Upload
andre-mendes
View
224
Download
0
Embed Size (px)
DESCRIPTION
OTP Piling Operations
Citation preview
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 1 of 8
Network Rail Work Activity Risk Assessment
Work Activity Assessed:
OTP Piling Operations Ref. No. NR/L3/MTC/WARA/MP20
Function:
Maintenance Discipline or Department:
All maintenance disciplines and departments
Location/site of work activity:
Generic Date Assessment carried out:
Groups at risk:
All maintenance disciplines and departments Previous assessments superseded:
Name: Positions: Bryan Smith
Operations & Standards Engineer, OTP. NST, Maintenance.
Persons carrying out assessment:
Reviewed and Approved by:
Bob
Date of acceptance and publication:
Planned review date:
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 2 of 8
Network Rail Work Activity Risk Assessment
Ref. No. MP20
1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity
Hazards Consequences Existing Controls S L R Additional Controls S L R Specialised Risk Assessment
On or about the track .
Being Struck by Train
Major or fatal Injury
See GH1 Rule Book Module T3 Railway Communication
Protocol
5 4 9
Working at night or in tunnels
Darkness - See GH3 - - -
On or about the track .
Underfoot Conditions
- See GH2 - - -
General activity with the OTP.
Overhead AC or Third Rail DC Electrified Lines
- See GH6 / GA20 - - -
On-Off tracking. Lifting. Turning
Machine overturning / collision
Major or fatal injury
Operator competency Safe working distance
between machines Slew locks
5 2 7
Operation. Machine failure
Major injury Pre-use checks Valid plant worthiness
certificate Maintenance
5 1 6
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 3 of 8
1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity
Hazards Consequences Existing Controls S L R Additional Controls S L R Specialised Risk Assessment
Transiting with piling equipment extended.
Contact with lineside structures.
Serious damage to structures and piling OTP. Fatality or major injury.
Operator competence Machine Controller Operating instructions
5 1 6
Operator or Controller activities.
Disregard for own safety (disobeying the rules)
Major or fatal injury
Selection of staff Possession Checks
5 1 6
Extended shift.
Lack of concentration / stress / fatigue resulting in staff being struck by train
Major or fatal injury
Monitoring of hours worked, including monitoring for fatigue
Pre-work planning Site meetings Training / competence Alcohol and drugs policy
5 2 7
Lack of local knowledge and being struck by train
Major or Fatal Injury
Pre-site planning Pre-work briefing by
PICOP/ES/COSS Sectional Appendix and
Hazard Directory Weekly Operating Notice Line Diagrams Local H&S Policy
5 2 7
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 4 of 8
1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity
Hazards Consequences Existing Controls S L R Additional Controls S L R Specialised Risk Assessment
Passing instructions or information.
Communication failure resulting in staff being struck by train
Major of fatal injury
Selection of staff for Machine Controller Duties
Training and competence assessment, including railway communication training
Engineering Supervisors Certificate RT3199
PICOP Form RT3198 COSS Briefing Form Record of movements
within an absolute possession
Back-to-back radios Monitoring by possession
checks Discipline and re-training Use of phonetic alphabet
and railway communication protocol
5 2 7
Adverse weather conditions
- See GH5 - - -
Young Persons (16-18 years old)
- See GA42 - - -
Lone Workers - See GA10 - - - New and
Expectant Mothers
- See GA43 - - -
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 5 of 8
Network Rail
Work Activity Risk Assessment Ref. No. MP20
Additional local condition factors that should be considered
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 6 of 8
Manual Handling Operations Risk Assessment Filter
Work Activity Risk Assessment Reference No. ..
Activity Assessed Assessed by .. Component of Activity
WARA risk classification
1 2 3 4
Y/N
Further controls identified (carry back to WARA)
Specialist MHO risk assessment required Y/N
Lifting and Lowering Weight outside guidelines according to body zone?
Y/N Y/N
Repetitive lifting/lowering -more than twice per minute?
Y/N Y/N
Twisting motion - more than 45 degrees?
Y/N Y/N
Carrying
Load supported some distance away from the body?
Y/N Y/N
Load carried more than 10m distance?
Y/N Y/N
Hands below knuckle height or above elbow height when carrying/lifting.?
Y/N Y/N
Pushing and Pulling Excessive force required to move load?
Y/N Y/N
Excessive force required to keep load in motion?
Y/N Y/N
Refer to Appendix D of NR/SP/OHS/00102 for guidance on completing this form
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 7 of 8
Noise Risk Assessment Filter
Work Activity Risk Assessment Reference No. ..
Activity Assessed . Assessed by ..
1 Component(s) of Activity
2 WARA risk classification
Manufacturers/Measurement Data (where available)
3 Name of Tool/Equipment/Noise source
4 Suppliers/Manufacturers/ Measurement Information available Y/N
Y/N Y/N Y/N Y/N
5 Continuous Noise Level dBA.
6 Impact Noise Level dB(C) (if applicable)
Listening Checks (where manufacturers/measurement data is not available)
7 Difficulty being heard at 2m (85dB(A))
8 Difficulty being heard at 1m (90dB(A))
Estimation of Noise Exposure
9 Estimated usage time (hrs.)
10 Noise exposure points (from Table 1)
11 Total noise exposure points
12 Estimated Noise Exposure (dB) (from Table 2)
Refer to Appendix D of NR/SP/OHS/00102 for guidance on completing this form
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 8 of 8
Hand-Arm Vibration Risk Assessment Filter
Work Activity Risk Assessment Reference No. ..
Activity Assessed . Assessed by ..
1 Component(s) of Activity
2 WARA risk classification
Manufacturers/Measurement Data (where available)
3 Name of Tool/Equipment/Vibration source
4 Suppliers/Manufacturers/ Field Measurement Information available Y/N
Y/N Y/N Y/N Y/N
5 Vibration Level (m/s2) from available information
6 Source of information
Estimation of Hand-Arm Vibration Exposure
7 Estimated usage time (hrs.)
8 HAV exposure points (from Table 1)
9 Total HAV exposure points
10 Estimated HAV Exposure (m/s2 A(8)) (from Table 2)
Refer to Appendix D of NR/SP/OHS/00102 for guidance on completing this form