture goods during rainy season and the road will be all weather.
Hence this estimate is framed.
Provisions:-
In order to gain above objectives following provisions are made in estimate;
For Road Work
1 Excavation of Catch water drain with its utilisation.
2 Providing Eartwork in embankment required as per standard cross section.
3 Blanketing as an admixture of Soft Murum & Sand 50 % respectively for full width.
4 80 mm metalling in 1 coat 200 mm loose of 3.30 mt. width.
5 40 mm metalling in 1 coats 100 mm loose of 3.00 mt. width.
Construction of Conc. Dhaba Drain at location of crossing. 2 Nos.
1 Rubble soling below face wall .
2 C.Conc. 1:4:8, 0.10 m thik below Bottom slab.
3 C.Conc. In M-15, 0.10 m thick.
4 Face wall in M-15
5 RCC slab in M-20 C. Conc.
Rate & Specifications:-
The rates are adopted as per current CSR 2012-2013 w.e.f. 01-09-2011. The standard
specifications of Govt. of Maharashtra will be followed for execution of these items.
Assistant Engineer Gr. 1
P.W. Sub-Division No. 1,
Gadchiroli
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part 1 Km 0/000 to 0/600 in
Gadchiroli Taluka & Dist. Gadchiroli.
7/31/2019 Nagari to Mohazari Road 1
4/52
GENERAL ABSTARCT
1 Work Cost Rs. 1499746.00
Rs. 1499746.00
Total Rs. 1499746.00
Say Rs. 1500000.00
Assistant Engineer Gr. 1
P.W. Sub-Division No. 1,
Gadchiroli
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part 1
Km 0/000 to 0/600 in Gadchiroli Taluka & Dist. Gadchiroli.
7/31/2019 Nagari to Mohazari Road 1
5/52
Sr. Quantity Rate Unit Amount
No. in Rs. in Rs.
a) Road Work
1
(C.S.R. It No 13 / Page No. 224 ) 356.00 105.50 Cum. 37558.00
2
(C.S.R. It No ( 27 - 28 ) /Page No. 227 ) 356.00 12.00 Cum. 4272.00
3
(C.S.R. It No 27 Page No. 227 ) 1280.44 155.85 Cum. 199557.00
4
For 80mm Metal 385.04 695.75 Cum. 267892.00
For 40mm Metal 175.02 723.35 Cum. 126601.00
5
738.73 456.85 Cum. 337489.00
6
694.98 455.95 Cum. 316876.00
Excavation for catch / side water gutter in all sort of soils, soft
murum etc. to the specified section including stacking the
excavated stuff in regular bund and disposing off unsuitable or
excess stuff upto a lead of 50 m and spreading as directed
Engineer-in-charge.
Laying, watering and compacting the embankment formed of
materials obtained from the road cutting, breaking clods,
dressing to 3% camber design superelevation curve &prescribed section for embankment within a lead of 50 m, after
laying them in layers of 20cm to 30cm. with static roller etc.
complete.
Providing earthwork in embankment with approved materials
obtained from departmental land or other sources including all
lifts, laying in layers of 20 cm. to 30 cm. thickness breaking
clods, dressing to the required lines, curves, grade and
section, watering and compacting with power roller complete. (
Including Royalty Charges )
CSR Item No. 33/229
Supplying sand at the road side, including conveying and
stacking complete.
CSR Item No. 34/229
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part 1 Km 0/000 to 0/600 in
Gadchiroli Taluka & Dist. Gadchiroli.
Item of Work
Supplying trap /granite /quartzite / gneiss stone metal of
required size by bringing the boulders at the road side
breaking them to required gradation including conveying the
boulders and stacking the broken metal etc. complete. (Prior
approval of sample stack of broken metal by the Ex.Engineer
is necessary, the date of approval will form part of the
measurements)
ABSTRACT SHEET
b) By Breaking boulder (Hand broken)
Supplying soft murum at the road side, including conveying
and stacking complete.
CSR Item No. 31(bi)/228
7/31/2019 Nagari to Mohazari Road 1
6/52
Sr. Quantity Rate Unit Amount
No. in Rs. in Rs.
Item of Work
7
1433.71 16.80 Cum. 24086.00
8385.04 27.60 Cum. 10627.00
9
175.02 24.00 Cum. 4200.00
10
1925.22 8.40 Sqm. 16172.00
11
1925.22 13.80 Sqm. 26568.00
12
1750.20 14.40 Sqm. 25203.00
13
5250.60 3.60 Sqm. 18902.00
(b) DHABA DRAINS
14
11.09 149.85 Cum. 1662.00
15
1.96 672.40 Cum. 1318.00
16
1.31 3213.25 Cum. 4209.00
Providing and laying in situ cement concrete of 1:4:8
proportion with trap / granite / quartzite / gneiss metal in
foundation including necessary compacting and curing
complete. (Including plywood/ steel formwork) The C.M. 1:3
plaster is considered for rendering uneven and honeycombed
surface only. Newly laid concrete shall be covered by gunny
bag, plastic, tarpaulin etc. (Wooden centering/formwork will
not be allowed).
CSR Item No. 2/216
CSR Item No. 1/216
CSR Item No. 42/230
Compacting the hard murum side widths layerwise on each
side with static roller including necessary artificial watering
complete .
Providing rubble filling of trap / granite / quartzite / gneiss
stones in foundation including hand packing filling gravel /
sand in the voids etc. complete.
CSR Item No. 44/230
Lift upto 1.5 meter
CSR Item No. 1/184
Excavation for foundation in earth, soils of all types, sand,
gravel soft murum etc. including shoring and strutting as
necessary and disposing off excavated stuff within lead of 100
m as directed etc. complete
CSR Item No. 39/229
Compacting the hard murum / kankar of all width (200 mm.
loose) with Static roller including necessary artificial watering
complete.
CSR Item No. 43/230
Compacting the sub grade/gravel/ oversize metal (200 mm
loose) layers of all width with static roller including necessary,labour, materials and artificial watering complete.
CSR Item No. 40/230
Compacting the sub grade/gravel/ size metal (100 mm loose)
layers of all width with static roller including necessary, labour,
materials and artificial watering complete.
Spreading 40 mm metal including sectioning complete.
Spreading 80 mm metal including sectioning complete.CSR Item No. 38/229
Spreading gravel/sand/soft murum/ available murum over
rubble soling/ W.B.M. surface blanketing berms etc. complete.
CSR Item No. 37/229
7/31/2019 Nagari to Mohazari Road 1
7/52
Sr. Quantity Rate Unit Amount
No. in Rs. in Rs.
Item of Work
17
4.54 5325.55 Cum. 24178.00
18
1.17 4922.45 Cum. 5759.00
19
2.23 135.50 Rmt 302.00
20
2.93 6774.85 Cum 19850.00
21
0.411 63834.20 MT 26236.00
Providing and casting in situ cement concrete of M-20 grade
of trap / granite /quartzite /gneiss metal for R.C.C slabs and
landings as per detailed design and drawings including steel
centering, plywood /steel formwork, steel props, compaction,
finishing uneven and honeycombed surface with C.M. 1:3 of
sufficient minimum thickness to give a smooth and even
surface or roughening the surface if special finish is to be
provided with fan hook box of 2 mm thick M.S.Sheet
rectangular size 180 mm x 100 mm with required depth, with
holes or notches, as required, bottom and top lids of 1.6 mm
thick M.S.Sheet
CSR Item No. 43/203
Providing and cutting, bending, hooking, laying, in position and
tying bar reinforcement as per detailed drawing for R.C.C.
works etc. complete.
CSR Item No. 35/200
CSR Item No. 16/191
Providing and laying in situ cement concrete of M-15 / 1:2:4
with trap / granite / quartzite / gneiss metal in face wall
including plywood/ steel formwork and steel centering,
compaction by vibrator, finishing uneven and honeycombed
surface with C.M.1:3 of sufficient minimum thickness to give
smooth and even surface, filling joints with bitumen, curing
etc. complete. (Excluding cost of reinforcement.) The C.M. 1:3
plaster is considered for rendering uneven and honeycombed
surface only. Newly laid concrete shall be covered by gunny
bag, plastic, tarpaulin etc. (Wooden centering/formwork will
not be allowed).
CSR Item No. 3/216
Providing and laying in situ M-15 / 1:2:4 cement concrete of
trap / granite / quartzite / gneiss metal for levelling coures
below R.C.C raft and in foundation including necessary
plywood/steel formwork, steel centering, compaction byvibrating finishing, curing etc. complete. The C.M. 1:3 plaster
is considered for rendering uneven and honeycombed surface
only. Newly laid concrete shall be covered by gunny bag,
plastic, tarpaulin etc. (Wooden centering/formwork will not be
allowed).
CSR Item No. 14/190
Providing and fixing A.C./ UPVC pipes of 100 mm diameter
and of required length for relieving water pressure, stone filter
as directed complete.(For vent holes in raft).
7/31/2019 Nagari to Mohazari Road 1
8/52
Sr. Quantity Rate Unit Amount
No. in Rs. in Rs.
Item of Work
22
0.65 353.05 Cum. 229.00
Total Rs. 1499746.00
Assistant Engineer Gr. 1
P.W. Sub-Division No. 1,
Gadchiroli
Providing selected murum (having PI < 6 ) filling including
laying in layers of 15 cm to 20 cm watering and compacting
etc. complete.
CSR Item No. 10/219
7/31/2019 Nagari to Mohazari Road 1
9/52
Sr. Nos. L. B. D. Quantity Unit
No.
a) Road Work
1
(C.S.R. It No 13 / Page No. 224 )
75% of Total Length 2 439.50 0.90 0.45 356.00
356.00 Cum.
2
(C.S.R. It No ( 27 - 28 ) /Page No. 227 ) As per Quantity of item no. 3 356.00
356.00 Cum.
3
(C.S.R. It No 27 Page No. 227 )
As per Std X- Section 1 583.40 (9.0+10.80)/2 0.45 2599.05 Cum.Deduct As per existing X- Section 1 583.40 (5.0+6.00)/2 0.30 -962.61
Less Qty obtained from Drain -356.00
Nett Qty. 1280.44 Cum.
4
b) By Breaking boulder (Hand broken)
CSR Item No. 31(bi)/228 80mm Metal583.40 1 583.40 3.30 0.20 385.04 Cum.
Total 385.04 Cum.
CSR Item No. 31(bii)/228
40mm Metal 1 583.40 3.00 0.10 175.02 Cum.
Total 175.02 Cum.
Providing earthwork in embankment with approved materials obtained from departmental land or other
sources including all lifts, laying in layers of 20 cm. to 30 cm. thickness breaking clods, dressing to the
required lines, curves, grade and section, watering and compacting with power roller complete. (
Including Royalty Charges )
Laying, watering and compacting the embankment formed of materials obtained from the road cutting,
breaking clods, dressing to 3% camber design superelevation curve & prescribed section forembankment within a lead of 50 m, after laying them in layers of 20cm to 30cm. with static roller etc.
complete.
Excavation for catch / side water gutter in all sort of soils, soft murum etc. to the specified section
including stacking the excavated stuff in regular bund and disposing off unsuitable or excess stuff upto
a lead of 50 m and spreading as directed Engineer-in-charge.
Supplying trap /granite /quartzite / gneiss stone metal of required size by bringing the boulders at the
road side breaking them to required gradation including conveying the boulders and stacking the
broken metal etc. complete. (Prior approval of sample stack of broken metal by the Ex.Engineer is
necessary, the date of approval will form part of the measurements)
MEASUREMENT SHEET
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part 1 Km 0/000 to 0/600 in
Gadchiroli Taluka & Dist. Gadchiroli.
Item of Work
7/31/2019 Nagari to Mohazari Road 1
10/52
Sr. Nos. L. B. D. Quantity Unit
No.
Item of Work
5
CSR Item No. 33/229
Murum Blanketing for Formation of Road
3.30 3.30
For Blanketing 3.30 3.30 1X1/2 583.40 3.30 0.20 192.52 Cum.For filling side of 80mm 2.55 2.25 2X1/2 583.40 (2.55+2.25)/2 0.20 280.03 Cum.
For side berms 2.40 2.25 2X1/2 583.40 (2.40+2.25)/2 0.10 135.64 Cum.
Murum for 80mm (1/2)X (3/8) 385.04 Cum. 72.200 Cum.
Murum for 40mm (1/3) 175.02 Cum. 58.340 Cum.
Total 738.73 Cum.
6
CSR Item No. 34/229
For Blanketing 3.30 3.30 1X1/2 583.40 3.30 0.20 192.52 Cum.
For filling side of 80mm 2.55 2.25 2X1/2 583.40 (2.55+2.25)/2 0.20 280.03 Cum.
For side berm 2.40 2.25 2X1/2 583.40 (2.40+2.25)/2 0.10 135.64 Cum.
Murum for 80 (1/2)X (3/8) 385.04 Cum. 72.200 Cum.
Murum for 40 (1/12) 175.02 Cum. 14.590 Cum.Total 694.98 Cum.
7
CSR Item No. 37/229
Quantity vide Item No. 3 738.73 Cum.
Quantity vide Item No. 4 694.98 Cum.
Total Qty. 1433.71 Cum.
8
CSR Item No. 38/229
Quantity vide Item No. 2 385.04 Cum.
9
CSR Item No. 39/229
Quantity vide Item No. 2 175.02 Cum.
10
CSR Item No. 43/230
Compaction of Murum Formation layer 583.40 1 583.40 3.30 --- 1925.22 Sqm.
Total 1925.22 Sqm.
11
CSR Item No. 40/230
80mm Metal 583.40 1 583.40 3.30 --- 1925.22 Sqm.
Total 1925.22 Sqm.
12
CSR Item No. 42/230
40mm Metal 583.40 1 583.40 3.00 --- 1750.20 Sqm.
Total 1750.20 Sqm.
Supplying sand at the road side, including conveying and stacking complete.
Supplying soft murum at the road side, including conveying and stacking complete.
Compacting the sub grade/gravel/ oversize metal (200 mm loose) layers of all width with static rollerincluding necessary, labour, materials and artificial watering complete.
Compacting the hard murum / kankar of all width (200 mm. loose) with Static roller including necessary
artificial watering complete.
Spreading 40 mm metal including sectioning complete.
Spreading 80 mm metal including sectioning complete.
Compacting the sub grade/gravel/ size metal (100 mm loose) layers of all width with static roller
including necessary, labour, materials and artificial watering complete.
Spreading gravel/sand/soft murum/ available murum over rubble soling/ W.B.M. surface blanketing
berms etc. complete.
7/31/2019 Nagari to Mohazari Road 1
11/52
Sr. Nos. L. B. D. Quantity Unit
No.
Item of Work
13
CSR Item No. 44/230
For filling side of 80mm 2 583.40 2.25 --- 2625.30 Sqm.
For side berm 2 583.40 2.25 --- 2625.30 Sqm.
Total 5250.60 Sqm.
(b) DHABA DRAINS14
CSR Item No. 1/184
For Dhaba Drain 1 9.00 1.45 0.85 11.09 Cum.
Total 11.09 Cum.
15
CSR Item No. 1/216
For Dhaba Drain 1 9.00 1.45 0.15 1.96 Cum.
Total 1.96 Cum.
16
For Dhaba Drain 1 9.00 1.45 0.10 1.31 Cum.
Total 1.31 Cum.
17
For Dhaba Drain (0.20+0.35)/2
2 1 9.00 0.28 0.90 4.46 Cum.Inscribing Pillars 4 1 0.25 0.25 0.30 0.08
Total 4.54 Cum.
Providing and laying in situ cement concrete of 1:4:8 proportion with trap / granite / quartzite / gneiss
metal in foundation including necessary compacting and curing complete. (Including plywood/ steel
formwork) The C.M. 1:3 plaster is considered for rendering uneven and honeycombed surface only.
Newly laid concrete shall be covered by gunny bag, plastic, tarpaulin etc. (Wooden centering/formwork
will not be allowed).
Providing rubble filling of trap / granite / quartzite / gneiss stones in foundation including hand packing
filling gravel / sand in the voids etc. complete.
Excavation for foundation in earth, soils of all types, sand, gravel soft murum etc. including
shoring and strutting as necessary and disposing off excavated stuff within lead of 100 m as directed
etc. complete
Compacting the hard murum side widths layerwise on each side with static roller including necessary
artificial watering complete .
Providing and laying in situ cement concrete of M-15 / 1:2:4 with trap / granite / quartzite / gneiss metal
in face wall including plywood/ steel formwork and steel centering, compaction by vibrator, finishing
uneven and honeycombed surface with C.M.1:3 of sufficient minimum thickness to give smooth and
even surface, filling joints with bitumen, curing etc. complete. (Excluding cost of reinforcement.) The
C.M. 1:3 plaster is considered for rendering uneven and honeycombed surface only. Newly laid
concrete shall be covered by gunny bag, plastic, tarpaulin etc. (Wooden centering/formwork will not be
allowed).
Lift upto 1.5 meter
CSR Item No. 3/216
CSR Item No. 2/216
7/31/2019 Nagari to Mohazari Road 1
12/52
Sr. Nos. L. B. D. Quantity Unit
No.
Item of Work
18
For Dhaba Drain 1 9.00 1.30 0.10 1.17 Cum.
Total 1.17 Cum.
19
2 1 9.00 0.90 0.28 2.23 Rmt
2
TOTAL QTY. 2.23 Rmt
20
Slab over Drain 1 9.00 1.30 0.25 2.93 Cum
Total 2.93 Cum
21
For Bottom Slab @ 60 Kg/ Cum 1.17 @ 0.060 0.070 MT
For Pier Sur. Reinf. @ 40 Kg/ Cum 4.54 @ 0.030 0.136
For Top Slab @ 70 Kg/ Cum 2.93 @ 0.070 0.205
TOTAL QTY. 0.411 MT
22
Side of Excavation 2 1 9.00 0.08 0.90 0.65 Cum.
Total 0.65 Cum.
Assistant Engineer Gr. 1
P.W. Sub-Division No. 1,
Gadchiroli
Providing and cutting, bending, hooking, laying, in position and tying bar reinforcement as per detailed
drawing for R.C.C. works etc. complete.
CSR Item No. 43/203
CSR Item No. 16/191
Providing selected murum (having PI < 6 ) filling including laying in layers of 15 cm to 20 cm watering
and compacting etc. complete.
CSR Item No. 10/219
CSR Item No. 35/200
Providing and laying in situ M-15 / 1:2:4 cement concrete of trap / granite / quartzite / gneiss metal for
levelling coures below R.C.C raft and in foundation including necessary plywood/steel formwork, steel
centering, compaction by vibrating finishing, curing etc. complete. The C.M. 1:3 plaster is considered
for rendering uneven and honeycombed surface only. Newly laid concrete shall be covered by gunny
bag, plastic, tarpaulin etc. (Wooden centering/formwork will not be allowed).
Providing and fixing A.C./ UPVC pipes of 100 mm diameter and of required length for relieving water
pressure, stone filter as directed complete.(For vent holes in raft).
Providing and casting in situ cement concrete of M-20 grade of trap / granite /quartzite /gneiss metal
for R.C.C slabs and landings as per detailed design and drawings including steel centering, plywood
/steel formwork, steel props, compaction, finishing uneven and honeycombed surface with C.M. 1:3 of
sufficient minimum thickness to give a smooth and even surface or roughening the surface if special
finish is to be provided with fan hook box of 2 mm thick M.S.Sheet rectangular size 180 mm x 100 mm
with required depth, with holes or notches, as required, bottom and top lids of 1.6 mm thick M.S.Sheet
CSR Item No. 14/190
7/31/2019 Nagari to Mohazari Road 1
13/52
RATE ANALYSIS
Sr. Rate/Unit Unito.
1
Rs. 88.00
Deduct 0.50 % for Insurance -0.44
Total = Rs. 87.56
Add 20 % for Naxal Special Action Plan 17.51Add 0.50 % for Insurance 0.44
Total = Rs. 105.51
Say = Rs. 105.50 /Cum.
2
Rs. 10.00
Deduct 0.50 % for Insurance -0.05
Total = Rs. 9.95
Add 20 % for Naxal Special Action Plan 1.99Add 0.50 % for Insurance 0.05
Total = Rs. 11.99
Say = Rs. 12.00 /Cum.
3
Rs. 130.00
Deduct 0.50 % for Insurance -0.65
Total = Rs. 129.35
Add 20 % for Naxal Special Action Plan 25.87Add 0.50 % for Insurance 0.65
Total = Rs. 155.87
Say = Rs. 155.85 /Cum.
4
(C.S.R. It No ( 27 - 28 ) /Page No. 227 )
Providing earthwork in embankment with approved materials
obtained from departmental land or other sources including all
l ifts, laying in layers of 20 cm. to 30 cm. thickness breaking clods,
dressing to the required lines, curves, grade and section, watering
and compacting with power roller complete. ( Including Royalty
(C.S.R. It No 27 Page No. 227 )
CSR Item No. 31(bi)/228
Excavation for catch / side water gutter in all sort of soils, soft
murum etc. to the specified section including stacking theexcavated stuff in regular bund and disposing off unsuitable or
excess stuff upto a lead of 50 m and spreading as directed
(C.S.R. It No 13 / Page No. 224 )
Laying, watering and compacting the embankment formed of
materials obtained from the road cutting, breaking clods, dressing
to 3% camber design superelevation curve & prescribed section
for embankment within a lead of 50 m, after laying them in layers
of 20cm to 30cm. with static roller etc. complete.
Supplying trap /granite /quartzite / gneiss stone metal of required
size by bringing the boulders at the road side breaking them to
required gradation including conveying the boulders and stacking
the broken metal etc. complete. (Prior approval of sample stack of
broken metal by the Ex.Engineer is necessary, the date of
approval will form part of the measurements)
b) By Breaking boulder (Hand broken)
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part 1 Km 0/000 to 0/600 in
Gadchiroli Taluka & Dist. Gadchiroli.
Item of Work
7/31/2019 Nagari to Mohazari Road 1
14/52
Sr. Rate/Unit Unito.
Item of Work
Rate as per Lead Statement For 80mm Rs. 592.00 /Cum.
Deduct for Royalty Charges 1.00 Cum.Rs. -70.60 /Cum. Rs. -70.60
Total Rs. 521.40
Deduct Insurance Charges 0.50 % Rs. -2.61
Total Rs. 518.79
Add for Naxal affected Area 20% Rs. 103.76
Add Insurance Charges 0.50 % Rs. 2.61
Add for Royalty Charges 1.00 Cum. Rs. 70.60 /Cum. Rs. 70.60
Total Rs. 695.76
Say Rs. 695.75 /Cum.
For 40mm
Rate as per Lead Statement Rs. 615.00 /Cum.
Deduct for Royalty Charges 1.00 Cum.Rs. -70.60 /Cum. Rs. -70.60
Total Rs. 544.40
Deduct Insurance Charges 0.50 % Rs. -2.72
Total Rs. 541.68
Add for Naxal affected Area 20% Rs. 108.34
Add Insurance Charges 0.50 % Rs. 2.72
Add for Royalty Charges 1.00 Cum. Rs. 70.60 /Cum. Rs. 70.60
Total Rs. 723.34
Say Rs. 723.35 /Cum.
5
Rate as per Lead Statement Rs. 392.75 /Cum.
Deduct for Royalty Charges 1.00 Cum.Rs. -70.60 /Cum. Rs. -70.60
Total Rs. 322.15
Deduct Insurance Charges 0.50 % Rs. -1.61
Total Rs. 320.54
Add for Naxal affected Area 20% Rs. 64.11Add Insurance Charges 0.50 % Rs. 1.61
Add for Royalty Charges 1.00 Cum. Rs. 70.60 /Cum. Rs. 70.60
Total Rs. 456.86
Say Rs. 456.85 /Cum.
6
Rate as per Lead Statement Rs. 391.98 /Cum.
Deduct for Royalty Charges 1.00 Cum.Rs. -70.60 /Cum. Rs. -70.60
Total Rs. 321.38
Deduct Insurance Charges 0.50 % Rs. -1.61
Total Rs. 319.77Add for Naxal affected Area 20% Rs. 63.95
Add Insurance Charges 0.50 % Rs. 1.61
Add for Royalty Charges 1.00 Cum. Rs. 70.60 /Cum. Rs. 70.60
Total Rs. 455.93
Say Rs. 455.95 /Cum.
CSR Item No. 33/229
Supplying sand at the road side, including conveying and stacking
complete.
CSR Item No. 34/229
Supplying soft murum at the road side, including conveying and
stacking complete.
7/31/2019 Nagari to Mohazari Road 1
15/52
Sr. Rate/Unit Unito.
Item of Work
7
Rate as per CSR Item No 37/229 Rs. 14.00 /Cum.
Deduct 0.50 % for Insurance -0.07
Total = Rs. 13.93
Add 20 % for Naxal Special Action Plan 2.79
Add 0.50 % for Insurance 0.07Rs. 16.79
Say Rs. 16.80 /Cum.
8
Rate as per CSR Item No 38/229 Rs. 23.00 /Cum.
Deduct 0.50 % for Insurance -0.12
Total = Rs. 22.88
Add 20 % for Naxal Special Action Plan 4.58Add 0.50 % for Insurance 0.12
Rs. 27.58
Say Rs. 27.60 /Cum.9
Rate as per CSR Item No 39/229 Rs. 20.00 /Cum.
Deduct 0.50 % for Insurance -0.10
Total = Rs. 19.90
Add 20 % for Naxal Special Action Plan 3.98Add 0.50 % for Insurance 0.10
Rs. 23.98
Say Rs. 24.00 /Cum.
10
Rate as per CSR Item No 43/230 Rs. 7.00 /Sqm.
Deduct 0.50 % for Insurance -0.04
Total = Rs. 6.96
Add 20 % for Naxal Special Action Plan 1.39Add 0.50 % for Insurance 0.04
Rs. 8.39
Say Rs. 8.40 /Cum.
11
Rate as per CSR Item No 40/230 Rs. 11.50 /Sqm.Deduct 0.50 % for Insurance -0.06
Total = Rs. 11.44
Add 20 % for Naxal Special Action Plan 2.29Add 0.50 % for Insurance 0.06
Rs. 13.79
Say Rs. 13.80 /Sqm.
12
Spreading gravel/sand/soft murum/ available murum over rubble
soling/ W.B.M. surface blanketing berms etc. complete.
Spreading 80 mm metal including sectioning complete.
CSR Item No. 43/230
Compacting the sub grade/gravel/ oversize metal (200 mm loose)
layers of all width with static roller including necessary, labour,
materials and artificial watering complete.
CSR Item No. 39/229
Compacting the hard murum / kankar of all width (200 mm. loose)
with Static roller including necessary artificial watering complete.
CSR Item No. 38/229
CSR Item No. 37/229
Compacting the sub grade/gravel/ size metal (100 mm loose)
layers of all width with static roller including necessary, labour,
materials and artificial watering complete.
Spreading 40 mm metal including sectioning complete.
CSR Item No. 40/230
CSR Item No. 42/230
7/31/2019 Nagari to Mohazari Road 1
16/52
Sr. Rate/Unit Unito.
Item of Work
Rate as per CSR Item No 42/230 Rs. 12.00 /Sqm.
Deduct 0.50 % for Insurance -0.06
Total = Rs. 11.94
Add 20 % for Naxal Special Action Plan 2.39Add 0.50 % for Insurance 0.06
Rs. 14.39
Say Rs. 14.40 /Sqm.
13
Rate as per CSR Item No 44/230 Rs. 3.00 /Sqm.
Deduct 0.50 % for Insurance -0.02
Total = Rs. 2.98
Add 20 % for Naxal Special Action Plan 0.60Add 0.50 % for Insurance 0.02
Rs. 3.60
Say Rs. 3.60 /Sqm.
14
Rate as per CSR Item No 1/184 Rs 125.00 /Cum
Deduct 0.50 % for Insurance -0.63
Total = Rs. 124.37
Add 20 % for Naxal Special Action Plan 24.87Add 0.50 % for Insurance 0.63
Rs. 149.87
Say Rs. 149.85 /Cum
15
Rate as per CSR Item No 1/216 Rs 395.00 /Cum
Add Tranptn of Metal 1.00 Cum Rs 162.80 /Cum Rs 162.80
Sand 0.30 Cum Rs 60.78 /Cum Rs 18.23
Rs 576.03
Deduct for Royalty Charges 1.30 Cum.Rs. -70.60 /Cum. Rs. -91.78
Total Rs. 484.25
Deduct Insurance Charges 0.50 % Rs. -2.42
Total Rs. 481.83
Add for Naxal affected Area 20% Rs. 96.37
Add Insurance Charges 0.50 % Rs. 2.42
Add for Royalty Charges 1.30 Cum. Rs. 70.60 /Cum. Rs. 91.78
Total Rs. 672.40
Say Rs. 672.40 /Cum
CSR Item No. 44/230
CSR Item No. 1/216
Compacting the hard murum side widths layerwise on each side
with static roller including necessary artificial watering complete .
Providing rubble fil ling of trap / granite / quartzite / gneiss stonesin foundation including hand packing filling gravel / sand in the
voids etc. complete.
Excavation for foundation in earth, soils of all types, sand, gravel
soft murum etc. including shoring and strutting as necessary anddisposing off excavated stuff within lead of 100 m as directed etc.
complete
Lift upto 1.5 meter
CSR Item No. 1/184
7/31/2019 Nagari to Mohazari Road 1
17/52
Sr. Rate/Unit Unito.
Item of Work
16
Rate as per CSR Item No 2/216 Rs 2520.00 /Cum
Add Tranptn Charges
HB Metal 0.90 Cum Rs 148.00 /Cum Rs 133.20
Sand 0.450 Cum Rs 60.78 /Cum Rs 27.35
Cement 3.40 Bag Rs 4.48 /Bag Rs 15.23
Rs 2695.78
Deduct for Royalty Charges 1.35 Cum.Rs. -70.60 /Cum. Rs. -95.31
Total Rs. 2600.47
Deduct Insurance Charges 0.50 % Rs. -13.00
Total Rs. 2587.47
Add for Naxal affected Area 20% Rs. 517.49
Add Insurance Charges 0.50 % Rs. 13.00
Add for Royalty Charges 1.35 Cum. Rs. 70.60 /Cum. Rs. 95.31
Total Rs. 3213.27
Say Rs. 3213.25 /Cum
17
Rate as per CSR Item No 3/216 Rs 3615.00 /Cum
Add Tranptn Charges
CB Metal 0.85 Cum Rs 926.70 /Cum Rs 787.70
Sand 0.425 Cum Rs 60.78 /Cum Rs 25.83
Cement 6.27 Bag Rs 4.48 /Bag Rs 28.09
Rs 4456.62
Deduct for Royalty Charges 1.28 Cum.Rs. -70.60 /Cum. Rs. -90.02
Total Rs. 4366.60
Deduct Insurance Charges 0.50 % Rs. -21.83
Total Rs. 4344.77
Add for Naxal affected Area 20% Rs. 868.95
Add Insurance Charges 0.50 % Rs. 21.83
Add for Royalty Charges 1.28 Cum. Rs. 70.60 /Cum. Rs. 90.02
Total Rs. 5325.57
Say Rs. 5325.55 /Cum
CSR Item No. 2/216
Providing and laying in situ cement concrete of M-15 / 1:2:4 with
trap / granite / quartzite / gneiss metal in face wall including
plywood/ steel formwork and steel centering, compaction by
vibrator, finishing uneven and honeycombed surface with C.M.1:3
of sufficient minimum thickness to give smooth and even surface,
filling joints with bitumen, curing etc. complete. (Excluding cost of
reinforcement.) The C.M. 1:3 plaster is considered for rendering
uneven and honeycombed surface only. Newly laid concrete shall
be covered by gunny bag, plastic, tarpaulin etc. (Wooden
centering/formwork will not be allowed).
Providing and laying in situ cement concrete of 1:4:8 proportion
with trap / granite / quartzite / gneiss metal in foundation including
necessary compacting and curing complete. (Including plywood/
steel formwork) The C.M. 1:3 plaster is considered for rendering
uneven and honeycombed surface only. Newly laid concrete shall
be covered by gunny bag, plastic, tarpaulin etc. (Wooden
centering/formwork will not be allowed).
CSR Item No. 3/216
7/31/2019 Nagari to Mohazari Road 1
18/52
Sr. Rate/Unit Unito.
Item of Work
18
Rate as per CSR Item No 14/190 Rs 2830.00 /Cum
Add Diff. in cost of Cement (6.27-4.40)=1.87 240.00 /Bag Rs 448.80
Add Tranptn Charges
CB Metal 0.85 Cum Rs 926.70 /Cum Rs 787.70
Sand 0.425 Cum Rs 60.78 /Cum Rs 25.83
Cement 6.27 Bag Rs 4.48 /Bag Rs 28.09
Rs 4120.42
Deduct for Royalty Charges 1.275 Cum.Rs. -70.60 /Cum. Rs. -90.02
Total Rs. 4030.40
Deduct Insurance Charges 0.50 % Rs. -20.15
Total Rs. 4010.25
Add for Naxal affected Area 20% Rs. 802.05
Add Insurance Charges 0.50 % Rs. 20.15
Add for Royalty Charges 1.275 Cum. Rs. 70.60 /Cum. Rs. 90.02
Total Rs. 4922.47
Say Rs. 4922.45 /Cum
19
Rate as per CSR Item No 16/191 Rs 113.00 /Rmt
Deduct 0.50 % for Insurance -0.57
Total = Rs. 112.43
Add 20 % for Naxal Special Action Plan 22.49Add 0.50 % for Insurance 0.57
Rs. 135.49
Say Rs. 135.50 /Rmt
20
Rate as per CSR Item No 43/203 Rs 4820.00 /Cum
Add Tranptn Charges
CB Metal 0.85 Cum Rs 926.70 /Cum Rs 787.70
Sand 0.425 Cum Rs 60.78 /Cum Rs 25.83
Cement 7.10 Bag Rs 4.48 /Bag Rs 31.81
Rs 5665.34
Providing and fixing A.C./ UPVC pipes of 100 mm diameter and of
required length for relieving water pressure, stone filter as
directed complete.(For vent holes in raft).CSR Item No. 16/191
Providing and laying in situ M-15 / 1:2:4 cement concrete of trap /
granite / quartzite / gneiss metal for levelling coures below R.C.C
raft and in foundation including necessary plywood/steel
formwork, steel centering, compaction by vibrating finishing,
curing etc. complete. The C.M. 1:3 plaster is considered for
rendering uneven and honeycombed surface only. Newly laid
concrete shall be covered by gunny bag, plastic, tarpaulin etc.
(Wooden centering/formwork will not be allowed).
CSR Item No. 14/190
Providing and casting in situ cement concrete of M-20 grade of
trap / granite /quartzite /gneiss metal for R.C.C slabs and landings
as per detailed design and drawings including steel centering,
plywood /steel formwork, steel props, compaction, finishing
uneven and honeycombed surface with C.M. 1:3 of sufficient
minimum thickness to give a smooth and even surface or roughening the surface if special finish is to be provided with fan
hook box of 2 mm thick M.S.Sheet rectangular size 180 mm x 100
mm with required depth, with holes or notches, as required,
bottom and top lids of 1.6 mm thick M.S.Sheet
CSR Item No. 43/203
7/31/2019 Nagari to Mohazari Road 1
19/52
Sr. Rate/Unit Unito.
Item of Work
Deduct for Royalty Charges 1.275 Cum.Rs. -70.60 /Cum. Rs. -90.02
Total Rs. 5575.32
Deduct Insurance Charges 0.50 % Rs. -27.88
Total Rs. 5547.44
Add for Naxal affected Area 20% Rs. 1109.49
Add Insurance Charges 0.50 % Rs. 27.88
Add for Royalty Charges 1.275 Cum. Rs. 70.60 /Cum. Rs. 90.02
Total Rs. 6774.83Say Rs. 6774.85 /Cum
21
Rate as per CSR Item No 35/200 Rs 53150.00 /MT
Add Tranptn Charges
Steel 1.000 MT Rs 89.55 /MT Rs 89.55
Rs 53239.55
Deduct 0.50 % for Insurance -266.20
Total = Rs. 52973.35
Add 20 % for Naxal Special Action Plan 10594.67Add 0.50 % for Insurance 266.20
Rs 63834.22
Say Rs. 63834.20 /MT
22
Rate as per CSR Item No 10/219 Rs 225.00 /Cum
Add Diff. in cost of Murum(140.00-130.00) 1.00 Cum. Rs. 10.00 /Cum. Rs -10.00
Add Transportation Charges
Murum 0.50 Cum Rs 121.55 /Cum Rs 60.78
Sand 0.50 Cum Rs 60.78 /Cum Rs 30.39
Rs 306.17
Deduct for Royalty Charges 1.000 Cum.Rs. -70.60 /Cum. Rs. -70.60
Total Rs. 235.57
Deduct Insurance Charges 0.50 % Rs. -1.18
Total Rs. 234.39
Add for Naxal affected Area 20% Rs. 46.88
Add Insurance Charges 0.50 % Rs. 1.18
Add for Royalty Charges 1.000 Cum. Rs. 70.60 /Cum. Rs. 70.60
Total Rs. 353.05
Say Rs. 353.05 /Cum
Assistant Engineer Gr. 1
P.W. Sub-Division No. 1,
Gadchiroli
CSR Item No. 35/200
Providing selected murum (having PI < 6 ) fill ing including laying
in layers of 15 cm to 20 cm watering and compacting etc.
complete.
CSR Item No. 10/219
Providing and cutting, bending, hooking, laying, in position and
tying bar reinforcement as per detailed drawing for R.C.C. works
etc. complete.
7/31/2019 Nagari to Mohazari Road 1
20/52
LEAD STATEMENT (For Road Work)
Sr. Material Source of supply Lead in Lead Supply Loading/ Net Unit
No. Km. Charges Chrges Unloadin Charges
1 H. Br.metal Dongargaon quarry 17.50 280.00 279.00 33.00 592.00 /Cum.
80 mm
2 40 mm Dongargaon quarry 17.50 280.00 302.00 33.00 615.00 /Cum.
3 Sand Kathani River 10.50 172.98 190.00 29.00 391.98 /Cum.
4 Murum Madia Tukum Quarry 17.00 233.75 130.00 29.00 392.75 /Cum.
5 C.B. Metal From Nandori Metal 136.00 1058.70 --- --- 1058.70 /Cum.
crusher quarry
6 Rubble Dongargaon quarry 17.50 308.00 308.00 /Cum.
Assistant Engineer Gr. 1
P.W. Sub-Division No. 1,
Gadchiroli
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part 1 Km
0/000 to 0/600 in Gadchiroli Taluka & Dist. Gadchiroli.
7/31/2019 Nagari to Mohazari Road 1
21/52
LEAD STATEMENT (For C.Conc. Work )
Sr. Material Source of supply Lead in Lead Deduct 5 Net Unit
No. Km. Charges km Lead Chargescharges
1 H. Br.metal Dongargaon quarry 17.50 280.00 132.00 148.00 /Cum.
80 mm &
40 mm
2 Rubble Dongargaon quarry 17.50 308.00 145.20 162.80 /Cum.
3 Sand Kathani River 10.50 172.98 112.20 60.78 /Cum.
4 Murum Madia Tukum Quarry 17.00 233.75 112.20 121.55 /Cum.
5 C.B. Metal From Nandori Metal 136.00 1058.70 132.00 926.70 /Cum.
crusher quarry
6 Cement Gadchiroli Market 13.00 208.35 118.80 89.55 /MT
4.48 /Bag
7 Steel Gadchiroli Market 13.00 208.35 118.80 89.55 /MT
Assistant Engineer Gr. 1
P.W. Sub-Division No. 1,Gadchiroli
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part 1 Km
0/000 to 0/600 in Gadchiroli Taluka & Dist. Gadchiroli.
7/31/2019 Nagari to Mohazari Road 1
22/52
Proposed 80mm metaling layer
40mm metaling 1 coat of 0.075m compacted
Side Berm 0.075 m compacted
7.50 Murum Sand blanketing
2.25 3.00 2.250
3.30
9
Av Banking Ht. in M 0.45
10.8
Assistant Engineer Gr. 1
P.W. Sub-Division No. 1,
Gadchiroli
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part 1 Km
0/000 to 0/600 in Gadchiroli Taluka & Dist. Gadchiroli.
TYPE CROSS SECTION OF ROAD (VR Std.)
7/31/2019 Nagari to Mohazari Road 1
23/52
Type Cross Section of RCC DHABA DRAIN
1.30
0.20 0.90 0.20
0.25
Surface Reinforcement 10 mm Dia
1: 6 30 Cm C/C. form of Closed Stirrups.
0.90
Weep Hole 100 mm Dia UPVC Pipe
1.25
0.60
0.35
0.10
0.10
0.15
Assistant Engineer Gr. 1
P.W. Sub-Division No. 1,
Gadchiroli
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part 1 Km 0/000
to 0/600 in Gadchiroli Taluka & Dist. Gadchiroli.
1.45
RCC Slab in M-20
C. Conc.
1:4:8 C. Conc.
Rubble Filling
7/31/2019 Nagari to Mohazari Road 1
24/52
LEAD STATEMENT
LEAD Metal Rubble Murum Sand Cement Steel Bricks Bit.Mix
0.50 68.00 74.80 57.80 57.80 61.20 61.20 68.00 61.20
1.00 75.00 82.50 63.75 63.75 67.50 67.50 75.00 67.50
1.50 82.00 90.20 69.70 69.70 73.80 73.80 82.00 73.80
2.00 89.50 98.45 76.08 76.08 80.55 80.55 89.50 80.552.50 96.50 106.15 82.03 82.03 86.85 86.85 96.50 86.85
3.00 103.50 113.85 87.98 87.98 93.15 93.15 103.50 93.15
3.50 110.50 121.55 93.93 93.93 99.45 99.45 110.50 99.45
4.00 118.00 129.80 100.30 100.30 106.20 106.20 118.00 106.20
4.50 125.00 137.50 106.25 106.25 112.50 112.50 125.00 112.50
5.00 132.00 145.20 112.20 112.20 118.80 118.80 132.00 118.80
5.50 138.50 152.35 117.73 117.73 124.65 124.65 138.50 124.65
6.00 145.00 159.50 123.25 123.25 130.50 130.50 145.00 130.50
6.50 152.00 167.20 129.20 129.20 136.80 136.80 152.00 136.80
7.00 158.50 174.35 134.73 134.73 142.65 142.65 158.50 142.657.50 165.00 181.50 140.25 140.25 148.50 148.50 165.00 148.50
8.00 171.50 188.65 145.78 145.78 154.35 154.35 171.50 154.35
8.50 178.00 195.80 151.30 151.30 160.20 160.20 178.00 160.20
9.00 185.00 203.50 157.25 157.25 166.50 166.50 185.00 166.50
9.50 191.50 210.65 162.78 162.78 172.35 172.35 191.50 172.35
10.00 198.00 217.80 168.30 168.30 178.20 178.20 198.00 178.20
10.50 203.50 223.85 172.98 172.98 183.15 183.15 203.50 183.15
11.00 209.00 229.90 177.65 177.65 188.10 188.10 209.00 188.10
11.50 215.00 236.50 182.75 182.75 193.50 193.50 215.00 193.50
12.00 220.50 242.55 187.43 187.43 198.45 198.45 220.50 198.4512.50 226.00 248.60 192.10 192.10 203.40 203.40 226.00 203.40
13.00 231.50 254.65 196.78 196.78 208.35 208.35 231.50 208.35
13.50 237.00 260.70 201.45 201.45 213.30 213.30 237.00 213.30
14.00 243.00 267.30 206.55 206.55 218.70 218.70 243.00 218.70
14.50 248.50 273.35 211.23 211.23 223.65 223.65 248.50 223.65
15.00 254.00 279.40 215.90 215.90 228.60 228.60 254.00 228.60
15.50 259.00 284.90 220.15 220.15 233.10 233.10 259.00 233.10
16.00 264.50 290.95 224.83 224.83 238.05 238.05 264.50 238.05
16.50 269.50 296.45 229.08 229.08 242.55 242.55 269.50 242.55
17.00 275.00 302.50 233.75 233.75 247.50 247.50 275.00 247.5017.50 280.00 308.00 238.00 238.00 252.00 252.00 280.00 252.00
18.00 285.00 313.50 242.25 242.25 256.50 256.50 285.00 256.50
18.50 290.50 319.55 246.93 246.93 261.45 261.45 290.50 261.45
19.00 295.50 325.05 251.18 251.18 265.95 265.95 295.50 265.95
19.50 301.00 331.10 255.85 255.85 270.90 270.90 301.00 270.90
20.00 306.00 336.60 260.10 260.10 275.40 275.40 306.00 275.40
7/31/2019 Nagari to Mohazari Road 1
25/52
20.50 311.00 342.10 264.35 264.35 279.90 279.90 311.00 279.90
21.00 315.50 347.05 268.18 268.18 283.95 283.95 315.50 283.95
21.50 320.50 352.55 272.43 272.43 288.45 288.45 320.50 288.45
22.00 325.00 357.50 276.25 276.25 292.50 292.50 325.00 292.50
22.50 330.00 363.00 280.50 280.50 297.00 297.00 330.00 297.00
23.00 335.00 368.50 284.75 284.75 301.50 301.50 335.00 301.50
23.50 339.50 373.45 288.58 288.58 305.55 305.55 339.50 305.55
24.00 344.50 378.95 292.83 292.83 310.05 310.05 344.50 310.05
24.50 349.00 383.90 296.65 296.65 314.10 314.10 349.00 314.10
25.00 354.00 389.40 300.90 300.90 318.60 318.60 354.00 318.60
25.50 358.50 394.35 304.73 304.73 322.65 322.65 358.50 322.65
26.00 363.00 399.30 308.55 308.55 326.70 326.70 363.00 326.70
26.50 367.00 403.70 311.95 311.95 330.30 330.30 367.00 330.30
27.00 371.50 408.65 315.78 315.78 334.35 334.35 371.50 334.35
27.50 376.00 413.60 319.60 319.60 338.40 338.40 376.00 338.40
28.00 380.50 418.55 323.43 323.43 342.45 342.45 380.50 342.45
28.50 385.00 423.50 327.25 327.25 346.50 346.50 385.00 346.50
29.00 389.00 427.90 330.65 330.65 350.10 350.10 389.00 350.10
29.50 393.50 432.85 334.48 334.48 354.15 354.15 393.50 354.15
30.00 398.00 437.80 338.30 338.30 358.20 358.20 398.00 358.2030.50 401.78 441.96 341.51 341.51 361.60 361.60 401.78 361.60
31.00 405.55 446.11 344.72 344.72 365.00 365.00 405.55 365.00
31.50 409.33 450.26 347.93 347.93 368.40 368.40 409.33 368.40
32.00 413.10 454.41 351.14 351.14 371.79 371.79 413.10 371.79
32.50 416.88 458.57 354.35 354.35 375.19 375.19 416.88 375.19
33.00 420.65 462.72 357.55 357.55 378.59 378.59 420.65 378.59
33.50 424.43 466.87 360.77 360.77 381.99 381.99 424.43 381.9934.00 428.20 471.02 363.97 363.97 385.38 385.38 428.20 385.38
34.50 431.98 475.18 367.18 367.18 388.78 388.78 431.98 388.78
35.00 435.75 479.33 370.39 370.39 392.18 392.18 435.75 392.18
35.50 439.53 483.48 373.60 373.60 395.58 395.58 439.53 395.58
36.00 443.30 487.63 376.81 376.81 398.97 398.97 443.30 398.97
36.50 447.08 491.79 380.02 380.02 402.37 402.37 447.08 402.37
37.00 450.85 495.94 383.22 383.22 405.77 405.77 450.85 405.77
37.50 454.63 500.09 386.44 386.44 409.17 409.17 454.63 409.17
38.00 458.40 504.24 389.64 389.64 412.56 412.56 458.40 412.56
38.50 462.18 508.40 392.85 392.85 415.96 415.96 462.18 415.96
39.00 465.95 512.55 396.06 396.06 419.36 419.36 465.95 419.36
39.50 469.73 516.70 399.27 399.27 422.76 422.76 469.73 422.7640.00 473.50 520.85 402.48 402.48 426.15 426.15 473.50 426.15
40.50 477.28 525.01 405.69 405.69 429.55 429.55 477.28 429.55
41.00 481.05 529.16 408.89 408.89 432.95 432.95 481.05 432.95
41.50 484.83 533.31 412.11 412.11 436.35 436.35 484.83 436.35
42.00 488.60 537.46 415.31 415.31 439.74 439.74 488.60 439.74
42.50 492.38 541.62 418.52 418.52 443.14 443.14 492.38 443.14
43.00 496.15 545.77 421.73 421.73 446.54 446.54 496.15 446.54
43.50 499.93 549.92 424.94 424.94 449.94 449.94 499.93 449.94
7/31/2019 Nagari to Mohazari Road 1
26/52
44.00 503.70 554.07 428.15 428.15 453.33 453.33 503.70 453.33
44.50 507.48 558.23 431.36 431.36 456.73 456.73 507.48 456.73
45.00 511.25 562.38 434.56 434.56 460.13 460.13 511.25 460.13
45.50 515.03 566.53 437.78 437.78 463.53 463.53 515.03 463.53
46.00 518.80 570.68 440.98 440.98 466.92 466.92 518.80 466.92
46.50 522.58 574.84 444.19 444.19 470.32 470.32 522.58 470.32
47.00 526.35 578.99 447.40 447.40 473.72 473.72 526.35 473.7247.50 530.13 583.14 450.61 450.61 477.12 477.12 530.13 477.12
48.00 533.90 587.29 453.82 453.82 480.51 480.51 533.90 480.51
48.50 537.68 591.45 457.03 457.03 483.91 483.91 537.68 483.91
49.00 541.45 595.60 460.23 460.23 487.31 487.31 541.45 487.31
49.50 545.23 599.75 463.45 463.45 490.71 490.71 545.23 490.71
50.00 549.00 603.90 466.65 466.65 494.10 494.10 549.00 494.10
50.50 552.78 608.06 469.86 469.86 497.50 497.50 552.78 497.50
51.00 556.55 612.21 473.07 473.07 500.90 500.90 556.55 500.90
51.50 560.33 616.36 476.28 476.28 504.30 504.30 560.33 504.30
52.00 564.10 620.51 479.49 479.49 507.69 507.69 564.10 507.69
52.50 567.88 624.67 482.70 482.70 511.09 511.09 567.88 511.09
53.00 571.65 628.82 485.90 485.90 514.49 514.49 571.65 514.4953.50 575.43 632.97 489.12 489.12 517.89 517.89 575.43 517.89
54.00 579.20 637.12 492.32 492.32 521.28 521.28 579.20 521.28
54.50 582.98 641.28 495.53 495.53 524.68 524.68 582.98 524.68
55.00 586.75 645.43 498.74 498.74 528.08 528.08 586.75 528.08
55.50 590.53 649.58 501.95 501.95 531.48 531.48 590.53 531.48
56.00 594.30 653.73 505.16 505.16 534.87 534.87 594.30 534.87
56.50 598.08 657.89 508.37 508.37 538.27 538.27 598.08 538.27
57.00 601.85 662.04 511.57 511.57 541.67 541.67 601.85 541.67
57.50 605.63 666.19 514.79 514.79 545.07 545.07 605.63 545.07
58.00 609.40 670.34 517.99 517.99 548.46 548.46 609.40 548.46
58.50 613.18 674.50 521.20 521.20 551.86 551.86 613.18 551.86
59.00 616.95 678.65 524.41 524.41 555.26 555.26 616.95 555.26
59.50 620.73 682.80 527.62 527.62 558.66 558.66 620.73 558.66
60.00 624.50 686.95 530.83 530.83 562.05 562.05 624.50 562.05
60.50 627.48 690.23 533.36 533.36 564.73 564.73 627.48 564.73
61.00 630.45 693.50 535.88 535.88 567.41 567.41 630.45 567.41
61.50 633.43 696.77 538.42 538.42 570.09 570.09 633.43 570.09
62.00 636.40 700.04 540.94 540.94 572.76 572.76 636.40 572.76
62.50 639.38 703.32 543.47 543.47 575.44 575.44 639.38 575.44
63.00 642.35 706.59 546.00 546.00 578.12 578.12 642.35 578.12
63.50 645.33 709.86 548.53 548.53 580.80 580.80 645.33 580.80
64.00 648.30 713.13 551.06 551.06 583.47 583.47 648.30 583.47
64.50 651.28 716.41 553.59 553.59 586.15 586.15 651.28 586.15
65.00 654.25 719.68 556.11 556.11 588.83 588.83 654.25 588.83
65.50 657.23 722.95 558.65 558.65 591.51 591.51 657.23 591.5166.00 660.20 726.22 561.17 561.17 594.18 594.18 660.20 594.18
66.50 663.18 729.50 563.70 563.70 596.86 596.86 663.18 596.86
67.00 666.15 732.77 566.23 566.23 599.54 599.54 666.15 599.54
67.50 669.13 736.04 568.76 568.76 602.22 602.22 669.13 602.22
68.00 672.10 739.31 571.29 571.29 604.89 604.89 672.10 604.89
68.50 675.08 742.59 573.82 573.82 607.57 607.57 675.08 607.57
69.00 678.05 745.86 576.34 576.34 610.25 610.25 678.05 610.25
69.50 681.03 749.13 578.88 578.88 612.93 612.93 681.03 612.93
7/31/2019 Nagari to Mohazari Road 1
27/52
70.00 684.00 752.40 581.40 581.40 615.60 615.60 684.00 615.60
70.50 686.98 755.68 583.93 583.93 618.28 618.28 686.98 618.28
71.00 689.95 758.95 586.46 586.46 620.96 620.96 689.95 620.96
71.50 692.93 762.22 588.99 588.99 623.64 623.64 692.93 623.64
72.00 695.90 765.49 591.52 591.52 626.31 626.31 695.90 626.31
72.50 698.88 768.77 594.05 594.05 628.99 628.99 698.88 628.99
73.00 701.85 772.04 596.57 596.57 631.67 631.67 701.85 631.6773.50 704.83 775.31 599.11 599.11 634.35 634.35 704.83 634.35
74.00 707.80 778.58 601.63 601.63 637.02 637.02 707.80 637.02
74.50 710.78 781.86 604.16 604.16 639.70 639.70 710.78 639.70
75.00 713.75 785.13 606.69 606.69 642.38 642.38 713.75 642.38
75.50 716.73 788.40 609.22 609.22 645.06 645.06 716.73 645.06
76.00 719.70 791.67 611.75 611.75 647.73 647.73 719.70 647.73
76.50 722.68 794.95 614.28 614.28 650.41 650.41 722.68 650.41
77.00 725.65 798.22 616.80 616.80 653.09 653.09 725.65 653.09
77.50 728.63 801.49 619.34 619.34 655.77 655.77 728.63 655.77
78.00 731.60 804.76 621.86 621.86 658.44 658.44 731.60 658.44
78.50 734.58 808.04 624.39 624.39 661.12 661.12 734.58 661.12
79.00 737.55 811.31 626.92 626.92 663.80 663.80 737.55 663.8079.50 740.53 814.58 629.45 629.45 666.48 666.48 740.53 666.48
80.00 743.50 817.85 631.98 631.98 669.15 669.15 743.50 669.15
80.50 746.48 821.13 634.51 634.51 671.83 671.83 746.48 671.83
81.00 749.45 824.40 637.03 637.03 674.51 674.51 749.45 674.51
81.50 752.43 827.67 639.57 639.57 677.19 677.19 752.43 677.19
82.00 755.40 830.94 642.09 642.09 679.86 679.86 755.40 679.86
82.50 758.38 834.22 644.62 644.62 682.54 682.54 758.38 682.54
83.00 761.35 837.49 647.15 647.15 685.22 685.22 761.35 685.22
83.50 764.33 840.76 649.68 649.68 687.90 687.90 764.33 687.90
84.00 767.30 844.03 652.21 652.21 690.57 690.57 767.30 690.57
84.50 770.28 847.31 654.74 654.74 693.25 693.25 770.28 693.25
85.00 773.25 850.58 657.26 657.26 695.93 695.93 773.25 695.93
85.50 776.23 853.85 659.80 659.80 698.61 698.61 776.23 698.61
86.00 779.20 857.12 662.32 662.32 701.28 701.28 779.20 701.28
86.50 782.18 860.40 664.85 664.85 703.96 703.96 782.18 703.96
87.00 785.15 863.67 667.38 667.38 706.64 706.64 785.15 706.64
87.50 788.13 866.94 669.91 669.91 709.32 709.32 788.13 709.32
88.00 791.10 870.21 672.44 672.44 711.99 711.99 791.10 711.99
88.50 794.08 873.49 674.97 674.97 714.67 714.67 794.08 714.67
89.00 797.05 876.76 677.49 677.49 717.35 717.35 797.05 717.35
89.50 800.03 880.03 680.03 680.03 720.03 720.03 800.03 720.03
90.00 803.00 883.30 682.55 682.55 722.70 722.70 803.00 722.70
90.50 805.98 886.58 685.08 685.08 725.38 725.38 805.98 725.38
91.00 808.95 889.85 687.61 687.61 728.06 728.06 808.95 728.06
91.50 811.93 893.12 690.14 690.14 730.74 730.74 811.93 730.7492.00 814.90 896.39 692.67 692.67 733.41 733.41 814.90 733.41
92.50 817.88 899.67 695.20 695.20 736.09 736.09 817.88 736.09
93.00 820.85 902.94 697.72 697.72 738.77 738.77 820.85 738.77
93.50 823.83 906.21 700.26 700.26 741.45 741.45 823.83 741.45
94.00 826.80 909.48 702.78 702.78 744.12 744.12 826.80 744.12
94.50 829.78 912.76 705.31 705.31 746.80 746.80 829.78 746.80
95.00 832.75 916.03 707.84 707.84 749.48 749.48 832.75 749.48
95.50 835.73 919.30 710.37 710.37 752.16 752.16 835.73 752.16
7/31/2019 Nagari to Mohazari Road 1
28/52
96.00 838.70 922.57 712.90 712.90 754.83 754.83 838.70 754.83
96.50 841.68 925.85 715.43 715.43 757.51 757.51 841.68 757.51
97.00 844.65 929.12 717.95 717.95 760.19 760.19 844.65 760.19
97.50 847.63 932.39 720.49 720.49 762.87 762.87 847.63 762.87
98.00 850.60 935.66 723.01 723.01 765.54 765.54 850.60 765.54
98.50 853.58 938.94 725.54 725.54 768.22 768.22 853.58 768.22
99.00 856.55 942.21 728.07 728.07 770.90 770.90 856.55 770.9099.50 859.53 945.48 730.60 730.60 773.58 773.58 859.53 773.58
100.00 862.50 948.75 733.13 733.13 776.25 776.25 862.50 776.25
100.50 865.23 951.75 735.45 735.45 778.71 778.71 865.23 778.71
101.00 867.95 954.75 737.76 737.76 781.16 781.16 867.95 781.16
101.50 870.68 957.75 740.08 740.08 783.61 783.61 870.68 783.61
102.00 873.40 960.74 742.39 742.39 786.06 786.06 873.40 786.06
102.50 876.13 963.74 744.71 744.71 788.52 788.52 876.13 788.52
103.00 878.85 966.74 747.02 747.02 790.97 790.97 878.85 790.97
103.50 881.58 969.74 749.34 749.34 793.42 793.42 881.58 793.42
104.00 884.30 972.73 751.66 751.66 795.87 795.87 884.30 795.87
104.50 887.03 975.73 753.98 753.98 798.33 798.33 887.03 798.33
105.00 889.75 978.73 756.29 756.29 800.78 800.78 889.75 800.78105.50 892.48 981.73 758.61 758.61 803.23 803.23 892.48 803.23
106.00 895.20 984.72 760.92 760.92 805.68 805.68 895.20 805.68
106.50 897.93 987.72 763.24 763.24 808.14 808.14 897.93 808.14
107.00 900.65 990.72 765.55 765.55 810.59 810.59 900.65 810.59
107.50 903.38 993.72 767.87 767.87 813.04 813.04 903.38 813.04
108.00 906.10 996.71 770.19 770.19 815.49 815.49 906.10 815.49
108.50 908.83 999.71 772.51 772.51 817.95 817.95 908.83 817.95
109.00 911.55 1002.71 774.82 774.82 820.40 820.40 911.55 820.40
109.50 914.28 1005.71 777.14 777.14 822.85 822.85 914.28 822.85
110.00 917.00 1008.70 779.45 779.45 825.30 825.30 917.00 825.30
110.50 919.73 1011.70 781.77 781.77 827.76 827.76 919.73 827.76
111.00 922.45 1014.70 784.08 784.08 830.21 830.21 922.45 830.21
111.50 925.18 1017.70 786.40 786.40 832.66 832.66 925.18 832.66
112.00 927.90 1020.69 788.72 788.72 835.11 835.11 927.90 835.11
112.50 930.63 1023.69 791.04 791.04 837.57 837.57 930.63 837.57
113.00 933.35 1026.69 793.35 793.35 840.02 840.02 933.35 840.02
113.50 936.08 1029.69 795.67 795.67 842.47 842.47 936.08 842.47
114.00 938.80 1032.68 797.98 797.98 844.92 844.92 938.80 844.92
114.50 941.53 1035.68 800.30 800.30 847.38 847.38 941.53 847.38
115.00 944.25 1038.68 802.61 802.61 849.83 849.83 944.25 849.83
115.50 946.98 1041.68 804.93 804.93 852.28 852.28 946.98 852.28
116.00 949.70 1044.67 807.25 807.25 854.73 854.73 949.70 854.73
116.50 952.43 1047.67 809.57 809.57 857.19 857.19 952.43 857.19
117.00 955.15 1050.67 811.88 811.88 859.64 859.64 955.15 859.64
117.50 957.88 1053.67 814.20 814.20 862.09 862.09 957.88 862.09118.00 960.60 1056.66 816.51 816.51 864.54 864.54 960.60 864.54
118.50 963.33 1059.66 818.83 818.83 867.00 867.00 963.33 867.00
119.00 966.05 1062.66 821.14 821.14 869.45 869.45 966.05 869.45
119.50 968.78 1065.66 823.46 823.46 871.90 871.90 968.78 871.90
120.00 971.50 1068.65 825.78 825.78 874.35 874.35 971.50 874.35
120.50 974.23 1071.65 828.10 828.10 876.81 876.81 974.23 876.81
121.00 976.95 1074.65 830.41 830.41 879.26 879.26 976.95 879.26
121.50 979.68 1077.65 832.73 832.73 881.71 881.71 979.68 881.71
7/31/2019 Nagari to Mohazari Road 1
29/52
122.00 982.40 1080.64 835.04 835.04 884.16 884.16 982.40 884.16
122.50 985.13 1083.64 837.36 837.36 886.62 886.62 985.13 886.62
123.00 987.85 1086.64 839.67 839.67 889.07 889.07 987.85 889.07
123.50 990.58 1089.64 841.99 841.99 891.52 891.52 990.58 891.52
124.00 993.30 1092.63 844.31 844.31 893.97 893.97 993.30 893.97
124.50 996.03 1095.63 846.63 846.63 896.43 896.43 996.03 896.43
125.00 998.75 1098.63 848.94 848.94 898.88 898.88 998.75 898.88125.50 1001.48 1101.63 851.26 851.26 901.33 901.33 1001.48 901.33
126.00 1004.20 1104.62 853.57 853.57 903.78 903.78 1004.20 903.78
126.50 1006.93 1107.62 855.89 855.89 906.24 906.24 1006.93 906.24
127.00 1009.65 1110.62 858.20 858.20 908.69 908.69 1009.65 908.69
127.50 1012.38 1113.62 860.52 860.52 911.14 911.14 1012.38 911.14
128.00 1015.10 1116.61 862.84 862.84 913.59 913.59 1015.10 913.59
128.50 1017.83 1119.61 865.16 865.16 916.05 916.05 1017.83 916.05
129.00 1020.55 1122.61 867.47 867.47 918.50 918.50 1020.55 918.50
129.50 1023.28 1125.61 869.79 869.79 920.95 920.95 1023.28 920.95
130.00 1026.00 1128.60 872.10 872.10 923.40 923.40 1026.00 923.40
130.50 1028.73 1131.60 874.42 874.42 925.86 925.86 1028.73 925.86
131.00 1031.45 1134.60 876.73 876.73 928.31 928.31 1031.45 928.31131.50 1034.18 1137.60 879.05 879.05 930.76 930.76 1034.18 930.76
132.00 1036.90 1140.59 881.37 881.37 933.21 933.21 1036.90 933.21
132.50 1039.63 1143.59 883.69 883.69 935.67 935.67 1039.63 935.67
133.00 1042.35 1146.59 886.00 886.00 938.12 938.12 1042.35 938.12
133.50 1045.08 1149.59 888.32 888.32 940.57 940.57 1045.08 940.57
134.00 1047.80 1152.58 890.63 890.63 943.02 943.02 1047.80 943.02
134.50 1050.53 1155.58 892.95 892.95 945.48 945.48 1050.53 945.48
135.00 1053.25 1158.58 895.26 895.26 947.93 947.93 1053.25 947.93
135.50 1055.98 1161.58 897.58 897.58 950.38 950.38 1055.98 950.38
136.00 1058.70 1164.57 899.90 899.90 952.83 952.83 1058.70 952.83
136.50 1061.43 1167.57 902.22 902.22 955.29 955.29 1061.43 955.29
137.00 1064.15 1170.57 904.53 904.53 957.74 957.74 1064.15 957.74
137.50 1066.88 1173.57 906.85 906.85 960.19 960.19 1066.88 960.19
138.00 1069.60 1176.56 909.16 909.16 962.64 962.64 1069.60 962.64
138.50 1072.33 1179.56 911.48 911.48 965.10 965.10 1072.33 965.10
139.00 1075.05 1182.56 913.79 913.79 967.55 967.55 1075.05 967.55
139.50 1077.78 1185.56 916.11 916.11 970.00 970.00 1077.78 970.00
140.00 1080.50 1188.55 918.43 918.43 972.45 972.45 1080.50 972.45
140.50 1083.23 1191.55 920.75 920.75 974.91 974.91 1083.23 974.91
141.00 1085.95 1194.55 923.06 923.06 977.36 977.36 1085.95 977.36
141.50 1088.68 1197.55 925.38 925.38 979.81 979.81 1088.68 979.81
142.00 1091.40 1200.54 927.69 927.69 982.26 982.26 1091.40 982.26
142.50 1094.13 1203.54 930.01 930.01 984.72 984.72 1094.13 984.72
143.00 1096.85 1206.54 932.32 932.32 987.17 987.17 1096.85 987.17
143.50 1099.58 1209.54 934.64 934.64 989.62 989.62 1099.58 989.62144.00 1102.30 1212.53 936.96 936.96 992.07 992.07 1102.30 992.07
144.50 1105.03 1215.53 939.28 939.28 994.53 994.53 1105.03 994.53
145.00 1107.75 1218.53 941.59 941.59 996.98 996.98 1107.75 996.98
145.50 1110.48 1221.53 943.91 943.91 999.43 999.43 1110.48 999.43
146.00 1113.20 1224.52 946.22 946.22 1001.88 1001.88 1113.20 1001.88
146.50 1115.93 1227.52 948.54 948.54 1004.34 1004.34 1115.93 1004.34
147.00 1118.65 1230.52 950.85 950.85 1006.79 1006.79 1118.65 1006.79
147.50 1121.38 1233.52 953.17 953.17 1009.24 1009.24 1121.38 1009.24
7/31/2019 Nagari to Mohazari Road 1
30/52
148.00 1124.10 1236.51 955.49 955.49 1011.69 1011.69 1124.10 1011.69
148.50 1126.83 1239.51 957.81 957.81 1014.15 1014.15 1126.83 1014.15
149.00 1129.55 1242.51 960.12 960.12 1016.60 1016.60 1129.55 1016.60
149.50 1132.28 1245.51 962.44 962.44 1019.05 1019.05 1132.28 1019.05
150.00 1135.00 1248.50 964.75 964.75 1021.50 1021.50 1135.00 1021.50
150.50 1137.73 1251.50 967.07 967.07 1023.96 1023.96 1137.73 1023.96
151.00 1140.45 1254.50 969.38 969.38 1026.41 1026.41 1140.45 1026.41151.50 1143.18 1257.50 971.70 971.70 1028.86 1028.86 1143.18 1028.86
152.00 1145.90 1260.49 974.02 974.02 1031.31 1031.31 1145.90 1031.31
152.50 1148.63 1263.49 976.34 976.34 1033.77 1033.77 1148.63 1033.77
153.00 1151.35 1266.49 978.65 978.65 1036.22 1036.22 1151.35 1036.22
7/31/2019 Nagari to Mohazari Road 1
31/52
Timber Tiles(Floor) Mang. Tiles AC/GI Sheet RCC Pipe bulk Bitn Pack Bitun
47.60 54.40 61.20 51.00 9.08 3.13 1.60
52.50 60.00 67.50 56.25 18.15 6.25 3.20
57.40 65.60 73.80 61.50 27.23 9.38 4.80
62.65 71.60 80.55 67.13 36.30 12.50 6.4067.55 77.20 86.85 72.38 45.38 15.63 8.00
72.45 82.80 93.15 77.63 54.45 18.75 9.60
77.35 88.40 99.45 82.88 63.53 21.88 11.20
82.60 94.40 106.20 88.50 72.60 25.00 12.80
87.50 100.00 112.50 93.75 81.68 28.13 14.40
92.40 105.60 118.80 99.00 90.75 31.25 16.00
96.95 110.80 124.65 103.88 99.83 34.38 17.60
101.50 116.00 130.50 108.75 108.90 37.50 19.20
106.40 121.60 136.80 114.00 117.98 40.63 20.80
110.95 126.80 142.65 118.88 127.05 43.75 22.40115.50 132.00 148.50 123.75 136.13 46.88 24.00
120.05 137.20 154.35 128.63 145.20 50.00 25.60
124.60 142.40 160.20 133.50 154.28 53.13 27.20
129.50 148.00 166.50 138.75 163.35 56.25 28.80
134.05 153.20 172.35 143.63 172.43 59.38 30.40
138.60 158.40 178.20 148.50 181.50 62.50 32.00
142.45 162.80 183.15 152.63 190.58 65.63 33.60
146.30 167.20 188.10 156.75 199.65 68.75 35.20
150.50 172.00 193.50 161.25 208.73 71.88 36.80
154.35 176.40 198.45 165.38 217.80 75.00 38.40158.20 180.80 203.40 169.50 226.88 78.13 40.00
162.05 185.20 208.35 173.63 235.95 81.25 41.60
165.90 189.60 213.30 177.75 245.03 84.38 43.20
170.10 194.40 218.70 182.25 254.10 87.50 44.80
173.95 198.80 223.65 186.38 263.18 90.63 46.40
177.80 203.20 228.60 190.50 272.25 93.75 48.00
181.30 207.20 233.10 194.25 278.63 96.88 49.60
185.15 211.60 238.05 198.38 285.00 100.00 51.20
188.65 215.60 242.55 202.13 291.38 103.13 52.80
192.50 220.00 247.50 206.25 297.75 106.25 54.40196.00 224.00 252.00 210.00 304.13 109.38 56.00
199.50 228.00 256.50 213.75 310.50 112.50 57.60
203.35 232.40 261.45 217.88 316.88 115.63 59.20
206.85 236.40 265.95 221.63 323.25 118.75 60.80
210.70 240.80 270.90 225.75 329.63 121.88 62.40
214.20 244.80 275.40 229.50 336.00 125.00 64.00
7/31/2019 Nagari to Mohazari Road 1
32/52
217.70 248.80 279.90 233.25 342.38 128.13 65.60
220.85 252.40 283.95 236.63 348.75 131.25 67.20
224.35 256.40 288.45 240.38 355.13 134.38 68.80
227.50 260.00 292.50 243.75 361.50 137.50 70.40
231.00 264.00 297.00 247.50 367.88 140.63 72.00
234.50 268.00 301.50 251.25 374.25 143.75 73.60
237.65 271.60 305.55 254.63 380.63 146.88 75.20
241.15 275.60 310.05 258.38 387.00 150.00 76.80
244.30 279.20 314.10 261.75 393.38 153.13 78.40
247.80 283.20 318.60 265.50 399.75 156.25 80.00
250.95 286.80 322.65 268.88 406.13 159.38 81.60
254.10 290.40 326.70 272.25 412.50 162.50 83.20
256.90 293.60 330.30 275.25 418.88 165.63 84.80
260.05 297.20 334.35 278.63 425.25 168.75 86.40
263.20 300.80 338.40 282.00 431.63 171.88 88.00
266.35 304.40 342.45 285.38 438.00 175.00 89.60
269.50 308.00 346.50 288.75 444.38 178.13 91.20
272.30 311.20 350.10 291.75 450.75 181.25 92.80
275.45 314.80 354.15 295.13 457.13 184.38 94.40
278.60 318.40 358.20 298.50 463.50 187.50 96.00
281.25 321.42 361.60 301.34 469.88 190.63 97.60
283.89 324.44 365.00 304.16 476.25 193.75 99.20
286.53 327.46 368.40 307.00 482.63 196.88 100.80
289.17 330.48 371.79 309.83 489.00 200.00 102.40
291.82 333.50 375.19 312.66 495.38 203.13 104.00
294.46 336.52 378.59 315.49 501.75 206.25 105.60
297.10 339.54 381.99 318.32 508.13 209.38 107.20299.74 342.56 385.38 321.15 514.50 212.50 108.80
302.39 345.58 388.78 323.99 520.88 215.63 110.40
305.03 348.60 392.18 326.81 527.25 218.75 112.00
307.67 351.62 395.58 329.65 533.63 221.88 113.60
310.31 354.64 398.97 332.48 540.00 225.00 115.20
312.96 357.66 402.37 335.31 546.38 228.13 116.80
315.60 360.68 405.77 338.14 552.75 231.25 118.40
318.24 363.70 409.17 340.97 559.13 234.38 120.00
320.88 366.72 412.56 343.80 565.50 237.50 121.60
323.53 369.74 415.96 346.64 571.88 240.63 123.20
326.17 372.76 419.36 349.46 578.25 243.75 124.80
328.81 375.78 422.76 352.30 584.63 246.88 126.40331.45 378.80 426.15 355.13 591.00 250.00 128.00
334.10 381.82 429.55 357.96 597.38 253.13 129.60
336.74 384.84 432.95 360.79 603.75 256.25 131.20
339.38 387.86 436.35 363.62 610.13 259.38 132.80
342.02 390.88 439.74 366.45 616.50 262.50 134.40
344.67 393.90 443.14 369.29 622.88 265.63 136.00
347.31 396.92 446.54 372.11 629.25 268.75 137.60
349.95 399.94 449.94 374.95 635.63 271.88 139.20
7/31/2019 Nagari to Mohazari Road 1
33/52
352.59 402.96 453.33 377.78 642.00 275.00 140.80
355.24 405.98 456.73 380.61 648.38 278.13 142.40
357.88 409.00 460.13 383.44 654.75 281.25 144.00
360.52 412.02 463.53 386.27 661.13 284.38 145.60
363.16 415.04 466.92 389.10 667.50 287.50 147.20
365.81 418.06 470.32 391.94 673.88 290.63 148.80
368.45 421.08 473.72 394.76 680.25 293.75 150.40371.09 424.10 477.12 397.60 686.63 296.88 152.00
373.73 427.12 480.51 400.43 693.00 300.00 153.60
376.38 430.14 483.91 403.26 699.38 303.13 155.20
379.02 433.16 487.31 406.09 705.75 306.25 156.80
381.66 436.18 490.71 408.92 712.13 309.38 158.40
384.30 439.20 494.10 411.75 718.50 312.50 160.00
386.95 442.22 497.50 414.59 723.90 315.63 161.60
389.59 445.24 500.90 417.41 729.30 318.75 163.20
392.23 448.26 504.30 420.25 734.70 321.88 164.80
394.87 451.28 507.69 423.08 740.10 325.00 166.40
397.52 454.30 511.09 425.91 745.50 328.13 168.00
400.16 457.32 514.49 428.74 750.90 331.25 169.60402.80 460.34 517.89 431.57 756.30 334.38 171.20
405.44 463.36 521.28 434.40 761.70 337.50 172.80
408.09 466.38 524.68 437.24 767.10 340.63 174.40
410.73 469.40 528.08 440.06 772.50 343.75 176.00
413.37 472.42 531.48 442.90 777.90 346.88 177.60
416.01 475.44 534.87 445.73 783.30 350.00 179.20
418.66 478.46 538.27 448.56 788.70 353.13 180.80
421.30 481.48 541.67 451.39 794.10 356.25 182.40
423.94 484.50 545.07 454.22 799.50 359.38 184.00
426.58 487.52 548.46 457.05 804.90 362.50 185.60
429.23 490.54 551.86 459.89 810.30 365.63 187.20
431.87 493.56 555.26 462.71 815.70 368.75 188.80
434.51 496.58 558.66 465.55 821.10 371.88 190.40
437.15 499.60 562.05 468.38 826.50 375.00 192.00
439.24 501.98 564.73 470.61 831.90 378.13 193.60
441.32 504.36 567.41 472.84 837.30 381.25 195.20
443.40 506.74 570.09 475.07 842.70 384.38 196.80
445.48 509.12 572.76 477.30 848.10 387.50 198.40
447.57 511.50 575.44 479.54 853.50 390.63 200.00
449.65 513.88 578.12 481.76 858.90 393.75 201.60
451.73 516.26 580.80 484.00 864.30 396.88 203.20
453.81 518.64 583.47 486.23 869.70 400.00 204.80
455.90 521.02 586.15 488.46 875.10 403.13 206.40
457.98 523.40 588.83 490.69 880.50 406.25 208.00
460.06 525.78 591.51 492.92 885.90 409.38 209.60462.14 528.16 594.18 495.15 891.30 412.50 211.20
464.23 530.54 596.86 497.39 896.70 415.63 212.80
466.31 532.92 599.54 499.61 902.10 418.75 214.40
468.39 535.30 602.22 501.85 907.50 421.88 216.00
470.47 537.68 604.89 504.08 912.90 425.00 217.60
472.56 540.06 607.57 506.31 918.30 428.13 219.20
474.64 542.44 610.25 508.54 923.70 431.25 220.80
476.72 544.82 612.93 510.77 929.10 434.38 222.40
7/31/2019 Nagari to Mohazari Road 1
34/52
478.80 547.20 615.60 513.00 934.50 437.50 224.00
480.89 549.58 618.28 515.24 939.90 440.63 225.60
482.97 551.96 620.96 517.46 945.30 443.75 227.20
485.05 554.34 623.64 519.70 950.70 446.88 228.80
487.13 556.72 626.31 521.93 956.10 450.00 230.40
489.22 559.10 628.99 524.16 961.50 453.13 232.00
491.30 561.48 631.67 526.39 966.90 456.25 233.60493.38 563.86 634.35 528.62 972.30 459.38 235.20
495.46 566.24 637.02 530.85 977.70 462.50 236.80
497.55 568.62 639.70 533.09 983.10 465.63 238.40
499.63 571.00 642.38 535.31 988.50 468.75 240.00
501.71 573.38 645.06 537.55 993.90 471.88 241.60
503.79 575.76 647.73 539.78 999.30 475.00 243.20
505.88 578.14 650.41 542.01 1004.70 478.13 244.80
507.96 580.52 653.09 544.24 1010.10 481.25 246.40
510.04 582.90 655.77 546.47 1015.50 484.38 248.00
512.12 585.28 658.44 548.70 1020.90 487.50 249.60
514.21 587.66 661.12 550.94 1026.30 490.63 251.20
516.29 590.04 663.80 553.16 1031.70 493.75 252.80518.37 592.42 666.48 555.40 1037.10 496.88 254.40
520.45 594.80 669.15 557.63 1042.50 500.00 256.00
522.54 597.18 671.83 559.86 1047.90 503.13 257.60
524.62 599.56 674.51 562.09 1053.30 506.25 259.20
526.70 601.94 677.19 564.32 1058.70 509.38 260.80
528.78 604.32 679.86 566.55 1064.10 512.50 262.40
530.87 606.70 682.54 568.79 1069.50 515.63 264.00
532.95 609.08 685.22 571.01 1074.90 518.75 265.60
535.03 611.46 687.90 573.25 1080.30 521.88 267.20
537.11 613.84 690.57 575.48 1085.70 525.00 268.80
539.20 616.22 693.25 577.71 1091.10 528.13 270.40
541.28 618.60 695.93 579.94 1096.50 531.25 272.00
543.36 620.98 698.61 582.17 1101.90 534.38 273.60
545.44 623.36 701.28 584.40 1107.30 537.50 275.20
547.53 625.74 703.96 586.64 1112.70 540.63 276.80
549.61 628.12 706.64 588.86 1118.10 543.75 278.40
551.69 630.50 709.32 591.10 1123.50 546.88 280.00
553.77 632.88 711.99 593.33 1128.90 550.00 281.60
555.86 635.26 714.67 595.56 1134.30 553.13 283.20
557.94 637.64 717.35 597.79 1139.70 556.25 284.80
560.02 640.02 720.03 600.02 1145.10 559.38 286.40
562.10 642.40 722.70 602.25 1150.50 562.50 288.00
564.19 644.78 725.38 604.49 1155.90 565.63 289.60
566.27 647.16 728.06 606.71 1161.30 568.75 291.20
568.35 649.54 730.74 608.95 1166.70 571.88 292.80570.43 651.92 733.41 611.18 1172.10 575.00 294.40
572.52 654.30 736.09 613.41 1177.50 578.13 296.00
574.60 656.68 738.77 615.64 1182.90 581.25 297.60
576.68 659.06 741.45 617.87 1188.30 584.38 299.20
578.76 661.44 744.12 620.10 1193.70 587.50 300.80
580.85 663.82 746.80 622.34 1199.10 590.63 302.40
582.93 666.20 749.48 624.56 1204.50 593.75 304.00
585.01 668.58 752.16 626.80 1209.90 596.88 305.60
7/31/2019 Nagari to Mohazari Road 1
35/52
587.09 670.96 754.83 629.03 1215.30 600.00 307.20
589.18 673.34 757.51 631.26 1220.70 603.13 308.80
591.26 675.72 760.19 633.49 1226.10 606.25 310.40
593.34 678.10 762.87 635.72 1231.50 609.38 312.00
595.42 680.48 765.54 637.95 1236.90 612.50 313.60
597.51 682.86 768.22 640.19 1242.30 615.63 315.20
599.59 685.24 770.90 642.41 1247.70 618.75 316.80601.67 687.62 773.58 644.65 1253.10 621.88 318.40
603.75 690.00 776.25 646.88 1258.50 625.00 320.00
605.66 692.18 778.71 648.92 1263.90 628.13 321.60
607.57 694.36 781.16 650.96 1269.30 631.25 323.20
609.48 696.54 783.61 653.01 1274.70 634.38 324.80
611.38 698.72 786.06 655.05 1280.10 637.50 326.40
613.29 700.90 788.52 657.10 1285.50 640.63 328.00
615.20 703.08 790.97 659.14 1290.90 643.75 329.60
617.11 705.26 793.42 661.19 1296.30 646.88 331.20
619.01 707.44 795.87 663.23 1301.70 650.00 332.80
620.92 709.62 798.33 665.27 1307.10 653.13 334.40
622.83 711.80 800.78 667.31 1312.50 656.25 336.00624.74 713.98 803.23 669.36 1317.90 659.38 337.60
626.64 716.16 805.68 671.40 1323.30 662.50 339.20
628.55 718.34 808.14 673.45 1328.70 665.63 340.80
630.46 720.52 810.59 675.49 1334.10 668.75 342.40
632.37 722.70 813.04 677.54 1339.50 671.88 344.00
634.27 724.88 815.49 679.58 1344.90 675.00 345.60
636.18 727.06 817.95 681.62 1350.30 678.13 347.20
638.09 729.24 820.40 683.66 1355.70 681.25 348.80
640.00 731.42 822.85 685.71 1361.10 684.38 350.40
641.90 733.60 825.30 687.75 1366.50 687.50 352.00
643.81 735.78 827.76 689.80 1371.90 690.63 353.60
645.72 737.96 830.21 691.84 1377.30 693.75 355.20
647.63 740.14 832.66 693.89 1382.70 696.88 356.80
649.53 742.32 835.11 695.93 1388.10 700.00 358.40
651.44 744.50 837.57 697.97 1393.50 703.13 360.00
653.35 746.68 840.02 700.01 1398.90 706.25 361.60
655.26 748.86 842.47 702.06 1404.30 709.38 363.20
657.16 751.04 844.92 704.10 1409.70 712.50 364.80
659.07 753.22 847.38 706.15 1415.10 715.63 366.40
660.98 755.40 849.83 708.19 1420.50 718.75 368.00
662.89 757.58 852.28 710.24 1425.90 721.88 369.60
664.79 759.76 854.73 712.28 1431.30 725.00 371.20
666.70 761.94 857.19 714.32 1436.70 728.13 372.80
668.61 764.12 859.64 716.36 1442.10 731.25 374.40
670.52 766.30 862.09 718.41 1447.50 734.38 376.00672.42 768.48 864.54 720.45 1452.90 737.50 377.60
674.33 770.66 867.00 722.50 1458.30 740.63 379.20
676.24 772.84 869.45 724.54 1463.70 743.75 380.80
678.15 775.02 871.90 726.59 1469.10 746.88 382.40
680.05 777.20 874.35 728.63 1474.50 750.00 384.00
681.96 779.38 876.81 730.67 1479.90 753.13 385.60
683.87 781.56 879.26 732.71 1485.30 756.25 387.20
685.78 783.74 881.71 734.76 1490.70 759.38 388.80
7/31/2019 Nagari to Mohazari Road 1
36/52
687.68 785.92 884.16 736.80 1496.10 762.50 390.40
689.59 788.10 886.62 738.85 1501.50 765.63 392.00
691.50 790.28 889.07 740.89 1506.90 768.75 393.60
693.41 792.46 891.52 742.94 1512.30 771.88 395.20
695.31 794.64 893.97 744.98 1517.70 775.00 396.80
697.22 796.82 896.43 747.02 1523.10 778.13 398.40
699.13 799.00 898.88 749.06 1528.50 781.25 400.00701.04 801.18 901.33 751.11 1533.90 784.38 401.60
702.94 803.36 903.78 753.15 1539.30 787.50 403.20
704.85 805.54 906.24 755.20 1544.70 790.63 404.80
706.76 807.72 908.69 757.24 1550.10 793.75 406.40
708.67 809.90 911.14 759.29 1555.50 796.88 408.00
710.57 812.08 913.59 761.33 1560.90 800.00 409.60
712.48 814.26 916.05 763.37 1566.30 803.13 411.20
714.39 816.44 918.50 765.41 1571.70 806.25 412.80
716.30 818.62 920.95 767.46 1577.10 809.38 414.40
718.20 820.80 923.40 769.50 1582.50 812.50 416.00
720.11 822.98 925.86 771.55 1587.90 815.63 417.60
722.02 825.16 928.31 773.59 1593.30 818.75 419.20723.93 827.34 930.76 775.64 1598.70 821.88 420.80
725.83 829.52 933.21 777.68 1604.10 825.00 422.40
727.74 831.70 935.67 779.72 1609.50 828.13 424.00
729.65 833.88 938.12 781.76 1614.90 831.25 425.60
731.56 836.06 940.57 783.81 1620.30 834.38 427.20
733.46 838.24 943.02 785.85 1625.70 837.50 428.80
735.37 840.42 945.48 787.90 1631.10 840.63 430.40
737.28 842.60 947.93 789.94 1636.50 843.75 432.00
739.19 844.78 950.38 791.99 1641.90 846.88 433.60
741.09 846.96 952.83 794.03 1647.30 850.00 435.20
743.00 849.14 955.29 796.07 1652.70 853.13 436.80
744.91 851.32 957.74 798.11 1658.10 856.25 438.40
746.82 853.50 960.19 800.16 1663.50 859.38 440.00
748.72 855.68 962.64 802.20 1668.90 862.50 441.60
750.63 857.86 965.10 804.25 1674.30 865.63 443.20
752.54 860.04 967.55 806.29 1679.70 868.75 444.80
754.45 862.22 970.00 808.34 1685.10 871.88 446.40
756.35 864.40 972.45 810.38 1690.50 875.00 448.00
758.26 866.58 974.91 812.42 1695.90 878.13 449.60
760.17 868.76 977.36 814.46 1701.30 881.25 451.20
762.08 870.94 979.81 816.51 1706.70 884.38 452.80
763.98 873.12 982.26 818.55 1712.10 887.50 454.40
765.89 875.30 984.72 820.60 1717.50 890.63 456.00
767.80 877.48 987.17 822.64 1722.90 893.75 457.60
769.71 879.66 989.62 824.69 1728.30 896.88 459.20771.61 881.84 992.07 826.73 1733.70 900.00 460.80
773.52 884.02 994.53 828.77 1739.10 903.13 462.40
775.43 886.20 996.98 830.81 1744.50 906.25 464.00
777.34 888.38 999.43 832.86 1749.90 909.38 465.60
779.24 890.56 1001.88 834.90 1755.30 912.50 467.20
781.15 892.74 1004.34 836.95 1760.70 915.63 468.80
783.06 894.92 1006.79 838.99 1766.10 918.75 470.40
784.97 897.10 1009.24 841.04 1771.50 921.88 472.00
7/31/2019 Nagari to Mohazari Road 1
37/52
786.87 899.28 1011.69 843.08 1776.90 925.00 473.60
788.78 901.46 1014.15 845.12 1782.30 928.13 475.20
790.69 903.64 1016.60 847.16 1787.70 931.25 476.80
792.60 905.82 1019.05 849.21 1793.10 934.38 478.40
794.50 908.00 1021.50 851.25 1798.50 937.50 480.00
796.41 910.18 1023.96 853.30 1803.90 940.63 481.60
798.32 912.36 1026.41 855.34 1809.30 943.75 483.20800.23 914.54 1028.86 857.39 1814.70 946.88 484.80
802.13 916.72 1031.31 859.43 1820.10 950.00 486.40
804.04 918.90 1033.77 861.47 1825.50 953.13 488.00
805.95 921.08 1036.22 863.51 1830.90 956.25 489.60
7/31/2019 Nagari to Mohazari Road 1
38/52
Sr.No. Name of Material Approximately Quantity Unit Place of Delivery
to be supplied
In Figures In Words
1 2 3 4 5 6 7
All the materials mentioned are to
1 H.Y.S.D. Steel 4.742 Per Metric ----- ----- procured by contractor at his own
MT Tonne cost and risk from open market &
proof of purchase of materials sho
be submitted. All materials should
tested from P.W. Distt. Laboratory
2 Cement 43 Grade 349 Per Bag ----- ----- his own cost. RCC Pipes should
Bags purchase from MSSIDC only & bi
along with test result should be
submitted.
Assistant Engineer Gr. 1 Executive Engineer
P.W. Sub-Division No. 1, P.W. Division No. 1
Gadchiroli Gadchiroli
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part 1 Km 0/000 to 0/600 in Gadchiroli Taluka
Gadchiroli.
APPENDIX "A"
Rate of which the materials
will be charged to the Contractor
7/31/2019 Nagari to Mohazari Road 1
39/52
1 km off 220.000
Nagari Village Mohazari Village
204/400
Proposed
Road
Kathani River 195.200
Sand
madiya
Tukum
Murum &
Brick
Quarry 0.50 Km off
192.300
98/800 MSH - 7 Gadchiroli 108/600 112/400 126/000
To Dhanora
CB Metal upto plant Site -128.50 Km
CB Metal upto Indira Chowk -123.20 Km
Chamorshi 170.600
1) Certified that the quarries shown have good and sufficeint quantity of material available in it.
A E II Assistant Engineer Gr. 1
P.W. Sub-Division No. 1,
Gadchiroli
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part 1 Km 0/000
to 0/600 in Gadchiroli Taluka & Dist. Gadchiroli.
Quarry Chart
Dongargao
n
Crusher1.0
Km off
2) Certified that the route shown is shortes one.
7/31/2019 Nagari to Mohazari Road 1
40/52
Sr. Item of Work Quantity Unit Amount SpeNo. In Figures In Words in Rs.
1 Excavation for catch / side water gutter in
all sort of soils, soft murum etc. to the
specified section including stacking the
excavated stuff in regular bund and disposing
off unsuitable or excess stuff upto a lead of 50
m and spreading as directed Engineer-in-
charge.
356.00 105.50 Rs. Eigthy Nine & Paise Eigthy
Five Only.
One Cubic
Meter
37558.00 Rd.9/Pag
2 Laying, watering and compacting the
embankment formed of materials obtained
from the road cutting, breaking clods, dressing
to 3% camber design superelevation curve &
prescribed section for embankment within a
lead of 50 m, after laying them in layers of20cm to 30cm. with static roller etc. complete.
356.000 12.00 Rs. Thirteen & Paise Twenty
Only.
One Cubic
Meter
4272.00 Rd.13/Pa
Rd.16/Pa
3 Providing earthwork in embankment with
approved materials obtained from
departmental land or other sources including
all lifts, laying in layers of 20 cm. to 30 cm.
thickness breaking clods, dressing to the
required lines, curves, grade and section,
watering and compacting with power roller
complete.
1280.440 155.85 Rs. One Hundred Forty Two &
Paise Fifty Only.
One Cubic
Meter
199557.00 Rd.13/Pa
Name of Work:- Construction of Nagari to Mohazari road ( V.R. - 9 ) Part 1 Km 0/000 to 0/600 in Gadchiroli Taluka & D
Gadchiroli.
SCHEDULE "B" & "C"
Rate
7/31/2019 Nagari to Mohazari Road 1
41/52
Sr. Item of Work Quantity Unit Amount S
No. In Figures In Words in Rs.
Rate
4 Supplying trap/granite/quartzite/ gneiss
stone metal of required size by bringing
the boulders at the road side breaking them
to required gradation including conveying the
boulders and stacking the broken metal etc.
complete. (Prior approval of sample stack ofbroken metal by the Ex.Engineer is necessary,
the date of approval will form part of the
measurements
b) By Breaking boulder (Hand broken)
80 mm Metal385.040 695.75 Rs. Eigth Hundred Twenty Nine
& Paise Eigthy Only.
One Cubic
Meter
267892.00 Rd.19
No. 19
40 mm Metal175.020 723.35 Rs. Eigth Hundred Fifty Four &
Paise Ninty Five Only.
One Cubic
Meter
126601.00 Rd.19
No. 19
5 Supplying soft murum at the road side,
including conveying and stacking complete.
738.730 456.85 Rs. Three Hundred Eigthy Five
& Paise Eigthy Only.
One Cubic
Meter
337489.00 Rd.24
6 Supplying sand at the road side, includingconveying and stacking complete.
694.980 455.95 Rs. Four Hundred Forty One &Paise Ninty Five Only.
One CubicMeter
316876.00 Rd.25
7 Spreading gravel/sand/soft murum/
available murum over rubble soling/ W.B.M.
surface blanketing berms etc. complete.
1433.710 16.80 Rs. Thirteen & Paise Twenty
Only.
One Cubic
Meter
24086.00 Rd.28
8 Spreading 80 mm metal including sectioning
complete.
385.040 27.60 Rs. Twenty Two & Paise
Seventy Five Only.
One Cubic
Meter
10627.00 Rd.29
9 Spreading 40 mm metal including sectioning
complete.
175.020 24.00 Rs. Ninteen & Paise Seventy
Five Only.
One Cubic
Meter
4200.00 Rd.29
7/31/2019 Nagari to Mohazari Road 1
42/52
Sr. Item of Work Quantity Unit Amount S
No. In Figures In Words in Rs.
Rate
10 Compacting the hard murum / kankar of all
width (200 mm. loose) with Static roller
including necessary artificial watering
complete.
1925.220 8.40 Rs. Six & Paise Sixty Only. One Square
Meter
16172.00 Rd.38
11 Compacting the sub grade/gravel/ oversizemetal (200 mm loose) layers of all width
with static roller including necessary, labour,
materials and artificial watering complete.
1925.220 13.80 Rs. Eleven & Paise Forty Only. One SquareMeter
26568.00 Rd.32
12 Compacting the sub grade/gravel/ size
metal (100 mm loose) layers of all width
with static roller including necessary, labour,
materials and artificial watering complete.
1750.200 14.40 Rs. Eleven & Paise Forty Only. One Square
Meter
25203.00 Rd.35
13 Compacting the hard murum side widths
layerwise on each side with static roller
including necessary artificial wateringcomplete .
5250.600 3.60 Rs. Three & Paise Sixty Only. One Square
Meter
18902.00 Rd.40
14 Excavation for foundation in earth, soils of
all types, sand, gravel soft murum etc.
including shoring and strutting as necessary
and disposing off excavated stuff within lead
of 100 m as directed etc. complete
11.090 149.85 Rs. One Hundred Twenty Eigth
& Paise Twenty Only.
One Cubic
Meter
1663.00 BR.3/
15 Providing rubble filling of trap / granite /
quartzite / gneiss stones in foundation
including hand packing filling gravel / sand in
the voids etc. complete.
1.960 672.40 Rs. Eigth Hundred Seventy &
Paise Ninty Only.
One Cubic
Meter
1318.00 CD.1/
7/31/2019 Nagari to Mohazari Road 1
43/52
Sr. Item of Work Quantity Unit Amount S
No. In Figures In Words in Rs.
Rate
16 Providing and laying in situ cement concrete
of 1:4:8 proportion with trap / granite /
quartzite / gneiss metal in foundation
including necessary compacting and curing
complete. (Including plywood/ steel formwork)
The C.M. 1:3 plaster is considered forrendering uneven and honeycombed surface
only. Newly laid concrete shall be covered by
gunny bag, plastic, tarpaulin etc. (Wooden
centering/formwork will not be allowed).
1.310 3213.25 Rs. Three Thousand One
Hundred Fifty Nine & Paise Nil
Only.
One Cubic
Meter
4209.00 CD.3/
17 Providing and laying in situ cement concrete
of M-15 / 1:2:4 with trap / granite / quartzite
/ gneiss metal in face wall including
plywood/ steel formwork and steel centering,
compaction by vibrator, finishing uneven and
honeycombed surface with C.M.1:3 of
sufficient minimum thickness to give smooth
and even surface, filling joints with bitumen,
curing etc. complete. (Excluding cost ofreinforcement.) The C.M. 1:3 plaster is
considered for rendering uneven and
honeycombed surface only. Newly laid
concrete shall be covered by gunny bag,
plastic, tarpaulin etc. (Wooden
centering/formwork will not be allowed).
4.540 5325.55 Rs. Four Thousand Seven
Hundred Eigthy Nine & Paise