30
Multiphase Metering and Well Rate Estimation Methods for Field Allocation Arne Morten Dahl (Statoil, DPN OMN KH PTC KRI) 2014-06-05

Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Embed Size (px)

Citation preview

Page 1: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Multiphase Metering and Well Rate Estimation Methods for Field Allocation Arne Morten Dahl (Statoil, DPN OMN KH PTC KRI)

2014-06-05

Page 2: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

2

Outline

• MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin

• Original metering philosophy and allocation principle

• Events and challenges

• Remedial actions and changes

• Status metering and allocation 2014

• Future challenges technologies / opportunities

2013-02-25

Page 3: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Kristin subsea infrastructure

6 x DEH flowlines,

7km to Kristin

Kristin Semi - processing

& gas export via ÅGT

Åsgard C

condensate export 4 production/

templates

2005 … 2009 …

Page 4: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Tyrihans subsea infrastructure

Classificati

on: Internal

2010-05-03

4 -

43km DEH flow-

line to Kristin

4 production/

GI templates

1 SRSWI template

(power from Kristin)

Gas injection/lift

flow-line from

Åsgard B

Kristin Semi - processing

& gas export via ÅGT

Åsgard C

condensate export

4 production/

GI templates 2005 … 2009 …

Page 5: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Metering

Classification: Internal 2011-05-20 5 - 2005 … 2009 2010 2011 2012 2013 2014 …

Liquid

processing

Gas export to Åsgard

Transport -> Kårstø

Gas lift

Tyrihans riser

FuelFlare

10"MPFM x2

Tyrihans Production wells

as

M

Fiscal standardM

Fiscal standard

Fuel gas fiscal meter (1,5 % std. vol)

wo od

gc

Flare gas fiscal meter (5,0 % std. vol)

Export gas fiscal meter (1,0 % mass)

Fiscal standard (1,5 % std. vol)

ss

ss

M

fm

fm

fm

Oil export to Åsgard C

Fuel for Tyrihans

SRSWI power

C

fm

Kristin platform

Inlet sep

ss

Well n

Test sep

M

M

Water treatmentFiscal standard

M

fm

ss

ss

Gas Processing

ss

Export oil fiscal meter (0,3 % std. vol)

Import gas fiscal meter (1,5 % std. vol)

fm

Gas lift

Tyrihans riserÅsgard B

Produced water to sea

fm

Tyrihans Gas Injection and Gas Liftgc

Tyrihans Gas Injection wells

C C

Well1

M C

C C

Gas lift

wells

MPFMPerformance

curve

Kristin wells

Well nWell1

CC

Tyrihans field

Kristin field

1x Flowline – 18", 43km

6x Flowlines – 10", 7km

Performance

curve

Performance

curve

wo

ow

M, D

Fiscal standard (1,0 % mass)

Page 6: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Tyrihans Topside and Subsea MPFM

Classification: Internal 2010-05-03 6 -

Subsea MPFM Topside MPFMs

2005 … 2009 2010 2011 2012 2013 2014 …

Page 7: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Main purposes of oil and gas allocation

• Fiscal allocation

− Ownership allocation, distribution of the income

• Oil and condensate mass

• Gas energy

• Production Management

− Detailed production monitoring and optimization

• Allocated production and injection volumes for individual wells

• Reservoir Management

− Reservoir simulation model history matching

• Allocated production and injection volumes for individual wells

7

Page 8: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Original Allocation principle: Kristin as balance field (Kristin by difference – KBD)

8 2005 … 2009 2010 2011 2012 2013 2014 …

Gas and Condensate Metering

Difference

Tyrihans allocated volume

Kristin allocated volume

Tyrihans mass/ volume

Volume to mass

Volume to mass

Tyrihans allocated mass

Kristin allocated mass

Fuel and Flare allocation

Fuel and Flare Metering

Oil recovery factors

Tyrihans TopsideMPFM

QC

TYR = 80% of total production

Page 9: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Allocation factor = Allocated volume/theoretical volume Tyrihans start-up

2005 … 2009 2010 2011 2012 2013 2014 …

Page 10: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Troubleshooting Allocation System

The original field allocation system does not reproduce the results from field tests.

Main issues seem to be:

Test separator readings high compared to export rates

Topside MPFM mass correction is not linear as a function of rate under calibration

Unable to calibrate topside MPFMs against the test separator at normal operational

conditions

Problem with gas measurements at high rates

Allocation principle with Kristin as balance field

2005 … 2009 2010 2011 2012 2013 2014 …

Page 11: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Multi phase flow meter calibration principle

TEST SEPARATOR

MU

LT

IPH

AS

E M

ET

ER

5000 Sm3/d

4000 Sm3/d

5000 Sm3/d

CALIBRATION AGAINST TEST SEPARATOR

Ko = 1.25

4000 Sm3/d

UNCORRECTED MULTIPHASE METER

CO

RR

EC

TE

D M

ULT

IPH

AS

E M

ET

ER

MULTIPHASE METER AT NORMAL OPERATION

8000 Sm3/d

10000 Sm3/d

2000 Sm3/d

1000 Sm3/d

NORMAL OPERATION

4000 Sm3/d

5000 Sm3/d

2005 … 2009 2010 2011 2012 2013 2014 …

Page 12: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Multi phase flow meter calibration principle

TEST SEPARATOR

MU

LT

IPH

AS

E M

ET

ER

5000 Sm3/d

4000 Sm3/d

5000 Sm3/d

CALIBRATION AGAINST TEST SEPARATOR

Ko = 1.25

4000 Sm3/d

UNCORRECTED MULTIPHASE METER

CO

RR

EC

TE

D M

ULT

IPH

AS

E M

ET

ER

MULTIPHASE METER AT NORMAL OPERATION

8000 Sm3/d

NORMAL OPERATION

5000 Sm3/d

FIELD TEST

10000 Sm3/d

8600 Sm3/d

2005 … 2009 2010 2011 2012 2013 2014 …

Page 13: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

New allocation method: 1) Subsea HC mass, 2) ProRata principle

13 2005 … 2009 2010 2011 2012 2013 2014 …

Gas and Condensate Metering

SUM

Kristin mass/ volume

SPLITPRO RATA (oil)

By difference (gas)

Tyrihans allocated volume

Kristin allocated volume

Imbalance

Tyrihans mass/ volume

Kristin Performance

curves

Volume to mass

Volume to mass

Tyrihans allocated mass

Kristin allocated mass

Fuel and Flare allocation

Fuel and Flare Metering

Tyrihans Performance

curves

Kristin SEMI HC production

Test separator metering

Update of Tyrihans performance curves

Oil recovery factors

Gas Export, Condensate Export, Fuel, Flare and

Lift Gas Metering

Tyrihans Subsea MPFM

QC QC

QC

Page 14: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Allocation quality control

• Kristin Flowline tests Campaign (KFC) –> Tyrihans by Difference (TBD)

• Topside MPFM “calibration”

− Topside MPFM rates with updated correction factors, trends

• Sum Tyrihans subsea MPFM and PC theoretical rates, trends

• Sum Kristin PC theoretical rates, trends

• Allocation factors

• Expected allocation results

− Kristin GOR from history matched reservoir simulations

• Single field tests

− Shut down one field, produce the other field through topside process fiscal

metering

14 2005 … 2009 2010 2011 2012 2013 2014 …

Page 15: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Allocation factors 2011

2005 … 2009 2010 2011 2012 2013 2014 …

Page 16: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Summary: Challenges in Kristin-Tyrihans Allocation

• Tyrihans topside multiphase flow meters (MPFM) disqualified for allocation

− Cannot be calibrated against test separator at normal operating conditions due to test

separator rate limitation

− Can be corrected against result for Tyrihans from Kristin Flowline tests (KFC) but

limited validity

• Sum Tyrihans subsea multiphase flow meters: backup method

− One or more subsea multiphase flow meters not in working order (backup for backup!)

• Extensive use of well performance curves (PC) both on Kristin (by design) and Tyrihans

(backup for subsea MPFMs)

• Single field tests that require shut-down of either Kristin or Tyrihans are costly and do not

show the mixing effect of the two fields.

• Field allocation requires extensive monitoring and follow-up

• Allocation accuracy dependent on test separator performance (availability, accuracy…..)

16 2005 … 2009 2010 2011 2012 2013 2014 …

Page 17: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Future challenges / concerns

• Replacing existing subsea MPFMs (present vendor)

− Long delivery time, dependent on available choke modules

− Reliability (will they fail again?)

• Low pressure production (LPP) from 2014

− Change in topside process conditions (PVT, ORF-factors, etc.)

− Test separator capacity change

− Performance of subsea MPFM change under LPP conditions?

• Topside MPFM – GVF approaching 95% (reduced accuracy, reduced validity of corrections

factors…..)

• Possible additional 3rd party tie-ins

− Change in metering philosophy

− Change in allocation procedure

− Change in topside process conditions (PVT, ORF-factors, etc.)

2013-02-25 17 2005 … 2009 2010 2011 2012 2013 2014 …

Page 18: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Future technologies / opportunities

• Virtual metering

− Replace direct measurements by

indirect analysis and modelling

− Replace/complement MPFMs

− «Model based allocation».

Calculations based on online data

model of the subsea system,

updating based on sensor changes

2013-02-25 18 2005 … 2009 2010 2011 2012 2013 2014 …

Figure: ©FMC

Page 19: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Tyrihans VM case

• Many parameters are measured in Tyrihans

production system

− WHP, WHT, USCP, USCT, DSCP, DSCT,

DHP, DHT, DHP1, DHP2, etc.

• Topside at Kristin Semi some important

parameters are also measured

− Corrected topside MPFM rates, KFC

rates, total Tyrihans fluid densities

• Use all this measured data to provide estimates

on well rates

• VM is a collection of mathematical models to

estimate well rates accounting for most

available data

• iVM is the software tool where the VM problem

is solved and where the results are presented

19

DHP1 DHP2

WHP1 WHP2

USCP2 USCP1

DSCP1 DSCP2

QoT

QgT

QwT

Qo1?

Qg1?

Qw1?

Qo2?

Qg2?

Qw2?

Well 1 Well 2

Flowline

Topside

2005 … 2009 2010 2011 2012 2013 2014 …

Page 20: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Petex iVM field overview

2013-02-25 20 2005 … 2009 2010 2011 2012 2013 2014 …

Figure: ©Petroleum Experts

Page 21: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

iVM rate estimation techniques

2013-02-25 21 2005 … 2009 2010 2011 2012 2013 2014 …

Figure: ©Petroleum Experts

If model predictions start to deviate:

- Well behaviour has changed (GOR, WC, PI etc.)

- Update model parameter constraints/initial values accordingly

Increasing # of models predicting same rate

- More confidence this is the correct rate

Page 22: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Current status / experience Tyrihans iVM

• System installed late 2013

• Q1-2014

− QC / troubleshooting software, models,

model updating, data transfer and system

stability

− System currently running continuously

updating results

• Q2-2014

− Further QC and software improvements

− Implement writing iVM rates to production

database (EC)

• Enables IVM rates available for input

to allocation, replacing performance

curves / subsea MPFM where

applicable

2013-02-25 22 2005 … 2009 2010 2011 2012 2013 2014 …

Page 23: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

23

Multiphase Metering and Well Rate

Estimation Methods for Field Allocation

Arne M. Dahl

Principal Engineer Prod Tech,

Kristin Petek

KH PTC KRI

[email protected]

Tel: +4792660405 www.statoil.com

2013-02-25

Acknowledgements:

• Trygve Kløv

• Kurt Haugnæss

• Even Lillemo

• Yngve H. Belsvik

• Kolbjørn Kyllo

(all Statoil)

Page 24: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Backup slides

2013-02-25 24

Page 25: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Allocation input and sources

• TYH HC mass

− TYH total mass (Subsea MPFM and Performance Curves)

− TYH total water mass fraction (Test separator)

• PVT

− TYH total HC composition (GOR) (“KFC” – KRI flowline separator tests)

− TYH total HC molecular weight pr component (Recombined PVT-samples)

− Tyrihans gas molecular weight (ISO 6976)

− Oil recovery factors (ORF) (Hysys process simulation)

− Tyrihans oil density (Hysys process simulation)

− Kristin condensate density (Hysys process simulation)

• Well rate estimates

− Kristin theoretical condensate volume (Performance Curves, “KFC” – KRI flowline separator tests)

− Tyrihans theoretical oil volume (Subsea MPFM and Performance Curves)

• Fiscal metering

− Total export oil and condensate (Fiscal export meters)

− Total export, fuel and flare gas (Fiscal export meters)

25 2005 … 2009 2010 2011 2012 2013 2014 …

Page 26: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

PVT sampling KRI/TYH Basis for ORF-calculations and allocation

• Process simulations (ORF update)

• Sampling of TYH mixed well stream +

condensate & export gas

− When necessary due to fluid changes

(new wells, wells shut down etc.)

− Approx. every three months

• Annual sampling of KRI wells / flowlines

• Reallocation is performed when ORF is

updated

26

Januar

April

Juli

Oktober

November

Desember

September

August

Juni

Mai

Mars

Februar

Page 27: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Allocation workflow

TFT KFC Tyrihans by difference

Pro rata period TFT KFC

27

TFT = Tyrihans Flowline Tests

KFC = Kristin Flowline Tests Campaign

• Tyrihans total water mass fraction based on TFT

• Kristin production based on KFC

• «Tyrihans by difference» (one production day)

• Tyrihans production based on total production and KFC/TFT

• Tyrihans GOR and WCT determined

• «Pro rata period» (normally 14+ days)

• Based on latest «Tyrihans by difference»

• Pro-rata principle to compensate for Tyrihans GOR/WCT development and Kristin

depletion effects (not captured by performance curves)

• Tyrihans GOR (total HC composition) adjusted if necessary (observed trends)

• After next TFT and KFC;

• Previous «pro rata period» adjusted based on new test results

Cont.

Input Adjustment Input

2005 … 2009 2010 2011 2012 2013 2014 …

Page 28: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Future technologies / opportunities

• Install new subsea MPFMs (new

vendor)

− Long delivery time, need

mechanical fitting, cost

− Increased subsea power

requirement

• Subsea PVT sampling (Mirmorax)

− Representative fluid sampling per

well, input to PVT for MPFM

calibration / allocation

− Need mechanical modifications

2013-02-25 28 2005 … 2009 2010 2011 2012 2013 2014 …

Figure: ©Mirmorax

Figure: ©FMC

Page 29: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Future technologies / opportunities

• Multi-diciplinary integrated modelling

− Integration of Reservoir simulation

to Topside process simulations for

history matching and future

forecast of ORF

• Possibility for more frequent

update of ORF calculations by

utilizing input from reservoir

simulations

• Possibility for less frequent

update of ORF based on Lab

sample measurements due to

knowledge of future

development

2013-02-25 29 2005 … 2009 2010 2011 2012 2013 2014 …

Figure: ©Petrostreamz

Page 30: Multiphase Metering and Well Rate Estimation Methods … Outline •MPFM for field allocation, introduced by tie-in of Tyrihans to Kristin •Original metering philosophy and allocation

Tyrihans virtual metering case

• For Tyrihans the following applies:

− The Tyrihans field was developed with limited metering flexibility

− No access to the test separator for individual wells

− Subsea multiphase flow meters (MPFMs) failing

− Calibration of subsea MPFMs against measured data not possible

− Accuracy of uncalibrated subsea MPFMs is questionable

• PVT - liquid and gas density has changed since installation

• Additional corrections due to drifting and change in meter behavior

• Virtual metering (VM) techniques can provide estimates for well rates that are not

measured or inaccurately measured

• The confidence in virtually metered rates should be higher than any other type of

estimates

2013-02-25 30

2005 … 2009 2010 2011 2012 2013 2014 …