DEMO 2MULTI-VENDOR INTEROPERABILITY FOR VSC-BASED HVDC SYSTEMS
“INNOVATIVE NETWORK TECHNOLOGIES AND THE FUTURE OF EUROPE'S ELECTRICITY GRID” BEST PATHS DISSEMINATION WORKSHOPPARIS, 5 NOVEMBER 2015
Claude COUNAN
RTE
16 November 2015
2
Scope of BestPaths Demo2 : Multi-vendor interoperability for VSC-based HVDC systems
The development of HVDC systems will be : gradual, growing by connecting step by step equipments from different
manufacturers
The interoperability of these equipments is a key issue for DC grids
DEMO 2 : OVERVIEW
+ ?
3
Targets
Explore interoperability conditions for multivendor HVDC systems toward DCgrids based on recent VSC converters.
Interoperability assessment performed on a wide variety of situations(combinations of DC topologies, AC connections, control modes, etc.) and fordifferent conditions (normal operation, fault conditions, special sequences).
Recommendations for standardization bodies and stakeholders of future DCG
DEMO 2 : OVERVIEW
4
Demo 2 partners :
TSOs to define the operational requirements of HVDC systems
Manufacturers to bring there best industrial solutions
Academic to contribute to interoperability studies
In very precise (and tricky!) IP conditions and rules
All partners to bring progress and build the conclusions
DEMO 2 : OVERVIEW
SIEMENS SIEMENS SIEMENS ALSTOM ALSTOM ALSTOM
ABB ABB ABB
DEMO 2 : EXPECTED RESULTS & IMPACT
5
Expected results
To define the driving conditions of safe interoperability of multivendorequipments on a HVDC grid
To develop a two-stage Interoperability assessment process :
EMT simulation using manufacturers models for converters (EMTP-RV)
Real-time simulations with actual control replicas provided by vendors (Hypersim)
…That could be used in a real HVDC grid development process
Recommendations for standardization bodies and stakeholders of future DC Grids
DEMO 2 : ACTIVITIES
6
HVDC Grids simulations
Definition of the combinations of Grid topologies DC, AC and operation conditions (normal operation, fault conditions, special sequences).
Off-line simulations with manufacturers AC/DC converters models ; Specifications for AC/DC converter control system replicas : WP 4
On-line (Hardware in the loop) simulations with AC/DC converters control system replicas provided by the manufactures: WP9
For both offline and real-time simulations
Only for offline simulations
As an option (offline simulation)
Demo 2: Status
After 1st year of activity
1ST GENERAL ASSEMBLY, 4 NOVEMBER 2015
7
Organization of Demo #2: Work Packages & tasks + current status
(i) Network topologies & functional specifications (Task 4.1)……………
(ii) Adaptation & validation of VSC EMTP models (Task 4.2)
(iii) EMTP models for network topologies (Task 4.3)
(iv) EMTP simulations: converters & topologies (Task 4.4)…………………
(v) Recommendations for interface specifications (Task 4.5) ……………
(vi) Specifications of the improved hardware HVDC Ctl (Task 9.1)………
(vii) Physical implementation in replicas (Task 9.2) ……………………………
(viii) Adaptation / extension of RTE’s RT facility (Task 9.3)
(ix) Installation / commissioning of replicas (Task 9.4)
(x) Test and demonstration of the coupled replicas (Task 9.5)……………
(xi) Final recommendations (Task 9.6) …………………………………………………
WP 4
WP 9
Work in progress
Implementation of topologies T1 to T5 for future offline interoperability tests
A combinatory issue:
Trade-off between the widest coverage and a pragmatic approach
Demo #2: Results
After 1st year of activity
1ST GENERAL ASSEMBLY, 4 NOVEMBER 2015
8
From the simplesttopology
To more than 200 AC/DC
configurations
Distributed over dozens of possible
scenarios
Demo 2: Outlook
Future activities and expected impacts
1ST GENERAL ASSEMBLY, 4 NOVEMBER 2015
9
WP 4
WP 9
Program of second year and next steps
Task 4.2: Adaptation & validation of VSC EMTP models………………… by Dec. 2015
Task 4.3: EMTP models for network topologies……………………………… by Dec. 2015
Task 4.4: EMTP simulations: converters & topologies…………………… by April 2016
Task 4.5: Recommendations for interface specifications…………………by Sept. 2016
Task 9.1: Specifications of the improved hardware HVDC Ctl …………by June 2016
CONTACT
10
www.bestpaths-project.euFollow us on Twitter: @BestPaths_eu
Demo 2: Outlook
Thank you for your attention!
1ST GENERAL ASSEMBLY, 4 NOVEMBER 2015
11
Results achieved
Generic converter model (EMTP-RV) to support Tasks 4.2 and 4.3
“By-product” rather than an expected outcome
Guarantee some homogeneity in EMTP co-development (by 7 partners)
Demo 2: Results
After 1st year of activity
1ST GENERAL ASSEMBLY, 4 NOVEMBER 2015
12
Template for convertermodels provided byvendors:provision of commoninterface.
A common “buildingbrick”:Example of simple HVDCconfiguration
Topologies 1 to 5:Making easier theimplementation oftopologies, situationsand scenarios.
Validation tests 1 to 39:Making easier theimplementation of thetests.