Upload
qzm74l
View
217
Download
0
Embed Size (px)
Citation preview
8/13/2019 MRP3
1/6
S.F.T. I nc.
A Preliminary Definition for M.R.P. III
(if you are not using a NETSCAPE-compatible browser, this page may appear poorly formatted)
Table of Contents
Introduction
The Development of M.R.P.
From M.R.P. to M.R.P. II
Defining an M.R.P. III Process
How theDemand Planning Tool Helps to Implement M.R.P. III
Introduction
Material Requirements Planning, or M.R.P., has been officially around since the 1960's, with
the advent of the use of computers in the manufacturing environment, though the basic
principles involved in M.R.P. are an integral part of the manufacturing process itself.
However, by defining what 'M.R.P.' is, companies and software vendors are able to adapt a
standardized set of methods by which they can schedule delivery of raw materials against the
manfacturing schedule, thus keeping their assembly lines moving while at the same time
minimizing the amount of inventory on-hand.
The ideal adaptation of the M.R.P. process has, in the past, been considered to be a 'just in
time' scenario, when raw materials arrive just as they are required on the assembly line.
Obviously, a system like this has the potential of being thrown 'out of balance' by even the
slightest problems; therefore, manufacturers build in 'safety stock' or 'lead time' factors to
prevent material shortages from ever causing a 'line stop'. But safety stock and long lead
times increase on-hand inventory, requiring larger warehouses to store raw materials, or even
work in process, with no immediate benefit. Plus, it ties up the company's liquid capital in
non-liquid inventory, which typically depreciates, gets damaged, spoils, and/or becomes
obsolete within a relatively short period of time.
Obviously, there is a 'happy medium' somewhere in between a true 'just in time' system,where a single late or missing delivery can have drastic consequences, and a 'just in case'
system, where piece part inventories 'turn' slowly, and often become wasted as obsolete
inventory or spoilage. Somehow we must find the best inventory position, where the potential
for material shortages is well-balanced with the need to minimize on-hand inventories, and
minimize lead times. Finding this balance point, however, has never been a traditional
component in an M.R.P. system, or even an 'M.R.P. II' system.
UsingBandwidth Managementit is possible to establish such a balance, between a
minimum inventory on-hand and a consistently operating assembly line; therefore, we at
S.F.T., Inc. propose to define the requirements for an 'M.R.P. III' system, which (among otherthings) includes the principles ofBandwidth Managementas an integral component of the
http://www.mrp3.com/dpt.htmlhttp://www.mrp3.com/bndwmgmt.htmlhttp://www.mrp3.com/bndwmgmt.htmlhttp://www.mrp3.com/bndwmgmt.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/mrp3.htmlhttp://www.mrp3.com/bndwmgmt.htmlhttp://www.mrp3.com/dpt.html8/13/2019 MRP3
2/6
process, as well as a 'Whole Business Planning' feedback loop to minimize the impact of an
improper demand forecast on obsolete and excess inventory, plant capacity, and customer
lead times.
The Development of M.R.P.
M.R.P. began as a relatively simple, yet important analysis of manufacturing processes and
production schedules, combined with bills of material and/or resources, to predict what the
requirements would be for various components and/or manufacturing processes in order to
meet the current master schedule. In addition, M.R.P. applies component and process lead
times to these requirements, along with various other "modifiers" (economic order quantities,
safety stock, shrink factors, and so on) to generate recommended build schedules for non-
master scheduled assemblies, and recommended purchasing orders for components. Existing
schedules are not modified by a 'standard M.R.P.' process, though reports that makerecommendations to re-schedule or cancel existing build schedules or purchase orders may be
included in a 'standard M.R.P.' system. In essence, the 'M.R.P.' system merely performs an
analysis of existing conditions, and reports back to you what the requirements are, and
optionally recommends changes to existing purchase and production schedules to meet the
requirements of the master schedule.
It has been my experience that a 'standard M.R.P.' package, when properly implemented, will
meet the needs of most customers that have consistent production schedules, adequate
resources for the 'critical paths' in the manufacturing process, and adequate delivery
performance by vendors for the various component parts. However, in most cases, the M.R.P.
system doesn't seem to work so well. Either the component deliveries are consistently not ontime, or the master schedule is constantly being changed, resulting in wildly fluctuating
parameters. Typically, to make up for such conditions, safety stock limits will be increased
until the warehouses are full of 'just in case' inventory. Eventually, design changes in finished
product cause a lot of this inventory to become 'obsolete', or require some kind of retrofit in
order to be usable again. This costs money. Further, in the electronics manufacturing
industry, component prices typically go DOWN over time, such that a warehouse full of old
inventory will ultimately increase the cost of manufacturing a product above that of the
competition, since the actual cost of components will be higher when purchased several
weeks or months in advance.
8/13/2019 MRP3
3/6
From M.R.P. to M.R.P. II
To assist planners in tracking some of the problems associated with inventory control, some
kind of 'feedback loop' is needed in the M.R.P. process, not only to automatically re-schedule
certain items (when possible), and avoid excessive manual effort in controlling the process,
but to detect and report performance that is 'out of spec' (such as a vendor performance report
to track on-time delivery performance). This 'feedback loop' is the defining factor for an
'M.R.P. II' system. Though many systems CLAIMto be an 'M.R.P. II' system, few actually
fit the mold exactly. Still, with automatic rescheduling capabilities for work orders and/or
repetitive build schedules, and 'reschedule action' reports for purchase orders and outsidecontracting, the amount of actual analysis is reduced significantly. Other information, such as
vender performance reports and process utilization reports, also help to measure the
'performance to plan' capability of the manufacturing plant.
Even when the production plan is running at optimum performance, companies still often
have serious problems with the manufacturing process. 'Hidden Cost' issues associated with
manufacturing increase the total cost of manufacturing, but are extremely hard to track. Some
of these 'Hidden Costs' can be caused by excessive P.O. rescheduling or excessive 'crash buy'
programs, excess and/or obsolete inventory, or planning problems that cause incorrectly
stocked finished goods (too much of one, not enough of the other) that result in shortages.
Another 'hidden cost' issue might be frequent line stops related to a 'limiting process' (such asa wave solder machine or component inserter), as well as material shortages and excessive
8/13/2019 MRP3
4/6
'kitting' of common components. In addition, potential revenue losses from excessively long
customer order lead times, or poor on-time customer delivery performance, are real problems,
but very difficult to track and measure. As such, none of these problems are tracked nor
reported by any 'standard M.R.P.' or 'M.R.P. II' system. To help solve these problems, and
improve the company's competiveness and profitability, beyond existing capabilities, the
M.R.P. system must go beyond the standard definition of 'M.R.P. II', into what we at S.F.T.Inc. refer to as 'M.R.P. III'.
Defining an M.R.P. III Process
We at S.F.T. Inc. therefore propose to define a 'whole business' M.R.P. process that goes
beyond simple component/assembly relationships, that goes beyond resource requirements,
that goes beyond vendor performance and component shrink factors and safety stocks. The
'M.R.P. III' process begins with anAccurate Demand Forecast,for it is this Demand
Forecast that drives the remainder of the business. Using the best possible demand forecast, aMaster Scheduleis developed. Ideally the total number of master scheduled items will be
minimized, so that the M.R.P. system can appropriately generate build schedules for
components and 'accessories' automatically, and will be derived directly from the Demand
Forecast with little or no changes.
From theMaster Schedule, the 'M.R.P. III' system derives the individual component and
assembly requirements, and recommends new purchase orders, just like a 'standard M.R.P.'
system, and also generates recommended purchase order reschedules, and automatically
reschedules non-master scheduled assemblies based on the availability of
components/resources and material requirements, just like an 'M.R.P. II' system. The M.R.P.
III system also monitors and reports vendor performance and 'performance to plan' by theassembly line, similar to an 'M.R.P. II' system. However, to minimize the total amount of
http://www.mrp3.com/dptapic3.htmlhttp://www.mrp3.com/dptapic3.htmlhttp://www.mrp3.com/dptapic3.htmlhttp://www.mrp3.com/dptapic3.html8/13/2019 MRP3
5/6
'detail information', the 'M.R.P. III' system concentrates on only reporting those items that fall
outside of the allowed tolerances, thus minimizing the number of reported items.
When the M.R.P. system has been fully integrated with the Order Management system, it
becomes possible to calculate 'Available to Promise' inventory, based on a combination of
existing order backlog, the current inventory, and the projected availability of a product overtime as it is built from the current production schedule. In this way, if a customer orders a
product within lead time, and delivery is already promised to another customer, order
management personnel can use this information to negotiate a realistic delivery schedule with
the customer. Also, delivery re-schedules would become easier to manage, since order
management personnel can view the current 'available to promise' inventory, and use this
information to determine when partial or full shipments could be re-scheduled. In all
likelihood, there will be available inventory to ship ahead of schedule, should the customer
need to perform a 'crash buy'. An 'M.R.P. III' system must therefore include the ability to
view the 'available to promise' inventory, based on current inventory, current backlog, and the
current production plan.
Finally, the 'M.R.P. III' system bases its operating parameters on the principles ofBandwidth
Management,dynamically adjusting parameters such as lead times and 'ideal inventory'
according to the historic data (when needed), and measuring performance to a set of
statistically derived 'control bands', rather than fixed parameters. The 'M.R.P. III' system then
generates exception reports for those items that fall outside of the control bands, and
automatically maintains as much of the manufacturing planning process as possible, with
little or no human intervention.
A process such as 'M.R.P. III' would help to eliminate certain kinds of errors that currently
plague manufacturing businesses on a nearly universal level. By far, the greatest single factor
in ruining a perfectly good manufacturing plan is the tendency for the Demand Forecast to
change on a regular basis, typically inside planning lead time. Or, the Demand Forecast may
be completely useless for manufacturing purposes, forcing the person responsible for the
master schedule to literally generate his own forecast in an attempt to predict what the
demand actually will be. Often times, a combination of both of these conditions exists, where
the marketing forecast is so inaccurate as to make it useless, forcing the master scheduler to
perform this task of generating a forecast. And, without some kind of forecast, there is no
master schedule. And, without a master schedule, there is no 'M.R.P.'. Any 'M.R.P.' system
without a demand forecast analysis capability is thus severely limited in its ability to help
reduce overall inventory and simultaneously meet the requirements of the production plan.
After all, "Garbage In, Garbage Out."
Still, with all of the potential for automating the manufacturing planning process, people still
need to use their skills and judgement within critical points in the planning process. Using
'exception planning' will minimize the amount of items that people need to look at. This
'exception planning' process is derived directly fromBandwidth Management, so that only
those items that need attention will be addressed. It is still the planner's responsibility to
implement purchase order re-scheduling or 'crash buy' programs, outside contracting, and so
forth, and (potentially) any manufacturing schedules oriented around a process or piece of
equipment that is considered a 'critical path' in the manufacturing process. The 'M.R.P. III'
system must therefore supply as much useful information to the planner as possible, to help
him make informed decisions, yet also limit this information to only those items that mayactually require his attention.
http://www.mrp3.com/bndwmgmt.htmlhttp://www.mrp3.com/bndwmgmt.htmlhttp://www.mrp3.com/bndwmgmt.htmlhttp://www.mrp3.com/bndwmgmt.htmlhttp://www.mrp3.com/bndwmgmt.htmlhttp://www.mrp3.com/bndwmgmt.html8/13/2019 MRP3
6/6
How the Demand Planni ng ToolHelps to Implement M.R.P. III
TheDemand Planning Tool,a product of S.F.T., Inc., is a combined effort of over 5 years of
development work, and is designed primarily to allow the user to quickly generate a more
accurate forecast, maintain this forecast along with a long-term business plan, and perform
daily or weeklyDemand Analysisto measure current performance (actual data) to theforecast. It contains a number of screens, graphs, and reports to make this process as easy and
fast as possible. TheDemand Planning Toolemploys the principles ofBandwidth
Managementto measure exceptions to the plan on a daily basis. By usingBandwidth
Management, the number of exceptions to the plan are minimized, and therefore the plan
becomes stable. A stable plan minimizes the negative impact of forecast changes inside of
lead time on the manufacturing process, and allows the master scheduler to more effectively
use the M.R.P. system, with much fewer problems. TheDemand Planning Toolforms a
major part of the total 'M.R.P. III' system, as outlined above, by analyzing the DEMAND
SIDEof the equation. The resultingDemand Forecastforms the input to the entire
manufacturing process. TheDemand Planning Toolcan also track on-time delivery
performance for customer orders, thereby measuring the overall system performance of the
manufacturing environment, by comparing the actual shipment date to the customer's
requested ship date.
Back to S.F.T. Inc. home page
1996 by Stewart~Frazier Tools, Inc. - all rights reserved
Last Update: 5/22/96
http://www.mrp3.com/dpt.htmlhttp://www.mrp3.com/index.htmlhttp://www.mrp3.com/index.htmlhttp://www.mrp3.com/dpt.html