Project : City tower 9(G+ 4P+ 20 Typ) Residential Building Location : Plot No. 166+180/1+168+150/1/168+1 Client : H.H Sheik Humaid Bin Rashed Al Noaimi Consultant : M/s Canadian Consultant
Kind Attention :ENG. MUSTHAFA Subject : Balance work for C1 & C2
Following are the balance work for the C1 and C2. You should finish and make ready for the testing and commissioning.Sl no:Work description
1AC drainage in roof and ground floor
2Water meter room drain 21-24 & 7
3WC fixing 14 pieces in C1 and 1 piece in C2
4Floor trap cover garbage room and meter room
5Gate valve cover all floor balance
6Flexible hose connection in C1 and C2
7Bathtub and sink mixer
8Meter room connection
9Ac drainage height problem
10Balcony drain fixing c1 and c2
This is for your information and take necessary action for this.Best regards Basil MohammedProject managerGolden empire for fire and gas system