9
Frankfurt (Germany), 6-9 June 2011 M.Sc. Terje Pynten, Dr. Jan Andor Foosnæs, M.Sc. Johan G Hernes, M.Sc. Erling Tønne NTE Nett AS Paper 0696 Finding maintenance project to priority

M.Sc . Terje Pynten, Dr. Jan Andor Foosnæs, M.Sc . Johan G Hernes, M.Sc . Erling Tønne

  • Upload
    wyome

  • View
    44

  • Download
    0

Embed Size (px)

DESCRIPTION

Finding maintenance project to priority. M.Sc . Terje Pynten, Dr. Jan Andor Foosnæs, M.Sc . Johan G Hernes, M.Sc . Erling Tønne NTE Nett AS Paper 0696. Ageing of the power system. Installed MV lines per year. Presumptions : - PowerPoint PPT Presentation

Citation preview

Page 1: M.Sc . Terje Pynten,  Dr. Jan Andor Foosnæs, M.Sc . Johan G Hernes,  M.Sc . Erling Tønne

Frankfurt (Germany), 6-9 June 2011

M.Sc. Terje Pynten, Dr. Jan Andor Foosnæs,M.Sc. Johan G Hernes, M.Sc. Erling Tønne

NTE Nett AS

Paper 0696

Finding maintenance project to priority

Page 2: M.Sc . Terje Pynten,  Dr. Jan Andor Foosnæs, M.Sc . Johan G Hernes,  M.Sc . Erling Tønne

Frankfurt (Germany), 6-9 June 2011

Ageing of the power system

Presumptions: Lifespan of lines ~ 40 år NTE Nett AS must replace 108 km/year. Lines are replaced 1:1 This is a 400 % increase from today.

0

20

40

60

80

100

120

140

160

180

1965 1970 1975 1980 1985 1990 1995 2000 2005 2010

Year

Km

/ Ye

ar

Installed MV lines per year

Page 3: M.Sc . Terje Pynten,  Dr. Jan Andor Foosnæs, M.Sc . Johan G Hernes,  M.Sc . Erling Tønne

Frankfurt (Germany), 6-9 June 2011

Wide and sparsely populated area

0102030405060708090

100110

1 11 21 31 41 51 61 71 81 91

Number of costumers per transformer

Dis

trib

utio

n tr

ansf

orm

ers

(%)

80 % of the transformers supplies less than 17 customers. Approximately 19 customers per km MV line.

Number of customers per transformer(cumulative distribution)

Page 4: M.Sc . Terje Pynten,  Dr. Jan Andor Foosnæs, M.Sc . Johan G Hernes,  M.Sc . Erling Tønne

Frankfurt (Germany), 6-9 June 2011

Efficiency The annual income cap does not give good enough incentives to do

reinvestments. The network companies must be able to build more MV lines per

Euro.

Simplifying the grid structure. New technologies and new solutions Choosing the right projects and implementing them in the optimum

order. Effective data acqusition and processing with quality and accuracy.

Page 5: M.Sc . Terje Pynten,  Dr. Jan Andor Foosnæs, M.Sc . Johan G Hernes,  M.Sc . Erling Tønne

Frankfurt (Germany), 6-9 June 2011

New technologies – new solutions New and improved building material

Reducing construction, maintenance and operation costs

New solutions Reduced operational costs More optimal usage of grid capacity / increased control of the

power flow Improved state estimation Extended life span in parts of the network

Page 6: M.Sc . Terje Pynten,  Dr. Jan Andor Foosnæs, M.Sc . Johan G Hernes,  M.Sc . Erling Tønne

Frankfurt (Germany), 6-9 June 2011

Priority process

Typical parameters in the assessment

process

Safety of supply Regulatory requirements

Terms of concession

Condition monitoring and inspections

Fault and interruption statistics

Technical state / indicators

Technical calculation / LCC

Experience and local knowledge

Climatic and environmental factors

Maintenance friendliness Load compositionNew technology

Costs of energy not supplied AestheticsAge

Regulation of revenue

Framework

Basis for decision making

Technical and economic analyses

Analysis methodology

Preventive maintenance

Renewal / Reinvestments

DecisionsExpected corrective

maintenance

Criteria:- HSE- Technical- Risk

Page 7: M.Sc . Terje Pynten,  Dr. Jan Andor Foosnæs, M.Sc . Johan G Hernes,  M.Sc . Erling Tønne

Frankfurt (Germany), 6-9 June 2011

Data acquisitionPresent: • Manual data acquisition/state

estimation. • External resources are used.• Large variation in data quality

(experience, character references and accuracy).

Future:• Smart technology (automatic

data acquisition)• New methods

Photo of a rotten traverse taken from a helicopter

Page 8: M.Sc . Terje Pynten,  Dr. Jan Andor Foosnæs, M.Sc . Johan G Hernes,  M.Sc . Erling Tønne

Frankfurt (Germany), 6-9 June 2011

Smartgrid pilot in Steinkjer NTE in partnership with The Norwegian Smartgrid Centre.

Main scope: To gain knowledge and practical experience by using smartgrid

technologies to operate the energy system more effectively regarding:

Economy System reliability Quality of delivery Occupational health and safety Environment, aesthetics

Page 9: M.Sc . Terje Pynten,  Dr. Jan Andor Foosnæs, M.Sc . Johan G Hernes,  M.Sc . Erling Tønne

Frankfurt (Germany), 6-9 June 2011

Smartgrid pilot in Steinkjer - Location

772 customer og 30 substations