EPCM - CONCEPT E --- Engineering P L F / C U F

P --- Procurement PERFORMANCE

C --- Construction O & M

M --- Management

ROI , IRR , DSCR , Debt : Equity

Detailed Project Report – Financial Closure

Capacity Utilisation Factor(CUF) =Energy measured (kWh) /

(365*24*installed capacity of the plant).

Major Components of EPCM Site Selection and Feasibility Analysis

Design [ DC/AC ] & Detailed Engineering - BOM

Signing of Legal / Power Purchase Agreements

Civil / Structural / Electrical Drawings

CEIG/TNEB Approvals

Procurement of Materials / Execution Strategy

Installation of the Plant within the Time Schedule

Synchronization and Handing over of plant

TNEB / MNRE / TEDA Inspection

Site Selection & Feasibility

VAO / DTCP / Statutory Approvals

Dry and Non Agricultural land / PCB /

Location of Substation and Transmission Grid

Approachability of the land from main road

Right Of Way Issues

Availability of Resources – Water / Elecy / House

Work force mobilization

Shadow Free Land , Data of flood and storm 20 years

Soil Test Report , Contour Mapping

Base Foundation For Structure

Design & Detailed Engineering DC design

Structure Design according to Wind Speed

PV Syst layout of the plant

BOM preparation

Procurement plan

Site Mobilization Plan

Installation Plan

Commissioning Action Plan

Civil Work Heat & Rain HOT TEMP > 45 DEG

RAIN / STORM // Weeds / Bushes //

Design of all erection structure - Module Mounting, lighting post, lightning arrestor

Design of trenches, water supply, Drainage etc…

Internal Roads & Land levelling

Structural Work Ground Mounted / Roof top / Stand Alone

Wind Load calculations

Selection of Structural Material /Hot Dip Galvanising

Structural Analysis for the load

Sasonal Tilting / Auto Tilting structure

Construction, supply and erection the mounting structures in the land

Panel Mounting Structure

DC Design DC Design Calculation

Shadow free analysis

String Combiner Box / MJB

DC BOM preparation

Panel layout diagram

PV SYST generation report

Generation Guarantee file

Skilled Manpower

S C A D A

No Network

No Signal

No Telephone

Line

Controls like

Tripping /

Closing Risky

Remote

Monitoring

Site Works 24 x 7

AC Design Selection of Inverters , Central vs String

LT Cable Design

LT Panel

Transformer Design

HT Cable Design

HT Panel

Relay & Control Panel

Synchronization Check Panel

Revenue Metering & Power Evacuation

Central Inverter Heat & Sound

Power Evacuation Delay in TNEB Works

Construction Power

Bay & Space Availability

Transmission Line Routing

Protection & Tripping Systems

HT Cable Lying

Conventional – LT & HT panel

Compact SS & Power Evacuation

Grid

Availability

Fluctuations

Frequency

Lower

Monthly

Shutdown

Tripping

Feeders

Rain , Wind

1 MWp - Solar Plant in Tamil Nadu

23

600 kWp-Roof Mounted

24

On RCC Roof

MRF, Chennai – 15.84 KW

KTV Foods, Chennai – 523KW

Reed Relays, Hosur – 50 KW BGS School, Bangalore – 50 KW

On Metal Sheet and Asbestos Sheet Roofs

KTV Foods, Chennai – 523KW

Naga Mills, Dindugul – 600KW

Braga Industries, Chennai – 20KW

KTV Foods, Chennai – 523KW

Quote – Thomas Alwa Edison

We Provide Professional Practical Solar Solution.

Thank You !

Pls Contact

Kumar -

9551663310

[email protected]

Technical Credentials NAME DESCRIPTION

P. Kumar

Vice President Engineering & Project.

Professional Engineer with 24 years of experience in Power PlantEngineering & Project Execution, Management, Operation & Maintenance.

2 Years in Auroville heading Renewable Power Sector.

15 Years served in Govt. Of Oman in charge of Power Generation &Distribution for Ministry of Defense.

Successfully Commissioned India’s FIRST 1 MWp Solar PV Plant underJNNSM Scheme .

Concept to Commisionning of more than 15 MW Solar Plants.

Team comprising of Team leader, EHS, Electrical installation andcommissioning engineers