Project : City tower 9(G+ 4P+ 20 Typ) Residential Building Location : Plot No. 166+180/1+168+150/1/168+1 Client : H.H Sheik Humaid Bin Rashed Al Noaimi Consultant : M/s Canadian Consultant Kind Attention :ENG. MUSTHAFA Subject : Balance work for C1 & C2 Following are the balance work for the C1 and C2. You should finish and make ready for the testing and commissioning. Sl no: Work description 1 AC drainage in roof and ground floor 2 Water meter room drain 21-24 & 7 3 WC fixing 14 pieces in C1 and 1 piece in C2 4 Floor trap cover garbage room and meter room 5 Gate valve cover all floor balance 6 Flexible hose connection in C1 and C2 7 Bathtub and sink mixer 8 Meter room connection 9 Ac drainage height problem 10 Balcony drain fixing c1 and c2

Musthafa Letter

Embed Size (px)

DESCRIPTION

mustafa

Citation preview

Project : City tower 9(G+ 4P+ 20 Typ) Residential Building Location : Plot No. 166+180/1+168+150/1/168+1 Client : H.H Sheik Humaid Bin Rashed Al Noaimi Consultant : M/s Canadian Consultant

Kind Attention :ENG. MUSTHAFA Subject : Balance work for C1 & C2

Following are the balance work for the C1 and C2. You should finish and make ready for the testing and commissioning.Sl no:Work description

1AC drainage in roof and ground floor

2Water meter room drain 21-24 & 7

3WC fixing 14 pieces in C1 and 1 piece in C2

4Floor trap cover garbage room and meter room

5Gate valve cover all floor balance

6Flexible hose connection in C1 and C2

7Bathtub and sink mixer

8Meter room connection

9Ac drainage height problem

10Balcony drain fixing c1 and c2